Cutting device and steel pipe cutting method
The cutting device efficiently cuts steel pipes vertically and horizontally by using a movable and rotatable support system with wheels and high-pressure water, facilitating easy removal of steel pipes and sheet piles.
Patent Information
- Application Number
- JP2023045095
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-22
- Publication Date
- 2024-10-04
AI Technical Summary
Existing cutting devices for steel pipe piles and sheet piles are inefficient in cutting them vertically and horizontally due to the need for large pulling forces to counteract earth and water pressure, making removal difficult.
A cutting device with a movable and rotatable cutting machine support means equipped with wheels and a high-pressure water injection system, allowing for vertical and horizontal cutting of steel pipes, minimizing the impact of earth and water pressure.
Enables easy division and removal of steel pipes and sheet piles by cutting them into smaller pieces, ensuring stability and reaction force through the use of wheels and high-pressure water injection, reducing the effects of earth and water pressure.
Smart Images

Figure 2024134747000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a cutting device and a steel pipe cutting method for cutting existing steel pipe piles or steel pipe sheet piles. [Background technology]
[0002] As a method for removing existing steel pipe piles, steel pipe sheet piles, etc., there is a method in which the steel pipe piles, steel pipe sheet piles, etc. are cut on-site and the cut pieces are removed in several steps. For example, Patent Document 1 discloses a cutting device for steel pipe sheet piles that cuts the steel pipe sheet pile in the circumferential direction (horizontal direction) by rotating a water jet nozzle inserted into the steel pipe sheet pile around a vertical axis. Patent Document 2 discloses a cutting device that cuts a joint pipe part of the steel pipe sheet pile with a grindstone cutter and cuts a main pipe part of the steel pipe sheet pile in the circumferential direction (horizontal direction) with a water jet nozzle that rotates around a rotating shaft. Note that neither of the cutting devices in Patent Documents 1 and 2 is intended to cut the steel pipe sheet pile in the axial direction (vertical direction). When a steel pipe is cut horizontally (circumferentially), the horizontally cut pieces are subjected to earth and water pressure from all sides, requiring a large pulling force. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] Japanese Patent Application Publication No. 61-087020 [Patent Document 2] Japanese Patent Application Publication No. 63-114721 Summary of the Invention [Problem to be solved by the invention]
[0004] From this viewpoint, the present invention aims to propose a cutting device and a steel pipe cutting method for cutting steel pipe piles or steel pipe sheet piles lengthwise and crosswise to divide them into pieces for removal. [Means for solving the problem]
[0005] The cutting device of the present invention for solving the above-mentioned problems is for cutting steel pipes installed underground or underwater, and includes a cutting machine main body capable of spraying high-pressure water for cutting the steel pipe, and a cutting machine support means installed inside the steel pipe and supporting the cutting machine main body. The cutting machine support means has a support part that supports the cutting machine main body so that it can move in the vertical direction, and wheels that can run on the inner surface of the steel pipe, and is rotatable around the central axis of the steel pipe. The cutting device may include a rotation device that is detachable from the cutting machine support means and that applies a rotational force to the cutting machine support means.
[0006] The steel pipe cutting method of the present invention utilizing the cutting device comprises an equipment installation process for installing the cutting machine support means within the steel pipe, a vertical cutting process for cutting the steel pipe vertically by moving the cutting machine main body vertically within the steel pipe via the cutting machine support means and spraying high-pressure water from the cutting machine main body, and a transverse cutting process for cutting the steel pipe circumferentially by rotating the cutting machine support means and spraying high-pressure water from the cutting machine main body.
[0007] According to this cutting device and steel pipe cutting method, the cutting machine body can move up and down and rotate circumferentially, so that the steel pipe can be cut in the vertical direction (axial direction) and horizontal direction (circumferential direction). Therefore, the steel pipe can be divided into small pieces and removed while minimizing the effects of earth pressure and water pressure, and the steel pipe pile or steel pipe sheet pile can be removed relatively easily. In addition, since the cutting machine support means is equipped with wheels, stability is ensured when the cutting machine support means is positioned and rotated, and a reaction force can be secured from the inner wall surface of the steel pipe when high-pressure water is sprayed from the cutting machine body to cut the steel pipe.
