A process condensate pre-cooling system for ammonium nitrate plants

By connecting a shell-and-tube cooler in series with the existing cooling coil in the ammonium nitrate unit, the process condensate is cooled in stages, which solves the problem of insufficient cooling efficiency, improves the temperature stability of the condensate, extends the service life of the diaphragm, and reduces maintenance costs.

CN224957221UActive Publication Date: 2026-11-10JINGMEN XINYANG FENGZHONG PHOSPHATE FERTILIZER CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522550289.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-01
Publication Date
2026-11-10
Estimated Expiration
2035-12-01

AI Technical Summary

Technical Problem

The existing ammonium nitrate plant has insufficient cooling efficiency of the condensate, resulting in a condensate temperature higher than the suitable feed temperature of the electrodialysis equipment. This causes large fluctuations in conductivity, shortens the membrane lifespan, and increases equipment maintenance costs.

Method used

By adding a shell-and-tube main cooler and a standby cooler to the existing cooling system and connecting them in series with the existing cooling coils, the process condensate is cooled in stages. The main cooling water and the standby cooling water are used for heat exchange to ensure that the condensate temperature drops below 40°C.

Benefits of technology

It significantly improves cooling efficiency, stabilizes electrical conductivity, extends the service life of membrane stacks and membrane sheets, reduces equipment maintenance frequency and cost, and has low retrofit cost without affecting the original device structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224957221U_ABST
    Figure CN224957221U_ABST
Patent Text Reader

Abstract

An ammonium nitrate device process condensate precooling system, including: process condensate main pipe;Main cooler and backup cooler, the shell is internally provided with heat exchange pipe group, the top of main cooler and backup cooler is provided with process condensate import with process condensate main pipe communication, the bottom of main cooler and backup cooler is provided with process condensate outlet connected process condensate delivery pipeline;Main cooling water inlet pipe and backup cooling water inlet pipe are connected with the cooling water inlet of the bottom of main cooler and backup cooler respectively;Main cooling water outlet pipe and backup cooling water outlet pipe are connected with the cooling water outlet of the top of main cooler and backup cooler respectively;The end of process condensate delivery pipeline is communicated with the liquid inlet of process condensate tank.The utility model has the advantages that: cooling efficiency is significantly improved, process condensate temperature is reduced from above 60 DEG C to below 40 DEG C, and the problem of insufficient cooling of single cooling coil is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of ammonium nitrate production technology, specifically to a pre-cooling system for process condensate in an ammonium nitrate plant. Background Technology

[0002] In the ammonium nitrate (AmN) plant production process, the process condensate temperature is high (typically exceeding 60°C), and the existing process only uses cooling coils within the process condensate tank for primary cooling. Due to insufficient cooling efficiency, the condensate temperature cannot be reduced to the suitable feed temperature for the electrodialysis equipment (generally required to be ≤40°C), resulting in significant fluctuations in the conductivity of the process water sent to the electrodialysis unit. This unstable conductivity accelerates the aging of the electrodialysis membrane stack, shortens membrane lifespan, increases equipment maintenance costs and operational risks, and in severe cases, may lead to membrane stack damage, affecting the continuous and stable operation of the entire AmN plant. Therefore, it is urgent to structurally improve the existing cooling system to solve the above problems. Utility Model Content

[0003] The purpose of this invention is to provide a pre-cooling system for process condensate in an ammonium nitrate plant, which addresses the aforementioned deficiencies by connecting a new cooler in series with the existing cooling coils to achieve staged cooling of the process condensate, thereby ensuring the stability of the temperature and conductivity of the condensate entering the electrodialysis unit.

[0004] A pre-cooling system for process condensate in an ammonium nitrate plant includes a process condensate main pipe 1, which is used to transport high-temperature process condensate from the reaction process of the ammonium nitrate plant to be cooled.

