Climbing boot for a rail-guided climbing system
The climbing shoe's pivotable and extendable design simplifies decoupling from the climbing rail, addressing inefficiencies and ergonomic issues in existing systems by allowing easy handling and reducing the number of shoes required for tall structures, enhancing safety and reducing manual effort.
Patent Information
- Application Number
- EP2021843983
- Authority / Receiving Office
- EP · EP
- Patent Type
- Patents
- Current Assignee / Owner
- Priority Date
- 2020-12-23
- Filing Date
- 2021-12-22
- Publication Date
- 2024-09-18
- Estimated Expiration
- 2041-12-22
AI Technical Summary
Existing climbing shoes for rail-guided climbing systems are inefficient and costly due to the need for multiple shoes to cover tall building heights, and they pose ergonomic and safety challenges during decoupling and reattachment processes, often requiring multiple handles and risking loss or misplacement of connecting elements.
A climbing shoe with pivotable and extendable rail guide elements, a receiving element for load introduction, and a displacement element with a handle that allows for easy decoupling from the climbing rail by moving the rail guide elements into a retracted position, ensuring ergonomic handling and reducing manual effort.
The solution enables quick, ergonomic, and safe decoupling of the climbing shoe from the wall or ceiling and release from the climbing rail, reducing the number of shoes needed and minimizing manual effort, while preventing loss of parts and enhancing occupational safety.
Smart Images

Figure IMGF0001 
Figure IMGF0002 
Figure IMGF0003
Abstract
Description
[0001] The invention relates to a climbing shoe for a rail-guided climbing system, comprising a shoe base body with first and second rail guide elements, wherein at least the first rail guide element, in particular the first and second rail guide elements, is / are pivotably and / or extendably arranged on the shoe base body such that, in the pivoted and / or extended guide state, a climbing rail displaceably arranged between the first and second rail guide elements is guided by the rail guide elements, with partial sections of the climbing rail being encompassed by the rail guide elements. The invention further relates to a rail-guided climbing system having this climbing shoe and a method for decoupling this climbing shoe coupled to a concreting section of a structure.
[0002] Self-climbing formwork is commonly used for the construction of tall buildings. This involves the formwork, a mold used to create concrete walls on a construction site, for example, being moved along a formed wall in the climbing direction, which in the case of walls points upwards, i.e. the formwork can be climbed. Rails are attached to the walls, along which the formwork can be moved upwards. The rails are secured to the wall with climbing shoes. The rails can then be pushed upwards using these climbing shoes so that another storey can be concreted, e.g. using a lifting device such as a hydraulic unit. The climbing shoes themselves are each attached to the wall via a bracket.
[0003] Climbing shoes, which serve as a connecting element between the already completed part of the building to be constructed and the climbing equipment and guide a vertically movable rail to which, for example, formwork and / or protective enclosures are attached, are used, for example, in the Rail Climbing System, abbreviated RCS, from PERl.
[0004] During a climbing process, several climbing shoes are typically required, arranged one below the other, to support and / or guide the climbing rail and assist the climbing mechanism, e.g., by allowing the lifting device to lean on these climbing shoes to move the rails upwards. Therefore, to concrete a tall building, a large number of climbing shoes would be required, arranged one below the other, to allow the self-climbing system to climb the entire height of the building. However, this is inefficient and expensive, which is why climbing shoes that are no longer needed, for example, those that have already been "climbed over" by the climbing system, should be reused. This reduces the total number of climbing shoes required.
[0005] The climbing shoe used in the RCS system is described in DE 10 2005 030 333 B4. It essentially consists of two parts: the wall or ceiling shoe and the sliding shoe. The wall shoe is attached to a wall, or the ceiling shoe is attached to a ceiling, e.g., concrete. The sliding shoe, which is pivotally connected to the wall or ceiling shoe, is connected to the climbing rail, i.e., it serves as a guide for the climbing rail, as a support for the lifting device, and as a holding point for the climbing rail. The wall or ceiling shoe is removed and installed at a higher location for reuse. To detach the sliding shoe from the wall or ceiling shoe and reattach it to the new location, the following steps must be performed (steps 1 to 6: detaching and transporting the climbing shoe, steps 7 - 10: attaching the climbing shoe): 1. Climbing shoe 10 must be "folded open," i.e., if the two claws 50 are designed to be foldable, both claws 50 enclosing the climbing rail 20 must be opened. To do this, two locking pins 56 must be pulled out and then reinserted into the sliding shoe 16. 2. Loosen the locking pin on the fastening bolt 34. 3. Pull the fastening bolt 34 while holding the climbing shoe, if necessary.by a second person, 4) Climbing shoe 10 can then be lifted out from between wall 14 and climbing rail 20, 5) Disassemble wall / ceiling shoe 18, 6) Both parts, wall / ceiling shoe 18 and sliding shoe 16, must finally be transported upwards into the new climbing area, i.e., the area in the climbing direction where the climbing shoe is to be used, 7) Mount the wall / ceiling shoe 18 at the designated anchor point in the new climbing area, 8) The opened sliding shoe 16, with the claws 50 open, must be positioned and held relative to the wall / ceiling shoe 18 so that the fastening bolt 34 reconnects the sliding shoe 16 to the wall / ceiling shoe 18, 9) Insert a safety pin onto the fastening bolt 34, and 10) the sliding shoe 16 must be "folded" to create a guide for the climbing rail 20, i.e. the two claws 50 which are still open must be closed.For this purpose, the two locking pins 56 must be pulled out, the claws 50 closed, and the locking pins 56 reinserted.
[0006] According to another prior art document EP 3 241 959 A1, a climbing shoe is disclosed in which a recess 16 is provided in each of two claws 11 of the climbing shoe (see Fig. 7 This document). By engaging the recesses 16 with the hand, the claws 11 can be pulled back individually, thus opening the climbing shoe. The steps for release, transport, and fastening are essentially the same as those required in EP 3 241 959 B1. A climbing shoe is also disclosed in the prior art document EP3272967A1.
[0007] The following disadvantages arise when removing and attaching the well-known climbing shoes to a wall or ceiling: Several manual movements are necessary, resulting in poor ergonomics and a high susceptibility to errors when carrying out the manual movements. Several connecting elements, e.g. wall or ceiling shoes and sliding shoes, are necessary, thus there is a risk of losing these connecting elements. Several steps have to be carried out at the same time, e.g. the climbing shoe has to be held in the hole position. For reasons of strength, the climbing shoe is made heavy with regard to its load-bearing capacity and can only be held briefly with one hand by a worker in order to insert a fastening bolt, which is held in the other hand, into the hole in the hole position, which is ergonomically disadvantageous and prone to errors.Two people may even be necessary to release and reattach the climbing shoe, for example, if the climbing shoe can only be held with both hands and the fastening bolt has to be inserted into the hole in the hole position by another worker.
[0008] In contrast, the object of the present invention is to provide a compact and portable climbing shoe for a rail-guided climbing system, which can be decoupled from a wall or ceiling of a concreting section of a building and released from a guide of a climbing rail of the climbing system easily and without great manual effort. In particular, the climbing shoe for the rail-guided climbing system should allow it to be decoupled quickly and ergonomically from the wall or ceiling of the concreting section and released from the guide of the climbing rail without any parts of the climbing shoe becoming lost. The climbing shoe according to the invention is therefore intended to avoid or at least reduce the disadvantages of the prior art when decoupling the climbing shoe from the wall or ceiling and releasing the climbing shoe from a guide of the climbing rail, which can lead to errors when detaching the climbing shoe from the wall or ceiling.Ceiling and its guide of the climbing rail and increases work safety.
[0009] This object is achieved by a climbing shoe having the features of patent claim 1 and a method for decoupling a climbing shoe attached to a concrete section of a structure having the features of patent claim 14. The subclaims specify expedient further developments.
[0010] The object of the invention is thus achieved by a climbing shoe for a rail-guided climbing system, which can be used in particular as a climbing formwork, climbing scaffold, climbing protection wall, and / or climbing work platform. The climbing shoe comprises a shoe base body with first and second rail guide elements, wherein at least the first rail guide element, in particular the first and second rail guide elements, is / are pivotably and / or extendably arranged on the shoe base body such that, in the pivoted and / or extended guide state, i.e., in the "closed" position, a climbing rail slidably arranged between the first and second rail guide elements is guided by the rail guide elements, with partial sections of the climbing rail being encompassed by the rail guide elements.The climbing shoe further comprises a receiving element arranged on the shoe base body, which is designed to interact with a first partial section of a console element arranged in a fixed position on a concreting section of a building in such a way that when the receiving element rests on the first partial section of the console element, a load of the climbing shoe can be introduced into the console element.Finally, the climbing shoe comprises a sliding element provided with a handle, which is designed such that it is mechanically coupled to the shoe base body and the first rail guide element, and, when the first rail guide element is in the guided state, a displacement of the sliding element relative to the shoe base body in a decoupling direction caused by actuation of the handle results in the first rail guide element being moved into the non-pivoted and / or retracted initial state, i.e. into the "open" position, in order to release the climbing shoe from a guide of the climbing rail.
[0011] The shoe base body and the sliding element can each be designed as a frame, whereby a shape as a flat body with or without recesses is possible. The shoe base body and the sliding element can consist of one or more parts / components that are detachably, i.e. reversibly, or irreversibly connected to one another. The parts or components of the shoe base body and sliding element can each be made of different materials, e.g. steel, aluminum or carbon fiber composite materials or a combination thereof, in order to keep the weight of the shoe base body and thus of the climbing shoe low. The advantages according to the invention already arise when the sliding element provided with the handle is only mechanically coupled to the shoe base body and the first rail guide element.In a preferred embodiment, however, the sliding element is mechanically coupled not only to the shoe base body but also to the first rail guide element, as well as to a locking element that serves to lock the climbing shoe to the console element. In the following, a coupling is understood to mean the attachment of one element to another element for the introduction or transfer of forces. A fastening is understood to mean a connection, for example, a screw or welded connection, between two elements in which the elements are firmly connected to one another in a form-fitting and / or force-fitting manner, i.e., they cannot be moved relative to one another.
[0012] The first and / or second rail guide elements can be pivotably and / or extendably mounted on the shoe base body by means of mechanical coupling elements, e.g., in the form of an axle element, such as a cylindrical bolt, and / or a displacement element. A combination of pivotable and extendable mounting of the at least one rail guide element on the shoe base body is possible. Preferably, both the first and second rail guide elements are pivotably mounted on the shoe base body and can be converted from the pivoted-in initial state to the pivoted-out guide state and vice versa by pivoting.
[0013] The receiving element arranged on the shoe base body can be arranged on the shoe base body by means of mechanical coupling elements, e.g., in the form of a screw or a bolt, or integrally with the shoe base body. Preferably, the receiving element is arranged in the form of a hook open counter to a climbing direction on an outer section of the shoe base body, e.g., on a lower section of the shoe base body when the climbing shoe is aligned with its longitudinal axis in the vertical climbing direction. In this case, the handle of the sliding element is preferably arranged in an upper section of the sliding element.Any form of mechanical coupling by attaching the receiving element to the first section is possible, provided it allows the load applied to the climbing shoe, which may be the weight of the climbing shoe itself or a load of the climbing system or a part thereof applied to the climbing shoe, to be transferred to the first section of the console element. Thus, simply placing the receiving element on the first section of the console element, which prevents movement of the receiving element in the direction of gravity, may be sufficient. The mechanical coupling between the receiving element and the console element can be removed by separating these elements from each other.The receiving element can be pivotally mounted on the shoe base body and can be converted from the pivoted-in initial position to the pivoted-out receiving position and vice versa by pivoting, whereby a locking function of the receiving element on the console element is not required. The receiving element can interact with the locking element of the shoe base body to lock the climbing shoe to the console element when the locking element is in the locked position.When the climbing shoe is aligned with its longitudinal axis in the vertical climbing direction, the receiving element can have a substantially horizontally oriented and cylindrical recess that opens downwards opposite to the climbing direction in order to receive a console support element, for example in the form of a cylindrical bolt, as a partial section of the console element when the climbing shoe is placed onto the console element from above, i.e. in the direction opposite to the climbing direction, or is suspended in the console element. The console element can be designed as a suspension element for suspending the climbing shoe, for example as a suspension ring, wherein all designs of the first partial section of the console element are included which interact with the receiving element such that when the receiving element rests against the first partial section of the console element, a load from the climbing shoe can be introduced into the console element.
[0014] The sliding element and the shoe base body can be arranged so as to be displaceable essentially parallel to one another in the decoupling direction. The handle is preferably arranged in an outer section of the sliding element and is connected to the sliding element detachably, e.g., by means of a screw or locking / snap connection, or irreversibly, e.g., in the case of an integrally formed element.
[0015] The sliding element can be pivotably and / or extendably coupled to the shoe base body, the first rail guide element, and the locking element by means of mechanical coupling elements, e.g., in the form of an axle element, such as a cylindrical bolt, and / or a displacement element, e.g., in the form of a carriage that can be guided via recesses in the shoe base body, or the sliding element itself, and / or a lever element and / or a driver element, e.g., in the form of a rod. A combination of a pivotable and extendable arrangement of the sliding element to the first and / or second rail guide element and the locking element is possible.Thus, when the climbing shoe is coupled to the console element and aligned with its longitudinal axis in the vertical climbing direction, the sliding body can be arranged so as to be displaceable essentially vertically and parallel to the shoe base body and can be coupled via two essentially vertically aligned rods to the ends of an axle element designed as a bolt for pivoting the locking element in and out in the form of a latching lug. Furthermore, in this case, the sliding body can be rotatably connected to the vertically pivotable first and second rail guide elements via two driver elements designed as arms, such that when the handle is actuated upwards in the vertical climbing direction, both the locking element and the first and second rail guide elements are returned to their initial state, thus decoupled from the console element and released from the guidance of the climbing rail.
[0016] Alternatively, the sliding element can be mechanically coupled to the shoe base body, the first and optionally second rail guide element and the locking element by means of tube-screw contours, also called guide elements. In this embodiment, the handle is connected to a rail or integrated into the rail, whereby the rail can only be moved / displaced relative to the shoe base body in and against the climbing direction, for example vertically, when the climbing shoe is mounted. The rail can be designed as part of the sliding element. When the handle is moved in the climbing direction, the rail moves in the climbing direction, for example vertically upwards, and when the handle is moved against the climbing direction, the rail moves against the climbing direction, for example vertically downwards.Parallel to the rail, a further rail section, the length of which can be shorter than the length of the rail in its longitudinal direction, can be connected to the rail at one end of the rail in the climbing direction, for example an upper end of the rail, or can be integrated into the rail and in this way connected to the handle in such a way that a free end of the rail section, in a closed climbing shoe, can engage both in a first recess in the shoe base body and in a first recess in the first or second rail guide element to secure the position of the rail guide element. The other end of the rail, for example the lower end, can also serve to secure the position of the rail guide element and, like the free end of the rail section, can engage in a second recess in the shoe base body and in a second recess in the first or second rail guide element.
