A flexible hoisting device for modular integrated buildings

The flexible hoisting device and its support and hanger mechanism solve the problems of uneven hoisting points and center of gravity shift during the hoisting of modular integrated buildings, enabling automated, safe and efficient hoisting operations that can adapt to modular units of different sizes and shapes.

CN224981179UActive Publication Date: 2026-11-17CHINA STATE CONSTR HAILONG TECH CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522537836.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-28
Publication Date
2026-11-17
Estimated Expiration
2035-11-28

AI Technical Summary

Technical Problem

In existing technologies, the hoisting methods for modular integrated buildings suffer from problems such as uneven distribution of hoisting points, center of gravity shift, low efficiency of manual operation, insufficient safety, and difficulty in adapting to modular units of different sizes and shapes.

Method used

A flexible hoisting device is adopted, including a support mechanism, a moving mechanism, and a gantry mechanism. Multiple detachably connected second hook units of the gantry mechanism are raised and lowered synchronously or independently to adjust the spacing between the lifting points. Magnetic hooks and tilt adjustment devices are used to ensure the stability and safety of the hoisting process.

Benefits of technology

It has achieved automation and improved safety in the modular integrated building hoisting process, reduced the labor intensity and error risk of manual operation, adapted to modular units of different sizes and shapes, and improved hoisting efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224981179U_ABST
    Figure CN224981179U_ABST
Patent Text Reader

Abstract

This utility model relates to the field of prefabricated building hoisting equipment technology, and more particularly to a flexible hoisting device for modular integrated buildings. The flexible hoisting device includes a support mechanism, a moving mechanism, and a hanger mechanism. The moving mechanism is movably mounted on the support mechanism and can drive the hanger mechanism and the integrated building to move along a track. The hanger mechanism is connected to the moving mechanism and is driven to lift and lower by the moving mechanism. The hanger mechanism includes multiple second hook units detachably connected to the lifting lugs of the integrated building. Each second hook unit can lift and lower synchronously or independently to keep the integrated building stable during hoisting. The hanger mechanism is extendable and retractable along the length of the track to adjust the spacing between the second hook units. The hanger mechanism can adapt to integrated building modules of different sizes. By driving the lifting and lowering of the second hook units, it corrects the levelness of the integrated building and avoids structural deformation caused by uneven stress.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of prefabricated building hoisting equipment technology, and in particular to a flexible hoisting device for modular integrated buildings. Background Technology

[0002] With the rapid development of industrialized building and green building technologies, modular integrated construction (MiC) has become an important development direction in the prefabricated building field due to its advantages such as factory production, standardized construction, and high energy efficiency. In the production process of modular integrated construction, the demolding and hoisting of module units is a key process that directly affects production efficiency and product quality.

[0003] In existing technologies, modular units of integrated buildings are typically demolded and transported using overhead crane systems. The typical operation includes: manually positioning the hook to the preset lifting point, manually adjusting the lifting equipment's balance, leveling using a hand-operated hoist, and manually unloading the hook. However, this traditional hoisting method has significant limitations:

[0004] 1) Due to design differences, modular units of integrated buildings often exhibit problems such as uneven distribution of lifting points and offset of geometric center and center of gravity. Especially in the lifting scenarios of large volume and heavy mass modules, it is necessary to rely on manual repeated adjustment of the hook position to achieve balance, which is labor-intensive and inefficient.

[0005] 2) Traditional hoisting equipment relies on the operator's experience to judge the module's posture, which can easily lead to module tilting, collision, or structural damage due to leveling deviations, posing a significant construction safety risk.

[0006] 3) Existing hoisting systems are mostly rigid structures, which are difficult to adapt to modular units of different sizes and shapes. Utility Model Content

[0007] (a) Technical problems to be solved

[0008] In view of the above-mentioned shortcomings and deficiencies of the prior art, this utility model provides a flexible hoisting device for modular integrated buildings, which solves the technical problems of hoisting imbalance and center of gravity deviation caused by uneven distribution of hoisting points, as well as low efficiency and insufficient safety of manual operation.

[0009] (II) Technical Solution

[0010] To achieve the above objectives, the main technical solutions adopted by this utility model include:

[0011] This utility model provides a flexible hoisting device for modular integrated buildings, including a support mechanism, a moving mechanism, and a hanger mechanism. The moving mechanism is movably mounted on the track of the support mechanism and can drive the hanger mechanism and the integrated building to move along the track. The hanger mechanism is connected to the moving mechanism and is driven to lift by the moving mechanism. The hanger mechanism includes multiple second hook units that can be detachably connected to the lifting lugs of the integrated building. Each second hook unit can lift synchronously or independently to keep the integrated building stable during hoisting. The hanger mechanism can extend and retract along the length of the track to adjust the spacing between the second hook units.

