Schedule preparation program generation method, schedule preparation program generation device, schedule preparation device, recording medium, generation program, schedule preparation program, substrate processing device, and substrate processing system

The use of reinforcement learning to generate schedule creation programs for substrate processing equipment addresses the challenge of varying device configurations, reducing developer burden and optimizing processing time for substrate processing.

JP2024138715APending Publication Date: 2024-10-09SCREEN HOLDINGS CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
JP2023049347
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-27
Publication Date
2024-10-09

AI Technical Summary

Technical Problem

Developers face the burden of having to create a unique processing flow for each model of substrate processing equipment due to varying device configurations, necessitating extensive manual effort in creating time schedules.

Method used

A schedule creation program generation method utilizing reinforcement learning to automatically generate time schedules for multiple components of a substrate processing apparatus, adjusting reward functions to optimize the time length of the schedule through reinforcement learning processes.

Benefits of technology

Reduces the developer's burden by generating efficient time schedules that minimize processing time for a predetermined number of substrates, improving learning efficiency and reducing the time required to complete substrate processing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024138715000001_ABST
    Figure 2024138715000001_ABST
Patent Text Reader

Abstract

To provide a schedule preparation program generation method which can reduce burdens on a developer.SOLUTION: A schedule preparation program generation method generates a schedule preparation program PL2 for preparing a time schedule of a plurality of components included in a substrate processing device WP by reinforcement learning. The method includes: a steps of increasing a value of a reward by repeating an experience step including an arrangement step (S11) and a reward determination step (S12) by the reinforcement learning; and a change step (S14) of changing a reward function for regulating a relation between time length of the time schedule and the value of the reward. The arrangement step (S11) shows a step of sequentially arranging a plurality of planning elements BL preliminarily given to each of substrates W in a time table TB. The reward determination step (S12) shows a step of determining the value of the reward on the basis of the reward function. The change step (S14) includes a step of changing the reward function so that an inclination in a part of sections TS becomes larger than before change.SELECTED DRAWING: Figure 8
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a schedule creation program generating method, a schedule creation program generating device, a schedule creation device, a recording medium, a generating program, a schedule creation program, a substrate processing apparatus, and a substrate processing system. [Background technology]

[0002] A schedule creation method for a substrate processing apparatus is known (see, for example, Patent Document 1). The schedule creation method for a substrate processing apparatus is a method for creating a time schedule for each component of the substrate processing apparatus. According to the schedule creation method for a substrate processing apparatus, a time schedule can be created so that the substrate processing apparatus can efficiently process substrates on a substrate-by-substrate basis (single substrate) or on a lot-by-lot basis (for example, 25 substrates). The schedule creation method of Patent Document 1 is applied to a batch-type substrate processing apparatus. Specifically, the schedule creation method of Patent Document 1 creates a time schedule for each component of the substrate processing apparatus on a lot-by-lot basis.

[0003] The schedule creation method for the substrate processing apparatus is implemented by a control unit including a CPU (Central Processing Unit) and a counter / timer, etc., executing a computer program. Therefore, the developer of the schedule creation method develops a process flow to be executed by the processor. Specifically, the developer determines rules (constraints) in consideration of the configuration of the substrate processing apparatus, and develops a process flow to be executed by the processor so that a time schedule reflecting the determined rules can be created. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2009-48320 A Summary of the Invention [Problem to be solved by the invention]

[0005] However, when developing a process flow to be executed by a processor so that rules (constraints) are determined in consideration of the configuration of the substrate processing apparatus and a time schedule reflecting the determined rules is created, the developer must develop the entire flow for each model because the configuration of the apparatus differs for each model. Therefore, taking into consideration the burden on the developer, there is room for further improvement.

[0006] The present invention has been made in consideration of the above-mentioned problems, and an object of the present invention is to provide a schedule creation program generation method, a schedule creation program generation device, a schedule creation device, a recording medium, a generation program, a schedule creation program, a substrate processing apparatus, and a substrate processing system that can reduce the burden on developers. [Means for solving the problem]

[0007] According to one aspect of the present invention, a method for generating a schedule creation program generates a schedule creation program for creating a time schedule for a plurality of components included in a substrate processing apparatus by reinforcement learning. The plurality of components are occupied by the substrates when processing a plurality of substrates. The method for generating a schedule creation program includes a step of repeating an experience step including a placement step and a reward determination step by the reinforcement learning to increase a value of a reward, and a modification step of modifying a reward function that defines a relationship between a time length of the time schedule and a value of the reward. The placement step indicates a step of sequentially placing a plurality of planning elements previously given to each of the substrates in a time table for defining the time schedule, thereby sequentially changing a state of the time table. The reward determination step indicates a step of determining a value of the reward based on the reward function and a final state of the time table in which all the planning elements are placed. The time schedule corresponds to the final state of the time table. The modification step includes a step of modifying the reward function so that a gradient in a part of a time range from a time length of the time schedule corresponding to a maximum value of the reward to a time length of the time schedule corresponding to a minimum value of the reward becomes larger than before the modification.

[0008] In one embodiment, the changing step includes changing the reward function to one whose gradient in a portion of the time range is greater than the gradient when the entire time range is defined by a linear function.

[0009] In one embodiment, the schedule creation program generation method includes a plurality of the changing steps. Each time the changing step is performed, the reward function is changed so that a gradient in a portion of the time range is larger than a gradient at a current stage.

[0010] In one embodiment, the changing step further includes the step of shifting the portion of the section.

[0011] In one embodiment, the multiple components include multiple substrate processing units and a transport unit. Each of the substrate processing units processes the substrate. The transport unit transports the substrate. The multiple plan elements include a first plan element and a second plan element. The first plan element indicates a plan for transporting the substrate to one of the substrate processing units by the transport unit and processing the substrate by one of the substrate processing units. The second plan element indicates a plan for transporting the substrate, after being processed by the substrate processing unit, from the substrate processing unit by the transport unit.

[0012] In one embodiment, the first planning element has a longer duration than the second planning element.

[0013] In one embodiment, the plurality of plan elements include plan elements corresponding to each of the substrate processing units, and in the arranging step, one of the plan elements corresponding to each of the substrate processing units is selected.

[0014] According to one aspect of the present invention, a schedule creation program generation device generates a schedule creation program for creating a time schedule for a plurality of components included in a substrate processing apparatus by reinforcement learning. The schedule creation program generation device includes a storage unit and a processing unit. The storage unit stores a generation program that defines the schedule creation program generation method. The processing unit executes the generation program to generate the schedule creation program.

[0015] According to one aspect of the present invention, a schedule creation device creates a time schedule for a plurality of components included in a substrate processing apparatus. The schedule creation device includes a storage unit and a processing unit. The storage unit stores a schedule creation program generated based on the schedule creation program generation method. The processing unit executes the schedule creation program to create the time schedule.

