METHOD FOR CLEANING A GRAVEL BED OF A TRACK
Patent Information
- Application Number
- DE502022002183
- Authority / Receiving Office
- DE · DE
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2022-02-17
- Publication Date
- 2024-12-05
- Estimated Expiration
- 2042-02-17
AI Technical Summary
The existing method for cleaning and maintaining ballast tracks requires multiple passes and extensive closure periods, leading to prolonged rail traffic disruptions and increased labor and equipment needs.
Implementing a deep tamping process that compacts all layers of new and cleaned ballast in a single pass, followed by stabilization, eliminating the need for separate ballast trains and reducing the number of tamping processes, and utilizing a ballast introduction device to reuse cleaned gravel directly after cleaning.
This approach shortens the closure period, reduces labor costs, minimizes equipment requirements, and maintains the quality of the ballast bed, allowing for faster rail traffic resumption with improved safety and reduced construction site efforts.
Description
Technical area
[0001] The invention relates to a method for cleaning a ballast bed of a track by means of track-bound machines, wherein ballast located under a track grid is removed by means of a cleaning machine with a ballast removal device, wherein, with respect to a working direction behind it, cleaned and / or new ballast is introduced into the track in several layers by means of a ballast introduction device and a ballast train, and wherein the introduced ballast is compacted by means of a tamping machine and a stabilization machine. State of the art
[0002] Ballasted tracks have properties that enable safe and efficient railway operations. The main requirement for a ballasted track is its ability to withstand static and dynamic loads. To achieve this, the ballast must exhibit sufficient stability and elasticity through a suitable grain distribution and good interlocking of the individual ballast grains. A low fines content and high sharp edges are crucial for this requirement.
[0003] Over extended periods of time, dynamic operational loads and weather influences cause the ballast to increasingly lose its beneficial properties. To restore an intact ballast bed, the ballast must be cleaned, supplemented, or completely replaced. A machine for performing ballast cleaning is known, for example, from AT 520989 A1. Using a ballast removal device designed as an endless clearing chain, the ballast located beneath the raised track panel is continuously removed and fed into a cleaning system. Immediately behind this, cleaned and / or new ballast is placed on the existing subgrade using a ballast placement device.
[0004] The publication by Schilling R.: Ballast Bed Cleaning on Single-Track Railway Lines. ZEVrail Glasers Annalen 129, Hanover, October 10, 2005, pp. 414-422, describes the ballast cleaning process, including all preparatory and main work. To compact the applied ballast after cleaning, several machines of a so-called mechanized track maintenance train (MDZ) are used. This train includes a tamping machine, a ballast plow, and a dynamic track stabilizer (DGS).
[0005] According to the state of the art, a first pass of ballast compaction takes place immediately after the cleaning machine. Next, a ballast train consisting of self-unloading ballast wagons unloads new ballast above the track panel. The track panel is raised by the mechanical ballast train and the new ballast is compacted beneath the sleepers. This process of new ballast supply, track lifting, and compaction is repeated to achieve a ballast bed of the desired height.
[0006] This common practice is discussed in detail with reference to Fig. 1 explained. The diagram illustrates the known process with four work phases, although for the sake of clarity, only the individual work units are shown. These units are arranged on machine frames (not shown) of the cleaning machine and the mechanical processing train.
[0007] The top image shows the first phase of ballast excavation and ballasting during a raising of the track grid. The ballast is removed from beneath the raised track grid using a cleaning chain. The clearing height is typically 300 mm. The removed old ballast is screened and sharpened. This cleaned ballast portion is returned to the track using a ballast conveyor belt and distributed with a plough to a maximum initial height of 150 mm. This maximum initial height is specified by the regulations of various railway infrastructure operators, for example, the French SNCF. As required, the ballast is immediately compacted using a stabilization unit, reducing the ballast bed height to approximately 130 mm.
