Climate control system for regulating interior space
By combining thermal energy storage components and multiple coolers, and utilizing controllers to regulate operating levels and cryogenic fluid distribution, the problem of excess electrical load during peak load periods in commercial building climate control systems is solved, achieving electrical load balancing and the utilization of additional capacity.
Patent Information
- Application Number
- CN202520907083.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Priority Date
- 2024-05-08
- Filing Date
- 2025-05-08
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-05-08
AI Technical Summary
Climate control systems in commercial buildings require a large amount of electrical load capacity to be reserved during peak load periods, resulting in unused electrical load capacity during off-peak periods and increasing operating costs.
By combining thermal energy storage (TES) components with multiple coolers, the operating level of the coolers and the distribution of cryogenic fluid are regulated by a controller to balance electrical load demand and release unused electrical load capacity for monetization or other uses.
This reduces the total electrical load demand of the climate control system, achieves electrical load balance and optimization, and increases the utilization value of additional capacitance.
Smart Images

Figure CN224984201U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to a climate control system for regulating interior spaces. Background Technology
[0002] Commercial buildings such as office buildings, retail stores, and data centers draw significant amounts of electricity from the local public power grid. Therefore, building owners and / or operators (collectively referred to as "building operators") are often keen to reduce the building's total electrical load to lower operating costs. Indoor climate control is typically an important (if not the largest) component of a commercial building's total electrical load demand. Therefore, the design and operation of building climate control systems can be a significant factor in reducing a building's electricity footprint. Utility Model Content
[0003] Some embodiments disclosed herein relate to a climate control system for regulating an interior space. In some embodiments, the climate control system includes an interior space heat exchange loop configured to circulate working fluid to cool airflow directed into the interior space. Furthermore, the climate control system includes a cooler configured to cool the working fluid. Further, the climate control system includes a thermal energy storage (TES) component that also includes a cryogenic fluid source and a heat exchanger coupled to the interior space heat exchange loop such that the heat exchanger is located upstream of the cooler along the interior space heat exchange loop. The heat exchanger is configured to receive fluid from the cryogenic fluid source to cool the working fluid, thereby supplementing the output cooling capacity of the cooler.
[0004] In some embodiments, the climate control system includes an interior space heat exchange loop configured to circulate working fluid to cool airflow directed into the interior space. Furthermore, the climate control system includes a plurality of coolers configured to cool the working fluid. Further, the climate control system includes a thermal energy storage (TES) component thermally coupled to the interior space heat exchange loop via a plurality of heat exchangers arranged along the interior space heat exchange loop. Still further, the climate control system includes a controller communicatively coupled to the plurality of coolers and the TES component. The controller is configured to regulate the output cooling capacity of the plurality of coolers and to regulate the distribution of cooling capacity from the TES component to maintain the electrical load of the climate control system at or below a baseline electrical load.
[0005] Some embodiments disclosed herein relate to a method for operating a climate control system for a building. In some embodiments, the method includes: (a) receiving weather data for a future day for the geographic area where the building is located. Furthermore, the method includes: (b) determining the total available cooling capacity of thermal energy storage (TES) components of the climate control system. Further, the method includes: (c) determining a baseline electrical load for operating the climate control system, based at least on the weather data and the total available cooling capacity of the TES components. Still further, the method includes: (d) determining the output cooling capacity of a plurality of coolers in the climate control system, and a cooling capacity allocation from the TES components, the allocation being configured to meet the cooling needs of the building when the electrical load of the climate control system is equal to or less than the baseline electrical load.
[0006] The embodiments described herein include combinations of features and characteristics designed to address various drawbacks associated with some existing apparatuses, systems, and methods. The foregoing provides a fairly broad overview of the features and technical characteristics of the disclosed embodiments to facilitate a better understanding of the following detailed description. These various features and characteristics, as well as other features, will be apparent to those skilled in the art upon reading the following detailed description and referring to the accompanying drawings. It should be understood that this disclosure can be readily used as a basis for modifying or designing other structures to achieve the same purpose as the disclosed embodiments. It should also be recognized that such equivalent constructions do not depart from the spirit and scope of the principles disclosed herein. Attached Figure Description
[0007] A detailed description of the various embodiments will now be given with reference to the accompanying drawings, in which:
[0008] Figure 1 This is a schematic diagram of a climate control system including a thermal energy storage component according to some embodiments disclosed herein;
[0009] Figure 2 Based on some embodiments disclosed herein Figure 1 A schematic diagram of the cooler in the climate control system;
[0010] Figure 3 The embodiments disclosed herein illustrate the relationship between output cooling capacity and outdoor ambient temperature. Figure 1 A graph showing the electrical load consumed by one of the coolers in the climate control system;
[0011] Figure 4 This is an illustration based on some embodiments disclosed herein. Figure 1 A graph showing the example electrical load consumed per unit time during the peak period of an example day by the climate control system;
[0012] Figure 5This is a schematic diagram of a climate control system including a thermal energy storage component according to some embodiments disclosed herein;
[0013] Figure 6 This is an illustration based on some embodiments disclosed herein. Figure 5 A graph showing the example electrical load consumed per unit time during an example day by the climate control system; and
[0014] Figure 7 This is a flowchart of a method for operating a climate control system for a building according to embodiments disclosed herein. Detailed Implementation
[0015] Climate control systems in commercial buildings can be a major (or even the largest) component of a building's electrical load. Therefore, the design and operation of a building's climate control system can significantly impact the building's total electrical load demand. Furthermore, the electrical load demand of a climate control system can vary considerably over a 24-hour period, typically following a sinusoidal curve, with peak loads (used for cooling) usually occurring in the late afternoon and minimum loads (also used for cooling) typically occurring in the early morning hours. Consequently, building operators must reserve sufficient electrical load capacity to operate the climate control system during peak load periods. However, this results in a significant amount of unused reserved electrical load capacity during other times of the day, capacity that could otherwise be monetized (e.g., by selling electrical load capacity to one or more tenants or users of the commercial building). Additionally, building operators may reserve sufficient electrical load capacity to operate the climate control system under the worst peak temperatures in historical periods (e.g., in some cases, 20 years). Therefore, the unused and reserved electrical load capacity of the climate control system is even greater on average throughout the day (when the highest or peak temperature is significantly lower than the worst-case peak temperature).
[0016] Therefore, the embodiments disclosed herein include systems and methods for designing and operating climate control systems designed to free up unused electrical load capacity, enabling it to be monetized or otherwise used by building operators. For example, embodiments of the systems and methods disclosed herein can be configured to substantially smooth the electrical load demand of the climate control system over a 24-hour period, thereby freeing up electrical load typically reserved for peak periods. Thus, by using the embodiments disclosed herein, building operators can reduce the total electrical load that must be reserved for the operation of a building's climate control system, and this additional electrical load capacity can be further monetized or used for other purposes.
