A suspended lifting platform used in the construction of a vertical pipeline structure
By designing a suspended lifting platform suitable for vertical pipe structures, using aerospace-grade aluminum and modular design, the problems of insufficient load-bearing capacity and low safety of suspended platforms are solved, achieving high load capacity, rapid assembly and stable lifting.
Patent Information
- Application Number
- CN202522644700.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-13
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-12-13
AI Technical Summary
Existing suspended lifting platforms have problems such as poor main load-bearing capacity, poor controllability of diameter limitation, and low safety in the construction of blast furnaces and hot blast stoves.
A suspended lifting platform suitable for vertical pipeline construction was designed. It is made of aerospace-grade aluminum and includes a main lifting structure, modular installation platform and controllable lifting components. The platform is kept stable through modular design and polyurethane corner wheels, and can be easily assembled and lifted.
It improves the platform's load-bearing capacity, ensures safety and controllability, features flexible load design, rapid assembly, lightweight individual components, and a high safety factor, making it suitable for construction needs of different diameters and sizes.
Smart Images

Figure CN224981190U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to cement kiln construction equipment, and in particular to a suspended lifting platform used in the construction of vertical pipeline structures. Background Technology
[0002] Currently, during the construction of blast furnaces, hot blast stoves, and other furnace bodies, the typical construction sequence is to first install the furnace shell and frame structures, followed by the installation of cooling and furnace roof equipment. When installing the internal water-cooled walls, carbon brick and refractory brick masonry, or spraying, the traditional construction method involves erecting a custom-designed suspended platform layer by layer, suitable for cyclone furnaces and limestone vertical kilns. Designed for different diameters, sizes, and loads, the platform can be assembled on the surface or lowered from the top opening after assembly. The platform is designed for operation by a person simply standing on it.
[0003] Publication No.: CN120867510A A furnace equipment installation and operation platform and construction method are described. The operation platform includes: main beams, radially uniformly arranged, with the center end of each main beam welded and fixed to a central fixed steel plate; top supports, installed on the outer ends of each main beam, capable of telescopic movement on the main beams; support beams, set between each main beam; treads, laid on the main beams and top supports; temporary lifting lugs, welded to the upper edge of the furnace top plate; and an electric hoist, with one end of its chain connected to the temporary lifting lug and the other end connected to the main beam, its sprocket set at a height easily accessible to construction personnel on the platform. The construction method involves fixing the operation platform to the upper edge of the already constructed furnace shell, and using the electric hoist to lift the operation platform layer by layer on the furnace shell for the installation of furnace equipment.
[0004] The aforementioned comparative documents exhibit shortcomings such as poor main load-bearing capacity, limited specified controllable diameter, and low controllability and safety. Utility Model Content
[0005] The purpose of this invention is to provide a suspended lifting platform for use in the construction of vertical pipeline structures. This is a custom-designed suspended platform suitable for cyclone separators, limestone vertical kilns, and steel furnaces. It is designed for different diameters, sizes, and loads. The platform can be assembled on the surface or lowered from the top opening after assembly. The platform is designed for operation by a person on it during the construction of vertical pipeline structures.
[0006] The technical solution adopted by this utility model to solve its technical problem is: a suspended lifting platform used in the construction of vertical pipeline structures, including a main hoisting structure, a mounting plate structure set on the upper part of the main hoisting structure, and a controllable hoisting assembly connected to the main hoisting structure. The main hoisting structure is characterized in that: the main hoisting structure includes a hexagonal central connecting frame structure, an outer connecting frame structure set outside the central connecting frame structure, a main support assembly set between the outer connecting frame structure and the central connecting frame structure, and a hoisting installation rod assembly set between the outer connecting frame structure and the central connecting frame structure. The controllable hoisting assembly is connected to the upper part of the hoisting installation rod assembly.
[0007] The aforementioned mounting pedal structure includes a central mounting pedal located on the central connecting frame structure, a peripheral mounting pedal located between the outer connecting frame structure and the central connecting frame structure, and an outer edge mounting pedal located on the outer side of the outer connecting frame structure.
[0008] The main support assembly includes a central bearing rod group located inside the central connecting frame structure, an outer bearing rod group located between the central connecting frame structure and the outer end connecting frame structure, and an outer end limiting rod group located outside the outer end connecting frame structure.
[0009] The center mounting pedal, the outer mounting pedal, and the upper part of the outer edge mounting pedal are all provided with anti-slip texture.
[0010] The central connecting frame structure includes a first pipe fitting connecting angle seat that is spliced into a hexagon and connects adjacent central connecting rods. The outer end connecting frame structure includes an outer end connecting rod group that is spliced into a hexagon and a second pipe fitting connecting angle seat that connects adjacent central connecting rods. The first pipe fitting connecting angle seat and the second pipe fitting connecting angle seat are arranged radially perpendicularly.
