Large-span membrane structure and rapid installation method thereof

Through modular design and rapid installation methods of prefabricated frame structures, the problem of the installation of large-span membrane structures in the material yard affecting production is solved, and efficient and economical membrane structure installation is achieved, and construction efficiency and cost-effectiveness are improved.

CN118958497APending Publication Date: 2024-11-15SHANGHAI BAOYE GRP CORP
View PDF 0 Cites 4 Cited by

Patent Information

Application Number
CN202410944129.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing large-span membrane structure installation method consumes a lot of mechanical shift costs in the material yard, affecting production, and has low installation efficiency and low economical style.

Method used

The large-span film structure with a modular design, including the membrane structure and the supporting film structure. The prefabricated frame structure and the supporting film structure are assembled and hoisted in sections using the floor tire frame, and the traction and fixation of the membrane unit is combined with the hoist and the wire rope. Achieve quick installation.

Benefits of technology

The construction process is simplified, the impact on the production line is reduced, the film material loss and machinery use cost are reduced, the installation speed and efficiency are improved, and the construction period is shortened.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958497A_ABST
    Figure CN118958497A_ABST
Patent Text Reader

Abstract

The invention discloses a large-span membrane structure and a rapid installation method thereof, the membrane structure comprises a membrane material structure and a membrane supporting structure, and the membrane material structure is arranged on the membrane supporting structure; the membrane material structure comprises a plurality of first membrane units and second membrane units; the film supporting structure comprises a roof film supporting structure, an external corner film supporting structure and a gable wall film supporting structure. The mounting method comprises the steps of membrane structure frame structure design, membrane structure deepening design and factory prefabrication; the frame structure and the film supporting structure are spliced in a segmented mode, and film units are cut and subjected to heat sealing; mounting a membrane material structure; and constructing the waterproof drape curtain and the like. The membrane is simple in structure, high in installation speed and low in cost, does not occupy the internal space of a material field, and can achieve the effect that material field production and membrane structure installation are carried out at the same time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of long-span membrane installation, and in particular to a long-span membrane structure and a rapid installation method thereof. Background Art

[0002] Large-span membrane structure is a form of lightweight building structure, usually using high-strength, weather-resistant and light-transmitting film materials as covering materials, combined with lightweight supporting structures. On the one hand, the membrane structure can achieve good sealing performance, and on the other hand, it can reduce the self-weight of the maintenance structure and reduce the amount of steel used in the skeleton. In the past, large-span membrane structures were mainly used in public buildings such as large venues. As the country's environmental protection control becomes more stringent, open-air storage sites such as material yards and coal yards are gradually adopting large-span membrane structures.

[0003] At present, the installation of large-span membrane structures usually adopts the on-site hoisting method, which uses a crane to hoist the membrane unit to the installation location, and then uses a car crane and manual laying of the membrane unit. This method not only consumes a lot of machine-shift costs, but also the car crane and membrane materials need to occupy the internal space of the material yard, affecting the normal production of the material yard, and the construction and production interfere with each other to a large extent, the installation efficiency is low, and the economy is low.

[0004] Therefore, how to avoid the use of large machinery affecting production and effectively reduce construction costs when installing large-span membrane structures in a material yard in a production state is a technical problem that urgently needs to be solved in this field. Summary of the invention

[0005] In view of the above problems, the purpose of the present invention is to provide a waterproof construction structure for the basement exterior wall that is simple, convenient to construct, and highly reliable. Through measures such as the treatment of construction joints during structural construction, the laying of waterproof membranes on the exterior walls during construction, and the installation of drainage boards on the inner side of the exterior walls, the leakage of the exterior walls can be effectively controlled to ensure the long-term waterproof effect of the exterior walls of the basement.

[0006] According to one aspect of the present invention, a long-span membrane structure is provided, comprising:

[0007] A membrane material structure and a membrane supporting structure, wherein the membrane material structure is arranged on the membrane supporting structure;

[0008] The membrane structure includes a plurality of first membrane units and second membrane units. The size of the first membrane unit is set according to the width between each two main trusses, and the area between each two main trusses is evenly divided into two first membrane units from the top of the arch truss; the size of the second membrane unit is set according to the width between the upper chords of the main trusses;

[0009] The membrane supporting structure includes a roof membrane supporting structure, a positive corner membrane supporting structure and a gable membrane supporting structure;

[0010] The roof membrane supporting structure is composed of a plurality of roof membrane supporting units, wherein the roof membrane supporting unit includes a first membrane supporting plate, at least two first rib plates are fixedly arranged in a vertical direction below the first membrane supporting plate, and the first rib plate is fixedly arranged above the upper chord tube of the roof arch truss below;

[0011] The outer corner film support structure is composed of a plurality of outer corner film support units, and the outer corner film support unit includes a second film support plate, the outer side of the second film support plate is set to be rounded, at least two second ribs are fixedly arranged below the second film support plate, and the lower side of the second rib is fixedly arranged on the outer top chord tube of the gable arch truss;

[0012] The gable supporting membrane structure is composed of a plurality of gable supporting membrane units, wherein the gable supporting membrane unit comprises a vertically arranged rectangular tube, wherein at least two third ribs are fixedly arranged in the horizontal direction of the rectangular tube, and the third ribs are fixedly arranged on the outer chord of the gable truss column at a side away from the rectangular tube;

[0013] During installation, the gable supporting membrane structure and the outer cantilevering position of the outer corner supporting membrane structure are kept consistent.

