A concrete test block curing frame

By designing a movable base and a curing cage with an open front, the problem of concrete test blocks slipping and inconvenient height adjustment was solved by using a hook suspension method, thus achieving stability and convenient operation of the concrete test blocks.

CN224978866UActive Publication Date: 2026-11-17CHINA CONSTR EIGHTH BUREAU SOUTH CHINA CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522008392.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-09-18
Publication Date
2026-11-17
Estimated Expiration
2035-09-18

AI Technical Summary

Technical Problem

Existing curing frames are prone to causing concrete test blocks to slip during movement or handling, and the height of the shelves is inconvenient to adjust.

Method used

A concrete test block curing frame was designed, which includes a movable base and a curing cage with an open front. The curing cage is suspended from a square tube column by hooks, and hooks are welded to the back of the curing cage. The cage is suspended by hooking the square tube column at the bottom of the hook hole. The suspension height of the curing cage can be adjusted as needed.

Benefits of technology

It effectively prevents concrete test blocks from slipping, and the height of the curing cage is adjustable through the hook suspension method, which improves the stability and ease of operation of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224978866U_ABST
    Figure CN224978866U_ABST
Patent Text Reader

Abstract

This utility model relates to a concrete test block curing frame, including a movable base and multiple curing cages with openings on the front and top. Two square tube columns perpendicular to the movable base are welded to the top of the base. Each square tube column has N hook holes evenly distributed along its axial direction on its front. Each curing cage has four hooks arranged in a rectangular array welded to its back. The hooks hook onto the square tube columns at the bottom of the hook holes, suspending the curing cage on the columns. A cage door is installed on the front of each curing cage. The advantages are: the design of the curing cage with openings on the front and top, and the installation of a cage door on the front, prevents the concrete test blocks inside the cage from slipping; the position of the hook holes can be selected as needed, thereby adjusting the suspension height of the curing cage.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of concrete testing equipment, and in particular to a concrete test block curing frame. Background Technology

[0002] Concrete test blocks are quality test blocks made of concrete in the form of cubes, cylinders, or frustums. They are used to reflect the construction quality of concrete structures. A concrete curing room is a room with specific temperature and humidity for storing concrete test blocks. During the curing process, the concrete test blocks are kept within the standard humidity range and placed on curing racks.

[0003] Existing curing racks generally consist of a frame and shelves. The shelves are placed on blocks or rods on the frame, and concrete test blocks are placed on the shelves. When the curing rack is moved as a whole or the entire shelf is transported, there is a risk that the concrete test blocks will slip off the shelves. Moreover, the placement of the shelves is not convenient to adjust according to the height of the concrete test blocks. Utility Model Content

[0004] The purpose of this utility model is to overcome the above-mentioned problems in the existing technology and provide a concrete test block curing frame.

[0005] To achieve the above-mentioned technical objectives and effects, this utility model is implemented through the following technical solution: A concrete test block curing frame includes a movable base and multiple curing cages with openings on the front and top. Two square tube columns perpendicular to the movable base are welded to the top of the movable base. Each square tube column has N hook holes evenly distributed along its axial direction on its front. Each curing cage has four hooks arranged in a rectangular array welded to its back. The hooks hook onto the square tube columns at the bottom of the hook holes, suspending the curing cage on the square tube columns. A cage door is installed on the front of each curing cage.

[0006] The movable base includes two symmetrical square tube longitudinal beams, at least two square tube transverse beams, and four casters. The square tube transverse beams are welded between the two square tube longitudinal beams, and a caster is installed at the bottom of each of the two ends of each square tube longitudinal beam.

[0007] The square tube column is vertically welded to the rear top of the square tube longitudinal beam.

[0008] A round tube handrail is welded between the upper parts of the two square tube columns.

[0009] The maintenance cage includes four first vertical steel bars arranged in a rectangular array and two first horizontal steel bars that are parallel to each other. A first vertical steel bar is vertically welded to the top of each of the two ends of the first horizontal steel bars. Multiple first longitudinal steel bars that are parallel to each other are welded to the bottom of the two first horizontal steel bars. Two second horizontal steel bars that are parallel to each other are welded between the two first vertical steel bars located on the back of the maintenance cage. The hook is welded to the back of the second horizontal steel bars. Two second longitudinal steel bars that are parallel to each other are welded between the two first vertical steel bars that are symmetrically arranged on the front and back of the side of the maintenance cage. Two sleeves that are symmetrically arranged on the front of the two first vertical steel bars located on the front of the maintenance cage are welded to the front of the cage.

[0010] The cage door includes two parallel third horizontal reinforcing bars, one second vertical reinforcing bar, and two third vertical reinforcing bars. One end of each third horizontal reinforcing bar is welded perpendicularly to the second vertical reinforcing bar, and the second vertical reinforcing bar is fitted into a sleeve on one side of the front of the maintenance cage. The other end of each third horizontal reinforcing bar is welded perpendicularly to a third vertical reinforcing bar, and the third vertical reinforcing bar is engaged with the sleeve on the other side of the front of the maintenance cage.

