Turnout rail part replacement operation vehicle and system
By using vehicle grouping and multiple gantry cranes in conjunction with wireless remote control, the problem of loading, unloading, and replacing the entire set of turnout rail components was solved, achieving safe and efficient replacement of turnout rail components and improving construction quality and safety.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-04-15
- Publication Date
- 2026-03-24
AI Technical Summary
Existing equipment is insufficient to meet the loading, unloading, and replacement needs of the entire turnout rail components, especially in the turnout area environment, where there are safety hazards and low operational efficiency.
The vehicle formation includes a first railcar, an equipment flatcar, a rail component flatcar, and a second railcar. The equipment flatcar is equipped with a gantry crane and a lifting platform, while the rail component flatcar is equipped with segmented turnout rail components. Multiple gantry cranes are used in conjunction with wireless remote control for hoisting and replacement.
This enabled the safe and reliable replacement of the entire set of turnout rail components, improved work efficiency, enhanced welding quality and track operation safety, and simplified the operation process.
Smart Images

Figure CN224031392U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of railway engineering machinery, and in particular to a work vehicle and system applied to replacement of whole turnout track components. BACKGROUND
[0002] The turnout track component mainly refers to a whole track component composed of components such as a frog, a point rail, a connecting rail and a basic rail above a sleeper, and has the main characteristics of long size and heavy weight, and is difficult to replace manually, and existing equipment cannot meet the requirements. With multiple speed increases of railways, vehicles pass quickly, and wheels impact and crush, which easily leads to long-distance wear of a rail line, especially a turnout, which is more easily worn and needs to be replaced. At the same time, high-frequency passage of vehicles requires that the rail be quickly repaired after wear. In order to save time, the whole turnout track component needs to be replaced at the same time, and because the operation area is limited, the track component is long, large and heavy, and existing rail replacement vehicles and 25-ton rail cranes cannot meet the requirements. Therefore, replacement of the whole turnout track component is a very difficult work, and improvement is urgently needed.
[0003] In the prior art, replacement of turnout components mainly has the following methods:
[0004] The first method is to use 2-3 25T hoisting rail cars from adjacent lines to hoist and operate large track components. However, this scheme is prone to damage due to large deformation of large track components during operation, and because the drivers of multiple hoisting rail cars operate synchronously, large swinging is prone to occur, thereby causing safety hazards and other problems.
[0005] The second method is to use a large turnout large component emergency replacement vehicle set for construction, which is composed of 2 hoisting rail cars and 1-2 rail cars. When the construction operation is performed, the two sets of hoisting rail cars are used to replace the track components. This scheme is limited by the number of lifting points, and usually cannot meet the operation requirements of long and large track components, and the equipment is large, expensive and complex to operate, and the operation preparation time is long, and the operation efficiency is difficult to meet the increasing demand for replacement of turnout track components.
[0006] In the prior art, the following documents are related to the present application:
[0007] Document 1 is a Chinese invention application with the application date of 2018-02-01 and the publication date of 2019-03-01, the publication number of CN109403161A. The invention discloses a large-tonnage lifting rail car switch replacement construction process, the specific steps are as follows: first, before the new switch is installed on the track bed, the pre-paved shifting method is used to assemble the new switch in sections; second, before the new switch is installed, the old switch is removed and the track bed is cleaned using the lifting rail car as the main disassembly equipment of the switch; third, after the new switch is assembled, the new switch is transported to the vicinity of the installation position using the lifting rail car as the main transfer equipment of the switch; fourth, after the new switch is transported to the vicinity of the installation position, the new switch is accurately installed on the track bed using the lifting rail car as the main installation equipment of the switch.
[0008] Document 2 is a Chinese utility model patent with the application date of 2016-08-15 and the announcement date of 2017-06-06, the announcement number of CN206219916U. The utility model discloses a railway switch large component quick replacement equipment, which comprises at least one set of bearing platform, a walking mechanism is arranged below the bearing platform, a bearing frame is arranged above the bearing platform, the bearing frame is connected with a telescopic girder, the telescopic girder is connected with a sliding hoisting mechanism, the telescopic girder is also provided with a driving mechanism, one end of the telescopic girder is connected with a frame hinge beam and can rotate or move horizontally based on the frame hinge beam, the bearing platform is also connected with at least one set of stable supporting device, and the front end of the telescopic girder is connected with at least one set of front end supporting device.