[0008] In addition, it is desirable for the cutting machine support means to include a support pillar arranged along the axial direction of the steel pipe and a rail arranged parallel to the support pillar, in which case the cutting machine body can be moved along the rail. In addition, when the cutter support means includes a support pillar provided along the axial direction of the steel pipe and a plurality of rails provided around the support pillar in parallel with the support pillar, it is preferable to provide a plurality of cutter bodies that can move along the rails. In this way, cutting work can be performed at a plurality of locations simultaneously, thereby shortening the construction period. If the cutting machine body is equipped with a pair of nozzles spaced apart from each other on the left and right and is capable of simultaneously spraying high-pressure water from both nozzles, the steel pipe can be cut into strips by moving one cutting machine body up and down. For example, if the steel pipe to be cut is connected to another steel pipe via a joint, the joint portion can be separated from the other portion by raising or lowering the cutting machine body with a pair of nozzles located on both the left and right sides of the joint.
[0009] In addition, when the cutting machine support means comprises a support column arranged along the axial direction of the steel pipe by connecting a plurality of support members in the axial direction, and a rail arranged parallel to the support column by connecting a plurality of rail members in the axial direction, in the equipment installation process, a cutting machine support means that reaches a predetermined depth can be formed by connecting an upper support member to the upper end of the lower support member held by a fixing jig provided at the upper end of the steel pipe. Furthermore, if the machine includes a first vertical cutting process for cutting the steel pipe vertically when the cutting machine body is lowered, and a second vertical cutting process for cutting the steel pipe vertically when the cutting machine body is raised, the steel pipe cutting operation can be performed efficiently. Effect of the Invention
[0010] According to the cutting device and steel pipe cutting method of the present invention, by dividing the steel pipe into small pieces in the axial and circumferential directions, existing steel pipe piles and steel pipe sheet piles can be easily removed. [Brief description of the drawings]
[0011] [Figure 1] FIG. 2 is a side view showing a cutting state of the steel pipe sheet pile according to the embodiment of the present invention. [Diagram 2] FIG. 2 is a diagram showing a cutting device and a steel pipe sheet pile of the first embodiment, in which (a) is a plan view and (b) is a cross-sectional view. [Diagram 3] FIG. 1 is a front view showing a cutting device according to a first embodiment. [Figure 4] FIG. 2 is a plan view showing the cutting device of the first embodiment. [Diagram 5] FIG. [Figure 6] 2 is a flowchart showing the procedure of the steel pipe cutting method of the first embodiment. [Figure 7] FIG. [Figure 8] FIG. 11 is an enlarged cross-sectional view showing the device installation process. [Figure 9] FIG. 4 is a plan view showing a vertical cutting step of the first embodiment. [Figure 10] FIG. 11 is a plan view showing a cutting device according to a second embodiment. [Figure 11] 10 is a flowchart showing the steps of a steel pipe cutting method according to a second embodiment. [Figure 12] FIG. 4 is a schematic diagram showing an overview of a steel pipe cutting method according to a second embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0012] Hereinafter, a case will be described in which a steel pipe sheet pile 1 constituting the diaphragm wall is cut underground and divided into pieces, and the cut pieces are extracted from the ground when a diaphragm wall remaining at a position where a new structure is to be constructed is removed. Fig. 1 is a cross-sectional view showing the cutting state of the steel pipe sheet pile 1. As shown in Fig. 1, the steel pipe sheet pile 1 is cut in the axial direction (vertical direction) and circumferential direction (horizontal direction) from the inside of the steel pipe 11 using a cutting device 2. 2 shows a steel pipe sheet pile 1 and a cutting device 2 of the first embodiment. The steel pipe sheet pile 1 is composed of a steel pipe 11 and a joint 12 fixed to the side of the steel pipe 11, and a continuous underground wall is formed by connecting a plurality of steel pipe sheet piles 1 underground while engaging the joints 12, 12 of adjacent steel pipe sheet piles 1, 1. Earth pressure and groundwater pressure act on the steel pipe sheet pile 1 (steel pipe 11) from all sides (all directions). By cutting the steel pipe 11 vertically, earth pressure and water pressure act on the cut pieces from one direction, making it easier to remove (pull out) the cut pieces.