[0005] Both the main cooler 2 and the standby cooler 10 are shell-and-tube structures, with heat exchange tube groups inside the shell. The top of both the main cooler 2 and the standby cooler 10 is provided with a process condensate inlet 3 that is connected to the process condensate main pipe 1, and the bottom of both the main cooler 2 and the standby cooler 10 is provided with a process condensate outlet 4 that is connected to the process condensate delivery pipeline 5.

[0006] The main cooling water inlet pipe 6 and the standby cooling water inlet pipe 7 are respectively connected to the cooling water inlet 8 at the bottom of the main cooler 2 and the standby cooler 10.

[0007] The main cooling water outlet pipe 11 and the standby cooling water outlet pipe 12 are respectively connected to the cooling water outlet 9 at the top of the main cooler 2 and the standby cooler 10.

[0008] The end of the process condensate delivery pipeline 5 is connected to the inlet of the process condensate tank.

[0009] Preferably, a butterfly valve A13 is provided at the connection point between the process condensate main pipe 1 and the process condensate inlet 3 of the main cooler 2 and the standby cooler 10.

[0010] Preferably, a butterfly valve B14 is provided at the connection point between the process condensate delivery pipeline 5 and the process condensate outlet 4 of the main cooler 2 and the standby cooler 10.

[0011] Preferably, a temperature sensor A15 and a conductivity meter 16 are installed on the process condensate delivery pipeline 5 downstream of the butterfly valve B14 at the process condensate outlet 4 of the main cooler 2 and the standby cooler 10.

[0012] Preferably, both the main cooling water outlet pipe 11 and the backup cooling water outlet pipe 12 are equipped with temperature sensors B17.

[0013] Preferably, a cleaning fluid main inlet pipe 18 is connected to the process condensate main pipe 1 between the process condensate inlet 3 of the main cooler 2 and the butterfly valve A13, and a cleaning fluid main outlet pipe 19 is connected to the process condensate delivery pipeline 5 between the process condensate outlet 4 of the main cooler 2 and the butterfly valve B14.

[0014] Preferably, a cleaning fluid backup inlet pipe 20 is connected to the process condensate main pipe 1 between the process condensate inlet 3 and the butterfly valve A13 of the backup cooler 10, and a cleaning fluid backup outlet pipe 21 is connected to the process condensate delivery pipeline 5 between the process condensate outlet 4 and the butterfly valve B14 of the backup cooler 10.

[0015] Preferably, ball valves are provided on the main inlet pipe 18, the backup inlet pipe 20, the main outlet pipe 19, and the backup outlet pipe 21 of the cleaning fluid.

[0016] The advantages of this invention are: significantly improved cooling efficiency, reducing the process condensate temperature from above 60℃ to below 40℃, solving the problem of insufficient cooling from a single cooling coil. Improved conductivity stability reduces the fluctuation range of conductivity in the process water sent to electrodialysis, significantly extending the service life of the membrane stack and membrane sheets. Significant cost advantages, eliminating the need for large-scale equipment replacement, resulting in low retrofit costs and reduced membrane stack replacement frequency and maintenance expenses. Simple structure and easy implementation, requiring only piping to connect the new cooler to the existing system; the retrofit process does not affect the original plant's foundation structure and can be quickly completed during ammonium nitrate unit maintenance. Attached Figure Description

[0017] Figure 1 This is a schematic diagram of the structure of this utility model. Detailed Implementation

[0018] To make the objectives, technical solutions, and advantages of the embodiments of this utility model clearer, the technical solutions of the embodiments of this utility model will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this utility model, and not all embodiments. The components of the embodiments of this utility model described and shown in the accompanying drawings can generally be arranged and designed in various different configurations.

[0019] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely to illustrate selected embodiments of the invention. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without inventive effort are within the scope of protection of the present invention.

[0020] It should be noted that similar labels and letters in the following figures indicate similar items. Therefore, once an item is defined in one figure, it does not need to be further defined and explained in subsequent figures.

