AI Technical Summary

Technical Problem

Existing visualization systems for industrial technical systems fail to reliably display trend curves and forecasts due to smoothing effects from averaging or median value formation, leading to missed secondary alarms when the display period is too long, and distortions in future forecasts.

Method used

The visualization system determines the minimum and maximum values of process data points during the acquisition period and displays secondary alarms when these values exceed predetermined thresholds, ensuring that secondary alarms are not missed due to averaging or median value formation, and provides improved forecasting by displaying predicted alarms.

Benefits of technology

This approach allows operators to reliably evaluate trend curves and forecasts, preventing missed alarms and improving predictive accuracy by clearly indicating potential process issues.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader
Need to check novelty before this filing date? Find Prior Art

Description

[0001] The present invention relates to a visualization method for process data using a visualization system, wherein an industrial technical plant is controlled and monitored by a process control system, wherein the process control system records the process data at each recording time and archives the recorded process data in the sense of a history, wherein the visualization system, based on the selection of a process date and the specification of an associated display period by at least one operator, requests the history of the selected process date from the process control system for the specified display period and outputs the associated time course as a graphic to the at least one operator, wherein the graphic comprises a number of process data points, wherein the visualization system determines the respective process data point based on the values ​​of the selected process date of a respective recording period characteristic for the respective process data point,where the respective process data point is a mean or median value of the process data for the respective recording period.

[0002] The present invention further relates to a computer program for a visualization system, wherein the computer program comprises machine code that can be executed by the visualization system, The visualization system, based on the execution of the machine code, requests the history of the selected process data from a process control system that controls and monitors an industrial technical plant and records the process data at recording times and archives it in the sense of a history for the specified display period, based on the selection of a process data date and the specification of an associated display period by at least one operator, and outputs the associated temporal progression as a graphic to the at least one operator, wherein the graphic comprises a number of process data points, and wherein the visualization system, based on the execution of the machine code, determines the respective process data point based on the values ​​of the selected process data of a respective recording period characteristic for the respective process data point.where the respective process data point is a mean or median value of the process data for the respective recording period.

[0003] The present invention further relates to a visualization system, wherein the visualization system is programmed with such a computer program, such that the visualization system performs the above-mentioned process steps in connection with the computer program during operation.

[0004] The process data can be, for example, actual or setpoint values ​​of a controller. The mean can alternatively be a weighted or an unweighted mean. The median can, in particular, be a percentage median (xx%), where xx is a suitable value.

[0005] For the operation and monitoring of process plants, so-called process object views are of great importance. In the corresponding plant diagrams, block symbols are integrated for the process objects. These symbols graphically represent not only an important process value but also various status information, such as process alarms or simulation results. From these block symbols, views can be opened for the process objects that allow not only observation but also operation. From these views, further views can be opened, such as trend curves or an alarm view displaying the process alarms relevant to the respective process object. Trend curves typically show the progression of a given process value as a function of time. Process alarms are usually displayed as a message sequence, i.e.,in the form of a chronological list of the process alarms that occurred. The presentation of a trend curve, i.e., the temporal progression of the determined process data points, corresponds to the prior art, which is the basis for the present invention.

[0006] Approaches to enriching trend curves with suitable information about secondary alarms are already known in the prior art. Secondary alarms are alarms that are not triggered by the process control system, but by the visualization system. When a secondary alarm is triggered, the visualization system checks for the respective process data point whether the calculated mean or median value meets a condition defined by the operator. For example, if a process alarm is triggered as soon as a process data point exceeds the value x, the operator can specify that a secondary alarm is displayed when the value calculated for the respective process data point exceeds the value y, where the value y is sufficiently below the value x. A similar approach can be used to check whether the value calculated for the respective process data point falls below a value z.In the case of a secondary alarm, for example, the corresponding area of ​​the trend curve can be highlighted in color.

[0007] The aforementioned approach yields good results provided the display period specified by the operator is sufficiently short so that the number of process data points is at least as large as the number of process data points recorded during that period. However, operators typically set the display period in such a way that the number of process data points is smaller than the number of process data points recorded during that period, often considerably smaller. In this case, it can happen that, due to averaging or median calculation and the associated smoothing, it is no longer possible to detect that the process data recorded during a specific period exceeds the value y or falls below the value z once or several times. This problem is even more pronounced when future forecasts are generated based on the trend curves.Such forecasts are also significantly distorted by the smoothing associated with calculating the mean or median. US 2017 / 248942 A1 describes the display of a time-dependent value trend of a process measurement.

