Power supply system, and control method therefor
The power supply system addresses high initial costs by switching between grid and self-sustaining modes, ensuring stable power supply during emergencies with a cost-effective configuration.
Patent Information
- Application Number
- JP2023045673
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-22
- Publication Date
- 2024-10-04
AI Technical Summary
Existing power supply systems with distributed power sources, such as solar cells and storage batteries, face high initial investment costs for large-capacity storage batteries, hindering their widespread adoption for extended power supply during emergencies.
A power supply system incorporating a solar cell, storage battery, combined heat and power device, and power control unit, with switching mechanisms to alternate between grid-connected and self-sustaining modes, ensuring power is supplied from these sources during outages by managing energy storage and generation.
The system provides stable power supply during emergencies by extending the duration of power availability with a cost-effective configuration, maintaining energy resilience by switching between grid and self-sustaining modes.
Smart Images

Figure 2024135136000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a power supply system and a control method thereof. [Background technology]
[0002] Conventionally, there is known a power supply system that is configured to be able to supply power from a commercial power grid via commercial power lines to a load installed in a house or the like, and that is also configured to be able to supply power generated by the solar cells or power stored in the storage battery via a branch power line from a distributed power source consisting of a solar cell and a storage battery capable of storing the power generated by the solar cell (see Patent Document 1). [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2021-40433 A Summary of the Invention [Problem to be solved by the invention]
[0004] As with the technology disclosed in Patent Document 1, a power supply system having a distributed power source that combines solar cells and storage batteries is effective from the perspective of strengthening energy resilience because it is possible to supply power even during a power outage. Here, energy resilience refers to the ability to stably supply the necessary energy to society, including consumers, in peacetime, and to have the ability to stop and restore energy supplies in both hard and soft aspects in the event of an emergency, such as when a natural or man-made disaster disrupts the energy supply, in order to reduce the impact of such disaster on human life, assets, economic activity, and society. (Definition based on the "Energy Resilience Principles" agreed upon by APEC in April 2020.) In the technology disclosed in Patent Document 1, in order to maintain power supply to loads (especially important loads) for long periods of time, including during bad weather and at night, when a power outage occurs, it is necessary to increase the capacity of the storage battery. However, increasing the capacity of the storage battery requires high initial investment, which has hindered the introduction of the system, and the development of new technology has been desired.
[0005] The present invention has been made in consideration of the above-mentioned problems, and its purpose is to provide a power supply system and a control method thereof that is capable of supplying a specified amount of power to consumers with a relatively economical configuration during peacetime, and that can extend the period of time during which stable power supply can be maintained even in the event of a power outage in an emergency. [Means for solving the problem]
[0006] The characteristic configuration of the power supply system to achieve the above object is as follows: a solar cell, a storage battery, a cogeneration system, and a power control unit that controls power supply to a load using the solar cell, the storage battery, and the cogeneration system; a connection switching unit that can switch a connection path between the solar cell and the storage battery and the load to either a path via a commercial connection path that brings the solar cell and the storage battery into a commercial power connection state in which they are connected to each other and to a commercial power system, or a path via an independent connection path that brings the solar cell and the storage battery into an independent connection state in which they are connected to each other and are electrically disconnected from the commercial power system, When the power control unit detects a power outage in the commercial power system, A first connection switching control is executed to switch the commercial power connection state to the independent connection state by the connection switching unit and to interconnect the heat and power cogeneration apparatus using the independent connection path as a bus line; The point is that when the average power generation value, which is the average value of the power generation by the solar cell over a specified period up to the present time, is less than the power consumption of the load, and the amount of stored power in the storage battery becomes less than or equal to a charging start threshold, which is a predetermined threshold for starting charging, power supply from the heat and power supply device is executed.
