A work trolley for installing pressure steel pipes in inclined shafts

CN224704351UActive Publication Date: 2026-09-01GEZHOUBA GRP NO 2 ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202521828203.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-08-27
Publication Date
2026-09-01
Estimated Expiration
2035-08-27

AI Technical Summary

Technical Problem

[0002]水电站输水系统压力管道斜井段压力钢管安装中,常见的方法是:斜井直管段压力钢管安装时,采用1台固定框架式施工台车进行作业,每安装一节钢管进行一次台车移位,台车牵引到位后,锁定在钢管内壁的吊耳上(在每节钢管管口处焊接有安装吊耳,吊耳在钢管运输前严格按照一类焊缝焊接,并经探伤检查合格后方可使用,在钢管安装焊接完成后将其割除),每节钢管内均需焊接2个吊耳用于挂装施工台车,且必须等到一节钢管安装与焊接、吊耳割除、打磨与防腐完成后才能进行下一节钢管的安装,施工难度和安全风险较大,施工效率低;上、下弯段施工时由于受管节弧度影响,斜井直管段施工台车无法利用,必须搭设施工排架,每安装一节压力钢管管节就要搭设施工排架并铺设简易平台,施工排架需随管节的上升逐节搭设,待弯段钢管安装完成后再逐层拆除,这样既费时又费力,导致斜井压力钢管安装作业的工期被延长,且施工排架的搭拆均存在一定的安全风险

Benefits of technology

[0016]本实用新型通过角度可调的作业台车,无需在钢管内壁焊接和拆除吊耳,也无需搭设施工排架,省去了大量辅助工序,且台车可覆盖斜井下弯段、直管段、上弯段全程,无需更换设备,大幅提升了施工连贯性和整体效率,缩短了工期;本实用新型通过液压油缸调节设备平台角度,确保其始终水平,再配合钢质链环、卸扣及手拉葫芦形成的双重防坠落机构,保障了施工人员作业安全,且台车移位通过卷扬机与牵引吊耳配合实现,过程稳定可控,减少了安全事故发生的可能性;本实用新型通过液压油缸的连续角度调节,可灵活适配斜井不同段落的弧度和坡度变化,实现全段一体化施工,适应性更强。附图说明

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224704351U_ABST
    Figure CN224704351U_ABST
Patent Text Reader

Abstract

This utility model relates to the field of inclined shaft construction technology and discloses a work trolley for installing pressure steel pipes in inclined shafts. The work trolley includes a trolley body and an operating platform located in the pressure steel pipe. The trolley body consists of a traveling beam and an equipment platform. One end of the equipment platform is rotatably connected to the traveling beam via a hinge device, and the other end is movably connected via an adjustable support connection mechanism. An independent hydraulic pump station on the equipment platform forms a closed-loop drive system with the mechanism, which can continuously adjust the angle of the equipment platform to keep it horizontal in the lower bend section, straight pipe section and upper bend section of the inclined shaft. The operating platform is leveled synchronously with it. It can also adapt to the curvature of the bend section by adjusting the angle, eliminating the need to erect scaffolding and improving construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of inclined shaft construction technology, specifically to a work trolley for installing pressure steel pipes in inclined shafts. Background Technology