[0008] In a second phase, new ballast is introduced using a ballast train and distributed using a plow. The track deck is then raised by 80 mm, while the raised sleepers are simultaneously tamped. A subsequent stabilization process leads to settlement of the track deck. The remaining height of the ballast bed under the sleepers is approximately 205 mm.
[0009] The third phase repeats the second phase, with a further raising of 80 mm and a settling to approximately 280 mm. The ballast in the track is usually sufficient to perform a final tamping operation in a fourth phase. However, it may also be necessary to unload new ballast in front of the tamping machine.
[0010] In the final pass, the tamping machine raises the track panel by 20 mm to 25 mm to a specified geometry. The subsequent stabilization lowers the ballast bed to its original height of approximately 300 mm. In a final step, the ballast bed is profiled and swept to remove any gravel particles lying on the sleepers.
[0011] The described multi-layer ballast placement requires long closures. If necessary, the work must be spread over several closures, with the track only being able to be reopened to rail traffic at significantly reduced speeds. Description of the invention
[0012] The invention is based on the object of improving the method of the type mentioned above compared to the prior art in such a way that all work can be carried out within a shortened track closure period. The quality of the compacted ballast bed should meet the specifications of the railway infrastructure operators.
[0013] According to the invention, this object is achieved by the features of independent claim 1. Dependent claims specify advantageous embodiments of the invention.
[0014] In this case, before a first tamping process, all layers of new and / or cleaned ballast are introduced using the ballast introduction device and the ballast train. During the first tamping process, the ballast bed is compacted into different depths using a deep tamping unit arranged on the tamping machine. The track is then stabilized using the stabilization machine. Immediately afterwards, the track panel is tamped into just one depth in a second tamping process using the same or a further tamping machine. After the second tamping process, the track is stabilized using the same or a further stabilization machine. In this way, compared to the known method, a separate ballast introduction using another ballast train as well as a subsequent tamping process and a stabilization process are no longer necessary.
[0015] In addition to shortening the required track closure, the new method has the advantage of allowing more cleaned ballast to be reused than the conventional method. This ballast is placed into the track via the ballast placement device immediately after cleaning and does not need to be temporarily stored or replaced with new ballast.
[0016] With the new method, only one ballast train is required for the cleanup site. If necessary, material conveyor and silo units (MFS) coupled to the cleaning machine can be used to bring additional new ballast to the construction site. With the conventional method, the material conveyor and silo units are pulled onto the site empty and loaded with spoil.
[0017] A further advantage is the reduction in tamping operations, which protects the ballast. Furthermore, a single pass is eliminated for the ballast plow and track stabilizer. This reduction in operations means fewer personnel are needed on the track. This reduces labor costs and contributes to the safety of the track construction site.
[0018] Overall, the length of the construction site is reduced by eliminating the previously required machinery and ballast self-unloading wagons. As a result, the effort required to secure the site is also reduced. Fewer safety personnel and less safety equipment are required. Furthermore, the section on an adjacent track with reduced speed is shortened, allowing more trains to pass the construction site.
[0019] Advantageously, the method according to the invention cleans the ballast bed at a removal height of at least 300 mm. This results in no compromises compared to the conventional method, while the required compaction quality is achieved with the deep tamping process.
[0020] A further improvement involves using the ballast placement device to place ballast for a bedding depth of at least 200 mm, and especially at least 250 mm. This ensures that the remaining lifting operations achieve the original ballast bed height without compromising the compaction quality.
[0021] For the first lifting operation after ballasting using the ballast train, it is advantageous if the track panel is lifted by at least 50 mm, especially by at least 70 mm. This means that only a small amount of lifting is required for the final second tamping operation to achieve the specified track geometry.
[0022] In the second lifting process, the track panel is preferably lifted in a range between 15 mm and 25 mm, particularly between 20 mm and 25 mm. This provides sufficient clearance for the specified track geometry without unnecessarily loosening the ballast bed.