[0017] For reference Figure 1According to some embodiments disclosed herein, a climate control system 10 including a thermal energy storage (TES) component 60 (or simply "TES" 60) is illustrated. The climate control system 10 may be configured to cool one or more interior spaces of a commercial building 12 (or simply "building" 12) during operation. Specifically, the climate control system 10 may include one or more (e.g., one or more) coolers 15 configured to cool a working fluid 54 circulating along an interior space heat exchange loop 50 between the coolers 15 and an interior space heat exchange component 52. The coolers 15 may be arranged in parallel along the interior space heat exchange loop 50; however, other arrangements are also contemplated. The working fluid 54 may include water or a suitable aqueous mixture (e.g., water-glycol). In some embodiments, the working fluid 54 may include a fluid other than water, such as, for example, air (e.g., air directly supplied to the regulated space). The regulated space heat exchange component 52 may include one or more heat exchangers (e.g., air processor units) configured to exchange heat between the working fluid 54 and an airflow supplied to the interior space inside the building 12.
[0018] Each cooler 15 may be configured to cool the working fluid 54 via one or more refrigeration circuits. For example, now referring to Figure 2 It illustrates some embodiments Figure 1 A general schematic diagram of one of the coolers 15 (it will be understood that in some embodiments, Figure 1 Other coolers 15 in the system can be configured to be similar to... Figure 2 (The same or similar shown).
[0019] Generally, each cooler 15 includes a refrigeration circuit 20 configured to circulate refrigerant to exchange heat between the interior space of building 12 and the surrounding environment (e.g., the outdoor environment surrounding building 12) to cool the interior space. The refrigeration circuit may include a first heat exchanger 22 and a second heat exchanger 24. The first heat exchanger 22 is configured to exchange heat between the refrigerant and the working fluid 44 of the ambient heat exchange circuit 40, and the second heat exchanger 24 is configured to exchange heat between the refrigerant and the working fluid 54 of the interior space heat exchange circuit 50.
[0020] The working fluid 44 may include water or any other suitable aqueous mixture, such as the mixture described above for working fluid 54. Alternatively, the working fluid 44 may include air. When the working fluid 44 is water, the cooler 15 may be referred to as a “water-cooled” cooler, and when the working fluid is air, the cooler 15 may be referred to as an “air-cooled” cooler unit. In any case, the working fluid 44 may circulate between the first heat exchanger 22 of the refrigeration assembly 20 and the ambient heat exchange assembly 42 to exchange heat between the refrigerant and the surrounding environment. In some embodiments, the ambient heat exchange assembly 42 includes one or more heat exchangers (e.g., water-cooled towers, radiators, finned fan coolers, etc.) configured to transfer heat between the surrounding environment and the working fluid 44. In some embodiments, such as in the case of an air-cooled cooler, the ambient heat exchange assembly 42 may be integrated and combined with the condenser 22 such that heat is directly exchanged between the refrigerant and an airflow that originates from and is returned to the surrounding environment. Furthermore, in some embodiments, such as in the case of a water-cooled cooler, the ambient heat exchange assembly 42 may be shared and integrated across each cooler 15 of the climate control system 10 (e.g., such that the first heat exchanger 22 of each cooler 15 is fluidly connected in parallel along a common ambient heat exchange loop 40).
[0021] In addition to the first heat exchanger 22 and the second heat exchanger 24, the refrigeration circuit 20 may include a compressor 26 (in some embodiments, one or more compressors 26) and an expansion valve 30. The compressor 26 and the expansion valve 30 may be in fluid communication with the first heat exchanger 22 and the second heat exchanger 24 along the refrigerant circuit 20. During operation, the refrigeration circuit 20 may be operated to allow the refrigerant to travel along... Figure 2 The first directional circulation shown transfers heat from the interior space (e.g., via interior space heat exchange loop 50) to the surrounding environment (e.g., via ambient heat exchange loop 40). This operation may be referred to herein as “cooling mode” operation.
[0022] Specifically, in Figure 2 In the cooling mode shown, the refrigerant (possibly in a vapor or semi-vapor state) is compressed by compressor 26 and delivered to the first heat exchanger 22 via refrigerant circuit 20. Within the first heat exchanger 22, heat is transferred from the refrigerant to the working fluid 44, which cools the refrigerant and at least partially condenses it into a liquid. Therefore, in... Figure 2 In the cooling mode operation shown, the first heat exchanger 22 can be referred to as the "condenser". Then, as previously described, heat is transferred from the heated working fluid 44 to the surrounding environment via the ambient heat exchange component 42 of the ambient heat exchange loop 40.
[0023] The condensed refrigerant is then discharged from the first heat exchanger 22 and flows to the second heat exchanger 24 via the expansion valve 30. The expansion valve 30 can be positioned along the refrigerant circuit 20 between the first heat exchanger 22 and the second heat exchanger 24. The expansion valve 30 can be actuated to controllably expand and thus cool the refrigerant upstream of the second heat exchanger 24.
[0024] The expanded and cooled refrigerant then flows to the second heat exchanger 24. Within the second heat exchanger 24, heat is transferred from the working fluid 54 to the refrigerant, causing the refrigerant to evaporate (or at least partially evaporate). Therefore, in Figure 1 In the cooling mode shown, the second heat exchanger 24 can be referred to as an "evaporator". The cooled working fluid 54 is then used to cool the interior space of the building 12 via the regulated space heat exchange assembly 52 of the internal space heat exchange loop 50.
[0025] Although not shown, in some embodiments, the refrigeration circuit 20 may allow the refrigerant to travel along the same path as the refrigerant. Figure 2 A second-direction circulation, in the opposite direction, transfers heat from the surrounding environment to the interior space of the building 12 via the ambient heat exchange loop 40 and the interior space heat exchange loop 50. This type of operation may be referred to herein as “heating mode” operation, and the refrigeration unit 20 configured to operate in heating mode may be referred to as a “heat pump.” During heating mode operation of the refrigeration loop 20, the first heat exchanger 22 may be used as an “evaporator” (to evaporate the refrigerant), and the second heat exchanger 24 may be used as a “condenser” (to condense the refrigerant).
[0026] The operation of the cooler 15 can be adjusted to provide different output cooling (or heating) capacities to the working fluid 54 during operation. Specifically, the mass flow rate of the refrigerant flowing along the refrigerant circuit 20 can be adjusted (e.g., by adjusting the operating speed of the compressor 26 and correspondingly adjusting the opening of the expansion valve 30), thereby changing the rate of heat transfer between the refrigerant and the working fluid 54 during operation. In some embodiments, when the cooling demand of the interior space of the building 12 is low, such as during off-peak periods, the cooler 15 can operate at a lower output cooling capacity (e.g., by reducing the speed of the compressor 26).
[0027] Refer again Figure 1 The TES 60 is configured to supplement the output cooling capacity of the cooler 15 by transferring heat to the working fluid 54 via one or more (e.g., one or more) heat exchangers 62. Specifically, the TES 60 may be configured to provide the cryogenic fluid 64 to the heat exchangers 62, thereby exchanging additional heat with the working fluid 54 of the internal space heat exchange loop 50, thereby reducing the cooling requirements of the cooler 15 during operation.
[0028] Each heat exchanger 62 may be positioned upstream of a cooler 15, such that the heat exchangers 62 can be arranged in parallel along the internal space heat exchange loop 50. Specifically, each heat exchanger 62 may be positioned upstream of a corresponding cooler 15, such that the working fluid 54 flows through one of the heat exchangers 62 first and then through the corresponding cooler 15 during operation, and the number of heat exchangers 62 may be equal to (or possibly less than) the number of coolers 15. Furthermore, multiple valves 66 may be provided between the TES 60 and the heat exchangers 62, which can selectively control the flow rate of the cryogenic fluid 64 from the TES 60 to each heat exchanger 62 during operation. Additionally, one or more pumps or other pressurizing devices (not specifically shown) may be used to facilitate the flow of the cryogenic fluid 64 to the heat exchangers 62 via the valves 66 during operation.