[0009] Document 3 is a Chinese invention application with the application date of 2016-08-15 and the publication date of 2018-03-06, the publication number of CN107761486A. The invention discloses a railway switch large component quick replacement method and the corresponding replacement equipment thereof, the replacement equipment comprises at least one set of bearing platform, a bearing frame is arranged above the bearing platform, the bearing frame is connected with a telescopic girder, the telescopic girder is connected with a sliding hoisting mechanism, the telescopic girder is also provided with a driving mechanism, one end of the telescopic girder is connected with a frame hinge beam, and the bearing frame is provided with a Z-direction overturning auxiliary adjusting mechanism.
[0010] Document 4 is a Chinese invention application with the application number CN103074829A, which was applied by China Railway Heavy Industry Co., Ltd. and China Railway Engineering Group Co., Ltd. on January 5, 2013 and was published on May 1, 2013. The invention discloses a railway turnout replacement construction method and a railway turnout track-laying machine set. The track-laying machine set comprises a main machine, an auxiliary machine and a hydraulic replacement frame. The main machine comprises a main machine flat car, an arm, a front column portal structure, a rear column portal structure, a hoist trolley, a hoist mechanism and a running mechanism. The auxiliary machine comprises at least an auxiliary machine flat car. The hydraulic replacement frame comprises a first replacement frame, a second replacement frame and a replacement lifting appliance.
[0011] In summary, there is no technical solution for replacing the whole set of turnout track components in the prior art, and there is an urgent need to propose a technical solution for replacing the whole set of turnout track components to solve the technical problem that the existing operation mode cannot better adapt to the whole set of turnout track component loading and unloading operation and the replacement of the turnout area environment. Practical new type content
[0012] Therefore, the purpose of the present application is to provide a turnout track component replacement operation vehicle and system to solve the technical problem that the existing turnout replacement operation vehicle and system cannot better adapt to the whole set of turnout track component loading and unloading operation and the replacement of the turnout area environment.
[0013] In order to achieve the above-mentioned practical new type purpose, the present application specifically provides a technical implementation scheme of a turnout track component replacement operation vehicle, which comprises:
[0014] Vehicle marshalling;
[0015] The vehicle marshalling comprises a first rail car, an equipment flat car, a track component flat car and a second rail car connected in sequence.
[0016] The first rail car is used to pull the equipment flat car, and the equipment flat car is used to load a portal crane device and a lifting platform.
[0017] The second rail car is used to pull the track component flat car, and the track component flat car is used to load the turnout track component.
[0018] The present application also specifically provides a technical implementation scheme of a turnout track component replacement operation system, which comprises:
[0019] The turnout track component replacement operation vehicle as described above;
[0020] The portal crane device and the lifting platform arranged on the equipment flat car;
[0021] And the turnout track component arranged on the track component flat car adopts a sectional structure.
[0022] Further, the turnout track component is cut into a first assembly, a second assembly and a third assembly from an insulating joint.
[0023] Further, the first assembly includes a straight basic rail and a curved nose rail.
[0024] Further, the second assembly includes a straight nose rail, a curved basic rail and a frog.
[0025] Further, the third assembly includes a curved lower leg and a guard rail.
[0026] Further, the equipment flat car is loaded with 4 sets of gantry cranes.
[0027] Further, the equipment flat car is loaded with 2 sets of lifting platforms.
[0028] Further, the system further includes a wireless remote controller arranged on the equipment flat car.
[0029] Further, the wireless remote controller includes a signal transmitter, and a signal receiver arranged on the gantry cranes and the lifting platforms.
