Water tank for PVC plastic pipe production

By adopting a water tank design with spiral spray pipes and scraper structure in the production of PVC plastic pipes, water stains after spray cooling are cleaned, solving the problem of water stain adhesion, improving production efficiency and reducing material damage.

CN224130430UActive Publication Date: 2026-04-17QINGDAO HANHAI PLASTIC MASCH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
QINGDAO HANHAI PLASTIC MASCH CO LTD
Filing Date
2025-03-31
Publication Date
2026-04-17

AI Technical Summary

Technical Problem

In the production of PVC plastic pipes, water stains after spraying and cooling adhere to the pipe surface, increasing the subsequent drying time and affecting production efficiency.

Method used

A water tank for PVC plastic pipe production was designed, which includes a spiral spray pipe and a scraper structure. It cools the water by spraying it with two different temperatures and uses the scraper to clean the residual water stains, thereby reducing water stain adhesion.

Benefits of technology

It effectively reduces water stains on the pipe surface, shortens drying time, improves production efficiency, and reduces material damage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224130430U_ABST
    Figure CN224130430U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of plastic pipe production, in particular to a water tank for PVC (polyvinyl chloride) plastic pipe production, which comprises a water tank main body and an acrylic cover plate connected to the water tank main body through screws, and is characterized in that a partition plate is fixedly connected to the interior of the water tank main body through screws, and a sealing ring is fixed between the periphery of the partition plate and the water tank main body; the interior of the water tank body is divided into a first cooling cavity and a second cooling cavity through a partition plate, hole grooves are correspondingly formed in the two sides of the water tank body, a first threading pipe and a second threading pipe are fixedly connected into the hole grooves correspondingly, and hole grooves are formed in the positions, corresponding to the first threading hole and the second threading hole, of the surface of the partition plate. And a pipeline main body is movably connected into the threading pipe I, the hole grooves in the partition plate and the threading pipe II. Water stains left on the surface of the pipeline body after spraying and cooling can be scraped and cleaned, water stains attached to the surface of the pipeline are reduced, the subsequent drying time of the pipeline body is shortened, and the subsequent production and processing efficiency of the pipeline is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of plastic pipe production technology, and in particular relates to a water tank for PVC plastic pipe production. Background Technology

[0002] During the production of PVC plastic pipes, an extruder is typically used to continuously extrude the pipe material. The temperature of PVC during extrusion is relatively high, and water cooling is usually used to cool the PVC pipes by spraying water onto the pipe wall. However, some of the sprayed water will adhere to the surface of the pipe. In subsequent processing, the pipes need to be dried, such as for subsequent marking on the pipe surface. This greatly affects the production efficiency of the pipes and increases the time spent on secondary processing. Utility Model Content

[0003] The purpose of this utility model is to provide a water tank for PVC plastic pipe production. This application can scrape and clean the residual water stains on the surface of the pipe body after spray cooling, reduce water stain adhesion on the pipe surface, reduce the subsequent drying time of the pipe body, and improve the efficiency of subsequent pipe production and processing, so as to solve the problems mentioned in the background art.

[0004] To achieve the above objectives, the present invention adopts the following technical solution: a water tank for PVC plastic pipe production, comprising a water tank body and an acrylic cover plate screwed onto the water tank body, characterized in that a partition plate is screwed and fixed inside the water tank body, and a sealing ring is fixed between the partition plate and the water tank body. The water tank body is divided into a first cooling chamber and a second cooling chamber by the partition plate. Holes and slots are correspondingly opened on both sides of the water tank body, and a first through-hole pipe and a second through-hole pipe are fixedly connected in the holes and slots respectively. Holes and slots are also opened on the surface of the partition plate at positions corresponding to the first through-hole pipe and the second through-hole pipe. A pipe body is movably connected to the first through-hole pipe, the holes and slots on the partition plate, and the second through-hole pipe. A spiral water spray pipe is sleeved on the outside of the pipe body located in the first cooling chamber and the second cooling chamber. Several spray holes are opened on the inner side of the spiral water spray pipe.

[0005] The inside of the second guide tube is fixedly connected to scraper one and scraper two respectively.

[0006] Preferably, a water pump is screwed and fixed to the front end face of the water tank body at the corresponding positions of the first cooling chamber and the second cooling chamber.

[0007] Preferably, the rear end face of the water tank body is fixedly connected to the corresponding positions of the first cooling chamber and the second cooling chamber with pipe joints.

