Grouting repair method for mining-induced high-position fracture space
The grouting repair method addresses the challenge of water and gas hazards in coal mines by using directional drilling to identify and plug key stratum fractures, ensuring comprehensive sealing and efficient mining operations, thus enhancing mine safety and efficiency.
Patent Information
- Application Number
- GB2022017186
- Authority / Receiving Office
- GB · GB
- Patent Type
- Patents
- Current Assignee / Owner
- Priority Date
- 2022-05-06
- Filing Date
- 2022-10-09
- Publication Date
- 2024-11-27
- Estimated Expiration
- 2042-10-09
AI Technical Summary
Dual-system coal mining causes fractures in the overlying strata, leading to water and gas hazards in coal mines, as existing methods either require precise determination of grouting areas or fail to completely plug fissures, posing risks to mine safety and efficiency.
A grouting repair method using horizontal directional drilling to identify and plug mining-induced high-position fractures by determining key stratum positions and using specific grouting materials and pressures to seal both upper and lower separation areas, ensuring comprehensive plugging and efficient mining progress.
This method effectively reduces water and gas leakage, enhancing mine safety and efficiency by ensuring complete plugging of fractures and matching grouting speed with mining progress, while being practical and reliable.
Smart Images

Figure 00000001_0000 
Figure 00000001_0001
Abstract
Description
TECHNICAE FIELD
[0001] The present disclosure relates to the technical field of key strata water hazard and gas hazard prevention and control methods, in particular to a prevention and control method for plugging mine key stratum fissures by means of directional grouting, which is applicable to the field of water hazard and gas hazard prevention and control of dual-system coal mining shafts. BACKGROUND
[0002] 1. Dual-system coal seam mining may cause movement and destruction of the overlying strata, resulting in "O" type and "X" type fractures in the main key stratum, such fractures are communicated from the ground to the coal mining working face, and may cause coal mine spontaneous combustion disasters and generate harmful gases such as CO. When groundwater and some harmful gas exist in the goaf, the main key stratum damaged by mining may enable the water and gas to permeate into the underground goaf along these fractures, the more the fissures communicating with the goaf, the larger the groundwater inflow, the more the harmful gas, which may cause the problems of roof water hazard and gas hazard in serious cases, endangering the safe and efficient production of the mine shaft. Along with advancing of the mining face, concentrated stress will be generated above a mine pressure support, and there is a risk of strong mine pressure. If relevant measures can be found to plug the fractures in the main key stratum, the occurrence probability of disasters and the hazard degree when the disasters occur can be greatly reduced.
[0003] 2. At present, there are two countermeasures for the prevention and control of roof water damage and gas damage. One is a grouting subsidence reduction technology for vertical borehole grouting from ground to the separation area for grouting, such technology is to block the spread of water and gas to the lower working face by grouting into the separation area, with better plugging effect. However, the size of the separation area needs to be determined in advance, and the grouting is hard for the separation area with small space. The other is to plug the water diversion fissure zone, such method for the prevention and control of the water and gas hazards is easy for grouting, but the fissures cannot be completely plugged. Therefore, it is necessary to optimize the above two methods for the prevention and control of water and gas hazards to achieve both the complete plugging and easy construction. SUMMARY
[0004] To overcome the shortcomings in the prior art, the present disclosure provides a grouting repair method for a mining-induced high-position fracture space. In combination with coal seam mining coefficients and hydrogeological conditions, by determining the position of a main key stratum and development conditions of a separation area, a method for plugging the main key stratum to prevent the water and gas leakage by plugging an upper separation area of the main key stratum and a lower separation area of the main key stratum by means of horizontal directional drilling grouting is determined, thereby reducing the water and gas leakage degree of a goaf and relieving the threat of the water hazard and the gas hazard downhole. Therefore, the safe and efficient production of the mine is achieved.
