Truss crane maintenance platform and maintenance system
By designing a gantry crane maintenance platform and utilizing traction rods and sliding components to achieve the sliding of the gantry crane maintenance platform, the problems of inconvenience and high cost in gantry crane maintenance are solved, achieving efficient and low-cost maintenance results.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- CHINA RAILWAY BRIDGE BUREAU NO 7 ENG CO LTD
- Filing Date
- 2024-12-26
- Publication Date
- 2026-05-05
AI Technical Summary
In the existing technology, it is inconvenient and costly to use aerial work platforms when maintaining the hoist and running track of a gantry crane.
Design a gantry crane maintenance platform, including a first track beam, a maintenance platform and a traction rod. The platform is connected to the gantry crane through the traction rod, and a sliding component is used to make the maintenance platform slide along the track beam to realize the maintenance of the gantry crane's running track and hoist.
It has made the maintenance of gantry cranes convenient and cost-effective, reduced equipment downtime, and lowered maintenance costs.
Smart Images

Figure CN224199031U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of gantry crane maintenance technology, and in particular to a gantry crane maintenance platform and maintenance method. Background Technology
[0002] Steel bar processing yards are typically shed structures with multiple rows of steel columns supporting the roof. A gantry crane is usually installed on one or more of these columns for hoisting steel bars and equipment. Gantry cranes are common special equipment in industrial production sites. To ensure safe operation, the gantry crane's hoist and running rails must be regularly inspected and maintained.
[0003] In related technologies, since the hoist and track of the gantry crane are at a high distance from the ground, aerial work platforms are mostly used for maintenance of the hoist and track. However, aerial work platforms are inconvenient to move around on site, occupy equipment for a long time, and are costly. Utility Model Content
[0004] This utility model provides a gantry crane maintenance platform and maintenance system to solve the problems in related technologies where using aerial work platforms to maintain the hoist and track of a gantry crane is inconvenient to move around the site, occupies the equipment for a long time, and is costly.
[0005] In a first aspect, a gantry crane maintenance platform is provided, characterized in that it comprises: a first track beam, the first track beam having a plurality of first brackets, the plurality of first brackets being spaced apart along the extension direction of the first track beam and used to fix to a plurality of steel columns, and the plurality of first brackets being supported on the first track beam; a maintenance platform, the maintenance platform including a platform, the bottom of the platform having a sliding component, the sliding component being slidably installed on the first track beam; and at least one traction rod, one end of the at least one traction rod being detachably connected to the platform, and the other end of the traction rod being used to detachably connect to the gantry crane.
[0006] In some embodiments, two traction rods are provided, which are respectively set on opposite sides of the gantry crane; each traction rod has a connecting part at both ends, one connecting part of each traction rod is hinged to the first traction base of the platform, and the other connecting part is hinged to the second traction base fixed on one side of the gantry crane.
[0007] In some embodiments, the traction rod further includes a connecting tube and two adjusting rods, the two adjusting rods being coaxially inserted through both ends of the connecting tube, and the adjusting rods being threadedly engaged with the connecting tube; the connecting part includes a connecting lug, the connecting lug being fixed to the adjusting rod.
[0008] In some embodiments, the first track beam has a first track, and the sliding assembly includes two sets of moving parts spaced apart at the bottom of the platform along the extension direction of the first track beam. Each set of moving parts includes two rollers and an axle connecting the two rollers. The axle is connected to the platform, and the axis of the rollers is perpendicular to the first track. The rollers are adapted to roll on the first track.
[0009] In some embodiments, the bottom of the platform is provided with at least two mounting seats at intervals, the axle passes through the two mounting seats, and the bottom of the mounting seat is provided with a limiting groove, and part of the roller is provided in the limiting groove; the first track beam is provided with at least two limiting plates, and the two limiting plates are adapted to abut against the opposite sides of the two mounting seats respectively.
