A wall-mounted device for construction hoists

By adopting a design that combines toothed grooves and convex toothed blocks in the wall-mounted device of the construction hoist, and utilizing the screw connection of threaded pipes and threaded rods, the wall-mounted device of the construction hoist can be quickly and efficiently adjusted. This solves the problem of requiring a large number of tools to disassemble and assemble screws in the existing technology, and improves the convenience and safety of adjustment.

CN224981065UActive Publication Date: 2026-11-17GUANGYITONG FUJIAN HEAVY MACHINERY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522769492.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-26
Publication Date
2026-11-17
Estimated Expiration
2035-12-26

AI Technical Summary

Technical Problem

The existing construction hoist wall-mounted frame requires tools to disassemble and assemble a large number of screws when adjusting the distance between the connecting frame and the support column, which makes the adjustment not quick enough.

Method used

The design employs a combination of toothed grooves and convex toothed blocks. The distance between the convex toothed blocks and the toothed grooves can be adjusted by moving the adjusting component. Quick adjustment is achieved by using the screw connection of the threaded tube and the threaded rod. Combined with the fixing of the clamp and the fixing strip, the connecting frame and the support column can be quickly connected.

Benefits of technology

It enables rapid and efficient adjustment of the wall-mounted device of the construction hoist, improving the convenience and safety of the adjustment process, and is faster and more efficient than the traditional bolt connection method.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224981065U_ABST
    Figure CN224981065U_ABST
Patent Text Reader

Abstract

This utility model provides a wall-mounted device for a construction hoist, belonging to the technical field of construction equipment. The wall-mounted device for a construction hoist includes a connecting frame, a support column, and a fixed connection part. The support column has a first planar structure on both sides, with a toothed groove on the inner side of the first planar structure. A crossbeam and a clamp are fixedly installed, with a fixing strip fixed to the end of the crossbeam. A movable adjustment component is installed inside the crossbeam to adjust the relative position of the protruding tooth blocks at both ends. The protruding tooth blocks cooperate with the toothed grooves. The clamp is located outside the protruding tooth blocks and fixed to the fixing strip. The movable adjustment component adjusts the distance between the protruding tooth blocks and the toothed grooves, thus adjusting the movement of the connecting frame. Adjusting the movable adjustment component pushes the protruding tooth blocks at both ends into the toothed grooves on the inner side of the support column. The protruding tooth blocks and the clamp are pressed and tightly fixed to the outside of the support column. Simultaneously, the toothed grooves and protruding tooth blocks, when locked together, also provide protection against axial movement of the support column.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of construction equipment technology, and more specifically, to a wall-mounted device for a construction hoist. Background Technology

[0002] The wall-mounted bracket is a key safety component of construction hoists, primarily used to securely connect the hoist's guide rails to the main building structure, ensuring the stability and safety of the equipment during vertical transportation. Currently, adjusting the distance between the connecting frame and the support columns of the wall-mounted bracket mainly uses bolt-fixed clamps. Each support column requires at least two sets of clamps, necessitating extensive tooling for loosening and loosening of bolts, making distance adjustment slow and inefficient. Utility Model Content

[0003] To overcome the above shortcomings, this utility model provides a wall-mounting device for construction hoists, which aims to improve the problem that existing wall-mounting frames require a lot of tools to disassemble and reassemble the screws on the clamps when adjusting the distance of the wall-mounting frame, resulting in the wall-mounting frame not being quick enough.

[0004] This utility model is implemented as follows: This utility model provides a wall-mounted device for a construction hoist, including a connecting frame, a support column, and a fixed connection part.

[0005] The two sides of the support column are configured as first planar structures, and the inner first planar structure is provided with toothed grooves. The fixed connection part includes a clamp, a crossbeam, a fixing strip, a toothed block, and a movable adjustment component. The crossbeam is fixedly installed with the clamp, the fixing strip is fixed to the end of the crossbeam, and the movable adjustment component is installed inside the crossbeam to adjust the relative position movement of the toothed blocks at both ends. The toothed blocks cooperate with the tooth grooves, and the clamp is located outside the toothed blocks and fixedly installed with the fixing strip.