[0013] First Embodiment As shown in FIG. 2, the cutting device 2 includes a cutting machine support means 3 and a cutting machine main body 4. The cutting machine support means 3 is installed inside the steel pipe 11 and supports the cutting machine main body 4. The cutting machine support means 3 has a support part 6 that supports the cutting machine main body 4 so that it can move in the vertical direction, and wheels 7 that can run on the inner surface of the steel pipe 11. The support portion 6 includes a pillar 61 provided along the axial direction of the steel pipe 11 and a rail 62 provided in parallel to the pillar 61 .
[0014] The support 61 is disposed at the center of the steel pipe 11 and can rotate around the central axis of the steel pipe 11. The support 61 is formed to a predetermined length by connecting a plurality of support members 63, 63, ... in the axial direction. The support member 63 is a columnar member constituting a part of the support 61 in the longitudinal direction, and is made of a square pipe with a total length of 1 to 12 m, preferably 1 to 6 m, and more preferably 2 to 4 m. FIG. 3 shows the details of the cutting device 2. As shown in FIG. 3, joint plates 64 for connecting to other support members 63 are attached to both ends (upper and lower ends) of the support member 63. Vertically adjacent support members 63 are joined to each other by bolts that pass through the joint plates 64, 64 that are stacked vertically.
[0015] In this embodiment, a pair of rails 62, 62 are provided at positions facing each other across a support 61. The rail 62 is formed to a predetermined length by connecting a plurality of rail members 65, 65, ... in the axial direction. The rail member 65 is a member that constitutes a part of the rail 62 in the longitudinal direction. The rail member 65 in this embodiment is made of a plate material having a length equivalent to that of the support member 63, and is fixed to the support member 63 via an attachment member 66. The attachment member 66 is a bracket that protrudes laterally from the side surface of the support member 63, and is fixed in a plurality of stages (five stages in this embodiment) at predetermined intervals (for example, 50 to 100 cm) in the axial direction of the support member 63. The attachment member 66 in this embodiment has a base that is fixed to the support member 63. The base has a through hole formed therein that has a shape equivalent to the outer shape of the support member 63. The support member 63 is inserted into the through hole. The method of fixing the mounting member 66 is not limited, and may be, for example, welded to the support member 63 or bolted. The rail member 65 is made of a steel plate and is fixed to an end face of the mounting member 66. The end faces of vertically adjacent rail members 65 are butted together and bolted together while being sandwiched between connecting plate members (not shown) disposed at the front and rear.
[0016] As shown in FIG. 2, the wheel 7 is attached to the support 61 via a bracket 71. The bracket 71 extends from the support 61 toward the side with its base end fixed to the support 61. The wheel 7 is attached to the tip of the bracket 71. The wheel 7 is a so-called caster, and is supported by the bracket 71 so as to be rotatable about an axis (radial direction of the steel pipe) perpendicular to the axis of the support 61, and rotates about a rotation axis perpendicular to the axis. That is, the wheel 7 rolls on the inner surface of the steel pipe 11 according to the moving direction of the cutting machine support means 3 (up and down direction or circumferential direction of the steel pipe). It is desirable to provide a buffer member such as a spring at the joint between the bracket 71 and the wheel 7 to reduce the influence of the backing ring. The number of stages and the intervals at which the wheels 7 (brackets 71) are installed are not limited, but one to two stages are provided for each support member 63. In this embodiment, the brackets 71 arranged above and below are connected to each other by a reinforcing member 72 (diagonal member or diagonal brace). In this embodiment, four brackets 71, 71, ... are provided at the same height position (each step) radially extending from the support 61. That is, the brackets 71 are provided in a cross shape in a plan view. It is desirable to arrange 3 to 6 brackets 71, and preferably 3 to 4 brackets 71 at equal intervals in the circumferential direction.
[0017] FIG. 4 shows the cutting machine body 4. As shown in FIG. 4, the cutting machine body 4 has a nozzle 41 and can spray high-pressure water for cutting the steel pipe 11. The cutting machine body 4 can move along a rail 62. In this embodiment, the cutting machine bodies 4 are arranged on the rails 62 provided at positions facing each other across a support 61. The cutting machine body 4 of this embodiment has a pair of nozzles 41, 41 arranged at a distance on the left and right. The pair of nozzles 41, 41 can spray high-pressure water simultaneously. The distance between the pair of nozzles 41, 41 is greater than the width (weld width) of the connection between the steel pipe 11 and the joint 12 of the steel pipe sheet pile 1.