[0012] Preferably, the hanger mechanism further includes a main beam unit and a telescopic unit; the main beam unit is detachably connected to the moving mechanism; the telescopic unit includes two telescopic beams, which are respectively disposed on both sides of the main beam unit and can move towards or away from each other; a plurality of second hook units are slidably installed on the bottom of the two telescopic beams and can slide along the length of the telescopic beams.

[0013] Preferably, the telescopic unit further includes at least one double piston rod cylinder; the cylinder body of the double piston rod cylinder is fixed on the main beam unit, and the piston rods at both ends are fixedly connected to the two telescopic beams respectively; by driving the double piston rod cylinder, the two telescopic beams can be driven to move towards or away from each other.

[0014] Preferably, the second hook unit includes a moving vehicle, a hoist, a second lifting rope, and a second hook; the moving vehicle is slidably mounted on the slide rail of the telescopic beam, the hoist is mounted on the moving vehicle, one end of the second lifting rope is wound around the output shaft of the hoist, and the other end is connected to the second hook, and the hoist drives the second hook to rise and fall by winding and unwinding the second lifting rope.

[0015] Preferably, the second hook unit further includes a tilt adjustment device; the tilt adjustment device is used to adjust the lifting and lowering amount of the hoist to level the integrated building.

[0016] Preferably, the second hook is a magnetic hook.

[0017] Preferably, the hanger mechanism further includes two guide columns; the two ends of the guide columns are connected to the main beam unit and the moving mechanism, and the guide columns can extend and retract in the vertical direction.

[0018] Preferably, the lifting mechanism further includes multiple lifting rings; the moving mechanism includes a first hook unit that corresponds one-to-one with the lifting rings and is detachably connected.

[0019] Preferably, the moving mechanism further includes a frame and multiple drive units; the frame includes two first main beams and two end beams connected to the ends of the two first main beams, and a first hook unit is fixedly connected to the first main beams; the drive units are installed on the end beams and are used to drive the frame to move along the track.

[0020] Preferably, the support mechanism includes two rail beams and multiple columns; the two rail beams are arranged in parallel and located above the first and second workstations, and each rail beam has a track on its top; the multiple columns are respectively supported below the two rail beams and are fixedly connected to the ground.

[0021] (III) Beneficial Effects

[0022] The beneficial effects of this utility model are:

[0023] This utility model discloses a flexible hoisting device for modular integrated buildings. The device uses a moving mechanism to drive the hoisting mechanism and the entire building module to move on a track, thus avoiding the need for multiple equipment to work together and repeated disassembly and assembly of hoisting tools in traditional methods.

[0024] The gantry mechanism can extend and retract horizontally to adjust the spacing between lifting points, adapting to integrated building modules of different sizes. The second hook unit of the gantry mechanism can be raised and lowered synchronously or independently. During hoisting, by driving the second hook unit to raise and lower, the spatial posture of the integrated building module can be adjusted, correcting its levelness to ensure the module remains stable during transport. This avoids structural deformation caused by uneven stress, eliminates the need for manual operation, and reduces the risk of human error. Attached Figure Description

[0025] Figure 1 This is a schematic diagram of the overall structure of a flexible hoisting device for modular integrated buildings according to the present invention;

[0026] Figure 2 This is a side view schematic diagram of a flexible hoisting device for modular integrated buildings according to the present invention;

[0027] Figure 3 This is a structural diagram of the moving mechanism and the lifting mechanism;

[0028] Figure 4 This is a schematic diagram of the moving mechanism;

[0029] Figure 5 This is a schematic diagram of the hanger mechanism;

[0030] Figure 6 for Figure 5 Enlarged view of point A in the middle;

[0031] Figure 7 This is a front view diagram of the second hook when it is not connected to the integrated building.

[0032] Figure 8 This is a front view diagram showing the connection between the hook of the second hook and the integrated building.