[0006] In one embodiment of this utility model, the movable adjustment component includes a threaded tube, a threaded rod, a square rod, and a knob. The two ends of the threaded tube are screwed to the threaded rod, the other end of the threaded rod is fixedly set to the square rod, the other end of the square rod is fixedly connected to the toothed block, the two threaded rods are arranged with opposite spiral directions, and the knob is fixedly sleeved on the outside of the threaded tube.

[0007] In one embodiment of this utility model, the crossbeam includes a square tube and a connecting plate. The two ends of the connecting plate are connected to two square tubes. The movable adjustment component is located in the space between the two sets of connecting plates. The fixing strip is fixedly connected to the end of the square tube.

[0008] In one embodiment of this utility model, the side of the fixing strip and the end of the square tube are provided with square groove holes that cooperate with the sliding of the square rod.

[0009] In one embodiment of this utility model, the fixed connection portion is provided in at least two sets, and the adjacent connecting plates in the two sets of fixed connection portions are fixedly connected.

[0010] In one embodiment of this utility model, the clamp includes a clamp ring and an ear plate, the ear plate connects the clamp ring and the end of the crossbeam, and the inner wall of the clamp ring is provided with a second planar structure that cooperates with the first planar structure on the surface of the support column.

[0011] In one embodiment of this utility model, a limit block is fixedly provided at one end of the support column near the connecting frame.

[0012] In one embodiment of this utility model, a reinforcing rod is fixedly connected between the connecting frame and the crossbeam.

[0013] The beneficial effects of this utility model are as follows: This utility model provides a wall-mounted device for construction hoists, designed as described above. The movable adjusting component adjusts the distance between the convex teeth and the tooth groove, thus adjusting the movement of the connecting frame. Adjusting the movable adjusting component pushes the convex teeth at both ends into the tooth grooves on the inner side of the support column. The convex teeth and the clamping component press and hold tightly to the outside of the support column. Simultaneously, the clamping of the tooth groove and the convex teeth also provides protection against axial movement of the support column. This wall-mounted device for construction hoists is faster and more efficient than the traditional wall-mounted frame clamp bolt fixing and adjustment method. Attached Figure Description

[0014] To more clearly illustrate the technical solutions of the embodiments of this utility model, the drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of this utility model and should not be regarded as a limitation of the scope. For those skilled in the art, other related drawings can be obtained from these drawings without creative effort.

[0015] Figure 1 This is a schematic diagram of the wall-mounted device for a construction hoist provided by an embodiment of the present invention; Figure 2 A schematic diagram of the fixed connection portion provided for an embodiment of this utility model; Figure 3 A schematic diagram of the clamp structure provided for an embodiment of this utility model; Figure 4 A schematic diagram of the internal structure of the crossbeam, the toothed block, and the movable adjustment component provided for an embodiment of this utility model.

[0016] In the diagram: 10-Connecting frame; 110-Reinforcing rod; 20-Support column; 210-First plane structure; 220-Groove; 230-Limiting block; 30-Fixed connection part; 310-Clamping part; 311-Clamping ring; 312-Ear plate; 313-Second plane structure; 320-Crossbeam; 321-Square tube; 322-Connecting plate; 330-Fixing strip; 331-Square slot hole; 340-Protruding tooth block; 350-Moving adjustment part; 351-Threaded tube; 352-Threaded rod; 353-Square rod; 354-Knob. Detailed Implementation

[0017] To make the objectives, technical solutions, and advantages of the embodiments of this utility model clearer, the technical solutions of the embodiments of this utility model will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this utility model, not all embodiments. Based on the embodiments of this utility model, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this utility model.

[0018] Example Please see Figures 1-4 This utility model provides a wall-mounted device for a construction hoist, including a connecting frame 10, a support column 20, and a fixed connection part 30.

[0019] The connection between the connecting frame 10 and the support column 20 can be quickly adjusted and fixed by cooperating with the connecting part 30. Compared with the traditional bolt and clamp method, the distance adjustment is faster and more efficient.