[0029] The cryogenic fluid 64 may include water or a suitable aqueous mixture (e.g., water-glycol). In some embodiments, the cryogenic fluid 64 may include other fluids besides water, such as, for example, air. The cryogenic fluid 64 is referred to as "cryo" because its temperature is low enough to facilitate heat transfer from the working fluid 54 to the cryogenic fluid 64 via the heat exchanger 62.
[0030] During operation, the TES 60 can deliver additional cooling (or heating) to the working fluid 54 via the cryogenic fluid 64 and the heat exchanger 62, thereby reducing the total electrical load consumed by the cooler 15. The TES 60 may include any device or system configured to store additional heating or cooling capacity that can be selectively delivered to the working fluid 54 via the cryogenic fluid 64 and the heat exchanger 62 during operation. For example, in some embodiments, the TES 60 may include a cold water tank, a phase change material (e.g., ice, wax, etc.) or other heat-absorbing material, a cold / hot fluid source (e.g., a water-cooled tower that circulates rainwater), a geothermal well, liquid nitrogen (N2), or liquid carbon dioxide (CO2).
[0031] In some embodiments, valve 66 can be activated to selectively supply cryogenic fluid 64 to one of selected heat exchangers 62 to provide targeted supplemental heat exchange for the working fluid 54, thereby effectively reducing the total electrical load consumed by the climate control system 10 while avoiding a reduction in the delivered cooling capacity during operation. Specifically, during operation, controller 120 can be used to selectively adjust the operating level of each cooler 15 and coordinate the distribution of cryogenic fluid 64 to the heat exchangers 62 to provide the desired cooling capacity to the interior space of building 12 via the interior space heat exchange loop 50, while achieving and maintaining the fundamentally optimized electrical performance of the climate control system 10. These adjustments by controller 120 can smooth the overall electrical demand of the climate control system 10 over a period of time (e.g., twenty-four hours), allowing building owners to release additional electrical capacity for building 12 (which can be monetized or utilized more effectively elsewhere, as described herein).
[0032] The controller 120 may be (or may be incorporated into) the main controller or primary controller of the climate control system 10, or it may be a standalone controller 120, for controlling the operating level of the cooler 15 and / or the distribution of the cryogenic fluid 64 into and out of the TES 60 during operation. In any case, the controller 120 may be described herein and referred to as part of the climate control system 10.
[0033] Controller 120 may include one or more computing devices, such as a computer, tablet computer, smartphone, server, circuit board, or other computing devices or systems. Therefore, controller 120 may include processor 122 and memory 124.
[0034] Processor 122 may include any suitable processing means or collection of processing means. In some embodiments, processor 122 may include a microcontroller, a central processing unit (CPU), a graphics processing unit (GPU), a timing controller (TCON), a scaler unit, or some combination thereof. During operation, processor 122 executes machine-readable instructions (such as machine-readable instruction 126) stored on memory 124, thereby causing processor 122 to perform some or all of the actions attributed herein to controller 120. Typically, processor 122 fetches, decodes, and executes instructions (e.g., machine-readable instruction 126). In addition, processor 122 may perform other actions, such as making determinations, detecting states or values, and communicating signals. If processor 122 assists another component in performing a function, it can be said that processor 122 causes that component to perform that function.
[0035] Memory 124 can be any suitable means or set of means for storing digital information, including data and machine-readable instructions (such as machine-readable instruction 126). For example, memory 124 may include volatile memory (such as random access memory (RAM)), non-volatile memory (such as flash memory, read-only memory (ROM), etc.), or a combination of volatile and non-volatile memory. Data read or written by processor 122 when executing machine-readable instruction 126 may also be stored on memory 124. Memory 124 may include "non-transient machine-readable medium," wherein the term "non-transient" does not include or encompasses transient propagating signals.
[0036] Processor 122 may include one or more processing devices distributed within (or communicatively connected to) controller 120 or more widely distributed within climate control system 10. Similarly, memory 124 may include one or more memory devices distributed within (or communicatively connected to) controller 120 or more widely distributed within climate control system 10. Therefore, controller 120 may include multiple individual “controllers” distributed throughout climate control system 10.
[0037] As previously described, controller 120 can be used to selectively adjust the operating level of each cooler 15 and coordinate the distribution of cryogenic fluid 64 to heat exchanger 62 to provide the desired cooling capacity to the interior space of building 12 via working fluid 54, while achieving and maintaining a fundamentally optimized electrical load for climate control system 10. Specifically, as will be described in more detail herein, it has been found that the efficiency of each cooler 15 may vary non-linearly across a range of operating levels at a given outdoor ambient temperature. Therefore, simply uniformly reducing the operating level of coolers 15 may not provide optimal operating efficiency (in terms of electrical load) for climate control system 10. Thus, controller 120 can optimize the electrical load utilization of climate control system 10 by operating a selected combination of coolers 15 (e.g., one or more or all) at selected operating levels while distributing cryogenic fluid 64 from TES 60 based on the non-linearly varying operating efficiency of coolers 15 and the outdoor ambient temperature surrounding building 12.
[0038] Now for reference Figure 3 According to some embodiments, a climate control system 10 based on output cooling capacity and outdoor ambient temperature is shown. Figure 1A table 32 shows the electrical load consumed by one of the coolers 15. Table 32 may represent the electrical load consumed by a particular cooler 15; therefore, each cooler 15 may include a similar (but unique) table 32, which the controller 120 may use during operation to adjust the output cooling capacity of the cooler 15 and / or the output cooling capacity from the TES 60. Figure 1 Distribution of cryogenic fluid 64.
[0039] The output cooling capacity of the cooler 15 associated with Table 32 may include the cooler 15 in the corresponding compressor 26 ( Figure 2 At a specific operating speed, the working fluid 54 ( Figure 1 The total heat transfer rate (e.g., in tons, i.e., British thermal units (BTU) per hour). The output cooling capacity can be expressed in Table 32 as a percentage of the maximum output cooling capacity that the cooler 15 can deliver. However, in some embodiments, the output cooling capacity of the cooler 15 associated with Table 32 can be expressed in different ways, such as directly in tons (or other suitable units of heat transfer rate).
[0040] The outdoor ambient temperature can be the temperature of the outdoor environment surrounding building 12. As an example, Table 32 uses 2... The increment shows 78 F to 96 The range of F; however, it may include any suitable temperature range (and scale). For example, in some embodiments, the temperature ranges included in Table 32 may be based on typical temperature ranges experienced in the geographical area where building 12 is located.
[0041] like Figure 3 As shown in Table 32, when the cooler 15 operates at 10%, 20%, 30%...100% of its maximum cooling capacity at an outdoor ambient temperature of 96°F, the cooler 15 may generate electrical loads A10, B10, C10...J10 (e.g., in kilowatts (kW)). The electrical loads A10, B10, C10...J10 typically increase with the output cooling capacity of the cooler 15; however, the increase in electrical loads A10, B10, C10...J10 may not be linear. Therefore, the difference between electrical loads A10 and B10 may differ from the difference between electrical loads B10 and C10, or from the difference between electrical loads C10 and D10, and so on.