[0005] To achieve the objective above, the present disclosure is implemented according to the following technical solutions:
[0006] A grouting repair method for a mining-induced high-position fracture space comprises the following steps:
[0007] Stepl, according to the breaking characteristics of key strata in overlying rock movement, collecting the ground drilling columnar data of each coal mining region, and 19 08 24 collecting a span upon occurrence of breakage for coal mining and a coal mining thickness in a mining area;
[0008] Step2, discriminating the positions of the key strata of the overlaying rock at each borehole by means of key stratum discrimination, thus determining the position of a main key stratum;
[0009] Step3, determining a breaking form of the main key stratum, delimiting a water diversion fissure region, and determining to horizontally drill along a rock stratum above the main key stratum and a rock stratum below the main key stratum by means of horizontal directional drilling according to the buried depth of the coal seam and borehole distribution conditions on the ground;
[0010] Step4: after drilling construction is completed, determining the arrangement distance between grouting holes according to the span upon occurrence of breakage , forming the grouting holes in a region, where the separation area has not been formed, of a high-position separation zone, starting grouting by a ground grouting station, pumping large-particle slurry to the high-position fracture area, plugging fissures in the lower separation area of the main key stratum and fissures in the lower portion of the main key stratum by using the grouting pressure; pumping the fine-particle grout to a fissure zone separation area, and plugging the fissures in the upper portion of the main key stratum by using the pressure of grout;
[0011] Step5, carrying out grouting on the separation area, and then continuing the advancement of a working face after the grouting in the separation area is completed; and
[0012] Step6, repeating the Stepl to the Step5 until the mining is finished.
[0013] Preferably, in the Step2, the discrimination mode for the key stratum is conducted by using KSPB software.
[0014] Specifically, in the Step3, the breaking form of the main key stratum comprises an "O-X" breaking form. The "O" type breaking portion forms a vertically-through fracture, and the "X" type breaking portion forms a fracture with the upper part closed and the lower part opened.
[0015] Specifically, in the Step3, a specific method of horizontal directional drilling comprises the steps: the maximum development position of the high-position fracture area is determined according to a water diversion fissure zone formula, and a double horizontal directional drilling operation is employed, wherein, after a horizontal section is leveled, a first horizontal directional borehole is located in the fissure zone separation area, and a second horizontal directional borehole is located in the high-position fracture area.
[0016] Specifically, the specific construction layout mode for the double horizontal directional boreholes is as follows: the two boreholes are both vertically drilled from the ground firstly, and the horizontal section of the first horizontal directional borehole is straightened above the main key stratum to make the horizontal section be located at the position 3m to 5 m above the main key stratum; the horizontal section of the second horizontal directional borehole is straightened in the main key stratum to make the horizontal section be located at the position 30 cm below the main key stratum, and each borehole is from a direction of a stop-mining line to a direction of an open-off cut, thus making the horizontal section borehole penetrate through the whole working face.
[0017] Preferably, in the Step4, the large-particle slurry is a cement-fly ash grout mixture that has a specific gravity of 1.4 to 1.6 and is mixed with large-particle aggregates (such as walnut shells) having a particle size of 4 mm to 6 mm, or a cement-fly ash grout mixture that has a specific gravity of 1.3 to 1.5 and is mixed with fiber-rich aggregates (such as cottonseed hulls) having a particle size of 2 mm to 3 mm, wherein a mixing proportion of the large-particle a aggregates is that 1 kg to 2 kg of large-particle aggregates is mixed into per 1 m of cement-fly ash grout mixture, and a mixing proportion of the fiber-rich aggregates is that 1 kg to 2 kg of a fiber-rich aggregates is mixed into per 1 m of cement-fly ash grout mixture.