[0017] A rod-shaped element, for example a bolt, can be fixed to the rail or integrated into the rail perpendicular to a longitudinal axis of the rail and moves with the rail when the handle is moved in or against the climbing direction, for example vertically up and down. The rod-shaped element can be guided by a rod-shaped guide element, for example another rail or a cylinder or axle element arranged parallel to the rail. The first rail guide element or each of the first and second rail guide elements has a third curved recess with a width that allows a free end and / or a section of the rod-shaped element to engage in the recess or to guide the recess, i.e. to run in the recess.The curved recess can have a screw- or thread-shaped profile in order to rotate the rail guide element when the rod-shaped element running in the recess is moved in or against the climbing direction relative to the shoe base body by actuating the handle. If, with the climbing shoe closed, the handle is actuated / pulled to unlock the climbing shoe in the climbing direction, for example upwards, the rail with the rod-shaped element moves in the climbing direction, for example vertically upwards, while the shoe base body is stationary. Since the rail and the rod-shaped element can only move in the climbing direction, e.g.vertically upwards, the rod-shaped element guides the rail guide element during the displacement of the rod-shaped element in such a way that, due to the curved recess, the rail guide element rotates to such an extent that a fictitious straight line of the recess is formed at the location of the rod-shaped element via the displacement of the rod-shaped element in the climbing direction that the rod-shaped element can travel.
[0018] The first and / or second rail guide element can each comprise an at least partially cylindrical hollow body into which the third curved recess is formed, for example, over a length of the displacement path of the handle relative to the shoe base body. The rail can be guided in the at least partially cylindrical hollow body such that the rod-shaped element can engage in the recess over its displacement path in order to guide the first and / or second rail guide element such that it is rotated relative to the shoe base body during the displacement of the handle.If the first and / or second rail guide element is to be rotated relative to the shoe base body in order to close the climbing shoe, the handle is moved relative to the shoe base body in the same way as when opening the climbing shoe, counter to the climbing direction, so that, since the rail and the rod-shaped element can only be moved counter to the climbing direction, e.g. vertically downwards, the rod-shaped element guides the respective rail guide element during the displacement of the rod-shaped element in such a way that, due to the curved recess, the respective rail guide element rotates along with it in order to close the climbing shoe.
[0019] The climbing shoe according to the invention for the construction sector thus has a handle on the sliding element, with the actuation of which the climbing shoe can be easily separated from the console element and released from the guide of a climbing rail when the displacement of the sliding element relative to the shoe base body, generated by the actuation of the handle, occurs in the decoupling direction. Preferably, the climbing shoe can be recoupled to the console element at the handle when the displacement of the sliding element relative to the shoe base body, generated by the actuation of the handle, occurs in the coupling direction, opposite to the decoupling direction. By actuating the handle, e.g., by a pulling movement, the rail guide elements, which encompass the climbing rail for guidance, open.Optionally, operating the handle also opens a locking element that secures the climbing shoe to the console element, and / or a latching or snap-in element into which the climbing rail is hooked before opening. In this way, the climbing shoe can be quickly and easily uncoupled / released from the console with just one movement and then removed. By operating the handle on the sliding element of the climbing shoe, several functions within the climbing shoe are carried out. This is necessary in order to easily uncouple / release and remove the climbing shoe between the console element of a wall or ceiling and the climbing rail, i.e. to dismantle, attach or install it.When activated, for example, by "pulling" the handle, the rail guide elements unlock and open, and the receiving element is separated from the console element. An existing locking element and / or latching / snap element is returned to its original position, i.e., opened or unlocked. This allows for simple and easy release and removal of the climbing shoe, i.e., removal of the climbing shoe from between the climbing rail and the structure.
[0020] If the climbing shoe is subsequently reattached to a different location on the structure to be erected, the rail guide elements and the optional locking element and / or optional latching / snap element for attaching the climbing rail are closed by further actuation of the handle in the coupling direction, e.g., by a downward pulling movement or by a pushing movement, i.e., "pushing" in reverse. The climbing shoe according to the invention thus allows for easy and minimal manual effort to be detached from a wall or ceiling and released from the guide of a climbing rail of the climbing system with just one movement.Since the climbing shoe can be held by the handle, which, when activated, also releases the climbing shoe from the console element and from a climbing rail guide, the climbing shoe allows for quick and ergonomic removal from the wall or ceiling of the concreting section and removal from the climbing rail guide. Since the sliding element is mechanically coupled to the shoe base body and the first rail guide element, thus mechanically coupling the moving parts of the climbing shoe, these parts of the climbing shoe cannot be lost when the climbing shoe is removed.
[0021] As mentioned above, the climbing shoe can comprise a locking element arranged on the shoe base body in a pivotable and / or extendable manner, which is designed to cooperate either with the first sub-section of the console element and the receiving element or with a second sub-section of the console element such that in the pivoted and / or extended locking state, the climbing shoe is releasably locked to the console element, wherein the sliding element provided with the handle is designed such that it is mechanically coupled to the shoe base body, the first rail guide element and the locking element, and, when the first rail guide element is in the guide state and the locking element is in the locked state, the displacement of the sliding element relative to the shoe base body in the decoupling direction caused by an actuation of the handle leads tothat the first rail guide element and the locking element are each set in the non-pivoted and / or retracted initial state in order to release the climbing shoe from a guide of the climbing rail and from a locking device on the console element.
[0022] The locking element arranged so as to be pivotable and / or extendable on the shoe base body can be pivotably and / or extendably arranged on the shoe base body by means of mechanical coupling elements, e.g. in the form of an axle element, such as a cylindrical bolt, or a displacement element. A combination of a pivotable and extendable arrangement of the at least one locking element on the shoe base body is possible. The locking element is preferably arranged as a latching or snap-in element in the form of a nose on an outer section of the shoe base body, e.g. on a lower section of the shoe base body when the climbing shoe is aligned with its longitudinal axis in the vertical climbing direction. In this case, the handle of the displacement element is preferably arranged in an upper section of the displacement element.The locking element can be pivotally attached to the shoe base body and can be converted from the pivoted-in initial state into the pivoted-out locking state and vice versa by pivoting. The locking element can interact with the receiving element of the shoe base body to fasten the climbing shoe to the console element when the locking element is in the locked state. When the climbing shoe is aligned with its longitudinal axis in the vertical climbing direction, the receiving element can have a substantially horizontally oriented and cylindrical recess which opens downwards opposite to the climbing direction in order to accommodate a console support element, for example in the form of a cylindrical bolt, as the first section of the console element when the climbing shoe is placed onto the console element from above, i.e. in the direction opposite to the climbing direction.
[0023] As already mentioned, the climbing shoe can further comprise at least one locking / snap-in element arranged on the shoe base body so as to be pivotable and / or extendable, which is designed to cooperate with a holding element of the climbing rail and / or a climbing lifting rail, which is displaceable relative to the climbing rail and guided by the climbing rail, for holding the at least one locking / snap-in element such that, in the pivoted and / or extended holding state, i.e., in the "closed" position, the climbing rail and / or climbing lifting rail can be hooked into the climbing shoe in a direction opposite to a climbing direction. The sliding element is designed such that it is mechanically coupled to the shoe base body, either to the first rail guide element or to the first rail guide element and the locking element, and additionally to the locking / snap-in element.If either the first rail guide element is in the guide state or the first rail guide element and the locking element are in the locking state, and additionally the latching / snap element is in the pivoted and / or extended holding state, i.e., in each case in the "closed" position, the displacement of the displacement element relative to the shoe base body generated by the operation of the handle results in either the first rail guide element or the first rail guide element and the locking element, and additionally the latching / snap element, being moved to the non-pivoted and / or retracted initial state, i.e., in each case in the "open" position, in order to either release the climbing shoe from the guide of the climbing rail or to release it from the guide of the climbing rail and release it from the locking on the console element, and additionally to free it from the holding state of the climbing rail and / or climbing lifting rail.In this embodiment, the locking / snap element supplements the function of the handle in such a way that when the handle is operated, not only is the climbing shoe separated from the console element and released from its guide of the climbing rail, but the climbing shoe is also released from the holding state of the climbing rail / climbing lifting rail.
[0024] The locking / snap-in element can either comprise a latch arranged substantially on a longitudinal axis of the climbing shoe or two latches arranged substantially horizontally from the longitudinal axis, in particular at substantially equal distances from the longitudinal axis. The latch or the two latches are designed to interact with one or more holding elements of the climbing rail for holding the latch or the two latches of the first locking / snap-in element in such a way that, in the pivoted and / or extended holding state, the climbing rail can be hooked into the climbing shoe in a direction opposite to a climbing direction. Two latches can accommodate a higher load than just one latch, whereby the latches can be actuated in pairs and can also be mechanically connected to one another in pairs.
[0025] The climbing direction can indicate an upward direction, although a sideways direction is also possible, for example in tunnel construction. Inclined linear, translational or curved, for example rotational directions are also possible as a climbing direction. The locking / snap element arranged so as to be pivotable and / or extendable on the shoe base body can be pivoted and / or extendable on the shoe base body by means of mechanical coupling elements, e.g. in the form of an axle element such as a cylindrical bolt, or a travel element. A combination of a pivotable and extendable arrangement of the at least one locking / snap element on the shoe base body is possible. The climbing direction can correspond to the decoupling direction. Other directions to one another, e.g. opposite or at right angles to one another, are also possible.
[0026] In a particularly preferred embodiment, the displacement element is designed such that, when the first rail guide element, the first rail guide element and the locking element, the first rail guide element and the latching / snap element, or the first rail guide element, the locking element and the latching / snap element are each in the non-pivoted and / or retracted initial state, i.e. in the "open" position, a displacement of the displacement element relative to the shoe base body, generated by a further actuation of the handle, in a coupling direction opposite to the decoupling direction, leads to the first rail guide element being moved into the guiding state, the first rail guide element being moved into the guiding state and the locking element into the locking state, the first rail guide element being moved into the guiding state and the latching / snap element into the holding state,or the first rail guide element is set to the guide position, the locking element to the locking position, and the latching / snap-in element to the holding position, i.e., each in the "closed" position, in order to place the climbing shoe in the guide of the climbing rail, to place the climbing shoe in the guide of the climbing rail and lock it to the console element, to place the climbing shoe in the guide of the climbing rail and lock it to the holding position of the climbing rail and / or climbing lifting rail, or to place the climbing shoe in the guide of the climbing rail, lock it to the console element, and lock it to the holding position of the climbing rail and / or climbing lifting rail. The sliding element is thus designed such that, upon actuation of the handle, the resulting displacement of the sliding element relative to the shoe base body occurs in a coupling direction opposite to the decoupling direction.The climbing shoe is coupled to the console element and placed in the guide of the climbing rail. If necessary, the climbing shoe is also locked to the console element and / or placed in the holding position of the climbing rail / climbing rail. The handle can therefore be used both to decouple / release and to couple / attach the climbing shoe to the console element and / or the climbing rail.
[0027] If the climbing shoe comprises at least one further locking / snap element arranged on the shoe base body so as to be pivotable and / or extendable, which interacts with at least one further holding element of the climbing rail and / or the climbing lifting rail to hold the further locking / snap element in such a way that, in the pivoted and / or extended holding state, the climbing rail and / or the climbing lifting rail can be hooked into the climbing shoe in a direction opposite to the climbing direction, wherein the locking / snap elements can be actuated simultaneously or independently of one another by means of the handle, the sliding plate can be designed such that, after the handle has been actuated, the climbing shoe can be released not only from the climbing rail, but separately or additionally from the climbing lifting rail. The use of the climbing shoe in climbing systems with multiple latches for holding the climbing lifting rail is also possible in this way.
[0028] Preferably, when the climbing shoe is coupled to the console element and a longitudinal axis of the climbing shoe is aligned in the climbing direction, a first locking / snap element of the locking / snap elements is arranged on the longitudinal axis of the climbing shoe in the climbing direction and substantially perpendicularly spaced from the longitudinal axis, in particular at equal intervals, while second and third locking / snap elements of the locking / snap elements are arranged. If the climbing direction points vertically upwards, the second and third locking / snap elements are arranged substantially horizontally spaced from the longitudinal axis. In this way, the climbing shoe can transfer a load from the climbing rail into the wall or ceiling that is higher than a load that is absorbed by only one or two locking / snap elements when the climbing rail and / or climbing lifting rail is attached. The symmetrical alignment of the locking / snap elements to the longitudinal axis simplifies the construction of the climbing shoe.In addition, the load-bearing capacity of the climbing shoe is optimized when the locking / snap elements are aligned symmetrically to the longitudinal axis.
[0029] It is advantageous if the first locking / snap element is arranged relative to the shoe base body such that it interacts with the further holding element of the climbing lifting rail for locking / snapping the first locking / snap element, and the second and third locking / snap elements are arranged relative to the shoe base body such that they interact either with further holding elements of the climbing lifting rail or with further holding elements of the climbing rail, each of which is different from the further holding element of the climbing lifting rail for locking / snapping the first locking / snap element, for locking / snapping the second and third locking / snap elements. In this embodiment, the second and third locking / snap elements can be used for holding elements in the climbing rail or for further holding elements in the climbing lifting rail, which leads to a high degree of flexibility in the use of the climbing shoe on the construction site.
[0030] It is also advantageous if first and second pawls of the first locking / snap element are arranged substantially on a first axis substantially perpendicular to the longitudinal axis of the climbing shoe, spaced from the longitudinal axis, in particular at substantially equal distances from the longitudinal axis, and second and third further locking / snap elements are arranged spaced therefrom in or opposite to the climbing direction, or at the same height in the climbing direction on a second axis substantially perpendicular to the longitudinal axis, spaced from the longitudinal axis, in particular at substantially equal distances from the longitudinal axis.By distributing the load-bearing capacity between two latches of the first locking / snap element and one latch each of the second and third additional locking / snap elements, whereby the first and second latches of the first locking / snap element and the latches of the second and third additional locking / snap elements can be actuated in pairs, the permissible load-bearing capacity can be higher than in a design in which the first locking / snap element has only one latch. To keep the design compact perpendicular to the longitudinal axis, the two latches of the first locking / snap element can be arranged offset relative to the second and third additional locking / snap elements in or against the climbing direction.