[0011] Among them, multiple parallel fourth vertical bars are welded between the two third transverse bars.

[0012] The square tube column has a rectangular reinforcing plate welded to the inner wall of the side with the hook hole. The reinforcing plate has through holes that correspond one-to-one with and are connected to the hook hole.

[0013] The beneficial effects of this utility model are: the use of a curing cage design with openings on the front and top, and the installation of a cage door on the front of the curing cage, can prevent the concrete test blocks inside the curing cage from slipping off; multiple hook holes are provided on the front of the square tube column, evenly distributed along the axis of the square tube column, and hooks are welded on the back of the curing cage. The curing cage is suspended on the square tube column by hooking the bottom of the hook hole with the hook. The position of the hook hole can be selected as needed to adjust the suspension height of the curing cage. Attached Figure Description

[0014] The accompanying drawings, which are included to provide a further understanding of the present invention and form part of this application, illustrate exemplary embodiments of the present invention and, together with the description thereof, serve to explain the present invention and do not constitute an undue limitation thereof. In the drawings: Figure 1 This is a schematic diagram of the structure of the curing frame in this utility model; Figure 2 This is a schematic diagram of the structure of the movable base, square tube column, and round tube handrail combined in this utility model; Figure 3 This is a schematic diagram of the longitudinal section of the square-tube column of this utility model; Figure 4 This is a schematic diagram of the reinforcing plate in this utility model; Figure 5 This is a schematic diagram of the structure of the curing cage and the cage door in the closed state of this utility model; Figure 6 This is a schematic diagram of the structure of the curing cage and the cage door in the open state of this utility model; Figure 7 This is a schematic diagram of the structure of the curing cage as viewed from the front top of this utility model; Figure 8 This is a schematic diagram of the structure of the curing cage as viewed from the rear top of this utility model; Figure 9 This is a schematic diagram of the cage door structure in this utility model; The following are the labels in the diagram: 1. Movable base; 11. Square tube longitudinal beam; 12. Square tube transverse beam; 13. Caster; 2. Square tube column; 21. Hook hole; 22. Reinforcing plate; 221. Through hole; 3. Curing cage; 31. Hook; 32. First vertical reinforcement; 33. First transverse reinforcement; 34. Second transverse reinforcement; 35. Second transverse reinforcement; 36. Sleeve; 37. Cage door; 4. Third transverse reinforcement; 41. Second vertical reinforcement; 42. Third vertical reinforcement; 43. Fourth vertical reinforcement; 44. Round tube handrail; 5. Detailed Implementation

[0015] The present invention will now be described in detail with reference to the accompanying drawings and embodiments.

[0016] like Figure 1 As shown in Figure 9, a concrete test block curing frame includes a movable base 1 and multiple curing cages 3 with openings on the front and top.

[0017] The movable base 1 includes two symmetrical square tube longitudinal beams 11, at least two square tube transverse beams 12, and four casters 13. The square tube transverse beams 12 are welded between the two square tube longitudinal beams 11. A caster 13 is installed at the bottom of each end of each square tube longitudinal beam 11. The casters 13 are universal casters with brakes, which are convenient for adjusting the direction when moving and for locking the casters to prevent movement when stopping.

[0018] Two square tube columns 2, perpendicular to the movable base 1, are welded to the top of the movable base 1. Specifically, the square tube columns 2 are welded vertically to the rear top of the square tube longitudinal beam 11.

[0019] Each square tube column 2 has N hook holes 21 evenly distributed along the axis of the square tube column on its front side. Each maintenance cage 3 has four hooks 31 arranged in a rectangular array welded on its back side. The hooks 31 are L-shaped and hook the square tube column 2 at the bottom of the hook holes 21 so that the maintenance cage 3 is suspended on the square tube column 2.

[0020] A rectangular reinforcing plate 22 is welded to the inner wall of the square tube column 2 on the side where the hook hole 21 is located. The reinforcing plate 22 has through holes 221 that correspond one-to-one with and are connected to the hook hole 21. The reinforcing plate 22 increases the support strength of the square tube column 2 on the side where the maintenance cage is suspended, and reduces the risk of deformation of the square tube column 2 due to the suspension of the maintenance cage.

[0021] To facilitate the movement of the maintenance frame by staff, a round tube handrail 5 is welded between the upper parts of the two square tube columns 2.

[0022] The maintenance cage 3 includes four first vertical steel bars 32 arranged in a rectangular array and two first horizontal steel bars 33 that are parallel to each other. At the top of each end of the first horizontal steel bar 33, a first vertical steel bar 32 is vertically welded. At the bottom of the two first horizontal steel bars 33, multiple first longitudinal steel bars 34 that are parallel to each other are welded. Between the two first vertical steel bars 32 located on the back of the maintenance cage 3, two second horizontal steel bars 35 that are parallel to each other are welded. Hooks 31 are welded to the back of the second horizontal steel bars 35. Between the two first vertical steel bars 32 located symmetrically on the front and back of the side of the maintenance cage 3, two second longitudinal steel bars 36 that are parallel to each other are welded. On the front of the two first vertical steel bars 32 located on the front of the maintenance cage 3, two sleeves 37 that are symmetrically connected are welded.