[0030] By implementing the technical scheme of the turnout rail piece replacement operation vehicle and system provided in the present application, the following beneficial effects are achieved:
[0031] (1) The turnout rail piece replacement operation vehicle and system of the present application adopts a flat car formation to transport the whole set of turnout rail pieces, which well adapts to the loading and unloading operation of the whole set of turnout rail pieces and the replacement of the turnout area environment, and systematically solves the technical problems of transportation, hoisting, laying and replacement of the whole set of turnout rail pieces;
[0032] (2) The turnout rail piece replacement operation vehicle and system of the present application can realize the on-site hoisting replacement operation of the whole set of turnout rail pieces, and the use of multiple gantry cranes can overcome the technical problems of large local deformation of the turnout rail pieces, large hoisting swing, low operation efficiency and long time occupation of the skylight;
[0033] (3) The turnout rail piece replacement operation vehicle and system of the present application realizes the pre-fabrication or welding of the whole set of turnout rail pieces, cancels the aluminum heat welding process in the turnout area, greatly improves the welding quality and efficiency by welding the turnout area in the base, and improves the turnout construction quality and the line operation safety;
[0034] (4) The turnout rail piece replacement operation vehicle and system of the present application uses multiple gantry cranes to hoist and replace the turnout rail pieces in a wireless remote control mode, which is safe and reliable, simple in structure and easy to operate, and at the same time, the whole set of turnout rail pieces is divided into straight legs and curved legs, which is convenient for rail piece flat car transportation and handling. BRIEF DESCRIPTION OF DRAWINGS
[0035] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the prior art, the accompanying drawings needed to be used in the embodiments or prior art description will be briefly introduced. Obviously, the accompanying drawings in the following description are only some embodiments of the present application, and for those skilled in the art, other embodiments can be obtained from these drawings without creative labor.
[0036] Figure 1 is a specific embodiment of the vehicle marshalling structure diagram of the turnout rail piece replacement operation vehicle and system of the present application;
[0037] Figure 2 is a specific embodiment of the local three-dimensional structure diagram of the turnout rail piece replacement operation system of the present application;
[0038] Figure 3 is a specific embodiment of the local side structure diagram of the turnout rail piece replacement operation system of the present application;
[0039] Figure 4 is a specific embodiment of the three-dimensional structure diagram of the door hoist device and lifting platform of the turnout rail piece replacement operation system of the present application;
[0040] Figure 5 is a specific embodiment of the three-dimensional structure diagram of the lifting platform of the turnout rail piece replacement operation system of the present application;
[0041] Figure 6 is a specific embodiment of the operation process diagram of the lifting platform deploying the door hoist device of the turnout rail piece replacement operation system of the present application;
[0042] Figure 7 is a specific embodiment of the structure diagram of the turnout rail piece of the turnout rail piece replacement operation system of the present application;
[0043] Figure 8 is a specific embodiment of the structure diagram of the first component of the turnout rail piece of the turnout rail piece replacement operation system of the present application;
[0044] Figure 9 is a specific embodiment of the structure diagram of the second component of the turnout rail piece of the turnout rail piece replacement operation system of the present application;
[0045] Figure 10 is a specific embodiment of the structure diagram of the third component of the turnout rail piece of the turnout rail piece replacement operation system of the present application;
[0046] Figure 11 is a specific embodiment of the process diagram of the vehicle marshalling and unmarshalling of the turnout rail piece replacement operation system of the present application;
[0047] Figure 12is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process of the removal of the third component of the old rail;
[0048] Figure 13 is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process of the placement of the gantry crane;
[0049] Figure 14 is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process of the unloading of the second component of the new rail;
[0050] Figure 15 is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process after the unloading of the second component of the new rail is completed;
[0051] Figure 16 is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process of the lifting out of the second component of the old rail;
[0052] Figure 17 is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process of the lifting in of the second component of the new rail;
[0053] Figure 18 is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process of the recovery of the second component of the old rail;
[0054] Figure 19 is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process of the unloading of the first and third components of the new rail;
[0055] Figure 20 is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process of the lifting out of the first component of the old rail;
[0056] Figure 21 is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process of the lifting in of the first component of the new rail;
[0057] Figure 22 is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process of the recovery of the first component of the old rail;
[0058] Figure 23 is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process of the recovery of the gantry crane;
[0059] Figure 24 is a specific embodiment of the switch rail piece replacement operation system of the present application, a schematic diagram of the operation process of the replacement of the third component of the old rail;
[0060] Figure 25is a specific embodiment of the switch rail replacement operation system of the present application, which is a structural schematic diagram of completing the switch rail replacement operation;
[0061] Figure 26 is a partial structural component schematic diagram of another specific embodiment of the switch rail replacement operation system of the present application;
[0062] In the figure: 1-first rail car, 2-equipment flat car, 3-second rail car, 4-rail flat car, 5-gantry crane device, 6-lifting platform, 7-main line, 8-adjacent line, 9-simple gantry crane, 10-operation system, 11-insulating joint, 12-signal transmitter, 13-signal receiver, 20-switch rail, 21-first component, 211-straight basic rail, 212-curved frog rail, 22-second component, 221-straight frog rail, 222-curved basic rail, 223-frog, 23-third component, 231-curved lower rail, 232-guard rail. DETAILED DESCRIPTION
[0063] In order to make the purpose, technical scheme and advantages of the embodiments of the present application more clear, the technical scheme of the embodiments of the present application will be described clearly and completely below in combination with the drawings of the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of protection of the present application.