[0002] In the installation of pressure steel pipes in the inclined shaft section of the pressure pipeline of a hydropower station's water conveyance system, a common method is as follows: When installing the pressure steel pipe in the straight section of the inclined shaft, a fixed frame construction trolley is used. The trolley is moved once after each section of steel pipe is installed. After the trolley is pulled into position, it is locked onto the lifting lugs on the inner wall of the steel pipe (lifting lugs are welded at the pipe opening of each section; these lugs are welded according to Class I weld standards before transporting the steel pipe and pass flaw detection before use; they are removed after the steel pipe installation and welding are completed). Two lifting lugs are welded inside each section of steel pipe for mounting the construction trolley, and this process must continue until one section of steel pipe is installed. The installation of the next section of steel pipe can only proceed after welding, removal of lifting lugs, grinding, and anti-corrosion treatment are completed. This process presents significant construction difficulties, safety risks, and low efficiency. During the construction of the upper and lower bends, the curvature of the pipe sections prevents the use of the straight pipe section construction trolley in the inclined shaft. A construction scaffold must be erected, with a simple platform laid for each pressure steel pipe section installed. The scaffold must be erected section by section as the pipe rises, and then dismantled layer by layer after the bend is installed. This process is both time-consuming and labor-intensive, extending the construction period of the inclined shaft pressure steel pipe installation. Furthermore, the erection and dismantling of the construction scaffold pose certain safety risks. Especially in the upper bend, due to its location, it is impossible to erect the scaffold from the lower bend all the way to the top. Therefore, steel brackets must be welded to the inner wall of the starting pipe section of the upper bend before the scaffold is erected layer by layer. When the brackets are removed, the cut areas on the inner wall of the steel pipe also need to be ground and repainted. Utility Model Content

[0003] The purpose of this utility model is to provide a work trolley for installing pressure steel pipes in inclined shafts. The work trolley includes a traveling beam and an equipment platform. One end of the equipment platform is connected to the traveling beam through a hinge device, and the other end is connected to the traveling beam through an adjustable support connection mechanism. The angle can be adjusted by the extension and retraction of the adjustable support connection mechanism to adapt to the curvature of the curved section. There is no need to erect a scaffold, thus avoiding the safety risks and construction time waste of scaffold erection and dismantling.

[0004] This utility model is achieved through the following technical solution: A work trolley for installing pressure steel pipes in inclined shafts includes a trolley body and an operating platform located in the pressure steel pipe. The trolley body includes a traveling beam and an equipment platform. One end of the equipment platform is rotatably connected to one end of the traveling beam via a hinge device, and the other end of the equipment platform is movably connected to the other end of the traveling beam via an adjustable support connection mechanism. The equipment platform is equipped with an independent hydraulic pump station, which forms a closed-loop drive system with the adjustable support connection mechanism. The angle of the equipment platform relative to the traveling beam is continuously adjusted by the telescopic drive of the closed-loop drive system, and the equipment platform can maintain a horizontal working state during construction of the inclined shaft lower bend section, straight pipe section and upper bend section. The operating platform is fixed to the edge of the equipment platform and is leveled synchronously with it.

[0005] In this solution, the hinge device and adjustable support connection mechanism work together to form a closed-loop drive system with an independent hydraulic pump station, enabling continuous adjustment of the angle of the equipment platform relative to the traveling beam. This ensures that the platform can maintain a horizontal working state during construction in the lower bend, straight pipe, and upper bend sections of the inclined shaft. At the same time, the operating platform is leveled synchronously with the equipment platform, allowing for the installation of pressure steel pipes throughout the inclined shaft without frequent equipment changes, the need to erect construction scaffolds, or the frequent welding of lifting lugs on the inner wall of the steel pipe. This solves the problems of low efficiency and high safety risks in traditional construction.

[0006] As a further embodiment of the work trolley, the adjustable support connection mechanism includes a first fixed hinge support, a hydraulic cylinder, and a second fixed hinge support. One end of the hydraulic cylinder is hinged to the equipment platform through the first fixed hinge support, and the other end of the hydraulic cylinder is hinged to the traveling beam through the second fixed hinge support. This provides a stable structural foundation and a flexible driving carrier for adjusting the angle of the equipment platform relative to the traveling beam. Combined with the closed-loop drive system formed by the independent hydraulic pump station, it can accurately achieve continuous angle adjustment of the equipment platform during construction in the lower curved section, straight pipe section, and upper curved section of the inclined shaft, while maintaining a horizontal working state.

