Assembly type wind and rain corridor convenient to butt joint

By combining a limiting slot, mounting support rod, and connecting screw, the contradiction between ease of installation and stability in prefabricated covered walkways is resolved, achieving a convenient and stable covered walkway design that adapts to various installation environments.

CN224048774UActive Publication Date: 2026-03-27ZHUHAI HUAFA ARCHITECTURAL DESIGN CONSULTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-03-03
Publication Date
2026-03-27

AI Technical Summary

Technical Problem

The ease of installation and dismantling of existing prefabricated covered walkways affects the overall stability of the structure after installation.

Method used

The system employs a plug-in structure of limiting slots and mounting rods. The plug-in connection between the positioning rods and the limiting slots, combined with the tightening of the connecting screws, forms four mounting frames and mounting rods symmetrically distributed around the top plate of the connecting corridor. Through the symmetrical layout of the load-bearing rods and the supporting base plate, the stability and safety of the top plate of the connecting corridor are ensured.

Benefits of technology

It enables convenient connection during prefabricated construction, enhances the stability and safety of the connecting corridor roof, resists external forces, adapts to different terrains and building layouts, and ensures stability and convenience after installation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224048774U_ABST
    Figure CN224048774U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of wind and rain corridors, and discloses a conveniently butted assembly type wind and rain corridor which comprises a corridor top plate, the bottom of the corridor top plate is fixedly connected with an installation clamping frame, and a limiting clamping groove is formed in the installation clamping frame. The top of the bearing supporting rod makes contact with the surface of the bottom end of the mounting supporting rod, effective transmission of force is further ensured, the weight of the corridor top plate can be evenly transmitted to the bearing supporting rod through the mounting supporting rod and then transmitted to the supporting bottom plate through the bearing supporting rod, the mounting supporting rod is inserted into the connecting clamping frame, and therefore the weight of the corridor top plate can be effectively reduced. The bearing supporting rod is also inserted into the connecting clamping frame, the inserting structure facilitates butt joint operation in the assembly type construction process, the relative positions of all the components can be finely adjusted to a certain degree by adjusting the fastening degree of the connecting screw rod, close fit of all the components is guaranteed, and the assembly type construction efficiency is improved. And different installation environments and requirements are met, and the supporting stability and convenience after installation are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to a wind and rain corridor technical field especially, relate to a kind of assembled wind and rain corridor of convenient butt joint. BACKGROUND

[0002] The wind and rain corridor is a kind of corridor with roof and column, usually located outside the building, connecting different areas or rooms, with the function of protecting people from bad weather. The original intention of the design of the wind and rain corridor is to provide convenience for pedestrians in bad weather, so it not only has practicality, but also has certain decorative nature. The wind and rain corridor is mainly composed of columns and roofs, and can span a large space to connect different buildings. Its design form is various, including straight corridor, curved corridor and complex corridor, which can be customized according to the terrain and architectural style. The wind and rain corridor is usually spacious enough to accommodate multiple people to pass through at the same time and provide comfortable walking space. It not only blocks wind and rain, but also provides a certain degree of sun-shading effect.

[0003] The existing assembled wind and rain corridor with convenient butt joint is mostly installed and fixed in two sections, which affects the operation convenience of the staff when installing and disassembling the corridor, and affects the support stability of the whole installed corridor. INVENTION CONTENTS

[0004] To solve the above technical problems, the utility model provides an assembled wind and rain corridor with convenient butt joint.

[0005] The utility model adopts the following technical scheme: an assembled wind and rain corridor with convenient butt joint, comprising a corridor top plate, the bottom of the corridor top plate is fixedly connected with a mounting clamping frame, a limiting clamping groove is formed in the inside of the mounting clamping frame;

[0006] An installation support rod is inserted into the inside of the mounting clamping frame, a positioning clamping rod is fixedly connected to the surface of the installation support rod, a connecting clamping frame is inserted into the bottom of the installation support rod, a connecting screw rod is screw-connected in the inside of the connecting clamping frame, a bearing support rod is inserted into the inside of the connecting clamping frame, a supporting bottom plate is fixedly connected to the bottom of the bearing support rod, and a positioning hole is formed in the inside of the bearing support rod.