[0011] Each outer end limit rod assembly is equipped with a polyurethane corner wheel on its outer side.
[0012] The beneficial effects of this utility model are as follows: The structure is typically designed with a net load of 6000lb and uses 6 hooks (which may vary depending on customer requirements). All structural components are made of aerospace-grade aluminum (6061-T6), with a minimum safety factor of 4:1. The hooks are easy to install, and the space around the hooks allows all cables to be cleared from the work platform. The platform is easy to control with buttons. The lifting platform adopts a modular design, which is easy to assemble. The weight of each component is less than 50lb and no longer than 10' (assembly can be completed in 1 hour) (each electric hook weighs 100lb). Three lever switches control polyurethane corner wheels installed at different positions under the platform to maintain the stability of the platform and protect the newly laid refractory bricks.
[0013] The present invention will be described in more detail below with reference to the accompanying drawings and embodiments. Attached Figure Description
[0014] Figure 1 This is a schematic diagram of the structure of this utility model.
[0015] Figure 2 for Figure 1 A schematic diagram of the main structure for hoisting.
[0016] Figure 3 for Figure 1 A schematic diagram of the structure in which the pedal is installed in the center.
[0017] Figure 4 for Figure 1 A schematic diagram of the structure of the pedals installed on the middle and outer perimeter.
[0018] Figure 5 for Figure 1 A schematic diagram of the structure of the pedal installed on the outer edge.
[0019] Figure 6 for Figure 1 Schematic diagram of the first pipe fitting connecting angle seat.
[0020] Figure 7 for Figure 1 Schematic diagram of the second pipe fitting connecting angle seat.
[0021] Figure 8 for Figure 1 A schematic diagram of the extended state of the main structure of the hoisting unit.
[0022] Figure 9 This is a structural diagram of another type of hoisting main structure.
[0023] Figure 10 This is a schematic diagram of the usage state 1 of this utility model.
[0024] Figure 11 This is a schematic diagram of the second usage state of this utility model.
[0025] Figure 12 This is a schematic diagram of the third usage state of this utility model.
[0026] In the diagram: 1. Controllable hoisting assembly, 2. Central connecting rod, 3. First pipe fitting connecting angle seat, 4. Outer end connecting rod assembly, 5. Second pipe fitting connecting angle seat, 6. Central mounting plate, 7. Peripheral mounting plate, 8. Outer edge mounting plate, 9. Central bearing rod assembly, 10. Outer bearing rod assembly, 11. Outer end limiting rod assembly, 12. Anti-slip texture, 13. Polyurethane corner wheel, 14. Hoisting installation rod assembly, 15. Hoisting point, 16. First upper end mounting sleeve, 17. Second upper end mounting sleeve, 18. Connecting sleeve. Detailed Implementation
[0027] The terms "upper," "lower," "inner," "outer," "front end," "rear end," "both ends," "one end," and "the other end" used in the application text to indicate the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings. They are used solely for the convenience of describing the present invention and for simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance.
[0028] In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the terms "installed," "equipped with," and "connected," etc., should be interpreted broadly. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be a connection within two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.
[0029] Example 1, as Figure 1-12 As shown, a suspended lifting platform used in the construction of a vertical pipeline structure includes a main lifting structure, an assembly-type installation platform structure set on the upper part of the main lifting structure, and a controllable lifting assembly 1 connected to the main lifting structure. The main lifting structure includes a hexagonal central connecting frame structure, an outer end connecting frame structure located outside the central connecting frame structure, a main support assembly located between the outer end connecting frame structure and the central connecting frame structure, and a lifting installation rod assembly 14 located between the outer end connecting frame structure and the central connecting frame structure. The controllable lifting assembly is connected to a lifting point 15 set on the upper part of the lifting installation rod assembly. The central connecting frame structure includes a first pipe fitting connecting angle seat 3 spliced in a hexagonal shape and connecting adjacent central connecting rods 2. The outer end connecting frame structure includes a second pipe fitting connecting angle seat 5 spliced in a hexagonal shape and connecting adjacent central connecting rods 4. The first pipe fitting connecting angle seat and the second pipe fitting connecting angle seat are arranged radially and perpendicularly.
[0030] The first pipe fitting connecting angle seat 3 and the second pipe fitting connecting angle seat 5 are provided with a first upper end mounting sleeve 16 and a second upper end mounting sleeve 17. The first upper end mounting sleeve 16 and the second upper end mounting sleeve 17 are connected to a hoisting installation rod assembly 14.
[0031] A sleeve 18 is provided on the outside of the central connecting rod 2, the outer end connecting rod group 4, and the outer end connecting rod group 4 to connect with the central bearing rod group 9, the outer bearing rod group 10 and the outer end limiting rod group 11 of the main support assembly. A variable diameter central bearing rod group 9 and outer bearing rod group 10 are also provided to connect with the outer end limiting rod group 11.