[0016] According to one aspect of the present invention, a recording medium is a computer-readable recording medium having recorded thereon a generation program that defines the schedule creation program generation method.

[0017] According to another aspect of the present invention, a recording medium is a computer-readable recording medium, which records a schedule creating program generated based on the above-described schedule creating program generating method.

[0018] According to one aspect of the present invention, a generating program is executable by a computer, the generating program defining the above-mentioned schedule creation program generating method.

[0019] According to one aspect of the present invention, a schedule creation program executable by a computer is generated based on the schedule creation program generation method described above.

[0020] According to one aspect of the present invention, a substrate processing apparatus includes a plurality of components, a storage unit, and a processing unit. The plurality of components are occupied by a plurality of substrates when processing the substrates. The storage unit stores a generation program that defines the schedule creation program generation method. The processing unit executes the generation program to generate a schedule creation program for creating a time schedule for the plurality of components. The processing unit executes the schedule creation program to create the time schedule.

[0021] According to another aspect of the present invention, a substrate processing apparatus includes a plurality of components, a storage unit, and a processing unit. The components are occupied by a plurality of substrates when processing the substrates. The storage unit stores a schedule creation program generated based on the schedule creation program generation method. The processing unit executes the schedule creation program to create a time schedule for the plurality of components.

[0022] According to one aspect of the present invention, a substrate processing system includes a substrate processing apparatus and the schedule creation program generating device. The schedule creation program generating device further includes a transmission unit that transmits the schedule creation program to the substrate processing apparatus. The substrate processing apparatus includes a plurality of components, a receiving unit, and a processing unit. The plurality of components are occupied by the substrates when processing a plurality of substrates. The receiving unit receives the schedule creation program transmitted from the transmission unit of the schedule creation program generating device. The processing unit executes the schedule creation program to generate a time schedule for the plurality of components.

[0023] According to another aspect of the present invention, a substrate processing system includes a substrate processing apparatus and the schedule creation device described above. The schedule creation device further includes a transmission unit that transmits the time schedule to the substrate processing apparatus. The substrate processing apparatus includes a plurality of components and a receiving unit. The plurality of components are occupied by the substrates when processing a plurality of substrates. The receiving unit receives the time schedule transmitted from the transmission unit of the schedule creation device. Effect of the Invention

[0024] The schedule creation program generating method, schedule creation program generating device, schedule creation device, recording medium, generating program, schedule creation program, substrate processing apparatus, and substrate processing system according to the present invention can reduce the burden on developers. [Brief description of the drawings]

[0025] [Figure 1] 1(a) and 1(b) are diagrams illustrating a schedule creation program generation system including a schedule creation program generation device according to a first embodiment of the present invention. [Diagram 2] 1 is a diagram showing an example of a substrate processing apparatus to which a schedule creation program according to a first embodiment of the present invention is applied; [Diagram 3] FIG. 11 is a diagram showing an example of a processing procedure, a processing time, and a planning element. [Figure 4] FIG. 4 is a diagram showing details of a second plan element shown in FIG. 3. [Diagram 5] 3 is a diagram showing an example of a time table corresponding to the substrate processing apparatus shown in FIG. 2. FIG. [Figure 6] FIG. 11 is a diagram showing an example of a processing flow for creating a time schedule. [Figure 7] FIG. 1 is a block diagram illustrating a reinforcement learning system. [Figure 8] 3 is a flowchart showing a schedule creation program generating method according to the first embodiment of the present invention. [Figure 9] 13 is a flowchart showing a time schedule creating process. [Figure 10] 13 is a flow chart showing a process for randomly selecting one of the actions to place a plan element in a timetable. [Figure 11] 13 is a flow chart showing a process for arranging plan elements in a timetable by predicting which action will maximize rewards. [Figure 12] 13A is a flowchart showing a first change process included in the change process, and FIG.13B is a flowchart showing a second change process included in the change process. [Figure 13] FIG. 11 illustrates an example of a first change process. [Figure 14] FIG. 11 is a diagram illustrating another example of the first change process. [Figure 15] FIG. 11 illustrates an example of a second change process. [Figure 16] FIG. 11 illustrates another example of the change process. [Figure 17] 1 is a diagram showing a substrate processing system including a substrate processing apparatus according to a first embodiment of the present invention. [Figure 18] FIG. 11 is a diagram showing a substrate processing system including a substrate processing apparatus according to a second embodiment of the present invention. [Figure 19] FIG. 13 is a diagram showing a substrate processing system according to a third embodiment of the present invention. [Figure 20]FIG. 13 is a diagram showing a substrate processing system according to a fourth embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0026] Hereinafter, with reference to the drawings (FIGS. 1 to 20), embodiments of the schedule creation program generating method, schedule creation program generating device, schedule creation device, recording medium, generation program, schedule creation program, substrate processing apparatus, and substrate processing system of the present invention will be described. However, the present invention is not limited to the following embodiments, and can be embodied in various aspects without departing from the gist of the present invention. Note that where explanations are repeated, explanations may be omitted as appropriate. Also, in the drawings, the same or corresponding parts are denoted by the same reference symbols, and explanations will not be repeated.

[0027] The "substrate" in the embodiment of the present invention can be various substrates such as a semiconductor wafer, a glass substrate for a photomask, a glass substrate for a liquid crystal display, a glass substrate for a plasma display, a substrate for an FED (Field Emission Display), a substrate for an optical disk, a substrate for a magnetic disk, and a substrate for a magneto-optical disk. In the following, the embodiment of the present invention will be described mainly using as examples a schedule creation program generation method, a schedule creation program generation device, a schedule creation device, a recording medium, a generation program, a schedule creation program, a substrate processing device, and a substrate processing system used in processing a disc-shaped semiconductor wafer, but the present invention can be similarly applied to the processing of the various substrates exemplified above. In addition, various substrate shapes can be applied.

[0028] [Embodiment 1] Hereinafter, a first embodiment of the present invention will be described with reference to Figs. 1 to 17. Figs. 1(a) and 1(b) are diagrams showing a schedule creation program generation system 100A including a schedule creation program generation device 100 of this embodiment. In detail, Fig. 1(a) shows the schedule creation program generation system 100A before creating a schedule creation program PL2. Fig. 1(b) shows the schedule creation program generation system 100A after creating the schedule creation program PL2.

[0029] As shown in FIG. 1( a ), a schedule creation program generation system 100 A includes a schedule creation program generation device 100 and a recording medium 110 .

[0030] The recording medium 110 is readable by a computer. The recording medium 110 non-temporarily records a program (computer program) to be executed by a computer. The recording medium 110 stores a generation program PL1. The generation program PL1 is a computer program executable by a computer.

[0031] The recording medium 110 may be, for example, a medium including a semiconductor memory such as an SD memory card and a USB (Universal Serial Bus) memory, or a medium including a magnetic disk such as a hard disk drive. Alternatively, the recording medium 110 may be an optical disk such as a CD (Compact Disk), a DVD (Digital Versatile Disk), or a Blu-ray disk. Alternatively, the recording medium 110 may be a main storage device or an auxiliary storage device mounted on another computer system.