[0010] In some embodiments, the platform includes: a platform, the platform and the first track beam being disposed on opposite sides of the sliding assembly; a fixed guardrail, the fixed guardrail including multiple crisscrossing fixed rods; and a lifting guardrail, the lifting guardrail being disposed on the side of the platform near the steel column, the fixed guardrail and the lifting guardrail being disposed on opposite sides of the platform.
[0011] In some embodiments, the lifting guardrail includes: a lifting railing and a sensing device disposed on one side of the lifting railing, the sensing device being installed on the side of the lifting railing away from the platform.
[0012] In some embodiments, the gantry crane maintenance platform further includes at least one stiffening plate, wherein at least one stiffening plate is disposed at the first corbel for fixing to the steel column.
[0013] Secondly, a gantry crane maintenance system is provided, characterized in that it comprises: at least two rows of steel columns, each row of steel columns being provided with a second track beam; a gantry crane spanning the at least two rows of steel columns and slidably mounted on the second track beam; a first track beam located below the second track beam, the first track beam being provided with a plurality of first brackets, the plurality of first brackets being spaced apart along the extension direction of the first track beam, each first bracket being fixed to a single steel column of each row of steel columns, and the plurality of first brackets being supported on the first track beam; a maintenance platform, the maintenance platform including a platform, the bottom of the platform being provided with a sliding component, the sliding component being slidably mounted on the first track beam; and at least one traction rod, one end of the at least one traction rod being detachably connected to the platform, and the other end of the traction rod being detachably connected to the gantry crane.
[0014] In some embodiments, the surface of the second track beam is provided with conductive slide rails, and the end of the gantry crane near the second track beam is provided with an electric slider that cooperates with the conductive slide rails.
[0015] The beneficial effects of the technical solution provided by this utility model include:
[0016] This utility model embodiment provides a gantry crane maintenance platform and maintenance system. Since the bottom of the platform is equipped with a sliding component, which is slidably installed on the first track beam, and the first track beam extends along the direction of multiple steel columns, when the gantry crane slides along the running track on the steel columns, the traction rod installed on the gantry crane is also pulled. The other end of the traction rod is connected to the platform, so the platform is pulled by the traction rod and slides along the first track beam. Therefore, maintenance personnel can be pulled on the platform to maintain the running track and hoist of the gantry crane. Attached Figure Description
[0017] To more clearly illustrate the technical solutions in the embodiments of this utility model, the drawings used in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0018] Figure 1 A front view structural schematic diagram of the gantry crane maintenance system provided in an embodiment of this utility model;
[0019] Figure 2 This is a side view of the gantry crane maintenance system provided in an embodiment of the present utility model.
[0020] Figure 3 A schematic diagram of the structure of the maintenance bench provided in this embodiment of the utility model;
[0021] Figure 4 A schematic diagram of the traction rod provided in an embodiment of this utility model;
[0022] Figure 5 This is a schematic diagram of the structure of the first traction base or the second traction base provided in the embodiments of this utility model;
[0023] Figure 6 This is a partially enlarged structural schematic diagram of the gantry crane maintenance system provided in an embodiment of the present invention.
[0024] In the picture:
[0025] 1. First track beam; 12. Limiting plate;
[0026] 2. First beef leg;
[0027] 3. Inspection platform; 31. Platform; 32. Sliding assembly; 311. First traction base; 312. Second traction base; 321. Moving part; 3211. Roller; 3212. Axle; 322. Mounting seat; 33. Station plate; 34. Fixed guardrail; 35. Lifting guardrail; 36. Platform panel;
[0028] 4. Traction rod; 41. Connecting part; 42. Connecting pipe; 43. Adjusting rod; 411. Connecting ear plate;
[0029] 5. Gantry crane; 52. Electric slider;
[0030] 6. Stiffening plate;
[0031] 7. Steel column; 71. Second track beam; 72. Conductive slide rail; 73. Second bracket;
[0032] 8. Crane hoist. Detailed Implementation
[0033] To make the objectives, technical solutions, and advantages of the embodiments of this utility model clearer, the technical solutions of the embodiments of this utility model will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of this utility model. Based on the embodiments of this utility model, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of this utility model.