[0064] As shown in the drawings, Figure 1 to the drawings, Figure 26 The specific embodiments of the switch rail replacement operation vehicle and system of the present application are shown, and the present application will be further described below in combination with the drawings and specific embodiments.
[0065] Embodiment 1
[0066] As shown in the drawings, Figure 1 An embodiment of the switch rail replacement operation vehicle of the present application specifically includes:
[0067] Vehicle marshalling;
[0068] The vehicle marshalling includes a first rail car 1, an equipment flat car 2, a rail flat car 4 and a second rail car 3 connected in sequence.
[0069] As shown in the drawings, Figure 2 to the drawings, Figure 6 The first rail car 1 is used to pull the equipment flat car 2 (which can specifically adopt a 15.4m flat car), and the equipment flat car 2 is used to load the gantry crane device 5 and the lifting platform 6.
[0070] The second rail car 3 is used to pull the rail flat car 4, and the rail flat car 4 is used to load the switch rail 20.
[0071] Example 2
[0072] As attached Figure 1 As shown, an embodiment of the turnout rail component replacement system of this application specifically includes:
[0073] The turnout rail component replacement vehicle as described in Example 1;
[0074] The gantry crane 5 and the lifting platform 6 are installed on the equipment flatcar 2;
[0075] And turnout rail component 20, which is installed on rail component flatcar 4 and adopts a segmented structure.
[0076] In a preferred embodiment of this application, the equipment flatcar 2 is equipped with four gantry cranes 5 and two lifting platforms 6. The operating system 10 further includes a power unit and a wireless remote controller mounted on the equipment flatcar 2. (See attached...) Figure 26 As shown, the wireless remote controller further includes a signal transmitter 12 and a signal receiver 13 installed on the gantry crane 5 and the lifting platform 6. Multiple gantry cranes 5 and lifting platforms 6 are all operated synchronously and remotely using the wireless remote controller. This system enables on-line operations; all gantry crane 5 retraction and retrieval, and the lifting of turnout rail components 20, can be controlled by the wireless remote controller. All lifting operations are conducted below the gantry cranes 5, ensuring safety, intelligence, and eliminating the risk of contact with the overhead contact line. Simultaneously, multi-point lifting is configured according to the rail component's center of gravity, preventing permanent deformation of the rail component and meeting the requirements of railway turnout 20 laying technology. Intelligent acceleration / deceleration control between the lifting points of multiple gantry cranes 5 ensures good synchronization, minimizes rail component sway, allows for rapid placement into the track, and results in high operational efficiency.
[0077] When the train sets arrive near the turnout area at the work site, they are disassembled. After removing the third component 23 of the old rail, the gantry crane 5 is deployed to unload the second component 22 of the new rail, retrieve the third component 23 of the old rail, and replace the second component 22 of the new rail. The second component 22 of the old rail is retrieved, and the first component 21 and the third component 23 of the new rail are unloaded, the first component 21 of the new rail is replaced, and the first component 21 of the old rail is retrieved. The gantry crane 5 is retrieved, the third component 23 of the old rail is replaced, and the replacement of the turnout rail component 20 is completed.
[0078] The operating system 10 described in this embodiment can complete the replacement of the entire set of turnout rail components 20 on this line within a single track window. The turnout section situation is as follows: Figure 7 As shown. In order to achieve hoisting, the turnout rail component 20 is cut into 3 large components from the insulating joint 11, namely the first component 21, the second component 22 and the third component 23.
[0079] As attached Figure 8 As shown, the first component 21 further includes a straight base rail 211 and a curved tip rail 212.
[0080] As shown in the accompanying drawings Figure 9 The second assembly 22 further comprises straight point rail 221, curved basic rail 222 and frog 223.
[0081] As shown in the accompanying drawings Figure 10 The third assembly 23 further comprises curved lower leg 231 and guard rail 232.
[0082] The first assembly 21, the second assembly 22 and the third assembly 23 are welded as a whole by gas pressure welding or flash welding in the base before being transported to the work site. The turnout rail piece 20 is welded as a whole by high-reliability gas pressure welding or flash welding in the base in advance, and the whole turnout rail piece 20 is hoisted and replaced on site, which can effectively cancel 8 aluminum heat welding points in the turnout area, save 2 skylights required for turnout replacement, and reduce more than 100 person-times of personnel on the track.
