Pipeline cleaning and dredging structure

By installing cleaning water bladders and cleaning racks inside the pipes, the problem of large debris clogging the pipes is solved by using the inflating water bladders to drag and spray water for cleaning, achieving a highly efficient pipe cleaning effect.

CN223875716UActive Publication Date: 2026-02-06JINAN QIYUAN ENVIRONMENTAL PROTECTION TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520345269.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-03-03
Publication Date
2026-02-06
Estimated Expiration
2035-03-03

AI Technical Summary

Technical Problem

Existing technologies are insufficient to effectively remove heavy debris from pipes, leading to blockages and reduced flow.

Method used

Design a pipe cleaning and unblocking structure, including a cleaning water bladder and a cleaning frame. The cleaning frame is inflated into an umbrella shape by filling it with water, and combined with the spray nozzles, water is sprayed to drag and clean debris in the pipe.

Benefits of technology

It effectively removes heavy debris from pipes, keeps pipes clear, and improves cleaning efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223875716U_ABST
    Figure CN223875716U_ABST
Patent Text Reader

Abstract

The pipeline cleaning and dredging structure comprises a pipe body, a sliding barrel, a water pipe connector, a drainage connector, a fixing disc, a cleaning frame, a limiting groove and a cleaning water bag, the side end of the pipe body is connected with the sliding barrel in a sliding mode, the water pipe connector is formed in the front end of the pipe body, the drainage connector is formed in the rear portion of the side end of the pipe body, and the fixing disc is fixed to the rear end of the pipe body. The rear end of the cleaning frame is hinged to the side end of the fixing disc, the limiting groove is formed in the inner end of the cleaning frame, and the cleaning water bag is installed on the rear portion of the pipe body through the fixing disc. The utility model solves the problem that the pipe diameter is influenced and the flow is reduced when sundries are accumulated in the pipeline. And when the sundries are heavy, pipe body cleaning equipment mainly depending on water flow washing is difficult to clean the sundries.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to pipeline cleaning field especially, relate to a pipeline cleaning dredging structure. BACKGROUND

[0002] Pipeline cleaning is the process of removing blockages, dirt or deposits to keep the pipe body unobstructed. Common methods include: chemical cleaning, physical cleaning and professional cleaning services. Preventive measures include regular flushing, installing filters and avoiding dumping grease.

[0003] When the sundry accumulation occurs in the pipe body, the pipe diameter is affected, and the flow is reduced. When the sundry weight is large, the pipeline cleaning equipment mainly relying on water flow scouring is difficult to remove the sundry. SUMMARY

[0004] The utility model discloses a pipeline cleaning dredging structure to solve the above technical problem.

[0005] In order to realize the above-mentioned purpose, the utility model adopts the following technical scheme: a pipeline cleaning dredging structure, including pipe body, sliding cylinder, water pipe interface, drainage interface, fixed disc, cleaning frame, limiting groove, cleaning water bag, the pipe body side end sliding connection sliding cylinder, the water pipe interface opens in the pipe body front end, the drainage interface opens in the pipe body side end rear, the fixed disc is fixed in the pipe body rear end, the cleaning frame rear end is hinged in the fixed disc side end, the limiting groove opens in the cleaning frame inner end, the cleaning water bag is installed in the pipe body rear portion through the fixed disc.

[0006] On the basis of the above technical scheme, the cleaning water bag includes an end plate, a bag body, a channel, a pressing plate, a limiting rail and a nozzle, the end plate is installed at the front end of the fixed disc, the bag body is installed at the front end of the end plate, the channel is opened in the middle part of the bag body, the bag body is connected to the pipe body through the channel, and the drainage interface is connected to the bag body through the channel, the pressing plate is installed at the front end of the channel, the limiting rail is distributed at the rear part of the side end of the bag body, and the limiting rail is connected to the limiting groove, and the nozzle is distributed in the middle part of the bag body.

[0007] On the basis of the above technical scheme, the bag body is inflated by water to support the cleaning frame and spray water through the nozzle.

[0008] Compared with the prior art, the utility model has the following advantages: the utility model installs the cleaning water bag at the end of the pipe body for cleaning, and the cleaning frame is inflated like an umbrella to drag and clean the sundry with large weight in the pipeline. BRIEF DESCRIPTION OF DRAWINGS

[0009] Fig. 1 It is the appearance structure schematic drawing of the utility model.

[0010] Fig. 2 It is the cleaning state schematic drawing of the utility model.

[0011] Fig. 3 It is the pipe body structure schematic view of the utility model.

[0012] Fig. 4 It is the cleaning water bag schematic view of the utility model.