[0018] The cutting machine body 4 is equipped with a plurality of wheels 42 capable of running on the front or rear surface of the rail 62. The wheels 42 are rotatable about a horizontal axis (an axis perpendicular to the longitudinal axis (vertical axis) of the rail 62) and are disposed on the front (steel pipe side) and rear (pillar side) of the rail 62, respectively. That is, the cutting machine body 4 is capable of moving up and down along the rail 62 by the plurality of wheels 42, 42, ... disposed with the rail 62 sandwiched between them from the front and rear. As shown in FIG. 3, the cutting machine body 4 is suspended by a suspending means 91 such as a wire. The cutting machine body 4 moves up and down along the rail 62 by winding up and letting out the suspending means 91.
[0019] The cutting device 2 also includes a rotating device 5 that is detachable from the cutting machine support means 3. The rotating device 5 applies a rotational force centered on a vertical axis (axis parallel to the central axis of the steel pipe) to a support 61 (cutting machine support means 3). FIG. 5 shows the rotating device 5. As shown in FIG. 5, the rotating device 5 can be installed above the steel pipe 11 (above ground). The rotating device 5 is composed of a motor 51, a rotating device main body 52, and a rotating shaft 53, and is provided above the steel pipe via a pedestal 54. The pedestal 54 is provided above the steel pipe via a leg 55 fixed to the upper end of the steel pipe. The rotating shaft 53 is connected to the support 61, and rotates by driving the motor 51. When the motor 51 is driven, the rotating device main body 52 operates and a rotational force is transmitted to the rotating shaft 53. When the rotating shaft 53 rotates, the support 61 connected to the rotating shaft 53 rotates.
[0020] Next, a steel pipe cutting method of this embodiment using the cutting device of this embodiment will be described. The procedure of the steel pipe cutting method is shown in Figure 6. As shown in Figure 6, the steel pipe cutting method includes an apparatus installation step S11, a vertical cutting step S12, a rotation device installation step S13, and a horizontal cutting step S14. In the device installation step S11, the cutting machine support means 3 is installed in the steel pipe 11. FIG. 7 shows the device installation step S11. As shown in FIG. 7, the support portion 6 of the cutting machine support means 3 is provided to a predetermined depth along the axial direction of the steel pipe 11. The support 61 is formed by connecting a plurality of support members 63, 63, ... in the axial direction. In addition, in conjunction with the installation of the support 61, a rail 62 is provided parallel to the support 61 by connecting a plurality of rail members 65, 65, ... in the axial direction. FIG. 8 shows the connection portion between the support members 63. When connecting the support members 63 to each other, as shown in FIG. 8, the lower support member 63 is held by a fixing jig 8 provided at the upper end of the steel pipe 11, and then the upper support member 63 is connected to the upper end of the lower support member 63. The fixing jig is interposed between the joint plate 64 of the support member 63 and the upper end of the steel pipe 11. In parallel with the operation of connecting the support members 63, the operation of connecting the rail members 65 is also performed. Then, by repeating the operation of connecting the support members 63 and the operation of lowering the connected support members 63, a cutting machine support means 3 that can reach a predetermined depth is formed.
[0021] In the vertical cutting step S12, the steel pipe 11 is cut in the vertical direction (up and down direction). FIG. 9 shows the vertical cutting step S12. The vertical cutting of the steel pipe 11 is performed by moving the cutting machine body 4 in the vertical direction within the steel pipe 11 via the cutting machine support means 3 and spraying high-pressure water from the cutting machine body 4. The cutting machine body 4 is suspended from a wire 91 extended from a lifting machine 9 such as a winch. The cutting machine body 4 moves up and down by operating the lifting machine 9 (sending and rewinding the wire 91) (see FIG. 1). In this embodiment, with the center of the cutting machine body 4 positioned at the position of the joint of the steel pipe, high-pressure water is sprayed from a pair of nozzles 41 of the cutting machine body 4 as shown in FIG. 9, to simultaneously cut two places on the left and right sides of the joint 12. In this way, the steel pipe 11 is divided into four pieces in a cross-sectional view (plan view).
[0022] In the rotating device installation process S13, the rotating device 5 is attached to the support 61 (see FIG. 5). The rotating device 5 is disposed on the steel pipe 11 via a pedestal 54. The rotating shaft 53 of the rotating device 5 is attached to the support 61. In addition, the wire 91 extending from the cutting machine body 4 is removed from the lifting machine 9 such as a winch. The cutting machine body 4 is fixed to the rail 62 via a jig. In other words, the cutting machine body 4 is held at a predetermined height.