[0031] Depending on the design of the climbing rail and / or climbing lifting rail, it may be advantageous for first distances from the longitudinal axis of the first and second latches of the first locking / snap element to differ from second distances of the second and third further locking / snap elements from the longitudinal axis, in particular for the first distances to be selected to be smaller than the second distances if the first and second latches of the first locking / snap element are arranged at a distance from the second and third further locking / snap elements in or against the climbing direction or are at the same height in the climbing direction as the second and third further locking / snap elements.The first and second latches of the first locking / snap-in element can be designed to cooperate with holding elements of the climbing lifting rail for holding the first and second latches of the first locking / snap-in element in such a way that, in the pivoted and / or extended holding state, the climbing lifting rail can be hooked into the climbing shoe in a direction opposite to a climbing direction, and the second and third further locking / snap-in elements can be designed to cooperate with one or more holding elements of the climbing rail for holding the second and third further locking / snap-in elements in such a way that, in the pivoted and / or extended holding state, the climbing rail can be hooked into the climbing shoe in a direction opposite to a climbing direction.The reverse embodiment, in which the first and second pawls of the first locking / snap element interact with the climbing rail and the second and third further locking / snap elements interact with the climbing lifting rail, is also possible.
[0032] It is particularly preferred if the climbing shoe is coupled to the console element and the longitudinal axis of the climbing shoe is oriented upwards in the vertical climbing direction, the handle is arranged in an upper section of the climbing shoe or forms an upper end of the climbing shoe, and the sliding element is coupled at least to the shoe base body in such a way that the handle is actuated in the decoupling direction vertically upwards in the climbing direction away from the shoe base body by means of a pulling movement, in particular with one hand. In this way, the climbing shoe can be released upwards with one hand from its coupling and any locking device with the console element and can be freed from any additional holding state of the climbing rail and removed from the wall or ceiling.
[0033] A particularly advantageous embodiment is provided when the climbing shoe comprises a finger sliding element provided with a finger grip, which is arranged displaceably relative to the shoe base body and the sliding element and is designed such that it is coupled to the shoe base body, the sliding element, the first rail guide element and the locking / snap element, and, when either the first rail guide element is in the guide state or the first rail guide element is in the guide state and the locking element is in the locking state, and the locking / snap element is in the holding state, i.e. the handle is not actuated, a finger displacement of the finger sliding element relative to the shoe base body and the sliding element in an unlocking direction, which is generated by actuating the finger grip, leads tothat the first rail guide element is locked in the pivoted and / or extended guide position, and the locking / snap-action element is set to the non-pivoted and / or retracted initial position in order to release the climbing shoe from the holding position of the climbing rail or climbing lifting rail and to guide the climbing rail or climbing lifting rail from the climbing shoe. If multiple locking / snap-action elements are present, the finger grip can be designed so that the locking / snap-action elements can be actuated simultaneously or independently of one another by the finger grip. By actuating the finger grip in the unlocking direction, the climbing shoe can be released from the climbing rail or climbing lifting rail.without releasing the locking mechanism of the climbing shoe on the console element and without removing the guide of the climbing rail or climbing lifting rail. This allows the climbing rail / climbing lifting rail to be easily moved in the climbing direction or against the climbing direction without uncoupling / releasing the climbing shoe from the console element. The climbing shoe can also be released from the climbing rail / climbing lifting rail before the climbing shoe is released from the console element, simplifying the process of releasing the climbing shoe from the climbing rail / climbing lifting rail.
[0034] The climbing shoe is particularly advantageously designed if the finger grip comprises a first finger grip element and a second finger grip element, wherein the first finger grip element is designed such that the at least one locking / snap element can be actuated by the first finger grip element, and the second finger grip element is designed such that the at least one further locking / snap element can be actuated independently of the at least one locking / snap element by the second finger grip element. In this way, the climbing shoe can be released / unlocked from the climbing rail or the climbing lifting rail independently of each other.
[0035] The climbing shoe is advantageously designed such that when the finger sliding element is displaced relative to the shoe base body and the sliding element by the amount of the finger displacement, i.e. the finger grip is actuated, the finger sliding element can be latched onto the shoe base body and / or the sliding element directly or indirectly, in particular by means of a central axis element, for example in the form of a bolt or a screw. When the finger sliding element is latched onto the shoe base body and / or the sliding element, the climbing rail / climbing lifting rail remains detached from the climbing shoe when the handle has been actuated to detach the climbing shoe from the console element, i.e. in the decoupling direction, or to attach the climbing shoe to the console element, i.e. in the coupling direction. This facilitates the decoupling of the climbing shoe.
[0036] By pulling and locking the finger-operated sliding element, the locking / snap-in element for holding the climbing rail / climbing rail can be set to its initial position, i.e., the "open" position. In one embodiment, setting the "open" position can only be achieved with a closed climbing shoe, i.e., when the locking element is set to the locked state, i.e., in the "closed" position. Due to the coupling of the locking element and the rail guide elements by the sliding element, "opening" the rail guide elements is then not possible.In addition, actuation of the finger grip can lock the mechanism for "opening" the rail guide elements by means of a spring element, which, when the finger grip is actuated, holds the locking element in the "closed" position and, due to the coupling to the rail guide elements via the sliding element, also holds the at least first rail guide element in the "closed" position. When the finger grip is not actuated, the climbing shoe can be in the state or working position in which the rail guide elements are in the guide position, an existing locking element is in the locked state, and an existing latching / snap element is in the holding state.
[0037] If the handle is designed as a first bar and the finger grip as a second bar, with the first and second bars thus arranged substantially parallel to each other, in particular spaced apart by 3 to 4 cm, the finger grip can be actuated when the handle is gripped. The climbing shoe can therefore be gripped when the finger grip is to be actuated. This simplifies the actuation of the finger grip, avoids errors when actuating the finger grip, and therefore ensures a high level of safety when using the climbing shoe.
[0038] The invention also encompasses a rail-guided climbing system comprising the climbing shoe according to the invention, the console element fixedly arranged on the concreting section of the structure, and the climbing rail displaceably arranged between the rail guide elements of the shoe base body, in particular with a climbing lifting rail that is displaceable relative to the climbing rail and guided by the climbing rail. The total length of the at least one climbing rail can be selected such that the climbing rail is guided by at least two climbing shoes spaced apart from each other at a predetermined distance, for example, one story height.
[0039] The invention also encompasses a method for decoupling a climbing shoe coupled to a concreting section of a structure for a rail-guided climbing system, which can be used in particular as a climbing formwork, climbing scaffold, climbing protection wall, and / or climbing work platform. The method comprises the following steps: a) Providing the climbing shoe with a shoe base body with first and second rail guide elements, wherein at least the first rail guide element, in particular the first and second rail guide elements, is / are pivotably and / or extendably arranged on the shoe base body such that, in the pivoted and / or extended guide state, a climbing rail displaceably arranged between the first and second rail guide elements is guided by the rail guide elements, in that partial sections of the climbing rail are encompassed by the rail guide elements, b) Providing a receiving element arranged on the shoe base body, which is designed to interact with a first partial section of a console element fixedly arranged on the concreting section of the structure,that when the receiving element is in contact with the first section of the console element, a load of the climbing shoe can be introduced into the console element, and c) providing a displacement element provided with a handle, arranged displaceably relative to the shoe base body and guided by the shoe base body, which displacement element is designed such that it is mechanically coupled to the shoe base body and the first rail guide element, and, when the first rail guide element is in the guided state, a displacement of the displacement element relative to the shoe base body in a decoupling direction caused by an actuation of the handle results in the first rail guide element being moved into the non-pivoted and / or retracted initial state in order to release the climbing shoe from a guide of the climbing rail, d) actuating the handle,wherein the generated displacement of the displacement element relative to the shoe base body results in the first rail guide element being moved into the non-pivoted and / or retracted initial state, and e) separating the receiving element from the first section of the console element and releasing the climbing shoe from a guide of the climbing rail).
[0040] The effects and advantages of this inventive method for decoupling a climbing shoe coupled to a concreting section of a structure correspond to those of the above-described inventive climbing shoe for a rail-guided climbing system. In the method steps, whenever the climbing rail is mentioned, this always refers to a climbing rail with or without a climbing lifting rail.
[0041] A method for decoupling the climbing shoe coupled to the concreting section of the structure for the rail-guided climbing system, wherein the climbing shoe is arranged between the concreting section and a climbing rail guided by the climbing shoe, is realized in a preferred embodiment of the invention when between steps b) and c), step b1) is additionally carried out: providing a locking element arranged on the shoe base body so as to be pivotable and / or extendable, which is designed to interact either with the first sub-section of the console element and the receiving element or with a second sub-section of the console element such that in the pivoted and / or extended locked state, the climbing shoe can be releasably locked to the console element, in step c) the sliding element is designed such that it is mechanically coupled not only to the shoe base body and the first rail guide element, but also to the locking element, and, if not only the first rail guide element is in the guide state, but also the locking element is in the locked state, the displacement of the sliding element relative to the shoe base body in the decoupling direction generated by actuating the handle leads tothat not only the first rail guide element, but also the locking element is moved into the non-pivoted and / or retracted initial state in order to release the climbing shoe from a guide of the climbing rail and from a lock on the console element. In step d), the displacement of the displacement element relative to the shoe base body caused by the actuation of the handle results in not only the first rail guide element, but also the locking element being moved into the non-pivoted and / or retracted initial state, and in step e), not only is the receiving element separated from the first section of the console element and the climbing shoe released from a guide of the climbing rail, but the locking of the climbing shoe on the console element is also released.
[0042] When a climbing rail is mentioned, this always refers to a climbing rail with or without a climbing lifting rail. This method offers the same advantages and effects as the previously described method, with the locking element for locking the climbing shoe to the console element being incorporated into the coupling of the sliding element to enable the locking of the climbing shoe to the console element to be released upon actuation of the handle.
[0043] Another method according to the invention for decoupling the climbing shoe coupled to the concreting section of the structure is carried out with the following steps when the climbing shoe is arranged between the concreting section and a climbing rail guided by the climbing shoe: between steps b) and c), step b2) is additionally carried out: B1) providing the climbing shoe with at least one locking / snap element arranged on the shoe base body so as to be pivotable and / or extendable, which cooperates with a holding element of the climbing rail and / or a climbing lifting rail, which is displaceable relative to the climbing rail and guided by the climbing rail, for holding the at least one locking / snap element in such a way that, in the pivoted and / or extended holding state, the climbing rail is hooked into the climbing shoe in a direction opposite to a climbing direction, in step c) the sliding element is designed such that it is mechanically coupled not only to the shoe base body, either to the first rail guide element or to the first rail guide element and the locking element, but also to the locking / snap element, and,if not only the first rail guide element is in the guide state or the first rail guide element is in the guide state and the locking element is in the locking state, but also the latching / snap element is in the pivoted and / or extended holding state, the displacement of the displacement element relative to the shoe base body in the decoupling direction caused by the actuation of the handle results in not only either the first rail guide element or the first rail guide element and the locking element, but also the latching / snap element being moved into the non-pivoted and / or retracted initial state in order to not only release the climbing shoe from the guide of the climbing rail or to release it from the guide of the climbing rail and to release it from the locking on the console element, but also to free it from the holding state of the climbing rail and / or climbing lifting rail,in step d) the displacement of the displacement element relative to the shoe base body caused by the actuation of the handle results in not only either the first rail guide element or the first rail guide element and the locking element, but also the latching / snap element being moved into the non-pivoted and / or retracted initial state, and in step e) not only a separation of the receiving element from the first section of the console element and a release of the climbing shoe from a guide of the climbing rail or a separation of the receiving element from the first section of the console element, a release of the climbing shoe from a guide of the climbing rail and a release of the locking of the climbing shoe on the console element, but also a release of the climbing shoe from the holding state of the climbing rail and / or climbing lifting rail takes place.
[0044] When a climbing rail is listed, this always refers to a climbing rail with or without a climbing lifting rail. This method offers the same advantages and effects as the previously described method, with the additional locking / snap-in element for holding the climbing rail / climbing lifting rail being incorporated into the coupling of the sliding element, allowing the climbing shoe to be released from the climbing rail / climbing lifting rail upon operation of the handle.
[0045] Another method of the invention is used to couple a climbing shoe to be coupled to a concreting section of a building, wherein the displacement element is designed such that, when the first rail guide element, the first rail guide element and the locking element, the first rail guide element and the latching / snap element, or the first rail guide element, the locking element and the latching / snap element are each in the non-pivoted and / or retracted initial state, a displacement of the displacement element relative to the shoe base body in a coupling direction opposite to the decoupling direction, generated by a further actuation of the handle, leads to the first rail guide element being moved into the guiding state, the first rail guide element being moved into the guiding state and the locking element into the locking state, the first rail guide element being moved into the guiding state and the latching / snap element into the holding state, or the first rail guide element into the guiding state,The locking element is set to the locking position and the latching / snap-in element is set to the holding position in order to place the climbing shoe in the guide of the climbing rail, to place the climbing shoe in the guide of the climbing rail and to lock it to the console element, to place the climbing shoe in the guide of the climbing rail and to put it in the holding position of the climbing rail and / or climbing lifting rail, or to place the climbing shoe in the guide of the climbing rail and to lock it to the console element and to put it in the holding position of the climbing rail and / or climbing lifting rail. The sliding plate is therefore designed in such a way that the climbing shoe can not only be decoupled from the console element or the console element and the climbing rail and / or climbing lifting rail by operating the handle, but can also be recoupled by operating the handle again. In this way, a simple,error-free and safe coupling and uncoupling of the climbing shoe is guaranteed.
[0046] If the process steps for uncoupling a climbing shoe coupled to a concreting section of a structure are carried out that the handle is arranged in an upper section of the climbing shoe or is formed as an upper end of the climbing shoe when the climbing shoe is oriented upwards in a vertical climbing direction, the sliding element is mechanically coupled at least to the shoe base body such that the actuation of the handle in the decoupling direction in the vertical climbing direction upwards away from the shoe base body takes place by means of a pulling movement, in particular one-handed, and in the continuous pulling movement in the climbing direction, the climbing shoe is released from a guide of the climbing rail and / or climbing lifting rail, released from a guide of the climbing rail and / or climbing lifting rail and released from the locking device on the console element, released from a guide of the climbing rail of the climbing rail and / or climbing lifting rail and released from the holding state of the climbing rail and / or climbing lifting rail,or is released from a guide of the climbing rail and / or climbing lifting rail, from a locking device on the console element and from the holding state of the climbing rail and / or climbing lifting rail and is removed from the concreting section held by the handle, In a continuous pulling motion, the climbing shoe can be decoupled from the console element or the console element and the climbing rail / climbing lifting rail and immediately removed from the concreting section by holding the handle without setting it down. This is a simple and safe step for the construction worker on site, and can also be performed one-handed.