[0034] This utility model provides a gantry crane maintenance platform, which solves the problems in related technologies where using aerial work platforms to maintain the hoist and track of a gantry crane is inconvenient, occupies equipment for a long time, and is costly.
[0035] See Figure 1 and Figure 2The diagram shows a gantry crane maintenance platform provided in this embodiment of the present invention. It may include: a first track beam 1, which has multiple first brackets 2. The first brackets 2 can be H-beams or box-beam structures. The multiple first brackets 2 are spaced apart along the extension direction of the first track beam 1 and are used to fix to multiple steel columns 7. The multiple first brackets 2 are supported by the first track beam 1. In this embodiment, the rebar processing area can be located on the ground, and multiple steel columns 7 are provided within the rebar processing area. Each steel column 7 can be fixed with one first bracket 2. Preferably, each first bracket 2 is at the same height from the ground, and the first track beam 1 can be fixed to the first brackets 2 away from the ground. One side; maintenance platform 3, the maintenance platform 3 includes a platform 31, the bottom of the platform 31 is provided with a sliding component 32, the sliding component 32 is slidably installed on the first track beam 1, that is, the platform 31 can slide along the extension direction of the first track beam 1, the maintenance personnel stand in the platform 31 at this time, and carry out maintenance on the track on which the gantry crane 5 runs as the platform 31 slides; and at least one traction rod 4, one end of the at least one traction rod 4 is detachably connected to the platform 31, the other end of the traction rod 4 is used to detachably connect to the gantry crane 5, the two ends of the traction rod 4 are respectively connected to the gantry crane 5 and the platform 31, when the gantry crane 5 runs on the track on the steel column 7, it can pull the platform 31 through the traction rod 4.
[0036] See Figure 2 As shown, in some optional embodiments, two traction rods 4 are provided, which are respectively set on opposite sides of the gantry crane 5. The two traction rods 4 make it easier to pull the platform 31. Each traction rod 4 has a connecting part 41 at both ends. One connecting part 41 of each traction rod 4 is hinged to the first traction base 311 of the platform 31, and the other connecting part 41 is hinged to the second traction base 312 fixed on one side of the gantry crane 5. During the process of the gantry crane 5 pulling the traction rod 4 and the traction rod 4 pulling the platform 31, the part of the connecting part 41 that connects the first traction base 311 and the second traction base 312 is set to be hinged, which makes the movement of the traction rod 4 more flexible and less prone to breakage.
[0037] See Figure 4 and Figure 5As shown, in some optional embodiments, the traction rod 4 includes a connecting pipe 42 and two adjusting rods 43. The connecting pipe 42 is a hollow structure, and the two adjusting rods 43 are coaxially inserted at both ends of the connecting pipe 42. The adjusting rods 43 are threadedly engaged with the connecting pipe 42, that is, the surface of the adjusting rods 43 and the inside of the connecting pipe 42 can be provided with threads. The length of the adjusting rods 43 extending out of the connecting pipe 42 is adjusted by screwing them in the connecting pipe 42, that is, the length of the entire traction rod 4 is adjusted. Preferably, nuts can be fixed at both ends of the connecting pipe 42. In this case, the adjusting rods 43 with threads on their surfaces are engaged with the nuts. The connecting part 41 includes a connecting ear plate 411. The connecting ear plate 411 is fixed with the adjusting rods 43. The connecting ear plate 411 can be provided with through holes. The first traction base 311 and the second traction base 312 are also provided with through holes to engage with it. The bolts and nuts passing through the through holes achieve hinged connection and also facilitate the removal of the adjusting rods 43 from the gantry crane 5 and the platform 31.