[0014] Further, in some embodiments, the thickness of the first membrane supporting plate and the second membrane supporting plate does not exceed 6 mm, and the first membrane supporting plate and the second membrane supporting plate have bolt holes on a side facing the larger membrane unit during installation.

[0015] Furthermore, in some embodiments, the membrane supporting structure is installed along the main truss pipeline, and the corresponding rib plate is cut at the ball node.

[0016] Furthermore, in some embodiments, the cutting lines of the membrane structure are orthogonal to the membrane fibers.

[0017] Furthermore, in some embodiments, the membrane material structure is made of PVDF membrane material, and the width of the membrane material heat-sealed weld is 50 mm.

[0018] According to another aspect of the present invention, a method for quickly installing a long-span membrane structure is provided, using the aforementioned long-span membrane structure, comprising the following steps:

[0019] Based on the working conditions at the construction site, we design the frame structure of the long-span membrane structure, including columns, beams, arches, and trusses, and generate the frame structure diagram;

[0020] Based on the frame structure diagram, a detailed design of the long-span membrane structure is performed to determine the number, shape and size of the membrane material structure and the membrane supporting structure, and a detailed design drawing is generated;

[0021] Prefabricate the frame structure and the membrane support structure in a factory based on the detailed design drawing;

[0022] After the frame structure is assembled in sections on the ground frame, the roof membrane supporting structure, the outer corner membrane supporting structure and the gable membrane supporting structure are respectively installed on the trusses corresponding to the frame structure using the ground frame; after the frame structure is hoisted and closed in sections, the membrane supporting structures at the corresponding sections are promptly connected to make a smooth transition;

[0023] Cutting the first film unit and the second film unit, and heat-sealing the cut film material structural units;

[0024] Install the membrane structural units from one side of the frame structure to the other side in sequence, or divide them into two groups and install them from the middle position to the gables on both sides respectively;

[0025] After the membrane structure is installed, waterproof curtain construction is carried out.

[0026] Further, in some embodiments, the first membrane unit installation comprises the following steps:

[0027] The area between every two main trusses is divided into two first membrane units from the top of the self-arch truss, and multiple winches are fixedly installed at the gutter position on one side of the self-arch truss;

[0028] When pulling the first membrane unit on the opposite side of the winch, pull the steel wire rope on each winch along the main truss to the gutter on the opposite side; when pulling the first membrane unit on the same side of the winch, install a guide pulley block at a position 2-3m away from the top of the arch truss, and return the steel wire rope to the gutter on the same side of the winch after passing through the pulley block; simultaneously start multiple winches to pull the first membrane units on both sides respectively through the steel wire ropes;

[0029] The first membrane units are tensioned and fixed respectively. The tensioning and fixing order of the first membrane units is to tension and fix the top short side of the first membrane unit first, then tension and fix the long side on one side of the first membrane unit, then tension and fix the opposite long side, and finally tension and fix the bottom short side.

[0030] Further, in some embodiments, the second membrane unit installation comprises the following steps:

[0031] The width of the second membrane unit is equal to the width between the upper chords of the main truss, and the length is equal to the arc length of the arch truss;

[0032] A plurality of winches are fixedly installed at the gutter position on one side of the self-arch truss;

[0033] Pulling the steel wire rope on each hoist along the main truss to the opposite gutter; and simultaneously starting multiple hoists to pull the second membrane unit through the steel wire rope;

[0034] The second membrane unit can be tensioned and fixed only after the first membrane units on both sides of the second membrane unit are tensioned and fixed. The tensioning and fixing order of the second membrane unit is to tension and fix the middle position first, then tension and fix one long side, then tension and fix the opposite long side, and finally tension and fix the bottom short sides on both sides.

[0035] Furthermore, in some embodiments, after the membrane structure is installed, a special force gauge is used to perform force sampling inspection on representative force application points of the tensioned membrane unit, and the force value has an allowable deviation of ±10%.

[0036] Furthermore, in some embodiments, when the membrane structure unit is heat-sealed, a certain pre-tension is applied to the membrane material in the welding area, the error value of the heat-sealing width of the membrane structure unit does not exceed 5%, and the deviation between the peripheral dimensions of the membrane structure unit after heat-sealing and the designed dimensions is not greater than 1%.

[0037] It should be understood that within the scope of the present invention, the above-mentioned technical features of the present invention and the technical features specifically described below (such as embodiments) can be combined with each other to form a new or preferred technical solution. Due to space limitations, they will not be described one by one here.

[0038] Compared with the prior art, the present invention has the following technical effects:

[0039] The large-span membrane structure of the present invention is simple and easy to install. During the installation process, it can save construction space, reduce the impact on the production line, reduce membrane material loss and crane hours, and has a fast installation speed. Material field production and membrane structure installation can be carried out simultaneously, which greatly saves project cost and construction period. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] The above and other features and advantages of the present invention will become more apparent by describing in detail exemplary embodiments thereof with reference to the attached drawings.

[0041] Figure 1 A schematic structural diagram of a roof membrane supporting unit according to an embodiment of the present invention is shown.

[0042] Figure 2 A schematic structural diagram of a positive corner support film unit according to an embodiment of the present invention is shown.

[0043] Figure 3 A schematic structural diagram of a gable membrane supporting unit according to an embodiment of the present invention is shown.

[0044] Figure 4 A front view of traction of the first membrane unit on the opposite side of the winch according to an embodiment of the present invention is shown.

[0045] Figure 5 A top view of pulling the first membrane unit on the opposite side of the winch according to an embodiment of the present invention is shown.