[0023] In the transverse cutting step S14, the steel pipe is cut in the transverse direction (circumferential direction). In the transverse cutting step S14, the rotation device 5 is operated to rotate the support 61 about the vertical axis (the central axis of the steel pipe 11). As the support 61 rotates, the cutting machine main body 4 also rotates about the support 61. In this embodiment, the steel pipe 11 is cut in the circumferential direction by simultaneously performing the operation of rotating the cutting machine support means 3 by 180° and the operation of spraying high-pressure water from the cutting machine main body 4. After the steel pipe 11 is cut at a predetermined depth, the piece of the steel pipe 11 is pulled up from above and removed.
[0024] As described above, according to the cutting device 2 and the steel pipe cutting method of this embodiment, the cutting machine body 4 can move in the vertical direction and rotate in the circumferential direction, so that the steel pipe 11 can be cut in the vertical direction (axial direction) and the horizontal direction (circumferential direction). Therefore, the steel pipe 11 can be divided into small pieces and removed while minimizing the effects of earth pressure and water pressure, and the steel pipe pile or steel pipe sheet pile can be removed relatively easily. In addition, since the cutting machine support means 3 is equipped with the wheels 7, stability is ensured when the cutting machine support means 3 is placed and rotated, and a reaction force can be secured from the inner wall surface of the steel pipe 11 when high-pressure water is sprayed from the cutting machine body 4.
[0025] When cutting the steel pipe 11 in the vertical direction, the cutting position is stable because the cutting machine body is moved along the rails 62. When cutting the steel pipe 11 in the horizontal direction, the cutting machine body 4 is suspended at a predetermined height and supported by the rails 62, ensuring stability. In addition, the cutting machine support means 3 is provided with wheels 7 that come into contact with the inner surface of the steel pipe 11, so shaking is suppressed and cutting work can be performed in a stable state. In other words, when high-pressure water is sprayed from the cutting machine main body 4, a reaction force can be secured by the cutting machine support means 3, so the spray position is stable. Furthermore, since the steel pipe 11 is divided into the joint portion and the other portion, it is easy to remove.
[0026] Second Embodiment The cutting device 20 of the second embodiment is shown in Fig. 10. As shown in Fig. 10, the cutting device 20 of the second embodiment includes a cutting machine support means 3 and a cutting machine main body 4. The cutting machine support means 3 is installed inside the steel pipe 11 and supports the cutting machine main body 4. The cutting machine support means 3 has a support part 6 that supports the cutting machine main body 4 so that it can move in the vertical direction, and wheels 7 (see FIG. 8) that can run on the inner surface of the steel pipe 11. The details of the support part 6 and the wheels 7 are similar to those of the first embodiment, so a detailed description will be omitted. The support portion 6 includes a pillar 61 provided along the axial direction of the steel pipe 11, and a rail 62 provided parallel to the pillar 61. Details of the pillar 61 are similar to those of the pillar 61 in the first embodiment, and therefore detailed description thereof will be omitted.
[0027] A rail 62 is provided on the support 61. The rail 62 is disposed at a position spaced apart from the side surface of the support 61. The rail 62 is formed to a predetermined length by connecting a plurality of rail members 65, 65, ... in the axial direction. The rail member 65 is made of a plate material having a length equivalent to that of the support member 63, and is fixed to the support member 63 via a mounting member 66. The mounting member 66 is a bracket that protrudes laterally from the side surface of the support member 63, and a plurality of mounting members 66 are fixed to the support member 63 at predetermined intervals in the axial direction. The rail member 65 is made of a steel plate, and is fixed to an end surface of the mounting member 66. The rail members 65 adjacent to each other in the vertical direction are arranged with their end surfaces butted against each other, and are bolted together while being sandwiched between connecting plate materials disposed in the front and rear.
[0028] The details of the wheel 7 are similar to those of the wheel 7 in the first embodiment, and therefore a detailed description thereof will be omitted. The cutting machine body 4 has a nozzle 41 and is capable of spraying high-pressure water for cutting the steel pipe 11. The cutting machine body 4 is capable of moving in the vertical direction along a rail 62. Other details of the cutting machine body are similar to those of the cutting machine body of the first embodiment, and therefore detailed description thereof will be omitted.