[0083] The turnout assembly 20 has irregular cross section and limited space. The turnout rail piece replacement operation system described in the embodiment can pre-fabricate or weld and assemble the whole turnout rail piece 20 in the base, cancel the process of aluminum heat welding in the turnout area, greatly improve the welding quality and efficiency by welding and replacing the turnout area in the base, not only improve the construction skylight operation efficiency, but also avoid the quality problem caused by short-time rapid welding of the turnout rail piece 20 on site, and improve the turnout construction quality and line operation safety.
[0084] When the vehicle formation reaches near the turnout area, the vehicle formation is uncoupled from behind the equipment flat car 2, the equipment flat car 2 is pulled by the first rail car 1 to place the portal crane device 5, and the second rail car 3 and the rail piece flat car 4 are on standby.
[0085] Before placing the portal crane device 5, the third assembly 23 of the old rail is removed and transferred to between the current line 7 and the adjacent line 8 through the simple portal crane 9, and then the simple portal crane 9 is removed. The first rail car 1 and the equipment flat car 2 enter the turnout area to place the portal crane device 5.
[0086] When the portal crane device 5 is deployed, the equipment flat car 2 is pushed in by the first rail car 1, and then the portal crane device 5 is placed along the current line in sequence by using the lifting platform 6.
[0087] After the portal crane device 5 is placed, the rail piece flat car 4 is pushed into the turnout area by the second rail car 3. After the turnout rail piece 20 is aligned, the second assembly 22 of the new rail is lifted from the rail piece flat car 4 by using the portal crane device 5, and is placed between the current line 7 and the adjacent line 8 and close to the leg of the portal crane device 5, while the third assembly 23 of the old rail is lifted onto the rail piece flat car 4, and the second rail car 3 and the rail piece flat car 4 exit.
[0088] When the second component 22 of the old rail is replaced, the second component 22 of the old rail is lifted by the portal crane 5 and placed between the main line 7 and the adjacent line 8 and close to the straight strand side, and the second component 22 of the new rail is lifted into the slot and fixed by the non-hole clamp.
[0089] When the second component 22 of the old rail is recycled, the second component 22 of the old rail is lifted by the portal crane 5, the second railcar 3 and the rail flatcar 4 are pushed in, after the second component 22 of the old rail is placed on the rail flatcar 4, the first component 21 of the new rail is lifted, transversely moved and unloaded, the third component 23 of the new rail is lifted, transversely moved and placed between the main line 7 and the adjacent line 8 and close to the leg of the portal crane 5, and the second railcar 3 and the rail flatcar 4 are withdrawn.
[0090] When the first component 21 of the new rail is replaced, the first component 21 of the old rail is lifted and placed between the main line 7 and the adjacent line 8 and close to the straight strand side, and the first component 21 of the new rail is lifted into the slot to restore the straight strand traffic.
[0091] When the first component 21 of the new rail is recycled, after the first component 21 of the old rail is lifted by the portal crane 5, the rail flatcar 4 is pushed into the turnout area by the second railcar 3, after the first component 21 of the old rail is placed on the rail flatcar 4, the second railcar 3 and the rail flatcar 4 are withdrawn.
[0092] When the portal crane 5 is recycled, the first railcar 1 pushes the equipment flatcar 2 into the turnout area, and the portal crane 5 is recycled along the main line 7 in reverse order by using the lifting platform 6, the vehicle formation is withdrawn, the third component 23 of the new rail is properly placed into the slot, and the replacement is completed.
[0093] When the portal crane 5 is recycled, after the vehicle formation is withdrawn from the turnout area, the third component 23 of the new rail is transferred from between the main line 7 and the adjacent line 8 to the curved lower strand position by the simple portal crane 9, and the replacement is completed.