[0042] Furthermore, the operating efficiency (in terms of power consumption) of the cooler 15 associated with Table 32 may vary under different output cooling capacities and outdoor ambient temperatures. Specifically, the operating efficiency of the cooler 15 associated with Table 32 can be expressed as the electrical load unit (e.g., kW or other suitable unit) per ton (or other suitable unit) of output cooling capacity provided by the cooler 15 using the table in Table 32. The variation of these operating efficiencies in Table 32 under specific outdoor ambient temperatures may be non-linear, at least in part due to the non-linear differences in the electrical load consumed by the cooler at different output cooling capacities, as previously described.
[0043] For example, in some embodiments, the cooler 15 associated with Table 32 may be configured to provide a maximum output cooling capacity of approximately 600 tons (e.g., 100% of the output cooling capacity in Table 32), and the electrical load values J10, I10, and H10 are approximately 650 kW, 513 kW, and 473 kW, respectively. Therefore, in this particular example, for the cooler 15 associated with Table 32, operating at 100% of the maximum output cooling capacity would likely require an electrical load of approximately 1.084 kW per ton of cooling capacity; operating at 90% of the maximum output cooling capacity would likely require an electrical load of approximately 0.949 kW per ton of cooling capacity; and operating at 80% of the maximum output cooling capacity would likely require an electrical load of approximately 0.986 kW per ton of cooling capacity. The operating efficiency of cooler 15 at 100%, 90%, and 80% output cooling capacity (calculated in kW of electrical load per ton of output cooling capacity) exhibits a non-linearity, even showing a rather striking increase in efficiency between operation at 90% output cooling capacity (approximately 0.949 kW / ton) and 80% output cooling capacity (approximately 0.986 kW / ton), whereas typically, the expected operating efficiency decreases as the output cooling capacity decreases. Without being limited to this theory or any other theory, these non-linear characteristics of cooler 15 are believed to stem from various unique characteristics and variations of cooler 15 (which may originate from manufacturing tolerances, installation parameters, operating history, or other factors).
[0044] Therefore, during operation, the controller 120 can selectively operate combinations of coolers 15 with different output cooling capacities based on the data associated with each cooler 15 in Table 32, thereby providing an optimal balance of cooling capacity consumed per unit of electrical load. Specifically, the controller 120 can be configured to determine the combination of coolers 15 to provide a selected output cooling capacity to meet the desired cooling demand (which may be based on the outdoor ambient temperature) while minimizing the total kW of electrical load per ton of output cooling capacity during operation. Using the specific and unique data in Table 32 allows the controller 120 to account for the non-linear variation characteristics and performance of the coolers 15.
[0045] In some embodiments, the data in Table 32 (e.g., electrical load data) may initially be calculated based on one or more parameters of the cooler 15. However, as the climate control system 10 operates, the values in Table 32 may be replaced (e.g., by the controller 120) with updated values based on the actual performance of the cooler 15 at the time of installation. Thus, over time, the controller 120 can adjust its operating parameters based on the unique performance of the cooler 15 within the range of outdoor ambient temperatures exposed to the building 12 within the climate control system 10. In some embodiments, Table 32 (or its indicative data) may be stored at least partially in the memory 124 of the controller 120.
[0046] Figure 4 Chart 70 is shown, illustrating an example electrical load consumed per unit time by the climate control system 10 during peak period 71 of an example day, according to some embodiments. "Peak period" 71 can refer to the period of day when temperatures are typically highest, which may begin in the late morning (or late "AM") and continue into the late afternoon (during early "PM"). Specifically, peak period 71 may include the portion of the day when temperatures rise above a threshold. The outdoor ambient temperature during peak period 71 may resemble a portion of a sine curve that rises smoothly to the peak temperature at peak time 75 (e.g., in some cases in the afternoon) and then smoothly declines from the peak temperature.
[0047] Figure 4 Figure 70 shows datasets 72 and 74 of the electrical load consumed by the climate control system 10 when operating to achieve the desired output cooling capacity of the interior space of building 12. Specifically, according to the embodiments disclosed herein, Figure 4 The dataset shown in curve 70 includes a first dataset 72 and a second dataset 74 based on the nonlinear operating efficiency of the cooler 15. The first dataset 72 shows the electrical load consumed per unit time by the climate control system 10 when the cooler 15 is used alone to meet the output cooling demand of the building 12. The second dataset 74 shows the electrical load consumed per unit time by the climate control system 10 when the cooler 15 and the TES 60 are used simultaneously to meet the output cooling demand of the building 12.
[0048] from Figure 4As shown in datasets 72 and 74, in the first dataset 72 (using only cooler 15 to meet the cooling needs of building 12), the electrical load consumed by the climate control system 10 increases with the increase of outdoor ambient temperature during peak period 71, thus resembling a sine curve. Its peak electrical load 78 occurs at (or near) peak temperature time 75, with periods of increase and decrease in electrical load before and after peak temperature time 75, respectively. Conversely, according to the embodiments disclosed herein, when the climate control system 10 meets the cooling needs of building 12 by using a selected combination of coolers 15 with selected output cooling capacity and the distribution of cryogenic fluid 64 from TES 60, Figure 4 During the peak period 71 shown, the electrical load consumed by the climate control system 10 can be kept substantially at or below the baseline electrical load 76, which is less than the peak electrical load 78. Therefore, according to the second dataset 74, the electrical load consumed by the climate control system 10 can be leveled off at or near the baseline electrical load 76, and the characteristic increases and decreases in electrical load associated with the first dataset 72 can be avoided (or at least significantly reduced).
[0049] Still referencing Figure 1 and Figure 4 During operation, controller 120 may receive a weather forecast for the upcoming day (or the upcoming peak period 71), and this weather forecast may include a predicted temperature profile for the day. The weather forecast may be obtained from any suitable source, including weather services, news agencies, etc. In some embodiments, the temperature profile of the weather forecast may include the expected temperature for the next day at regular time intervals (e.g., every hour, every half hour, every five minutes, etc.). Controller 120 may use the weather forecast to determine the peak temperature for the upcoming day, and may also determine the total available cooling capacity (e.g., via cryogenic fluid 64 and heat exchanger 62) that can be delivered from TES 60 during peak period 71. In some embodiments, controller 120 may determine the total available cooling capacity that can be delivered from TES 60 by using one or more sensors (e.g., temperature sensors, volume sensors, level sensors, etc.) that may indicate the available volume and temperature of cryogenic fluid 64 that can be delivered from TES 60.