[0008] Preferably, one end of the spiral water spray pipe is fixed to the partition plate by screws, one end of the spiral water spray pipe extends to the bottom of the water tank body, and the other end is connected to the water pump supply end, and the water pump pump pumping end is connected to the inside of the treatment tank.

[0009] Preferably, the number of scraper blade one and scraper blade two is at least three sets of rings evenly distributed on the inner wall of the through-tube two.

[0010] Preferably, the first scraper and the second scraper are made of hard rubber, and the three scraper blades form a conical structure.

[0011] Preferably, a drainage hole is provided on the lower outer surface of the second guide tube between the first scraper and the second scraper.

[0012] In summary, compared with the prior art, the beneficial effects of this utility model are: this application can scrape and clean the residual water stains on the surface of the pipe body after spray cooling, reduce the adhesion of water stains on the pipe surface, reduce the subsequent drying time of the pipe body, and improve the efficiency of subsequent pipe production and processing.

[0013] This application enables the pipe body to be cooled by spraying twice, which can reduce the damage caused by the rapid cooling of the pipe body material compared with traditional low-temperature direct spraying. Attached Figure Description

[0014] Figure 1 This is an overall structural view of the present invention;

[0015] Figure 2 This is a rear view of the overall structure of this utility model;

[0016] Figure 3 This is an internal view of the main body of the water tank of this utility model;

[0017] Figure 4 This is a top view of the main body of the water tank of this utility model;

[0018] Figure 5 This is a cross-section of the second insertion tube of this utility model;

[0019] Figure 6 This is a structural diagram of the scraper blade of this utility model.

[0020] Legend:

[0021] 1. Acrylic cover plate; 2. Water tank body; 3. Pipe body; 4. Through-pipe one; 5. Water pump; 6. Pipe joint; 7. Partition plate; 8. Spiral water spray pipe; 9. First cooling chamber; 10. Second cooling chamber; 11. Through-pipe two; 12. Scraper one; 13. Scraper two; 14. Drain hole. Detailed Implementation

[0022] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of the present utility model.

[0023] Please see Figure 1-6 This utility model provides a technical solution:

[0024] A water tank for PVC plastic pipe production includes a tank body 2 and an acrylic cover plate 1 screwed onto the tank body 2. A partition plate 7 is screwed and fixed inside the tank body 2. Sealing rings are fixed between the partition plate 7 and the tank body 2. The interior of the tank body 2 is divided into a first cooling chamber 9 and a second cooling chamber 10 by the partition plate 7. The areas of the first cooling chamber 9 and the second cooling chamber 10 can be changed according to the installation position of the partition plate 7 in the tank body 2, allowing for the replacement of corresponding spiral water spray pipes 8. The cooling water temperature sprayed by the spiral water spray pipes 8 in the first cooling chamber 9 is 35℃-45℃, and the cooling water temperature sprayed by the spiral water spray pipes 8 in the second cooling chamber 10 is... The temperature is between 18℃ and 22℃. By cooling the pipe body 3 with two cooling waters of different temperatures, the pipe body 3 can be gradually cooled and shaped. Compared with the traditional method of directly spraying low temperature cooling water, this method can reduce the damage caused by the rapid temperature change of the pipe body 3 material. The two sides of the water tank body 2 are provided with corresponding slots. Through-hole pipe 1 4 and through-hole pipe 2 11 are fixedly connected in the slots. The surface of the partition plate 7 is also provided with slots corresponding to through-hole 1 and through-hole 2. The pipe body 3 is movably connected in through-hole pipe 1 4, slots on the partition plate 7 and through-hole pipe 2 11. The pipe body 3 located in the first cooling chamber 9 and the second cooling chamber 10 is sleeved with a spiral water spray pipe 8. Several spray holes are provided on the inner side of the spiral water spray pipe 8.

[0025] The inside of the second through-tube 11 is fixedly connected to scraper 12 and scraper 2 13 respectively.

[0026] Specifically, water pumps 5 are screwed and fixed to the front end face of the water tank body 2 at the corresponding positions of the first cooling chamber 9 and the second cooling chamber 10.

[0027] Specifically, the rear end face of the water tank body 2 is fixedly connected to the corresponding positions of the first cooling chamber 9 and the second cooling chamber 10 with pipe joints 6. One end of the spiral water spray pipe 8 is fixedly connected to the partition plate 7 by screws. One end of the spiral water spray pipe 8 extends to the bottom of the water tank body 2, and the other end is connected to the water supply end of the water pump 5. The water pump 5's pumping end is connected to the inside of the treatment tank.