[0007] As a further embodiment of the work trolley, the traveling beams are arranged in pairs, and each traveling beam has multiple traveling wheels at its bottom. The radial direction of the traveling wheels and the radial direction of the inner wall of the pressure steel pipe are in a straight line, which ensures the stability and fit of the trolley when it travels inside the pressure steel pipe, so that the wheels are always in contact with the inner wall of the steel pipe perpendicularly, and can adapt to the direction of the steel pipe in different sections of the inclined shaft.

[0008] As a further embodiment of the work trolley, the two traveling beams are arranged in parallel and are fixed by welding with transverse connecting channel steel. Each traveling beam has traveling wheels at both ends of its bottom. The traveling wheels at the front end are nylon casters, and the traveling wheels at the rear end are fixed wheels of the same specification. Through the combination of the front casters and the rear fixed wheels, the trolley can flexibly adapt to the turning requirements of the inclined shaft curves and maintain the stability of straight-line travel in the straight pipe sections. This provides a reliable foundation for the smooth movement of the trolley in the lower curves, straight pipe sections, and upper curves of the inclined shaft.

[0009] As a further option for the work trolley, the operating platform is divided into multiple stepped sections along the angle of the inclined shaft, which facilitates welding operations at different locations during the installation of pressure steel pipes. At the same time, the multi-step stepped structure can meet the needs of multiple construction workers to work together, thus improving construction efficiency.

[0010] As a further solution for the work trolley, the operating platform is divided into three layers: upper, middle, and lower. The maximum height of the upper platform from the equipment platform surface is 1350mm, ensuring that construction personnel can work efficiently within a safe range.

[0011] As a further solution for the work platform, to further improve the practicality and safety of the platform, the upper platform is fully covered with anti-slip metal planks, while the middle and lower platforms are only covered with planks of the same specification on both sides near the inner wall of the steel pipe, and the planks are connected by bolts.

[0012] As a further solution for the work trolley, two traction lugs are welded to the front sides of the equipment platform. A slow-speed winch is used to drag the work trolley through the traction lugs, allowing it to move along the inner wall of the pressure steel pipe. This ensures that the trolley can accurately reach the work position as the installation progresses. With the guidance of the traveling wheels, the relocation process is stable and controllable, avoiding the inefficiency caused by the inconvenience of equipment movement in traditional construction. At the same time, the use of the slow-speed winch ensures the safety of the relocation process.

[0013] As a further solution for the work trolley, the front end of the equipment platform is also equipped with two fixed lifting lugs. The fixed lifting lugs are connected to the pressure steel pipe opening through steel chain links and shackles, and are combined with multiple hand-operated hoists to cross-lock and form a double anti-fall mechanism, ensuring that the trolley will not slip or fall during equipment platform angle adjustment and construction personnel operation. It is especially suitable for the safety requirements of inclined shaft environment, avoiding the safety risks caused by insecure fixing in traditional construction. At the same time, there is no need to weld temporary lifting lugs on the inner wall of the steel pipe, reducing damage to the steel pipe body and subsequent processing procedures.

[0014] As a further solution for the work platform, to further improve the practicality and safety of the platform, a temporary safety guardrail is provided at the part where the gap between the equipment platform and the inner wall of the steel pipe exceeds 300mm. The height of the safety guardrail is not less than 1200mm, and a steel kick plate is provided at its bottom.

[0015] Compared with the prior art, this utility model has the following advantages and beneficial effects:

[0016] This invention utilizes an angle-adjustable work trolley, eliminating the need for welding and dismantling lifting lugs on the inner wall of the steel pipe, as well as the erection of construction scaffolding, thus saving numerous auxiliary procedures. The trolley can cover the entire inclined shaft, including the lower bend, straight section, and upper bend, without requiring equipment replacement, significantly improving construction continuity and overall efficiency, and shortening the construction period. The invention uses hydraulic cylinders to adjust the platform angle, ensuring it remains level. Combined with a double anti-fall mechanism formed by steel chain links, shackles, and hand-operated hoists, this guarantees the safety of construction personnel. Trolley movement is achieved through a winch and traction lugs, ensuring a stable and controllable process and reducing the possibility of accidents. Furthermore, the continuous angle adjustment of the hydraulic cylinders allows for flexible adaptation to changes in the curvature and slope of different sections of the inclined shaft, enabling integrated construction throughout the entire section and providing greater adaptability. (See attached drawings.) The accompanying drawings, which are included to provide a further understanding of the embodiments of the present invention and form part of this application, do not constitute a limitation thereof. In the drawings: Figure 1 This is a schematic diagram of the longitudinal section structure of the construction trolley of this utility model; Figure 2 This is a schematic diagram of the elevation structure of the construction trolley of this utility model; Figure 3 This is a top view of the construction trolley equipment platform structure of this utility model; Figure 4 This is a schematic diagram of the locking mechanism of the construction trolley during actual construction. Figure 5 This is a schematic diagram of the longitudinal section layout of the construction trolley during operation.

[0017] The attached diagram shows the markings and corresponding component names: 1-Hinge device, 2-Hydraulic pump station, 3-Equipment platform, 101-Trolley body, 102-Operating platform, 4-First fixed hinge support, 5-Hydraulic cylinder, 6-Second fixed hinge support, 7-Traveling beam, 8-Traveling wheel, 9-Traction lug, 10-Fixed lug, 11-Steel chain link, 12-Hook, 13-Hand chain hoist, 14-Power distribution control cabinet. Detailed Implementation

[0018] To make the objectives, technical solutions, and advantages of this utility model clearer, the present utility model will be further described in detail below with reference to the embodiments and accompanying drawings. The illustrative embodiments and descriptions of this utility model are only used to explain this utility model and are not intended to limit this utility model.

[0019] Example 1 This embodiment 1 provides a work trolley for installing pressure steel pipes in inclined shafts, such as... Figure 1As shown, it includes a trolley body 101 and an operating platform 102 located in a pressure steel pipe; like Figures 1-4 As shown, the trolley body 101 includes two parallel traveling beams 7 and an equipment platform 3; Among them, such as Figures 1-4 As shown, the traveling beam 7 is welded and fixed by transverse connecting channel steel to form a stable frame structure. Two traveling wheels 8 are installed at each end of the bottom of the traveling beam 7, for a total of four. The two front traveling wheels 8 are 12×2.5-inch heavy-duty iron-core nylon universal wheels (60mm wide, 300mm in diameter), which can turn 360°. The two rear traveling wheels 8 are fixed wheels of the same specification, with a rated load of 3t per wheel. The radial direction of all traveling wheels 8 is consistent with the radial direction of the inner wall of the pressure steel pipe, ensuring that when the trolley travels along the axis of the steel pipe, the wheels are always in contact with the inner wall of the steel pipe perpendicularly, avoiding slippage or deviation, and providing stable walking support for the trolley.

[0020] At the same time, such as Figures 1-4 As shown, the bottom of the above-mentioned equipment platform 3 is reinforced by crisscrossing I-beams, with a rated load capacity of 8t. One end of the equipment platform 3 is hinged to the front end of the traveling beam 7 via a hinge device 1, forming a rotation fulcrum. The other end of the equipment platform 3 is connected to the rear end of the traveling beam 7 via an adjustable support connection mechanism to achieve angle adjustment.

[0021] Specifically, such as Figures 1-2 As shown, the adjustable support connection mechanism includes a first fixed hinge support 4, a hydraulic cylinder 5, and a second fixed hinge support 6. The first fixed hinge support 4 is welded to the bottom of the equipment platform 3 at the end away from the hinge device 1. The second fixed hinge support 6 is welded to the top of the rear end of the traveling beam 7. The two ends of the hydraulic cylinder 5 are respectively hinged to the two fixed hinge supports through pins to form a telescopic support structure. Furthermore, the equipment platform 3 is equipped with an independent hydraulic pump station 2 and a power distribution control cabinet 14. The power distribution control cabinet 14 is installed at the rear end of the equipment platform 3, and the hydraulic pump station 2 is fixed in the middle of the equipment platform 3. Hydraulic pump station 2 is connected to hydraulic cylinder 5 via high-pressure oil pipe to form a closed-loop drive system. Hydraulic pump station 2 can control the extension and retraction of hydraulic cylinder 5 through solenoid valve to change the angle between equipment platform 3 and traveling beam 7, so that equipment platform 3 can maintain a horizontal state in different slope sections of the inclined shaft, ensuring construction stability. In actual application, the power distribution control cabinet 14 also has built-in circuit breaker, contactor and wireless receiving module to realize remote adjustment of the angle of equipment platform 3. Construction personnel can operate the remote control from the safety passage on the outer wall of the steel pipe to avoid danger when entering the inclined platform.