[0033] [Explanation of Labels in the Attached Image]

[0034] 1: Supporting mechanism; 11: Rail bearing beam; 111: Rail; 12: Column; 13: First connecting beam;

[0035] 2: Moving mechanism; 21: Frame; 211: First main beam; 212: End beam; 213: Second connecting beam; 22: Drive unit; 221: Traveling wheel; 222: First drive motor; 23: First hook unit; 231: Winch; 232: First lifting rope; 233: First hook;

[0036] 3: Hanger mechanism; 31: Main beam unit; 311: Second main beam; 312: Third connecting beam; 32: Telescopic unit; 321: Telescopic beam; 322: Guide rod; 323: Double piston rod cylinder; 3231: Cylinder body; 3232: Piston rod; 33: Second hook unit; 331: Moving vehicle; 3311: Second drive motor; 332: Hoist; 333: Second lifting rope; 334: Second hook; 3341: Hook body; 3342: Magnetic suction element; 3343: Outer shell; 34: Guide column; 35: Lifting ring; 36: Support leg;

[0037] a: Integrated building; a1: Lifting lug; b: First workstation; c: Second workstation. Detailed Implementation

[0038] To better explain and facilitate understanding of this utility model, the present utility model will be described in detail below with reference to the accompanying drawings and specific embodiments.

[0039] To better understand the above technical solutions, exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present invention are shown in the drawings, it should be understood that the present invention can be implemented in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided so that the present invention can be understood more clearly and thoroughly, and that the scope of the present invention can be fully conveyed to those skilled in the art.

[0040] Example

[0041] like Figure 1As shown, this embodiment provides a flexible hoisting device for modular integrated buildings. The flexible hoisting device includes a support mechanism 1, a moving mechanism 2, and a hanger mechanism 3. The moving mechanism 2 is movably mounted on the track 111 of the support mechanism 1 and can drive the hanger mechanism 3 and the integrated building a to move along the track 111. The hanger mechanism 3 is connected to the moving mechanism 2 and is driven to lift and lower by the moving mechanism 2. The hanger mechanism 3 includes multiple second hook units 33 that can be detachably connected to the lifting lugs a1 of the integrated building a. Each second hook unit 33 can lift and lower synchronously or independently to keep the integrated building a stable during hoisting. The hanger mechanism 3 is extendable and retractable along the length of the track 111 to adjust the spacing between the second hook units 33. By using the moving mechanism 2 to drive the hanger mechanism 3 and the entire building module to move on the track 111, the need for multiple equipment to work together and repeated disassembly and assembly of hoisting tools in traditional methods is avoided. The hanger mechanism 3 can extend and retract horizontally to adjust the spacing between the lifting points to adapt to integrated building a modules of different sizes. The second hook unit 33 of the gantry mechanism 3 can be raised and lowered synchronously or independently. During the hoisting process, by driving the second hook unit 33 to raise and lower, the spatial posture of the integrated building module a can be adjusted and its levelness corrected so that the module is in a stable state during hoisting, avoiding structural deformation caused by uneven force, eliminating the need for manual operation and reducing the risk of human error.

[0042] like Figure 3 and Figure 5 As shown, the hanger mechanism 3 also includes a main beam unit 31 and a telescopic unit 32. The main beam unit 31 is detachably connected to the moving mechanism 2. The telescopic unit 32 includes two telescopic beams 321, which are respectively disposed on both sides of the main beam unit 31 and can move towards or away from each other. Multiple second hook units 33 are slidably installed on the bottom of the two telescopic beams 321 and can slide along the length of the telescopic beams 321.

[0043] Preferably, the main beam unit 31 includes two parallel second main beams 311 and a plurality of third connecting beams 312 spaced apart along its length direction, with the two ends of the third connecting beams 312 respectively fixedly connected to the two second main beams 311.

[0044] The telescopic unit 32 is also provided with multiple guide rods 322. One end of the guide rod 322 is fixedly connected to the telescopic beam 321, and the other end slides through the telescopic channel opened on the third connecting beam 312. The telescopic beam 321 is telescopically extended and retracted by the sliding of the guide rod 322 in the telescopic channel.

[0045] Preferably, the telescopic unit 32 further includes at least one double-piston rod cylinder 323. The cylinder body 3231 of the double-piston rod cylinder 323 is fixed to the main beam unit 31, and the piston rods 3232 at both ends are fixedly connected to the two telescopic beams 321 respectively. By driving the double-piston rod cylinder 323, the two telescopic beams 321 can be moved towards or away from each other.

[0046] In this embodiment, two double piston rod cylinders 323 are provided, located at both ends of the main beam unit 31 respectively.