[0007] According to the above characteristic configuration, when a power outage in the commercial power system is detected, the connection switching unit switches the connection state from a commercial power connection state to an independent connection state, and executes a first connection switching control to interconnect the heat and power cogeneration system using the independent connection path as a bus line, thereby enabling the load to be supplied with power from the solar cell and the storage battery, and also from the heat and power cogeneration system. Furthermore, when the average power generation value, which is the average power generation value of the solar cell over a predetermined period up to the present time, is less than the power consumption of the load, the amount of stored power in the storage battery is likely to be consumed, and the amount of stored power in the storage battery is equal to or less than a predetermined threshold for starting charging, the cogeneration system is started to enable power supply, so that when the amount of stored power in the storage battery is likely to be consumed and the amount of stored power in the storage battery is relatively low, the power generated by the cogeneration system can be supplied to the storage battery. This makes it possible to actively maintain the amount of stored power in the storage battery and actively maintain an independent connection state in which the solar cell and the storage battery are independently connected to the load and can supply power. As a result, for example, if there is no power generated by the solar cells and the amount of power stored in the storage battery reaches a lower limit (e.g., zero), the independent connection state can no longer be maintained, and as a result, the cogeneration system is disconnected from the grid and switches to independent operation in which the cogeneration system supplies power to the load alone, thereby preventing the occurrence of a situation in which the cogeneration system alone supplies power to the load. In other words, during a power outage in an emergency, when other natural disasters such as earthquakes have occurred, there is a risk that the fuel supply to the cogeneration system will be cut off. However, with the above-described characteristic configuration, it is possible to maintain good power supply from the cogeneration system to the load and power supply from the solar cell and storage battery to the load, thereby creating a system with enhanced energy resilience. As a result, it is possible to realize a power supply system that can supply a specified amount of energy to consumers in peacetime with a relatively economical configuration equipped with a cogeneration system, and that can extend the time during which stable power supply can be maintained even in the event of a power outage in an emergency.
[0008] Further characteristic configurations of the power supply system include: When the power control unit detects a power outage in the commercial power system and executes the first connection switching control, and then the amount of stored power in the storage battery becomes equal to or greater than a predetermined charging stop threshold as a threshold for stopping charging, The point is that, regardless of the average power generation value of the solar cells, the power supply from the cogeneration system is stopped while maintaining the independent connection state and maintaining the grid connection using the independent connection path of the cogeneration system as a busbar.
[0009] According to the above characteristic configuration, after detecting a power outage in the commercial power grid and executing the first connection switching control, if the amount of electricity stored in the storage battery becomes equal to or exceeds a predetermined charging stop threshold for stopping charging, the power supply from the cogeneration system is stopped, thereby preventing the system from becoming unstable due to excessive power supply to the autonomous connection path. Furthermore, the power supply from the cogeneration system is stopped while maintaining an independent connection state and while maintaining a grid connection using the independent connection path of the cogeneration system as a busbar. This maintains a state in which the power supply from the cogeneration system to the load can be instantly resumed, thereby achieving control that maintains energy resilience.
[0010] Further characteristic configurations of the power supply system include: When the power control unit detects a power outage in the commercial power grid and executes the first connection switching control, and then detects a stop of power supply via the independent connection path, The second connection switching control is executed to disconnect the interconnection using the independent connection path of the cogeneration system as a busbar, and switch the cogeneration system to independent operation, thereby executing power supply from the cogeneration system to the load.
[0011] As in the above characteristic configuration, when a power outage in the commercial power system is detected and a first connection switching control is executed, and then a stop in the power supply via the independent connection path is detected, a second connection switching control is executed to disconnect the interconnection using the independent connection path of the cogeneration device as the busbar and switch the cogeneration device to independent operation, and power is supplied from the cogeneration device to the load.By this, even if the independent connection state cannot be maintained, the cogeneration device itself operates independently and maintains the power supply to the load, so that the time during which power can be supplied to the load can be extended and a more stable power supply system can be realized.