[0038] In some optional embodiments, the first track beam 1 has a first track, and the sliding assembly 32 includes two sets of moving parts 321 spaced apart at the bottom of the platform 31 along the extension direction of the first track beam 1. Each set of moving parts 321 includes two rollers 3211 and an axle 3212 connecting the two rollers 3211. The axle 3212 is connected to the platform 31. The axis of the rollers 3211 is perpendicular to the first track, and the rollers 3211 are adapted to roll on the first track. That is, the platform 31 slides on the first track beam 1 by the cooperation of the rollers 3211 and the first track, so that the rollers 3211 roll along the first track to change the position of the platform 31 in the first track beam 1. In some other embodiments, the platform 31 can also slide in the first track beam 1 by setting a groove in the first track beam 1, and setting a slider at the bottom of the platform 31 that cooperates with the groove.
[0039] See Figure 6As shown, preferably, the bottom of the platform 31 is provided with at least two mounting seats 322 at intervals. The axle 3212 passes through the two mounting seats 322 and can be fixed to the mounting seats 322. The bottom of the mounting seat 322 is provided with a limiting groove, and part of the roller 3211 is located in the limiting groove, that is, part of the roller 3211 can extend beyond the bottom surface of the mounting frame. Preferably, four rollers 3211 are provided. Two rollers 3211 arranged perpendicular to the extension direction of the first track beam 1 are connected by the axle 3212. Two first track beams 1 can be provided, and the two first track beams 1 are arranged in parallel. The first track beam 1 can be close to the steel column 7. The side view is considered as the first side, and the side away from the steel column 7 is considered as the second side. The first track beam 1 on both the first and second sides is provided with two rollers 3211. The two rollers 3211 on the same side can be located in the limiting groove of the same mounting seat 322. Both first track beams 1 can be H-beams or box beams. The first track beam 1 is provided with at least two limiting plates 12. The two limiting plates 12 are adapted to abut against the opposite sides of the two mounting seats 322 respectively. The limiting plates 12 can contact the mounting seats 322 or be spaced apart from the mounting seats 322. The limiting plates 12 can protect the platform 31 from the rollers 3211 from sliding off the first track beam 1 during the sliding process of the first track beam 1.
[0040] See Figure 3 As shown, in some optional embodiments, the platform 31 includes a platform 33, which is disposed on opposite sides of the sliding component 32 along with the first track beam 1. Preferably, a platform panel 36 can be added on the side of the platform 33 away from the sliding component 32 to further increase the safety of the platform 31. In some embodiments, the first traction base 311 can be disposed on the upper surface of the mounting base 322, in which case the surfaces of the platform 33 and the platform panel 36 are provided with perforations through which the first traction base 311 can pass. A fixed guardrail 34, comprising multiple crisscrossing fixed bars, is provided to protect the safety of maintenance personnel during maintenance. A lifting guardrail 35 is installed on the side of the platform 33 closest to the steel column 7. Since the guardrail on the side closest to the steel column 7 is a lifting guardrail 35, it can be lowered when the platform 31 encounters a structure on the steel column 7 that obstructs its movement, thus preventing obstruction. Both the fixed guardrail 34 and the lifting guardrail 35 have a certain height to protect the safety of maintenance personnel. The fixed guardrail 34 and the lifting guardrail 35 are located on opposite sides of the platform 33. In some other embodiments, guardrails may also be installed on the other two sides of the platform 33.
[0041] In some optional embodiments, the lifting guardrail 35 includes: a lifting railing and a sensing device disposed on one side of the lifting railing. The sensing device is installed on the side of the lifting railing away from the platform 33. In this embodiment, the sensing device is set as a light sensor. When the sensing device senses a change in the brightness of the light, it automatically raises and lowers. During the raising and lowering process of the lifting railing, the height of the raising and lowering is limited, that is, when the lifting railing is lowered to the lowest point, it also has a height that can protect maintenance personnel. In some other embodiments, the lifting guardrail 35 can also be set as manually adjustable. When encountering a structure set on the steel column 7 that obstructs the operation of the maintenance platform 3, the height of the lifting guardrail 35 can be manually lowered to allow smooth passage.