[0047] If, in order to couple a climbing shoe to be arranged on a concreting section of a building, the climbing shoe held by the handle above the console element is brought closer to the concreting section and, in a continuous movement in the coupling direction opposite to the decoupling direction and counter to the climbing direction, the receiving element is placed on the first sub-section of the console element and, in addition, the climbing shoe is placed in the pivoted and / or extended guide state, placed in the pivoted and / or extended guide state and locked to the console element, placed in the pivoted and / or extended guide state and placed in the holding state of the climbing rail and / or climbing lifting rail, arranged, or placed in the pivoted and / or extended guide state, locked to the console element and placed in the holding state of the climbing rail and / or climbing lifting rail,Connecting the climbing shoe to the console element, or between the console element and the climbing rail / climbing lifting rail, is just as easy and safe as disconnecting the climbing shoe from it. When connecting the climbing shoe by moving vertically downwards against the climbing direction, there is no need to lift against gravity, which simplifies the connecting step of the climbing shoe, especially when performed one-handed.
[0048] The method steps according to the invention for decoupling and / or coupling the climbing shoe are preferably defined as a cycle and the cycle is run through until a scaffold unit and / or protective wall attached to the climbing rail has reached another or several further floors of the building or a next concreting section of the building to be concreted.
[0049] Further features and advantages of the invention will become apparent from the following detailed description of an exemplary embodiment of the invention, from the patent claims, and from the figures of the drawing, which illustrate details essential to the invention. The features shown in the drawing are presented in such a way that the special features of the invention can be clearly seen. The various features can be implemented individually or in combinations in variants of the invention. In the figures, identical reference numerals designate identical or corresponding elements.
[0050] They show: Fig. 1a, a side view of the climbing shoe according to the invention of a first embodiment in a "closed" position, in which the rail guide elements are in the guide state ( Fig. 1a ), and a further side view of the climbing shoe according to the invention of a second embodiment in a "closed" position, in which the rail guide elements are in the guide state, a locking element is in the locking state and a latching / snap element in the form of a pawl is in the holding state ( Fig. 1b ). Fig. 2a-spatial external views, side and rear views as well as cross sections of the Fig. 1b shown climbing shoe in different positions from the "closed" position to an "open" position, in which the rail guide elements, the locking element and the latch are in the initial state, Fig. 3a-c each in a spatial external view of the in Fig. 1b shown climbing shoe in "closed" position with a finger grip operated in an unlocking direction, in which the rail guide elements are in the guide position and the latch is in the initial position ( Fig. 3a ), with non-actuated finger grip, in which the rail guide elements are in the guide position and the latch is in the holding position ( Fig. 3b ), and in the "open" position, in which the finger grip actuated in the unlocking direction is carried by a sliding element ( Fig. 3c ), Fig. 4a-cden in Fig. 1b shown climbing shoe in "closed" position with the finger grip actuated and locked in the unlocking direction in side view ( Fig. 4a ), in spatial external view ( Fig. 4b ) and in cross-sectional view ( Fig. 4c ), Fig. 5a, bottom in Fig. 1b shown climbing shoe in "closed" position with finger grip not actuated in the unlocking direction, with the latch in the holding position, in cross-sectional view ( Fig. 5a ) and in spatial external view ( Fig. 5b ), Fig. 6a - spatial external views, side views and cross sections of the climbing shoe according to the invention in a third embodiment with three pawls, wherein a first pawl can engage in holding elements of a climbing lifting rail and second and third pawls can engage in support elements attached to a climbing rail, Fig. 7a - spatial external views, side views and cross sections of the climbing shoe according to the invention in a fourth embodiment with three pawls, wherein a first pawl can engage in holding elements of the climbing lifting rail and second and third pawls can engage in recesses of the climbing rail, and Fig. 8a, b spatial external views of the climbing shoe according to the invention in an open ( Fig. 8a ) and closed position ( Fig. 8b ) in a fifth embodiment with four pawls, wherein first and second pawls can engage in holding elements of the climbing lifting rail and third and fourth pawls can engage in recesses of the climbing rail.
[0051] Figur 1a shows a side view of the climbing shoe 1 according to the invention in a "closed" position, in which rail guide elements 3a, 3b (rail guide element 3b is concealed by rail guide element 3a and therefore not shown) are in a guided state, i.e., in the "closed" position. The climbing shoe 1 has a shoe base body 2 with the first rail guide element 3a, which is pivotally mounted on the shoe base body 2. In the pivoted guided state in the "closed" position, a climbing rail inserted between the rail guide elements 3a, 3b is guided by the rail guide elements.The climbing shoe 1 has a receiving element 5 enclosed by the shoe base body 2, which has a recess 5a in the X direction, for example in a cylindrical shape, which is open in the negative Z direction, i.e. downwards, counter to a climbing direction in the Z direction, in order to receive a console support element of the console element as a partial section of the console element when the climbing shoe 1 is placed on the console element in the negative Z direction, i.e. from above. The receiving element 5 acts after being placed on or placed on a partial section of the console element, as described further below in the . Figuren 1a und 1b As shown, the partial section of the console element for introducing a load from the climbing shoe 1 into the console element. The climbing shoe 1 also has a displacement element 6 provided with a handle 7, which is arranged displaceably relative to the shoe base body 2 and guided by the shoe base body 2. The displacement element 6 is designed such that it is mechanically coupled to the shoe base body 2 and the first rail guide element 3a. When the first rail guide element 3a is in the guided state, a displacement of the displacement element 6 relative to the shoe base body 2 in a decoupling direction in the Z direction, generated by actuating the handle 7, results in the first rail guide element 3a being moved into the non-pivoted initial state, i.e., the "open" position, in order to release the climbing shoe 1 from the guidance of the climbing rail.
[0052] Figur 1b shows a side view of the climbing shoe 1 according to the invention in a second embodiment in a "closed" position, in which the rail guide elements 3a, 3b (rail guide element 3b is not shown) are in a guide state, i.e. in the "closed" position, a locking element 4 in the locking state and a latching / snap element in the form of a pawl (in Fig. 1a not shown) are in a holding state, i.e., also in the "closed" position. The climbing shoe 1 thus has a locking element 4 pivotally mounted on the shoe base body 2, which interacts with a partial section of the console element of the concreting section of the structure to be erected such that, in the pivoted locking state, i.e., in the "closed" position, the climbing shoe 1 is releasably locked to the console element. In particular, the climbing shoe 1 can have the receiving element 5 encompassed by the shoe base body 2, which has the recess 5a in the X direction, which is open in the negative Z direction, i.e., downwards, counter to a climbing direction in the Z direction, in order to accommodate the console support element of the console element when the climbing shoe 1 is placed on the console element in the negative Z direction, i.e., from above.In this case, the receiving element 5 cooperates with the locking element 4 of the shoe base body 2 to lock the climbing shoe 1 to the console element in the locked state of the locking element 4.The climbing shoe 1 also has the sliding element 6, which is provided with the handle 7 and is arranged displaceably relative to the shoe base body 2 and guided by the shoe base body 2. The sliding element 6 is designed such that it is mechanically coupled to the shoe base body 2, the first rail guide element 3a, and the locking element 4. When the first rail guide element 3a is in the guided state and the locking element 4 is in the locked state, a displacement of the sliding element 6 relative to the shoe base body 2 in a decoupling direction in the Z direction, generated by actuation of the handle 7, results in the first rail guide element 3a and the locking element 4 each being displaced into the non-pivoted initial state, i.e., the "open" position, in order to decouple the climbing shoe 1 from the console element and to release it from guiding the climbing rail.
[0053] All of the following further embodiments of the Fig. 1b ff. shown climbing shoe 1 according to the invention also apply to the first embodiment of the climbing shoe 1 shown in Fig. 1a shown climbing shoe 1 according to the invention, provided that the features do not relate to the locking element 4 and the latching / snap element or are connected to these elements.
[0054] The climbing shoe made from Figur 1b is in spatial external view with the console element 8a for attachment to a ceiling and the climbing rail 9 in "closed" position in Fig. 2a shown, with the climbing shoe 1 in Fig. 2b in the "open" position and with the console element 8b for attachment to a wall in a further embodiment. In Figur 2a The console element 8a is oriented in the Y direction and can be attached to an already completed concreting section (not shown), for example, by means of screw connections. In both figures, the climbing shoe 1 is shown on a climbing rail 9 oriented in the climbing direction, i.e., the Z direction. Figur 2a The climbing shoe 1 is in the "closed" position, in which the rail guide elements 3a, 3b guide the climbing rail 9, in that sections of the climbing rail 9, which are oriented in an X / Z plane, are encompassed by the rail guide elements 3a, 3b. Although it is sufficient for the invention if one of the two rail guide elements 3a, 3b, in particular the first rail guide element 3a, is designed to be pivotable, in the case of the Fig. 1 In the climbing shoe 1 shown, both the first rail guide element 3a and the second rail guide element 3b are pivotally mounted on the shoe base body 2. In the "closed" position, the bracket element 8a is also locked, i.e., releasably attached, to the climbing shoe 1, more precisely to the shoe base body 2 of the climbing shoe 1, by means of the locking element 4. The bracket element 8a has a bracket support element 8c in the form of a bolt, which is oriented in the X direction and is guided into the opening 5a of the climbing shoe 1 in order to be fixed by the locking element 4 by means of the receiving element 5, thus connecting the bracket element 8a to the climbing shoe 1.When the locking element 4 is in the locked state and the rail guide elements 3a, 3b are in the guide state in which the climbing rail 9 is guided by the rail guide elements 3a, 3b, the sliding element 6 is pushed in with the handle 7 in the Z direction opposite to the decoupling direction relative to the shoe base body 2, so that a displacement of the sliding element 6 relative to the shoe base body 2 in the negative Z direction is not possible.
[0055] In contrast, in Figur 2b The sliding element 6 is displaced relative to the shoe base body 2 by a displacement in the decoupling direction generated by actuating the handle 7 in such a way that the rail guide elements 3a, 3b and the locking element 4 are each moved to the non-pivoted initial state, i.e., to the "open" position. When the handle 7 is fully actuated to move the rail guide elements and the locking element to the "open" position, the sliding element 6 cannot be displaced further in the Z direction relative to the shoe base body 2. If, after actuating the handle 7 in the Z direction, the rail guide elements 3a, 3b and the locking element 4 are in the "open" position, i.e. in their initial states, the climbing rail 9 can be released from the guide of the rail guide elements 3a, 3b and the console element 8b can be decoupled / released from the climbing shoe 1. Thus, according to Fig. 2b The bolt-shaped console receiving element 8c is not locked by the locking element 4, and the console element 8b can therefore be decoupled from the climbing shoe 1. The climbing rail 9 can also be oriented in the X or Y direction, for example, when using the climbing shoe 1 for a rail-guided climbing system on a ceiling, e.g., for the construction of a tunnel. The rail guide elements 3a, 3b and the locking element 4 do not have to be pivotably arranged on the shoe base body 2, since an extendable arrangement of these elements or parts of these elements on the shoe base body 2 is also possible.The sliding element 6 is coupled to the shoe base body 2, the rail guide elements 3a and / or 3b, and the locking element 4 such that when the sliding element 6 is displaced in the decoupling direction in the Z direction relative to the shoe base body 2, the rail guide elements 3a, 3b and the locking element 4 are each moved to their initial state, i.e., the "open" position. The climbing shoe can be decoupled from the console element 8a, 8b and the climbing rail 9 at the handle 7 in the Z direction and removed upwards from its position between the console element 8a, 8b and the climbing rail 9. The upward decoupling and removal of the climbing shoe 1 can be performed in a continuous movement in the Z direction, particularly with one hand, which can be performed easily and ergonomically for the user on the construction site.On the other hand, the climbing shoe 1, held by the handle 7, allows it to be inserted between the console element 8a, 8b and the climbing rail 9 in the negative Z direction and, by pressing down the handle 7 and thus the sliding element 6 in the negative Z direction relative to the shoe base body 2, to be coupled / attached to both the console element 8a, 8b and the climbing rail 9 in a further continuous movement.
[0056] In Fig. 2c The climbing shoe 1 is shown in a spatial external view without the console element 8a, 8b and the climbing rail 9, wherein the rail guide elements 3a, 3b are in a position between their initial state and the guide state, the locking element 4 is in the locking state, and a latching / snap element 10 in the form of a catch is in the holding state, i.e., in the "closed" position. Although not required for the climbing shoe 1 of the invention, in the second embodiment of the climbing shoe 1 according to Figur 1b the locking / snap element is pivotally connected to the shoe base body 2 in order to cooperate with a holding element of the climbing rail 9 and / or a climbing lifting rail (not shown), which is displaceable relative to the climbing rail 9 and guided by the climbing rail 9, for holding the locking / snap element 10 in such a way that in the pivoted holding state, i.e. in the "closed" position, the climbing rail 9 and / or the climbing lifting rail can be hooked into the climbing shoe 1 in the direction opposite to the climbing direction in the Z direction, i.e. in the negative Z direction. The sliding element 6 is thus designed in such a way that it is mechanically coupled not only to the shoe base body 2, the rail guide elements 3a, 3b and the locking element 4, but also to the latching / snap element 10 in the form of a pawl, and, if not only the rail guide elements 3a, 3b are in the guided state and the locking element 4 is in the locked state,but additionally the locking / snap element 10 are each in the pivoted holding position. The displacement of the sliding element 6 relative to the shoe base body 2 in the decoupling direction in the Z direction, generated by the actuation of the handle 7, results in not only the rail guide elements 3a, 3b and the locking element 4, but also the locking / snap element 10 being moved to the non-pivoted initial state, i.e., the "open" position, in order to not only decouple / release the climbing shoe 1 from the console element 8a, 8b and release it from the guide of the climbing rail 9, but also to decouple it from the climbing rail 9 and / or a climbing lifting rail. The displacement between the sliding element 6 and the shoe base body 2 is not complete.to decouple the climbing shoe 1 from the climbing rail 9. Instead, the handle 7 is pulled approximately one-third of the possible full displacement, and the first and second rail guide elements, also called claws, are slightly open compared to their "closed" position. In , Figur 2c The locking / snap element 10 is shown in its holding position, i.e., closed. The sliding element 6 is partially displaced relative to the shoe base body 2, in which the rail guide elements 3a, 3b are located between their initial position and the guide position, i.e., partially pivoted, and the locking element 4, like the locking / snap element 10, is still in the "closed" position.