[0032] The schedule creation program generation device 100 generates a schedule creation program PL2 for creating a time schedule for a plurality of components included in the substrate processing apparatus WP based on the generation program PL1. More specifically, the generation program PL1 includes a program for reinforcement learning. The schedule creation program generation device 100 generates the schedule creation program PL2 by reinforcement learning. The schedule creation program generation device 100 may be, for example, a general-purpose computer system or a dedicated computer system.

[0033] As shown in FIG. 1( a ), a schedule creation program generation device 100 includes an input unit 101 , a storage unit 102 , an interface unit 103 , a display unit 104 , and a calculation processing unit 105 .

[0034] The interface unit 103 exchanges information, data, or signals with the recording medium 110. Specifically, the interface unit 103 reads out the generation program PL1 from the recording medium 110 and inputs it to the calculation processing unit 105. As a result, the generation program PL1 is installed in the schedule creation program generation device 100. Furthermore, as shown in Fig. 1(b), the interface unit 103 causes the recording medium 110 to carry the schedule creation program PL2.

[0035] For example, the interface unit 103 may be electrically connected to the recording medium 110 to input and output information, data, or signals between the recording medium 110. For example, the interface unit 103 may include a slot and a USB terminal. A card-shaped information carrier such as an SD memory card may be inserted into the slot. For example, a USB memory may be inserted into the USB terminal, or one end of a USB cable electrically connected to a hard disk drive may be inserted into the USB terminal. Alternatively, the interface unit 103 may include an optical disk drive. The optical disk drive reads information (data) from CDs, DVDs, and Blu-ray disks. Also, the optical disk drive writes information (data) to CDs, DVDs, and Blu-ray disks.

[0036] Furthermore, the interface unit 103 may receive the generation program PL1 from another computer system. For example, the interface unit 103 may be communicatively connected to the other computer system via a cable, or may be communicatively connected to the other computer system via a line network such as the Internet.

[0037] The input unit 101 includes a user interface device operated by an operator. The input unit 101 inputs a signal according to an operation by the operator to the arithmetic processing unit 105. The input unit 101 includes, for example, a keyboard and a mouse. The input unit 101 may include a touch sensor superimposed on the display surface of the display unit 104. A graphical user interface may be configured by superimposing the touch sensor on the display surface of the display unit 104.

[0038] The worker can, for example, operate the input unit 101 to instruct the installation of the generation program PL1. The worker can operate the input unit 101 to instruct the start of reinforcement learning. The worker can operate the input unit 101 to set a condition for terminating the reinforcement learning. For example, a threshold value for the number of times the creation (trials) of a time schedule is repeated may be set as a condition for terminating the reinforcement learning. In this case, when the number of times the time schedule is created (the number of trials) reaches the set threshold value, the reinforcement learning is terminated. Hereinafter, the threshold value set as a condition for terminating the reinforcement learning may be referred to as a "first threshold value."

[0039] In this embodiment, one time schedule is created in one step of reinforcement learning. In other words, one episode of reinforcement learning is completed by creating a time schedule. Therefore, the number of times that the creation (trial) of the time schedule is repeated corresponds to the number of times that the step of reinforcement learning is repeated.

[0040] The display unit 104 is controlled by the calculation processing unit 105 to display various screens. Specifically, the display unit 104 may display a learning curve. The learning curve indicates the relationship between the number of steps in reinforcement learning and the reward. The display unit 104 includes a display device such as a liquid crystal display device or an organic EL (electroluminescence) display device.

[0041] The storage unit 102 has a main storage device. The main storage device includes, for example, a semiconductor memory. The storage unit 102 may further include an auxiliary storage device. The auxiliary storage device includes, for example, at least one of a semiconductor memory and a hard disk drive. The storage unit 102 may include a removable medium. The storage unit 102 stores various computer programs and various data. Specifically, the storage unit 102 stores the generation program PL1. The storage unit 102 also stores a condition for ending the reinforcement learning. For example, the storage unit 102 stores a first threshold value set by an operator by operating the input unit 101 as a condition for ending the reinforcement learning.

[0042] As already described, the generation program PL1 includes a program for reinforcement learning. The algorithm of the reinforcement learning is not particularly limited, but may be, for example, an algorithm conforming to Q-learning, the SARSA method, the policy gradient method, the Actor-Critic method, or the Monte Carlo method.

[0043] The neural network of the reinforcement learning may include a neural network that performs deep learning. Specifically, the neural network may include a deep neural network (DNN), a deep Q-network (DQN), a recurrent neural network (RNN), a convolutional neural network (CNN), or a quantum neural network (QNN). For example, the deep neural network includes an input layer, multiple intermediate layers (hidden layers), and an output layer.

[0044] The arithmetic processing unit 105 includes a processor. The arithmetic processing unit 105 may include, for example, a central processing unit (CPU), a micro processing unit (MPU), a graphics processing unit (GPU), a neural network processing unit (NPU), or a quantum computer. Alternatively, the arithmetic processing unit 105 may include a general-purpose processor or a dedicated processor. For example, the arithmetic processing unit 105 may include a field-programmable gate array (FPGA) or an application specific integrated circuit (ASIC).

[0045] The calculation processing unit 105 executes the generating program PL1 stored in the storage unit 102 to generate the schedule creating program PL2. The calculation processing unit 105 causes the recording medium 110 to record the schedule creating program PL2.

[0046] Specifically, in each step of the reinforcement learning, the calculation processing unit 105 creates a time schedule for a plurality of components included in the substrate processing apparatus WP by arranging a plurality of plan elements BL, which will be described with reference to Fig. 3 and Fig. 4, in a time table TB, which will be described with reference to Fig. 5. That is, the calculation processing unit 105 repeats attempts to create a time schedule by reinforcement learning.

[0047] For example, when the calculation processing unit 105 repeatedly attempts to create a time schedule for processing 25 substrates W under the condition that four plan elements BL are placed in the time table TB for each substrate W, the calculation processing unit 105 places 100 plan elements BL in the time table TB in each step of reinforcement learning. Information indicating the time table TB is stored in the storage unit 102. The information indicating the time table TB may be included in the generation program PL1, or may be input by an operator operating the input unit 101.

[0048] In detail, the generation program PL1 includes a reward function that is defined so as to give a higher reward as the time length of the time schedule is shorter. The calculation processing unit 105 refers to the reward function and obtains a reward each time a time schedule is created. The calculation processing unit 105 adjusts the parameters (weighting coefficients) of the neural network so as to maximize the value of the reward in the process of repeating the reinforcement learning steps (trials). In other words, the calculation processing unit 105 adjusts the parameters of the neural network so as to shorten the time length of the time schedule. As a result, the schedule creation program PL2 (trained model) is generated. By creating a time schedule using the schedule creation program PL2 generated in this way, it is possible to create a time schedule that completes the processing of a predetermined number of substrates W in a shorter period of time.