[0029] The cutting device 2 also includes a rotating device 5 that is detachable from the cutter support means 3. The details of the rotating device 5 are similar to those of the rotating device 5 in the first embodiment, and therefore a detailed description thereof will be omitted.
[0030] Next, a steel pipe cutting method of this embodiment using the cutting device of this embodiment will be described. The procedure of the steel pipe cutting method is shown in Figures 11 and 12. As shown in Figure 11, the steel pipe cutting method includes an apparatus installation step S21, a first vertical cutting step S22, a rotating device installation step S23, a horizontal cutting step S24, a rotating device removal step S25, and a second vertical cutting step S26. In the second embodiment, as shown in Fig. 12, after the steel pipe is cut in the vertical direction while lowering the cutting device 2 (not shown) (first vertical cutting step S22), the steel pipe is cut in the circumferential direction while rotating the cutting device 2 (horizontal cutting step S24), and further, the steel pipe is cut in the vertical direction while lifting the cutting device 2. Note that in Fig. 12, the movement direction of the cutting device 2 (nozzle 41) is indicated by an arrow. In the device installation step S21, the cutting machine support means 3 is installed in the steel pipe 11. Details of the device installation step S21 are similar to the device installation step S11 in the first embodiment, and therefore detailed description thereof will be omitted.
[0031] In the first vertical cutting step S22, the steel pipe 11 is cut in the vertical direction (up and down direction). When cutting the steel pipe 11 in the vertical direction, the operation of lowering the cutting machine body 4 into the steel pipe 11 via the cutting machine support means 3 and the operation of spraying high-pressure water from the cutting machine body 4 are performed simultaneously. The cutting machine body 4 is suspended by a wire extended from a winch, and is lowered by operating the winch. In this embodiment, with the center of the cutting machine body 4 positioned at the position of the joint of the steel pipe 11, high-pressure water is sprayed from a pair of nozzles of the cutting machine body 4, thereby simultaneously cutting both the left and right sides of the joint in the axial direction. In this way, the steel pipe 11 is divided into two in a cross-sectional view (plan view).
[0032] In the rotation device installation step S23, the rotation device 5 is attached to the support 61 (see FIG. 5). Details of the rotation device installation step S23 are similar to the rotation device installation step S13 in the first embodiment, and therefore detailed description thereof will be omitted. In the transverse cutting step S24, the steel pipe is cut in the transverse direction (circumferential direction). In the transverse cutting step S24, the rotation device 5 is operated to rotate the support 61 about the vertical axis (the central axis of the steel pipe 11). As the support rotates, the cutting machine main body 4 also rotates about the support 61. In this embodiment, the steel pipe 11 is cut in the circumferential direction by simultaneously performing the operation of rotating the cutting machine support means 3 by 360° and the operation of spraying high-pressure water from the cutting machine main body 4. After the steel pipe 11 is cut at the predetermined depth, the cutting device 2 is rotated another 180°.
[0033] In the rotating device removal step S25, the cutting machine support means 3 is replaced with a fixing jig 8 (see FIG. 8), and then the rotating device 5 is removed. In the second vertical cutting process S26, the steel pipe 11 is cut vertically by combining an operation of raising the cutting machine body 4 inside the steel pipe 11 via the cutting machine support means 3 and an operation of spraying high-pressure water from the cutting machine body 4. The cutting machine body 4 is suspended by a wire extended from a winch and is raised by operating the winch. In this embodiment, with the center of the cutting machine body 4 positioned at the position of the joint 12 of the steel pipe 11, high-pressure water is sprayed from a pair of nozzles of the cutting machine body 4, thereby simultaneously cutting both the left and right sides of the joint 12 in the axial direction. In this way, the steel pipe 11 is divided into four pieces in a cross-sectional view (plan view). After the steel pipe 11 is cut, the piece of steel pipe 11 is pulled up from above and removed.
[0034] As described above, according to the cutting device and steel pipe cutting method of the second embodiment, similar to the cutting device and steel pipe cutting method of the first embodiment, by dividing the steel pipe into smaller pieces in the axial and circumferential directions, existing steel pipe piles and steel pipe sheet piles can be easily removed.