[0007] As a further improvement of the above scheme, a positioning clamping rod is inserted into the inside of the limiting clamping groove, and the installation support rod is inserted into the inside of the limiting clamping groove. The bottom of the corridor top plate is in contact with the top surface of the installation support rod.

[0008] As a further improvement of the above scheme, the number of the mounting clamping frame and the installation support rod is four, and each two is a group. The four mounting clamping frames and installation support rods are symmetrically distributed around the corridor top plate.

[0009] Through the technical scheme, the limiting clamping grooves in the installation clamping frames and the plug-in structures of the installation supporting rods, and the plug-in of the positioning clamping rods and the limiting clamping grooves enable the installation supporting rods to be accurately positioned below the corridor roof plate, and the four installation clamping frames and the installation supporting rods are symmetrically distributed with the corridor roof plate as the center, the symmetric layout provides uniform supporting force for the corridor roof plate, and ensures the stability of the corridor roof plate and prevents the corridor roof plate from tilting or shaking during use.

[0010] As a further improvement of the above-mentioned scheme, the top of the positioning clamping rod is in surface contact with the bottom surface of the corridor roof plate, and the connecting screw rod extends through the connecting clamping frame to the inside of the installation supporting rod.

[0011] As a further improvement of the above-mentioned scheme, the connecting screw rod extends through the connecting clamping frame to the inside of the bearing supporting rod and the positioning hole, and the number of the bearing supporting rods is four.

[0012] Through the technical scheme, the connecting screw rod extends through the connecting clamping frame to the inside of the installation supporting rod, the bearing supporting rod and the positioning hole, and the installation supporting rod, the connecting clamping frame and the bearing supporting rod are tightly connected together, the setting of multiple connecting screw rods enhances the firmness of the connection, and the frame structure of the whole corridor is more stable.

[0013] As a further improvement of the above-mentioned scheme, the top of the bearing supporting rod is in surface contact with the bottom end of the installation supporting rod, and the number of the connecting screw rods is several, and each two is a group.

[0014] As a further improvement of the above-mentioned scheme, the number of the supporting bottom plates is four, and the four supporting bottom plates are symmetrically distributed with the corridor roof plate as the center.

[0015] Compared with the prior art, the utility model has the advantages that:

[0016] The utility model discloses the top of bearing supporting rod is in surface contact with the bottom end of installation supporting rod, further ensure the effective transmission of force, make the weight of corridor roof plate can be evenly transmitted to bearing supporting rod through installation supporting rod, again by bearing supporting rod transmission to supporting bottom plate, the plug-in structure is convenient for the butt joint operation in the assembly type construction process through setting installation supporting rod and plug-in in connecting clamping frame inside, bearing supporting rod also plug-in in connecting clamping frame inside, and the relative position between parts can be fine-tuned to a certain extent through the fastening degree of connecting screw rod, guarantee the close cooperation between parts, adapt to different installation environment and requirement and the support stability and convenience after installation.

[0017] The utility model discloses a four support bottom plate is set up to be symmetrical with the corridor roof plate as center, provides stable bottom support for whole rain porch, they can evenly share the weight of porch, including the weight of porch roof plate, installation support pole, connecting card frame and bearing support pole etc. BRIEF DESCRIPTION OF DRAWINGS

[0018] Figure 1 It is whole structure schematic diagram of the utility model;

[0019] Figure 2 It is explosion structure schematic diagram of the utility model;

[0020] Figure 3 It is side anatomical structure schematic diagram of the utility model;

[0021] Figure 4 It is the structure schematic diagram of the utility model of looking up;

[0022] Figure 5 It is the structure schematic diagram of the utility model of right view.

[0023] Main symbol explanation:

[0024] 1, porch roof plate;2, installation card frame;3, limit card slot;4, installation support pole;5, positioning card rod;6, connecting card frame;7, connecting screw;8, bearing support pole;9, positioning hole;10, support bottom plate. DETAILED DESCRIPTION

[0025] Below, combining the drawings and specific implementation, the utility model is described further, need explaining is, under the premise of not conflicting, the following description between each embodiment or between each technical feature can be combined to form new embodiment.