[0012] A method for controlling a power supply system to achieve the above object includes the steps of: a solar cell, a storage battery, a cogeneration system, and a power control unit that controls power supply to a load using the solar cell, the storage battery, and the cogeneration system; A control method for a power supply system including a connection switching unit that can switch a connection path between the solar cell and the storage battery and the load to either a path via a commercial connection path that brings the solar cell and the storage battery into a commercial power connection state in which the solar cell and the storage battery are connected to each other and to a commercial power system, or a path via an independent connection path that brings the solar cell and the storage battery into an independent connection state in which the solar cell and the storage battery are connected to each other and are electrically disconnected from the commercial power system, When a power outage of the commercial power system is detected, the connection switching unit switches from the commercial power connection state to the independent connection state, and executes a first connection switching control to interconnect the heat and power cogeneration apparatus using the independent connection path as a bus line; The point is that when the average power generation value, which is the average value of the power generation by the solar cell over a specified period up to the present time, is less than the power consumption of the load, and the amount of stored power in the storage battery becomes less than or equal to a charging start threshold, which is a predetermined threshold for starting charging, power supply from the heat and power supply device is executed. [Brief description of the drawings]
[0013] [Figure 1]FIG. 1 is a schematic configuration diagram of a power supply system according to an embodiment, illustrating a state in which power is supplied to a load in a state in which the power supply system is interconnected with a commercial power system. [Diagram 2] FIG. 1 is a schematic diagram of a power supply system according to an embodiment, illustrating a state in which a cogeneration system is interconnected with an independent connection path of a distributed power source including a solar cell and a storage battery as a busbar to supply power to a load. [Diagram 3] FIG. 1 is a schematic configuration diagram of a power supply system according to an embodiment, illustrating a state in which a cogeneration system supplies power to a load through independent operation. [Figure 4] FIG. 4 is a control flow diagram relating to control during a power outage. [Diagram 5] 10A to 10C are graphs showing an example of changes in generated power, consumed power, and the amount of stored power in a storage battery when control is being executed in the power supply system according to the embodiment in the event of a power outage. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0014] The power supply system and control method according to an embodiment of the present invention are capable of supplying a specified amount of power to consumers in a relatively economical configuration during peacetime, and are also capable of extending the period of time during which stable power supply can be maintained even in the event of a power outage during an emergency. Hereinafter, a power supply system 100 according to an embodiment and a control method thereof will be described with reference to FIGS.
[0015] The power supply system 100 includes a solar cell PV, a storage battery SB, a heat and power cogeneration system CG, a power conversion unit PC (an example of a power control unit) that controls the power supply from the solar cell PV and the storage battery SB to an important load IR (an example of a load), a first power generation control unit CG1 (an example of a power control unit) that controls the power supply from the heat and power cogeneration system CG to the important load IR, and a first connection switching unit SW1 and a second connection switching unit SW2 as connection switching units. The power conversion unit PC and the first power generation control unit CG1 are configured to be able to communicate with each other via wire or wirelessly.
[0016] The power conversion unit PC is configured as a so-called power conditioner, and includes a second power generation control unit PC1 that controls charging of the power generated by the solar cell PV to the storage battery SB, and controls output of the power generated by the solar cell PV or the power charged (stored) in the storage battery SB to the outside. The storage battery SB is configured of a secondary battery such as a lithium ion battery.
[0017] Furthermore, the power conversion unit PC includes an interconnection output unit PC2 that outputs power via a commercial connection path L1 that is connected to a fifth connection path L5 from the commercial power system K, and an independent output unit PC3 that independently outputs power via the independent connection path L2 by maintaining the voltage, frequency, and phase of the power at predetermined values. In addition, the independent output unit PC3 has the function of a bidirectional inverter and is capable of supplying power from the power conversion unit PC to the important load IR via the independent connection path L2, and is configured to be able to charge the power generated by the heat and power cogeneration system CG to the storage battery SB via the independent connection path L2.