[0049] Next, an example of a substrate processing apparatus WP to which the schedule creation program PL2 of the present embodiment is applied will be described with reference to Fig. 2. Fig. 2 is a diagram showing an example of a substrate processing apparatus WP to which the schedule creation program PL2 of the present embodiment is applied.

[0050] The substrate processing apparatus WP shown in Fig. 2 is a single-wafer processing apparatus that processes one substrate W at a time. The substrate processing apparatus WP shown in Fig. 2 includes four load ports LP, an indexer robot IR, a transfer unit PS, a transport robot CR, and four substrate processing units PU (a first substrate processing unit PU1 to a fourth substrate processing unit PU4).

[0051] A substrate accommodation container CA is docked to each of the load ports LP. Each of the substrate accommodation containers CA accommodates a plurality of substrates W in a stacked state. Specifically, the plurality of substrates W are stacked vertically in the substrate accommodation container CA in a horizontal position with a gap between them. Here, the horizontal position refers to a state in which the thickness direction of the substrates W is aligned with the vertical direction. The substrate accommodation container CA may be, for example, a FOUP (Front Opening Unified Pod), a SMIF (Standard Mechanical Interface) pod, or an OC (Open Cassette).

[0052] The indexer robot IR transports an unprocessed substrate W from the substrate storage container CA to the transfer part PS. The indexer robot IR also transports a processed substrate W from the transfer part PS to the substrate storage container CA. Here, the unprocessed substrate W refers to the substrate W before it is processed by the substrate processing unit PU. The processed substrate W refers to the substrate W after it has been processed by the substrate processing unit PU. The indexer robot IR is an example of a "transport part".

[0053] The indexer robot IR includes two hands (hands 8A, 8B). Each of the hands 8A and 8B holds one substrate W. More specifically, the hand 8A holds an unprocessed substrate W. The hand 8B holds a processed substrate W. Note that the hands 8A and 8B may be arranged so as to overlap one on top of the other, but in FIG. 2, the hands 8A and 8B are shifted in a direction parallel to the paper surface (horizontal direction) for clarity.

[0054] The transfer section PS has multiple shelves that support the substrates W. More specifically, the transfer section PS has at least one shelf that supports an unprocessed substrate W, and at least one shelf that supports a processed substrate W. In this embodiment, the transfer section PS has one shelf that supports an unprocessed substrate W, and one shelf that supports a processed substrate W. Hereinafter, the shelf that supports the unprocessed substrate W may be referred to as "shelf PS1." Furthermore, the shelf that supports the processed substrate W may be referred to as "shelf PS2."

[0055] The transport robot CR transports an unprocessed substrate W from the transfer section PS to one of the substrate processing sections PU. The transport robot CR also transports a processed substrate W from the substrate processing section PU to the transfer section PS. The transport robot CR is an example of a "transport section." Specifically, the transport robot CR includes two hands (hands 13A, 13B). Each of the hands 13A and 13B holds one substrate W. More specifically, the hand 13A holds an unprocessed substrate W. The hand 13B holds a processed substrate W. Note that the hands 13A and 13B may be arranged so as to overlap one another, but in FIG. 2, the hands 13A and 13B are shifted in a direction parallel to the paper surface (horizontal direction) for clarity.

[0056] The substrate processing unit PU processes the substrates W one by one. The substrates W are processed by any of the four substrate processing units PU (first substrate processing unit PU1 to fourth substrate processing unit PU4). The type of processing performed by the substrate processing unit PU is not particularly limited, and for example, the substrate processing unit PU performs a processing using a processing agent (processing liquid or processing gas, or processing liquid and processing gas), a processing using electromagnetic waves such as ultraviolet light, or a physical cleaning processing (brush cleaning or spray nozzle cleaning, etc.) on the substrate W. For example, the substrate processing unit PU may perform any of the substrate processings of chemical cleaning processing, brush cleaning processing, wet etching processing, dry etching processing, photosensitive film coating processing, developing processing, annealing processing, and drawing processing on the substrate W.

[0057] Next, the processing procedure PD, processing time PT, and plan element BL will be described with reference to Fig. 3 and Fig. 4. Fig. 3 is a diagram showing an example of the processing procedure PD, processing time PT, and plan element BL. In detail, Fig. 3 shows the processing procedure PD, processing time PT, and plan element BL corresponding to the substrate processing apparatus WP shown in Fig. 2. Information indicating the processing procedure PD, information indicating the processing time PT, and information indicating the plan element BL are stored in the storage unit 102 in association with each other. All or part of this information may be included in the generation program PL1. All or part of this information may be input by an operator operating the input unit 101.

[0058] The processing procedure PD indicates a procedure of processing performed by the substrate processing apparatus WP, more specifically, the processing procedure PD indicates a procedure of processing performed by a plurality of components included in the substrate processing apparatus WP.

[0059] As shown in Fig. 3, the processing procedure PD corresponding to the substrate processing apparatus WP shown in Fig. 2 includes processing pattern A to processing pattern M. Processing pattern A to processing pattern M are executed in this order for one substrate W. The processing procedure PD shows the flow of processing executed for one substrate W. In a time table TB which will be described with reference to Fig. 5, processing pattern A to processing pattern M are arranged in this order along the time axis of the time table TB.

[0060] Processing pattern A shows a process in which the indexer robot IR takes out an unprocessed substrate W from a substrate storage container CA. Processing pattern B shows a process in which the indexer robot IR transports the unprocessed substrate W to the transfer part PS and then loads the unprocessed substrate W into the transfer part PS. While processing pattern A and processing pattern B are being executed, hand 8A of the indexer robot IR is occupied by one substrate W.

[0061] Processing pattern C indicates a process in which an unprocessed substrate W is carried into the transfer part PS. Processing pattern D indicates a process in which an unprocessed substrate W is carried out from the transfer part PS. While processing pattern C and processing pattern D are being executed, shelf PS1 of the transfer part PS is occupied by one substrate W.

[0062] Processing pattern E shows a process in which the transport robot CR takes out an unprocessed substrate W from the transfer part PS. Processing pattern F shows a process in which the transport robot CR transports an unprocessed substrate W to one of the substrate processing parts PU and takes the unprocessed substrate W into one of the substrate processing parts PU. While processing pattern E and processing pattern F are being executed, the hand 13A of the transport robot CR is occupied by one substrate W.

[0063] The processing pattern G indicates a substrate processing performed by any one of the substrate processing units PU. While the processing pattern G is being performed, any one of the substrate processing units PU is occupied by one substrate W.

[0064] Processing pattern H indicates a process in which the transport robot CR takes out the processed substrate W from the substrate processing unit PU. Processing pattern I indicates a process in which the transport robot CR transports the processed substrate W to the transfer part PS and carries the processed substrate W into the transfer part PS. While processing pattern H and processing pattern I are being executed, the hand 13B of the transport robot CR is occupied by one substrate W.

