AI Technical Summary

Technical Problem

The increasing integration of decentralized, renewable energy generation systems into energy networks poses a challenge in stabilizing energy networks, as reactionary approaches are insufficient to utilize small quantities of decentralized control power effectively.

Method used

A method for controlling energy swarm systems, where energy clusters determine and update future-oriented energy flow schedules and flexibility offers, which are then aggregated and offered to energy network operators, enabling proactive stabilization of the network by balancing energy surpluses and deficits, regardless of the clusters' physical structure or location.

Benefits of technology

This approach allows for the efficient integration of decentralized energy producers into energy networks, providing control energy on a relevant scale, enhancing network stability and reducing regulatory efforts, by bundling small flexibility offers into larger packages and optimizing energy utilization across the system.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader
Need to check novelty before this filing date? Find Prior Art

Description

[0001] The invention relates to a method for controlling energy networks, energy swarm systems and / or energy clusters. Furthermore, the invention relates to a computer and database system for the automatic execution of such a method.

[0002] The increasing need to integrate volatile, renewable energy sources into energy grids is raising the demands on both grid stabilization control systems and the integration of decentralized energy generation plants, which must be integrable into the grids using a standardized procedure. Currently, these requirements for energy distribution networks are primarily met by reactive solutions that analyze the current centralized generation of electrical and / or thermal energy, the current energy consumption, and the current distribution of electrical and / or thermal power within the energy grids. Based on this analysis, these solutions initiate steps to stabilize the grid and redistribute energy within the grid.

[0003] A person skilled in the art recognizes that, according to the first law of thermodynamics, energy can neither be created nor consumed, but only transformed. When this document refers to energy generation, consumption, or storage, it means the conversion of energy into another physical form.

[0004] For example, WO 2018 / 114404 A1 describes a method for structuring an existing energy network, whereby different network components are grouped according to their properties and control limits. Control processes are assigned to each group, which must be executed to maintain the control limits when trigger criteria are reached. The claimed method thus reacts to trigger criteria and applies certain control processes when these criteria are met. This corresponds to a top-down control approach.

[0005] WO 2018 / 224249 A1 discloses a method for operating a large number of technical units as a network on an electrical distribution network. A central control system is used to receive flexibility data from each technical unit. Using this flexibility data, the unit specifies a power range within which its electrical power may or is expected to vary. From this flexibility data, an individual, non-binding incentive function is determined for each unit and provided to the respective unit. In response, the unit generates a schedule, and from these schedules, an overall schedule for the network is created.

[0006] WO 2013 / 063581 A1 discloses a device, systems and methods for generating an operating plan based on an optimization process for controlling an energy storage system that communicates with a transport vehicle.

[0007] US 2018 / 0260892 A1 discloses various embodiments of a comparison engine for coordinating electrical energy generation and consumption, particularly in the presence of uncertainties. The engine provides a comparison based on uncertainty and flexibility in energy supply and demand chains.

[0008] Bremer Jörg et al.: "Assessment of the similarity of flexibilities of renewable energy generation in the Smart Grid" shows various aspects for an adequate modeling of the flexibilities of the plants participating in a Smart Grid, which is essential so that classic control and regulation tasks of operational management can be carried out.

[0009] Thorbaghan Shahab Shariat et al.: "Local market framework for exploiting flexibility from the end users" describes a decentralized, implicit interaction framework for the economically efficient trading of flexibility provided by prosumers. The proposed framework consists of two mechanisms: pre-planning by markets and real-time dispatching.

[0010] The increasing development of decentralized, often renewable, energy generation and conversion plants necessitates the use of even small quantities of decentralized energy as available balancing power to stabilize energy grids. Since this cannot be achieved through a purely reactive approach, the object of the invention is to provide a method for stabilizing energy grids that is capable of accessing decentralized energy potentials, regardless of their size, and making them usable for grid stabilization. Simultaneously, a system is to be described with which this object can be solved, preferably in an automated manner.

[0011] The present problem is solved by a method according to the invention for controlling an energy swarm system. According to the invention, an energy swarm system comprises one or more energy clusters, each energy cluster comprising one or more thermal, electrical, and / or material energy producers and / or energy consumers and / or energy storage devices. An energy swarm system according to the invention can therefore comprise only one energy cluster, but can also comprise a plurality of energy clusters. An energy cluster within the scope of the invention represents at least one physically inseparable or indivisible unit for energy generation, consumption, and / or energy storage, but can also be a mixed network of several energy producers and / or energy consumers and / or energy storage devices, which, however, forms, for example, an economic unit.The invention also includes coupled energy generators in an energy cluster that convert one energy flow into two energy flows, for example, a material energy flow into both thermal and electrical energy flows. Furthermore, the method according to the invention is applicable to energy clusters that are physically interconnected, but can also be applied to energy clusters and / or energy swarm systems that have physically non-connected subunits, especially those that are spatially separated. The feasibility of the method according to the invention is therefore independent of the structure of the energy clusters. According to the invention, the method according to independent claim 1 comprises the following steps, which are performed iteratively:

[0012] First, energy cluster control units, of which each individual energy cluster has one, determine and update, in step a), future-oriented energy flow schedules for each individual energy cluster. These schedules depict the individual positive and negative energy flows within the energy cluster over the course of the day in a predefined timeframe with a constant or variable step size. Energy flow is defined here as the transfer of a physical quantity of energy to, from, or between technical components. In a subsequent step b), the cluster control units determine and update future-oriented energy flexibility offers for each energy cluster. These offers represent the future realizable energy potentials of the energy cluster within the predefined timeframe.The associated energy flow plan of the energy cluster and boundary conditions for the energy cluster, such as storage levels or capacity limits of generation plants, are taken into account. The flexibility offers according to the invention specify, broken down within a given timeframe, how far the energy flows in the energy cluster can deviate in a positive or negative direction from the energy flows in the energy flow schedule. The flexibility offers do not represent actual energy flows, but rather energy potentials that can be accessed as needed. Like the energy flow schedules, the flexibility offers are also determined through forecasts.