[0020] The support column 20 has a first planar structure 210 on both sides, and the inner first planar structure 210 has a toothed groove 220. The fixed connection part 30 includes a clamp 310, a crossbeam 320, a fixing strip 330, a toothed block 340, and a movable adjustment part 350. The crossbeam 320 is fixedly installed with the clamp 310, the fixing strip 330 is fixed to the end of the crossbeam 320, and the movable adjustment part 350 is installed inside the crossbeam 320 to adjust the relative position movement of the toothed blocks 340 at both ends. The toothed blocks 340 cooperate with the toothed groove 220. The clamp 310 is located outside the toothed blocks 340 and is fixedly installed with the fixing strip 330.

[0021] When the convex teeth 340 at both ends are moved and retracted by adjusting the movable adjusting component 350, the convex teeth 340 disengage from the toothed grooves 220 on the inner side of the support column 20. At this time, the connecting frame 10 and the crossbeam 320 can be moved. The moving crossbeam 320 will drive the fixing plate 330, the convex teeth 340, and the movable adjusting component 350 to move together along the axial direction of the support column 20. After the connecting frame 10 moves to the designated position, the movable adjusting component 350 pushes the convex teeth 340 at both ends into the toothed grooves 220 on the inner side of the support column 20. The convex teeth 340 and the clamping component 310 squeeze and hold them tightly to the outside of the support column 20. At the same time, the clamping of the toothed grooves 220 and the convex teeth 340 also has a protective function to prevent axial movement of the support column 20. This wall-mounted device for construction hoists is faster and more efficient than the traditional wall-mounted frame clamp bolt fixing and adjustment method.

[0022] In the above specific embodiment, the movable adjustment component 350 includes a threaded tube 351, a threaded rod 352, a square rod 353, and a knob 354. Both ends of the threaded tube 351 are screwed into the threaded rod 352. The other end of the threaded rod 352 is fixedly connected to the square rod 353, and the other end of the square rod 353 is fixedly connected to the toothed block 340. The two threaded rods 352 have opposite spiral directions. The knob 354 is fixedly sleeved on the outside of the threaded tube 351. Rotating the knob 354 causes the threaded tube 351 to rotate. Through the screwed engagement between the threaded tube 351 and the threaded rod 352, relative movement occurs between the threaded rod 352 and the threaded tube 351, thereby moving the toothed block 340 at the end of the square rod 353 to adjust the distance between the toothed block 340 and the toothed groove 220.

[0023] In its specific configuration, the crossbeam 320 includes a square tube 321 and a connecting plate 322. The connecting plate 322 connects to two square tubes 321 at both ends. The movable adjusting member 350 is located in the space between the two sets of connecting plates 322. The fixing strip 330 is fixedly connected to the end of the square tube 321. The side of the fixing strip 330 and the end of the square tube 321 are both provided with square slot holes 331 that slide with the square rod 353. The square slot holes 331 improve the stability of the square rod 353 during movement.

[0024] Furthermore, the fixed connection portion 30 is provided in at least two sets, and the adjacent connecting plates 322 in the two sets of fixed connection portions 30 are fixedly connected. The provision of two sets of fixed connection portions 30 is to improve the stability when the fixed connection portion 30 is fixed to the support column 20.

[0025] In its specific configuration, the clamp 310 includes a clamp ring 311 and an ear plate 312. The ear plate 312 connects the clamp ring 311 and the end of the crossbeam 320. The inner wall of the clamp ring 311 is provided with a second planar structure 313 that mates with the first planar structure 210 on the surface of the support column 20. A limit block 230 is fixedly installed at one end of the support column 20 near the connecting frame 10. The limit block 230 is provided to prevent the crossbeam 320 from falling off when adjusting the relative distance from the support column 20, thereby improving the safety of the adjustment. A reinforcing rod 110 is fixedly connected between the connecting frame 10 and the crossbeam 320.