[0057] The climbing shoe 1 has a longitudinal axis L in the Z-direction, whereby the climbing shoe 1 is constructed and designed to be axially symmetrical in the X-direction or negative X-direction with respect to the longitudinal axis L. The sliding element 6 has bulges 6a, 6b in the X-direction or negative X-direction, which ensure that, when the handle 7 is not actuated and the climbing shoe 1 is therefore in the "closed" position, the rail guide elements 3a, 3b cannot be brought into the initial state, i.e., the "open" position. In addition, sliding rotation arms 3a2, 3b2 (not shown, see Fig. 2j ), via which the sliding element 6 with handle 7 is rotatably coupled to the rail guide elements 3a, 3b, ensure that the rail guide elements 3a, 3b cannot be moved into the "open" position. The bulges 6a, 6b therefore serve as guide locks for the rail guide elements 3a, 3b.Between slotted hole elements of the sliding element 6 with slots in a Y / Z plane, the climbing shoe 1 has a finger sliding element 11 with a finger grip 12, which is designed such that it is coupled to the shoe base body 2, the sliding element 6, the rail guide elements 3a, 3b and the locking / snap element 10, and, when the handle 7 is not actuated, a finger displacement of the finger sliding element 11 relative to the shoe base body 2 and the sliding element 6 in an unlocking direction in essentially the Z direction, generated by an actuation of the finger grip 12, results in the rail guide elements 3a, 3b being locked in the initial state, i.e. in the "closed" position, and the locking / snap element 10 being moved into the non-pivoted initial state, i.e. "open" position, in order to only release the climbing rail 9 or climbing lifting rail from the Climbing shoe 1.Since the locking / snap element 10 is in the holding state, the finger sliding element 11 is not actuated.
[0058] In Fig. 2d is an enlarged view of a part of Fig. 2c shown. On the shoe base body 2, elongated hole elements 2a are provided in the Y direction with elongated holes 2b, symmetrically offset to the longitudinal axis L in the X direction or negative X direction, with a central axis element 2c in the form of a bolt being displaceable in the Z direction by the elongated hole elements 2a and guided in the X direction. The sliding element 6 has sliding hole elements 6c with sliding holes 6d, symmetrically offset to the longitudinal axis L in the X direction and in the negative X direction, with the central axis element 2c being guided by the sliding hole elements 6c. The sliding element 6 is displaced in the Z-direction relative to the shoe base body 2 in such a way that a path in each of the sliding slots 6d is traversed in a substantially negative Z-direction as a partial displacement of the sliding element 6 relative to the shoe base body 2 in order to partially move the rail guide elements 3a, 3b into the initial state, i.e. the "open" position.Compared to a state of the climbing shoe 1 in which the handle 7 is not actuated, the state of the climbing shoe 1 is as shown in . Fig. 2d that is, that the sliding element 6 is displaced in the Z direction by the path of the sliding slots 6d, and due to the coupling of the sliding element 6 with the rail guide elements 3a, 3b, due to this partial displacement, the rail guide elements 3a, 3b are partially displaced from their holding state into the initial state.
[0059] In Fig. 2e is a first cross-sectional view of the Fig. 2c The cross-section of the climbing shoe 1 shown is shown. The cross-section does not run through the longitudinal axis L, but is offset from this longitudinal axis L in the negative X direction. The sliding element 6 with the handle 7 is connected via the sliding slotted hole elements 6c and the central axis element 2c to locking arms 6e, 6f, which are coupled at their upper end in the Z direction to the central axis element 2c via slots and at their lower end in the negative Z direction to a sliding axis element 4b, which is coupled to the locking element 4 in such a way that when the handle 7 is actuated in the decoupling direction in the Z direction, the locking arms 6e, 6f are also displaced in the decoupling direction and cause the locking element 4 to be moved to its initial state, i.e., the "open" position. The locking / snap element 10 is pivotally coupled to the shoe base body 2 about a locking / snap axis element 10a, which is oriented in the X direction.The finger sliding element 11 with finger grip 12 is coupled to the locking / snap element 10, wherein the finger sliding element 11 is coupled to the sliding element 6 via the central axis element 2c and the sliding slot elements 6c. This is more clearly shown in a second cross-sectional view of the device shown in FIG. Figur 2c shown climbing shoe 1, the cross section of this figure being compared to the cross section in Fig. 2e in the direction of the longitudinal axis L, i.e. in the X-direction. In addition to the rail guide element 3a, the sliding element 6 with handle 7 and the shoe base body 2, the finger sliding element 11 with finger grip 12 can be seen, which has an elongated hole in its upper area in the Z-direction in order to be guided by the central axis element 2c, and in its lower area in the negative Z-direction comprises two axis arms 11a, 11b, at the lower end of which a finger axis element 10b is present in the locking / snap element 10, which connects the axis arms 10a, 10b of the finger sliding element 11 to one another. The locking / snap element 10 further comprises a spring element arm 10c, from which a spring element 10d, which in the present embodiment of the climbing shoe 1 is designed as a compression spring, wherein at a lower end of the spring element in the negative Z direction a support is provided by the locking element 4 for the spring element.Instead of the locking arms 6e, 6f, pipe-screw contours can also be used, as described on pages 8 to 10 of the description. A combination of the pipe-screw contours instead of the locking arms 6e, 6f with the others in connection with . Fig. 2e described elements is possible.
[0060] In Fig. 2g is the one in Figur 1b The climbing shoe 1 shown is shown in a spatial external view in the "open" position, with the rail guide elements 3a, 3b, the locking element 4, and the latching / snap element 10 in their initial state, i.e., in the "open" position. The sliding element 6 is displaced in the Z direction not only by the distance in the sliding slots 6d, but also by a distance that is passable in the slots 2b of the slotted elements 2a of the shoe base body 2. Further displacement of the sliding element 6 relative to the shoe base body 2 in the Z direction is therefore not possible.
[0061] In the spatial cross-sectional view of the climbing shoe 1 in Fig. 2h The central axis element 2c is guided at the upper end of the axis arms 11a, 11b and at the lower end of the sliding slotted holes 6d in the sliding slotted hole elements 6c. Additionally, the finger sliding element 11 is carried by the central axis element 2c in the decoupling direction in the Z direction from the sliding element 6, so that the locking / snap element 10 is moved to its initial state, i.e., the "open" position, and the spring element 10d is compressed by the spring element arm 10c to exert pressure on the locking element 4 such that the locking element 4 can be moved into the locked state.By displacing the sliding element 6 in the decoupling direction in the Z direction, the locking / snap element 10 is rotated clockwise around the locking / snap axis element 10a, and the spring element arm 10c is displaced in the negative Z direction, so that the spring element 10d can exert pressure on the locking element via the support surface of the locking element 4 to reach the "closed" position. However, this is prevented by the displacement of the sliding element 6 relative to the shoe base body 2, which displaces the locking arms 6e, 6f in the Z direction from the central axis element 2c, so that the locking element 4 is pivoted into its initial "open" position by the sliding axis element 4b.
[0062] Fig. 2i shows a cross-section of the climbing shoe 1 in the state in which the sliding element 6 with handle 7 is displaced relative to the shoe base body 2 in the Z direction by a displacement that results in the rail guide elements 3a, 3b, the locking element 4, and the latching / snap element 10 each being moved to their initial state, i.e., the "open" position. Further displacement of the sliding element 6 in the Z direction, for example, by pulling the handle 7 in the Z direction, does not result in any further displacement of the sliding element 6 relative to the shoe base body 2. The sliding element 6 is coupled to the finger sliding element 11 via the central axis element 2c in such a way that the locking element 4 is pivoted about a locking axis element 4a by means of the axis arms 6e, 6f.The locking / snap element 10 is rotated clockwise around the locking / snap axis element 10a into the "open" position, whereby the spring element 10d, which is guided in the spring element 10c, can exert pressure on the support surface of the locking element 4, which remains in its initial state, i.e. "open" position, due to the guidance via the axis arms 6e, 6f.
[0063] In Fig. 2j is a rear view of the Figur 1b The climbing shoe shown is shown in the "open" position. The rail guide elements 3a, 3b are rotatably guided by rail guide axis elements 3a1, 3b1 and coupled via these to the shoe base body 2. The sliding element 6 with handle 7 is rotatably coupled to the rail guide elements 3a, 3b via the sliding rotary arms 3a2, 3b2. To pivot the rail guide elements 3a, 3b in the Y direction when the sliding element 6 is displaced relative to the shoe base body 2 in the decoupling direction in the Z direction, the sliding rotary arm 3a2 is coupled at its lower end to the rail guide element 3a via a lower sliding rotary arm axis element 3a3 and at its upper end to the sliding element 6 via an upper sliding rotary arm axis element 6h.Due to the axisymmetric design of the climbing shoe 1 with respect to the longitudinal axis L, the sliding rotary arm 3b1 is coupled at its lower end in the negative Z direction via the sliding rotary arm axis element 3b3 to the rail guide element 3b and at its upper end in the Z direction via the upper sliding rotary arm axis element 6g to the sliding element 6. The coupling points for the upper sliding rotary arm axis elements 6h, 6g are arranged in a lower section of the sliding element 6 in the negative Z direction below the bulges 6a, 6b. The displacement element 6 is coupled to the shoe base body 2 via the rail guide elements 3a, 3b by means of the displacement rotary arms 3a2, 3b2 in such a way that after actuation of the handle 7 in the Z direction, the displacement rotary arms 3a2, 3b2 are oriented substantially perpendicularly in the Z direction in such a way that further displacement of the displacement element 6 relative to the shoe base body 2 is not possible.A displacement VO of the sliding element 6 relative to the shoe base body 2 results in the rail guide elements 3a, 3b, the locking element 4, and the latching / snap-in element 10 each being in their initial state, i.e., in the "open" position. In this state, an upper edge of the handle 7 is spaced apart by the distance AO from a lower edge of a lower support of the shoe base body 2 for receiving the rail guide elements 3a, 3b.
[0064] In Fig. 2k The climbing shoe 1 is made of Figur 1b Shown in a rear view in the "closed" position. The bulge 6a locks the rail guide element 3a against pivoting toward the "open" position, and the bulge 6b locks the rail guide element 3b against pivoting toward the "open" position. Measured from an upper edge of a support of the rail guide elements 3a, 3b for receiving the rail guide axis elements 3a1, 3b1 to an upper edge of the bulges 6a, 6b, the displacement of the sliding element 6 relative to the shoe base body 2 is zero (see displacement in the "closed" position VG). The sliding rotation arms 3a2, 3b2 are aligned horizontally in the X direction and, via stops on the rail guide elements 3a, 3b, ensure that the sliding element 6 cannot be displaced further in the negative Z direction relative to the shoe base body 2.A distance from a lower edge of a support of the shoe base body 2 for receiving the rail guide axis elements 3a1, 3b2 to an upper edge of the handle 7 AG is smaller than the distance AO by the displacement VO (see . Figur 2j ). Due to the inserted state of the sliding element 6 relative to the shoe base body 2, Fig. 2k unlike in Fig. 2j the finger grip 12 of the finger sliding element 11 is visible.
[0065] In Fig. 3a is in spatial external view of the Figur 1b The climbing shoe 1 shown is shown in the "closed" position with the finger grip 12 actuated in an unlocking direction, essentially in the Z direction. The rail guide elements 3a, 3b are in the guided state, and the locking / snap element 10 in the form of a pawl is in its initial state. The sliding element 6 cannot be moved further in the negative Z direction relative to the shoe base body 2. Due to the actuation of the finger grip 12, the finger sliding element 11 is coupled to the locking / snap element 10 in such a way that the locking / snap element is moved to its initial state, i.e., the "open" position.
[0066] In Fig. 3b The climbing shoe 1 is shown in the state with the handle 7 not actuated, i.e., in the "closed" position, in which the rail guide elements 3a, 3b are in the guided state and the locking / snap element 10 is in the holding state. Since the finger grip 12 is not actuated, both the rail guide elements 3a, 3b, the locking element 4, and the locking / snap element 10 are in the "closed" position.
[0067] In contrast to the "closed" position of the climbing shoe 1, the climbing shoe 1, which is in Fig. 3c As shown, in the "open" position, the sliding element 6 with the handle 7 is displaced in the Z direction relative to the shoe base body 6 such that further displacement in the Z direction is no longer possible. Therefore, the rail guide elements 3a, 3b are spread apart and are in their initial state, the locking element 4 is in the "open" position in its initial state, and the latching / snap-in element 10 is also in its initial state, since the finger grip 12, actuated in the unlocking direction essentially in the Z direction, is carried along by the sliding element 6 via the finger sliding element 11 and displaced in the Z direction.
[0068] In Fig. 4a The climbing shoe 1 is in accordance with Figur 1b Shown in a side view in the "closed" position with the finger grip 12 actuated and locked in the unlocking direction. The rail guide elements 3a and 3b (3b is hidden by 3a and therefore not shown) are shifted in the negative Y direction into the holding position to guide the climbing rail 9. In addition, the locking element 4 is transferred into the locking position, in which it forms the opening 5a with the receiving element 5 of the shoe base body 2 for receiving the console support element 8c of the console element 8a, 8b as a subsection thereof. The central axle element 2c guides the sliding element 6 in an upper section of the sliding slots 6b. The axle arm 6f, behind which the finger sliding element 11 with the finger grip 12 is arranged, can be seen through the slot 2b of the shoe base body 2.
[0069] The climbing shoe 1 in the state with the handle 7 not actuated and the finger grip 12 actuated and locked is in Fig. 4b shown in a spatial external view. The finger displacement element 11 is latched to the central axis element 2c in the actuated position such that the latching / snap element 10 is in its initial state, while the rail guide elements 3a, 3b are in the guided state.
[0070] The cross-sectional view of the Fig. 4c shows the finger sliding element 11 in the locked state on the central axis element 2c. The finger sliding element 11 has a locking element 11c in the form of two locking lugs for locking, which are arranged at equal intervals in the X direction with respect to the longitudinal axis L or in the negative X direction from the longitudinal axis L. An elongated hole in the finger sliding element 11, through which the finger sliding element 11 is guided by the central axis element 2c, has a bulge 11d in the Y direction due to the locking element 11c, into which the central axis element 2c can be received for locking the finger sliding element 11.In the locked state, due to the actuation of the finger grip 12, the finger displacement element 11 is displaced in the Z direction such that the locking / snap element 10 is rotated counterclockwise, so that the spring element 10d exerts pressure on the support surface in an upper section of the locking element 4 in order to keep the locking element 4 in the locked state, i.e. closed.