[0021] In the description of the embodiments of this utility model, it should be noted that if terms such as "upper," "lower," "inner," or "outer" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, or the orientation or positional relationship commonly used when the utility model product is in use, they are only for the convenience of describing the utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the utility model. Furthermore, if terms such as "first" or "second" appear in the description of this utility model, they are only used to distinguish descriptions and should not be construed as indicating or implying relative importance.

[0022] In the description of the embodiments of this utility model, it should also be noted that, unless otherwise explicitly specified and limited, the terms "set" and "connection" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.

[0023] As shown in the attached figure, a pre-cooling system for process condensate in an ammonium nitrate plant includes a process condensate main pipe 1, which is used to transport high-temperature process condensate from the reaction process of the ammonium nitrate plant to be cooled.

[0024] Both the main cooler 2 and the standby cooler 10 are shell-and-tube structures, with heat exchange tube groups inside the shell. The top of both the main cooler 2 and the standby cooler 10 is provided with a process condensate inlet 3 that is connected to the process condensate main pipe 1, and the bottom of both the main cooler 2 and the standby cooler 10 is provided with a process condensate outlet 4 that is connected to the process condensate delivery pipeline 5.

[0025] The main cooling water inlet pipe 6 and the standby cooling water inlet pipe 7 are respectively connected to the cooling water inlet 8 at the bottom of the main cooler 2 and the standby cooler 10.

[0026] The main cooling water outlet pipe 11 and the standby cooling water outlet pipe 12 are respectively connected to the cooling water outlet 9 at the top of the main cooler 2 and the standby cooler 10.

[0027] The end of the process condensate delivery pipeline 5 is connected to the inlet of the process condensate tank. The process condensate tank is an existing storage container with existing cooling coils (as existing cooling components). The condensate, after being pre-cooled by the newly added cooler, enters the process condensate tank and comes into contact with the existing cooling coils for further cooling.

[0028] In another technical solution, a butterfly valve A13 is provided at the connection point between the process condensate main pipe 1 and the process condensate inlet 3 of the main cooler 2 and the standby cooler 10.

[0029] In another technical solution, a butterfly valve B14 is provided at the connection point between the process condensate delivery pipeline 5 and the process condensate outlet 4 of the main cooler 2 and the standby cooler 10.

[0030] In another technical solution, a temperature sensor A15 and a conductivity meter 16 are installed on the process condensate delivery pipeline 5 behind the butterfly valve B14 at the process condensate outlet 4 of the main cooler 2 and the backup cooler 10, so as to facilitate monitoring of the temperature and conductivity of the process condensate.

[0031] In another technical solution, both the main cooling water outlet pipe 11 and the backup cooling water outlet pipe 12 are equipped with temperature sensors B17, which can appropriately increase the cooling water flow rate when the temperature is high.

[0032] In another technical solution, a cleaning fluid main inlet pipe 18 is connected to the process condensate main pipe 1 between the process condensate inlet 3 of the main cooler 2 and the butterfly valve A13, and a cleaning fluid main outlet pipe 19 is connected to the process condensate delivery pipeline 5 between the process condensate outlet 4 of the main cooler 2 and the butterfly valve B14. A cleaning fluid backup inlet pipe 20 is connected to the process condensate main pipe 1 between the process condensate inlet 3 of the standby cooler 10 and the butterfly valve A13, and a cleaning fluid backup outlet pipe 21 is connected to the process condensate delivery pipeline 5 between the process condensate outlet 4 of the standby cooler 10 and the butterfly valve B14. Ball valves are installed on the cleaning fluid main inlet pipe 18, the cleaning fluid backup inlet pipe 20, the cleaning fluid main outlet pipe 19, and the cleaning fluid backup outlet pipe 21. A cleaning interface is installed on the process condensate inlet and outlet pipes of the newly added cooler, connected to a high-pressure cleaning pump, allowing for periodic flushing with a 5% citric acid solution.