[0013] In a further step c), the energy flow schedules and flexibility offers of the individual energy clusters are transmitted to a central swarm control unit of the energy swarm system, this transmission preferably occurring after determination or updating according to one of steps a) and / or b). The invention therefore also encompasses performing only one of the two steps a) or b), skipping the other step, and then transmitting the energy flow schedules and flexibility offers in step c).

[0014] In the following step d), flexibility offers, broken down according to the specified time grid, are offered by the swarm control unit to energy network operators and / or energy suppliers, with the offer being made at least one time interval before the offered energy quantity is physically available. It is evident to a person skilled in the art that at least one physical connection, through which an energy quantity can be transported, must exist between the energy clusters of the energy swarm system and the energy network operator and / or energy supplier to enable the exchange of such an energy quantity. If such a connection exists, the method according to the invention is applicable even if the energy swarm system is spatially separated from the energy network operated by the energy network operator and / or the supply area of ​​the energy supplier.

[0015] According to the invention, the flexibility offers of the cluster control units can be aggregated by the swarm control unit before being offered to the energy network operators and / or energy suppliers, so that a larger quantity of energy flexibility, bundled from several smaller flexibility offers—a so-called package—can be offered to the energy network operators and / or energy suppliers. Such packages typically have a size of 100 kW or more, as specified by the energy network operator. From this, those skilled in the art will recognize in particular the bottom-up approach chosen by the invention, in contrast to the top-down control used in the prior art.

[0016] As is evident to those skilled in the art, aggregating flexibility offers is only possible if the energy swarm system comprises several energy clusters, each of whose cluster control units has sent a flexibility offer to the control unit of the energy swarm system, either individually or to a certain extent. According to the invention, energy network operators and energy suppliers can then select from all the unaggregated and / or aggregated flexibility offers provided to them by the swarm control units of different energy swarm systems and access these through external flexibility demands. It is common knowledge to deduce from the preceding explanations that an energy network managed by an energy network operator, or an energy network supplied by an energy supplier, can comprise one or more energy swarm systems, each of which in turn can comprise one or more energy clusters.

[0017] Within the scope of the invention, the swarm control units of the energy swarm systems, or the swarm control unit of the energy swarm system itself, can determine optimized energy utilization within the energy swarm system based on the transmitted energy flow schedules and flexibility offers before the flexibility offers are presented to energy network operators and / or energy suppliers in step d). This allows for the optimal balancing of energy surpluses and deficits within the energy clusters within the energy swarm system, controlled by the swarm control unit, before the remaining energy, which can be either a surplus or a deficit, is forwarded as a flexibility request or offer to energy suppliers and / or energy network operators. The swarm control unit can also distribute energy according to criteria relevant to grid stability.Overall, when determining this optimized energy utilization in the energy swarm system, factors such as the existing energy network structure, which may define physical limits for energy distribution, existing contractual obligations, and achievable sales revenues through the sale of flexibility offerings can be taken into account.

[0018] According to the invention, energy flow schedules and / or flexibility queries can be determined based on data that is defined once at the beginning of the process by a user, for example, during the commissioning of the energy cluster. However, it is also possible to use historical energy generation, energy storage, and energy consumption data to determine and update the energy flow schedules and / or flexibility offers, and to forecast future data using predictions based on infrastructure data, weather, seasonal and calendar data, contract data, price trends, consumer behavior, and / or legal requirements. A person skilled in the art will recognize that other data can also be incorporated here, influencing the forecasting of the energy flow schedules and / or flexibility offers or making the forecast more reliable. The aforementioned list is therefore only exemplary and does not claim to be exhaustive.When applying such a method, the energy flow schedules are not calculated independently of the system behavior observed over time, as would be the case with a one-time initialization of the process step for determining and updating the energy flow schedules, but rather the calculation and updating of the energy flow schedules is continuously improved, with the improvement becoming increasingly accurate as the process runs longer, since more and more historical energy generation, energy storage and energy consumption data can be used to improve the update quality.

[0019] According to the invention, the determination and updating of the flexibility offers by the cluster control units in step b) can be carried out in such a way that, over the longest possible period of the time grid, i.e., over the largest possible cycles of the time grid, the highest possible, yet constant, deviation from the calculated energy flow schedule is possible. Offering energy blocks with constant power output as flexibility offers facilitates further processing at higher levels. Energy blocks spanning a long period and exhibiting a constant value result in lower computational effort than energy blocks covering only a short period, since fewer calculations per unit of time may be required to process the energy quantity in the case of long-lasting energy blocks. Constant energy or flexibility blocks also support the stability of forecasts, since, under certain circumstances,The exploitation of extreme potentials is avoided in order to maintain a constant energy or flexibility block. Extreme potentials are thus not overinterpreted, whereas any extreme potentials that are actually available are provided as a control reserve to ensure stability in adhering to energy flow schedules. However, experts are also aware of other objectives that can be used to determine flexibility offerings.

[0020] A similar objective can be pursued in determining and updating energy flow schedules in step a), namely that the energy flows in the energy flow schedule remain constant over the longest possible period. This also contributes to the stability of the energy supply of the energy cluster.

