A pressure relief inspection well installed at the end of a pressure drainage pipe

By installing pressure relief devices such as elbows, flanged short pipes, and blind flanges inside the inspection well, the high-pressure impact at the end of the pressure drainage pipe is alleviated, the water hammer effect problem of the inspection well is solved, and structural protection and safety stability are achieved.

CN224955218UActive Publication Date: 2026-11-10POWERCHINA HEBEI ELECTRIC POWER SURVEY & DESIGN INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522230269.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-10-22
Publication Date
2026-11-10
Estimated Expiration
2035-10-22

AI Technical Summary

Technical Problem

In the existing technology, the connection between the pressure drainage pipe and the inspection well is simple, which leads to an instantaneous high-pressure impact inside the inspection well, causing water hammer effect, damaging the structure and increasing safety risks. There is a lack of suitable pressure relief structures.

Method used

A pressure relief device, including an elbow, a flange short pipe, and a blind flange, is installed inside the inspection well. The elbow changes the direction of water flow and slowly releases high-pressure water between the flange short pipe and the blind flange. Stability is ensured by the guide slope and the mounting bracket.

Benefits of technology

It effectively buffers the impact of high-pressure water, avoids water hammer effect, protects inspection wells and pipeline structures, reduces maintenance costs, and is suitable for various specifications of pressure drainage pipelines.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224955218U_ABST
    Figure CN224955218U_ABST
Patent Text Reader

Abstract

This utility model discloses a pressure relief inspection well installed at the end of a pressure drainage pipe, belonging to the field of municipal engineering technology. It includes an inspection well body and a pressure relief device, which is fixedly installed inside the inspection well body near the interface of the pressure drainage pipe. The pressure relief device includes an elbow, a flanged short pipe, and a blind flange located above the flanged short pipe. One end of the elbow is sealed to the end of the pressure drainage pipe, and the other end is fixedly connected to one end of the flanged short pipe. The other end of the flanged short pipe is detachably connected to the blind flange via bolts and nuts. The diameter of the inspection well body is selected based on the overall dimensions of the pressure relief device, and the length of the pressure relief device in the well diameter direction does not exceed 1 / 2 × (inspection well body diameter - gravity flow pipe diameter), while the diameter of the inspection well body is not less than 1.5m. This utility model can avoid the water hammer effect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of municipal engineering technology, and in particular to a pressure relief inspection well installed at the end of a pressure drainage pipe. Background Technology

[0002] In municipal engineering and various industrial and civil building water supply systems or process piping systems, pressurized drainage pipes are an important component, mainly used to transport pressurized water to designated locations. To ensure that the water in the pipes can be drained in a timely manner during system maintenance, repair, or abnormal operating conditions, the end of the pressurized drainage pipe is usually connected to a rainwater inspection well or sewage inspection well, so that the water in the pipe flows into the subsequent gravity flow drainage network through the inspection well.

[0003] However, current technologies for connecting pressure drainage pipes to manholes are relatively simple, mostly involving directly inserting the pressure drainage pipe into the manhole without any specific pressure relief or regulation devices. Because the pressure drainage pipe maintains continuous operating pressure, when high-pressure water is directly discharged into the manhole, it creates an instantaneous high-pressure impact, triggering a strong water hammer effect. This water hammer effect not only violently erodes and impacts the manhole walls, bottom, and cover, but also affects the stability of upstream and downstream connecting pipes, leading to problems such as cracks in the manhole body, loose pipe joints, and seal failure. In severe cases, it can cause water leaks, manhole covers being washed away, and other safety accidents, posing a threat to nearby pedestrians and facilities. Simultaneously, long-term high-pressure erosion continuously degrades the structural strength of the manhole and pipes, significantly shortening their service life and increasing subsequent maintenance costs and network operation risks.

[0004] Currently, while some technologies exist in the industry to protect against water hammer in pipelines, most involve installing pressure reducing valves and water hammer absorbers in the middle sections of the pipeline. These devices are complex in structure, expensive, and require separate installation space and regular professional maintenance, making them unsuitable for scenarios where manholes connect to the ends of pipelines. Furthermore, pressure relief structures specifically designed for manholes are scarce. Improvements to existing manholes primarily focus on manhole materials and seepage prevention performance, failing to address the pressure relief issue at the ends of pressurized drainage pipelines.