[0023] The method is further developed by an advantageous deep tamping process, in which, after the first lifting process using the deep tamping unit, a first tamping process is carried out in a lower layer of the ballast bed using vibrating and adjusting tamping picks, and a second tamping process is carried out in an upper layer of the ballast bed using the same tamping picks. The track panel is held in position during the tamping processes by means of a lifting unit.
[0024] The efficiency of the method according to the invention is further increased if the tamping process is carried out after the second lifting process using a multi-sleeper tamping unit. This allows the second tamping process to be completed at an increased operating speed.
[0025] The speed of the work is further increased when the tamping work is carried out using a tamping machine integrated into a cleaning train. The cleaning process and the respective compaction process are coordinated by a higher-level control system. Furthermore, all units are supplied via a shared drive unit of the cleaning train, with an optimized power supply for the integrated machines. Short description of the drawings
[0026] The invention is explained below by way of example with reference to the accompanying figures. They show schematically: Fig. 1 Method according to the prior art Fig. 2 Method according to the invention Description of the embodiments
[0027] Fig. 1 shows the process described above, with the layer-by-layer introduction of cleaned and / or new ballast 1 into a track 2. The ballast 1 located on a subgrade 3 forms a ballast bed 4 for a track grid 5 made of sleepers 6 and rails 7 attached to it. A track-mounted cleaning machine 8 is used to clean the ballast bed 4. For the sake of clarity, this is indicated only by dashed outlines and comprises several machine frames supported on rail bogies. Devices and units for processing the track 2 are arranged on the machine frames.
[0028] Using lifting devices 9, the track grid 5 is raised and held in position, while a ballast removal device 10 removes the ballast 1 at a removal height h1 (e.g., 300 mm). This defined removal height h1 extends from the subgrade 3 to be exposed to the lower edges of the sleepers 6 stored in the ballast bed 4. Naturally, the ballast 1 located between the sleepers 6 is also removed. Typically, the ballast removal device 10 comprises a rotating endless clearing chain that continuously collects the ballast 1 during forward travel and transfers it to a conveyor system for further transmission to a screening plant.
[0029] A further conveyor device delivers the cleaned ballast 1 to a ballast introduction device 11. With respect to a working direction 12, this ballast introduction device 11 applies a first layer of the cleaned ballast 1 directly behind the removal device 10 to the exposed subgrade 3. A plough 13 distributes the applied ballast 1 to a desired first bedding height h2 (e.g., 150 mm) on the subgrade 3.
[0030] The track grid 5, laid on this newly created ballast bed 4, is vibrated by a stabilization unit 14 under load. This stabilization process anticipates settlement of the ballast bed 4. The result is a reduced second bedding height h3 (e.g., approximately 130 mm).
[0031] In the second work phase, a further layer of ballast is poured onto track 2 by means of a ballast train 15. A ballast plough 16, preferably designed as a separate machine, distributes the ballast 1 with adjustable plough blades 17. This ensures that there is sufficient ballast 1 on and between the sleepers 6 for a first tamping process.
[0032] A dedicated tamping machine 18 comprises a lifting unit 19 and a tamping unit 20. The lifting unit 19 raises the track deck 5 with a first lift h4 (e.g., 80 mm) to a third bedding height h5 (e.g., 210 mm). A stabilizing machine 21, also called a dynamic track stabilizer (DGS), is then deployed. This stabilizer is either designed as a separate machine or coupled to the tamping machine 18. The action of the stabilizing unit 14 results in a compaction of the ballast bed 4 to a fourth bedding height h6 (e.g., 205 mm).
[0033] The work steps of the second phase are repeated in a third phase, during which a third layer of ballast is introduced into track 2 by means of a ballast train 15. Subsequently, the track grid 5 is initially raised to a fifth bedding height (e.g., 285 mm) with a second lift h7 (e.g., 80 mm). After being secured by the tamping unit 20, it is again slightly lowered by the stabilization unit 14 to a sixth bedding height h9 (e.g., 280 mm).