[0022] like Figure 1As shown, the operating platform 102 has a trapezoidal step structure, fixed to the edge of the equipment platform 3, and is leveled synchronously with the equipment platform 3. Specifically, it consists of three layers: upper, middle, and lower. The upper platform is 1350mm above the equipment platform surface (to meet the maximum operating height requirements of construction personnel), and the upper platform is fully covered with 300mm×3000mm anti-slip metal planks. The middle and lower platforms are only covered with two planks of the same specification on each side near the inner wall of the steel pipe. The planks are connected by M16 bolts with an overlap length of ≥100mm. The open surfaces of the upper and middle platforms are equipped with safety railings with a height of 1200mm, and the bottom of the railings is equipped with 200mm high steel kick plates to prevent tools or debris from falling.

[0023] To ensure that the trolley does not slip or fall in the inclined environment of the shaft, this embodiment also includes a displacement and fixing system, specifically, such as... Figure 1 and Figure 4 As shown, two traction lugs 9 are symmetrically welded on both sides of the front end of the equipment platform 3. They are connected to a slow-speed winch via wire ropes and used for moving the trolley inside the steel pipe. During the traction process, the angle of the equipment platform 3 can be pre-adjusted by the hydraulic cylinder 5 to make the trolley adapt to the direction of the steel pipe. At the same time, two fixed lugs 10 are welded to the middle of the front end of the equipment platform 3. After the trolley is moved to the working position, it is connected and fixed to the pressure steel pipe opening via steel chain links 11 and 10t shackles. Two 5t hand chain hoists 13 are also set up. One end is hooked to the fixed lugs 10, and the other end is cross-hooked to the steel chain links 11 to form double anti-fall protection to ensure that the trolley does not slip or fall in the inclined environment of the inclined shaft.

[0024] In summary, the work trolley in this embodiment can achieve efficient installation of the entire pressure steel pipe in the inclined shaft through the above-mentioned structure, without the need to erect a construction scaffold or weld temporary lifting lugs, effectively solving the problems of cumbersome procedures, high safety risks, and easy damage to the steel pipe body in traditional construction.