[0008] The object of the present invention is to create possibilities that enable the operator to reliably evaluate a trend curve. Furthermore, forecasts should be possible with the greatest possible reliability.

[0009] The problem is solved by a visualization method with the features of claim 1. Advantageous embodiments of the visualization method are the subject of dependent claims 2 to 4.

[0010] According to the invention, a visualization method of the type mentioned above is designed by: that the visualization system also determines the minimum and / or maximum values ​​of the selected process data during the respective recording period for the respective process data point, and that the visualization system displays a secondary alarm together with the respective process data point whenever the minimum determined for the respective process data point falls below a specified minimum value and / or the determined maximum exceeds a specified maximum value.

[0011] By additionally determining the minimum and / or maximum and subsequently determining the secondary alarms, it is no longer possible for a secondary alarm to go undetected due to averaging or median values ​​over an excessively long recording period and thus too much process data.

[0012] Preferably, the visualization method is designed in such a way that that the process data within the process control system are assigned to a respective process object, that the process control system automatically sets a process alarm whenever the process data assigned to the respective process object fulfills a predetermined triggering condition, that the process control system also records the currently set process alarms for each process object at the recording times and archives the recorded process alarms in accordance with the aforementioned history.The system stores the information that, along with the history of the selected process data for the same display period, the visualization system also requests the history of the process alarms assigned to the respective process object, and that the visualization system displays at least one of the process alarms along with the respective process data point whenever at least one process alarm occurred during the recording period assigned to the respective process data point.

[0013] The process alarm display immediately alerts the operator if a process alarm has occurred during the respective recording period. The predetermined triggering condition can be met, for example, if one of the object sizes exceeds or falls below a specific predefined value.

[0014] The display period can, for example, include the present if the operator specifies the content "show me process data x for the past y minutes" or a comparable specification. Utilizing the predicted minima and / or maxima in predicting secondary alarms also improves the determination of these predicted secondary alarms. Preferably, the visualization system also displays a predicted process alarm, along with the respective predicted process data point, whenever the predicted minimum and / or maximum fulfills the predetermined triggering condition. This allows the operator to recognize more reliably than with prior art whether and when a specific process alarm is imminent.

[0015] Preferably, the visualization system displays the determined minima and / or maxima based on an operator input from at least one person, along with the process data points, and suppresses the display of the determined minima and / or maxima based on an inverse operator input from the same person. This allows the operator to display the determined minima and / or maxima in the trend curve as needed, or to hide them from the trend curve.

[0016] The problem is further solved by a computer program having the features of claim 5. Advantageous embodiments of the computer program are the subject of dependent claims 6 to 8.

[0017] According to the invention, a computer program of the type mentioned above is designed in such a way that the visualization system is generated based on the processing of the machine code. For each process data point, the minimum and / or maximum values ​​of the selected process data during the respective recording period are also determined, and whenever the minimum determined for the respective process data point falls below a predefined minimum value and / or the maximum determined exceeds a predefined maximum value, a secondary alarm is displayed together with the respective process data point.

[0018] The advantages achieved thereby correspond to those of the visualization method. Furthermore, the advantageous features of the computer program also correspond to the advantageous features of the visualization method. The same applies to the advantages achieved by each of these advantageous features.

[0019] The problem is further solved by a visualization system with the features of claim 9. According to the invention, a visualization system of the type mentioned at the outset is programmed with a computer program according to the invention, such that the visualization system also executes the process steps of the computer program according to the invention during operation.

[0020] The properties, features, and advantages of this invention described above, as well as the manner in which they are achieved, will become clearer and more readily understandable in connection with the following description of the exemplary embodiments, which are explained in more detail in conjunction with the drawings. These show, in schematic representation: FIG 1 an overview of a plant, FIG 2 a process object, FIG 3 a flowchart, FIG 4 a flowchart, FIG 5 a timeline of a process date and a graph, FIG 6 a flowchart, FIG 7 a timeline of a process date and a graph, FIG 8 a flowchart, FIG 9 a timeline of a process date and a graph and FIG 10 a flowchart.