[0047] like Figure 6 As shown, the second hook unit 33 includes a moving carriage 331, a hoist 332, a second lifting rope 333, and a second hook 334. The moving carriage 331 is slidably mounted on the slide rail of the telescopic beam 321. The hoist 332 is mounted on the moving carriage 331. One end of the second lifting rope 333 is wound around the output shaft of the hoist 332, and the other end is connected to the second hook 334. The hoist 332 drives the second hook 334 to rise and fall by winding and unwinding the second lifting rope 333. A second drive motor 3311 is mounted on the moving carriage 331. The second drive motor 3311 drives the moving carriage 331 to slide along the slide rail of the telescopic beam 321. Each second hook unit 33 can independently adjust its position in the horizontal direction. The second hook unit 33 can be aligned with the lifting lugs a1 of integrated building modules a of different sizes and different lifting point spacings, improving the efficiency of hoisting preparation and adaptability to different products.

[0048] Preferably, the second hook 334 is a magnetic hook. For example... Figure 7 and Figure 8 As shown, the second hook 334 includes a housing 3343, a hook body 3341, a magnetic chuck 3342, and a third drive motor (not shown in the figure). The hook body 3341 is rotatably connected to the housing 3343 via a rotating shaft. The magnetic chuck 3342 is fixedly installed on the housing 3343 and located beside the rotation path of the hook body 3341. The third drive motor is fixed inside the housing 3343, and its output end is connected to the rotating shaft of the hook body 3341 for driving the hook body 3341 to rotate relative to the housing 3343.

[0049] During hoisting, the second hook 334 is first moved to the vicinity of the lifting lug a1 using a moving vehicle 331 and a hoist 332. When the magnetic suction component 3342 approaches the lifting lug a1 of the integrated building module a, it first magnetically attracts the lug a1, achieving initial connection and positioning. This process effectively prevents the hook from swaying in the air, improving the convenience and safety of hook operation. After the magnetic attraction is completed, the third drive motor starts, driving the hook body 3341 to rotate from the open state to the closed state, finally passing through the hole in the lifting lug a1 and forming a mechanical interlock with the magnetic suction component 3342. The magnetic hook enhances the safety and reliability of the hoisting connection, avoiding the risk of detachment that may occur during swaying or power failure.

[0050] Preferably, the second hook unit 33 further includes a tilt adjustment device (not shown in the figure), which is used to adjust the extension and retraction of the hoist 332 to level the integrated building a. The tilt adjustment device is installed at one end of the telescopic beam 321. The tilt adjustment device includes a visual detector, a gyroscope, and a tilt sensor. The position of the lifting lug a1 of the integrated building a is identified by the visual detector, causing the second drive motor 3311 to drive the moving vehicle 331 to move directly above the lifting point. Through the cooperation of the gyroscope, tilt sensor, and hoist 332, any tilting of the integrated building a can be corrected, ensuring that it remains level and stable throughout the entire lifting process. This not only prevents structural deformation of the integrated building a due to uneven stress but also improves the safety of the lifting operation.

[0051] It should be noted that this embodiment does not involve any improvement or use of the computer program itself. The automatic alignment and automatic leveling functions implemented by the device are achieved through the combination and coordinated operation of existing hardware components such as visual detection, gyroscope, tilt sensor, drive motor, and hoist 332. Any control logic involving the above functions is considered to be executed by mature and universal control units or circuit systems in the prior art, and does not constitute any innovation of the computer program content in this utility model.

[0052] To enhance the stability of the suspension mechanism 3 during the lifting process, such as Figure 2 and Figure 5 As shown, the lifting mechanism 3 also includes two guide columns 34. The two ends of the guide columns 34 are connected to the main beam unit 31 and the moving mechanism 2. The guide columns 34 can extend and retract in the vertical direction. The guide columns 34 can limit the horizontal swaying and torsion of the lifting mechanism 3 during the lifting process, ensuring that it moves smoothly along the preset vertical trajectory and improving the safety of the lifting operation.

[0053] Preferably, the lifting mechanism 3 further includes multiple lifting rings 35, which are fixedly connected to the top of the main beam unit 31. The moving mechanism 2 is detachably connected to the lifting mechanism 3 through the lifting rings 35. This enables quick connection and separation between the two, facilitating the replacement and maintenance of the lifting mechanism 3. At the same time, the lifting force is evenly applied to the main beam unit 31 through the lifting rings 35, thereby ensuring the stability and safety of the entire lifting process.

[0054] like Figure 3 and Figure 4 As shown, the moving mechanism 2 includes a frame 21 and multiple drive units 22. The frame 21 includes two first main beams 211 and two end beams 212 connected to the ends of the two first main beams 211. The drive units 22 are mounted on the end beams 212 and include wheels 221 and a first drive motor 222. The first drive motor 222 drives the wheels 221 to rotate, thereby moving the entire frame 21 along the track 111.