[0042] Preferably, the gantry crane maintenance platform further includes: stiffening plate 6, which is disposed at the first bracket 2 for fixing to the steel column 7. Multiple stiffening plates 6 can be disposed at the positions where the first bracket 2 and the steel column 7 are subjected to relatively concentrated forces, in order to increase the stress strength of the first bracket 2.
[0043] This utility model embodiment also provides a gantry crane maintenance system, which may include: at least two rows of steel columns 7, each row of steel columns 7 is provided with a second track beam 71, the second track beam 71 extends along the extension direction of the first track beam 1, in some optional embodiments, the lower part of the second track beam 71 may also be provided with multiple second brackets 73 for supporting the second track beam 71, each second bracket 73 is fixed to the steel column 7, so that the fixation between the second track beam 71 and the steel column 7 is more secure, the second bracket 73 is preferably H-beam or box beam; gantry crane 5, the gantry crane 5 spans across at least two rows of steel columns 7, the gantry crane 5 is slidably installed on the second track beam 71, that is, multiple rows of steel columns 7 are set in the steel bar processing yard, the gantry crane 5 spans across the second track beam 71 of two adjacent rows of steel columns 7, the bottom of the second track beam 71 may be provided with second brackets 73 for support; first track beam 1 The first track beam 1 is located below the second track beam 71. The first track beam 1 is provided with a plurality of first brackets 2, which are spaced apart along the extension direction of the first track beam 1. Each first bracket 2 is fixed to a single steel column 7 of each row of steel columns 7, and the plurality of first brackets 2 are supported on the first track beam 1. The maintenance platform 3 includes a platform 31, and a sliding component 32 is provided at the bottom of the platform 31. The sliding component 32 is slidably installed on the first track beam 1. The maintenance platform 3 includes at least one traction rod 4, one end of which is detachably connected to the platform 31, and the other end of which is detachably connected to the gantry crane 5. In this embodiment, except for the gantry crane 5, the steel columns 7, and the second track beam 71 provided on the steel columns 7, its structure is the same as the gantry crane maintenance platform described above, and will not be described again here.
[0044] Preferably, the surface of the second track beam 71 is provided with conductive slide rails 72, and the end of the gantry crane 5 near the second track beam 71 is provided with an electric slider 52 that cooperates with the conductive slide rails 72. The sliding method of the gantry crane 5 on the second track beam 71 can also be other common sliding structures.
[0045] This utility model embodiment provides a gantry crane maintenance platform and maintenance system. Since the bottom of the platform 31 is equipped with rollers 3211, the rollers 3211 and the first slide rail can cooperate. The first track beam 1 extends along the direction of multiple steel columns 7. When the gantry crane 5 slides along the electric slide rail on the steel columns 7, the traction rod 4 set on the gantry crane 5 is also pulled. The other end of the traction rod 4 is connected to the platform 31, that is, connected to the maintenance platform 3. The maintenance platform 3 is pulled by the traction rod 4 and slides along the first track beam 1. Therefore, maintenance personnel can be pulled on the maintenance platform 3 to maintain the running track of the gantry crane 5. The fixed guardrail 34 and the lifting guardrail 35 can protect the safety of maintenance personnel. The limit plate 12 can further prevent the rollers 3211 from sliding off the first slide rail. The detachable traction rod 4 can facilitate maintenance personnel to maintain multiple rows of steel columns 7 in the steel bar processing yard, saving materials and reducing some installation steps.