[0065] Processing pattern J indicates a process in which a processed substrate W is carried into the transfer part PS. Processing pattern K indicates a process in which a processed substrate W is carried out from the transfer part PS. While processing pattern J and processing pattern K are being executed, shelf PS2 of the transfer part PS is occupied by one substrate W.

[0066] Processing pattern L indicates a process in which the indexer robot IR takes out the processed substrate W from the transfer part PS. Processing pattern M indicates a process in which the indexer robot IR transports the processed substrate W to the substrate housing container CA and loads the processed substrate W into the substrate housing container CA. While processing pattern L and processing pattern M are being executed, the hand 8B of the indexer robot IR is occupied by one substrate W.

[0067] As described above with reference to Fig. 3, one substrate W sequentially occupies a plurality of components included in the substrate processing apparatus WP. In this manner, processing patterns A to M indicate occupancy information by one substrate W. In the substrate processing apparatus WP shown in Fig. 2, one substrate W sequentially occupies any one of the hands 8A and 8B of the indexer robot IR, the shelves PS1 and PS2 of the transfer unit PS, the hands 13A and 13B of the transport robot CR, and the substrate processing unit PU. The hands 8A and 8B of the indexer robot IR, the shelves PS1 and PS2 of the transfer unit PS, the hands 13A and 13B of the transport robot CR, and the four substrate processing units PU (first substrate processing unit PU1 to fourth substrate processing unit PU4) are examples of a plurality of components included in the substrate processing apparatus WP.

[0068] Next, the processing time PT will be described. The processing time PT indicates the time length of each process performed by the substrate processing apparatus WP. More specifically, the processing time PT indicates the time length of a process performed by each component included in the substrate processing apparatus WP. In other words, the processing time PT indicates the time length during which each component included in the substrate processing apparatus WP is occupied by one substrate W.

[0069] 3, the processing time PT corresponding to the substrate processing apparatus WP shown in FIG. 2 includes processing time X1 to processing time X13. Processing time X1 to processing time X13 indicate the time lengths of processing pattern A to processing pattern M, respectively. Processing time X1 to processing time X13 are stored in memory unit 102 in association with processing pattern A to processing pattern M, respectively. Of processing time X1 to processing time X13, processing time X1 to processing time X6 and processing time X8 to processing time X13 indicate the time length required for transporting substrate W. Processing time X7 indicates the time length required for substrate processing. The time lengths of processing time X1 to processing time X6 and processing time X8 to processing time X13 are shorter than processing time X7.

[0070] Next, the plan element BL will be explained. As shown in FIG. 3, the processing procedure PD is divided into a plurality of plan elements BL. Each plan element BL includes at least one of the processing patterns included in the processing procedure PD. In the example shown in FIG. 3, processing pattern A to processing pattern M are divided into four plan elements BL (first plan element BL1 to fourth plan element BL4). Each plan element BL indicates a component that is consecutively occupied by a substrate W. The plurality of plan elements BL are given in advance for the processing procedure PD. In other words, a plurality of plan elements BL are given in advance for one substrate W.

[0071] The first plan element BL1 includes processing patterns A to C. That is, the first plan element BL1 indicates a plan for transporting an unprocessed substrate W from a substrate storage container CA to a shelf PS1 of the transfer part PS by the indexer robot IR. The first plan element BL1 also indicates that one substrate W successively occupies the hand 8A of the indexer robot IR and the shelf PS1 of the transfer part PS.

[0072] The second plan element BL2 includes processing patterns D to G. That is, the second plan element BL2 indicates a plan in which an unprocessed substrate W is transported by the transport robot CR from the shelf PS1 of the transfer unit PS to one of the substrate processing units PU, and the unprocessed substrate W is processed by one of the substrate processing units PU. The second plan element BL2 also indicates that one substrate W successively occupies the shelf PS1 of the transfer unit PS, the hand 13A of the transport robot CR, and one of the substrate processing units PU.

[0073] The third plan element BL3 includes processing patterns H to J. That is, the third plan element BL3 indicates a plan for transporting a processed substrate W from the substrate processing unit PU to the shelf PS2 of the transfer unit PS by the transport robot CR. In other words, the third plan element BL3 indicates that one substrate W successively occupies the hand 13B of the transport robot CR and the shelf PS2 of the transfer unit PS.

[0074] The fourth plan element BL4 includes processing patterns K to M. That is, the fourth plan element BL4 indicates a plan for transporting a processed substrate W from the shelf PS2 of the transfer part PS to the substrate accommodation container CA. The fourth plan element BL4 also indicates that one substrate W successively occupies the shelf PS2 of the transfer part PS and the hand 8B of the indexer robot IR.

[0075] 1 arranges a plurality of plan elements BL in a time table TB according to the order of the processing procedures PD. More specifically, the calculation processing unit 105 arranges process patterns A to M in the time table TB for each plan element BL according to the order of the processing procedures PD. By arranging process patterns A to M in the time table TB for each plan element BL, physically impossible actions can be prohibited in the substrate processing apparatus WP.

[0076] Next, the processing procedure PD and the plan element BL will be described with reference to FIG. 4. FIG. 4 is a diagram showing details of the second plan element BL2 shown in FIG. 3. As described with reference to FIG. 2, one substrate W is processed by any one of the first substrate processing unit PU1 to the fourth substrate processing unit PU4. Therefore, as shown in FIG. 4, the second plan element BL2 includes four second plan elements BL2-1 to BL2-4. Therefore, seven plan elements BL are provided in advance for the processing procedure PD (one substrate W). When arranging the second plan element BL2 in the timetable TB, the calculation processing unit 105 shown in FIG. 1 arranges one of the four second plan elements BL2-1 to BL2-4.

[0077] Specifically, the second plan element BL2-1 indicates that a substrate W is processed by the first substrate processing unit PU1. In other words, the second plan element BL2-1 indicates that one substrate W occupies the first substrate processing unit PU1. Similarly, the second plan elements BL2-2 to BL2-4 indicate that a substrate W is processed by the second substrate processing unit PU2 to the fourth substrate processing unit PU4, respectively.

[0078] Next, the constraint conditions will be explained. Table 1 below shows an example of the constraint conditions corresponding to the substrate processing apparatus WP shown in FIG. 2. The constraint conditions indicate the conditions when arranging the plan elements BL in the timetable TB. The constraint conditions depend on the equipment configuration of the substrate processing apparatus WP. For example, the constraint conditions include a condition to prohibit physically impossible actions in the substrate processing apparatus WP. [Table 1]

[0079] 1 places multiple plan elements BL (processing pattern A to processing pattern M) in a time table TB with reference to the constraint conditions. The constraint conditions are stored in the storage unit 102. The constraint conditions may be included in the generation program PL1, or may be input by an operator operating the input unit 101.