[0025] Example 2 To avoid the inefficiencies and safety risks associated with equipment switching, scaffolding erection and dismantling, and welding and dismantling of lifting lugs in traditional construction, this embodiment 2 provides a construction method for installing pressure steel pipes in inclined shafts, based on a work trolley used in embodiment 1. The steps are as follows: Step 1: Assemble the steel pipe sections of the inclined shaft bend section 1-5 using traditional methods; Step 2: Before installing the sixth section of the lower bend pipe, transport the trolley from the lower flat tunnel to the steel pipe inside the lower bend section of the steel pipe. As the steel pipe installation progresses, use a winch to pull the construction trolley to the steel pipe installation position. Step 3: After the trolley is pulled into place, adjust the angle between the equipment platform 3 and the traveling beam 7, observe whether the equipment platform is level, and make appropriate adjustments. Specifically, when adjusting the level of the equipment platform 3, the construction personnel stand on the pedestrian safety passage near the pipe opening of the installed steel pipe and start the hydraulic pump station 2 by wirelessly operating the power distribution and control cabinet 14 through the remote control. The extension and retraction of the hydraulic cylinder 5 is used to adjust the angle between the equipment platform 3 and the traveling beam 7, so as to achieve the purpose of leveling the equipment platform 3. During the adjustment, the equipment platform 3 needs to be adjusted 2 to 3 times in the upper and lower curved sections of the inclined shaft steel pipe, and only one angle adjustment is needed in the straight section of the inclined shaft. Step 4: After the trolley equipment platform 3 is leveled, the construction personnel enter the equipment platform 3 through the ladder and lock the trolley at the pipe opening using steel chain links 11, shackles and hooks 12. In addition, two hand chain hoists 13 are set up to be locked together with the steel chain links 11 as a fall protection for the trolley to prevent it from falling. A ladder is set up inside the trolley as a passage to go up and down the platform. It is strictly forbidden to start other work without locking the trolley. Step 5: After locking and leveling the construction trolley, the construction personnel can weld the weld between the two steel pipes on the operating platform 102. Step 6: After completing the installation work between the two steel pipe sections, use a winch to continue lowering the steel pipe section, lift it up, and lock the construction trolley at the top of the steel pipe opening. Repeat the above construction steps. Step 7: Complete the installation of all pressure steel pipe segments from the lower bend section and straight pipe section to the upper bend section of the inclined shaft.

[0026] In steps 2) and 4), before the winch lowers the inclined section of the steel pipe, two additional steel wire ropes are prepared. The upper ends of the steel wire ropes are hung on the winch hook, and the lower ends extend into the steel pipe. When the steel pipe section is lowered to a distance of approximately 300mm from the end of the installed steel pipe, the lower ends of the two steel wire ropes pre-hung on the winch hook are respectively hung on two additional traction lugs 9 on the construction trolley. The winch lifting button is activated, and after the two steel wire ropes are under tension, the operator stands on the equipment platform 3 and removes the locking hook 12 hanging on the end of the installed steel pipe. The winch lowers the hook, placing the steel pipe to be installed onto the installed pipe section. After removing the wire rope from the winch attached to the steel pipe to be installed, the winch continues to lift the construction trolley. When the equipment platform 3 is about 1m away from the pipe opening of the steel pipe to be installed, the hook 12 of the steel chain link 11 on the construction trolley is attached to the pipe opening of the steel pipe to be installed. After the winch lifts the construction trolley and slowly lowers it to the installation position, two hand-operated hoists 13 are used to lock it together with the steel pipe chain link 11. Then, the two wire ropes that pull the construction trolley on the winch are removed.

[0027] Example 3 This embodiment, based on the aforementioned work trolley, details the installation and construction steps for a working condition with a 45° inclined shaft angle, a 6.8m inner diameter pressure steel pipe, and a 3m length per section, as follows: Step 1: Install 1-5 sections of the downward bend steel pipe using traditional hoisting technology. The steel pipe is hoisted to the entrance of the lower horizontal tunnel using a ground gantry crane. Two 25t winches pull the steel pipe down the inclined shaft track. When the front end of the steel pipe is 300mm away from the installed pipe section, the docking axis is finely adjusted using a hand-operated hoist 13 to ensure that the misalignment is ≤1mm and the gap is 2-3mm. The pipe is then temporarily fixed with rigid supports. The circumferential seams of sections 1-5 of the steel pipe are welded using manual electric arc welding. After layered welding, ultrasonic testing is performed to ensure that the weld quality meets the Class I weld standard, thus forming the initial working reference section.

[0028] Step 2: Transport the work trolley through the lower tunnel to the opening of the 5th steel pipe. Connect the wire rope of the slow winch to the trolley traction lug 9 through the guide wheel. Start the winch and slowly pull the trolley into the installed steel pipe. Pull the trolley to the installation position of the 6th lower bend pipe (1.5m away from the pipe opening to be installed), and stop pulling.