[0026] Embodiment:

[0027] Please combine Figures 1-5 , a kind of convenient docking's assembly type rain porch of the embodiment, including porch roof plate 1, the bottom of porch roof plate 1 is fixedly connected with installation card frame 2, limit card slot 3 is set in the inside of installation card frame 2;

[0028] The inside of the installation clamping frame 2 is inserted with the installation supporting rod 4, the surface of the installation supporting rod 4 is fixedly connected with the positioning clamping rod 5, the bottom of the installation supporting rod 4 is inserted with the connecting clamping frame 6, the inside of the connecting clamping frame 6 is threadedly connected with the connecting screw rod 7, the inside of the connecting clamping frame 6 is inserted with the bearing supporting rod 8, the bottom of the bearing supporting rod 8 is fixedly connected with the supporting bottom plate 10, the inside of the bearing supporting rod 8 is provided with the positioning hole 9, the top of the bearing supporting rod 8 is in surface contact with the bottom end of the installation supporting rod 4, which further ensures the effective transmission of force, so that the weight of the corridor roof plate 1 can be evenly transmitted to the bearing supporting rod 8 through the installation supporting rod 4, and then transmitted to the supporting bottom plate 10 through the bearing supporting rod 8, the installation supporting rod 4 is inserted in the inside of the connecting clamping frame 6, and the bearing supporting rod 8 is also inserted in the inside of the connecting clamping frame 6, so that the butt joint operation in the assembly type construction process is facilitated, and the relative positions between the components can be adjusted to a certain extent by adjusting the fastening degree of the connecting screw rod 7, so as to ensure the close cooperation between the components, adapt to different installation environments and requirements, and ensure the supporting stability and convenience after installation.

[0029] The inside of the limiting clamping groove 3 is inserted with the positioning clamping rod 5, and the installation supporting rod 4 is inserted in the inside of the limiting clamping groove 3.

[0030] The number of the installation clamping frame 2 and the installation supporting rod 4 is four, and every two is a group, and the four installation clamping frames 2 and the installation supporting rods 4 are symmetrically distributed around the corridor roof plate 1.

[0031] The insertion structure of the limiting clamping groove 3 in the installation clamping frame 2 and the installation supporting rod 4, and the insertion of the positioning clamping rod 5 and the limiting clamping groove 3, enables the installation supporting rod 4 to be accurately positioned below the corridor roof plate 1, and the four installation clamping frames 2 and the installation supporting rods 4 are symmetrically distributed around the corridor roof plate 1, which provides uniform support force for the corridor roof plate 1, ensures the stability of the corridor roof plate 1, and prevents it from tilting or shaking during use.

[0032] The top of the positioning clamping rod 5 is in surface contact with the bottom of the corridor roof plate 1, and the connecting screw rod 7 extends through the connecting clamping frame 6 to the inside of the installation supporting rod 4.

[0033] The connecting screw 7 extends through the connecting clamping frame 6 to the inside of the bearing support rod 8 and the positioning hole 9. The number of bearing support rods 8 is four, which are symmetrically distributed around the corridor top plate 1 by setting four support bottom plates 10. They provide stable bottom support for the entire covered walkway and can evenly share the weight of the corridor, including the weight of the corridor top plate 1, the mounting rod 4, the connecting clamping frame 6 and the bearing support rod 8, etc. At the same time, they can also resist lateral forces generated by external forces such as wind and rain to ensure the safety and stability of the covered walkway during use. They can effectively play a supporting role in different terrains and building layouts and are an important foundation of the entire assembled covered walkway structure.

[0034] The connecting screw 7 extends through the connecting clamping frame 6 to the inside of the mounting rod 4, the bearing support rod 8 and the positioning hole 9, tightly connecting the mounting rod 4, the connecting clamping frame 6 and the bearing support rod 8 together. The setting of multiple connecting screws 7 enhances the firmness of the connection and makes the frame structure of the entire covered walkway more stable.