[0050] Using these information sources, controller 120 can then determine the operating schedule of climate control system 10 during the upcoming peak period 71. In determining the operating schedule of climate control system 10, controller 120 can first determine a combination of cooler 15 at a selected operating level with supplemental cooling distribution from TES 60, which will provide the desired cooling capacity to the interior spaces of building 12 at a reduced baseline electrical load 76 during peak temperature time 75 (and expected peak temperature), which is less than the cooling capacity of cooler 15 operating alone as previously described (e.g., Figure 4 The expected peak electrical load 78 is derived from the first dataset 72 in the dataset. In some embodiments, this is based at least in part on the unique nonlinear variation in the operating efficiency of the cooler 15 (e.g., Figure 3 (See Table 32 in the table). The controller 120 can determine the baseline electrical load 76 by selecting a combination of coolers 15 and their corresponding output cooling capacities, which will require the lowest electrical load (e.g., in kilowatts) per unit of cooling capacity (e.g., in tons) and combine it with the cooling capacity provided by the TES 60 to meet the cooling needs of the building 12, as previously described.
[0051] The controller 120 can then set the newly determined baseline electrical load 76 as the maximum electrical load of the climate control system 10 during other periods of peak time 71 (in some cases, even the entire 24 hours). Specifically, after determining the new baseline electrical load 76 based on the predicted peak temperature at peak temperature time 75 and the available cooling capacity of the TES 60, the controller 120 can determine additional combinations (and operating levels) of the coolers 15 and the distribution of cryogenic fluid 64 from the TES 60, which provides the desired cooling capacity for the interior spaces of the building 12 at other predicted temperatures during peak time 71 (before and after peak temperature time 75), without exceeding the determined baseline electrical load 76.
[0052] When determining the operating plan of the climate control system 10, the controller 120 can refer to Table 32 ( Figure 3 Based on the operating efficiency and expected output cooling capacity provided, the controller 120 determines the most efficient combination (and operating level) of the coolers 15 for operating the climate control system 10, as previously described. Since the data provided in Table 32 can be continuously updated as previously described, the controller 120 can accurately determine the most efficient combination (and operating level) of the coolers 15 for operating the climate control system 10 based on the outdoor ambient temperature throughout the entire service life of the climate control system 10.
[0053] As controller 120 determines the allocation combination of cooler 15 and TES 60 to achieve a cooling demand equal to or below the baseline electrical load 76, controller 120 can also determine whether the predicted allocation of TES 60 can efficiently meter and thus fully release the available cooling capacity of TES 60 throughout the peak period 71, without fully allocating the available cooling capacity of TES 60 before the end of peak period 71, and without leaving cooling capacity (or excess cooling capacity exceeding a threshold or safety reserve) after peak period 71 ends. If the initial allocation plan determined by controller 120 results in inefficient allocation of TES 60, controller 120 can restart the entire process described above to determine a new baseline electrical load 76 that allows for efficient allocation of the cooling capacity of TES 60 throughout peak period 71.
[0054] During peak period 71, controller 120 can execute the planned operation of climate control system 10 to ensure operation at baseline electrical load 76. However, during peak period 71, deviations between actual and predicted temperature profiles may require additional operational adjustments by controller 120. Specifically, controller 120 can operate different combinations of coolers 15 at different operating levels, and / or distribute cryogenic fluid 64 from TES 60 to selected heat exchangers 62 at different rates to provide the desired cooling capacity at deviated temperatures without exceeding the baseline electrical load 76 during operation. As previously mentioned, when adjusting the operation of climate control system 10 to cope with deviated temperatures, controller 120 can again use Table 32 ( Figure 3 The most efficient combination of coolers 15 (and its associated operating level) is determined by the available cooling capacity in the TES 60 and the TES 60.
[0055] When designing the climate control system 10 for building 12, the operating schedule of the climate control system 10 can be determined based on the worst-case predicted temperature (or temperature profile) over a 24-hour period. The worst-case predicted temperature (or temperature profile) corresponds to the highest temperature observed in the geographic area where building 12 is located during a historical period (e.g., in some cases, the past twenty years). Parameters of the coolers 15 (e.g., type, quantity, size, etc.) and the TES 60 (e.g., type, size, capacity, etc.) can be determined so that the climate control system 10 can meet the cooling requirements associated with the worst-case predicted temperature (or temperature profile) while maintaining the electrical load at or below the expected (or maximum expected) baseline electrical load (e.g., baseline electrical load 76). The parameters of the coolers 15 and the TES 60 can also be further determined by any additional system constraints, such as, for example, the available space that the climate control system 10 may occupy, any equipment requirements of the climate control system 10 (e.g., the requirement to use only air-cooled or water-cooled coolers), the availability or demise of a particular type of TES 60, etc. The final climate control system 10 can be configured to provide the worst-case cooling requirements (e.g., based on the worst-case predicted temperature) under the desired baseline electrical load 76.
[0056] The difference ΔP between the baseline electrical load 76 that a climate control system using only coolers can withstand and the theoretical peak electrical load 78 can represent additional electrical load capacity that can be monetized or utilized more efficiently elsewhere, as described herein. Specifically, in the case of some commercial buildings (such as, for example, data centers), the additional electrical load capacity (e.g., ΔP) can be sold to building tenants (e.g., for the electrical equipment used to run them), thereby generating additional revenue for the building operator.
[0057] Now for reference Figure 5 The illustration shows an embodiment of a climate control system 10, including a specific example of a TES 60. Generally, the TES 60 can be configured as a fluid tank 100 that stores a volume of cryogenic fluid 64 and can deliver the cryogenic fluid 64 to or from a heat exchanger 62 to supplement the cooling capacity of the cooler 15, as previously described. The cryogenic fluid 64 stored in the fluid tank 100 can be recharged during operation by one or more recharge coolers 102. The recharge coolers 102 are typically constructed similarly to the cooler 15 (…). Figure 2 Since the refrigerant loop is the same, the cryogenic fluid 64 can be cooled using the refrigerant loop, and then the cryogenic fluid 64 can be output back to the cold storage tank 100 for storage and subsequent distribution, as described above.
[0058] Recharge coolers 102 and 15 can be powered via a common bus 106 (or other suitable power distribution system). Controller 120 can control and regulate the operation of recharge coolers 102 and 15 during operation via bus 106 or directly (not via bus 106). Bus 106 can be powered by the local power grid 114.
[0059] Furthermore, the TES 60 (or more broadly, the climate control system 10) may include a solar power generation module 111. For example, the solar power generation module 111 may include one or more photovoltaic cells (or solar panels) configured to convert sunlight 112 into electric current. The current generated by the solar power generation module 111 may be direct current (DC). Therefore, the current generated by the solar power generation module 111 can be converted to alternating current (AC) by a DC-AC inverter 108. The inverted DC current can then be conducted from the DC-AC inverter 108 to bus 106. A controller 120 may be communicatively coupled to bus 106, allowing the controller 120 to monitor and determine how much current is conducted to bus 106 via the solar power generation module 111.
[0060] During operation of the climate control system 10, the controller 120 can gain additional operating efficiency through the utilization of the recharge cooler 102 and the solar power generation module 111. Specifically, refer to Figure 6 The diagram 200, shown according to some embodiments, illustrates... Figure 5 The embodiment of the climate control system 10 shown represents the example electrical load consumed per unit time in an example day. Figure 6 Chart 200 in the figure can show Figure 4 The peak period 71 and the non-peak period 202 shown together constitute a 24-hour day. The "non-peak period" 202 can refer to the time of day when temperatures are typically lowest, which may begin in the late afternoon or evening (or late PM) and continue into the late morning (during the later "AM" period). As previously mentioned, the peak period 71 can include the portion of the day when temperatures exceed a threshold, while the non-peak period 202 can include the remaining portion of the day when temperatures are equal to or below the threshold. The outdoor ambient temperature during the non-peak period 71 can also exhibit a portion of a sine curve, smoothly descending to the lowest temperature (e.g., in some cases at dawn) and then smoothly rising towards the peak period 71.