[0034] Subsequently, in a third tamping process, the track deck 5 is brought into a specified track geometry with a third lift h10 (e.g., 20 mm to 25 mm). The final track position is achieved after a final stabilization using the stabilization unit 14. The ballast bed 4 renewed in this way has approximately the same height as before the cleaning process. A disadvantage of this known method is the numerous work steps required for the layer-by-layer ballast placement and ballast compaction.
[0035] The method according to the invention reduces the number of work steps without reducing the quality of the cleaned ballast bed 4. The new sequence of work steps is explained with reference to Fig. 2 .
[0036] As before, the cleaning of a ballast bed 4 starts with a cleaning machine 8. A lifting unit 9 of the cleaning machine 8 lifts a section of the track grid 5 to be treated. For this purpose, the lifting unit 9 comprises roller grippers that grip the respective rail head of the rails 7 and roll along the rails 7 as the cleaning machine 8 moves forward.
[0037] A ballast removal device 10, which runs with a crossbeam below the raised track section, picks up the ballast 1 at a predetermined removal height h1 (e.g., 300 mm). Specifically, the ballast is picked up by an endless clearing chain that surrounds the track section 5. The clearing chain conveys the removed ballast 1 upwards via a lateral channel to a first conveyor (not shown). In this way, the ballast 1 is fed to a screening system arranged on the cleaning machine 8.
[0038] The ballast 1 is cleaned in the screening plant. If necessary, the edges are then sharpened in an impact crusher. The cleaned ballast 1 is transported to the ballast introduction device 11 by means of another conveyor system. If there is insufficient processed ballast 1, it is supplemented with new ballast 1. This is stored, for example, in a storage unit of the cleaning machine 1. New ballast 1 can also be transported using so-called material conveyor and silo units (MFS). These units are rail vehicles coupled to the cleaning machine 8 and serve to collect overburden generated during ballast cleaning.
[0039] According to the invention, considerably more ballast 1 is introduced into the track 2 with the ballast introduction device 11 of the cleaning machine 8 than previously. The ballast layer smoothed with the plough 13 of the cleaning machine 8 advantageously has a first bedding height h2' of 250 mm, measured from the exposed subgrade 3 to the lower edges of the sleepers 6. With a stabilization unit 14 integrated in the cleaning machine 8, the ballast bed 4 is compacted to a second bedding height h3' (approx. 230 mm).
[0040] In a second work phase, new ballast 1 is deposited onto track 2 by means of a ballast train 15. A ballast plough 16 distributes this ballast 1 for a subsequent tamping process. During this process, a lifting unit 19 of a tamping machine 18 lifts the track deck 5 with an initial lift h4' by advantageously 70 mm. This achieves a third ballast height h5' of approximately 300 mm.
[0041] According to the present invention, the track grid 5 is secured in this raised position in two steps using a deep tamping unit 22. Such a unit 22 is disclosed in AT 522237 A1 by the same applicant. Compared to a conventional tamping unit 20, the deep tamping unit 22 has a larger vertical range of motion of the tool carrier. In addition, longer tamping tines 23 are used.
[0042] In a first step, the tamping picks 23 of the deep tamping unit 22 are immersed in a lower layer of the ballast bed 4 and are vibrated there. The upper edges of the pick plates located at the ends of the tamping picks are at least 100 mm below the lower edges of the sleepers 6. The vibration is advantageously generated by a rotating eccentric shaft to which hydraulic positioning cylinders are connected. The positioning movement and vibration can also be superimposed in the respective hydraulic cylinder, whereby a corresponding control system with integrated displacement measurement must be provided.
[0043] To achieve the specified tamping forces and tamping times, the tamping cylinders must be pressurized accordingly during deep tamping. The pressure setting must be adjusted so that the same forces and times are achieved during deep tamping as during the subsequent normal tamping. The overall compaction result may be positively influenced if the tamping tines 23 are only vibrated during the first compaction step. This eliminates the need for a tamping process.