[0021] The invention also encompasses the possibility that flexibility offers can be directly passed on by the swarm control units or bundled before being passed on and, for example, sent to adjacent swarm control units, i.e., to swarm control units located in the same energy network as the sending swarm control unit, with a physical connection existing between the associated energy swarm systems. External energy demands can also be accessed from these adjacent swarm control units. It is within the scope of skilled craftsmanship to provide a solution for this that can include an energy network operator who provides the physical network connecting the two or the multitude of energy swarm systems.

[0022] According to the invention, the method after step d) of offering flexibility options by the swarm control unit to energy network operators and / or energy suppliers further comprises the following steps: In step e), a future-oriented energy exchange requirement within the specified time frame between the energy clusters is determined by the swarm control unit of the energy swarm system from the energy flow schedules, the flexibility options and external energy demands.

[0023] The energy exchange requirement indicates whether and how energy can be redistributed between energy clusters within the energy swarm system. Various boundary conditions, such as economic or ecological constraints, etc., familiar to experts, can be incorporated into the calculation. In contrast to the previously performed optimization of the energy flow(s) within the energy swarm system before the transmission of flexibility offers, which can be either passed on directly or aggregated, the determination of the future energy exchange requirement between energy clusters is carried out after receiving external energy demands from energy suppliers and / or grid operators. These can then be taken into account when determining the energy exchange requirement.

[0024] In step f), flexibility requests are determined based on a future-oriented energy exchange requirement for the use of the individual flexibility offers between the energy clusters or for providing flexibility offers to another energy swarm system or to an energy network or an energy supplier.

[0025] In a further step (g), flexibility requests are transmitted from the swarm control unit to the cluster control units. Simultaneously, in this step, the flexibility supply to swarm control units of other energy swarm systems, to energy network operators, or to energy suppliers is updated. In a further step (h), the energy flow schedules in the energy clusters are adjusted by the cluster control units according to the transmitted flexibility requests.

[0026] The cluster control units then control the energy flows in the energy clusters, for example, using local energy management systems, according to the adapted energy flow schedules.

[0027] According to the invention, the energy flows of an energy cluster can be monitored by a control unit. If a deviation in an energy flow, detected by the control unit, necessitates an adjustment of the energy flow schedule, or if the cluster control unit or an energy management system of the energy cluster instructs the energy cluster to adjust the energy flow to the corresponding value in the energy flow schedule, an energy flow schedule adapted by the cluster control unit and a flexibility offer adapted thereto can be transmitted, as described in step c). The control unit can thus include feedback that feeds the measured values ​​from the energy management systems of the energy cluster back to the control unit, enabling the control unit to perform a target-actual value comparison to verify whether the specified predicted energy flows actually correspond to the real energy flows in the energy cluster.If a target value from the energy flow plan deviates from a value of a monitored actual variable, the energy flows in the energy cluster can be adjusted back to the energy flow plan value. If a detected deviation of an energy flow from the value in the energy flow plan necessitates an adjustment of the energy flow plan—for example, because the energy flow can no longer be aligned with the energy flow plan due to an error in an energy generation forecast—then an adjusted energy flow plan and a corresponding flexibility offer can be determined.

[0028] Preferably, such a control system is implemented independently of the energy cluster's architecture, i.e., the existing energy converters and / or storage devices. This enables the platform-independent provision of the same cluster control units and monitoring units, resulting in simpler maintenance and implementation for the provider and lower costs for the user. According to the invention, this can be achieved, for example, by a standardized protocol interface located in the information flow between the energy management system's measurement unit in the energy cluster and the monitoring unit. This interface can act as a translator between the communication structure and the monitoring unit.The fieldbus systems of the energy management systems and the communication structure of the cluster control units function and normalize the measured variables in such a way that they can be processed by the cluster control unit independently of the underlying physical measured variable.

[0029] Within the scope of the invention, external energy requests made by energy network operators and / or energy suppliers and / or subordinate swarm control units to the swarm control unit that sent the flexibility offers can be structured as contracts. Requested energy quantities and / or services and / or provided energy quantities and / or services can be assigned an economic and / or ecological equivalent. Those skilled in the art will recognize that economic / ecological equivalents can take many forms, for example, as a monetary amount, but also in the form of, for example, emission allowances or other services that represent some form of value in the energy supply. The provision of a voucher system is also encompassed by the inventive concept.

[0030] According to the invention, the energy flow schedules cover a period of minutes, hours, days, weeks, or months from the time of calculation, depending on the application. Power and energy values ​​are specified in a predefined time grid with time intervals of minutes, hours, or days, or fractions thereof. For example, the time grid, which can be used by energy network operators and / or energy suppliers as well as swarm control units and cluster control units, is 15 minutes, and the forecast horizon of the energy flow schedules is 48 hours from the time of calculation. This allows for early response to any fluctuations in energy generation or consumption patterns and also permits the provision of balancing power. It is within the scope of expert knowledge to select other time periods or time steps, which can be adapted depending on the application.

[0031] According to the invention, the process is repeated at regular intervals. Preferably, the process is repeated in 15-minute increments; however, the invention also encompasses carrying out the process at other regular or irregular intervals (time units) and adjusting the time units depending on the time of day or day of the week, e.g., at night or on weekends and holidays, or according to other forecasts such as weather data, stock market prices, changes in legislation, etc.

[0032] The regular time intervals at which the process is carried out can correspond to the time intervals of the predefined time grid in which the flexibility offers and energy flow schedules are represented. However, the invention also encompasses the possibility of carrying out the process at other regular or irregular intervals (time intervals) than those specified by the time steps of the predefined time grid. In this case, however, the time intervals should have a common denominator.