[0080] As described above with reference to FIGS. 1 to 4 and Table 1, when arranging multiple plan elements BL on the timetable TB, the calculation processing unit 105 refers to information indicating the processing procedure PD, information indicating the processing time PT, information indicating the plan elements BL, and constraint conditions. Furthermore, when arranging multiple plan elements BL on the timetable TB, the calculation processing unit 105 refers to information indicating the number of substrates W. Hereinafter, the information indicating the number of substrates W may be referred to as "number information." The number information may be included in the generation program PL1, or may be input by an operator operating the input unit 101.

[0081] The calculation processing unit 105 refers to the number information and arranges in the time table TB the number of plan elements BL corresponding to the number of substrates W. For example, under the condition that four plan elements BL are arranged in the time table TB for each substrate W, when the number information indicates 25 substrates, the calculation processing unit 105 arranges 100 plan elements in each step of reinforcement learning to create a time schedule.

[0082] Next, the timetable TB will be described with reference to Figs. 1 to 5. Fig. 5 is a diagram showing an example of the timetable TB corresponding to the substrate processing apparatus WP shown in Fig. 2. As shown in Fig. 5, a plurality of plan elements BL are arranged in the timetable TB. Each of the plan elements BL is arranged in the timetable TB and exclusively occupies at least one of a plurality of components included in the substrate processing apparatus WP. By arranging the plurality of plan elements BL in the timetable TB, a time schedule for each component of the substrate processing apparatus WP is defined. In other words, by arranging the plurality of plan elements BL in the timetable TB, a scheduled occupancy time for each component of the substrate processing apparatus WP is defined.

[0083] Specifically, the horizontal axis of the timetable TB indicates time. In the timetable TB, a processing pattern corresponding to each component of the substrate processing apparatus WP is arranged along the time axis of the timetable TB. In the timetable TB shown in Fig. 5, the first planning element BL1 to the fourth planning element BL4 (processing pattern A to processing pattern M) are arranged based on the constraints 1 to 9 shown in Table 1 with reference to Figs. 3 and 4. The timetable TB is, for example, a Gantt chart. Note that the processing pattern A to processing pattern M arranged in the timetable TB may be numerical information or image information.

[0084] As shown in Figs. 3 to 5, the second plan element BL2 includes a processing pattern G (substrate processing). Therefore, the time length of the second plan element BL2 is longer than the other plan elements BL (the first plan element BL1, the third plan element BL3, and the fourth plan element BL4). The second plan element BL2 is an example of a plan element in which an unprocessed substrate W is carried into any one of the substrate processing units PU by a transport robot CR (transport unit) and the unprocessed substrate W is processed by any one of the substrate processing units PU. The third plan element BL3 is an example of a plan element in which a substrate W processed by the substrate processing unit PU is carried out from the substrate processing unit PU by a transport unit robot (transport unit).

[0085] Next, the process of creating a time schedule will be described with reference to Fig. 1 to Fig. 6. Fig. 6 is a diagram showing an example of the flow of the process of creating a time schedule. In detail, Fig. 6 shows the process of arranging multiple plan elements BL in a time table TB. Hereinafter, the process of arranging multiple plan elements BL in a time table TB may be referred to as "time schedule creation process."

[0086] 6, the calculation processing unit 105 refers to the current state of the timetable TB and a plurality of plan elements BL, and acquires plan elements BL that are not yet placed in the timetable TB (step S1). Hereinafter, the plan elements BL that are not yet placed may be referred to as "plan elements NBL."

[0087] For example, at the start of the time schedule creation process, all plan elements BL are plan elements NBL. For example, under the condition that four plan elements BL are arranged in the time table TB for each board W, if the number information indicates 25 sheets, the calculation processing unit 105 acquires 100 plan elements NBL at the start of the time schedule creation process. As the time schedule creation process progresses, the number of plan elements NBL decreases. The time schedule creation process continues until there are no more plan elements NBL.

[0088] When the calculation processing unit 105 acquires the plan element NBL, it refers to the current state of the timetable TB, the plan element NBL, the constraint conditions (constraint conditions 1 to 9), and the processing procedure PD to acquire the plan element BL that can be placed next from among the plan elements NBL. Hereinafter, the plan element BL that can be placed next is sometimes referred to as the "plan element ABL."

[0089] When the calculation processor 105 acquires the plan element ABL, it refers to the current state of the timetable TB, the plan element ABL, the constraints (constraints 1 to 9), and the processing procedure PD to calculate the possible placement time of each of the plan elements ABL (step S2). The possible placement time corresponds to the time indicated by the timetable TB. In more detail, the possible placement time indicates the time on the timetable TB at which the process included in the plan element ABL can be started.

[0090] After calculating the possible arrangement time, the calculation processing unit 105 generates an action AC for each plan element ABL (step S3). The action AC indicates a behavior of placing the plan element ABL at the possible arrangement time of the timetable TB.

[0091] When the calculation processing unit 105 generates the actions AC, it selects one of the actions AC (step S4), and arranges the plan element BL (plan element ABL) in the time table TB based on the selected action AC (step S5). As a result, the time table TB is updated. In other words, the time table TB becomes the following state.

[0092] Here, a first example of the process of selecting an action AC will be described. For example, the calculation processing unit 105 randomly selects one of the action ACs in the early stage of reinforcement learning. When the number of times that the reinforcement learning steps (trials) are repeated reaches or exceeds a second threshold, the calculation processing unit 105 predicts and selects an action AC that maximizes the reward from among the action ACs. Specifically, the generation program PL1 includes a behavior selection neural network 121 (see FIG. 7). The behavior selection neural network 121 includes a neural network that constructs a predictor. The predictor calculates an evaluation value (Q value) for each action AC. The evaluation value indicates an expected value of the reward. The calculation processing unit 105 (behavior selection neural network 121) selects an action AC with the largest evaluation value (expected value of the reward).

[0093] In addition, the calculation processing unit 105 may randomly select one of the action ACs based on a predetermined first condition after the number of times the reinforcement learning step (trial) is repeated becomes equal to or greater than a second threshold. For example, the first condition may indicate a period for randomly selecting one of the action ACs. In this case, the calculation processing unit 105 randomly selects one of the action ACs periodically.

[0094] Alternatively, the first condition may indicate the timing for randomly selecting one of the actions AC by the number of steps (number of trials). Hereinafter, the number of steps that specifies the timing for randomly selecting one of the actions AC may be referred to as the "random selection step number". The random selection step number may indicate a number of steps. In this case, the calculation processing unit 105 randomly selects one of the actions AC every time the number of times the reinforcement learning steps are repeated (the number of trials) reaches the number of steps included in the random selection step number. Note that one step (one trial) indicates the process from the start of the time schedule creation process to the time when all the plan elements BL are placed in the time table TB and the reward is obtained.