[0046] When using the gantry crane maintenance platform and system to inspect the hoist 8 and the running track of the gantry crane 5, the specific installation process of the maintenance platform can be as follows:
[0047] First, select the specifications and materials of each component in the maintenance platform 3 according to the actual maintenance needs, and then assemble them. Based on the weight of the assembled maintenance platform 3 and the span of each row of 7 steel columns, select appropriate first track beam 1 and second track beam 71. Before installing the first track beam 1 onto the steel columns 7, the limiting plate 12 needs to be welded in advance. Then, based on the weight of the maintenance platform 3 and the first track beam 1, select appropriate first bracket 2. At a certain height below the gantry crane 5, weld the first bracket 2 to the side of the steel column 7. The steel column 7 and the first corbel 2 are subjected to concentrated stress. A certain number of stiffening plates 6 can be welded at the locations where the stress is concentrated. Then, the hoist 8 in the steel bar processing yard is used to hoist the first track beam 1 to the design position. With the assistance of maintenance personnel, the installation and fixation of the first track beam 1 is completed. After that, the hoist 8 is used again to hoist the maintenance platform 3 to the design position for temporary fixation. The maintenance platform 3 is then used to install the second traction base 312 in the gantry crane 5. Finally, the traction rod 4 is connected to the gantry crane 5 and the maintenance platform 3 respectively. When installing the maintenance platform 3, the installation steps can be as follows: first, complete the connection and fixation of the roller 3211 and the axle 3212. Then, assemble the axle 3212 and the roller 3211 to the mounting base 322 and fix the mounting base 322 to the station plate 33. Then, lay the platform panel 36 in the station plate 33. Finally, fix the guardrail 34 and the lifting guardrail 35 on the side of the station plate 33.
[0048] When using the gantry crane maintenance platform and system to inspect the hoist 8 and the running track of the gantry crane 5, the specific maintenance method may be:
[0049] First, maintenance personnel enter the maintenance platform 3. Then, the gantry crane 5 is intermittently started and stopped, causing it to move intermittently along the second track beam 71. Simultaneously, maintenance personnel perform maintenance work on the corresponding side of the hoist 8 and conductive slide rail 72 on the maintenance platform 3. After completing maintenance work on one side, the maintenance personnel leave the maintenance platform 3 and use the hoist 8 to lift it to the first track beam 1 on the other side. The traction rod 4 is then installed. After completing maintenance work on the other side, the traction rod 4 is disassembled, and the maintenance personnel leave the maintenance platform. The maintenance platform 3 is then lowered to the ground or temporarily fixed to the first track beam 1, awaiting the next maintenance operation. Maintenance personnel can enter the maintenance platform 3 either through a ladder structure installed between the steel columns 7 or by using an external ladder. Intermittent start-stop gantry crane 5 means that by intermittently starting and stopping the operation of gantry crane 5, gantry crane 5 can move intermittently in the second track beam 71 and can stop at the corresponding position of the second track beam 71, which facilitates maintenance personnel to carry out maintenance operations. In other words, the maintenance process of maintenance personnel is actually carried out section by section.
[0050] In the description of this utility model, it should be noted that the terms "upper," "lower," etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this utility model. Unless otherwise expressly specified and limited, the terms "installed," "connected," and "linked" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal connection of two components. For those skilled in the art, the specific meaning of the above terms in this utility model can be understood according to the specific circumstances.
[0051] It should be noted that in this invention, relational terms such as "first" and "second" are used merely to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus. Without further limitations, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes said element.
[0052] The above description is merely a specific embodiment of the present invention, enabling those skilled in the art to understand or implement the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention is not to be limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features claimed herein.
Claims
1. A gantry crane maintenance platform, characterized in that, It includes: The first track beam (1) is provided with a plurality of first brackets (2). The plurality of first brackets (2) are spaced apart along the extension direction of the first track beam (1) and are used to fix to a plurality of steel columns (7). The plurality of first brackets (2) are supported on the first track beam (1). The maintenance platform (3) includes a platform (31), and a sliding component (32) is provided at the bottom of the platform (31). The sliding component (32) is slidably installed on the first track beam (1). And at least one traction rod (4), one end of the at least one traction rod (4) is detachably connected to the platform (31), and the other end of the traction rod (4) is detachably connected to the gantry crane (5).