[0061] and Figure 4 Similar to Chart 70 in the text, Figure 6Figure 200 in Figure 200 shows datasets 72 and 74, where dataset 72 shows the electrical load consumed per unit time by the climate control system 10 when using only the cooler 15 to meet the output cooling demand of the building 12 without the TES 60, and dataset 74 shows the electrical load consumed per unit time by the climate control system 10 when using both the cooler 15 and the TES 60 to meet the output cooling demand of the building 12. In Figure 200, datasets 72 and 74 are extended to further illustrate the performance during peak hours 71 and off-peak hours 202, and reference... Figure 5 An embodiment of the climate control system 10 shown.
[0062] Since off-peak period 202 may represent a period when outdoor ambient temperatures are typically low, controller 120 can use cooler 15 to meet the cooling needs of the interior spaces in building 12 when there is no allocation from TES 60 and the electrical load value is lower than the baseline electrical load 76 determined based on the upcoming peak period (or another peak period as previously described). The reduction in electrical load consumed by climate control system 10 can indicate... Figure 6 The reduction in electrical load consumption is shown in the off-peak period of the first dataset 72. Therefore, the controller 120 may have additional electrical load capacity during the off-peak period 202, characterized by the difference between the baseline electrical load 76 of the peak period 71 and the reduced electrical load during the off-peak period 202. Since building owners or operators may typically reserve up to the baseline electrical load 76 for the operation of the climate control system 10, the unused electrical load during the off-peak period 202 is often unusable for other purposes, and thus may represent a "waste" from the building operator's perspective. Therefore, the controller 120 can utilize the additional electrical load capacity during the off-peak period 202 to supplement the TES 60 to allow for subsequent distribution of the cryogenic fluid 64 during the subsequent peak period 71.
[0063] Specifically, in some embodiments, during off-peak periods 202, controller 120 may operate recharge cooler 102 to recharge tank 100 with cryogenic cold fluid 64. During this process, controller 120 may limit the operation of recharge cooler 102 (e.g., by adjusting the speed of compressor 26 of one or more recharge coolers 102) such that the total electrical load consumed by climate control system 10 (including recharge cooler 102 and cooler 15) is equal to or lower than baseline electrical load 76. Thus, the overall effect is to further smooth the electrical load consumed by climate control system 10, keeping it substantially at (or below) baseline electrical load during both peak periods 71 and off-peak periods 202.
[0064] Furthermore, during peak period 71, embodiments of the climate control system 10 can operate to achieve higher operating efficiency than described herein. Specifically, during peak period 71, the sun may be above the horizon, allowing the solar power generation module 111 to generate current supplied by bus 106, as previously described. The current generated by the solar power generation module 111 can represent additional current that does not contribute to the power drawn from the grid 114 (and can therefore be used to offset it). Thus, the controller 120 can utilize the current generated by the solar power generation module 111 to supplement the operation of the climate control system 10 (including cooler 15 and / or TES 60).
[0065] For example, in some embodiments, during peak period 71, controller 120 is able to operate one or more recharge coolers 102 with an electrical load equal to (or less than) the total current generated by solar power generation components 111, thereby further replenishing tank 100 and extending and enhancing the potential distribution of cryogenic fluid 64 from tank 100 during peak period 71. Thus, the effective capacity of tank 100 can be increased using the current generated by solar power generation components 111 without increasing its capacity. Furthermore, by limiting the operating electrical load of recharge coolers 102 to equal to or less than the total current generated by solar power generation components 111, recharge coolers 102 can be operated without adding additional net electrical load to bus 106.
[0066] Furthermore, in some embodiments, during peak period 71, controller 120 may cause cooler 15 to operate at a higher operating level, such that the total electrical load of climate control system 10 during peak period 71 may be higher than baseline electrical load 76, but the excess is equal to (or less than) the current generated by solar power generation module 111. The additional electrical load utilized by cooler 15 via the current generated by solar power generation module 111 provides additional cooling capacity, which may reduce the allocation rate or capacity of TES 60 during peak period (which in turn allows for more efficient or optimized allocation).
[0067] Overall, Figure 5 The embodiment of the climate control system 10 shown can allow for a stronger baseline electrical load 76 during operation. Specifically, the additional cooling capacity provided by the recharge cooler 102 and the solar power generation modules 111 allows the climate control system 10 to achieve and maintain a relatively low baseline electrical load 76 even during the worst peak period 71. Therefore, the embodiment of the climate control system 10 can achieve even higher electrical load capacities, which can be monetized or otherwise used by the building owner or operator, as previously described.
[0068] Furthermore, it should be understood that climate control system 10 (e.g., Figure 1 The embodiments shown or Figure 5 (As illustrated in the embodiments) temporary use of additional cooling capacity sources to provide additional cooling capacity to cope with unusually high electrical loads (e.g., due to heat waves or other weather events) without causing the operation of the climate control system 10 to exceed the baseline electrical load 76. For example, in some embodiments, additional tanks of cooling or cold fluids (e.g., liquid nitrogen, liquid CO2, etc.) may be temporarily connected to the TES 60 to supplement the cooling capacity provided via the TES 60, thereby avoiding further increases in the electrical load consumed by the cooler 15 to meet the cooling needs of the interior space of the building 12.
[0069] Now for reference Figure 7 This illustrates a method 300 for operating a climate control system for a building (e.g., building 12) according to some embodiments. Method 300 can use... Figure 1 and 5 The climate control system 10 shown in the illustration is used to perform this; however, it should be understood that embodiments of method 300 can also be implemented by using at least some aspects of the same... Figure 1 and 5 The climate control system 10 shown in the figure is implemented by different climate control systems.
[0070] First, method 300 includes receiving weather data for the geographic area where the building is located for the next day at box 302. This weather data may include a weather forecast and at least a predicted temperature profile for the next day (e.g., temperature variation over time). In some embodiments, the weather data may also include a sunshine forecast, which can be used to predict the performance of solar power generation components (e.g., solar panels ... Figure 5 The effectiveness or efficiency of the solar power generation module 111 shown.
[0071] Furthermore, method 300 includes determining, at block 304, the total available cooling capacity of the thermal energy storage (TES) components of the building climate control system. The TES components may include those previously described herein. Figure 1 One or more TES components in TES 60. Therefore, in some embodiments, the TES component in block 304 may include a cryogenic fluid source, such as a fluid tank. The cryogenic fluid may include cryogenic water or other cryogenic aqueous fluids, which may be stored in the tank and dispensed from it during operation.