[0005] Therefore, there is an urgent need for a manhole structure that is simple in structure, easy to install, cost-controllable, and has a reliable pressure relief effect, in order to fill the gap in existing technology and ensure the safe and stable operation of the connection between the pressure drainage network and the manhole. Utility Model Content

[0006] To address the lack of pressure relief structures specifically designed for manholes in existing technologies, this invention provides a pressure relief manhole installed at the end of a pressure drainage pipeline. This manhole effectively buffers and relieves pressure, and is suitable for connecting pressure drainage pipelines and manholes in various water conveyance systems and process piping systems. It can be widely applied in urban municipal drainage, industrial park drainage, and residential community drainage projects.

[0007] The technical solution adopted by this utility model for a pressure relief inspection well installed at the end of a pressure drainage pipeline is as follows: A pressure relief inspection well installed at the end of a pressure drainage pipe includes an inspection well body and a pressure relief device. The pressure relief device is fixedly installed inside the inspection well body on the side near the interface of the pressure drainage pipe. The pressure relief device includes an elbow, a flange short pipe, and a blind flange located above the flange short pipe. One end of the elbow is sealed to the end of the pressure drainage pipe, and the other end is fixedly connected to one end of the flange short pipe. The other end of the flange short pipe is detachably connected to the blind flange by bolts and nuts. The diameter of the manhole body is selected based on the overall size of the pressure relief device, and the length of the pressure relief device in the diameter direction does not exceed 1 / 2 × (diameter of manhole body - diameter of gravity flow pipe), while the diameter of the manhole body is not less than 1.5m.

[0008] A further improvement of this utility model is that the distance L between the blind flange and the flange short pipe is D+80~120mm, where D is the nominal diameter of the pressure drainage pipe.

[0009] A further improvement of this utility model is that the elbow is a 90° elbow, and the axis of the elbow is coaxial with the axis of the pressure drainage pipe.

[0010] A further improvement of this utility model is that: an installation bracket is fixedly provided on the inner side of the manhole body corresponding to the position of the flange short pipe, and the installation bracket is fixedly connected to the outer wall of the flange short pipe to support and fix the pressure relief device.

[0011] A further improvement of the present invention is that: the bottom of the inspection well body is provided with an arc-shaped flow channel, and the side of the arc-shaped flow channel near the pressure relief device is provided with a guide slope, and the angle between the guide slope and the horizontal direction is 15°~30°.

[0012] A further improvement of the present invention is that: the top of the inspection well body is provided with an inspection port, the inspection port is equipped with an inspection port cover with a locking structure, and the inspection port cover is connected to the top edge of the inspection well body by a hinge.

[0013] The technological advancements achieved by this utility model due to the adoption of the above technical solution are as follows: This invention provides a pressure relief device consisting of an elbow, a flanged short pipe, and a blind flange, installed within the manhole body. This device allows high-pressure water in the pressure drainage pipe to first change its flow direction through the elbow, and then be slowly released through the gap between the flanged short pipe and the blind flange. This effectively buffers the impact of the high-pressure water, avoids the water hammer effect caused by instantaneous high pressure, and solves the problem of scouring and damage to the manhole body and pipeline.

[0014] This utility model pressure relief device is installed on one side of the flow channel inside the inspection well body, and the blind flange and the flange short pipe are detachably connected. During later maintenance, it is only necessary to open the inspection port cover and loosen the bolts to remove the blind flange, and clean, inspect or replace parts inside and around the pressure relief device. The operation is simple.

[0015] The diameter of the inspection well body of this utility model can be flexibly selected according to the size of the pressure relief device and the diameter of the gravity flow pipe. The distance between the blind flange and the flange short pipe can be adjusted according to the nominal diameter of the pressure drainage pipe. It can be adapted to pressure drainage pipes of various specifications such as DN50~DN300 and can be widely used in pressure drainage pipe network systems in different scenarios such as municipal drainage, industrial drainage, and building community drainage. Attached Figure Description

[0016] Figure 1 This is a top view of the present invention; Figure 2 This utility model Figure 1 Cross-sectional view at point 1-1; Figure 3 This utility model Figure 1 Enlarged view of node 1; Figure 4 This utility model Figure 3 Top view.

[0017] In the attached diagram: 1. Inspection well body; 2. Pressure relief device; 3. Elbow; 4. Flange short pipe; 5. Blind flange; 6. Arc-shaped flow channel; 7. Guide slope. Detailed Implementation

[0018] To make the objectives, technical solutions, and advantages of this utility model clearer, the present utility model will be further described in detail below with reference to specific embodiments and accompanying drawings. In the following description, descriptions of well-known structures and technologies are omitted to avoid unnecessarily obscuring the concept of this utility model.