[0028] Specifically, the number of scraper blades 12 and 13 is at least three sets of annularly distributed on the inner wall of the through-tube 11. The scraper blades 12 and 13 are made of hard rubber material, and the three scraper blades 12 and 13 form a conical structure. A drainage hole 14 is opened on the lower side of the outer surface of the through-tube 11 between the scraper blades 12 and 13.

[0029] Working principle:

[0030] During operation, the main pipe 3 enters the water tank body 2 through the through-pipe 4, passes through the first cooling chamber 9 and the spiral spray pipe 8, then extends through the slots on the partition 7 to the second cooling chamber 10 and the spiral spray pipe 8, and finally extends out of the water tank body 2 through the through-pipe 11. As the main pipe 3 passes through the first cooling chamber 9 and the second cooling chamber 10, the corresponding water pump 5 draws and delivers the cooling water from the cooling chambers to the spiral spray pipe 8. The water is then evenly sprayed onto the surface of the main pipe 3 through the spray holes in the spiral spray pipe 8, thus improving the cooling effect on the pipe. The main body 3 is cooled, and the corresponding cooling chamber is also controlled by the external water pump 5 or the circulating water temperature control system through the pipe joint 6. This is used to strictly control the temperature of the cooling water in the corresponding cooling chamber. The temperature sensor is built into the bottom of the corresponding cooling chamber. When the main body 3 passes through the second through-pipe 11, the water stains attached to the surface of the main body 3 are scraped and cleaned by the scraper blades 12 and 13. The water droplets scraped and cleaned by the scraper blade 13 fall into the inside of the second through-pipe 11 and are finally discharged into the second cooling chamber 10 through the drain hole 14.

[0031] The above description is only a preferred embodiment of the present utility model, but the protection scope of the present utility model is not limited thereto. Any equivalent substitutions or changes made by those skilled in the art within the technical scope disclosed in the present utility model, based on the technical solution and the inventive concept of the present utility model, should be included within the protection scope of the present utility model.

Claims

1. A water tank for PVC plastic pipe production, comprising a water tank body (2) and an acrylic cover plate (1) screwed on the water tank body (2), characterized in that, The water tank body (2) is internally screwed and fixed with a partition (7). A sealing ring is fixed between the partition (7) and the water tank body (2). The interior of the water tank body (2) is divided into a first cooling chamber (9) and a second cooling chamber (10) with the partition (7) as the center. The water tank body (2) is provided with corresponding slots on both sides. A through-tube one (4) and a through-tube two (11) are fixedly connected in the slots. The surface of the partition (7) is also provided with slots corresponding to the through-hole one and through-hole two. A pipe body (3) is movably connected in the through-tube one (4), the slots on the partition (7) and the through-tube two (11). A spiral water spray pipe (8) is sleeved on the outside of the pipe body (3) located in the first cooling chamber (9) and the second cooling chamber (10). Several water spray holes are provided on the inner side of the spiral water spray pipe (8). The inside of the second through-tube (11) is fixedly connected to scraper one (12) and scraper two (13).

2. The water tank for PVC plastic pipe production according to claim 1, characterized in that, Water pumps (5) are screwed and fixed to the front end face of the water tank body (2) at the corresponding positions of the first cooling chamber (9) and the second cooling chamber (10).

3. The water tank for PVC plastic pipe production according to claim 2, characterized in that, The rear end face of the water tank body (2) is fixedly connected to the corresponding positions of the first cooling chamber (9) and the second cooling chamber (10) with pipe joints (6).

4. The water tank for PVC plastic pipe production according to claim 1, characterized in that, One end of the spiral water spray pipe (8) is fixed to the partition plate (7) by screws. One end of the spiral water spray pipe (8) extends to the bottom of the water tank body (2), and the other end is connected to the water pump (5) water delivery end. The water pump (5) water pump end is connected to the inside of the treatment tank.

5. The water tank for PVC plastic pipe production according to claim 1, characterized in that, The number of scraper blade one (12) and scraper blade two (13) is at least three sets of rings equally spaced on the inner wall of the through-tube two (11).

6. The water tank for PVC plastic pipe production according to claim 5, characterized in that, The scraper blade 1 (12) and scraper blade 2 (13) are made of hard rubber material, and the three scraper blades 1 (12) and scraper blade 2 (13) form a conical structure.

7. A PVC plastic pipe production water tank according to claim 1, characterized in that, A drainage hole (14) is provided on the lower outer surface of the second through-tube (11) between the first scraper (12) and the second scraper (13).