[0021] According to FIG 1 An industrial plant 1 is controlled and monitored by a process control system 2. The industrial plant 1 can be, for example, a process plant. However, it can also be another type of plant. The process control system 2 comprises control devices for individual parts of the industrial plant 1. The action of the control devices on the respective part of the industrial plant 1 and the interaction of the control devices with each other are managed by higher-level computers.

[0022] The process control system 2 is aware of so-called process objects 3. These process objects 3 can be defined, for example, during the design phase of the process control system 2. An example of a process object 3 is a controller that regulates a parameter of the industrial plant 1. However, there are also other types of process objects 3.

[0023] The process objects 3 are as shown in the representation in FIG 2 Within process control system 2, process data x, x*, Pi (i = 1, 2, ... m) are assigned to each process object 3. The process data x, x*, Pi can be, for example, actual values ​​x, setpoint values ​​x*, parameters Pi of a controller, and so on. The parameters Pi, for example, in the case of a PI controller, can be the proportional gain, the reset time, and the magnitude of the controller's maximum output. Process control system 2 also knows the assignment of the respective process data x, x*, Pi to the process objects 3.

[0024] As a rule, the process objects can be assigned 3 according to the representation in FIG 2 Process alarms Aj (j = 1, 2, ... n) are also assigned. In this case, the process control system 2 also knows the assignment of the respective process alarms Aj to the process objects 3. The process alarms Aj each have a priority. The respective priority is in FIG 2 The code Aj is placed in parentheses after the respective process alarm for illustrative purposes only.

[0025] The process control system 2 executes a control and monitoring procedure, which is described below in conjunction with FIG 3 will be explained in more detail.

[0026] According to FIG 3 In step S1, the process control system 2 receives a current state Z of the industrial plant 1. The current state Z includes, in particular, the actual values ​​x of the controllers. In step S2, the process control system 2 receives from an operator 4 (see FIG 1 ) Inputs are accepted. The inputs can include specifications for the process objects 3, for example, new setpoints x* for the controllers or a change in parameters Pi of the controllers. The term "operator" is used in a generic sense within the scope of the present invention. It can refer to a single operator or to several persons.

[0027] In step S3, the process control system 2 determines control variables for the industrial plant 1. In determining these control variables, the process control system 2 uses, in particular, the process data x, x*, Pi assigned to the individual process objects 3. In step S4, the process control system 2 outputs the determined control variables to the industrial plant 1 and thereby controls the industrial plant 1.

[0028] If the process control system 2, as is common practice, also sets process alarms, it checks in step S5 whether a triggering condition is met for a process alarm Aj. The process control system 2 performs this check individually for each process object 3 and, within each process object 3, individually for each process alarm Aj. The process control system 2 decides whether the respective triggering condition is met or not based on the process data x, x*, Pi assigned to the respective process object 3. The triggering condition can be met, for example, if a process data x, x*, Pi of the corresponding process object 3 – in particular, an actual value x – exceeds or falls below a certain predefined value, or if certain combinations of values ​​are present, or if other derived values ​​fall below or exceed certain limits.

[0029] If the triggering condition is met, the process control system 2 automatically sets the corresponding process alarm Aj in step S6 and transmits a corresponding alarm message M to a visualization system 5 (see FIG 1 Otherwise, if the triggering condition is not met, step S6 is skipped.

[0030] In step S7, the process control system 2 archives at least the process data x, x*, and Pi. Typically, in step S7, the process control system 2 also archives the currently set process alarms Aj. Archiving is performed in a historical manner. Each archived value x, x*, Pi, and Aj is therefore assigned its respective acquisition time. Furthermore, the already archived values ​​are not overwritten. Instead, the newly archived values ​​are added to the existing archived values, so that both the newly archived and the already archived values ​​are available for later analysis.

[0031] The approach of FIG 3 This process is repeated cyclically. From step S7, the process control system 2 thus returns to step S1. This cyclical repetition usually occurs at a fixed interval.

[0032] The visualization system 5 is programmed with a computer program 6. The computer program 6 comprises machine code 7, which can be executed by the visualization system 5. Due to the execution of the machine code 7, the visualization system 5 performs (among other things) a visualization procedure, which is described below in conjunction with FIG 4 will be explained in more detail.