[0044] Immediately following, a second compaction step follows, in which the tamping tines 23 are lowered into an upper depth layer of the ballast bed 4. A setting process is performed there under vibration. This upper depth layer lies between the previously compacted lower depth layer and the lower edges of the sleepers 6. In this way, the ballast bed 4 is compacted over the entire bedding height h5' by means of the deep tamping unit 22. A stabilization process then follows using a stabilization machine 21, resulting in a slightly reduced bedding height h6' (approximately 295 mm).
[0045] The final geometry of track 2 is created in a final work phase. During this phase, track 2 is processed using the same or a separate tamping machine 18. A lifting / straightening unit 19 lifts track panel 5 with a slight camber compared to the specified track geometry. This takes subsequent track settlement into account during stabilization. This second lift h7' is in the range of 20 mm to 25 mm and is thus significantly less than the first lift h4'. In addition, track panel 5 is laterally straightened.
[0046] A tamping unit 20 for the simultaneous under-tamping of several sleepers 6 reduces the processing time during this work phase. This tamping unit 20 is arranged either in addition to the deep tamping unit 22 on the same tamping machine 18 or on a separate tamping machine 18. In the former case, the same lifting / straightening unit 19 is advantageously used for all lifting steps. Finally, a stabilization process is carried out by means of a stabilization unit 14. This is arranged either in a separate stabilization machine 21 or on a machine frame coupled to the tamping machine 18.
[0047] The new working method is not limited to the track cleaning process illustrated by way of example. In particular, the method according to the invention is applicable to cleaning trains with integrated tamping machines 18 and stabilizing machines 21, and optionally, plough blades 17. The method can also be used for switch cleaning or switch replacement. Here, too, ballast is introduced at a time up to a bedding height h2' of 250 mm and then compacted in a single pass using deep tamping, normal tamping, and stabilization.
Claims
1. A method for cleaning a ballast bed (4) of a track (2) by means of track-bound machines (8, 18, 21), with ballast (1) located below a track panel (5) being removed by means of a cleaning machine (8) using a ballast removal device (10), with cleaned and / or new ballast (1) being placed behind, in relation to a working direction (12), in the track (2) in several layers by means of a ballast placement device (11) and a ballast train (15), and with the placed ballast (1) being compacted by means of a tamping machine (18) and a stabilizing machine (21), characterized in that, prior to a first tamping process, all layers of the new and / or cleaned ballast (1) are placed by means of the ballast placement device (11) and the ballast train (15), that the ballast bed (4) is compacted in different depth layers during the first tamping process by means of a deep tamping unit (22), that the track (2) is then stabilized by means of the stabilizing machine (21), that the track panel (5) is then immediately tamped in only one depth layer by means of the same or a further tamping machine (18) in a second tamping process, and that the track (2) is stabilized after the second tamping process by means of the same or a further stabilizing machine (21).
2. A method according to claim 1, characterized in that the ballast bed (4) is cleaned at least with a removal height (h1) of 300 mm.
3. A method according to claim 1 or 2, characterized in that ballast (1) for a bed height (h2') of at least 200 mm, particularly of at least 250 mm, is placed by means of the ballast placement device (11).
4. A method according to one of the claims 1 to 3, characterized in that the track panel (5) is lifted by at least 50 mm, particularly by at least 70 mm, in the first lifting process.
5. A method according to one of the claims 1 to 4, characterized in that the track panel (5) is lifted during the second lifting process with a lift in a range between 15 mm and 25 mm, particularly in a range between 20 mm and 25 mm.
6. A method according to one of the claims 1 to 5, characterized in that, after the first lifting process, by means of the deep tamping unit (22) a first tamping process is carried out in a lower depth layer of the ballast bed (4) with vibrating and squeezing tamping tines (23), and a second tamping process is carried out in an upper depth layer of the ballast bed (4) with the same tamping tines (23).
7. A method according to one of the claims 1 to 6, characterized in that the tamping process is carried out after the second lifting process by means of a multi-sleeper tamping unit (20).
8. A method according to one of the claims 1 to 7, characterized in that the tamping work is carried out with a tamping machine (18) integrated into a cleaning train.