[0046] Figure 6 A front view of traction of the first membrane unit on the same side of the winch according to an embodiment of the present invention is shown.

[0047] Figure 7 A top view of traction of the first membrane unit on the same side of the winch according to an embodiment of the present invention is shown.

[0048] Figure 8 A flowchart showing a method for quickly installing a large-span membrane structure according to an embodiment of the present invention DETAILED DESCRIPTION

[0049] In order to make the purpose, technical solution, beneficial effects and significant progress of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in combination with the embodiments of the present invention. Obviously, all the embodiments described are only partial embodiments of the present invention, not all embodiments; based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0050] The present invention will be further described below in conjunction with specific implementations. It should be understood that these embodiments are only used to illustrate the present invention and are not intended to limit the scope of the present invention.

[0051] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present invention. The phrase appearing in various locations in the specification does not necessarily refer to the same embodiment, nor is it limited to mutually exclusive independent or alternative embodiments. Those skilled in the art should be able to understand that the embodiments herein may be combined with other embodiments without causing structural conflicts.

[0052] In the description of this article, unless otherwise clearly specified and limited, the technical terms "installed", "connected", "connected" and the like should be understood in a broad sense, and can be a movable connection, a fixed connection or an integral connection, or a connection through a certain connector. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of this application can be understood according to specific circumstances.

[0053] In the description of this document, terms indicating orientation or positional relationships, such as "up", "down", "left", "right", "horizontal", "vertical", "height", "length", and "width", are intended to accurately describe the embodiments and simplify the description, but are not intended to limit the parts or structures involved to have a specific orientation, be installed or operate in a specific orientation, and should not be construed as a limitation on the embodiments in this document.

[0054] In the description of this article, the terms "first", "second" and the like are only used to distinguish different objects, and cannot be understood as indicating relative importance or limiting the quantity, specific order or primary and secondary relationship of the described technical features. In the description of this article, the meaning of "plurality" is at least two.

[0055] Embodiments of the present invention will now be described in detail with reference to the accompanying drawings. Reference will now be made in detail to preferred embodiments of the present invention, examples of which are shown in the accompanying drawings. Whenever possible, the same reference numerals will be used throughout the drawings to represent the same or similar parts.

[0056] Based on one aspect of the present invention, the present application provides a long-span membrane structure, which is particularly suitable for a long-span tube truss membrane structure installation project in which the inner space of the membrane structure is in a production state. The long-span membrane structure of the present application includes:

[0057] A membrane material structure and a membrane supporting structure, wherein the membrane material structure is arranged on the membrane supporting structure.

[0058] The membrane structure includes a plurality of first membrane units and second membrane units. The size of the first membrane unit is set according to the width between each two main trusses, and the area between each two main trusses is divided into two first membrane units from the top of the arch truss; the size of the second membrane unit is set according to the width between the upper chords of the main trusses. Preferably, the division of membrane units is mainly determined based on factors such as membrane unit area, weight, lifting capacity, and membrane material tear resistance.

[0059] The membrane support structure includes a roof membrane support structure, a positive corner membrane support structure and a gable membrane support structure. The purpose is to design the membrane support structure into three structural forms according to the arch truss structure form and the PVDF membrane installation process and force requirements for different locations such as the arch top, the junction of the wall and roof, and the gable.

[0060] like Figure 1 As shown in the figure, the roof support membrane structure is composed of multiple roof support membrane units. Figure 1 The structure of one of the roof membrane supporting units is shown, and the roof membrane supporting unit includes a first membrane supporting plate 11, at least two first rib plates 12 are fixedly arranged in the vertical direction below the first membrane supporting plate 11, and the first rib plates are fixedly arranged above the upper chord tube 13 of the roof arch truss.

[0061] In one embodiment of the present invention, the roof membrane supporting unit uses a 6mm thick 120mm first membrane supporting plate, a 6*300mm specification first rib plate, the spacing between the first rib plates is set to 300mm, and the first membrane supporting plate is welded and fixed to the first rib plate.

[0062] like Figure 2As shown, the positive corner support membrane structure is composed of a plurality of positive corner support membrane units, and the positive corner support membrane unit includes a second support membrane plate 21, the outer side of the second support membrane plate 21 is set to be rounded, at least two second rib plates 22 are fixedly arranged below the second support membrane plate 21, and the lower part of the second rib plate 22 is obliquely fixedly arranged on the top chord tube 23 on the outer side of the gable arch truss.

[0063] In one embodiment of the present invention, the outer corner film support unit uses a 6mm thick 120mm second film support plate, a 6*300mm second rib plate, and the spacing between the second rib plates is set to 300mm. The second film support plate is welded and fixed to the second rib plate. The outer corner is at the junction of the roof and the gable. The outer corner film support unit structure can smoothly transition between the roof and the gable membrane structure. The outer side of the second film support plate is rounded when it is made to prevent damage to the membrane material.

[0064] like Figure 3 As shown, the gable supporting membrane structure is composed of a plurality of gable supporting membrane units, and the gable supporting membrane unit includes a vertically arranged rectangular tube 31, and the rectangular tube 31 is fixedly provided with at least two third ribs 32 in the horizontal direction, and the third ribs 32 are fixedly provided on the outer chord 33 of the gable truss column on the side away from the rectangular tube 31.

[0065] In one embodiment of the present invention, the gable membrane supporting unit is made by welding a 100×100×5mm rectangular tube and an 8*100mm third rib plate. The position of the gable membrane supporting unit is consistent with the external cantilever position of the corner membrane supporting unit, which can ensure a smooth transition of the membrane material at the corner.