[0035] Although an embodiment of the present invention has been described above, the present invention is not limited to the above-described embodiment, and each of the above-described components can be appropriately modified without departing from the spirit of the present invention. In the above embodiment, the case of cutting a steel pipe sheet pile 1 has been described, but the cutting device 2 of the present invention may also be used to cut, for example, a steel pipe pile, and the object to be cut is not limited as long as it is a component having a steel pipe 11. Furthermore, the number and arrangement of the rails 62 provided on the cutting machine support means 3 are not limited and may be determined appropriately. Similarly, the number and arrangement of the nozzles 41 and wheels 42 provided on the cutting machine body 4 may be determined appropriately. The order of the vertical cutting step and the horizontal cutting step is not limited. The vertical cutting step may be performed after the horizontal cutting step, or the vertical cutting step may be performed after the horizontal cutting step. Furthermore, the vertical cutting step and the horizontal cutting step may be performed alternately. The shape of the rail member 65 and the material constituting the rail member 65 are not limited, and the rail member 65 may be made of steel, such as L-shaped steel or T-shaped steel, for example. [Explanation of symbols]
[0036] 1 Steel pipe sheet pile 11 Steel pipe 12 Joints 2 Cutting device 3 Cutting machine support means 4 Cutting machine body 41 Nozzle 42 wheels 5 Rotating device 6 Support part 61 Pillar 62 Rail 7 wheels
Claims
1. A cutting device for cutting steel pipes installed underground or underwater, a cutting machine body capable of spraying high-pressure water for cutting the steel pipe; a cutting machine support means installed in the steel pipe and supporting the cutting machine body, A cutting device characterized in that the cutting machine support means has a support part that supports the cutting machine body so that it can be moved in the vertical direction and wheels that can run on the inner surface of the steel pipe, and is rotatable around the central axis of the steel pipe.
2. A rotating device is provided for applying a rotational force to the cutting machine support means, 2. The cutting apparatus of claim 1, wherein said rotating device is detachable from said cutter support means.
3. The cutting machine support means includes a support pillar provided along the axial direction of the steel pipe and a rail provided parallel to the support pillar, The cutting device according to claim 1 , wherein the cutting machine body is movable along the rail.
4. The cutting machine support means includes a support pillar provided along the axial direction of the steel pipe, and a plurality of rails provided around the support pillar and parallel to the support pillar, 2. The cutting device according to claim 1, further comprising a plurality of said cutting machine bodies movable along said rails.
5. The cutting machine body includes a pair of nozzles arranged at a distance from one another on the left and right, 2. The cutting device according to claim 1, wherein high-pressure water can be jetted from both nozzles simultaneously.
6. A steel pipe cutting method for cutting a steel pipe installed underground or underwater using the cutting device according to any one of claims 1 to 5, an apparatus installation step of installing the cutting machine support means in the steel pipe; a vertical cutting process for cutting the steel pipe in the vertical direction by moving the cutting machine body vertically within the steel pipe via the cutting machine support means and spraying high-pressure water from the cutting machine body; A steel pipe cutting method comprising: a transverse cutting process for cutting the steel pipe in a circumferential direction by rotating the cutting machine support means and spraying high-pressure water from the cutting machine body.
7. The cutting machine support means includes a support provided along the axial direction of the steel pipe by connecting a plurality of support members in the axial direction, and a rail provided parallel to the support by connecting a plurality of rail members in the axial direction, The steel pipe cutting method described in claim 6, characterized in that in the equipment installation process, an upper support member is connected to the upper end of the lower support member held by a fixing jig provided at the upper end of the steel pipe, thereby forming a cutting machine support means that reaches a predetermined depth.
8. A steel pipe cutting method for cutting a steel pipe installed underground or underwater using the cutting device according to any one of claims 1 to 5, an apparatus installation step of installing the cutting machine support means in the steel pipe; a first vertical cutting process for cutting the steel pipe in a vertical direction by lowering the cutting machine body into the steel pipe via the cutting machine support means and spraying high-pressure water from the cutting machine body; a transverse cutting process for cutting the steel pipe in a circumferential direction by rotating the cutting machine support means and spraying high-pressure water from the cutting machine body; A steel pipe cutting method comprising: an operation of raising the cutting machine body within the steel pipe via the cutting machine support means; and a second vertical cutting process of cutting the steel pipe vertically by an operation of spraying high-pressure water from the cutting machine body.
Citation Information