[0018] The commercial connection path L1 and the independent connection path L2 are connected to the power supply path L3 in a form that is selectively switched and connected by a first connection switch unit SW1. That is, the first connection switching unit SW1 switches the connection path between the solar cell PV and the storage battery SB and the important load IR to either a path via a commercial connection path L1 that sets the solar cell PV and the storage battery SB in a commercial power connection state (the connection state shown in Figure 1) in which the solar cell PV and the storage battery SB are connected to each other and to the commercial power system K, or a path via an independent connection path L2 that sets the solar cell PV and the storage battery SB in an independent connection state (the connection state shown in Figure 2) in which the solar cell PV and the storage battery SB are connected to each other and are electrically disconnected from the commercial power system K. Incidentally, as will be described in detail later, the power supply path L3 is connected, in the order listed, to the first connection switching unit SW1 side, with a fourth connection path L4 to which an important load IR is connected and a sixth connection path L6 to which a cogeneration system CG is connected.
[0019] The second power generation control unit PC1 is transmitted the measurement result of a voltage measurement unit S1 that measures the voltage of the power of a fifth connection path L5 connected to the commercial power system K, and the measurement result of a first current measurement unit S2 that measures the current of the power of the fifth connection path L5.
[0020] The voltage measurement unit S1 is configured using, for example, a potential transformer used to measure the voltage value of power. The second power generation control unit PC1 of the power conversion unit PC refers to the measurement result of the voltage measurement unit S1 and judges whether the state is a normal power supply state in which power is being supplied normally from the commercial power system K, or a power outage state in which power is not being supplied normally from the commercial power system K. For example, if the voltage value transmitted from the voltage measurement unit S1 is equal to or greater than a predetermined value, the second power generation control unit PC1 judges that the state is a normal power supply state in which power is being supplied normally from the commercial power system K, and if the voltage value transmitted from the voltage measurement unit S1 is less than the predetermined value, it judges that the state is a power outage state in which power is not being supplied normally from the commercial power system K.
[0021] The first current measurement unit S2 is configured using, for example, a current transformer (instrument current transformer) used to detect the current value of power. The second power generation control unit PC1 of the power conversion unit PC measures the power flowing from the fifth connection path L5 to the commercial connection path L1 with reference to the measurement result of the first current measurement unit S2. The second power generation control unit PC1 can derive the power value from the product of the current value transmitted from the first current measurement unit S2 and the measurement result of the voltage measurement unit S1 or a predetermined voltage value (for example, 100V, 200V, etc.).
[0022] In a normal power supply state where power is normally supplied from the commercial power system K, the second power generation control unit PC1 of the power conversion unit PC switches the first connection switching unit SW1 to a commercial power connection state where the commercial connection path L1 is connected to the power supply path L3, and supplies power via the grid-connected output unit PC2 of the power conversion unit PC. On the other hand, in a power outage state where power is not normally supplied from the commercial power system K, the second power generation control unit PC1 switches the first connection switching unit SW1 to an independent connection state where the independent connection path L2 is connected to the power supply path L3, and supplies power via the independent output unit PC3 of the power conversion unit PC or charges the storage battery SB. In addition, although not shown in the figure, the second power generation control unit PC1 is capable of detecting the power consumption of the important load IR by integrating the current flowing through the fourth connection path L4 and a predetermined voltage value (e.g., 100V, 200V, etc.).
[0023] The cogeneration system CG is configured using, for example, a device including an engine and a generator driven by the engine, and is configured to include a first power generation control unit CG1 that converts the power generated by itself into power of a desired voltage, frequency, and phase, a grid-connected output unit CG2 that outputs the generated power in a form connected to the power supplied to the power supply path L3, an independent output unit CG3 that independently outputs the power by maintaining the voltage, frequency, and phase of the power at a predetermined value, and a second connection switching unit SW2 that selectively connects the sixth connection path L6 to either the grid-connected output unit CG2 or the independent output unit CG3. The heat generated by the cogeneration system CG is supplied to a heat utilization unit (not shown).
[0024] The heat and power cogeneration system CG receives the measurement results of a second current measuring unit S3 that measures the current of the power between the connection point between the power supply path L3 and the fourth connection path L4 and the first connection switching unit SW1 in the power supply path L3.