[0055] Furthermore, the frame 21 also includes a plurality of second connecting beams 213, which laterally fix the two first main beams 211. The second connecting beams 213 are used to enhance the overall stability of the frame 21.

[0056] like Figure 4 As shown, the moving mechanism 2 also includes a first hook 233 unit 23 that corresponds one-to-one with the lifting ring 35 of the hanger mechanism 3 and is detachably connected. The first hook 233 unit 23 is fixedly connected to the first main beam 211.

[0057] Furthermore, the first hook 233 unit 23 includes a winch 231, a first lifting rope 232, and a first hook 233. The winch 231 is fixedly installed on the second connecting beam 213. One end of the first lifting rope 232 is wound around the output shaft of the winch 231, and the other end is connected to the first hook 233. The winch 231 drives the first hook 233 to rise and fall by winding and unwinding the first lifting rope 232.

[0058] It should be noted that the first hook unit 233 is used to realize the main load-bearing and vertical lifting of the lifting mechanism 3 and the integrated building module a being lifted, while the second hook unit 33 is used to adjust the integrated building module a horizontally before lifting and during the lifting process.

[0059] like Figure 1 and Figure 2 As shown, the support mechanism 1 includes two rail beams 11 and multiple columns 12. The two rail beams 11 are arranged in parallel and are located above the first work station b and the second work station c. Each rail beam 11 is provided with a rail 111 on its top. The multiple columns 12 are respectively supported below the two rail beams 11 and are fixedly connected to the ground.

[0060] Furthermore, the support mechanism 1 also includes multiple first connecting beams 13, which are laterally fixed to the two rail bearing beams 11 to enhance the stability of its overall structure.

[0061] The working process of the flexible hoisting device for modular integrated buildings is as follows:

[0062] First, the moving mechanism 2 and the lifting mechanism 3 move to above the first work station b, and activate the double piston rod cylinder 323 of the telescopic unit 32 to drive the two telescopic beams 321 to move in opposite directions, thereby adjusting the width of the lifting mechanism 3 to be slightly larger than the size of the integrated building a to be lifted; then, the moving mechanism 2 drives the lifting mechanism 3 to descend to an appropriate height, and drives the moving carriages 331 of each second hook unit 33 to slide along the telescopic beams 321, so that all the second hooks 334 move to directly above each lifting lug a1, and lower the second hooks 334; then, when the magnetic suction component 3342 below the magnetic second hook 334 approaches the lifting lug a1, it first adheres to the lifting lug a1 by magnetic force. The third drive motor of the second hook 334 starts, driving the hook body 3341 to rotate, so that it passes through the lifting lug a1 and locks with the magnetic suction piece 3342 above. The tilt adjustment device detects the levelness of the building module and adjusts the retraction and extension of each hoist 332. Next, the moving mechanism 2 drives the entire gantry mechanism 3 and the building module to rise, and transports the building module horizontally from the first work station b to above the second work station c along the track 111 at the top of the support mechanism 1. Finally, the moving mechanism 2 drives the gantry mechanism 3 to descend, the third drive motor drives the hook body 3341 to rotate and disengage from the magnetic suction piece 3342, and then the hoist 332 retracts the second lifting rope 333, completing the unhooking.

[0063] In the description of this utility model, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of this utility model, "multiple" means two or more, unless otherwise explicitly specified. In this utility model, unless otherwise explicitly specified and limited, terms such as "installed," "connected," "joined," and "fixed" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral part; a mechanical connection or an electrical connection; a direct connection or an indirect connection through an intermediate medium; or a connection within two components or an interaction between two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model according to the specific circumstances.

[0064] In this utility model, unless otherwise explicitly specified and limited, "above" or "below" the second feature can mean that the first feature is in direct contact with the second feature, or that the first feature is in indirect contact with the second feature through an intermediate medium. Furthermore, "above," "on top of," and "over" the second feature can mean that the first feature is directly above or diagonally above the second feature, or simply indicates that the first feature is at a higher horizontal level than the second feature. "Below," "below," and "beneath" the second feature can mean that the first feature is directly below or diagonally below the second feature, or simply indicates that the first feature is at a lower horizontal level than the second feature.