[0066] During installation, the gable supporting membrane structure and the outer cantilevering position of the outer corner supporting membrane structure are kept consistent.

[0067] Furthermore, in some embodiments, the thickness of the first membrane supporting plate and the second membrane supporting plate does not exceed 6 mm, and the first membrane supporting plate and the second membrane supporting plate have bolt holes facing the side of the larger membrane unit during installation, so as to facilitate the installation of the membrane supporting structure at a later stage. As can be understood by those skilled in the art, since the overall curvature of the arch truss is relatively large, the thickness of the first membrane supporting plate and the second membrane supporting plate does not exceed 6 mm, so that it can be ensured that there is no need to bend into a corresponding curvature during processing, and the corresponding curvature can be naturally formed during installation.

[0068] Furthermore, in some embodiments, the membrane supporting structure is installed along the main truss pipeline, and the corresponding ribs are cut at the ball nodes, so as to ensure the linear shape of the entire membrane supporting structure and improve the aesthetics.

[0069] Furthermore, in some embodiments, the cutting line of the membrane structure is orthogonal to the membrane fiber. As those skilled in the art can understand, since the membrane is disconnected at the cutting line, stress concentration is easily generated there. If the shear stress at the cutting line is large, it will affect the stress performance of the membrane. Therefore, the cutting line should be orthogonal to the membrane fiber as much as possible, so that the main stress direction is consistent with the fiber direction to avoid shearing in the main stress direction.

[0070] Furthermore, in some embodiments, the membrane material structure is made of PVDF membrane material, and the width of the membrane material heat-sealed weld is 50 mm.

[0071] According to another aspect of the present invention, a method for quickly installing a large-span membrane structure is provided, using the large-span membrane structure as described above. Figure 8 As shown, the following steps are included:

[0072] S10. Design the long-span membrane frame structure based on the working conditions at the construction site, including columns, beams, arches, and trusses, and generate the frame structure diagram.

[0073] S20. Based on the framework structure diagram, a detailed design of the large-span membrane structure is performed to determine the number, shape and size of the membrane material structure and the membrane supporting structure, and a detailed design drawing is generated.

[0074] S30. Prefabricate the frame structure and the membrane supporting structure in a factory based on the detailed design drawing.

[0075] S40. After the frame structure is assembled in sections on the ground cradle, the roof membrane supporting structure, the outer corner membrane supporting structure and the gable membrane supporting structure are respectively installed on the trusses corresponding to the frame structure using the ground cradle; after the frame structure is hoisted and joined in sections, the membrane supporting structures at the corresponding sections are promptly connected to ensure a smooth transition.

[0076] As can be understood by those skilled in the art, after the frame structure, i.e., the arch truss, is assembled in sections on the ground frame, the roof membrane support structure, the outer corner membrane support structure, and the gable membrane support structure are respectively installed on the trusses corresponding to the frame structure using the ground frame, which can effectively reduce the amount of high-altitude work, reduce the difficulty of installing the membrane support structure, and ensure the installation quality of the membrane support structure. It should be noted that the installation quality should be checked in time during the cutting and installation of the membrane support structure to minimize the impact of structural errors on the PVDF membrane.

[0077] S50. Cut the first membrane unit and the second membrane unit, and heat-seal the cut membrane structure units; this step can be performed simultaneously with step S30 or S40, which can shorten the construction period and improve efficiency.

[0078] Furthermore, the cutting and processing of the membrane structure may include the following steps S501-S505:

[0079] S501. Raw material re-inspection. After the raw materials of membrane structures enter the factory, their mechanical properties such as tensile strength, tear stiffness, elongation, as well as combustion performance, light transmittance, durability and other properties must be re-inspected and they can only be used after being confirmed to be qualified.

[0080] S502. Membrane cutting. Use fully automatic membrane material processing equipment for fully automatic cutting, layout, etc. The equipment accuracy and control system must meet the processing requirements to ensure that the membrane cloth processing is under comprehensive and effective monitoring to ensure cutting quality.

[0081] Preferably, the design tension and elongation should be considered before cutting, and the tensile strength, local pressure, etc. should be verified according to the membrane surface shape, stress size at the membrane corner and weld width, and finally the cutting size of each membrane unit should be determined, and the membrane material should be cut according to the relevant parameters.

[0082] Preferably, the formation of the curved surface of the membrane structure is related to the initial pre-tension, and the elastic retraction of the membrane material after stress release must be considered during cutting. The influence of the pre-tension in the membrane can be eliminated by correcting the size of the cut membrane sheet (retraction along the warp and weft directions) according to the initial pre-tension and the performance of the membrane material used.

[0083] Preferably, the dimensional deviation of the diaphragm below 10m in each direction should not be greater than ±3mm, and the dimensional deviation of the diaphragm above 10m in each direction should not be greater than ±6mm.

[0084] S503. Film heat sealing. According to the area of ​​the film to be processed and the type of material, the LHP-SS2 fully automatic heat sealing equipment is selected to heat seal the cut film. Before heat sealing the film, a heat sealing process evaluation test should be carried out according to the characteristics of the film to determine the film connection method, butt width, process parameters of the heat sealing machine, number of heat sealing layers and heat sealing form. The inventor finally determined through experiments that the PVDF film weld width is 50mm, and the tensile strength of the P-type film heat-sealed part should not be less than 80% of the parent material strength.