[0019] Example 1 This utility model provides a pressure relief inspection well installed at the end of a pressure drainage pipe, including an inspection well body 1 and a pressure relief device 2. The pressure relief device 2 is fixedly installed inside the inspection well body 1 on the side near the interface of the pressure drainage pipe. The pressure relief device 2 includes an elbow 3, a flange short pipe 4, and a blind flange 5 located above the flange short pipe 4. One end of the elbow 3 is sealed to the end of the pressure drainage pipe, and the other end is fixedly connected to one end of the flange short pipe 4. The other end of the flange short pipe 4 is detachably connected to the blind flange 5 by bolts and nuts. The distance L between the blind flange 5 and the flange short pipe 4 is D+80~120mm, where D is the nominal diameter of the pressure drainage pipe.

[0020] The diameter of the manhole body 1 is selected based on the overall size of the pressure relief device 2, and the length of the pressure relief device 2 in the well diameter direction does not exceed 1 / 2 × (diameter of manhole body 1 - diameter of gravity flow pipe), while the diameter of the manhole body 1 is not less than 1.5m.

[0021] In this embodiment, the manhole body 1 is made of reinforced concrete. Its diameter is determined according to the overall size of the pressure relief device 2 and the diameter of the gravity flow pipe. It must meet two conditions: first, the length of the pressure relief device 2 in the well diameter direction does not exceed 1 / 2 × (diameter of manhole body 1 - diameter of gravity flow pipe); second, the diameter of the manhole body 1 is not less than 1.5m, so as to ensure that the pressure relief device 2 has sufficient installation space and water diffusion space. For example, when the nominal diameter of the pressure drainage pipe is D=DN80 and the diameter of the gravity flow pipe is DN300, the length of the pressure relief device 2 in the well diameter direction is designed to be 520mm. In this case, a manhole body 1 with a diameter of 1.5m is selected, and the calculation shows that 1 / 2×(1500mm-300mm)=600mm. Since 520mm<600mm, the installation requirements are met. When the nominal diameter of the pressure drainage pipe is D=DN150 and the diameter of the gravity flow pipe is DN400, the length of the pressure relief device 2 in the well diameter direction is designed to be 650mm. A manhole body 1 with a diameter of 1.8m is selected, and 1 / 2×(1800mm-400mm)=700mm. Since 650mm<700mm, the installation requirements are also met.

[0022] The bottom of the inspection well body 1 is provided with an arc-shaped flow channel 6. The radius of curvature of the arc-shaped flow channel 6 is adapted to the diameter of the inspection well body 1 to ensure smooth gravity flow drainage. A guide slope 7 is provided at one end of the arc-shaped flow channel 6 near the pressure relief device 2. The guide slope 7 makes an angle of 20° with the horizontal direction. This guide slope 7 can guide the water released by the pressure relief device 2 to flow smoothly into the arc-shaped flow channel 6, preventing the water from forming vortices or accumulating in the inspection well. The top of the inspection well body 1 is provided with a circular inspection port with a diameter of 600mm. The inspection port is equipped with an inspection port cover with a locking structure, which is connected to the top edge of the inspection well body 1 by a hinge. This facilitates opening during later maintenance and prevents unauthorized personnel from opening it, ensuring safe use.

[0023] In this embodiment, the pressure relief device 2 includes an elbow 3, a flange short pipe 4, a blind flange 5, bolts, nuts, and sealing gaskets. All components are made of stainless steel, which has good corrosion resistance and structural strength.

[0024] The aforementioned elbow 3 is a 90° standard elbow 3, whose nominal diameter is consistent with the nominal diameter of the pressure drainage pipe. One end of the elbow 3 is sealed to the end of the pressure drainage pipe by welding. The weld is treated with an epoxy resin anti-corrosion coating to prevent corrosion and leakage. The other end of the elbow 3 is welded to one end of the flange short pipe 4. During welding, it is ensured that the axis of the elbow 3 is coaxial with the axis of the pressure drainage pipe, and the outlet direction of the elbow 3 faces the arc-shaped flow channel 6 of the inspection well body 1, so that the water can flow directly to the guide slope 7 after being released.

[0025] The length of the aforementioned flange short pipe 4 is determined based on the installation space of the inspection well body 1, and is generally 200~300mm. The other end of the flange short pipe 4 is provided with a flange, on which multiple bolt holes adapted to the bolts are evenly opened. The dimensions of the blind flange 5 are the same as the flange of the flange short pipe 4, and it is also provided with corresponding bolt holes.