[0094] The turnout rail replacement operation system described in embodiment 2 can realize on-site hoisting replacement operation of a complete set of turnout rails, and can overcome the technical problems of large local deformation of turnout rails, large hoisting swing, low operation efficiency, and long time occupation of skylight, and the replacement process of the turnout rails is safe and reliable; the complete operation system can replace a complete set of turnout rails within one skylight time, which greatly improves the operation efficiency compared with the existing technical solution which requires ≥4 skylights. The turnout rail replacement operation system of the present application uses a flat car to transport a complete set of turnout rails, which is well adapted to the loading and unloading operation of a complete set of turnout rails and the replacement of the turnout area environment, and systematically solves the technical problems of transportation, hoisting, and replacement of a complete set of turnout rails. The turnout rail replacement operation system of the present application uses multiple gantry crane devices to replace the turnout rails by wireless remote control, which is safe and reliable, simple in structure, and easy to operate. At the same time, the complete set of turnout rails is divided into straight side and curved side parts for hoisting replacement, which is convenient for rail flat car transportation and handling.
[0095] Embodiment 3
[0096] As shown in the accompanying Figure 9 , an embodiment of a turnout rail replacement operation method based on the system described in embodiment 2, specifically comprising the following steps:
[0097] S1) Vehicle marshalling operation. Transport the replacement equipment flat car (i.e. equipment flat car 2) and rail transport flat car (i.e. rail flat car 4) to the operation turnout area through the rail car (i.e. first rail car 1 and second rail car 3).
[0098] S2) The vehicle marshalling arrives near the operation site turnout area.
[0099] Step S2) further comprises the following process:
[0100] When the vehicle marshalling arrives near the turnout area, the vehicle marshalling is unmarshalled from the rear of the equipment flat car 2, the first rail car 1 pulls the equipment flat car 2 to place the gantry crane device 5, and the second rail car 3 and the rail flat car 4 are on standby, as shown in the accompanying Figure 11 .
[0101] S3) Remove the third component 23 of the old rail.
[0102] Step S3) further comprises the following process:
[0103] Before the gantry crane device 5 is placed, the third component 23 of the old rail is removed and transferred to the line 7 between the adjacent line 8 through the simple gantry crane 9, and then the simple gantry crane 9 is removed, and the first rail car 1 and the equipment flat car 2 enter the turnout area to place the gantry crane device 5, as shown in the accompanying Figure 12 .
[0104] S4) Deploy the portal crane 5. After the portal crane 5 is placed one by one, the second railcar 3 pushes the rail flatcar 4 to the opposite line below the equipment flatcar 2.
[0105] Step S4) further includes the following process:
[0106] The equipment flatcar 2 is pushed in by the first railcar 1, and the portal crane 5 is placed along the line in the order from right to left 4, 3, 2, 1, as shown in the accompanying Figure 13 .
[0107] S5) Unload the second component 22 of the new rail and recycle the third component 23 of the old rail. The portal crane 5 is used to unload the new turnout rail and place it on the side of the line, and the equipment flatcar 2 is removed; and the portal crane 5 is used to transfer the old turnout rail to the side of the line, and after the railcar 4 is pushed in, the old turnout rail is placed on the railcar 4 to complete loading.
[0108] Step S5) further includes the following process:
[0109] After the portal crane 5 is placed, the railcar 4 is pushed into the turnout area by the second railcar 3, and after the turnout rail 20 is aligned, the portal crane 5 is used to lift the second component 22 of the new rail from the railcar 4 and move it horizontally, placing it between the main line 7 and the adjacent line 8 and close to the leg of the portal crane 5, while the third component 23 of the old rail is lifted onto the railcar 4, and the second railcar 3 and the railcar 4 exit, as shown in the accompanying Figure 14 and 15 .
[0110] S6) Replace the second component 22 of the new rail.
[0111] Step S6) further includes the following process:
[0112] The second component 22 of the old rail is lifted out by the portal crane 5 and placed between the main line 7 and the adjacent line 8 and close to the straight strand side, and the second component 22 of the new rail is lifted into the slot, and a non-hole clamp is used to fix the rail head, as shown in the accompanying Figure 16 and 17 .
[0113] S7) Recycle the second component 22 of the old rail and unload the first component 21 and the third component 23 of the new rail.
[0114] Step S7) further includes the following process:
[0115] The second component 22 of the old rail is lifted by the portal crane 5, the second railcar 3 and the rail flatcar 4 are pushed in, after the second component 22 of the old rail is placed on the rail flatcar 4, the first component 21 of the new rail is lifted, moved horizontally and unloaded, the third component 23 of the new rail is lifted, moved horizontally, placed between the current line 7 and the adjacent line 8 and placed close to the supporting leg of the portal crane 5, and the second railcar 3 and the rail flatcar 4 are withdrawn, as shown in Figs. 1-3. Figure 18 and 19 .