[0023] The first longitudinal steel bar 34 is welded to the bottom end of the first transverse steel bar 33. When the concrete test block is placed on the first longitudinal steel bar, the first transverse steel bar 33 acts as a barrier to prevent the concrete test block from slipping out of the curing cage even if the cage door is not closed.

[0024] A cage door 4 is installed on the front of the curing cage 3. The cage door 4 includes two parallel third horizontal steel bars 41, one second vertical steel bar 42, and two third vertical steel bars 43. One end of the third horizontal steel bar 41 is welded perpendicularly to the second vertical steel bar 42. The second vertical steel bar 42 is fitted into the sleeve 37 on one side of the front of the curing cage 3. The other end of each third horizontal steel bar 41 is vertically welded to a third vertical steel bar 43. The third vertical steel bar 43 is inserted into and removed from the sleeve 37 on the other side of the front of the curing cage 3.

[0025] Multiple parallel fourth vertical reinforcing bars 44 are welded between the two third horizontal reinforcing bars 43.

[0026] In this embodiment, plain round steel bars with a diameter of 10 mm are used to make the curing cage and the cage door. The total height of the curing cage is 17 cm, and the spacing between adjacent first longitudinal steel bars is 6 cm.

[0027] In this utility model, unless otherwise explicitly specified and limited, the terms "installation," "connection," "joining," and "fixing," etc., should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral part; they can refer to a mechanical connection, an electrical connection, or a connection that allows communication between them; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal communication of two components or the interaction between two components, unless otherwise explicitly limited. Those skilled in the art can understand the specific meaning of the above terms in this utility model according to the specific circumstances.

[0028] The foregoing has shown and described the basic principles, main features, and advantages of this utility model. Those skilled in the art should understand that this utility model is not limited to the above embodiments. The embodiments and descriptions in the specification are merely illustrative of the principles of this utility model. Various changes and modifications can be made to this utility model without departing from its spirit and scope, and all such changes and modifications fall within the scope of the claimed utility model.

Claims

1. A concrete test block curing frame, characterized in that: The maintenance cage includes a movable base and multiple openings on the front and top. The top of the movable base is welded with two square tube columns perpendicular to the movable base. Each square tube column has N hook holes evenly distributed along the axis of the square tube column on its front side. Each maintenance cage has four hooks arranged in a rectangular array welded on its back side. The hooks hook onto the square tube columns at the bottom of the hook holes, so that the maintenance cage is suspended on the square tube columns. A cage door is installed on the front of the maintenance cage.

2. The concrete test block curing frame according to claim 1, characterized in that: The movable base includes two symmetrical square tube longitudinal beams, at least two square tube transverse beams, and four casters. The square tube transverse beams are welded between the two square tube longitudinal beams, and a caster is installed at the bottom of each of the two ends of each square tube longitudinal beam.

3. The concrete test block curing frame according to claim 2, characterized in that: The square tube column is vertically welded to the rear top of the square tube longitudinal beam.

4. The concrete test block curing frame according to claim 1, characterized in that: A round tube handrail is welded between the upper parts of the two square tube columns.

5. The concrete test block curing frame according to claim 1, characterized in that: The maintenance cage includes four first vertical steel bars arranged in a rectangular array and two first horizontal steel bars that are parallel to each other. A first vertical steel bar is vertically welded to the top of each of the two ends of the first horizontal steel bars. Multiple first longitudinal steel bars that are parallel to each other are welded to the bottom of the two first horizontal steel bars. Two second horizontal steel bars that are parallel to each other are welded between the two first vertical steel bars located on the back of the maintenance cage. The hook is welded to the back of the second horizontal steel bars. Two second longitudinal steel bars that are parallel to each other are welded between the two first vertical steel bars that are symmetrically arranged on the front and back of the side of the maintenance cage. Two sleeves that are symmetrically arranged on the front of the two first vertical steel bars located on the front of the maintenance cage are welded to the front of the cage.

6. The concrete test block curing frame according to claim 1, characterized in that: The cage door includes two parallel third horizontal reinforcing bars, one second vertical reinforcing bar, and two third vertical reinforcing bars. One end of the third horizontal reinforcing bar is welded perpendicularly to the second vertical reinforcing bar, and the second vertical reinforcing bar is fitted into a sleeve on one side of the front of the maintenance cage. The other end of each third horizontal reinforcing bar is welded perpendicularly to a third vertical reinforcing bar, and the third vertical reinforcing bar is engaged with the sleeve on the other side of the front of the maintenance cage.

7. The concrete test block curing frame according to claim 6, characterized in that: Multiple parallel fourth vertical reinforcing bars are welded between the two third transverse reinforcing bars.

8. The concrete test block curing frame according to claim 1, characterized in that: A rectangular reinforcing plate is welded to the inner wall of the square tube column on the side with the hook hole. The reinforcing plate has through holes that correspond one-to-one with and are connected to the hook hole.