[0033] In one possible embodiment of the method according to the invention, a computation time grid has different time steps compared to a communication time grid, the time grid in which the energy flow schedules and flexibility offers for communication between cluster control units, swarm control units, and energy network operators or suppliers are broken down. Preferably, the energy flow schedules and flexibility offers are calculated at the cluster level according to the computation time grid and then converted into the temporal resolution of the communication time grid when the energy flow schedules and flexibility offers are communicated to the swarm control unit. More preferably, the step size of the computation time grid is chosen to be larger than that of the communication time grid or even variable in order to increase the computational efficiency of the method.If the method according to the invention features a computation time grid with a variable step size, the step size can be adapted to the complexity of the computation. This makes it possible to perform computationally intensive or numerically unstable computational steps with a smaller step size, thereby increasing the accuracy and stability of the method. Less computationally intensive steps can be performed with a larger step size, which conserves computational resources. It is advantageous if the step sizes of the communication time grid and the computation time grid have a common divisor, which facilitates the conversion between the computation time grid and the communication time grid.

[0034] The method according to the invention can further comprise a third time grid, e.g., an execution time grid, which has a step size different from the computation time grid and / or communication time grid. This time grid forms the basis for controlling the energy flows at the cluster level by the cluster control units in step h). Similar to the computation time grid, a dense execution time grid can be selected here for complex control requirements, whereas simple control signals are executed in a less dense execution time grid.

[0035] According to the invention, the execution of the method can be triggered by certain physical events, either additionally or alternatively to execution at regular intervals. For example, an alarm can be generated when a measured value exceeds a limit value, prompting the cluster control unit monitoring that measured value to begin executing the method according to the invention.

[0036] Additionally or alternatively, alarms from other, subordinate swarm control units and / or other subordinate cluster control units and / or energy network operators and / or energy suppliers may also require the execution of the method according to the invention. This may be particularly necessary if, due to short-term detected system changes, adjustments to flexibility calls, flexibility offers, energy flow schedules, or energy redistribution become necessary.

[0037] According to the invention, determining and updating the energy flow schedules in step a) and / or adapting the energy flow schedules in step h) can be achieved by optimizing data models. Such data models can also be used for optimization when optimizing energy flows in the energy swarm system before transmitting flexibility offers in step d) or when determining the energy exchange requirement in step e). According to the invention, the data models can be suitable for predicting the future behavior of the energy cluster(s) or the energy swarm system(s). Energy network structures, the current state of the energy cluster, contract data and / or weather data and / or supply contracts and / or energy supply prices can be taken into account.Varying the model parameters, such as the power output of energy generation plants or the amount of energy absorbed by energy storage systems, affects the resulting energy flow schedule. Characteristic values ​​of the energy flow schedules, such as energy supply costs or primary energy consumption, are summarized in an objective function. From the function arguments of this objective function, a target value characteristic of the energy flow schedule can then be calculated, which is to be minimized or maximized depending on the application. In other words, determining, updating, and / or adapting energy flow schedules is achieved by optimizing a target value that is the result of an objective function whose function arguments are calculated from data models.

[0038] In one possible embodiment of the objective function, the arguments it contains can have their influence on the target value, which represents the result of the objective function, weakened or strengthened by weighting factors. According to the invention, for example, the weather data, etc., used in the objective function and / or the data models can be predicted by the cluster controllers or swarm controllers. However, the invention also includes, for example, the inclusion of external forecasts for weather data, etc., in the calculations. According to the invention, flexible pricing for energy supply can also be incorporated into the determination, updating, and / or adjustment of the energy flow schedules. For example, according to the invention, a flexible pricing system based on energy supply and energy demand can be applied, which determines a real-time price for energy supply from these two variables.In order to be able to react proactively to changes in energy behavior in energy networks, one embodiment of the invention provides for predicting future price developments by the cluster control units, the swarm control units or an external forecasting unit.

[0039] Mixed-integer linear data models can be used, for example, to determine and / or update energy flow schedules and flexibility offers. These offer the advantage that efficient processing of the model data is possible through the linear representation of energy systems. Thus, even with limited computing power, the energy behavior of energy clusters and / or energy swarms can be predicted reliably and quickly. In such a linear model according to the invention, for example, a mixed-integer model, all quantities that predict the future system behavior of the energy system represented by the model can be implemented as time series. For example, consumers or producers whose consumption or generation is based on static quantities can be described by predicting their power output in the form of a time series.According to the invention, the problem of insufficient accuracy in predictions derived from mixed-integer, linear data models can be addressed by repeatedly comparing the actual system behavior with the predictions of the data model. If deviations between the prediction and the actual behavior are detected, the parameters of the data model can be adjusted to improve the prediction quality.

[0040] In the case of a linear model, the energy converters can essentially be described by matrices or vectors that convert incoming energy flows into outgoing energy flows for each time step; that is, the outgoing time series can be calculated from the incoming time series by multiplying it by the matrix describing the converter. In accordance with the principle of energy conservation, no energy may be lost or added in an energy system model according to the invention. To avoid unsolvable optimization problems that can arise in the model due to these two conditions, artificial energy sources and energy sinks can be incorporated into the model according to the invention. These compensate for physically nonsensical energy flows at very high costs, thus preventing the model from becoming unsolvable. According to the invention, these linear models can be solved using...Linear optimization algorithms are used for the resulting linear objective functions. It is evident to those skilled in the art that the methods according to the invention can also be performed with non-linear data models, even though this entails a higher computational effort compared to linear models. However, the accuracy of the model is increased in the non-linear case.