[0033] Working Principle: High-temperature process condensate flows out from the process condensate main pipe and enters the main cooler. Cooling water enters the shell side of the main cooler from the main cooling water inlet pipe, where it exchanges heat with the high-temperature process condensate in the tube side, completing pre-cooling. The pre-cooled process condensate flows out from the process condensate outlet and enters the process condensate tank through process condensate delivery pipeline 5, where it contacts the existing cooling coils for further cooling. When the main cooler fails, it can be switched to the standby cooler for pre-cooling of the high-temperature process condensate. This device has a simple structure and is easy to implement. It only connects the new cooler to the original system through piping. The modification process does not affect the basic structure of the original unit and can be quickly completed during maintenance of the ammonium nitrate unit.

[0034] The above-described embodiments are only intended to illustrate the technical solution and features of this utility model, and are intended to enable those skilled in the art to implement them. They should not be used to limit the scope of protection of this utility model. All equivalent changes or modifications made in accordance with the spirit and essence of this utility model are within the scope of protection of this utility model. Anything not described in detail is prior art.

Claims

1. A pre-cooling system for process condensate in an ammonium nitrate plant, characterized in that, include Process condensate main (1) is used to transport high-temperature process condensate from the reaction process of the ammonium nitrate unit to be cooled; The main cooler (2) and the standby cooler (10) are both shell-and-tube structures. The shell is equipped with heat exchange tubes. The top of the main cooler (2) and the standby cooler (10) are equipped with a process condensate inlet (3) that is connected to the process condensate main pipe (1). The bottom of the main cooler (2) and the standby cooler (10) are equipped with a process condensate outlet (4) that is connected to the process condensate delivery pipeline (5). The main cooling water inlet pipe (6) and the standby cooling water inlet pipe (7) are respectively connected to the cooling water inlets (8) at the bottom of the main cooler (2) and the standby cooler (10); The main cooling water outlet pipe (11) and the standby cooling water outlet pipe (12) are respectively connected to the cooling water outlet (9) at the top of the main cooler (2) and the standby cooler (10); The end of the process condensate delivery pipeline (5) is connected to the inlet of the process condensate tank.

2. The ammonium nitrate plant process condensate precooling system according to claim 1, characterized in that, The process condensate main pipe (1) is equipped with butterfly valves A (13) at the connection points with the process condensate inlets (3) of the main cooler (2) and the standby cooler (10).

3. The ammonium nitrate plant process condensate precooling system according to claim 1, characterized in that, The process condensate delivery pipeline (5) is equipped with butterfly valves B (14) at the connection points between the main cooler (2) and the process condensate outlet (4) of the standby cooler (10).

4. The ammonium nitrate plant process condensate precooling system according to claim 3, characterized in that, Temperature sensor A (15) and conductivity meter (16) are installed on the process condensate delivery pipeline (5) behind the butterfly valve B (14) at the process condensate outlet (4) of the main cooler (2) and the standby cooler (10).

5. The pre-cooling system for process condensate in an ammonium nitrate plant according to claim 1, characterized in that, Temperature sensors B (17) are installed on both the main cooling water outlet pipe (11) and the backup cooling water outlet pipe (12).

6. The ammonium nitrate plant process condensate precooling system according to claim 3, characterized in that, The main inlet pipe (18) of cleaning fluid is connected to the main condensate inlet (3) of the main cooler (2) and the main condensate conveying pipeline (5) between the main cooler (2) and the butterfly valve A (13). The main outlet pipe (19) of cleaning fluid is connected to the main condensate delivery pipeline (5) between the main cooler (2) and the process condensate outlet (4) and the butterfly valve B (14).

7. A pre-cooling system for process condensate in an ammonium nitrate plant according to claim 6, characterized in that, A cleaning fluid backup inlet pipe (20) is connected to the process condensate main pipe (1) between the process condensate inlet (3) of the backup cooler (10) and the butterfly valve A (13), and a cleaning fluid backup outlet pipe (21) is connected to the process condensate delivery pipeline (5) between the process condensate outlet (4) of the backup cooler (10) and the butterfly valve B (14).