[0029] Step 3: The construction workers stand on the pedestrian safety passage on the outer wall of the 5th steel pipe section and start the power distribution control cabinet 14 with the remote control to put the hydraulic pump station 2 into working condition; operate the remote control to control the extension and retraction of the hydraulic cylinder 5 to adjust the angle between the equipment platform 3 and the traveling beam 7; since the sixth section is a downward-bending steel pipe section, it needs to be adjusted twice according to the curvature of the pipe section: the first adjustment is to make the front end of the platform slightly higher than the horizontal state, and after the steel pipe is connected, it is finely adjusted again to be completely horizontal. The extension and retraction of the hydraulic cylinder at this time is recorded as the reference value for the adjustment of the same type of bending section.

[0030] Step 4: After leveling the trolley, connect the fixed lifting lug 10 at the front end of the equipment platform 3 to the pre-set lifting point at the pipe opening of the sixth section of steel pipe to be installed through two steel chain links 11. The two ends of the chain links are locked with 10t shackles to ensure that the connection is not loose. Two 5t hand-operated hoists 13 are cross-set between the steel chain links 11 and the equipment platform 3. Slowly tighten the hoists to make the chain bear the force, forming a double anti-fall protection. At this time, check the overall stability of the trolley to ensure that there is no shaking. The construction personnel enter the operating platform through the built-in ladder of the trolley, check the firmness of the metal plank of the upper platform and the connection quality of the safety guardrail. After confirming that everything is correct, prepare for welding operation.

[0031] Step 5: The sixth steel pipe is lowered along the track by a ground winch. When the front end of the steel pipe is 300mm away from the opening of the fifth steel pipe, the lowering is stopped. The lower ends of the two traction wire ropes are hung on the traction lugs 9 of the trolley, and the upper ends are connected to the winch hook. The winch lifting button is activated to load the wire ropes. The construction personnel remove the temporary support at the opening of the fifth steel pipe on the operating platform and slowly lower the hook to make the sixth steel pipe accurately connect with the fifth steel pipe. The axis deviation is checked by the scale on the edge of the trolley operating platform to ensure that it meets the specifications. After the connection is completed, a rigid clamp is used for temporary fixation. The construction personnel perform circumferential welding on the upper, middle and lower layers of the operating platform. Except for the upper platform which is fully covered with metal planks, the other platforms are only covered with metal planks at both ends near the inner wall of the steel pipe. The specifications of the metal planks are 300mm (width) × 3000mm (length). Safety railings are set on all open surfaces of the upper and middle platforms, and kick guards are installed at the bottom of the railings with a height of 200mm.

[0032] Step 6: After the sixth section of steel pipe is welded and passes the flaw detection, loosen the shackles of the hand chain hoist 13 and the steel chain link 11, start the winch to lift the trolley, and stop lifting when the equipment platform is 1m away from the opening of the sixth section of steel pipe; re-hook the steel chain link 11 onto the opening of the sixth section of steel pipe, lower the trolley to the installation position, lock the shackles, and once again use the hand chain hoist 13 to form a fall protection, and remove the traction wire rope.

[0033] Repeat steps 3-5 to install the subsequent steel pipes. For each section of the lower bend, the angle of the equipment platform needs to be adjusted 2-3 times. For each section of the straight pipe, it needs to be adjusted once. The adjustment method for the upper bend is the same as that for the lower bend. When the pipe is installed to the top of the inclined shaft, it is connected to the pre-embedded parts at the wellhead through the fixed lifting lug 10 at the front end of the trolley to ensure the stability of the trolley when welding the last section of the steel pipe.

[0034] Step 7: After the entire steel pipe section is installed, conduct a final visual inspection and water pressure test on all circumferential joints.

[0035] This embodiment achieves efficient installation of the entire steel pipe section of the inclined shaft through angle adjustment, safety locking, and cyclic operation process of the work trolley. Compared with the traditional process, it reduces the construction period and avoids damage caused by welding of the lifting lugs on the inner wall of the steel pipe.

[0036] The specific embodiments described above further illustrate the purpose, technical solution, and beneficial effects of this utility model. It should be understood that the above description is only a specific embodiment of this utility model and is not intended to limit the scope of protection of this utility model. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this utility model should be included within the scope of protection of this utility model.