[0085] S504. During the formal processing, first align the membrane at the joint, check whether the front and back of the membrane material and the joint sequence are correct, clean the area to be welded; perform heat sealing according to the parameters obtained from the heat sealing test. Finally, bury the rope and reinforce the corners according to the design drawings. When heat sealing, it is advisable to use tension welding, that is, to apply a certain pre-tension to the membrane material in the area to be welded, so as to reduce the shrinkage of the membrane material caused by heat sealing and improve the stress state at the weld after tension forming. During the heat sealing process, the operation should be carried out strictly in accordance with the test parameters, and the heat sealing process records should be kept. The error value of the heat sealing width of the membrane material should not exceed 5%, and the deviation of the peripheral dimensions of the heat-sealed membrane unit from the design dimensions should not be greater than 1%.

[0086] S505. Determine the unfolding direction of the membrane surface and the order of folding and packaging according to the conditions of the construction site and installation equipment. After cleaning both sides of the processed membrane surface, fold and package it according to the specified requirements. The unfolding direction should be marked on the soft packaging bag, and then packed in wooden boxes for easy transportation.

[0087] S60. Install the membrane material structural units sequentially from the gable on one side of the frame structure to the other side, or divide them into two groups and install them from the middle position to the gables on both sides respectively.

[0088] In some embodiments, after the membrane structure arrives at the site, its packaging will be checked to see if it is intact, and the accompanying quality certification documents will be checked. The corresponding membrane unit will be hoisted to the corresponding gutters on both sides of the arch truss according to the packaging number.

[0089] Further, in some embodiments, in combination Figures 4 to 7 The first membrane unit installation includes the following steps S601-S603:

[0090] S601. Combine Figure 4 The area between every two main trusses is evenly divided into two first membrane units from the top of the self-arch truss, and a plurality of winches 62 are fixedly installed at the position of the gutter 61 on one side of the self-arch truss.

[0091] Specifically, in one embodiment of the present invention, the area between the two main trusses is divided into two first membrane units, namely the south membrane unit and the north membrane unit, from the top of the arch truss; before the membrane unit is pulled, four 3-ton winches are installed at the corresponding positions of the south gutter, and the base of each winch is connected and fixed to the concrete structure by planting four M16 chemical bolts.

[0092] S602. Combine Figures 4 to 5 When the first membrane unit 63 on the opposite side of the winch 62 is pulled, the wire rope 64 on each winch 62 is pulled along the main truss 65 to the opposite gutter 61. Figure 6 to Figure 7 When the first membrane unit 63 on the same side of the winch 62 is towed, a guide pulley block 66 is installed at a position 2-3m away from the top of the arch truss, and the wire rope 64 passes through the pulley block 66 and returns to the gutter 61 on the same side of the winch 63; at the same time, multiple winches 62 are turned on to tow the first membrane units on both sides through the wire ropes 64.

[0093] Specific, combined Figures 4 to 5 In one embodiment of the present invention, the north membrane unit (i.e., the first membrane unit 63 on the opposite side of the winch 62) is first pulled from the south gutter. The four Φ16mm steel wire ropes 64 on the south gutter winch are pulled along the main truss to the north gutter, and the steel wire ropes 64 are respectively connected to the four sets of triangular tooling 67 ( Figure 5Only two sets are shown in the figure. Each triangular tooling 67 is connected to 6 clamps 68, and the spacing between the clamps 68 is 300mm. The clamps 68 are then used to evenly clamp the folded north membrane unit located in the north concrete gutter. Two acrylic ropes are used to tie the clamps in the middle position of the two triangular toolings 67 respectively. Before traction of the north membrane unit, soft tape or discarded membrane material is laid in advance at the positive corner of the north concrete gutter retaining wall to avoid damage to the membrane unit during traction. After the preparation work is completed, the membrane material traction path should be checked again to ensure that the path is clean and free of dirt, and to ensure that there are no sharp burrs to avoid damage or contamination to the membrane surface. At the same time, the four winches are turned on, and the north membrane unit begins to slowly lift along the traction route. Two workers are arranged on both sides of the traction route to hold acrylic ropes to shake the membrane surface to assist in the traction of the membrane surface, and to observe and coordinate at any time to deal with possible problems in the traction process. When one end of the north membrane surface is pulled to the designed position (top of the arch truss), the winch is stopped, and then the two corner areas at the top of the north membrane unit and several positions on the long side are temporarily fixed with clamps (to prevent the membrane surface from being affected by strong winds after being put in place), and the traction tooling and corresponding traction clamps are removed. At this time, the north membrane unit is basically in place. It should be noted that due to the large wind-driving area of ​​the first membrane unit, attention should be paid to weather conditions during construction. In case of adverse conditions such as cloudy days or possible changes in weather, the membrane units should be bundled into a cylinder with a diameter of 1-1.5m every 8-10m during the membrane material traction process to prevent adverse effects caused by sudden increases in wind force at high altitudes.

[0094] Secondly, combined Figure 6 to Figure 7 The south membrane unit is pulled in the south gutter. When pulling the south membrane unit, the folded membrane material is placed in the south gutter 61, which is on the same side as the winch 62. A guide pulley block 66 is installed 2-3m north of the top of the truss. The wire rope 64 passes through the pulley block 66 and returns to the south gutter 61. The triangular tooling 67 is connected to complete the pulling of the south membrane unit. The rest of the construction method is similar to the pulling of the north membrane unit.

[0095] S603. Tension and fix the first membrane units respectively. The order of tensioning and fixing the first membrane units is to tension and fix the top short side of the first membrane unit first, then tension and fix the one long side of the first membrane unit, then tension and fix the opposite long side, and finally tension and fix the bottom short side.