[0026] The working principle of the wall-mounted device for construction hoists is as follows: During use, the convex tooth blocks 340 at both ends are moved and retracted by adjusting the adjusting component 350, causing the convex tooth blocks 340 to disengage from the toothed grooves 220 on the inner side of the support column 20. At this time, the connecting frame 10 and the crossbeam 320 can be moved. The moving crossbeam 320 will drive the fixing plate 330, the convex tooth blocks 340, and the adjusting component 350 to move together along the axial direction of the support column 20. After the connecting frame 10 moves to the designated position, the adjusting component 350 pushes the convex tooth blocks 340 at both ends into the toothed grooves 220 on the inner side of the support column 20. The convex tooth blocks 340 are pressed and clamped by the clamping component 310 to be fixed to the outside of the support column 20. At the same time, the clamping of the toothed grooves 220 and the convex tooth blocks 340 also has a protective function to prevent axial movement of the support column 20. This wall-mounted device for construction hoists is faster and more efficient than the traditional wall-mounted frame, clamping bolt fixing and adjustment method.

[0027] The above description is merely a preferred embodiment of this utility model and is not intended to limit the utility model. Various modifications and variations can be made to this utility model by those skilled in the art. Any modifications, equivalent substitutions, or improvements made within the spirit and principles of this utility model should be included within the protection scope of this utility model.

Claims

1. A wall attachment device for a construction elevator, characterized in that, include The connecting frame (10) and the support column (20) are provided with a first planar structure (210) on both sides of the support column (20) and a toothed groove (220) on the inner side of the first planar structure (210). The fixed connection part (30) includes a clamp (310), a crossbeam (320), a fixing strip (330), a toothed block (340), and a movable adjustment part (350). The crossbeam (320) is fixedly disposed with the clamp (310). The fixing strip (330) is fixed at the end of the crossbeam (320). The movable adjustment part (350) is installed inside the crossbeam (320) to adjust the relative position movement of the toothed blocks (340) at both ends. The toothed blocks (340) cooperate with the tooth groove (220). The clamp (310) is located outside the toothed blocks (340) and is fixedly disposed with the fixing strip (330).

2. The wall-mounted device for a construction hoist according to claim 1, characterized in that, The movable adjustment component (350) includes a threaded tube (351), a threaded rod (352), a square rod (353), and a knob (354). The two ends of the threaded tube (351) are threadedly connected to the threaded rod (352). The other end of the threaded rod (352) is fixedly connected to the square rod (353). The other end of the square rod (353) is fixedly connected to the toothed block (340). The two threaded rods (352) are arranged with opposite spiral directions. The knob (354) is fixedly sleeved on the outside of the threaded tube (351).

3. A wall-mounted device for a construction hoist according to claim 2, characterized in that, The crossbeam (320) includes a square tube (321) and a connecting plate (322). The two ends of the connecting plate (322) are connected to two square tubes (321). The movable adjustment component (350) is located in the space between the two sets of connecting plates (322). The fixed strip (330) is fixedly connected to the end of the square tube (321).

4. A wall-mounted device for a construction hoist according to claim 3, characterized in that, The fixed strip (330) side and the end of the square tube (321) are provided with square slot holes (331) that slide with the square rod (353).

5. A wall-mounted device for a construction hoist according to claim 3, characterized in that, The fixed connection portion (30) is provided in at least two sets, and the adjacent connecting plates (322) in the two sets of fixed connection portions (30) are fixedly connected.

6. A wall-mounted device for a construction hoist according to claim 1, characterized in that, The clamp (310) includes a clamp ring (311) and an ear plate (312). The ear plate (312) connects the clamp ring (311) and the end of the crossbeam (320). The inner wall of the clamp ring (311) is provided with a second planar structure (313) that cooperates with the first planar structure (210) on the surface of the support column (20).

7. A wall-mounted device for a construction hoist according to claim 1, characterized in that, A limit block (230) is fixedly installed at one end of the support column (20) near the connecting frame (10).

8. A wall-mounted device for a construction hoist according to claim 1, characterized in that, A reinforcing rod (110) is fixedly connected between the connecting frame (10) and the crossbeam (320).