[0041] The optimization algorithms according to the invention can, for example, calculate total energy supply costs, CO2 equivalent emissions for energy supply, total energy demand for energy supply, a characteristic value for distribution network stability, or a comparable economic, ecological, or technical characteristic value for energy supply. These values ​​can be the result of optimized objective functions. The individual function arguments that comprise the objective functions can be converted into the unit of the target value, so that essentially only one physical or economic unit predominates in the objective function. The invention also allows this to be achieved using weighting factors that assign a constant scaling factor to the respective function argument.A conversion can also be performed during the calculation of the function arguments themselves, thus eliminating the need for conversion using weighting factors. Both solutions are covered by the inventive concept, as are other solutions that fall within the scope of skilled work. Selecting the appropriate optimization algorithm for each objective function also falls within the scope of skilled work. For example, a linear minimization algorithm can be used for an objective function that represents the total costs of energy supply in a linear form.

[0042] In one embodiment of the invention, an analysis of the actual past energy behavior and an analysis of the actual past thermal, electrical, and material energy over time are performed during the creation and / or updating of the data models. This analysis allows the model data, which the data models use to represent reality, to be continuously updated and compared, leading to a better representation of the actual system behavior by the model. For such a training process, training algorithms from the field of neural networks or genetic algorithms, which are familiar to those skilled in the art, can be used, for example.

[0043] According to the invention, the control units of the energy swarm systems and / or the energy network operators and / or the energy suppliers can, for example, select from several flexibility offers provided by different swarm control units. This enables the development of a market concept based on supply and demand, which can always find the best economic and / or ecological solution for energy provision.

[0044] Preferably, the method is executed automatically by one or more computers connected to databases, whereby the cluster control unit and the swarm control unit can be implemented on different terminals or on the same terminal. For spatially contiguous swarm energy systems consisting of locally adjacent or closely spaced clusters, it can be advantageous to execute the swarm control unit of the swarm energy system and the cluster control units, or the single cluster control unit of the energy swarms, on the same computer. However, if a swarm energy system comprises several spatially widely separated cluster energy systems, the swarm control unit and the subordinate control units are preferably implemented on different computers.

[0045] The invention also includes a computer and database system with several interconnected software and / or hardware units for the automated execution of the method according to the invention.

[0046] The inventive method for controlling an energy swarm system thus offers a way to integrate decentralized energy producers into energy generation and distribution in a simple and cost-effective manner and to proactively react to generation bottlenecks or surpluses in the energy network. Through predictive flexibility offers that are independent of the structure of the energy clusters, communication between lower and higher levels of an energy system is enabled, which can be applied regardless of the structure of the energy system.By bundling small flexibility offers into large flexibility packages, it becomes possible to provide balancing energy on a scale relevant to energy distribution networks, thereby enabling energy network operators, energy suppliers and decentralized energy producers to contribute to energy network stability and providing a solution for the increased control effort resulting from the integration of decentralized, statistical producers into energy networks.

[0047] The invention is described in more detail below with reference to selected exemplary embodiments, which, however, do not limit the scope of the inventive concept. The detailed application examples can be combined with one another, as well as with features that were only described in general terms above. Figure 1 shows an exemplary embodiment of a method for controlling an energy swarm system. Figure 2 shows a further embodiment of a method for controlling an energy swarm system. Figure 3 shows a further exemplary embodiment of a method for controlling an energy swarm system. Figure 4 shows a diagram of an energy network according to the invention. Figure 5 shows a diagram of electrical power generation in a combined heat and power plant, operated once according to the prior art and once according to the method according to the invention. Figure 6 shows an exemplary flexibility offering according to the invention.

[0048] Figure 1 Figure 1 shows an embodiment of the method according to the invention as claimed in claim 1, in which the method steps a) to d) are carried out iteratively. Furthermore, the following are shown in Figure 1: Figure 1The steps shown are divided in such a way as to indicate whether they take place at the level of an energy cluster 1 or an energy swarm system 2. According to the invention, an energy swarm system 2 comprises at least one energy cluster 1, and an energy swarm system 2 may also have several energy clusters 1. The precise configuration of an energy cluster 1 or the number of energy clusters 1 that an energy swarm system 2 has is irrelevant for the feasibility of the method according to the invention. It is equally irrelevant whether an energy cluster 1 comprises, for example, only one or no energy generation plant or energy conversion plant, or a plurality of energy conversion plants, all of which are subordinate to the same cluster control unit 11.By forwarding the future-oriented energy flow schedules of energy clusters 1, determined and updated in step a), and by transmitting the future-oriented energy flexibility offers 6 of the individual energy clusters 1, determined and updated in step b), a communication structure is created between the cluster control units 11 and a control unit 12 of the energy swarm system 2, which is independent of the structure of the energy clusters 1. Step c), which is executed after step b), represents this transmission of the energy flow schedules and the flexibility offers 6 of the energy cluster 1 to a central swarm control unit 12.The control unit 12 of the energy swarm system 2, also referred to as the swarm control unit 12, offers flexibility options to energy network operators 13 and / or energy suppliers in step d), wherein the energy swarm system 2 is preferably arranged in physical proximity to the network 3 of the energy network operator 13 and / or to the energy supply company's energy generation plant. Particularly preferably, the swarm energy system 2 is even part of the network of the energy network operator 13. However, the invention also encompasses the possibility that the energy swarm system is not part of the energy network 3 of the energy network operator 13 and is also not arranged in physical proximity to the same network 3 and / or to the energy supply company's generation plant.