[0026] The distance L between the flange of the blind flange 5 and the flange short pipe 4 is adjusted according to the nominal diameter D of the pressure drainage pipe, specifically satisfying L = (D + 80~120) mm. This distance design allows high-pressure water to be released evenly through the gap, ensuring both pressure relief and preventing secondary impact caused by excessive water flow velocity. For example, when D = DN80, L = 80 + 100 = 180 mm; when D = DN100, L = 100 + 100 = 200 mm; when D = DN150, L = 150 + 110 = 260 mm.

[0027] In this embodiment, to enhance the stability of the pressure relief device 2, an installation bracket is fixedly installed on the inner side of the manhole body 1 corresponding to the position of the flange short pipe 4. The installation bracket is made of angle steel welded together. One end of the installation bracket is fixed to the pre-embedded steel plate of the manhole wall by expansion bolts, and the other end is welded to the outer wall of the flange short pipe 4 to ensure that the pressure relief device 2 does not shift or shake under the impact of high pressure water.

[0028] In the above embodiments, a pressure relief inspection well installed at the end of a pressure drainage pipe is provided. Through this structural design, the high-pressure water in the pressure drainage pipe, when discharged into the inspection well, first changes its flow direction via an elbow, and then is slowly released through the gap between the flange short pipe and the blind flange. This effectively buffers the water pressure and prevents water hammer. Simultaneously, the overall structure is simple, easy to install, and has low maintenance costs. It can adapt to pressure drainage pipes of different specifications and is suitable for various municipal and industrial drainage scenarios, demonstrating significant practicality and promotional value.

[0029] The embodiments described above are merely preferred embodiments of the present invention and are not intended to limit the concept and scope of the present invention. Various modifications and improvements made to the technical solutions of the present invention by those skilled in the art without departing from the design concept of the present invention should fall within the protection scope of the present invention. The technical content for which protection is sought in the present invention has been fully described in the claims.

Claims

1. A pressure relief inspection well installed at the end of a pressure drainage pipe, characterized in that: The system includes a manhole body (1) and a pressure relief device (2). The pressure relief device (2) is fixedly installed inside the manhole body (1) on one side near the interface of the pressure drainage pipe. The pressure relief device (2) includes an elbow (3), a flange short pipe (4), and a blind flange (5) located above the flange short pipe (4). One end of the elbow (3) is sealed to the end of the pressure drainage pipe, and the other end is fixedly connected to one end of the flange short pipe (4). The other end of the flange short pipe (4) is detachably connected to the blind flange (5) by bolts and nuts. The diameter of the manhole body (1) is selected based on the overall size of the pressure relief device (2), and the length of the pressure relief device (2) in the well diameter direction does not exceed 1 / 2 × (diameter of manhole body (1) - diameter of gravity flow pipe), while the diameter of the manhole body (1) is not less than 1.5m.

2. A pressure relief inspection well installed at the end of a pressure drainage pipe according to claim 1, characterized in that: The distance L between the blind flange (5) and the flange short pipe (4) is D+80~120mm, where D is the nominal diameter of the pressure drainage pipe.

3. A pressure relief inspection well installed at the end of a pressure drainage pipe according to claim 1, characterized in that: The elbow (3) is a 90° elbow (3), and the axis of the elbow (3) is coaxial with the axis of the pressure drainage pipe.

4. A pressure relief inspection well installed at the end of a pressure drainage pipe according to claim 1, characterized in that: The inner side of the manhole body (1) is fixedly provided with an installation bracket corresponding to the position of the flange short pipe (4). The installation bracket is fixedly connected to the outer wall of the flange short pipe (4) to support and fix the pressure relief device (2).

5. A pressure relief inspection well installed at the end of a pressure drainage pipe according to claim 1, characterized in that: The bottom of the inspection well body (1) is provided with an arc-shaped flow channel (6), and the side of the arc-shaped flow channel (6) near the pressure relief device (2) is provided with a guide slope (7), and the angle between the guide slope (7) and the horizontal direction is 15°~30°.

6. A pressure relief inspection well installed at the end of a pressure drainage pipe according to claim 1, characterized in that: The top of the inspection well body (1) is provided with an inspection port, and the inspection port is equipped with an inspection port cover with a locking structure. The inspection port cover is connected to the top edge of the inspection well body (1) by a hinge.