[0025] The second current measuring unit S3 is configured using, for example, a current transformer (instrument current transformer) used to detect the current value of electric power. The first power generation control unit CG1 of the cogeneration system CG can measure (derive) the electric power flowing from the first connection switching unit SW1 to the connection portion of the electric power supply path L3 and the fourth connection path L4 by referring to the measurement result of the second current measuring unit S3. For example, the first power generation control unit CG1 can derive the electric power value from the product of the current value transmitted from the second current measuring unit S3 and a predetermined voltage value (for example, 100V, 200V, etc.). Furthermore, the first power generation control unit CG1 is configured to be able to determine between a normal power supply state in which power is being supplied normally from the commercial power system K or a power supply state in which power is being supplied from the independent output unit PC3 of the power conversion unit PC, and a power outage state in which power is not being supplied from both the commercial power system K and the power conversion unit PC.
[0026] When the first power generation control unit CG1 is in a normal power supply state in which power is being supplied normally from the commercial power system K or in a power supply state in which power is being supplied from the independent output unit PC3 of the power conversion unit PC, it connects the grid-connected output unit CG2 and the sixth connection path L6 via the second connection switching unit SW2 and controls power generation in a form in which the commercial connection path L1 is connected as a bus line, and when the first power generation control unit CG1 is in a power outage state in which power is not being supplied from both the commercial power system K and the power conversion unit PC, it connects the independent output unit CG3 and the sixth connection path L6 via the second connection switching unit SW2 and controls power generation in a form in which the voltage, frequency, and phase of the power are maintained at predetermined values and power is output independently. In addition, when the first power generation control unit CG1 is in a normal power supply state in which power is being supplied normally from the commercial power system K, it refers to the measurement results of the second current measuring unit S3 and controls the generated power supplied from the cogeneration unit CG so as to prevent reverse power flow from the cogeneration unit CG to the first connection switching unit SW1.
[0027] Now, the power supply system 100 according to this embodiment is capable of supplying a specified amount of power to consumers in a relatively economical configuration during peacetime, and also performs the following control in order to extend the time during which stable power supply can be maintained even in the event of a power outage in an emergency. When the second power generation control unit PC1 detects a power outage in the commercial power system K, the first connection switching unit SW1 switches from a commercial power connection state to an independent connection state (switching from the connection state shown in Figure 1 to the connection state shown in Figure 2), and the first power generation control unit CG1 executes the first connection switching control in a form in which the cogeneration device CG is interconnected using the independent connection path L2 as a bus, and when the average generated power, which is the average value of the generated power of the solar cell PV for a predetermined period up to the present time (for example, a period of 30 seconds or more and 60 seconds or less), is less than the power consumption of the important load IR and the amount of stored power in the storage battery SB becomes less than a predetermined charging start threshold (for example, 50% of the maximum storage capacity) which is a threshold for starting charging.
[0028] Here, after the first connection switching control, the second power generation control unit PC1 controls so that the generated power for maintaining the independent connection state (for example, if the rated generated power of the heat and power combined supply unit CG and the generated power of the power conversion unit PC are about 5 kW, then the generated power is about 250 W or more and 500 W or less, and preferably about 200 W) is supplied from the power conversion unit PC to the important load IR via the independent connection path L2, and the first power generation control unit CG1 controls so as to operate the heat and power combined supply unit CG at the rated output.
[0029] Furthermore, after detecting a power outage in the commercial power system K and executing the first connection switching control, if the amount of stored power in the storage battery SB becomes equal to or exceeds a predetermined charging stop threshold (e.g., 90% of the maximum storage capacity) as a threshold for stopping charging, the first power generation control unit CG1 and the second power generation control unit PC1 maintain the independent connection state (state shown in Figure 2) via the independent connection path L2 regardless of the average power generation value of the solar cell PV, and stop the power supply from the cogeneration unit CG while maintaining the interconnection connection with the independent connection path L2 of the cogeneration unit CG as a bus (putting the cogeneration unit CG in an idling state).