[0095] Next, a second example of the process of selecting an action AC will be described. For example, the calculation processing unit 105 acquires a random number and determines whether or not the value of the acquired random number is equal to or greater than a third threshold. If the value of the random number is equal to or greater than the third threshold, the calculation processing unit 105 predicts and selects an action AC that will maximize the reward from among the action ACs. If the value of the acquired random number is less than the third threshold, the calculation processing unit 105 randomly selects one of the action ACs. The calculation processing unit 105 reduces the third threshold in accordance with an increase in the number of steps (number of trials).

[0096] When the time table TB is updated, the calculation processing unit 105 executes the processes of steps S1 to S5 again. The calculation processing unit 105 repeats the processes of steps S1 to S5 until there are no more plan elements NBL. As a result, the time schedule creation process ends.

[0097] When the time schedule creation process is completed, the calculation processing unit 105 determines the reward based on the final state of the time table TB and the reward function (step S6). As already described, the reward function is defined so that the shorter the time length of the time schedule, the higher the reward.

[0098] Next, the reinforcement learning system 120 constructed by the arithmetic processing unit 105 executing the generation program PL1 will be described with reference to Fig. 7. Fig. 7 is a block diagram showing the reinforcement learning system 120.

[0099] As shown in Fig. 7, the reinforcement learning system 120 selects an action of an agent AG. The action of the agent AG causes an interaction between the agent AG and an environment EB. Specifically, the action of the agent AG includes an action AC described with reference to Fig. 6. The environment EB includes a timetable TB described with reference to Fig. 5. The reinforcement learning system 120 selects an action AC as described with reference to Fig. 6. The agent AG places a plan element BL in the timetable TB based on the selected action AC.

[0100] The reinforcement learning system 120 includes an action selection neural network 121 and a training engine 122. The training engine 122 includes a replay memory 123. The replay memory 123 is included in the storage area of ​​the storage unit 102.

[0101] As already described, the behavior selection neural network 121 calculates an evaluation value (Q value) for each action AC and selects the action AC with the largest evaluation value. The training engine 122 trains the behavior selection neural network 121 and adjusts multiple parameters (weighting coefficients) included in the behavior selection neural network 121.

[0102] In detail, the training engine 122 stores the experience data in the replay memory 123. The experience data indicates the result of the agent AG interacting with the environment EB. The experience data is learning data (training data) for supervised learning, and the training engine 122 trains the behavior selection neural network 121 by having the behavior selection neural network 121 learn the experience data. As a result, a plurality of parameters (weighting coefficients) included in the behavior selection neural network 121 are adjusted, and the prediction accuracy of the behavior selection neural network 121 is improved.

[0103] Specifically, the training engine 122 (the calculation processing unit 105) generates experience data every time a plan element BL is placed in the timetable TB, and stores the experience data in the replay memory 123. The experience data includes the current state of the timetable TB, the current plan element NBL (unassigned plan element BL), the current available time for placement, the selected action AC (selected plan element ABL), and the state of the next timetable TB. The experience data upon completion of creation of the time schedule further includes a reward value.

[0104] The training engine 122 (the calculation processing unit 105) trains the behavior selection neural network 121 based on a predetermined second condition. For example, the second condition may indicate a period for training the behavior selection neural network 121. In this case, the training engine 122 (the calculation processing unit 105) trains the behavior selection neural network 121 periodically.

[0105] Alternatively, the second condition may indicate the timing for training the behavior selection neural network 121 by the number of steps. Hereinafter, the number of steps that specifies the timing for training the behavior selection neural network 121 may be referred to as the "number of training steps." The number of training steps indicates a number of multiple steps. In this case, the training engine 122 (arithmetic processing unit 105) causes the behavior selection neural network 121 to learn experience data every time the number of times the reinforcement learning steps have been repeated (the number of trials) reaches the number of steps included in the number of training steps.

[0106] Next, a schedule creation program generating method of this embodiment will be described with reference to Figs. 1 to 16. Fig. 8 is a flowchart showing the schedule creation program generating method of this embodiment. The schedule creation program generating method of this embodiment is executed by the schedule creation program generating device 100 described with reference to Figs. 1 to 7. Specifically, the schedule creation program generating method of this embodiment is executed by the calculation processing unit 105 described with reference to Figs. 1 to 7. Thus, Fig. 8 shows the flow of processing executed by the calculation processing unit 105.

[0107] As shown in Fig. 8, the schedule creation program generation method of the present embodiment includes steps S11 to S15. For example, in a state where the generation program PL1 is installed in the schedule creation program generation device 100, the process shown in Fig. 8 may be started in response to an instruction to start reinforcement learning by an operator operating the input unit 101.

[0108] When the process shown in Fig. 8 starts, the calculation processing unit 105 creates a time schedule (step S11). The process of creating a time schedule will be described later with reference to Fig. 9. Step S11 is an example of an "arrangement step".

[0109] After creating the time schedule, the calculation processing unit 105 determines the reward value based on the final state of the time table TB and the reward function (step S12). The final state of the time table TB indicates the state of the time table TB in which all the plan elements BL have been placed. The time schedule corresponds to the final state of the time table TB. Step S12 is an example of a "reward determination step".

[0110] After determining the reward value, the calculation processing unit 105 determines whether or not to change the reward function (step S13). Specifically, the calculation processing unit 105 determines whether or not to change the reward function based on a predetermined third condition. For example, the third condition may indicate a period for changing the reward function. In this case, the calculation processing unit 105 changes the reward function periodically.

[0111] Alternatively, the third condition may indicate the timing to change the reward function by the number of steps. Hereinafter, the number of steps that specifies the timing to change the reward function may be referred to as the "number of change steps." The number of change steps indicates at least one step number. In this case, the calculation processing unit 105 decides to change the reward function every time the number of times the reinforcement learning steps have been repeated (the number of trials) reaches the number of steps included in the number of change steps.

[0112] When it is determined to change the reward function (Yes in step S13), the calculation processing unit 105 executes a change process to change the reward function (step S14). The change process will be described later with reference to Figs. 12 to 16. Step S14 is an example of a "change process".

[0113] After changing the reward function, the calculation processing unit 105 determines whether or not to end the reinforcement learning (step S15). Alternatively, when the calculation processing unit 105 determines not to change the reward function (No in step S13), it determines whether or not to end the reinforcement learning (step S15).

[0114] When the calculation processing unit 105 determines not to end the reinforcement learning (No in step S15), the process shown in Fig. 8 returns to the process in step S11. On the other hand, when the calculation processing unit 105 determines to end the reinforcement learning (Yes in step S15), the process shown in Fig. 8 ends.

[0115] For example, as described with reference to Fig. 1, a first threshold may be set as a condition for terminating the reinforcement learning. In this case, the calculation processing unit 105 determines to terminate the reinforcement learning when the number of times the reinforcement learning steps have been repeated (the number of trials) becomes equal to or greater than the first threshold.