[0096] Specifically, in one embodiment of the present invention, tensioning and fixing the first membrane unit includes the following steps S6031-S6034:

[0097] S6031. Tension and fix the short side of the top of the first membrane unit. First, arrange the membrane surface of the first membrane unit, use two 300mm aluminum alloy strips to press and fix one corner of the upper end of the first membrane unit on the membrane support plate, and then use the membrane pressing plate and stainless steel self-tapping screws to fix the short side of the top from left to right. The tensioning force is controlled at 75% (±10%) of the tensile strength of the membrane material in the weft direction. This process is mainly controlled by the tensioning force. Move the tensioning point every 3m until the tensioning and fixation of the short side of the top of the first membrane unit is completed. When fixing the membrane surface, pay attention to keep the buried rope close to the side of the membrane pressing plate to prevent the membrane from being displaced due to stress in the later stage.

[0098] S6032. The long side of the first membrane unit is tensioned and fixed. The construction method is similar to the tensioning and fixing method of the short side at the top of the first membrane unit. The difference is that the tensioning direction is from the top to the bottom along the arch axis, and the long side is fixed with a pressure strip and a 10mm diameter stainless steel bolt until the long side is fixed.

[0099] S6033. Tension and fix the other long side of the first membrane unit. After fixing the first long side of the first membrane unit, start tensioning and fixing the other long side of the first membrane unit. Use 6 sets of clamps, wire ropes and lever hoists, with a spacing of 300mm between each clamp. The clamps are fixed to the upper chord of the main truss through shackles, wire ropes, lever hoists and rope buckles. Among them, 5 sets of tensioning equipment are parallel to each other and perpendicular to the axis direction of the upper chord of the arch truss. The last set of tensioning equipment is tensioned downward at a 45° angle with the other tensioning equipment. The 6 sets of tensioning equipment are tensioned at the same time, and the tensioning force is controlled at 75% (±10%) of the tensile strength of the membrane material in the longitudinal direction. The tensioning process is mainly controlled by displacement, supplemented by tensioning force control. After a section of tensioning is completed, the membrane pressing plate is fixed, and then the tensioning equipment is moved to the next tensioning and fixing process until the tensioning and fixing of the long side of the membrane unit is completed.

[0100] S6034. Tension and fix the short side of the bottom of the membrane unit. The tensioning method of the bottom of the membrane unit is the same as that of the top, except that one end of the hand hoist is connected to the clamp, and the other end is connected to the 25mm diameter steel bar implanted in advance on the side wall of the concrete gutter.

[0101] Further, in some embodiments, the second membrane unit installation includes the following steps S611-S614:

[0102] S611. The width of the second membrane unit is equal to the width between the upper chords of the main truss, and the length is equal to the arc length of the arch truss;

[0103] Specifically, in one embodiment of the present invention, the width of the second membrane unit is about 6m, which is relatively narrow and is located directly above the main truss. The length is equivalent to the arc length of the entire arch truss. Two sets of traction triangle tooling and two winches can be used for traction. The traction method refers to the above-mentioned method of traction of the first membrane unit on the opposite side of the winch, with the difference that the second membrane unit has only one piece and can be pulled into place at one time.

[0104] S612. Multiple winches are fixedly installed at the gutter position on one side of the self-arch truss;

[0105] S613. Pull the steel wire rope on each of the winches along the main truss to the opposite gutter; and simultaneously start multiple winches to pull the second membrane unit via the steel wire rope.

[0106] S614. The second membrane unit can be tensioned and fixed only after the first membrane units on both sides of the second membrane unit are tensioned and fixed. The tensioning and fixing order of the second membrane unit is to tension and fix the middle position first, then tension and fix one long side, then tension and fix the opposite long side, and finally tension and fix the bottom short sides on both sides.

[0107] Specifically, in one embodiment of the present invention, tensioning and fixing the second membrane unit includes the following steps: the second membrane unit is located directly above the main truss and is a whole membrane unit. The second membrane unit can be tensioned and fixed only after the first membrane units on both sides of the second membrane unit are tensioned and fixed. The tensioning and fixing sequence of the second membrane unit is to first tension and fix the middle position (highest point) of the narrow membrane, then tension and fix one long side, then tension and fix the opposite long side, and finally tension and fix the bottom short side. The entire tensioning and installation method is similar to that of the first membrane unit.

[0108] S70. After the membrane structure is installed, waterproof curtains are constructed. Specifically, after the entire roof membrane unit is installed, waterproof curtains are constructed in sections and blocks. After the waterproof curtains are cut by the processing factory, they are hot-melted on site using a handheld hot air gun. Before hot melting, hot melting process tests should be performed as required to determine parameters such as hot melting temperature, speed and width. Before formal hot melting, clean the area to ensure that there is no dust or debris to ensure the quality of waterproof curtain construction. After the waterproof curtains are fully constructed, a water spray test should be performed to ensure that the structure is leak-proof.

[0109] Furthermore, in some embodiments, after the membrane structure is installed, a special force gauge is used to perform force sampling on representative force application points of the tensioned membrane unit, and the force value has an allowable deviation of ±10%, which is specifically selected by the design unit, the supervision unit and the construction unit.

[0110] Furthermore, in some embodiments, when the membrane structure unit is heat-sealed, a certain pre-tension is applied to the membrane material in the welding area, the error value of the heat-sealing width of the membrane structure unit does not exceed 5%, and the deviation between the peripheral dimensions of the membrane structure unit after heat-sealing and the designed dimensions is not greater than 1%.