[0030] In addition, when the first power generation control unit CG1 and the second power generation control unit PC1 detect a power outage in the commercial power system K and execute the first connection switching control, and then detect a stop in the power supply from the power conversion unit PC via the independent connection path L2, they execute a second connection switching control to disconnect the cogeneration device CG, which uses the independent connection path L2 as a bus, and switch the cogeneration device CG to independent operation, and connect the independent output unit CG3 and the sixth connection path L6 by the second connection switching unit SW2 (as the connection state shown in Figure 3), and supply power from the cogeneration device CG to the important load IR. In the power supply system 100 according to this embodiment, the above-described control realizes a system that can prolong the time during which stable power supply can be achieved even in the event of a power outage in an emergency.
[0031] Next, control during a power outage in the power supply system 100 according to this embodiment will be described based on the control flow shown in FIG. When the second power generation control unit PC1 detects a power outage in the commercial power system K (Yes in #01), the second power generation control unit PC1 switches from the commercial power connection state to the independent connection state using the first connection switching unit SW1 (switching from the connection state shown in Figure 1 to the connection state shown in Figure 2), and the first power generation control unit CG1 executes the first connection switching control in a form in which the cogeneration unit CG is interconnected with the independent connection path L2 as a bus (#02). On the other hand, if the second power generation control unit PC1 does not detect a power outage in the commercial power system K (No in #01), it continues to detect a power outage in the commercial power system K (continuously performs the determination in #01).
[0032] If the average power generation power Ppv, which is the average power generation power of the solar cell PV over a specified period up to the present time, is less than the power consumption Pld of the important load IR and the stored power Qb of the storage battery SB is less than a predetermined threshold Qlow (e.g., 50% of the maximum storage capacity) for starting charging (Yes in #03), the second power generation control unit PC1 operates the cogeneration system CG at rated power and supplies power from the cogeneration system CG (#04). On the other hand, if the average power generation power Ppv, which is the average power generation power of the solar cell PV over a specified period up to the present time, is equal to or greater than the power consumption Pld of the important load IR, or if the amount of stored power Qb of the storage battery SB exceeds a predetermined threshold value Qlow (for example, 50% of the maximum storage capacity) for starting charging (No in #03), the second power generation control unit PC1 will not supply power from the cogeneration system CG (sets the cogeneration system CG to an idling state).
[0033] Next, when the amount of stored power in the storage battery SB becomes equal to or greater than a predetermined charging stop threshold (for example, 90% of the maximum storage capacity) as a threshold for stopping charging (Yes in #05), regardless of the average power generation value of the solar cell PV, the first power generation control unit CG1 and the second power generation control unit PC1 stop the power supply from the cogeneration unit CG (put the cogeneration unit CG in an idle state) while maintaining the independent connection state (the state shown in Figure 2) via the independent connection path L2 and maintaining the interconnection with the independent connection path L2 of the cogeneration unit CG as a busbar (#06). On the other hand, if the amount of stored electricity in the storage battery SB is less than a predetermined charging stop threshold (e.g., 90% of the maximum storage capacity) as a threshold for stopping charging (No in #05), the current power supply state of the cogeneration system CG is maintained.
[0034] Furthermore, when the first power generation control unit CG1 and the second power generation control unit PC1 detect a stop in the power supply via the independent connection path L2 by the power conversion unit PC (Yes in #07), they execute a second connection switching control to disconnect the cogeneration unit CG, which uses the independent connection path L2 as a bus, and switch the cogeneration unit CG to independent operation, and connect the independent output unit CG3 and the sixth connection path L6 by the second connection switching unit SW2 (as the connection state shown in Figure 3), thereby supplying power from the cogeneration unit CG to the important load IR (#08). On the other hand, if the first power generation control unit CG1 and the second power generation control unit PC1 do not detect a stop of the power supply from the power conversion unit PC via the independent connection path L2 (No in #07), they return to before step #3.