2. The gantry crane maintenance platform as described in claim 1, characterized in that: Two traction rods (4) are provided, and the two traction rods (4) are respectively set on opposite sides of the gantry crane (5); Each of the traction rods (4) has a connecting part (41) at both ends. One of the connecting parts (41) of each traction rod (4) is hinged to the first traction base (311) of the platform (31), and the other connecting part (41) is hinged to the second traction base (312) fixed on one side of the gantry crane (5).
3. The gantry crane maintenance platform as described in claim 2, characterized in that: The traction rod (4) also includes a connecting pipe (42) and two adjusting rods (43). The two adjusting rods (43) are coaxially inserted at both ends of the connecting pipe (42), and the adjusting rods (43) are threadedly engaged with the connecting pipe (42). The connecting part (41) includes a connecting ear plate (411), which is fixed to the adjusting rod (43).
4. The gantry crane maintenance platform as described in claim 1, characterized in that, The first track beam (1) has a first track. The sliding assembly (32) includes two sets of moving parts (321) spaced apart at the bottom of the platform (31) along the extension direction of the first track beam (1). Each set of moving parts (321) includes two rollers (3211) and an axle (3212) connecting the two rollers (3211). The axle (3212) is connected to the platform (31). The axis of the rollers (3211) is perpendicular to the first track, and the rollers (3211) are adapted to roll on the first track.
5. The gantry crane maintenance platform as described in claim 4, characterized in that: The bottom of the platform (31) is provided with at least two mounting seats (322) spaced apart. The axle (3212) passes through the two mounting seats (322). The bottom of the mounting seat (322) is provided with a limiting groove. A portion of the roller (3211) is located in the limiting groove. The first track beam (1) is provided with at least two limiting plates (12), and the two limiting plates (12) are adapted to abut against the opposite sides of the two mounting seats (322).
6. The gantry crane maintenance platform as described in claim 1, characterized in that, The platform (31) includes: The station plate (33) and the first track beam (1) are disposed on opposite sides of the sliding assembly (32); Fixed guardrail (34), the fixed guardrail (34) includes multiple crisscrossing fixed bars; The lifting guardrail (35) is used to be installed on the side of the station plate (33) near the steel column (7), and the fixed guardrail (34) and the lifting guardrail (35) are installed on opposite sides of the station plate (33).
7. The gantry crane maintenance platform as described in claim 6, characterized in that, The lifting guardrail (35) includes: The lifting railing and a sensing device installed on one side of the lifting railing, the sensing device being installed on the side of the lifting railing away from the station plate (33).
8. The gantry crane maintenance platform as described in claim 1, characterized in that, The gantry crane maintenance platform also includes: At least one stiffening plate (6) is provided at the first corbel (2) for fixing to the steel column (7).
9. A gantry crane maintenance system, characterized in that, It includes: At least two rows of steel columns (7), each row of steel columns (7) is provided with a second track beam (71); A truss crane (5) spans at least two rows of steel columns (7) and is slidably installed on the second track beam (71). The first track beam (1) is located below the second track beam (71). The first track beam (1) is provided with a plurality of first brackets (2). The plurality of first brackets (2) are spaced apart along the extension direction of the first track beam (1). Each first bracket (2) is fixed to a single steel column (7) of each row of steel columns (7), and the plurality of first brackets (2) are supported on the first track beam (1). The maintenance platform (3) includes a platform (31), and a sliding component (32) is provided at the bottom of the platform (31). The sliding component (32) is slidably installed on the first track beam (1). And at least one traction rod (4), one end of the at least one traction rod (4) is detachably connected to the platform (31), and the other end of the traction rod (4) is detachably connected to the gantry crane (5).
10. The gantry crane maintenance system as described in claim 9, characterized in that: The surface of the second track beam (71) is provided with conductive slide rails (72), and the end of the gantry crane (5) near the second track beam (71) is provided with an electric slider (52) that cooperates with the conductive slide rails (72).