[0111] Furthermore, in some embodiments, burrs, sharp corners, and sharp points at the connection between the membrane structure and the supporting membrane structure, frame structure, etc. will cause stress concentration at that location, and scratches on the membrane structure coating will also affect the service life of the membrane structure. Before and during installation, the upper surface of the supporting membrane structure and the frame structure should be carefully checked for burrs, welding slag, or foreign matter. The top corner concrete of the gutter parapet in front of the traction membrane unit should be paved with old membrane material or soft rubber material to prevent damage to the membrane surface during traction and tensioning and affect the normal service life.

[0112] Furthermore, in some embodiments, the membrane support plate at the same position is used to fix the membrane units on both sides thereof. Bolt holes with a spacing of 150 mm are arranged on the membrane support plate near the first membrane unit for fixing the wide membrane. During installation, attention should be paid to fixing the first membrane unit first, and then fixing the second membrane units on both sides of the first membrane unit, so as to avoid difficulty in inserting the bolts of the first membrane unit after fixing the second membrane unit.

[0113] Furthermore, in some embodiments, a dedicated person is assigned to take unified command during the membrane unit traction process, personnel should be arranged at the winch and the membrane unit lead-out side for real-time supervision, and relevant personnel should hold walkie-talkies and stop the process in time in case of emergency.

[0114] Furthermore, in some embodiments, although the PVDF membrane material has a strong self-cleaning property, its self-cleaning property is mainly reflected in that after being contaminated by dust, it can easily be kept clean by rain. However, when it is unfolded on the ground, it is easily contaminated by construction such as paint, and attention should be paid to the protection of the finished product during the construction process.

[0115] Furthermore, in some embodiments, the method for repairing damaged membrane surface during construction is as follows: if the membrane material is damaged during installation and the damage range is within 0.2-500mm, manual heat sealing can be performed, and the heat sealing is performed using a high-frequency manual heat sealing machine and a special PVDF membrane.

[0116] Furthermore, in some embodiments, the on-site repair method for membrane materials that are too large includes: if it is found during the installation process that the membrane material is too large, the existing membrane edge embedded rope can be pulled out first, and then the membrane material is folded back (the folded size is determined according to the actual oversized size on site), and the pulled out embedded rope is wrapped to form a new membrane edge (because the clamp needs to be directly shuttled and tensioning force is started, the effect of synchronously fixing the embedded rope is achieved, and there is no need to strengthen the edge heat sealing, but the size after folding should ensure that it is located in a position that can be normally covered by the drape), and then the clamp is shuttled and fixed, and after the clamp is fixed, the bolts are adjusted and fixed to complete the tensioning of the membrane material.

[0117] Furthermore, in some embodiments, the on-site repair method for a membrane material that is too small includes: if the membrane material is found to be too small during the installation process, the membrane material must first be removed and placed on a flat ground, and colored strips of cloth are laid on the ground. At the same time, based on the actual smaller size on site, the same type of membrane material from the same factory is heat-sealed on site.

[0118] Furthermore, in some embodiments, the on-site repair method for wrinkles generated after the membrane material is installed and formed includes: if the wrinkles do not affect the functional use of the project and do not cause the risk of water accumulation, they may not be processed after on-site consultation by all parties; if large-area wrinkles appear, a special tensioner may be used on-site to perform local tensioning and wrinkle removal. After the bolts are fixed, the excess membrane material may be cut, and then the surface layer of the part may be covered with a layer of the same type of membrane material from the same factory for reinforcement.

[0119] Furthermore, in some embodiments, during the construction process, if strong winds (level 4 to 5) or heavy rain are encountered, the deployed but unfinished membrane materials need to be reinforced with wind ropes to ensure the safety of personnel. After reinforcement, they need to be returned to the ground immediately, safely and orderly, and operations need to be stopped until the weather improves before construction can be resumed.

[0120] In summary, the large-span membrane structure and the rapid installation method thereof of the present invention have the following beneficial effects compared with the prior art:

[0121] 1. A large-span membrane structure of the present invention includes a membrane material structure and a membrane support structure, wherein the membrane material structure includes a plurality of first membrane units and a second membrane unit, and the membrane support structure includes a roof membrane support structure, a positive corner membrane support structure, and a gable membrane support structure. The modular combination design optimizes the layout and support of the membrane structure, and improves the stability and bearing capacity of the overall structure.

[0122] 2. A rapid installation method for a large-span membrane structure of the present invention prefabricates a frame structure and a membrane supporting structure, performs in-depth design of the membrane supporting structure in the frame structure design stage, and synchronously installs the membrane supporting structure in the frame structure installation stage. By prefabricating the membrane unit and then pulling the membrane unit outside the frame structure, it avoids affecting the production operations in the material yard in the production state, while improving the construction efficiency and shortening the construction period.

[0123] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.