[0033] In step S11, the visualization system 5 receives the transmitted alarm messages M from the process control system 2. In step S12, the visualization system 5 outputs the corresponding process alarms Aj – more precisely, corresponding messages – to the operator 4. The output of the respective process alarm Aj to the operator 4 can, for example, be visual. If necessary, the visual display can be supported by an audible signal. In step S13, the visualization system 5 checks whether it has received an acknowledgment for the respective process alarm Aj from the operator 4. As long as this is not the case, the visualization system 5 skips step S14. If, however, the visualization system 5 has received an acknowledgment for the corresponding process alarm Aj from the operator 4, the visualization system 5 terminates the output of the respective process alarm Aj to the operator 4 in step S14.

[0034] Steps S11 to S14 are generally present, but are of minor importance within the framework of the basic principle of the present invention.

[0035] In step S15, the visualization system 5 receives a selection of process data x, x*, Pi from the operator 4. In principle, the operator 4 can select any process data x, x*, Pi in step S15. However, it will often be an actual value x. In step S15, the visualization system 5 also receives a display period from the operator 4. Since the display period is defined by the operator 4, its length is not known in advance from the perspective of the visualization system 5. Therefore, from the perspective of the visualization system 5, the display period can, in principle, be arbitrary.

[0036] In step S16, the visualization system 5 requests from the process control system 2 at least the history of the selected process data x, x*, Pi for the specified display period. Typically, in step S16, the visualization system 5 also requests from the process control system 2 the history of the process alarms Aj assigned to the respective process object 3 for the same display period. In step S17, the visualization system 5 receives the requested process data x, x*, Pi and, if applicable, the requested process alarms Aj from the process control system 2.

[0037] In step S18, the visualization system 5 determines a graphic 8 (see FIG 1 and 5Figure 8 shows the time course of the selected process data x, x*, Pi for the specified display period. Secondary alarms A' can be assigned to the process data points 9. The secondary alarms A' are also determined in step S18. Step S18 is performed in conjunction with FIG 6 This will be explained in detail. Figure 8 shows the visualization system 5 outputting S19 to the operator 4 in one step.

[0038] According to FIG 6 The visualization system 5 first selects a first process data point 9 in step S21 to determine the graphic 8 (see FIG 5 In step S22, the visualization system 5 determines a corresponding acquisition period for the selected process data point 9. The respective acquisition period can encompass multiple acquisition times. If, for example, the graphic 8 can include a maximum of 200 process data points 9, but the process data x, x*, Pi and, if applicable, the process alarms Aj were acquired 10,000 times during the entire display period, then the process data x, x*, Pi and, if applicable, the process alarms Aj from multiple acquisition times must necessarily be combined for each process data point 9 in order to determine the respective process data point 9.

[0039] In step S23, the visualization system 5 then determines the corresponding value of the selected process data point 9 based on the values ​​of the selected process data x, x*, Pi archived during this acquisition period. For example, the visualization system 5 can use the unweighted mean (i.e., the sum of the values ​​divided by the number of values) or the weighted mean (i.e., the sum of the values ​​weighted by a respective weighting factor divided by the sum of the weighting factors) of the values ​​of the selected process data x, x*, Pi as the corresponding value. Alternatively, the value of the respective process data point 9 can be determined, for example, by a median value. The median value can, in particular, be a xx% median value, where xx is a suitable value between 0 and 100 (excluding the limits). The value of xx is usually between 40 and 60.

[0040] In step S24, the visualization system 5 determines the minimum (Min) of the values ​​archived for the selected process data point x, x*, Pi during this recording period. In step S25, the visualization system 5 checks whether the determined minimum (Min) falls below a minimum value (MIN). If so, in step S26, the visualization system 5 assigns a secondary alarm A' to the process data point 9. Otherwise, step S26 is skipped. The minimum value (MIN) can be set, for example, by the operator 4. In particular, the minimum value (MIN) can be chosen such that, as the process data point x, x*, Pi decreases, the secondary alarm A' is triggered before the corresponding process alarm Aj.

[0041] In step S27, the visualization system 5 determines the maximum value (Max) of the selected process data x, x*, Pi archived during this recording period. In step S28, the visualization system 5 checks whether the determined maximum value (Max) exceeds a maximum value (MAX). If so, in step S29, the visualization system 5 also assigns a secondary alarm (A') to the process data point 9. Otherwise, step S29 is skipped. The maximum value (MAX) can be set, for example, by the operator 4. In particular, the maximum value (MAX) can be chosen such that, as the process data x, x*, Pi increases, the secondary alarm (A') is triggered before the corresponding process alarm (Aj).