[0035] The top of the bearing support rod 8 is in contact with the bottom end surface of the mounting rod 4. The number of connecting screws 7 is several, and each two is a group.

[0036] The number of support bottom plates 10 is four, which are symmetrically distributed around the corridor top plate 1.

[0037] The implementation principle of the assembled covered walkway for convenient docking in the embodiment of the application is that the top of the bearing support rod 8 is in contact with the bottom end surface of the mounting rod 4, which further ensures the effective transmission of force, so that the weight of the corridor top plate 1 can be evenly transmitted to the bearing support rod 8 through the mounting rod 4, and then transmitted to the support bottom plate 10 through the bearing support rod 8. The mounting rod 4 is inserted into the connecting clamping frame 6, and the bearing support rod 8 is also inserted into the connecting clamping frame 6. This insertion structure facilitates docking operation during assembly construction. By adjusting the fastening degree of the connecting screw 7, the relative positions between the components can be adjusted to a certain extent, ensuring the close cooperation between the components, adapting to different installation environments and requirements, and ensuring the support stability and convenience after installation. Four support bottom plates 10 are symmetrically distributed around the corridor top plate 1, providing stable bottom support for the entire covered walkway. They can evenly share the weight of the corridor, including the weight of the corridor top plate 1, the mounting rod 4, the connecting clamping frame 6 and the bearing support rod 8, etc. At the same time, they can also resist lateral forces generated by external forces such as wind and rain to ensure the safety and stability of the covered walkway during use. They can effectively play a supporting role in different terrains and building layouts and are an important foundation of the entire assembled covered walkway structure.

[0038] The above-mentioned embodiments are only preferred embodiments of the present application, and cannot be used to limit the scope of protection of the present application. Any non-essential changes and replacements made by those skilled in the art on the basis of the present application shall fall within the scope of protection of the present application.

Claims

1. A prefabricated weather porch which facilitates docking, characterized in that Including the corridor roof (1), the bottom of the corridor roof (1) is fixedly connected with the installation card frame (2), the inside of the installation card frame (2) is provided with the limiting card slot (3); The inside of the installation card frame (2) is inserted with the installation support rod (4), the surface of the installation support rod (4) is fixedly connected with the positioning card rod (5), the bottom of the installation support rod (4) is inserted with the connecting card frame (6), the inside of the connecting card frame (6) is threadedly connected with the connecting screw rod (7), the inside of the connecting card frame (6) is inserted with the bearing support rod (8), the bottom of the bearing support rod (8) is fixedly connected with the support bottom plate (10), and the inside of the bearing support rod (8) is provided with the positioning hole (9).

2. The prefabricated enclosed walkway of claim 1, wherein: The inside of the limiting card slot (3) is inserted with the positioning card rod (5), the installation support rod (4) is inserted in the inside of the limiting card slot (3), and the bottom of the corridor roof (1) is in contact with the top surface of the installation support rod (4).

3. The prefabricated enclosed walkway of claim 1, wherein: The number of the installation card frame (2) and the installation support rod (4) is four, and every two is a group, and four installation card frames (2) and installation support rods (4) are symmetrically distributed around the corridor roof (1).

4. The prefabricated enclosed walkway of claim 1, wherein: The top of the positioning card rod (5) is in contact with the bottom surface of the corridor roof (1), and the connecting screw rod (7) extends through the connecting card frame (6) to the inside of the installation support rod (4).

5. The prefabricated enclosed walkway of claim 1, wherein: The connecting screw rod (7) extends through the connecting card frame (6) to the inside of the bearing support rod (8) and the positioning hole (9), and the number of the bearing support rod (8) is four.

6. The prefabricated enclosed walkway that facilitates docking according to claim 1, characterized in that: The top of the bearing support rod (8) is in contact with the bottom end surface of the installation support rod (4), and the number of the connecting screw rod (7) is several, and every two is a group.

7. The prefabricated enclosed walkway that facilitates docking according to claim 1, characterized in that: The number of the support bottom plate (10) is four, and four support bottom plates (10) are symmetrically distributed around the corridor roof (1).