[0071] In Fig. 5a is the one in Figur 1b The climbing shoe shown in the state with the handle 7 not actuated, i.e., in the "closed" position, with the finger grip 12 not actuated in the unlocking direction. The locking / snap element 10 is therefore in the holding state, with the spring element 10d still exerting pressure on the locking element via the upper contact surface of the locking element 4. The state of the climbing shoe 1 in the "closed" position with the finger grip 12 not actuated is shown in a spatial external view in Fig. 5b opposite Fig. 5a Shown enlarged. The finger sliding element 11 is not engaged with the central axis element 2c. The handle 7 is not actuated in the decoupling direction in the Z direction, and the locking / snap element 10 engages with a retaining element of the climbing lifting rail 9b, which is guided by the climbing rail 9 and is movable relative to it. The locking / snap element 10 can also engage with a bushing of the climbing rail 9.
[0072] In Fig. 6a The climbing shoe 1 is shown in a third embodiment with three locking / snap-on elements 10, 10', 10" in the "closed" position coupled to the climbing rail 9 with first and second climbing rail outer elements 9a1, 9a2. When coupled to the console element 8a, 8b, the console element would connect to the climbing shoe 1 in the Y-direction such that the receiving elements 5 enclose the console support element 8c, which would be oriented in the X-direction. The climbing rail outer elements 9a1, 9a2 each have a C-shape, wherein the climbing rail outer elements are oriented away from each other in the X-direction and parallel to each other in the negative X-direction. In each case, an upper leg of the first climbing rail outer element 9a1 and the second climbing rail outer element 9a2 are encompassed by the rail guide elements 3a, 3b, which are each in the Guide state, i.e. in "closed" position.The climbing rail outer elements 9a1, 9a2 are spaced apart from one another via struts oriented in the X direction, which are distributed in the negative Z direction along the climbing rail 9, and are connected to one another, for example via screw connections, as in . Figur 6a shown. Between the climbing rail outer elements, a climbing lifting rail guide element 9a4 is attached to each of the climbing rail outer elements, for example by means of a further screw connection, in order to guide the climbing lifting rail 9b, which is guided by the climbing lifting rail guide elements 9a4 and which is arranged displaceably relative to the climbing rail 9. The first locking / snap element 10, which is arranged centrally on the longitudinal axis L, is designed to engage in at least one holding element of the climbing lifting rail 9b and in this way to couple the climbing rail 9 to the climbing shoe 1. In the X direction and in the negative X direction next to the holding elements of the climbing lifting rail, support elements are attached to each of the climbing rail outer elements 9a1, 9a2 in the Y direction, for example by means of a further screw connection 9a3. In the top view of the Figur 6a the locking / snap-in elements 10', 10" are each arranged in the Z direction above the holding elements of the climbing lifting rail 9b and the support elements of the climbing rail outer elements 9a1, 9a2, while the locking / snap-in element 10 is arranged below the holding element of the climbing lifting rail 9b.
[0073] In Fig. 6b is the climbing shoe 1, as it is in Figur 6a shown in a spatial external view. The rail guide elements 3a, 3b are in the guided state, which means that the sliding element 6 with handle 7 is arranged relative to the shoe base body 2 in such a way that further displacement of the sliding element 6 relative to the shoe base body 2 in the negative Z direction is not possible. The central locking / snap element 10 arranged on the longitudinal axis L is located between the further locking / snap elements 10', 10" arranged adjacent to this locking / snap element in the X direction and in the negative X direction. Since the locking / snap elements 10, 10', 10" are each in the holding state, i.e., in the "closed" position, the finger displacement element 11 provided with the finger grip 12, which is guided by the central axis element 2c, is not actuated such that the finger displacement element 11 cannot be displaced relative to the shoe base body 2 in the negative Z direction.
[0074] In Fig. 6c is a cross-sectional view of the Figur 6a The locking / snap-in element 10 in the form of a latch engages a holding element of the climbing rail 9b, wherein the holding element of the climbing rail 9b partially covers the further locking / snap-in element 10", which is in the held state, i.e., in the "closed" position, such that the support element 9a5 can rest on the locking / snap-in element 10" in its lower section in the negative Z direction. The climbing rail guide element 9a4 is fastened to the second climbing rail outer element 9a2 by means of a bolt, for example, via a screw or welded connection. Since the locking / snap elements 10, 10', 10" are each in the holding state, the finger displacement element 11 is not displaced in the negative Z direction relative to the shoe base body 2, i.e., is not actuated, which also applies to the handle 7, whose displacement element 6, like the finger displacement element 11, is guided by the central axis element 2c.Because the handle 7 is not actuated, the climbing shoe 1 is in the "closed" position, such that the locking element 4, which interacts with the receiving element 5, is in the locked state, i.e., also in the "closed" position. It is also possible for the central locking / snap element 10 to interact with retaining elements of the climbing lifting rail 9b, and for the additional locking / snap elements 10', 10" to interact with retaining elements of another climbing lifting rail, which, like the climbing lifting rail 9b, is arranged within the climbing rail outer elements 9a1, 9a2, to secure the climbing rail 9 to the climbing shoe 1. In this case, the climbing rail outer elements 9a1, 9a2 would not have support elements 9a5 (not shown).
[0075] The climbing shoe 1 coupled to the climbing rail 9 and / or climbing lifting rail 9b as in Figur 6a is shown in Fig. 6d shown in a spatial external view. The central locking / snap-in element 10 is in the holding position, but does not rest on a holding element of the climbing rail 9b. The other locking / snap-in elements 10', 10", however, each rest on a support element 9a5, which is attached to each of the climbing rail outer elements 9a1, 9a2.
[0076] In Fig. 6e The climbing shoe 1 is shown spaced apart by a distance of, for example, 10 cm from the climbing rail 9 with the climbing lifting rail 9b and the climbing rail outer elements 9a1, 9a2 to better identify the arrangement of the locking / snap elements 10, 10', 10" relative to the climbing lifting rail 9b and the support elements 9a5. Both the rail guide elements 3a, 3b and the locking / snap elements 10, 10', 10" and the locking element 4 are in the "closed" position, so that the sliding element 6 with the handle 7 cannot be moved any further in the negative Z direction relative to the shoe base body 2.
[0077] In Fig. 6f In a cross-sectional view, the climbing lifting rail 9b is shown, guided by the climbing lifting rail guide elements 9a4, which is suspended with one of its holding elements in the locking / snap element 10 and thus transfers a load of the climbing system via the climbing rail 9 into the climbing shoe 1. Each of the locking / snap elements 10', 10" is not engaged with a lower section of the support elements 9a5, so that the load of the climbing system is transferred via the climbing lifting rail 9b into the climbing shoe 1 and via the climbing shoe 1 into the completed concreting section of the structure to be erected. In contrast to the state of the climbing shoe 1 with respect to the climbing rail 9 and the climbing lifting rail 9b according to Fig. 6f is in Figur 6g The load of the climbing system is transferred into the climbing shoe 1 via the locking / snap elements 10', 10", whereby the central locking / snap element 10 is not engaged in a holding element of the climbing lifting rail 9b. The support elements 9a5 are arranged opposite the climbing lifting rail guide elements 9a4 in the Y direction, i.e. in the direction from the climbing lifting rail 9 to the climbing shoe 1.
[0078] In a further embodiment of the climbing shoe 1, as shown in Fig. 7a shown, the central locking / snap element 10 and the further locking / snap elements 10', 10" are arranged relative to the climbing rail 9 with the climbing rail outer elements 9a1, 9a2 and the climbing lifting rail 9b in such a way that the central locking / snap element 10 can engage in a holding element of the climbing lifting rail 9b and the further locking / snap elements 10', 10" can engage in recesses as holding elements of the climbing rail outer elements 9a1, 9a2. Alternatively, bulges can also be provided as holding elements on the climbing rail outer elements 9a1, 9a2 and / or the climbing lifting rail 9b, which interact with the locking / snap elements 10, 10', 10". For example, blocks can be welded onto the climbing rail outer elements 9a1, 9a2, which can engage with the latches 10' and / or 10".The arrangement of the locking / snap elements 10', 10" which are not arranged centrally to the longitudinal axis L relative to the legs of the climbing rail outer elements 9a1, 9a2 facing the climbing shoe 1 is shown in . Figur 7a This is illustrated by the fact that the climbing shoe 1 is located at a distance of, for example, 10 cm from the climbing rail 9.
[0079] The state of the climbing shoe 1 in "closed" position coupled to the climbing rail 9 with the climbing lifting rail 9b is in Fig. 7b shown. The locking / snap-in elements 10', 10" which are not arranged centrally to the longitudinal axis L each engage in recesses of the climbing rail outer elements 9a1, 9a2 such that, when the climbing rail 9 is coupled to the climbing shoe 1, the sections of the locking / snap-in elements 10', 10" which pass through the recesses are located on mutually opposite outer sides of the climbing rail outer elements 9a1, 9a2. The area between the climbing rail outer elements 9a1, 9a2 is therefore reserved for the climbing lifting rail guide elements 9a4, the climbing lifting rail 9b and the locking / snap-in element 10 arranged centrally on the longitudinal axis L.
[0080] In Fig. 7c the climbing shoe 1 is engaged with the non-centrally arranged locking / snap elements 10', 10" in the holding elements 9a6 in the form of the recesses such that the climbing rail 9 is held with the climbing lifting rail 9b by the locking / snap elements 10', 10" arranged adjacent to the centrally arranged locking / snap element 10. The central locking / snap element 10 is not engaged with a holding element of the climbing lifting rail 9b, which is located below the central locking / snap element 10 in the negative Z direction, as is the case when the climbing lifting rail 9b is retracted in the negative Z direction relative to the climbing rail outer elements 9a1, 9a2.
[0081] In contrast to the arrangement of the climbing rail 9 relative to the climbing shoe 1 according to Figur 7c is in Fig. 7d an external view of the climbing shoe 1 coupled to the climbing rail 9 is shown, in which the non-centrally arranged locking / snap elements 10', 10" do not engage in the recesses of the holding elements 9a6, but the climbing rail 9 is held by the climbing shoe 1 via the climbing lifting rail 9b and the locking / snap element 10 engaging with a holding element of the climbing lifting rail 9b. The climbing lifting rail 9b thus transfers the load of the climbing system via the central locking / snap element 10 into the climbing shoe 1, wherein the climbing rail outer elements 9a1, 9a2 are guided by the rail guide elements 3a, 3b and can be moved relative to the climbing lifting rail 9b.
[0082] In Fig. 7e An external view of the climbing shoe 1 coupled to the climbing rail 9 is shown, wherein the non-centrally arranged locking / snap-action elements 10', 10" each engage in recesses of the climbing rail outer elements 9a1, 9a2 serving as holding elements 9a6 in order to couple the climbing rail 9 to the climbing shoe 1. The central locking / snap-action element 10 in the form of a latch, which is concealed by the climbing lifting rail 9b, does not engage with a holding element of the climbing lifting rail 9b, so that the climbing lifting rail 9b can be moved in the Z direction relative to the central locking / snap-action element 10 which is not in the holding position. Moving the climbing lifting rail 9b relative to the central locking / snap-action element 10 is also possible in the negative Z direction, as long as the locking / snap-action element 10 in the "closed" position does not engage with a holding element of the climbing lifting rail 9b intervenes.A travel path of the climbing lifting rail 9b relative to the climbing shoe 1 is therefore dependent on a distance between adjacent holding elements of the climbing lifting rail 9b for engagement in the central locking / snap element 10. In the embodiment shown, the distance between the holding elements of the climbing lifting rail 9b in the Z direction for the latch 10 of the climbing shoe 1 is essentially the same as the distance between the recesses 9a6 of the climbing rail 9 for the other latches 10', 10". The travel path, also called stroke, is greater than the distances between the recesses in the climbing rail 9 or the distances between the holding elements in the climbing lifting rail 9b. The overlap area is required for climbing.
[0083] In Fig. 7f The climbing shoe 1 is shown in the "closed" position at a distance of, for example, 10 cm from the climbing rail 9 with the climbing lifting rail 9b in a spatial external view in the fourth embodiment of the climbing shoe 1. Recesses in the climbing shoe 1 in the coupled state of the climbing shoe 1 on the climbing rail 9, on the legs of the climbing rail outer elements 9a1, 9a2 facing the climbing shoe 1, serve as holding elements 9a6, by means of which the climbing rail 9 can engage the non-centrally arranged locking / snap elements 10', 10". The locking / snap element 10, arranged centrally to the longitudinal axis L, is designed to engage holding elements of the climbing lifting rail 9b, which is arranged centrally between the climbing rail outer elements 9a1, 9a2.The climbing shoe 1 is in the state in which a displacement of the displacement element 6 relative to the shoe base body 2 in the negative Z-direction is not possible, i.e. the handle 7 is not actuated in the decoupling direction in the Z-direction, so that the rail guide elements 3a, 3b are in the guide state, the locking element 4 is in the locking state and each of the locking / snap elements 10, 10', 10" is in the holding state.
[0084] By actuating the handle 7 in the decoupling direction, for example in the Z-direction, the climbing shoe 1 can be put into the state in which the rail guide elements 3a, 3b, the locking element 4 and the latching / snap elements 10, 10', 10" are each in their initial state, i.e. in the "open" position. This is possible because the sliding element 6 is arranged displaceably relative to the shoe base body 2 and is mechanically coupled to the shoe base body 2, the rail guide elements 3a, 3b, the locking element 4 and the latching / snap elements 10, 10', 10" and, when the rail guide elements 3a, 3b are in the guide state, the locking element 4 is in the locked state and the latching / snap elements 10, 10', 10" are in the pivoted holding state, which are Displacement VO generated by actuating handle 7 (see Figur 2j ) of the sliding element 6 relative to the shoe base body 2 results in the rail guide elements 3a, 3b, the locking element 4 and the locking / snap elements 10, 10', 10" each being set to the non-pivoted initial state, i.e. in the "open" position, in order to separate the climbing shoe 1 from the console element 8a, 8b (see Figuren 2a, 2b ) and to decouple it from the climbing rail 9 with or without the climbing lifting rail 9b and to release it from the guidance of the climbing rail 9 and / or the climbing lifting rail 9b.