[0042] In step S30, visualization system 5 checks whether a process alarm Aj is assigned to the process data x, x*, Pi. If so, visualization system 5 assigns one of the process alarms Aj to the process data point 9 in step S31. Typically, the process alarm Aj with the highest priority is assigned in step S31. If no process alarm Aj is assigned to the process data x, x*, Pi, step S31 is skipped.

[0043] In step S32, the visualization system 5 checks whether it has already executed steps S22 to S31 for all process data points 9. If this is not the case, the visualization system 5 proceeds to step S33, in which it selects the next process data point 9. The visualization system 5 then returns to step S22. Otherwise, the procedure of FIG 6 finished.

[0044] The above described a procedure in which steps S24 to S26, steps S27 to S29, and steps S30 and S31 are all present. However, it is also possible to configure the procedure in which only steps S24 to S26 and steps S27 to S29, or only steps S24 to S26 and steps S30 and S31, or only steps S27 to S29 and steps S30 and S31 are present. Configurations are also possible in which only steps S24 to S26 or only steps S27 to S29 are present.

[0045] Figure 8 thus includes a number of process data points 9. FIG 5 On the one hand, it shows the progress of process data points 9. FIG 5 It also shows the progression of the determined minima (Min) and the progression of the determined maxima (Max). Furthermore, in FIG 5 The identified secondary alarms A' and the associated process alarms Aj are also shown.

[0046] It is possible that graphic 8 is output to operator 4 as it appears in FIG 5 This is shown. In this case, the temporal progression of the process data points 9 and the secondary alarms A' are displayed. Furthermore, the temporal progressions of the determined minima (Min) and maxima (Max) are also displayed, insofar as they have been determined. If applicable, the process alarms Aj are also displayed. In this context, it should be noted that while the display of the process alarms Aj is generally present, it is of minor importance within the scope of the present invention. The advantage of the representation according to FIG 5 The main problem is that if the recording period of a given process data point 9 encompasses multiple recording times, it is often no longer possible to determine from the data value of that process data point 9 whether, and if so, why, a specific process alarm Aj was triggered or a secondary alarm A' was detected. However, the display method just described provides the operator 4 with the information as to why this is the case and at which points they need to request a more detailed representation of process data x, x*, Pi to obtain complete information.

[0047] It is possible that graphic 8 always corresponds to the representation in FIG 5 is issued to operator 4. However, it is also possible that operator 4, as shown in the illustration, FIG 1 The visualization system 5 can be configured with an operator input I+ or its inverse, I-. If the operator 4 specifies the operator input I+, the output is displayed according to the representation in FIG 5 If, however, operator 4 specifies the inverse input I-, the output will be as shown in the diagram. FIG 7 According to the representation of FIG 7 Only the time series of process data points 9 and the secondary alarms A' (and, if applicable, the process alarms Aj) are displayed. The time series of the determined minimum values ​​(Min) and / or the determined maximum values ​​(Max) are not displayed. Operator 4 can therefore, as needed, show or hide the time series of the determined minimum values ​​(Min) and maximum values ​​within the display of process data points 9. If necessary, the display or hiding of the minimum values ​​(Min) and maximum values ​​can also be done individually.

[0048] The advantage of this suppression lies particularly in the fact that while the secondary alarms A' are still correctly determined, thus still providing operator 4 with the information on where to request a more detailed representation of process data x, x*, Pi to obtain complete information, the actual trend, i.e., the temporal progression of the process data points 9, is more readily apparent.

[0049] Because the display period is specified by the operator 4, it is also possible that the specified display period includes the present. For example, the operator 4 can specify to the visualization system 5 that the display period should extend from a point in the past, which is otherwise arbitrarily selectable (for example, from a certain time), until "now," or that the display period should extend from "now" into the past for a certain period of time (for example, 10 minutes or 3 hours). If this is the case, i.e., if the present is included, the procedure according to the invention is preferably carried out by the following in conjunction with FIG 8 The procedure described has been supplemented.

[0050] FIG 8 builds on the approach of FIG 6 Additionally, steps S41 to S47 are present. In step S41, the visualization system 5 uses the determined process data points 9 – that is, the process data points 9 determined for the display period – to calculate a forecast of the future course of the process data points 9. The forecast calculation can be performed in the same way as in the prior art. Therefore, the details of the calculation do not need to be discussed further.