[0072] Further, method 300 includes, at block 306, determining the baseline electrical load of the operating climate control system based at least on weather data and the total cooling capacity available to the TES components. Even further, method 300 includes determining the output cooling capacity of multiple coolers in the climate control system, and the allocation from the TES components, configured to meet the building's cooling needs when the electrical load of the climate control system is equal to or less than the baseline electrical load. For example, as described above for... Figure 1 and 5 As described in the embodiment of the climate control system 10 shown, the controller 120 can determine the baseline electrical load 76 of the climate control system 10. Figure 4 and 6 The baseline electrical load 76 can be the minimum electrical load of the climate control system 10, used to distribute both the cooler 15 and the cryogenic fluid 64 from the TES 60 to meet the cooling needs of the interior space of the building 12 at the peak temperature of the upcoming day. Once the baseline electrical load 76 is determined, the controller 120 can adjust the operation of the cooler 15 and the distribution of the cryogenic fluid from the TES 60 to meet the cooling needs of the building 12, while keeping the total electrical load of the climate control system 10 at or below the baseline electrical load 76.
[0073] As explained above and reiterated below, this disclosure includes, but is not limited to, the following exemplary implementations.
[0074] Technical Solution 1: A climate control system for regulating an interior space, the climate control system comprising: an interior space heat exchange loop configured to circulate working fluid to cool airflow directed to the interior space; a cooler configured to cool the working fluid; and a thermal energy storage (TES) component comprising: a cryogenic fluid source; and a heat exchanger coupled to the interior space heat exchange loop such that the heat exchanger is located upstream of the cooler along the interior space heat exchange loop, the heat exchanger being configured to receive a cryogenic fluid flow from the cryogenic fluid source to cool the working fluid, thereby supplementing the output cooling capacity of the cooler.
[0075] Technical Solution 2: The climate control system according to any one of the technical solutions, wherein the cooler includes a refrigeration circuit, the refrigeration circuit including a compressor, the compressor mechanism causing to operate at multiple different speeds to regulate the output cooling capacity of the cooler.
[0076] Technical Solution 3: The climate control system according to any one of the technical solutions, wherein the cryogenic fluid source includes a tank configured to maintain a certain volume of cryogenic fluid, and wherein the TES component further includes a recharge cooler configured to reduce the temperature of the cryogenic fluid and output the cryogenic fluid to the tank.
[0077] Technical Solution 4: The climate control system according to any one of the technical solutions, wherein the TES component further includes one or more valves configured to control the flow rate of cold fluid to the heat exchanger.
[0078] Technical Solution 5: The climate control system according to any one of the technical solutions further includes a controller configured to: regulate the flow rate of cold fluid to the heat exchanger; and regulate the output cooling capacity of the cooler.
[0079] Technical Solution 6: The climate control system according to any one of the technical solutions further includes: a busbar electrically connected to the cooler and the recharge cooler; and a solar power generation component electrically connected to the busbar.
[0080] Technical Solution 7: A climate control system for regulating an interior space, the climate control system comprising: an interior space heat exchange loop configured to circulate working fluid to cool airflow directed to the interior space; a plurality of coolers configured to cool the working fluid; a thermal energy storage (TES) component thermally coupled to the interior space heat exchange loop via the plurality of heat exchangers arranged along the interior space heat exchange loop; and a controller communicatively coupled to the plurality of coolers and the TES component, wherein the controller is configured to regulate the output cooling capacity of the plurality of coolers and regulate the distribution of cooling capacity from the TES component to maintain the electrical load of the climate control system at or below a baseline electrical load.
[0081] Technical Solution 8: The climate control system according to any one of the technical solutions, wherein the TES component includes a cryogenic fluid source in fluid communication with a plurality of heat exchangers, wherein each of the plurality of heat exchangers is positioned upstream of a corresponding cooler among a plurality of coolers along an internal space heat exchange loop.
[0082] Technical Solution 9: A climate control system according to any one of the technical solutions, wherein the controller is configured to regulate the distribution of cooling capacity from the TES component by adjusting the flow rate of cryogenic fluid from the source to one or more of the plurality of heat exchangers.
[0083] Technical Solution 10: A climate control system according to any one of the technical solutions, wherein each of the plurality of coolers includes a refrigeration circuit, the refrigeration circuit includes a compressor, and wherein the controller is configured to regulate the output cooling capacity of the plurality of coolers by adjusting the speed of the compressor of one or more of the plurality of heat exchangers.
[0084] Technical Solution 11: The climate control system according to any one of the technical solutions, wherein the cryogenic fluid source includes a tank configured to maintain a certain volume of cryogenic fluid, and wherein the TES further includes one or more recharge coolers configured to reduce the temperature of the cryogenic fluid and output the cryogenic fluid to the tank.
[0085] Technical Solution 12: The climate control system according to any one of the technical solutions further includes: a bus electrically connected to a plurality of coolers and one or more recharge coolers; and a solar power generation module electrically connected to the bus, wherein the controller is configured to operate one or more recharge coolers such that the electrical load of the one or more recharge coolers is equal to or less than the current generated by the solar power generation module.
[0086] Technical Solution 13: A climate control system according to any one of the technical solutions, wherein the controller is configured to: receive a weather forecast for the upcoming day; and determine a baseline electrical load based at least in part on the highest temperature in the weather forecast.
[0087] Technical Solution 14: A climate control system according to any one of the technical solutions, wherein the controller is further configured to determine the baseline electrical load based at least in part on the cooling capacity stored in the TES component.
[0088] Technical Solution 15: A method for operating a building climate control system, the method comprising: (a) receiving weather data for a future day for the geographic area where the building is located; (b) determining the total available cooling capacity of thermal energy storage (TES) components of the climate control system; (c) determining a baseline electrical load for operating the climate control system based at least on the weather data and the total available cooling capacity of the TES components; and (d) determining the output cooling capacity of a plurality of coolers of the climate control system and a cooling capacity allocation from the TES components, the allocation being configured to meet the cooling needs of the building when the electrical load of the climate control system is equal to or less than the baseline electrical load.
[0089] Technical Solution 16: The method according to any one of the technical solutions, wherein a plurality of coolers are configured to cool working fluid flowing along an internal space heat exchange loop of a climate control system, wherein the TES component includes: a cryogenic fluid source; and a plurality of heat exchangers connected to the internal space heat exchange loop such that each of the plurality of heat exchangers is located upstream of a corresponding one of the plurality of coolers along the internal space heat exchange loop, the heat exchangers being configured to receive a cryogenic fluid flow from the cryogenic fluid source to cool the working fluid; and wherein the method further includes: (e) distributing the cooling capacity from the TES component according to a distribution by adjusting the flow rate of the cryogenic fluid flowing to one or more of the plurality of heat exchangers.
[0090] Technical Solution 17: The method according to any one of the technical solutions, wherein each of the plurality of coolers includes a refrigeration circuit, the refrigeration circuit including a compressor; and wherein the method further includes: (f) adjusting the output cooling capacity of one or more coolers in the plurality of coolers by adjusting the speed of each compressor in one or more coolers in the plurality of coolers.
[0091] Technical Solution 18: The method according to any one of the technical solutions, wherein the cryogenic fluid source of the TES module includes a tank; wherein the TES module further includes one or more recharge coolers configured to reduce the temperature of the cryogenic fluid and output the cryogenic fluid to the tank; wherein the method further includes: (g) determining the current generated by the solar power generation module of the climate control system; and (h) operating one or more recharge coolers such that the electrical load of the one or more recharge coolers is equal to or less than the current generated by the solar power generation module.