[0035] Next, if the first power generation control unit CG1 and the second power generation control unit PC1 detect the restoration of power supply via the autonomous connection path L2 by the power conversion unit PC (Yes in #09), they return to before step #3, and if they do not detect the restoration of power supply via the autonomous connection path L2 by the power conversion unit PC (No in #09), they return to before step #08 and maintain the power supply to the critical load IR by the combined heat and power supply unit CG.
[0036] Although not shown in the control flow, when the power outage of the commercial power system K is restored, the power outage control ends.
[0037] Next, as shown in the graph of Figure 5, when the solar cell PV is generating power according to the sunlight conditions and the important load IR is consuming a predetermined amount of power, an example of the flow of various events when the above-mentioned power outage control is being executed when a power outage occurs at time t1 is shown. The power consumption of the important load IR is 5.0kW or 10.0kW during the day (6:00-18:00) and 2.5kW or 10.0kW at night (18:00-6:00), and the power generated by the cogeneration system CG is switched between the rated output (5.0kW) and the idling state (0kW). The independent output from the power conversion unit PC is at least 200W or more to maintain an independent connection state, but is not shown in the graph of FIG. 5.
[0038] When a power outage of the commercial power system K is detected at time t1, the first connection switching control is executed. At this time, the power generation average value Ppv, which is the average value of the power generation power of the solar cell PV for a predetermined period up to the present time, is less than the power consumption Pld of the important load IR, and the amount of stored power Qb of the storage battery SB is less than the charge start threshold value Qlow (for example, 50% of the maximum storage capacity) as a predetermined threshold value for starting charging (to satisfy the condition of step #03 described above), so that the cogeneration system CG starts supplying power to the important load IR. At time t2, the power consumption of the important load IR increases to 7.5 kW, but the power generation of the solar cell PV also starts to increase, so the amount of power stored in the storage battery SB increases. However, since the amount of stored electricity in the storage battery SB is less than a predetermined charging stop threshold (e.g., 90% of the maximum storage capacity) which is a threshold for stopping charging (because the condition of step #05 described above is not satisfied), the current power supply state of the heat and power supply unit CG is maintained. Next, at time t3, the amount of stored power in the storage battery SB becomes equal to or greater than a predetermined charging stop threshold (e.g., 90% of the maximum storage capacity) as a threshold for stopping charging (to satisfy the condition of step #05 described above), so that, regardless of the average power generation value of the solar cell PV, the independent connection state (state shown in Figure 2) via the independent connection path L2 is maintained and the power supply from the cogeneration unit CG is stopped while maintaining the interconnection with the independent connection path L2 of the cogeneration unit CG as a busbar. Furthermore, by the time t4, the amount of sunlight on the solar cell PV decreases and the amount of electricity stored in the storage battery SB decreases, and at time t4, the condition of the above-mentioned step #03 is satisfied, i.e., the average power generation power Ppv, which is the average power generation power of the solar cell PV over a specified period up to the present time, is less than the power consumption Pld of the important load IR, and the amount of electricity stored in the storage battery SB becomes less than the charge start threshold Qlow (for example, 50% of the maximum storage capacity), which is a predetermined threshold for starting charging, and then the cogeneration device CG starts supplying power to the important load IR.
[0039] [Another embodiment] (1) In the above embodiment, an example was shown in which the combined heat and power supply system CG was configured using a device including an engine and a generator driven by the engine, but it may also be configured as a device including a fuel cell.
[0040] (2) In step #04 of the control flow in the above embodiment, a configuration example is shown in which the cogeneration system CG operates at its rated power. However, this does not necessarily have to be the rated power, and a configuration in which it operates at a specified output less than the rated output may also be adopted.