[0051] The forecast is made for a forecast horizon H. The forecast horizon H extends according to FIG 9 From the present into the future. It is possible that the extent to which the forecast horizon H extends into the future is fixed for the visualization system 5. Alternatively, it is possible that the extent is determined by the visualization system 5 depending on the specified display period, for example, as a certain percentage of the display period. Alternatively, it is possible that the extent is specified for the visualization system 5 by the operator 4. However, the general statement, valid for any forecast, applies: the further into the future the forecast extends, the more uncertain it becomes.

[0052] In step S42, the visualization system 5 uses the determined minimum values ​​(Min) – that is, the minimum values ​​determined for the display period – to calculate a forecast of the future course of the minimum value (Min). The forecast can be calculated in the same way as in step S41. The only difference is that the basis for the calculation is not the process data points (9), but the minimum values ​​(Min). In step S43, the visualization system 5 checks whether a predicted minimum value (Min) falls below the minimum value (MIN). If this is the case, the visualization system 5 assigns a predicted secondary alarm (A') to the corresponding predicted process data point (9) in step S44. Otherwise, step S44 is skipped.

[0053] In step S45, visualization system 5 uses the determined maxima Max – that is, the maxima Max determined for the display period – to calculate a forecast of the future course of the maximum Max. The forecast can be calculated in the same way as in step S41. The only difference is that the basis for the calculation is not the process data points 9, but the maxima Max. In step S46, visualization system 5 checks whether a predicted maximum Max exceeds the maximum value MAX. If this is the case, visualization system 5 also assigns a predicted secondary alarm A' to the corresponding predicted process data point 9 in step S47. Otherwise, step S47 is skipped.

[0054] The above described a procedure in which both steps S42 to S44 and steps S45 to S47 are present. However, it is also possible to implement versions in which only steps S42 to S44 or only steps S45 to S47 are present.

[0055] Step S19 itself remains unchanged. However, within step S19, the following steps are performed as described in the diagram. FIG 9 Not only is the process data point 9 displayed for the current display period, but also the predicted process data point 9. The corresponding secondary alarms A' are also displayed for both types of process data point 9. The display of the time series of the minimum (Min) and the maximum (Max) can be configured as needed, as described in... FIG 9 The relevant process alarms (Aj) can be displayed or hidden. If required, the associated process alarms can also be shown for the display period. The time "now," i.e., the present, is in FIG 9 indicated by a vertical double line.

[0056] If the associated process alarms Aj are also displayed for the display period, the procedure is as follows: FIG 8 preferably according to the illustration in FIG 10 supplemented. According to FIG 10 Steps S42 to S44 are supplemented by steps S51 and S52, and steps S45 to S47 are supplemented by steps S53 and S54.

[0057] In step S51, visualization system 5 checks whether a predicted minimum (Min) meets the triggering condition. If so, visualization system 5 assigns a predicted process alarm (Aj) to the corresponding predicted process data point (9) in step S52. Otherwise, step S52 is skipped.

[0058] In step S53, visualization system 5 checks whether a predicted maximum Max fulfills the triggering condition. If so, visualization system 5 also assigns a predicted process alarm Aj to the corresponding predicted process data point 9 in step S54. Otherwise, step S54 is skipped.

[0059] If steps S51 and S52 and / or steps S53 and S54 are present, they will be performed according to the illustration in FIG 9 In addition to the actual process alarms Aj transmitted by the process control system 2, the predicted process alarms Aj are also displayed.

[0060] The invention has been explained above in its core form and in various advantageous embodiments. At its core, however, the present invention relates to the following situation: An industrial plant 1 is controlled and monitored by a process control system 2. At specific times, it records process data x, x*, Pi and archives this data as a history. Based on the selection of a process data point x, x*, Pi and the specification of a corresponding display period by an operator 4, a visualization system 5 requests the history of the selected process data point x, x*, Pi from the process control system 2 and outputs the corresponding time series as a graph 8 to the operator 4. The graph 8 comprises a number of process data points 9.Visualization system 5 determines the respective process data point 9 as the mean or median value of the values ​​of the selected process data x, x*, Pi for a specific acquisition period characteristic of that process data point 9. It also determines the minimum (Min) and / or the maximum (Max) of the values ​​of the selected process data x, x*, Pi during the respective acquisition period for each process data point 9. Whenever the minimum (Min) determined for the respective process data point 9 falls below a predefined minimum value (MIN) and / or the maximum (Max) determined exceeds a predefined maximum value (MAX), visualization system 5 displays a secondary alarm A' along with the respective process data point 9.