[0092] Technical Solution 19: The method according to any one of the technical solutions, wherein the cryogenic fluid source of the TES component includes a tank; wherein the TES component further includes one or more recharge coolers configured to reduce the temperature of the cryogenic fluid and output the cryogenic fluid to the tank; wherein the method further includes: (i) determining that the electrical load of the climate control system is lower than the baseline electrical load; and (j) operating one or more recharge coolers such that the difference between the electrical load of the climate control system and the baseline electrical load decreases in response to (i).
[0093] Technical Solution 20: The method according to any one of the technical solutions, wherein the weather data includes a temperature profile for the upcoming day, wherein (c) includes determining a baseline electrical load configured to provide full release of the cooling capacity available to the TES components during the peak period of the temperature profile for the upcoming day.
[0094] The embodiments disclosed herein include systems and methods for designing and operating climate control systems configured to significantly reduce the electrical load requirements of the climate control system over a 24-hour period. In some embodiments, the climate control system according to the embodiments disclosed herein may employ a thermal storage component configured to supplement the output capacity of the climate control system during peak periods, thereby significantly reducing the peak electrical load of the climate control system. Therefore, by using the embodiments disclosed herein, commercial building owners or operators can reduce the total electrical load that must be reserved for the operation of a building's climate control system, and this additional electrical load capacity can be further monetized or used for other purposes.
[0095] The foregoing discussion has provided various exemplary embodiments. However, those skilled in the art will understand that the examples disclosed herein have broad applications, and the discussion of any embodiment is merely illustrative and does not imply that the scope of this disclosure, including the claims, is limited to that embodiment.
[0096] The accompanying drawings are not necessarily drawn to scale. Some features and components in this article may be shown at an enlarged scale or in some schematic form, and for clarity and simplicity, some details of conventional components may not be shown.
[0097] In the discussion and claims herein, the terms “comprising” and “including” are used in an open-ended manner and should therefore be interpreted as “including but not limited to”. Furthermore, the terms “couple” or “couples” are intended to indicate an indirect or direct connection. Thus, if a first device is coupled to a second device, the connection can be a direct connection between the two devices or an indirect connection established via other devices, components, nodes, and connections. Additionally, as used herein, the terms “axial” and “axially” generally refer to along or parallel to a given axis (e.g., the central axis of a body or port), while the terms “radial” and “radially” generally refer to perpendicular to a given axis. For example, axial distance refers to a distance measured along or parallel to an axis, and radial distance refers to a distance measured perpendicular to an axis. Furthermore, when used herein (including in the claims), the words “about,” “substantially,” “essentially,” “approximately,” etc., when referring to said values, mean within ±10% of said value.
[0098] While exemplary embodiments have been shown and described, those skilled in the art may modify them without departing from the scope or teachings herein. The embodiments described herein are exemplary only and not restrictive. Many variations and modifications of the systems, devices, and processes described herein are possible and are within the scope of this disclosure. Therefore, the scope of protection is not limited to the embodiments described herein, but is limited only by the following claims, the scope of which should include all equivalents of the subject matter of the claims. Unless otherwise expressly stated, the steps in the method claims may be performed in any order. The statement of identifiers such as (a), (b), (c) or (1), (2), (3) before the steps in the method claims is not intended to specify a particular order of the steps, but is used to simplify subsequent references to these steps.
Claims
1. A climate control system for regulating an interior space, the climate control system comprising: An internal space heat exchange loop is configured to circulate working fluid to cool the airflow directed into the internal space; A cooler configured to cool the working fluid; as well as Thermal energy storage components, including: Cryogenic fluid source; as well as A heat exchanger is connected to the internal space heat exchange loop such that the heat exchanger is located upstream of the cooler along the internal space heat exchange loop, the heat exchanger being configured to receive a cryogenic fluid flow from the source to cool the working fluid, thereby supplementing the output cooling capacity of the cooler.
2. The climate control system according to claim 1, characterized in that, The cooler includes a refrigeration circuit, which includes a compressor, and the compressor mechanism is configured to operate at multiple different speeds to adjust the output cooling capacity of the cooler.
3. The climate control system according to claim 1, characterized in that, The cryogenic fluid source includes a tank configured to maintain a certain volume of cryogenic fluid, and wherein the thermal energy storage assembly further includes a recharge cooler configured to reduce the temperature of the cryogenic fluid and output the cryogenic fluid to the tank.
4. The climate control system according to claim 3, characterized in that, The thermal energy storage assembly also includes one or more valves configured to control the flow rate of cold fluid to the heat exchanger.
5. The climate control system according to claim 4, characterized in that, It also includes a controller, which is configured to: Regulating the flow rate of the cold fluid to the heat exchanger; and Adjust the output cooling capacity of the cooler.
6. The climate control system according to claim 4, characterized in that, Also includes: A busbar, which is electrically connected to the cooler and the recharge cooler; as well as A solar power generation module, which is electrically connected to the busbar.
7. A climate control system for regulating an interior space, the climate control system comprising: An internal space heat exchange loop is configured to circulate working fluid to cool the airflow directed into the internal space; Multiple coolers configured to cool the working fluid; A thermal energy storage component, which is thermally connected to the internal space heat exchange loop via a plurality of heat exchangers arranged along the internal space heat exchange loop; as well as A controller, communicatively connected to a plurality of coolers and a thermal energy storage assembly, wherein the controller is configured to regulate the output cooling capacity of the plurality of coolers and regulate the distribution of cooling capacity from the thermal energy storage assembly to keep the electrical load of the climate control system at or below a baseline electrical load.
8. The climate control system according to claim 7, characterized in that, The thermal energy storage assembly includes a cryogenic fluid source in fluid communication with the plurality of heat exchangers, wherein each of the plurality of heat exchangers is positioned upstream of a corresponding cooler along the internal space heat exchange loop.
9. The climate control system according to claim 8, characterized in that, The controller is configured to regulate the distribution of cooling capacity from the thermal energy storage assembly by adjusting the flow rate of cryogenic fluid from the source to one or more of the plurality of heat exchangers.
10. The climate control system according to claim 8, characterized in that, Each of the plurality of coolers includes a refrigeration circuit, the refrigeration circuit including a compressor, and wherein the controller is configured to regulate the output cooling capacity of the plurality of coolers by adjusting the speed of the compressor of one or more of the plurality of heat exchangers.
11. The climate control system according to claim 8, characterized in that, The cryogenic fluid source includes a tank configured to hold a volume of cryogenic fluid, and wherein the thermal energy storage assembly further includes one or more recharge coolers configured to reduce the temperature of the cryogenic fluid and output the cryogenic fluid to the tank.
12. The climate control system according to claim 11, characterized in that, Also includes: A busbar electrically connected to the plurality of coolers and the one or more recharge coolers; as well as Solar power generation components, which are electrically connected to the busbar. The controller is configured to operate the one or more recharge coolers such that the electrical load of the one or more recharge coolers is equal to or less than the current generated by the solar power generation module.
13. The climate control system according to claim 7, characterized in that, The controller is configured such that: Receive the weather forecast for the next day; and The baseline electrical load is determined at least in part based on the highest temperature in the weather forecast.
14. The climate control system according to claim 13, characterized in that, The controller is also configured to determine the baseline electrical load based at least in part on the cooling capacity stored in the thermal energy storage component.