[0065] In the description of this specification, the terms "one embodiment," "some embodiments," "embodiment," "example," "specific example," or "some examples," etc., refer to specific features, structures, materials, or characteristics described in connection with that embodiment or example, which are included in at least one embodiment or example of the present invention. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples. Moreover, without contradiction, those skilled in the art can combine and integrate the different embodiments or examples described in this specification, as well as the features of different embodiments or examples.

[0066] Although embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and should not be construed as limiting the present invention. Those skilled in the art can make modifications, alterations, substitutions and variations to the above embodiments within the scope of the present invention.

Claims

1. A flexible hoisting device for modular integrated construction, characterized in that, It includes a support mechanism (1), a moving mechanism (2), and a hanging mechanism (3); The moving mechanism (2) is movably mounted on the track (111) of the supporting mechanism (1) and can drive the hanging mechanism (3) and the integrated building (a) to move along the track (111); The hanging mechanism (3) is connected to the moving mechanism (2) and is driven to lift by the moving mechanism (2); The gantry mechanism (3) includes a plurality of second hook units (33) that can be detachably connected to the lifting lugs (a1) of the integrated building (a). Each second hook unit (33) can be raised and lowered synchronously or independently to keep the integrated building (a) stable during hoisting. The gantry mechanism (3) is extendable along the length of the track (111) to adjust the spacing between the second hook units (33).

2. The flexible hoisting device for modular integrated buildings as described in claim 1, characterized in that: The hanger mechanism (3) also includes a main beam unit (31) and a telescopic unit (32); The main beam unit (31) is detachably connected to the moving mechanism (2); The telescopic unit (32) includes two telescopic beams (321), which are respectively disposed on both sides of the main beam unit (31) and can move towards or away from each other; Multiple second hook units (33) are slidably mounted on the bottom of the two telescopic beams (321) and are able to slide along the length of the telescopic beams (321).

3. The flexible hoisting device for modular integrated buildings as described in claim 2, characterized in that: The telescopic unit (32) also includes at least one double piston rod cylinder (323). The cylinder body (3231) of the double piston rod cylinder (323) is fixed on the main beam unit (31), and the piston rods (3232) at both ends are fixedly connected to the two telescopic beams (321) respectively. By driving the double piston rod cylinder (323), the two telescopic beams (321) can be moved towards or away from each other.

4. The flexible hoisting device for modular integrated buildings as described in claim 2, characterized in that: The second hook unit (33) includes a mobile vehicle (331), a hoist (332), a second hoisting rope (333), and a second hook (334); The mobile vehicle (331) is slidably mounted on the slide rail of the telescopic beam (321). The hoist (332) is mounted on the mobile vehicle (331). One end of the second hoisting rope (333) is wound around the output shaft of the hoist (332), and the other end is connected to the second hook (334). The hoist (332) drives the second hook (334) to rise and fall by winding and unwinding the second hoisting rope (333).

5. The flexible hoisting device for modular integrated buildings as described in claim 4, characterized in that: The second hook unit (33) also includes an angle adjustment device; The tilt adjustment device is used to adjust the take-up and take-down amount of the hoist (332) to level the integrated building (a).

6. The flexible hoisting device for modular integrated buildings as described in claim 4, characterized in that: The second hook (334) is a magnetic hook.

7. The flexible hoisting device for modular integrated buildings as described in claim 2, characterized in that: The hanger mechanism (3) also includes two guide columns (34); The two ends of the guide column (34) are connected to the main beam unit (31) and the moving mechanism (2), and the guide column (34) can extend and retract in the vertical direction.

8. The flexible hoisting device for modular integrated buildings as described in claim 1, characterized in that: The hanger mechanism (3) also includes multiple lifting rings (35); The moving mechanism (2) includes a first hook unit (23) that corresponds one-to-one with the lifting ring (35) and is detachably connected.

9. The flexible hoisting device for modular integrated buildings as described in claim 8, characterized in that: The moving mechanism (2) also includes a frame (21) and multiple drive units (22); The frame (21) includes two first main beams (211) and two end beams (212) connected to the ends of the two first main beams (211), and the first hook unit (23) is fixedly connected to the first main beams (211); The drive unit (22) is mounted on the end beam (212) and is used to drive the frame (21) to move along the track (111).

10. The flexible hoisting device for modular integrated buildings as described in claim 1, characterized in that: The support mechanism (1) includes two rail bearing beams (11) and multiple columns (12). The two rail support beams (11) are arranged in parallel and located above the first and second work stations. The top of each rail support beam (11) is provided with the rail (111). The multiple columns (12) are respectively supported under the two rail beams (11) and are fixedly connected to the ground.