[0061] The present invention offers many advantages. First, it enables a trend display that is more intuitively understandable and easier for the operator 4 to grasp. Furthermore, it provides improved forecasting, particularly regarding future expected process alarms Aj and secondary alarms A'. This facilitates proactive interventions by the operator 4 in the process flow of the industrial plant 1. Moreover, it prevents secondary alarms A' from being omitted due to an "unfavorable" choice of display period, alarms that would be displayed with a "favorable" choice of display period. This also applies to the display according to [reference to relevant figure]. FIG 7 , since here too the determination of the secondary alarms A' is based on the minimum Min and / or the maximum Max, even if the minimum Mini and the maximum Max themselves are not displayed. Reference symbol list

[0062] 1. Industrial technical plant 2. Process control system 3. Process objects 4. Operator 5. Visualization system 6. Computer program 7. Machine code 8. Graphics 9. Process data points AjProcess alarms A'Secondary alarms HForecast horizon I+, I-operating inputs MAlarm message MaxMaximum MAXMaximum value MinMinimum MINMinimum value S1 to S54Steps x, x*, PiProcess data ZState

Claims

1. Visualisation method for process data (x, x*, Pi) by a visualisation system (5), - wherein an industrial technical installation (1) is controlled and monitored by a process control system (2), - wherein the process control system (2) at acquisition points in time in each case acquires the process data (x, x*, Pi) and the process data (x, x*, Pi) that is acquired is archived in the sense of a history, - wherein, owing to the selection of an item of process data (x, x*, Pi) and the specification of an associated display period of time by at least one operator (4) of the process control system (2) for the predetermined display period of time, the visualisation system (5) requests the history of the selected item of process data (x, x*, Pi) and outputs the associated temporal curve as a graphic (8) to the at least one operator (4), - wherein the graphic (8) comprises a number of process data points (9), characterised in that - the visualisation system (5) determines the respective process data point (9) with reference to the values of the selected item of process data (x, x*, Pi) of a respective acquisition period of time that is characteristic of the respective process data point (9), wherein the acquisition period of time comprises a plurality of acquisition points in time, - the respective process data point (9) is a mean value or a median value of the process data (x, x*, Pi) of the respective acquisition period of time, - the visualisation system (5) also determines the minimum (Min) and / or the maximum (Max) of the values of the selected item of process data (x, x*, Pi) for the respective process data point (9) during the respective acquisition period of time and - the visualisation system (5) checks whether the minimum that is determined for the respective process data point (9) is below a predetermined minimum value (MIN) and / or the maximum (Max) that is determined exceeds a predetermined maximum value (MAX) and for the case that one or both checks are positive, the visualisation system (5) displays a secondary alarm (A') together with the respective process data point (9), wherein a secondary alarm (A') represents an alarm that is not set by the process control system but rather is set by the visualisation system.

2. Visualisation method according to claim 1, characterised in that - the process data (x, x*, Pi) is allocated within the process control system (2) to a respective process object (3), - the process control system (2) in each case automatically sets a process alarm (Aj) if the process data (x, x*, Pi) that is allocated to the respective process object (3) meets a predetermined triggering condition, - the process control system (2) for each process object (3) at the acquisition points in time also detects the process alarms (Aj) that are currently set and archives or stores the detected process alarms (Aj) in the sense of the mentioned history, - the visualisation system (5) together with the history of the selected item of process data (x, x*, Pi) for the same display period of time also requests the history of the process alarms (Aj) that are allocated to the respective process object (3) and - the visualisation system (5) always then displays the process data points (9) together with the respective process data point (9) of at least one of the process alarms (Aj) if at least one process alarm (Aj) occurs during the acquisition period of time that is allocated to the respective process data point (9).

3. Visualisation method according to claim 2, characterised in that - if the predetermined display period of time includes the present, the visualisation system (5) always then determines a prediction of the future curve of the process data points (9) with reference to the determined process data points (9) for a prediction horizon (H) that reaches from the present into the future, - in this case for the prediction horizon (H) the visualisation system (5) furthermore also determines a prediction of the future curve of the minimum (Min) with reference to the determined minima (Min) and / or determines a prediction of the future curve of the maximum (Max) with reference to the determined maxima (Max) and - the visualisation system (5) always then displays a predicted secondary alarm (A') together with the respective predicted process data point (9) if a respective predicted minimum (Min) is below the predetermined minimum value (MIN) and / or a respective predicted maximum (Max) exceeds the predetermined maximum value (MAX).