[0116] S8) The first component 21 of the new rail is replaced.
[0117] The step S8) further includes the following process:
[0118] The first component 21 of the old rail is lifted out and placed between the current line 7 and the adjacent line 8 and placed close to the straight strand side, and then the first component 21 of the new rail is lifted into the slot, and the straight strand is restored to be open to traffic, as shown in Figs. 4-6. Figure 20 and 21 .
[0119] S9) The first component 21 of the old rail is recovered. The turnout rail 20 is lifted by the portal crane 5 group lifting mode and loaded on the rail flatcar 4 for transportation.
[0120] The step S9) further includes the following process:
[0121] After the first component 21 of the old rail is lifted by the portal crane 5, the rail flatcar 4 is pushed into the turnout area by the second railcar 3, after the first component 21 of the old rail is placed on the rail flatcar 4, the second railcar 3 and the rail flatcar 4 are withdrawn, as shown in Figs. 7-9. Figure 22 .
[0122] S10) The portal crane 5 is recovered.
[0123] The step S10) further includes the following process:
[0124] The equipment flatcar 2 is pushed in by the first railcar 1, the portal crane 5 is recovered along the current line 7 in the order of 1, 2, 3, 4 in reverse by using the lifting platform 6, the vehicle marshalling is withdrawn, the third component 23 of the new rail is properly placed into the slot, and the replacement is completed, as shown in Figs. 10-12. Figure 23 .
[0125] S11) The third component 23 of the old rail is replaced.
[0126] The step S11) further includes the following process:
[0127] After the vehicle marshalling is withdrawn from the turnout area, the third component 23 of the new rail is transferred from between the current line 7 and the adjacent line 8 to the position under the curve strand by the simple portal crane 9, and the replacement is completed, as shown in Figs. 13-15. Figure 24 and 25 .
[0128] S12) Complete the replacement of the turnout rail 20. After the portal crane device 5 is recycled one by one, the two ends of the new turnout rail are aligned and welded, polished and fine-tuned, that is, the hoisting and replacement construction of the whole set of turnout rail 20 is completed.
[0129] The portal crane device 5 adopts group hoisting to hoist out the old straight stock rail and hoist in the new straight stock rail; then hoist out the old curved stock rail and hoist in the new curved stock rail, to complete the hoisting and replacement of the whole turnout rail 20.
[0130] The vehicle consists further comprises a first rail car 1, an equipment flat car 2, a rail flat car 4 and a second rail car 3 connected in turn. The equipment flat car 2 is used to load the portal crane device 5 and the lifting platform 6, and the rail flat car 4 is used to load the turnout rail 20.
[0131] The turnout rail 20 is cut off from the insulating joint 11 to form a first component 21, a second component 22 and a third component 23.
[0132] The first component 21 further comprises a straight basic rail 211 and a curved frog rail 212.
[0133] The second component 22 further comprises a straight frog rail 221, a curved basic rail 222 and a frog 223.
[0134] The third component 23 further comprises a curved lower stock rail 231 and a guard rail 232.
[0135] The first component 21, the second component 22 and the third component 23 are welded as a whole by using gas pressure welding or flash welding in the base before being transported to the work site. The turnout rail 20 is welded into two parts of curved stock rail and straight stock rail in advance in the base.
[0136] In the description of the present application, it should be noted that when an element is referred to as "fixed to" or "disposed on" another element, it can be directly disposed on the other element or indirectly disposed on the other element. When an element is referred to as "connected to" another element, it can be directly connected to the other element or indirectly connected to the other element.
[0137] It should be understood that the terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer" and the like indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the devices or elements referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore cannot be understood as a limitation on the present application.
[0138] In addition, the terms "first", "second", "third", etc. are used herein only to describe different instances, and are not used to indicate or imply relative importance or a number of indications of the technical features indicated. Therefore, the features defined as "first", "second", "third", etc. can explicitly or implicitly include one or more of the features. In the description of the present application, the meaning of "a plurality of" or "several" is two or more, unless otherwise explicitly and specifically limited.
[0139] It should be noted that the structures, proportions, sizes, etc. shown in the drawings of the present application are only used to illustrate the content disclosed in the present application, to enable those skilled in the art to understand and read, and are not used to limit the conditions for implementing the present application, and therefore do not have technical significance. Any modification of the structure, change of the proportion relationship, or adjustment of the size, without affecting the effects and purposes that can be achieved by the present application, should still fall within the scope of the technical content disclosed by the present application.