Claims

1. A service car for installation of a pressure steel pipe in an inclined shaft, characterized in that, The device includes a trolley body (101) and an operating platform (102) located in a pressure steel pipe. The trolley body (101) includes a traveling beam (7) and an equipment platform (3). One end of the equipment platform (3) is rotatably connected to one end of the traveling beam (7) through a hinge device (1). The other end of the equipment platform (3) is movably connected to the other end of the traveling beam (7) through an adjustable support connection mechanism. The equipment platform (3) is equipped with an independent hydraulic pump station (2). The hydraulic pump station (2) and the adjustable support connection mechanism form a closed-loop drive system. The angle of the equipment platform (3) relative to the traveling beam (7) is continuously adjusted by the telescopic drive of the closed-loop drive system. The equipment platform (3) can maintain a horizontal working state during the construction of the inclined shaft lower bend section, straight pipe section and upper bend section. The operating platform (102) is fixed to the edge of the equipment platform (3) and is leveled synchronously with it.

2. The work trolley for installing pressure steel pipes in inclined shafts according to claim 1, characterized in that, The adjustable support connection mechanism includes a first fixed hinge support (4), a hydraulic cylinder (5) and a second fixed hinge support (6). One end of the hydraulic cylinder (5) is hinged to the equipment platform (3) through the first fixed hinge support (4), and the other end of the hydraulic cylinder (5) is hinged to the traveling beam (7) through the second fixed hinge support (6).

3. The work trolley for installing pressure steel pipes in inclined shafts according to claim 1, characterized in that, The traveling beams (7) are arranged in pairs, and each traveling beam (7) has multiple traveling wheels (8) at its bottom. The radial direction of the traveling wheels (8) and the radial direction of the inner wall of the pressure steel pipe are on a straight line.

4. The work trolley for installing pressure steel pipes in inclined shafts according to claim 3, characterized in that, The two traveling beams (7) are arranged in parallel and are fixed by welding through transverse connecting channel steel. Each traveling beam has a traveling wheel (8) at both ends of its bottom. The traveling wheel (8) at the front end is a nylon universal wheel, and the traveling wheel (8) at the rear end is a fixed wheel of the same specification.

5. A work trolley for installing pressure steel pipes in inclined shafts according to claim 1, characterized in that, The operating platform (102) is divided into multiple stepped sections along the angle of the inclined shaft.

6. A work trolley for installing pressure steel pipes in inclined shafts according to claim 5, characterized in that, The operating platform (102) is divided into three layers: upper, middle and lower. The maximum height of the upper platform from the surface of the equipment platform (3) is 1350mm.

7. A work trolley for installing pressure steel pipes in inclined shafts according to claim 5, characterized in that, The upper platform is fully covered with anti-slip metal planks, while the middle and lower platforms are only covered with planks of the same specification on both sides near the inner wall of the steel pipe, and the planks are connected by bolts.

8. A work trolley for installing pressure steel pipes in inclined shafts according to claim 1, characterized in that, Two traction lugs (9) are welded to the front sides of the equipment platform (3). The slow winch is dragged by the traction lugs (9) to move the construction trolley on the inner wall of the pressure steel pipe.

9. A work trolley for installing pressure steel pipes in inclined shafts according to claim 8, characterized in that, The front end of the equipment platform (3) is also provided with two fixed lifting lugs (10). The fixed lifting lugs (10) are connected to the pressure steel pipe opening through steel chain links (11) and shackles, and are locked together with multiple hand chain hoists (13) to form a double anti-fall mechanism.

10. A work trolley for installing pressure steel pipes in inclined shafts according to claim 1, characterized in that, Temporary safety railings are provided at the part where the gap between the equipment platform (3) and the inner wall of the steel pipe exceeds 300mm. The height of the safety railings is not less than 1200mm, and a steel kick plate is provided at the bottom.