4. Visualisation method according to claim 3, characterised in that the visualisation system (5) furthermore always then displays a predicted process alarm (Aj) together with the respective predicted process data point (9) if the respective predicted minimum (Min) and / or the respective predicted maximum (Max) meets the predetermined triggering condition.

5. Computer program for a visualisation system (5), wherein the computer program comprises machine code (7) that can be processed by the visualisation system (5), - wherein, owing to the processing of the machine code (7) owing to the selection of an item of process data (x, x*, Pi) and the specification of an associated display period of time by at least one operator (4) of a process control system (2) that controls and monitors an industrial technical installation (1) and that acquires the item of process data (x, x*, Pi) at acquisition points in time and in each case archives said item of process data in the sense of a history for the predetermined display period of time, the visualisation system (5) requests the history of the selected item of process data (x, x*, Pi) and outputs the associated temporal curve as a graphic (8) to the at least one operator (4), - wherein the graphic (8) comprises a number of process data points (9), characterised in that - owing to the processing of the machine code (7), the visualisation system (5) determines the respective process data point (9) with reference to the values of the selected item of process data (x, x*, Pi i) of a respective acquisition period of time that is characteristic of the respective process data point (9), wherein the acquisition period of time comprises a plurality of acquisition points in time, - the respective process data point (9) is a mean value or a median value of the process data (x, x*, Pi i) of the respective acquisition period of time, owing to the processing of the machine code (7) the visualisation system (5) - also determines the minimum (Min) and / or the maximum (Max) of the values of the selected item of process data (x, x*, Pi) for the respective process data point (9) during the respective acquisition period of time and - always then displays a secondary alarm (A') together with the respective process data point (9) if the minimum (Min) that is determined for the respective data point (9) is below a predetermined minimum value (MIN) and / or the determined maximum (Max) exceeds a predetermined maximum value (MAX), wherein a secondary alarm (A') represents an alarm that is not set by the process control system but rather is set by the visualisation system.

6. Computer program product according to claim 5, characterised in that - the process data (x, x*, Pi) is allocated within the process control system (2) to a respective process object (3), - the process control system (2) in each case automatically sets a process alarm (Aj) if the process data (x, x*, Pi) that is allocated to the respective process object (3) meets a predetermined triggering condition, for each process object (3) at the acquisition points in time also detects the process alarms (Aj) that are currently set and archives or stores the detected process alarms (Aj) in the sense of the mentioned history, and - owing to the processing of the machine code (7), the visualisation system (5) together with the history of the selected item of process data (x, x*, Pi) for the same display period of time also requests the history of the process alarms (Aj) that are allocated to the respective process object (3) and together with the respective process data points (9) of at least one of the process alarms (Aj) always then displays the process data points (9) if at least one process alarm (Aj) occurs during the acquisition period of time that is allocated to the respective process data point (9).

7. Computer program according to claim 6, characterised in that owing to the processing of the machine code (7) - if the predetermined display period of time includes the present, the visualisation system (5) always then determines a prediction of the future curve of the process data points (9) with reference to the determined process data points (9) for a prediction horizon (H) that reaches from the present into the future, - in this case for the prediction horizon (H) the visualisation system (5) furthermore also determines a prediction of the future curve of the minimum (Min) with reference to the determined minima (Min) and / or determines a prediction of the future curve of the maximum (Max) with reference to the determined maxima (Max), and - the visualisation system (5) always then displays a predicted secondary alarm (A') together with the respective predicted process data point (9) if a respective predicted minimum (Min) is below the predetermined minimum value (MIN) and / or a respective predicted maximum (Max) exceeds the predetermined maximum value (MAX).

8. Computer program according to claim 7, characterised in that the visualisation system (5) always then displays a predicted process alarm (Aj) together with the respective predicted process data point (9) if the respective predicted minimum (Min) and / or the respective predicted maximum (Max) meets the predetermined triggering condition.

9. Visualisation system, wherein the visualisation system is programmed using a computer program (6) according to one of claims 5 to 8 with the result that during operation the visualisation system implements the method steps specified in the corresponding one of claims 5 to 8.