[0049] The arrows in Figure 1The diagram visualizes the direction of the process. First, in step a), a future-oriented energy flow schedule is determined, followed in step b), by the determination of future-oriented energy flexibility offers 6. Subsequently, the energy flow schedules 10 and the flexibility offers 6 are transmitted to a central swarm control unit 12, which represents step c). In step d), which follows step c), the flexibility offers 6 are offered to energy network operators 13 and / or energy suppliers. A back-reference arrow from step d) to step a) illustrates the iterative execution of the process according to the invention. According to the invention, the energy flow schedules 10 determined in step a) and the energy flexibility offers 6 determined in step b) may only be updated during repeated iterations of the process and not recalculated.

[0050] Figure 2 shows an energy swarm system 2 that has several energy clusters 1. It is also in Figure 2 It has been shown that steps a) to c) of the method according to the invention, which are carried out by cluster control units 11, are performed separately for each cluster 1, which in turn has a cluster control unit 11, wherein step d) is performed once for the entire swarm energy system 2, which can only have one swarm control unit 12. The cluster control units 11 thus determine, or update, future-oriented energy flow schedules 10 for each energy cluster 1 separately in step a), which depict the individual energy flows 9 in the energy cluster 1 in a predetermined time grid. In step b), the cluster control units 11 perform the following for each energy cluster 1, i.e., in the case of Figure 2Three future-oriented energy flexibility offers 6 are identified and updated, which, taking into account the associated energy flow schedule and boundary conditions for the energy cluster, represent future realizable energy potentials of energy cluster 1 within the specified timeframe. In step c), each cluster control unit 11 transmits the energy flow schedules 10 and flexibility offers 6 of the individual energy clusters 1 that it has calculated to the central swarm control unit 12 of the energy swarm system 2 after identification or updating according to one of steps a) or b).The energy flow schedules 10 and flexibility offers 6 of the individual energy clusters 1 are combined by the swarm control unit 12 of the energy swarm system 2 and offered as broken-down flexibility offers 6 to energy network operators 13 and / or energy suppliers according to the specified time grid, whereby the offering takes place at least one time step in the time grid before the energy can be physically provided.

[0051] According to the invention, the flexibility offers 6 sent by the cluster control units 11 to the swarm control unit 12 can be forwarded directly to energy network operators 13 and / or energy suppliers. However, it is also possible for the flexibility offers 6 of several cluster control units 11 or all cluster control units 11 to be aggregated by a higher-level swarm control unit 12 before being offered to the energy network operators 13 and / or energy suppliers in step d), i.e., bundled into flexibility packages, and subsequently offered. Furthermore, the invention encompasses the swarm control unit 12 offering the energy network operators 13 and / or energy suppliers a mixture of aggregated and non-aggregated flexibility offers 6. Regardless of the status of the flexibility offers 6, these can be adjusted by energy network operators 13 and / or energy suppliers based on external energy demands 7 or...External flexibility requests can be made.

[0052] In Figure 3 Figure 2 shows another exemplary design of an energy swarm system. Figure 3 Figure 1 shows two energy swarm systems 2, each of which, for the sake of simplicity of representation and description, has, for example, only one energy cluster 1. The two energy swarm systems 2 are part of an energy network 3, to which they are connected after passing through the process steps a) to d), which are already mentioned in connection with the Figure 1 and 2 As explained, flexibility offers 6 are provided and the swarm control units 12 of the energy swarm systems 2 receive external energy demands 6 from them. According to the invention, an exchange of flexibility offers 6 and external energy demands 7 can also take place between the two energy swarm systems 2.

[0053] In step e), the swarm control units 12 can determine a future energy exchange requirement between the energy clusters 1. This requirement is broken down into a predefined timeframe and is determined from the energy flow schedules 10 transmitted by the cluster control units 11, the flexibility offers 6, and external energy demands 7. If the energy swarm systems 2 only have one energy cluster 1, this step can be omitted.

[0054] In step f), the swarm control units can determine 12 flexibility requests 7 based on a future energy exchange demand. These can be used to utilize the flexibility offers 6 between the individual energy clusters 1, but can also provide flexibility offers 6 to another energy swarm system 2, an energy network 3, or an energy supplier. The energy exchange demand is divided here into packages, the flexibility requests 7, which can be provided by the cluster control units.

[0055] In step g), flexibility requests 7 can be transmitted from the swarm control units 12 to the cluster control units 11. The flexibility offer 6, which can be made available to other swarm control units 12 and / or energy network operators 13 and / or energy suppliers, is then updated and adjusted. Flexibilities that have already been requested are removed from the offers.

[0056] In step h), the energy flow schedules 10 at the energy cluster 1 level are adjusted by the cluster control units 11 according to the transmitted flexibility requests 7. The energy flows 9 in the energy clusters 1 are controlled by the cluster control units 11 according to the adjusted energy flow schedules.

[0057] This method according to the invention can also be carried out iteratively, as shown by the feedback arrow.

[0058] Figure 4 Figure 3 shows the exemplary structure of an energy network 3, which has several energy swarm systems 2, which in turn can have several energy clusters 1. In Figure 4The energy clusters 1 and energy swarm systems 2 are depicted as spatially connected units; however, this is not strictly necessary according to the invention. The invention also encompasses combining spatially distant units into energy clusters 1 and / or energy swarm systems 2. Furthermore, in Figure 4 Different configurations of energy swarm systems 2 are indicated, each characterized by a different interconnection of the energy clusters 1 via energy networks 3. The number of energy clusters 1 in an energy swarm system 2 can also vary.