[0013] In the drawing: 1, pipe body, 2, sliding cylinder, 3, water pipe interface, 4, drainage interface, 5, fixed disc, 6, cleaning frame, 7, limiting groove, 8, cleaning water bag, 9, end plate, 10, bag body, 11, passage, 12, pressing plate, 13, limiting rail, 14, nozzle. DETAILED DESCRIPTION

[0014] The utility model is further described in detail below in combination with the drawings and specific embodiments.

[0015] As Figs. 1 to 4 Shown, a pipeline cleaning dredging structure, including pipe body 1, sliding cylinder 2, water pipe interface 3, drainage interface 4, fixed disc 5, cleaning frame 6, limiting groove 7, cleaning water bag 8, pipe body 1 side end sliding connection sliding cylinder 2, water pipe interface 3 open in pipe body 1 front end, drainage interface 4 open in pipe body 1 side end rear, fixed disc 5 is fixed in pipe body 1 rear end, cleaning frame 6 rear end articulates in fixed disc 5 side end, limiting groove 7 opens in cleaning frame 6 inner end, cleaning water bag 8 is installed in pipe body 1 rear portion through fixed disc 5.

[0016] Cleaning water bag 8 includes end plate 9, bag body 10, passage 11, pressing plate 12, limiting rail 13, nozzle 14, end plate 9 is installed in fixed disc 5 front end, bag body 10 is installed in end plate 9 front end, passage 11 opens in bag body 10 middle part, and bag body 10 is connected to pipe body 1 through passage 11, and drainage interface 4 is connected to bag body 10 through passage 11, pressing plate 12 is installed in passage 11 front end, limiting rail 13 is distributed in bag body 10 side end rear, and limiting rail 13 is connected to limiting groove 7, nozzle 14 is distributed in bag body 10 middle part.

[0017] Bag body 10 is inflated by filling water and supports open cleaning frame 6, and water is sprayed through nozzle 14.

[0018] The working principle of the utility model: after the rear part in the pipeline is inserted into the accumulated sundries, the water is filled through water pipe interface 3, the water is filled into bag body 10 through drainage interface 4, bag body 10 is inflated by filling water and supports open cleaning frame 6, and the front part of cleaning frame 6 presents umbrella shape, bag body 10 holds cleaning frame 6 through limiting rail 13 and limiting groove 7, holds pipe body 1 and pulls forward, and cleaning frame 6 presents umbrella shape and pulls the accumulated sundries in the pipeline forward, and bag body 10 sprays water through nozzle 14 and cleans, realizes the cleaning and dredging of the pipeline, finally, sliding cylinder 2 is slid forward and pushes and presses pressing plate 12, and bag body 10 is flattened, forcing cleaning frame 6 to reset.

[0019] The above is the preferred embodiment of the present application. For those skilled in the art, according to the teachings of the present application, without departing from the principles and spirit of the present application, the changes, modifications, replacements and variations of the embodiments still fall within the protection scope of the present application.

Claims

1. A pipe cleaning and unblocking structure, comprising a pipe body (1), a sliding cylinder (2), a water pipe interface (3), a drainage interface (4), a fixing plate (5), a cleaning frame (6), a limiting groove (7), and a cleaning water bladder (8), characterized in that: The pipe body (1) is slidably connected with a sliding cylinder (2) at one end, the water pipe interface (3) is formed at the front end of the pipe body (1), the drain interface (4) is formed at the rear part of the side end of the pipe body (1), the fixing disc (5) is fixed to the rear end of the pipe body (1), the cleaning frame (6) is hingedly connected to the side end of the fixing disc (5) at the rear end, the limiting groove (7) is formed at the inner end of the cleaning frame (6), and the cleaning water bag (8) is installed at the rear part of the pipe body (1) through the fixing disc (5).

2. A pipe cleaning and unblocking structure according to claim 1, wherein: The cleaning water bag (8) comprises an end plate (9), a bag body (10), a channel (11), a pressing plate (12), a limiting rail (13) and a nozzle (14), the end plate (9) is installed at the front end of the fixing disc (5), the bag body (10) is installed at the front end of the end plate (9), the channel (11) is formed at the middle part of the bag body (10), the bag body (10) is connected with the pipe body (1) through the channel (11), the drain interface (4) is connected with the bag body (10) through the channel (11), the pressing plate (12) is installed at the front end of the channel (11), the limiting rail (13) is distributed at the rear part of the side end of the bag body (10) and connected with the limiting groove (7), and the nozzle (14) is distributed at the middle part of the bag body (10).

3. A pipe cleaning and unblocking structure according to claim 2, wherein: The bag body (10) is inflated by water to support the cleaning frame (6) and spray water through the nozzle (14).