[0032] The aforementioned mounting pedal structure includes a central mounting pedal 6 located on the central connecting frame structure, a peripheral mounting pedal 7 located between the outer connecting frame structure and the central connecting frame structure, and an outer edge mounting pedal 8 located on the outer side of the outer connecting frame structure.
[0033] The main support assembly includes a central bearing rod group 9 located inside the central connecting frame structure, an outer bearing rod group 10 located between the central connecting frame structure and the outer end connecting frame structure, and an outer end limiting rod group 11 located outside the outer end connecting frame structure.
[0034] The first pipe fitting connecting angle seat 3 and the second pipe fitting connecting angle seat 5 are provided with a first upper end mounting sleeve 16 and a second upper end mounting sleeve 17. The first upper end mounting sleeve 16 and the second upper end mounting sleeve 17 are connected to a hoisting installation rod assembly 14.
[0035] A connecting sleeve 18 is provided on the outside of the central connecting rod 2, the outer end connecting rod group 4, and the outer end connecting rod group 4 to connect with the central bearing rod group 9, the outer bearing rod group 10, and the outer end limiting rod group 11 of the main support assembly. A variable diameter central bearing rod group 9, outer bearing rod group 10, and outer end limiting rod group 11 are also provided for connection.
[0036] The center mounting pedal, the outer mounting pedal, and the outer edge mounting pedal are all provided with anti-slip texture 12.
[0037] Each outer end limit rod assembly is equipped with a polyurethane corner wheel 13.
[0038] This structure is typically designed for a net load of 6000 lbs and uses 6 hooks (the number may vary depending on customer requirements). All structural components are made of aerospace-grade aluminum (6061-T6), with a minimum safety factor of 4:1. Hook installation is simple, and the space around the hooks allows all cables to be cleared from the work platform. The platform is easy to control with simple buttons. The lifting platform adopts a modular design, which is easy to assemble. All individual components weigh less than 50 lbs and are no longer than 10 inches (assembly can be completed in 1 hour). (Electric hooks weigh 100 lbs each). Three lever switches control polyurethane casters installed at different positions under the platform to maintain platform stability and protect newly laid refractory bricks.
[0039] The above embodiments are merely descriptions of preferred embodiments of the present utility model and are not intended to limit the scope of the present utility model. Various modifications and improvements to the technical solutions of the present utility model made by those skilled in the art without departing from the spirit of the present utility model should fall within the protection scope defined by the claims of the present utility model.
[0040] The parts not covered in this utility model are the same as or can be implemented using existing technologies.
Claims
1. A suspended hoisting platform used in vertical pipeline structure construction, comprising a hoisting main structure, an attached mounting footboard structure arranged at the upper part of the hoisting main structure, and a controllable hoisting assembly connected with the hoisting main structure, characterized in that: The hoisting main structure includes a hexagonal central connecting frame structure, an outer connecting frame structure located outside the central connecting frame structure, a main support assembly located between the outer connecting frame structure and the central connecting frame structure, and a hoisting installation rod assembly located between the outer connecting frame structure and the central connecting frame structure. The controllable hoisting assembly is connected to the upper part of the hoisting installation rod assembly.
2. A suspended hoist platform for use in the construction of a vertical pipe structure as defined in claim 1, characterized in that: The aforementioned mounting pedal structure includes a central mounting pedal located on the central connecting frame structure, a peripheral mounting pedal located between the outer connecting frame structure and the central connecting frame structure, and an outer edge mounting pedal located on the outer side of the outer connecting frame structure.
3. The suspended hoist platform for use in the construction of a vertical pipe structure of claim 1, wherein: The main support assembly includes a central bearing rod group located inside the central connecting frame structure, an outer bearing rod group located between the central connecting frame structure and the outer end connecting frame structure, and an outer end limiting rod group located outside the outer end connecting frame structure.
4. The suspended hoist platform for use in the construction of a vertical pipe structure of claim 2, wherein: The center mounting pedal, the outer mounting pedal, and the upper part of the outer edge mounting pedal are all provided with anti-slip texture.
5. The suspended lifting platform used in the construction of vertical pipeline structures as described in claim 1, characterized in that: The central connecting frame structure includes a first pipe fitting connecting angle seat that is spliced into a hexagon and connects adjacent central connecting rods. The outer end connecting frame structure includes an outer end connecting rod group that is spliced into a hexagon and a second pipe fitting connecting angle seat that connects adjacent central connecting rods. The first pipe fitting connecting angle seat and the second pipe fitting connecting angle seat are arranged radially perpendicularly.
6. The suspended lifting platform used in the construction of vertical pipeline structures as described in claim 3, characterized in that: Each outer end limit rod assembly is equipped with a polyurethane corner wheel on its outer side.
Citation Information
Patent Citations
In-furnace equipment installation operation platform and construction method
CN120867510A