[0059] Thus, in Figure 4For example, a swarm system 2 is shown that has only one energy cluster system 1. However, swarm systems 2 are also shown that have three energy cluster systems 1. The person skilled in the art will recognize that an even larger number of energy clusters 1 can be provided in an energy swarm system 2. The energy swarm systems 2 are connected by an energy network 3, wherein the energy network 3 has a plurality of energy lines 4. It is within the scope of the invention to understand the energy lines 4 not only as electrical lines, but also as material and / or thermal energy lines or as communication lines, which can also enable an exchange of energy and power as well as data via the energy network 3. The energy network 3 further has connections to other energy networks 3, which enable an energy exchange between energy networks 3.

[0060] Figure 4Furthermore, it shows that each energy cluster 1 is assigned a cluster control unit 11. The cluster control units 11 also communicate, for example, via information links 5, which can be wired or wireless and are located in Figure 4 The cluster control units 11 are represented as dash-dot lines and are connected to higher-level swarm control units 12. The invention also includes the fact that the cluster control units 11 are interconnected by information links 5. The swarm control units 12 communicate with an energy network operator 13 via these information links 5. The information links 5 can, for example, be used to transmit flexibility offers 6 and / or flexibility requests 7 and / or external energy demands 8. Other signals can also be exchanged between the control units of the energy system via the information links 5.

[0061] Figure 5Figure 1 shows a comparison of two diagrams. The first, upper diagram depicts the electrical power curve of an energy cluster 1, using the example of a combined heat and power (CHP) plant controlled according to a prior art method. The lower diagram shows the electrical power of a CHP plant controlled according to the inventive method. In both cases, time is plotted on the abscissa of the diagrams, while the ordinate shows a graph for the electrical power of the CHP plant in kilowatts and a graph for a day-ahead market price in euros per megawatt-hour. The solid lines in both diagrams correlate with the day-ahead market price. The dashed lines correspond to the electrical power of the CHP plant.

[0062] The diagram above shows that when a CHP unit is operated in heat-led mode – a common practice in the state of the art – high day-ahead exchange prices are not used to sell electrical energy, although the CHP unit shown here and the energy system in which the CHP unit is located and which supplies it with heat and electrical energy have some potential to shift the generation periods in which the CHP unit generates electrical energy.

[0063] Through the exchange of flexibility offers and requests between energy clusters 1, energy swarm systems 2, and energy network operators 13 and / or energy suppliers according to the invention, it is possible to access the potential of the CHP unit precisely when the market price for electricity is highest. Therefore, the dashed line representing the electrical power generation of the CHP unit in the second diagram differs from the first diagram in that it provides high electrical power precisely when the day-ahead market price is highest. The method according to the invention serves not only the economic optimization of electricity procurement and sales but also grid stability, since the market price is composed of supply and demand and is therefore particularly high when supply and demand threaten to drift apart, which jeopardizes the stability of the frequency in the electrical grid.

[0064] Figure 6 Figure 1 shows an example of how energy flow schedules and flexibility offers can be communicated from cluster control units 11 to swarm control units 12 and / or from swarm control units 12 to energy network operators 13 and / or energy suppliers. According to the invention, this can be done, for example, in tabular form, or optionally in matrix form, where the exemplary table can have eight columns.

[0065] The first column shows the time intervals of a predefined time grid, which forms the common basis for energy flow schedules and flexibility offers from all control units. The eighth column displays values ​​for an energy flow schedule, such as those that can be provided by a power generation plant. The columns in between illustrate how and at what price the power generation plant's energy production can deviate from the predefined schedule. The third column provides an overview of the power potential for each time interval that can be provided in a positive direction relative to the energy flow schedule. Column four shows the corresponding positive energy quantity, and column two shows the corresponding price charged for the energy quantity drawn. Columns five through seven show the price, power, and energy for a negative deviation from the energy flow schedule.

[0066] By relating energy quantities and power outputs to a predetermined time clock inherent to the entire system within a predefined time grid, fast and unambiguous communication between higher-level and lower-level units is enabled. Furthermore, flexibility and potential queries can thus be made simultaneously, as they always refer to the same time grid.

[0067] The in Figure 6 The proposed communication structure, based on flexibility offers and energy flow schedules, is independent of the structure of the control units between which communication takes place. It can therefore be used for a wide variety of applications and, despite or even because of its versatility, can make a significant contribution to utilizing the economic and ecological potential of decentralized energy generation. REFERENCE MARK LIST

[0068] 1 Energy cluster 2 Energy swarm system 3 Energy grid 4 Energy line 5 Information connection 6 Flexibility supply 7 Flexibility demand 8 External energy demand 9 Energy flow 10 Energy flow diagram 11 Cluster control unit 12 Swarm control unit 13 Energy grid operator