[0085] In Fig. 8a a spatial external view of the climbing shoe according to the invention in the open position is shown in a fifth embodiment, wherein the climbing shoe has four latches, wherein the first 10 1< and second latches 10 2< can engage in holding elements of the climbing lifting rail and the third 10' and fourth latches 10" can engage in recesses of the climbing rail. The sliding element 6 is mechanically coupled to the first 3a and second rail guide elements 3b by means of tube-screw contours, also called links. In this embodiment, the handle 7 is connected via the sliding element 6 to rails 13a, 13b, which, as shown, can be arranged substantially parallel to one another and substantially symmetrically to the longitudinal axis L of the climbing shoe.When the climbing shoe is mounted, the rails 13a, 13b are only displaceable / movable relative to the shoe base body 2 in and against the climbing direction, for example, vertically, along the longitudinal axis L of the climbing shoe. The rails 13a, 13b can be designed as part of the sliding element 6. When the handle 7 is moved in the climbing direction, the rail 13a, 13b moves in the climbing direction, for example, upwards, and when the handle 7 is moved against the climbing direction, the rail 13a, 13b moves against the climbing direction, for example, downwards.
[0086] Parallel to the rail 13a, 13b, a further rail section 14a, 14b, the length of which is shorter than the length of the rail 13a, 13b in its longitudinal direction, is connected to the rail 13a, 13b at one end of the rail 13a, 13b in the climbing direction, for example, as shown, to an upper end of the rail 13a, 13b and in this way to the handle 7 via the sliding element 6 in such a way that a free end of the rail section 14a, 14b in the closed climbing shoe according to Fig. 8b can engage both in a first recess 15a, 15b of the shoe base body 2 and in a first recess 15 1< of the first 3a and second rail guide element 3b to secure the position of the rail guide element 3a, 3b. The other, for example lower end of the rail 13a, 13b can also serve to secure the position of the rail guide element 3a, 3b, as shown, which, like the free end of the rail section 14a, 14b, can engage in a second recess 16a, 16b of the shoe base body 2 and in a second recess 16 2< (in Fig. 8a only visible for the rail guide element 3b, since for the other rail guide element 3a it is shown covered) of the first 3a and second rail guide element 3b can engage.
[0087] Perpendicular to a longitudinal axis of the rail is a rod-shaped element 19a (in Fig. 8a for the rail 13b (shown covered), for example a bolt, is fixed to the rail 13a, 13b, which engages with the rail 13a, 13b when the handle 7 is moved in or against the climbing direction. The rod-shaped element 19a can be guided by a rod-shaped guide element, for example another rail or a cylinder or axle element arranged parallel to the rail (not shown). The first 3a and second rail guide element 3b have a third curved recess 18a, 18b with a width that allows a free end and / or a section of the rod-shaped element 19a to engage in the recess 18a, 18b or to guide the recess 18a, 18b, i.e. to run in the recess 18a, 18b.The curved recess has a screw-shaped or thread-shaped course in order to rotate the rail guide element 3a, 3b when the rod-shaped element 19a running in the recess 18a, 18b is moved in or against the climbing direction relative to the shoe base body 2 by means of an actuation of the handle 7. If the climbing shoe is closed as in . Fig. 8b shown the handle 7 for unlocking the climbing shoe in the climbing direction, i.e. as in Fig. 8a opposite Fig. 8b shown upwards, actuated / pulled, the rail 13a, 13b with the rod-shaped element 19a moves in the climbing direction, i.e. upwards, with the shoe base body 2 stationary. Since the rail 13a, 13b and the rod-shaped element 19a can only be moved in the climbing direction, i.e. upwards, the rod-shaped element 19a guides the rail guide element 13a, 13b during the displacement of the rod-shaped element 19a in such a way that, due to the curved recess 18a, the rail guide element 13a, 13b rotates to such an extent that a fictitious straight line of the recess 19a is formed at the location of the rod-shaped element 13a, 13b via the displacement of the rod-shaped element 19a in the climbing direction, which the rod-shaped element 19a can travel.
[0088] The first 3a and second rail guide elements 3b each comprise an at least partially cylindrical hollow body 17a, 17b, into which the third curved recess 18a is introduced, for example, over a length of the displacement path of the handle 7 relative to the shoe base body 2. The rail 13a, 13b can be guided in the at least partially cylindrical hollow body 17a, 17b such that the rod-shaped element 19a can engage in the recess 18a over its displacement path in order to guide the first 3a and second rail guide elements 3b such that they are rotated relative to the shoe base body 2 during the displacement of the handle 7.If the first 3a and second rail guide elements 3b are to be rotated relative to the shoe base body 2 to close the climbing shoe, the handle 7 is displaced relative to the shoe base body 2 in the same manner as when opening the climbing shoe, so that, since the rails 13a, 13b and the rod-shaped element 19a can only be displaced relative to the climbing direction, i.e. downwards, the rod-shaped element 19a guides the respective rail guide element 3a, 3b during the displacement of the rod-shaped element 19a in such a way that, due to the curved recess 18a, the respective rail guide element 3a, 3b rotates along with it in order to place the climbing shoe in the "closed" position.
[0089] The finger grip 12 is designed to actuate the first 10 1< and second pawls 10 2< of the first locking / snap element and the third 10' and fourth pawls 10" of the second locking / snap element. However, it is also possible to provide a first finger grip element and a second finger grip element instead of the finger grip 12, wherein the first finger grip element is designed such that the first pawl 10 1< and the second pawl 10 2< can be actuated by the first finger grip element and the third pawl 10' and the fourth pawl 10" can be actuated independently of the first and second pawls 10 1<, 10 2< by the second finger grip element. In this way, the climbing shoe can be released / unlocked independently of one another from the climbing rail or from the climbing lifting rail.
[0090] First and second pawls 10 1< , 10 2< of the first locking / snap element are arranged substantially on a first axis substantially perpendicular to the longitudinal axis L of the climbing shoe and spaced from the longitudinal axis L at substantially equal distances from the longitudinal axis L, and third and fourth pawls 10 ', 10 " as further locking / snap elements are arranged substantially on a second axis substantially perpendicular to the longitudinal axis L and spaced from the longitudinal axis L at substantially equal distances from the longitudinal axis L, opposite to the climbing direction. The first and second pawls 10 1< , 10 2< of the first locking / snap element and the third and fourth pawls 10 ', 10 " of the second and third further locking / snap element can be actuated in pairs.In order to keep the design compact perpendicular to the longitudinal axis L, the two pawls 10 1< , 10 2< of the first locking / snap element are offset from the third and fourth pawl pairs 10', 10" of the further locking / snap elements opposite to the climbing direction, i.e. vertically. The first and / or the further locking / snap element(s) can also have more than two pawls.
[0091] First distances from the longitudinal axis L of the first and second pawls 10 1< , 10 2< differ from second distances of the third and fourth pawls 10', 10" from the longitudinal axis, wherein the first distances are selected to be smaller than the second distances. The first and second pawls 10 1< , 10 2< cooperate with the climbing lifting rail and the third and fourth pawls 10', 10" cooperate with the climbing rail. A reverse embodiment, in which the first and second pawls 10 1< , 10 2< cooperate with the climbing rail and the third and fourth pawls 10', 10" cooperate with the climbing lifting rail, is also possible.
[0092] The features of the invention described with reference to the illustrated embodiment, such as the locking / snap elements 10', 10" of the third or fourth embodiment of the climbing shoe 1, which are not located on the longitudinal axis L, can also be present in other embodiments of the invention, such as the first or second embodiment of the climbing shoe 1, unless otherwise stated or prohibited for technical reasons. In addition, the locking / snap elements 10, 10', 10" can be actuated independently of one another by the handle 7 and / or finger grip 12, even if the figures for the third and fourth embodiment only show and describe embodiments in which these elements can be actuated simultaneously by the handle 7 and / or finger grip 12. Bezugszeichenliste
[0093] 1Climbing shoe 2Shoe base body 2aSlot element 2bSlot 2cCentral axis element 3aRail guide element 3a1, 3b1Rail guide axis element 3a2, 3b2Sliding rotary arm 3a3, 3b3Lower sliding rotary arm axis element 3bRail guide element 4Locking element 4aLocking axis element 4bSliding axis element 5Receiving element 5aOpening 6Sliding element 6a, 6bBump 6cSliding slot element 6dSliding slot 6e, 6fLocking arm 6g, 6Upper sliding rotary arm axis element 7Handle 8a, 8bBracket element 8cBracket support element 9Climbing rail 9a1, 9a2Climbing rail outer element 9a3Screw connection 9a4Climbing lifting rail guide element 9a5Support element 9a6Holding element 9bClimbing lifting rail 10, 10 1< , 10 2< , 10', 10"Locking / snap-in element 10aLocking / snap-in axis element 10bFinger axis element 10cSpring element arm 10dSpring element 11Finger sliding element 11a, 11bAxle arm 11cLocking element 11dBump 12Finger grip 13a, 13bRail 14a, 14bRail section 15a,15bRecess in shoe base body for rail section 15 1<Recess in rail guide element for rail section 16a, 16bRecess in shoe base body for rail 16 2<Recess in rail guide element for rail 17a, 17bHollow body rail guide element 18a, 18bCurved recess 19Bar-shaped element AGDistance in "closed" position AODistance in "open" position LLongitudinal axis VGDisplacement in "closed" position VODisplacement in "open" position,
Claims
1. Climbing boot (1) for a rail-guided climbing system, which can be used in particular as a climbing formwork, climbing frame, protective climbing wall and / or climbing working platform, wherein the climbing boot (1) comprises: - a main boot body (2) having first and second rail guide elements (3a, 3b), wherein at least the first rail guide element (3a), in particular the first and second rail guide elements (3a, 3b), is / are arranged on the main boot body (2) so as to be pivotable and / or extendable in such a way that, in the pivoted and / or extended guidance state, a climbing rail (9), which is arranged slidably between the first and second rail guide elements (3a, 3b) is guided by the rail guide elements (3a, 3b) by portions of the climbing rail (9) being surrounded by the rail guide elements (3a, 3b), - a receiving element (5) that is arranged on the main boot body (2) and is designed to interact with a first portion of a bracket element (8a, 8b), arranged in a stationary manner on a concreting segment of a building, in such a way that, when the receiving element (5) is attached to the first portion of the bracket element (8a, 8b), a load of the climbing boot (1) can be introduced into the bracket element (8a, 8b), characterized in that the climbing boot further comprises: - a sliding element (6) that is provided with a handle (7) and is designed in such a way that it is mechanically coupled to the main boot body (2) and the first rail guide element (3a), and, when the first rail guide element (3a) is in the guidance state, sliding (VO) of the sliding element (6) in relation to the main boot body (2) in a decoupling direction (Z), which sliding is caused by an actuation of the handle (7), results in the first rail guide element (3a) being set into the non-pivoted and / or retracted initial state in order to release the climbing boot (1) from being guided by the climbing rail (9).
2. Climbing boot according to claim 1, comprising a locking element (4) which is arranged so as to be pivotable and / or extendable on the main boot body (2) and is designed to interact with the first portion of the bracket element (8a, 8b) and the receiving element (5) or with a second portion of the bracket element (8a, 8b) in such a way that, in the pivoted and / or extended locking state, the climbing boot (1) is releasably locked to the bracket element (8a, 8b), wherein the sliding element (6) provided with the handle (7) is designed in such a way that it is mechanically coupled to the main boot body (2), the first rail guide element (3a) and the locking element (4), and, when the first rail guide element (3a) is in the guidance state and the locking element (4) is in the locking state, sliding (VO) of the sliding element (6) in relation to the main boot body (2) in a decoupling direction (Z), which sliding is caused by an actuation of the handle (7), results in the first rail guide element (3a) and the locking element (4) being set in each case into the non-pivoted and / or retracted initial state in order to release the climbing boot (1) from being guided by the climbing rail (9) and to release it from being locked on the bracket element (8a, 8b).
3. Climbing boot according to claim 1 or claim 2, comprising at least one latching / snap element (10, 101, 102, 10', 10") that is arranged on the main boot body (2) so as to be pivotable and / or extendable and is designed to interact with a holding element (9a6) of the climbing rail (9) and / or a climbing lift rail (9b), which can be displaced relative to the climbing rail (9) and is guided by the climbing rail (9), for holding the at least one latching / snap element (10, 101, 102, 10', 10") in such a way that, in the pivoted and / or extended holding state, the climbing rail (9) and / or climbing lift rail (9b) can be suspended in the climbing boot (1) in the opposite direction to a climbing direction, wherein the sliding element (6) is designed in such a way that it is mechanically coupled to the main boot body (2), either the first rail guide element (3a) or the first rail guide element (3a) and the locking element (4), and additionally to the latching / snap element (10, 101, 102, 10', 10"), and, if either the first rail guide element (3a) is in the guidance state or the first rail guide element (3a) and the locking element (4) are in the locking state, and additionally the latching / snap element (10, 101, 102, 10', 10") is in the pivoted and / or extended holding state, sliding (VO) of the sliding element (6) in relation to the main boot body (2), which sliding is caused by an actuation of the handle (7), results in the first rail guide element (3a) or the first rail guide element (3a) and the locking element (4), and additionally the latching / snap element (10, 101, 102, 10', 10") being set in each case into the non-pivoted and / or retracted initial state in order to release the climbing boot (1) from being guided by the climbing rail (9) or to release it from being guided by the climbing rail (9) and from being locked on the bracket element (8a, 8b), and additionally to free it from being held by the climbing rail (9) and / or climbing lift rail (9b).
4. Climbing boot according to claim 3, in which, when the climbing boot (1) is coupled to the bracket element (8a, 8b) and a longitudinal axis (L) of the climbing boot (1) is oriented in the climbing direction, the latching / snap element (10, 101, 102) comprises either one pawl substantially arranged on the longitudinal axis (L) of the climbing boot (1) or two pawls arranged substantially horizontally spaced apart from the longitudinal axis (L), in particular at substantially equal distances from the longitudinal axis (L), wherein the pawl or the two pawls are designed to interact with one or more holding elements (9a6) of the climbing rail (9) for holding the pawl or the two pawls of the first latching / snap element (10, 101, 102) in such a way that, in the pivoted and / or extended holding state, the climbing rail (9) can be suspended in the climbing boot (1) in the opposite direction to a climbing direction.
5. Climbing boot according to any of the preceding claims, in which the sliding element (6) is designed in such a way that, if the first rail guide element (3a), the first rail guide element (3a) and the locking element (4), the first rail guide element (3a) and the latching / snap element (10, 101, 102, 10', 10"), or the first rail guide element (3a), the locking element (4) and the latching / snap element (10, 101, 102, 10', 10") are in each case in the non-pivoted and / or retracted initial state, sliding (VO) of the sliding element (6) in relation to the main boot body (2) in a coupling direction opposite to the decoupling direction (Z), which sliding is caused by a further actuation of the handle (7), results in the first rail guide element (3a) being set into the guidance state, the first rail guide element (3a) being set into the guidance state and the locking element (4) being set into the locking state, the first rail guide element (3a) being set into the guidance state and the latching / snap element (10, 101, 102, 10', 10") being set into the holding state, or the first rail guide element (3a) being set into the guidance state, the locking element (4) being set into the locking state and the latching / snap element (10, 101, 102, 10', 10") being set into the holding state in order to move the climbing boot (1) into the guide of the climbing rail (9), to move the climbing boot (1) into the guide of the climbing rail (9) and lock it on the bracket element (8a, 8b), to move the climbing boot (1) into the guide of the climbing rail (9) and set it into the holding state of the climbing rail (9) and / or climbing lift rail (9b), or to move the climbing boot (1) into the guide of the climbing rail (9), lock it on the bracket element (8a, 8b) and set it into the holding state of the climbing rail (9) and / or climbing lift rail (9b).