[0140] By implementing the technical solutions of the turnout rail piece replacement operation vehicle and system described in the embodiments of the present application, the following technical effects can be achieved:
[0141] (1) The turnout rail piece replacement operation vehicle and system described in the embodiments of the present application uses a flat car formation to transport the whole set of turnout rail pieces, which well adapts to the loading and unloading operation of the whole set of turnout rail pieces and the replacement of the turnout area environment, and systematically solves the technical problems of transportation, hoisting, and replacement of the whole set of turnout rail pieces;
[0142] (2) The turnout rail piece replacement operation vehicle and system described in the embodiments of the present application can realize on-site hoisting replacement operation of the whole set of turnout rail pieces, and using multiple sets of gantry cranes can overcome the technical problems of large local deformation of the turnout rail pieces, large hoisting swing, low operation efficiency, and long time occupation of the skylight;
[0143] (3) The turnout rail piece replacement operation vehicle and system described in the embodiments of the present application realizes pre-fabrication or welding of the whole set of turnout rail pieces, cancels the aluminum heat welding process in the turnout area, greatly improves the welding quality and efficiency by welding the turnout area in the base, and improves the turnout construction quality and line operation safety;
[0144] (4) The turnout rail piece replacement operation vehicle and system described in the embodiments of the present application uses multiple sets of gantry cranes to hoist and replace the turnout rail pieces in a wireless remote control mode, which is safe and reliable, simple in structure, and easy to operate. At the same time, the whole set of turnout rail pieces is divided into straight strands and curved strands, which facilitates rail piece flat car transportation and handling.
[0145] Each embodiment in the present specification is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between each embodiment can be referred to each other.
[0146] The above descriptions are only the preferred embodiments of the present application, not intended to limit the present application in any form. Although the present application has been disclosed as above with the preferred embodiments, it is not intended to limit the present application. Any person skilled in the art, without departing from the spirit and technical solutions of the present application, can make many possible changes and modifications to the technical solutions of the present application, or modify equivalent embodiments with equivalent changes. Therefore, any simple modification, equivalent replacement, equivalent change and modification made to the above embodiments according to the technical essence of the present application, without departing from the technical solutions of the present application, still belongs to the protection scope of the technical solutions of the present application.
Claims
1. A turnout rail replacement jumbo, characterized by, Comprise: a vehicle formation; the vehicle formation comprises a first rail car, an equipment flat car, a rail piece flat car and a second rail car connected in sequence; the first rail car is used to tow the equipment flat car, and the equipment flat car is used to load a portal crane and a lifting platform; the second rail car is used to tow the rail piece flat car, and the rail piece flat car is used to load a turnout rail piece.
2. A turnout rail replacement operation system characterized by, Comprise: the turnout rail piece replacement vehicle of claim 1; a portal crane and a lifting platform arranged on the equipment flat car; and a turnout rail piece arranged on the rail piece flat car, adopting a sectional structure.
3. The turnout rail replacement system of claim 2, wherein: The turnout rail piece is cut from an insulated joint into a first component, a second component and a third component.
4. The turnout rail replacement system of claim 3, wherein: The first component comprises a straight main rail and a curved switch rail.
5. The turnout rail replacement system of claim 4, wherein: The second component comprises a straight switch rail, a curved main rail and a frog.
6. The turnout rail replacement system of claim 5, wherein: The third component comprises a curved lower stock rail and a guard rail.
7. The turnout rail replacement system according to any one of claims 2 to 6, characterized in that: The equipment flat car is loaded with 4 sets of portal cranes.
8. The turnout rail replacement system of claim 7, wherein: The equipment flat car is loaded with 2 sets of lifting platforms.
9. The turnout rail replacement system of claim 2, 3, 4, 5, 6, or 8, wherein: The system further comprises a wireless remote controller arranged on the equipment flat car.
10. The turnout rail replacement system of claim 9, wherein: The wireless remote controller comprises a signal transmitter, and a signal receiver arranged on the portal crane and the lifting platform.
Citation Information
Patent Citations
Railway switch changing construction method and railway switch track laying unit thereof
CN103074829A
Railway turnout large-size component rapid replacing method and corresponding equipment thereof
CN107761486A
Construction process for changing turnout by using large-tonnage hoisting track car
CN109403161A
Big parts quick replacement equipment of railway switch
CN206219916U