[0018] Preferably, in the Step4, the fine-particle slurry is a cement-fly ash grout mixture with a specific gravity of 1.1 to 1.3. 19 08 24
[0019] Specifically, in the Step4, the specific method for grouting is as follows:
[0020] Step4.1, after the second horizontal directional borehole is formed, arranging a grouting pipe in a hole channel of the second horizontal directional borehole, wherein the first grouting hole is located at the position 40 m away from the open-off cut; injecting the cement-fly ash grout mixture that has a specific gravity of 1.4 to 1.6 and is mixed with the fiber-rich aggregates having the particle size of 2 mm to 3 mm, after continuing to inject for 2 h, if the grouting pressure is 0, continuing to carry out grouting by using the cement-fly ash grout mixture mixed with large-particle aggregates having the particle size of 4 mm to 6 mm;
[0021] Step4.2, continuing to inject the cement-fly ash grout mixture mixed with the fiber-rich aggregates until the grouting pressure rises, continuing to carry out grouting by using the cement-fly ash grout mixture mixed with the large-particle aggregates, when the pressure of grout rises to 1 MPa to 2 MPa, carrying out grouting by using a quick-setting grout mixture prepared from cement and water glass, and stopping grouting until the pressure of the grout rises; and
[0022] Step4.3, after the grouting at the high-position fracture area is completed, carrying out grouting on the fissure zone separation area, directly injecting the cement-fly ash grout mixture with a specific gravity of 1.1 to 1.3, and stopping grouting when the grouting pressure starts to rise.
[0023] Compared with the prior art, a grouting repair method for a mining-induced high-position fracture space provided by the present disclosure has the following beneficial effects:
[0024] The method is mainly suitable for the determination of plugging the main key stratum through borehole grouting through under the dual-system mining conditions, which may provide a guarantee for the prevention and control of water and gas leakage disasters in the mine shafts, is reliable in use and strong in practicability.
[0025] Based on the influence of mining parameters on the development of the water diversion fissure zone of the main key stratum under the coal seam geological occurrence conditions, both the distribution region of the water diversion fissure zone of the overlaying rock and the influence of grouting materials and the grouting method on the plugging effect are considered, and it is also guaranteed that the grouting speed is matched with the advance rate on the working face. In a mode of comprehensively considering the fissures on the main key stratum under dual-system mining, the grouting is carried out on the separation layer area, all the fissures on the key strata are plugged by the pressure of the grout, not only is the defect that the grouting is difficult in a grouting subsidence reduction method overcome, but also the grouting speed is guaranteed to be matched with various parameters such as the advance on the working face. In addition, the comprehensiveness of grouting is guaranteed, the "O-X" breaking fractures are comprehensively plugged. The method is safe, reliable and high in practicability, and can effectively reduce the degree of water and gas leakage and relieve the water hazard and gas hazard. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] To describe the technical solutions in the embodiments of the present disclosure or in the prior art more clearly, the following briefly introduces the accompanying drawings required for describing the embodiments. Apparently, the accompanying drawings in the following description show merely some embodiments of the present disclosure, and those of ordinary skill in the art may still derive other drawings from these accompanying drawings without creative efforts.
[0027] FIG. 1 is a plan view of borehole layout of a grouting repair method for a mining-induced high-position fracture space in accordance with the present disclosure;
[0028] FIG. 2 is a sectional view of A-A in FIG. 1. 19 08 24 DETAILED DESCRIPTION OF THE EMBODIMENTS
[0029] The present disclosure is further described below with reference to the accompanying drawings and specific embodiments. The illustrative embodiments and illustrations of the present disclosure herein serve to explain the present disclosure rather than limiting.
[0030] FIG. 1 and FIG. 2 are schematic diagrams of a grouting repair method for a mining-induced high-position fracture space used by a certain mining shaft in the embodiment. In the drawings, 1 denotes a grouting hole, 2 denotes an open-off cut, 3 denotes a goaf protection coal pillar, 4 denotes a "O" type fracture, 5 denotes an "X" type fracture, 6 denotes a second horizontal directional borehole, 7 denotes a stop-mining line, 8 denotes a roadway, 9 denotes a water diversion fissure region, 10 denotes a ground grouting station, 11 denotes a goaf, 12 denotes a working face, 13 denotes a main key stratum, 14 denotes a near field key stratum, 15 denotes a high-position fracture area, 16 denotes a first horizontal directional borehole, and 17 denotes a fissure zone separation area.