Claims

1. Method for controlling an energy swarm system (2) comprising one or more energy clusters (1), wherein each energy cluster (1) comprises one or more thermal, electrical and / or material energy generators and / or energy consumers and / or energy stores, wherein the method comprises the following steps, which can be iteratively passed through: a) Determining and updating the future-oriented energy flow schedules (10) for each individual energy cluster (1) by cluster control units (11), which map the individual energy flows (9) in the energy cluster (1) in a predetermined time grid; b) determining and updating future-oriented energy flexibility offers (6) of the individual energy clusters (1) by the cluster control units (11), which, taking into account the associated energy flow schedule (10) and boundary conditions for the energy cluster (1), map energy potentials of the energy cluster (1) that can be realised in the future in the predetermined time frame; c) Transmission of the energy flow schedules (10) and the flexibility offers (6) of the individual energy clusters (1) to a central swarm control unit (12) of the energy swarm system (2) after a determination or update according to one of the steps a) or b); d) offering of flexibility offers (6), itemised in accordance with the predetermined time pattern, by the swarm control unit (12) to energy network operators (13) and / or energy suppliers at least one time unit of the time pattern before the energy can be physically provided; e) determination by the swarm control unit (12) of a future energy exchange requirement in the prescribed time frame between the energy clusters (1) from the energy flow schedules (10), the flexibility offers (6) and external energy demands (8); f) determining flexibility calls (7) on the basis of the future-oriented energy exchange requirement for the utilisation of the individual flexibility offers (6) between the energy clusters (1) or for the provision of flexibility offers (6) to a further energy swarm system (2) or to an energy network (3) or an energy supplier; g) Transmitting flexibility calls (7) to the cluster control units (11) and updating the flexibility offer to other swarm control units and / or energy grid operators and / or energy suppliers; h) adjusting the energy flow schedules (10) by the cluster control units (11) according to the transmitted flexibility calls (7) and controlling the energy flows (9) in the energy clusters (1) according to the adjusted energy flow schedules (10).

2. Method according to claim 1, wherein several flexibility offers (6) of the cluster control units (11) are aggregated by the swarm control unit (12) before being offered to the energy network operators (13) and / or to the energy suppliers in step d) and are offered subsequently, and the energy network operators (13) and / or energy suppliers can call up the non-aggregated or aggregated flexibility offers (6) by means of external energy demands (8).

3. Method according to one of the claims 1 or 2, in which, before step d), an optimised energy utilisation in the energy swarm system (2) is determined by the swarm control unit (12) from the transmitted energy flow schedules (10) and flexibility offers (6), taking into account an existing energy network structure, contractual obligations of the energy swarm system, achievable sales revenues from the sale of the flexibility offers, environmental criteria, or similar.

4. Method according to any of the preceding claims, wherein historical energy generation, energy storage and energy consumption data are used to determine and update the energy flow schedules (10) and forecasts are made for the future by means of predictions based on infrastructure data, weather and season data, calendar data, contract data, price trends, consumer behaviour and / or legal requirements.

5. Method according to one of the previous claims, wherein the energy flow schedules (10) in step a) are determined in such a way that they provide constant energy flows (9) over as long a period of the time grid as possible and / or the flexibility offers (6) are determined in step b) in such a way that a deviation from the energy flow schedule (10) that is as high as possible but constant over the period of time is possible over as long a period of the time grid as possible.

6. Method according to one of the previous claims, wherein the flexibility offers (6) are also sent in step d) to parallel swarm control units (12) and can be called up by these through external energy demands (8).

7. Method according to one of the previous claims, wherein the energy flows (9) of an energy cluster (1) are monitored by a control unit and a transmission according to step c) of an energy flow schedule (10) adapted by the cluster control unit (11) and of a flexibility offer (6) adapted thereto takes place if the deviation of an energy flow (9) determined by the control unit makes it necessary to adjust the energy flow schedule (10), or the cluster control unit (11) or an energy management system of the energy cluster (1) instructs the energy cluster (1) to adjust the energy flow (9) to the corresponding value in the energy flow schedule (10).

8. Method according to one of the previous claims, wherein the external energy demands (8) are implemented as contracts between swarm control units (12) and the energy network operators (13) and / or the energy suppliers and / or co-ordinated swarm control units (12) and an economic and / or ecological equivalent is assigned to the retrieved energy quantities and / or power.

9. Method according to any of the preceding claims, wherein the energy flow schedules (10) cover a period of minutes and hours, days, weeks or months from the calculation time and power and energy values are given in a predetermined time pattern with time cycles, the length of which is minutes, hours or days or fractions thereof.

10. Method according to any of the previous claims, wherein the method is repeated in regular time steps.

11. Method according to any of the previous claims, wherein steps a) and b) are carried out in a calculation time step that is different from the time step size of the predetermined time grid in which energy flow schedules (10) and flexibility offers (6) are itemised.

12. Method according to one of the previous claims, wherein the determination and updating of the energy flow diagrams (10) in step a) and / or the determination of the energy exchange requirement in step e) and / or the adaptation of the energy flow diagrams (10) in step h) and / or the determination of an optimised energy utilisation according to claim 3 by optimising data models that are suitable for predicting the future behaviour of the energy clusters (1), energy swarm systems (2), taking into account the energy network structures, the current state of the energy cluster (1), contractual data and / or weather data and / or energy prices and / or further economic and / or ecological specifications.

13. Method according to claim 12, wherein the data models are mixed-integer linear data models and mixed-integer linear optimisation algorithms are used for optimising the energy flow schedules (10) and the flexibility offers (6).

14. Method according to claim 12 or 13, wherein the optimisation algorithms calculate the total costs for the energy supply, a CO2 equivalent output for the energy supply, a total energy requirement for the energy supply, a characteristic value for distribution network stability or a comparable economic, ecological or technical characteristic value for the energy supply, always under the condition that existing supply contracts are fulfilled.

15. Method according to any one of claims 12 to 14, wherein the data models are created and / or continuously updated by analysing past energy behaviour and by analysing past thermal, electrical and material energy flows over time.

16. Method according to one of the previous claims, wherein the swarm control units (12) and / or the energy network operators (13) and / or the energy suppliers can select from a plurality of flexibility offers (6) provided by different swarm control units (12).

17. Method according to one of the previous claims, wherein the method is carried out automatically by one or more computers connected to databases and networked with each other.

18. A computer and database system with several hardware and software units communicating with each other for automatically carrying out the method according to one of the previous claims.