6. Climbing boot according to claim 3 or any of claims 4 or 5, insofar as they refer back to claim 3, comprising at least one further latching / snap element (10', 10") that is arranged on the main boot body (2) so as to be pivotable and / or extendable and interacts with at least one further holding element of the climbing rail (9) and / or the climbing lift rail (9b) for holding the further latching / snap element (10', 10") in such a way that, in the pivoted and / or extended holding state, the climbing rail (9) and / or the climbing lift rail (9b) can be suspended in the climbing boot (1) in the direction opposite the climbing direction, wherein the latching / snap elements (10, 101, 102, 10', 10") can be actuated simultaneously or independently of one another by the handle (7).
7. Climbing boot according to claim 6, in which, when the climbing boot (1) is coupled to the bracket element (8a, 8b) and a / the longitudinal axis of the climbing boot (1) is oriented in the climbing direction, a first latching / snap element (10) of the latching / snap elements is arranged on the longitudinal axis (L) of the climbing boot (1) in the climbing direction and second (10') and third latching / snap elements (10") of the latching / snap elements are arranged so as to be spaced substantially horizontally from the longitudinal axis (L), in particular at equal distances.
8. Climbing boot according to claim 7, in which the first latching / snap element (10) is arranged relative to the main boot body (2) in such a way that it interacts with the further holding element of the climbing lift rail (9b) for latching / snapping the first latching / snap element (10), and the second (10') and third latching / snap elements (10") are arranged relative to the main boot body (2) in such a way that, for latching / snapping the second (10') and third latching / snap elements (10"), they interact either with further holding elements of the climbing lift rail (9b) or with further holding elements of the climbing rail (9), which are in each case different from the further holding element of the climbing lift rail (9b) for latching / snapping the first latching / snap element (10).
9. Climbing boot according to claim 6, in which, when the climbing boot (1) is coupled to the bracket element (8a, 8b) and a longitudinal axis (L) of the climbing boot (1) is aligned in the climbing direction, first and second pawls of the first latching / snap elements (101, 102) are arranged on a first axis substantially perpendicular to the longitudinal axis (L) at a distance from the longitudinal axis (L), in particular at substantially equal distances from the longitudinal axis (L), and second (10') and third further latching / snap elements (10") are arranged at a distance therefrom in or opposite the climbing direction or at the same level in the climbing direction on a second axis substantially perpendicular to the longitudinal axis (L) at a distance from the longitudinal axis (L), in particular at substantially equal distances from the longitudinal axis (L).
10. Climbing boot according to claim 9, in which the first and second pawls of the first latching / snap element (101, 102) are arranged on the first axis substantially perpendicular to the longitudinal axis (L) at a distance from the longitudinal axis (L) at substantially equal first distances from the longitudinal axis (L) and the second (10') and third further latching / snap elements (10") are arranged on the second axis substantially perpendicular to the longitudinal axis (L) at a distance from the longitudinal axis (L) at substantially equal second distances from the longitudinal axis (L), wherein the first and second distances are different from each other, in particular the first distances are chosen to be smaller than the second distances, wherein the first and second pawls of the first latching / snap element(101, 102) are designed to interact with holding elements (9a6) of the climbing lift rail (9b) for holding the first and second pawls of the first latching / snap element (101, 102) in such a way that, in the pivoted and / or extended holding state, the climbing lift rail (9b) can be suspended in the climbing boot (1) in the opposite direction to a climbing direction, and the second (10') and third further latching / snap elements (10") are designed to interact with one or more holding elements of the climbing rail (9) for holding the second (10') and third further latching / snap elements (10") in such a way that, in the pivoted and / or extended holding state, the climbing rail (9) can be suspended in the climbing boot (1) in the opposite direction to a climbing direction, or vice versa.
11. Climbing boot according to any of the preceding claims, in which, when the climbing boot (1) is coupled to the bracket element (8a, 8b) and a / the longitudinal axis of the climbing boot (1) is oriented upward in a / the vertical climbing direction, the handle (7) is arranged in an upper portion of the climbing boot (1) or forms an upper end of the climbing boot (1), and the sliding element (6) is coupled at least to the main boot body (2) in such a way that the actuation of the handle (7) in the decoupling direction (Z) is effected by means of a pulling movement, in particular with one hand, in the climbing direction away from the main boot body (2).
12. Climbing boot according to claim 3 or any of claims 4 or 5, insofar as they refer back to claim 3, and 6 to 11, comprising a finger sliding element (11) that is provided with a finger grip (12) and is arranged slidably with respect to the main boot body (2) and the sliding element (6), which finger sliding element is designed in such a way that it is coupled to the main boot body (2), the sliding element (6), the first rail guide element (3a) and the latching / snap element (10, 101, 102, 10', 10"), and, if either the first rail guide element (3a) is in the guidance state or the first rail guide element (3a) is in the guidance state and the locking element (4) is in the locking state, and the latching / snap element (10, 101, 102, 10', 10") is in the holding state, i.e., the handle (7) is not actuated, finger sliding of the finger sliding element (11) with respect to the main boot body (2) and the sliding element (6) in an unlocking direction, which finger sliding is caused by an actuation of the finger grip (12), results in the first rail guide element (3a) being locked in the pivoted and / or extended guidance state and the latching / snap element (10, 101, 102, 10', 10") being set into the non-pivoted and / or retracted initial state in order to free the climbing boot (1) from the holding state of the climbing rail (9) or climbing lift rail (9b) and to guide the climbing rail (9) or climbing lift rail (9b) from the climbing boot (1), wherein, if a plurality of latching / snap elements (10, 101, 102, 10', 10") are present, the finger grip (12) is designed in such a way that the latching / snap elements (10, 101, 102, 10', 10") can be actuated simultaneously or independently of each other by the finger grip (12), wherein - the finger grip (12) in particular has a first finger grip element and a second finger grip element, wherein the first finger grip element is designed in such a way that the at least one latching / snap element (10, 101, 102) can be actuated by the first finger grip element and the second finger grip element is designed in such a way that the at least one further latching / snap element (10', 10") can be actuated by the second finger grip element independently of the at least one latching / snap element (10, 101, 102), or. - the climbing boot in particular is designed such that, when the finger sliding element (11) is displaced relative to the main boot body (2) and the sliding element (6) is displaced about the finger displacement, i.e., the finger grip (12) is actuated, the finger sliding element (11) can be latched directly or indirectly to the main boot body (2) and / or the sliding element (6), in particular by means of a central axle element (2c), for example in the form of a bolt or a screw, or - with the climbing boot the handle (7) is designed in particular as a first web and the finger grip (12) is designed as a second web, wherein the first and second webs are arranged so as to be substantially parallel to one another, in particular at a distance of 3 to 4 cm from one another, in such a way that the finger grip (12) can be actuated when the handle (7) is gripped.
13. Rail-guided climbing system, comprising a climbing boot (1) according to any of the preceding claims, the bracket element (8a, 8b) arranged in a stationary manner on the concreting segment of the building and the climbing rail (9) arranged slidably between the rail guide elements (3a, 3b) of the main boot body (2), in particular with a climbing lift rail (9b) that is slidable with respect to the climbing rail (9) and guided by the climbing rail (9).
14. Method for decoupling a climbing boot (1) coupled to a concreting segment of a building for a rail-guided climbing system, which can be used in particular as a climbing formwork, climbing frame, protective climbing wall and / or climbing working platform, comprising the following steps: a) providing the climbing boot (1) having a main boot body (2) with first and second rail guide elements (3a, 3b), wherein at least the first rail guide element (3a), in particular the first and second rail guide elements (3a, 3b), is / are arranged on the main boot body (2) so as to be pivotable and / or extendable in such a way that, in the pivoted and / or extended guidance state, a climbing rail (9) arranged slidably between the first and second rail guide elements (3a, 3b) is guided by the rail guide elements (3a, 3b) in that portions of the climbing rail (9) are gripped by the rail guide elements (3a, 3b), b) providing a receiving element (5) that is arranged on the main boot body (2) and is designed to interact with a first portion of a bracket element (8a, 8b), arranged in a stationary manner on the concreting segment of the building, in such a way that, when the receiving element (5) is attached to the first portion of the bracket element (8a, 8b), a load of the climbing boot (1) can be introduced into the bracket element (8a, 8b), characterized in that the method further comprises the following steps: c) providing a sliding element (6) that is provided with a handle (7), arranged slidably with respect to the main boot body (2) and guided by the main boot body (2), which sliding element is designed in such a way that it is mechanically coupled to the main boot body (2) and the first rail guide element (3a), and, when the first rail guide element (3a) is in the guidance state, sliding (VO) of the sliding element (6) in relation to the main boot body (2) in a decoupling direction (Z), which sliding is caused by an actuation of the handle (7), results in the first rail guide element (3a) being set into the non-pivoted and / or retracted initial state in order to release the climbing boot (1) from being guided by the climbing rail (9), d) actuating the handle (7), wherein the generated sliding (VO) of the sliding element (6) in relation to the main boot body (2) results in the first rail guide element (3a) being set into the non-pivoted and / or retracted initial state, and e) separating the receiving element (5) from the first portion of the bracket element (8a, 8b) and releasing the climbing boot from being guided by the climbing rail (9) as a result of the actuation of the handle (7), wherein in particular, when the climbing boot (1) is arranged between the concreting segment and a climbing rail (9) guided by the climbing boot (1), - step b1) is additionally carried out between steps b) and c): providing a locking element (4) that is arranged so as to be pivotable and / or extendable on the main boot body (2) and is designed to interact with the first portion of the bracket element (8a, 8b) and the receiving element (5) or a second portion of the bracket element (8a, 8b) in such a way that the climbing boot (1) can be releasably locked on the bracket element (8a, 8b) in the pivoted and / or extended locking state, - in step c), the sliding element (6) is designed in such a way that it is mechanically coupled not only to the main boot body (2) and the first rail guide element (3a) but additionally to the locking element (4), and, when not only the first rail guide element (3a) is in the guidance state, but also the locking element (4) is in the locking state, sliding (VO) of the sliding element (6) in relation to the main boot body (2) in the decoupling direction (Z), which sliding is caused by an actuation of the handle (7), causes not only the first rail guide element (3a) but also the locking element (4) to be set into the non-pivoted and / or retracted initial state in order to release the climbing boot (1) from being guided by the climbing rail (9) and to release it from being locked on the bracket element (8a, 8b). - in step d), the sliding (VO) of the sliding element (6) in relation to the main boot body (2), which sliding is caused by actuating the handle (7), causes not only the first rail guide element (3a) but also the locking element (4) to be set into the non-pivoted and / or retracted initial state, and - in step e), not only is the receiving element (5) separated from the first portion of the bracket element (8a, 8b) and the climbing boot released from being guided by the climbing rail (9), but the climbing boot (1) is also released from being locked on the bracket element (8a, 8b).
15. Method according to claim 14 for decoupling the climbing boot (1) coupled to the concreting segment of the building for the rail-guided climbing system, wherein the climbing boot (1) is arranged between the concreting segment and a climbing rail (9) guided by the climbing boot (1), wherein - step b2) is additionally carried out between steps b) and c): providing the climbing boot (1) with at least one latching / snap element (10, 101, 102, 10', 10") arranged on the main boot body (2) so as to be pivotable and / or extendable, which latching / snap element interacts with a holding element of the climbing rail (9) and / or a climbing lift rail (9b), which is slidable relative to the climbing rail (9) and is guided by the climbing rail (9), for holding element the at least one latching / snap element (10, 101, 102, 10', 10") in such a way that, in the pivoted and / or extended holding state, the climbing rail (9) and / or climbing lift rail (9b) is suspended in the climbing boot (1) in the opposite direction to a climbing direction, - in step c), the sliding element (6) is designed in such a way that it is mechanically coupled not only to the main boot body (2), either to the first rail guide element (3a) or the first rail guide element (3a) and the locking element (4), but also to the latching / snap element (10, 101, 102, 10', 10"), and, if not only the first rail guide element (3a) is in the guidance state or the first rail guide element (3a) is in the guidance state and the locking element (4) is in the locking state, but also the latching / snap element (10, 101, 102, 101, 10") is in the pivoted and / or extended holding state, sliding (VO) of the sliding element (6) in relation to the main boot body (2) in the decoupling direction (Z), which sliding is caused by the actuation of the handle (7), results in not only the first rail guide element (3a) or the first rail guide element (3a) and the locking element (4), but also the latching / snap element (10, 101, 102, 10', 10") being set in each case into the non-pivoted and / or retracted initial state in order to not only release the climbing boot (1) from being guided by the climbing rail (9) or from being guided by the climbing rail (9) and locked on the bracket element (8a, 8b), but also to release it from the holding state of the climbing rail (9) and / or climbing lift rail (9b), - in step d), the sliding (VO) of the sliding element (6) in relation to the main boot body (2), which sliding is caused by actuating the handle (7), causes not only the first guide rail guide element (3a) or the first rail guide element (3a) and the locking element (4), but also the latching / snap element (10, 101, 102, 10', 10") to be set into the non-pivoted and / or retracted initial state, and - in step e) not only is the receiving element (5) separated from the first portion of the bracket element (8a, 8b) and the climbing boot released from being guided by the climbing rail (9) or the receiving element (5) separated from the first portion of the bracket element (8a, 8b), the climbing boot released from being guided by the climbing rail (9) and the climbing boot (1) released from being locked on the bracket element (8a, 8b), but the climbing boot (1) is also freed from the holding state of the climbing rail (9) and / or climbing lift rail (9b).
Citation Information
Patent Citations
Split climbing shoe of a climbing shell
DE102005030333B4
Climbing shoe for fixing a climbing scaffold to a concrete section of a building under construction
EP3241959B1
Self-climbing perimetric protection system for construction works in buildings
EP2365159A1
Climbing shoe for fixing a climbing scaffold to a concrete section of a building under construction
EP3241959A1
Anchoring system for anchoring a climbing head
EP3272967A1