[0031] The grouting repair method for a mining-induced high-position fracture space of the present embodiment comprises the following steps:
[0032] Stepl, according to the breaking characteristics of key strata in overlying rock movement, collecting the ground drilling columnar data of each coal mining region, and collecting a span upon occurrence of breakage for coal mining and a coal mining thickness in a mining area;
[0033] Step2, discriminating the positions of the key strata of the overlaying rock at each borehole by means of key stratum discrimination, thus determining the position of a main key stratum 13;
[0034] Step3, determining a breaking form of the main key stratum 13, delimiting a water diversion fissure region 9, and determining to horizontally drill along a rock stratum above the main key stratum 13 and a rock stratum below the main key stratum 13 by means of horizontal directional drilling according to the buried depth of the coal seam and borehole distribution conditions on the ground;
[0035] Step4: after drilling construction is completed, determining the arrangement distance between grouting holes 1 according to the span upon occurrence of breakage , forming the grouting holes 1 in a region, where the separation area has not been formed, of a high-position separation zone, starting grouting by a ground grouting station 10, pumping large-particle slurry to the high-position fracture area 15, plugging fissures in the lower separation area of the main key stratum 13 and fissures in the lower portion of the main key stratum 13 by using the grouting pressure; pumping the fine-particle grout to a fissure zone separation area 17, and plugging the fissures in the upper portion of the main key stratum 13 by using the pressure of grout;
[0036] Step5, carrying out grouting on the high-position fracture area 15 and the fissure zone separation area 17, and then continuing the advancement of a working face after the grouting on the high-position fracture area 15 and the fissure zone separation area 17 is completed; and
[0037] Step6, repeating the Stepl to the Step5 until the mining is finished.
[0038] In accordance with the embodiment, in the Step2, the positions of the overlaying rock key strata at various boreholes are discriminated by using key stratum discrimination software KSPB.
[0039] In accordance with the embodiment, in the Step3, the breaking form of the main key stratum 13 comprises an "O-X" breaking form. The "O" type breaking portion forms a vertically-through fracture, which is an "O" type fracture 4; and the "X" type breaking portion forms a fracture with the upper part closed and the lower part opened, which is an "X" type fracture 5.
[0040] In accordance with the embodiment, in the Step3, a specific method of horizontal directional drilling comprises the steps: the maximum development position of the high-position fracture area 15 is determined according to a water diversion fissure zone formula, and a double horizontal directional drilling operation is employed, wherein, after a horizontal section is 19 08 24 leveled, a first horizontal directional borehole 16 is located in the fissure zone separation area 17, and a second horizontal directional borehole 6 is located in the high-position fracture area 15.
[0041] In accordance with the embodiment, the specific construction layout mode for the double horizontal directional boreholes is as follows: the two boreholes are both vertically drilled from the ground firstly, and the horizontal section of the first horizontal directional borehole 16 is straightened above the main key stratum 13 to make the horizontal section be located at the position 3 m to 5 m above the main key stratum 13; the horizontal section of the second horizontal directional borehole 6 is straightened in the main key stratum 13 to make the horizontal section be located at the position 30 cm below the main key stratum 13, and each borehole is from a direction of a stop-mining line 7 to a direction of an open-off cut 2, thus making the horizontal section borehole penetrate through the whole working face 12.