Claims

1. Long-span membrane structure, characterized in that: include: A membrane material structure and a membrane supporting structure, wherein the membrane material structure is arranged on the membrane supporting structure; The membrane structure includes a plurality of first membrane units and second membrane units. The size of the first membrane unit is set according to the width between each two main trusses, and the area between each two main trusses is evenly divided into two first membrane units from the top of the arch truss; the size of the second membrane unit is set according to the width between the upper chords of the main trusses; The membrane supporting structure includes a roof membrane supporting structure, a positive corner membrane supporting structure and a gable membrane supporting structure; The roof membrane supporting structure is composed of a plurality of roof membrane supporting units, wherein the roof membrane supporting unit includes a first membrane supporting plate, at least two first rib plates are fixedly arranged in a vertical direction below the first membrane supporting plate, and the first rib plate is fixedly arranged above the upper chord tube of the roof arch truss below; The outer corner film support structure is composed of a plurality of outer corner film support units, and the outer corner film support unit includes a second film support plate, the outer side of the second film support plate is set to be rounded, at least two second ribs are fixedly arranged below the second film support plate, and the lower side of the second rib is fixedly arranged on the outer top chord tube of the gable arch truss; The gable supporting membrane structure is composed of a plurality of gable supporting membrane units, wherein the gable supporting membrane unit comprises a vertically arranged rectangular tube, wherein at least two third ribs are fixedly arranged in the horizontal direction of the rectangular tube, and the third ribs are fixedly arranged on the outer chord of the gable truss column at a side away from the rectangular tube; During installation, the gable supporting membrane structure and the outer cantilevering position of the outer corner supporting membrane structure are kept consistent.

2. The long-span membrane structure according to claim 1, characterized in that: The thickness of the first membrane supporting plate and the second membrane supporting plate does not exceed 6 mm. When installing, the first membrane supporting plate and the second membrane supporting plate have bolt holes on one side facing the larger membrane unit.

3. The long-span membrane structure according to claim 1, characterized in that: The membrane supporting structure is installed along the main truss pipeline, and the corresponding rib plate is cut when encountering a ball node.

4. The long-span membrane structure according to claim 1, characterized in that: The cutting line of the membrane structure is orthogonal to the membrane fibers.

5. The long-span membrane structure according to claim 1, characterized in that: The membrane material structure is made of PVDF membrane material, and the width of the membrane material heat-sealed weld is 50 mm.

6. A rapid installation method for a large-span membrane structure, characterized in that: The long-span membrane structure according to any one of claims 1 to 5 is adopted, comprising the following steps: Based on the working conditions at the construction site, we design the frame structure of the long-span membrane structure, including columns, beams, arches, and trusses, and generate the frame structure diagram; Based on the frame structure diagram, a detailed design of the long-span membrane structure is performed to determine the number, shape and size of the membrane material structure and the membrane supporting structure, and a detailed design drawing is generated; Prefabricate the frame structure and the membrane support structure in a factory based on the detailed design drawing; After the frame structure is assembled in sections on the ground frame, the roof membrane supporting structure, the outer corner membrane supporting structure and the gable membrane supporting structure are respectively installed on the trusses corresponding to the frame structure using the ground frame; after the frame structure is hoisted and closed in sections, the membrane supporting structures at the corresponding sections are promptly connected to make a smooth transition; Cutting the first film unit and the second film unit, and heat-sealing the cut film material structural units; Install the membrane structural units from one side of the frame structure to the other side in sequence, or divide them into two groups and install them from the middle position to the gables on both sides respectively; After the membrane structure is installed, waterproof curtain construction is carried out.

7. The rapid installation method according to claim 6, characterized in that: The installation of the first membrane unit includes the following steps: The area between every two main trusses is divided into two first membrane units from the top of the self-arch truss, and multiple winches are fixedly installed at the gutter position on one side of the self-arch truss; When pulling the first membrane unit on the opposite side of the winch, pull the steel wire rope on each winch along the main truss to the gutter on the opposite side; when pulling the first membrane unit on the same side of the winch, install a guide pulley block at a position 2-3m away from the top of the arch truss, and return the steel wire rope to the gutter on the same side of the winch after passing through the pulley block; simultaneously start multiple winches to pull the first membrane units on both sides respectively through the steel wire ropes; The first membrane units are tensioned and fixed respectively. The tensioning and fixing order of the first membrane units is to tension and fix the top short side of the first membrane unit first, then tension and fix the long side on one side of the first membrane unit, then tension and fix the opposite long side, and finally tension and fix the bottom short side.

8. The rapid installation method according to claim 7, characterized in that: The installation of the second membrane unit includes the following steps: The width of the second membrane unit is equal to the width between the upper chords of the main truss, and the length is equal to the arc length of the arch truss; A plurality of winches are fixedly installed at the gutter position on one side of the self-arch truss; Pulling the steel wire rope on each hoist along the main truss to the opposite gutter; and simultaneously starting multiple hoists to pull the second membrane unit through the steel wire rope; The second membrane unit can be tensioned and fixed only after the first membrane units on both sides of the second membrane unit are tensioned and fixed. The tensioning and fixing order of the second membrane unit is to tension and fix the middle position first, then tension and fix one long side, then tension and fix the opposite long side, and finally tension and fix the bottom short sides on both sides.

9. The rapid installation method according to claim 8, characterized in that: After the membrane structure is installed, a special dynamometer is used to perform force sampling inspection on representative force application points of the tensioned membrane unit, and the force value is allowed to have a deviation of ±10%.

10. The rapid installation method according to claim 6, characterized in that: When the membrane structure unit is heat-sealed, a certain pre-tension is applied to the membrane material in the welding area. The error value of the heat-sealing width of the membrane structure unit does not exceed 5%, and the deviation between the peripheral size of the membrane structure unit after heat sealing and the design size is not greater than 1%.

Citation Information

Cited By

  • Membrane material tensioning structure for frame structure and tensioning method of membrane material tensioning structure

    CN119572065A

  • Membrane tensioning structure for a frame structure and method for tensioning the same

    CN119572065B

  • Complex space cable truss and membrane structure synchronous tensioning and precision control method