[0041] Furthermore, the configurations disclosed in the above embodiments (including other embodiments, the same applies below) can be applied in combination with configurations disclosed in other embodiments, provided that no contradiction arises. Furthermore, the embodiments disclosed in this specification are merely examples, and the embodiments of the present invention are not limited thereto, and can be appropriately modified within the scope that does not deviate from the purpose of the present invention. [Industrial Applicability]
[0042] The power supply system and control method of the present invention can be effectively used as a power supply system and control method that can supply a specified amount of power to consumers in a relatively economical configuration during peacetime, and can also extend the period of time during which stable power can be supplied even in the event of a power outage in an emergency. [Explanation of symbols]
[0043] 100: Power supply system CG: Combined heat and power generation equipment CG1: First power generation control unit IR: Important load K: Commercial power system L1: Commercial connection route L2: Self-supporting connection path PC1: Second power generation control unit PV: solar cell Pld: Power consumption Ppv: Average power generation value Qb: Charge amount Qlow: Charging start threshold SB:Storage battery SW1: First connection switch SW2: Second connection switch
Claims
1. a solar cell, a storage battery, a cogeneration system, and a power control unit that controls power supply to a load using the solar cell, the storage battery, and the cogeneration system; a connection switching unit that can switch a connection path between the solar cell and the storage battery and the load to either a path via a commercial connection path that brings the solar cell and the storage battery into a commercial power connection state in which they are connected to each other and to a commercial power system, or a path via an independent connection path that brings the solar cell and the storage battery into an independent connection state in which they are connected to each other and are electrically disconnected from the commercial power system, When the power control unit detects a power outage in the commercial power system, A first connection switching control is executed to switch from the commercial power connection state to the independent connection state by the connection switching unit and to interconnect the heat and power cogeneration apparatus using the independent connection path as a bus line; A power supply system that supplies power from the cogeneration device when an average power generation value, which is the average value of the power generated by the solar cell over a specified period up to the present time, is less than the power consumption of the load and the amount of stored power in the storage battery is less than a predetermined threshold for starting charging.
2. When the power control unit detects a power outage in the commercial power system and executes the first connection switching control, if the amount of stored power in the storage battery becomes equal to or greater than a predetermined charging stop threshold as a threshold for stopping charging, The power supply system of claim 1, wherein the power supply from the cogeneration system is stopped while maintaining the independent connection state and the interconnection using the independent connection path of the cogeneration system as a bus bar, regardless of the average power generation value of the solar cells.
3. When the power control unit detects a power outage in the commercial power system and executes the first connection switching control, and then detects a stop of power supply via the independent connection path, The power supply system according to claim 1 or 2, wherein a second connection switching control is executed to disconnect the interconnection using the independent connection path of the cogeneration device as a busbar, and switch the cogeneration device to independent operation, thereby executing power supply from the cogeneration device to the load.
4. a solar cell, a storage battery, a cogeneration system, and a power control unit that controls power supply to a load using the solar cell, the storage battery, and the cogeneration system; A control method for a power supply system including a connection switching unit that can switch a connection path between the solar cell and the storage battery and the load to either a path via a commercial connection path that brings the solar cell and the storage battery into a commercial power connection state in which the solar cell and the storage battery are connected to each other and to a commercial power system, or a path via an independent connection path that brings the solar cell and the storage battery into an independent connection state in which the solar cell and the storage battery are connected to each other and are electrically disconnected from the commercial power system, When a power outage of the commercial power system is detected, the connection switching unit switches from the commercial power connection state to the independent connection state, and executes a first connection switching control to interconnect the heat and power cogeneration apparatus using the independent connection path as a bus line; A control method for executing power supply from the cogeneration system when an average power generation value, which is the average value of the power generation power of the solar cell over a specified period up to the present time, is less than the power consumption of the load, and the amount of stored electricity in the storage battery becomes less than a predetermined threshold for starting charging.
Citation Information
Patent Citations
Energy management apparatus, and energy management method
JP2015149861A
Power controller, power control method and fuel cell system
JP2017117673A
Power supply system
JP2020058102A
Power supply system
JP2021040433A