[0042] In accordance with the embodiment, in the Step4, the large-particle slurry is a cement-fly ash grout mixture that has a specific gravity of 1.4 to 1.6 and is mixed with large-particle aggregates (such as walnut shells) having a particle size of 4 mm to 6 mm, or a cement-fly ash grout mixture that has a specific gravity of 1.3 to 1.5 and is mixed with fiber-rich aggregates (such as cottonseed hulls) having a particle size of 2 mm to 3 mm, wherein a mixing proportion of the large-particle aggregates is that 1 kg to 2 kg of large-particle aggregates is mixed into per a 1 m of cement-fly ash grout mixture, and a mixing proportion of the fiber-rich aggregates is that a 1 kg to 2 kg of fiber-rich aggregates is mixed into per 1 m of cement-fly ash grout mixture. In accordance with the embodiment, in the Step4, the fine-particle slurry is a cement-fly ash grout mixture with a specific gravity of 1.1 to 1.3.
[0043] In accordance with the embodiment, in the Step4, the specific method for grouting is as follows:
[0044] Step4.1, after the second horizontal directional borehole 6 is formed, arranging a grouting pipe in a hole channel of the second horizontal directional borehole 6, wherein a first grouting hole 1 is located at the position 40 m away from the open-off cut 2; injecting the cement-fly ash grout mixture that has a specific gravity of 1.4 to 1.6 and is mixed with the fiber-rich aggregates having the particle size of 2 mm to 3 mm, after continuing to inject for 2 h, if the grouting pressure is 0, continuing to carry out grouting by using the cement-fly ash grout mixture mixed with large-particle aggregates having the particle size of 4 mm to 6 mm;
[0045] Step4.2, continuing to inject the cement-fly ash grout mixture mixed with the fiber-rich aggregates until the grouting pressure rises, continuing to carry out grouting by using the cement-fly ash grout mixture mixed with the large-particle aggregates, when the pressure of grout rises to 1 MPa to 2 MPa, carrying out grouting by using a quick-setting grout mixture prepared from cement and water glass, and stopping grouting until the pressure of the grout rises; and
[0046] Step4.3, after the grouting at the high-position fracture area 15 is completed, carrying out grouting on the fissure zone separation area 17, directly injecting the cement-fly ash grout mixture with the specific gravity of 1.1 to 1.3, and stopping grouting when the grouting pressure starts to rise.
[0047] The technical solution of the present disclosure is not limited by the specific embodiments described above, and all technical variations made according to the technical solution of the present disclosure shall fall within the scope of protection of the present disclosure.
Claims
1. A grouting repair method for a mining-induced high-position fracture space, comprising the following steps:Stepl, according to the breaking characteristics of key strata in overlying rock movement, collecting the ground drilling columnar data of each coal mining region, and collecting a span upon occurrence of breakage for coal mining and a coal mining thickness in a mining area;Step2, discriminating the positions of the key strata of the overlaying rock at each borehole by using a KSPB software, thus determining the position of a main key stratum;Step3, determining a breaking form of the main key stratum, delimiting a water diversion fissure region according to the breaking form of the main key stratum, and adopting horizontal directional drilling according to a buried depth of a coal seam and borehole distribution conditions on ground for horizontally drilling along a rock stratum above the main key stratum and a rock stratum below the main key stratum in the water diversion fissure region; wherein the breaking form of the main key stratum comprises an "O-X" breaking form; "O" type breaking portion forms a vertically-through fracture, and "X" type breaking portion forms a fracture with an upper part closed and a lower part opened;Step4: after drilling construction is completed, determining an arrangement distance between grouting holes according to the span upon occurrence of breakage, forming grouting holes in a region, where a fracture has not been formed, of a high-position fracture area, starting grouting by a ground grouting station, pumping a large-particle slurry to the high-position fracture area, plugging fissures in the lower separation area of the main key stratum and fissures in the lower portion of the main key stratum by using the grouting pressure; pumping a fine-particle slurry to a fissure zone separation area, and plugging the fissures in the upper portion of the main key stratum by using the pressure of grout;Step5, carrying out grouting on the fissure zone separation area, and then continuing the advancement of a working face after the grouting in the fissure zone separation area is completed; andStep6, repeating the Stepl to the Step5 until the mining is finished.
2. The grouting repair method for a mining-induced high-position fracture space according to claim 1, wherein in the Step3, a specific method of horizontal directional drilling comprises the steps: the maximum development position of the high-position fracture area is determined according to a water diversion fissure zone formula, and a double horizontal directional drilling operation is employed, wherein, after a horizontal section is leveled, a first horizontal19 08 24directional borehole is located in the fissure zone separation area, and a second horizontal directional borehole is located in the high-position fracture area.
3. The grouting repair method for a mining-induced high-position fracture space according to claim 2, wherein the specific construction layout mode for the double horizontal directional boreholes is as follows: the two boreholes are both vertically drilled from the ground firstly, and the horizontal section of the first horizontal directional borehole is straightened above the main key stratum to make the horizontal section be located at the position 3 m to 5 m above the main key stratum; the horizontal section of the second horizontal directional borehole is straightened in the main key stratum to make the horizontal section be located at the position 30 cm below the main key stratum, and each borehole is from a direction of a stop-mining line to a direction of an open-off cut, thus making the horizontal section borehole penetrate through the whole working face.
4. The grouting repair method for a mining-induced high-position fracture space according to claim 3, wherein, in the Step4, the large-particle slurry is a cement-fly ash grout mixture that has a specific gravity of 1.4 to 1.6 and is mixed with large-particle aggregates (such as walnut shells) having a particle size of 4 mm to 6 mm, or a cement-fly ash grout mixture that has a specific gravity of 1.3 to 1.5 and is mixed with fiber-rich aggregates (such as cottonseed hulls) having a particle size of 2 mm to 3 mm, wherein a mixing proportion of the large-particle aaggregates is that 1 kg to 2 kg of large-particle aggregates is mixed into per 1 m of cement-fly ash grout mixture, and a mixing proportion of the fiber-rich aggregates is that 1 kg to 2 kg of afiber-rich aggregates is mixed into per 1 m of cement-fly ash grout mixture.
5. The grouting repair method for a mining-induced high-position fracture space according to claim 4, wherein in the Step4, the fine-particle slurry is a cement-fly ash grout mixture with a specific gravity of 1.1 to 1.3.
6. The grouting repair method for a mining-induced high-position fracture space according to claim 5, wherein in the Step4, the specific method for grouting is as follows:Step4.1, after the second horizontal directional borehole is formed, arranging a grouting pipe in a hole channel of the second horizontal directional borehole, wherein the first grouting hole is located at the position 40 m away from the open-off cut; injecting the cement-fly ash grout mixture that has a specific gravity of 1.4 to 1.6 and is mixed with the fiber-rich aggregates having the particle size of 2 mm to 3 mm, after continuing to inject for 2 h, if the grouting pressure is 0, continuing to carry out grouting by using the cement-fly ash grout mixture mixed with large-particle aggregates having the particle size of 4 mm to 6 mm;Step4.2, continuing to inject the cement-fly ash grout mixture mixed with the fiber-richaggregates until the grouting pressure rises, continuing to carry out grouting by using the cement-fly ash grout mixture mixed with the large-particle aggregates, when the pressure of grout rises to 1 MPa to 2 MPa, carrying out grouting by using a quick-setting grout mixture prepared from cement and water glass, and stopping grouting until the pressure of the grout rises; andStep4.3, after the grouting at the high-position fracture area is completed, carrying out grouting on the fissure zone separation area, directly injecting the cement-fly ash grout mixture with a specific gravity of 1.1 to 1.3, and stopping grouting when the grouting pressure starts to rise.
Citation Information
Patent Citations
Isolated-section grouting filling coal-mining method for mining overburden rock
CN102704933A
Composite grouting method for production of thick coal beds with large coal mining working face widths
CN110671145A
Overlying strata separation layer grouting surface subsidence control method and grouting device thereof
CN114351685A
Mining high-position fracture space grouting repair method
CN114876403A
AU2020100234A4