[0116] As described with reference to Figs. 6 and 7, the calculation processing unit 105 adjusts the parameters (weighting coefficients) of the action selection neural network 121 in the process of repeating the time schedule creation process. Therefore, the value of the reward increases as the reinforcement learning steps (trials) are repeated. In this embodiment, one reinforcement learning step (one trial) includes steps S11 to S15 shown in Fig. 8. Among steps S11 to S15, the steps including steps S11 and S12 are an example of an "experience step".

[0117] Next, the time schedule creation process (step S11) shown in Fig. 8 will be described with reference to Fig. 9. Fig. 9 is a flowchart showing the time schedule creation process.

[0118] 9, the time schedule creation process includes steps S21 and S22. When the calculation processing unit 105 starts the time schedule creation process, it places one of the multiple plan elements BL in the time table TB to change the state of the time table TB (step S21).

[0119] When the calculation processing unit 105 places one of the plurality of plan elements BL in the time table TB, it judges whether or not all the plan elements BL have been placed in the time table TB (step S22).

[0120] When the calculation processing unit 105 determines that all the plan elements BL have been arranged in the timetable TB (Yes in step S22), the time schedule creation process ends, and the calculation processing unit 105 determines the value of the reward (step S12 in FIG. 8).

[0121] When the calculation processing unit 105 determines that some of the multiple plan elements BL are not placed on the timetable TB (No in step S22), it returns to step S21 and selects the next plan element BL and places it on the timetable TB. In this way, the calculation processing unit 105 sequentially places the multiple plan elements BL on the timetable TB, and sequentially changes the state of the timetable TB.

[0122] Next, the process of placing the plan element BL in the timetable TB (step S21 in FIG. 9) will be described with reference to FIG. 10 and FIG. 11. As described with reference to FIG. 6 and FIG. 7, the calculation processing unit 105 randomly selects one of the actions AC to place one of the plan elements BL (plan element ABL) that can be placed next in the timetable TB. Alternatively, the calculation processing unit 105 predicts and selects an action AC that will maximize the reward from among the actions AC to place one of the plan elements BL (plan element ABL) that can be placed next in the timetable TB.

[0123] Fig. 10 is a flowchart showing a process of randomly selecting one of the actions AC and arranging the plan element BL in the timetable TB. As shown in Fig. 10, when randomly selecting one of the actions AC, the process of arranging the plan element BL in the timetable TB (step S21 in Fig. 9) includes steps S31 to S34.

[0124] When the calculation processing unit 105 starts the process of arranging the plan elements BL in the timetable TB, it acquires the plan element BL (plan element ABL) that can be arranged next in the timetable TB from among the unarranged plan elements BL (plan element NBL) (step S31).

[0125] When the calculation processing unit 105 acquires the next available plan element BL (plan element ABL), it acquires the available time for each plan element ABL (step S32). When the calculation processing unit 105 acquires the available time for placement, it randomly selects one of the plan elements ABL (step S33). In more detail, the calculation processing unit 105 generates an action AC for each plan element ABL, and randomly selects one of the action ACs.

[0126] The calculation processing unit 105 places the randomly selected plan element ABL in the time table TB (step S34). As a result, the process shown in Fig. 10 ends. In detail, the calculation processing unit 105 places the plan element BL (plan element ABL) in the time table TB based on the randomly selected action AC.

[0127] When one of the plan elements ABL is randomly selected, if the second plan element BL2 is selected, one of the second plan elements BL2-1 to BL2-4 is randomly selected. In other words, one of the first substrate processing unit PU1 to the fourth substrate processing unit PU4 is selected, and the second plan element BL2 corresponding to the selected substrate processing unit PU is arranged in the timetable TB.

[0128] Fig. 11 is a flowchart showing a process of predicting an action AC that will maximize the reward and arranging the plan element BL in the timetable TB. As shown in Fig. 11, when predicting an action AC that will maximize the reward, the process of arranging the plan element BL in the timetable TB (step S21) includes steps S41 to S44.

[0129] Steps S41, S42, and S44 shown in FIG. 11 are similar to steps S31, S32, and S34 shown in FIG. 10, and therefore the description thereof will be omitted.

[0130] As shown in Fig. 11, after acquiring the possible placement time, the calculation processing unit 105 selects the plan element BL (plan element ABL) with the largest evaluation value (expected reward value) (step S43). In detail, the calculation processing unit 105 generates an action AC for each plan element ABL. Then, the calculation processing unit 105 selects the action AC with the largest evaluation value from among the action ACs using the action selection neural network 121 (see Fig. 7). The calculation processing unit 105 places the plan element BL (plan element ABL) in the timetable TB based on the selected action AC.

[0131] When selecting one of the plan elements ABL, if the second plan element BL2 is selected, one of the second plan elements BL2-1 to BL2-4 is selected. In other words, one of the first substrate processing unit PU1 to the fourth substrate processing unit PU4 is selected, and the second plan element BL2 corresponding to the selected substrate processing unit PU is arranged in the timetable TB.

[0132] Next, the change process (step S14) shown in FIG. 8 will be described with reference to FIG. 12(a). FIG. 12(a) is a flowchart showing a first change process included in the change process. As shown in FIG. 12(a), when the calculation processing unit 105 decides to change the reward function, it changes the reward function to one that has a larger gradient in the target section TS than the current reward function (step S51). As a result, the process shown in FIG. 12(a) ends.

[0133] In this embodiment, the change process (step S14) may further include a second change process shown in FIG. 12(b). FIG. 12(b) is a flowchart showing the second change process included in the change process. As shown in FIG. 12(b), when the calculation processing unit 105 decides to change the reward function, it shifts the section (target section TS) whose gradient has been increased by the process (first change process) of FIG. 12(a) (step S52). As a result, the process shown in FIG. 12(b) is terminated.

[0134] The calculation processing unit 105 may execute the first change process shown in FIG. 12(a) every time it is decided to change the reward function. As a result, the gradient of the target section TS gradually increases. Alternatively, the first change process may be executed only once. For example, the calculation processing unit 105 may execute the first change process only when it is decided for the first time to change the reward function.

[0135] After executing the first change process at least once, the calculation processing unit 105 executes the second change process shown in FIG. 12(b). The calculation processing unit 105 may alternately execute the first change process and the second change process. Alternatively, the calculation processing unit 105 may execute the first change process and the second change process simultaneously every time it is determined to change the reward function after the first execution of the first change process. Alternatively, the calculation processing unit 105 may execute only the second change process every time it is determined to change the reward function after the first execution of the first change process. Note that the second change process may be omitted.

[0136] Next, the first change process will be described with reference to Fig. 13 and Fig. 14. Fig. 13 is a diagram showing an example of the first change process. In detail, Fig. 13 shows an initial reward function 2 and a reward function 3 after the first change process. In Fig. 13, the horizontal axis indicates the final unloading time, and the vertical axis indicates the reward. Here, the final unloading time indicates the time at which the last substrate W returns to the substrate accommodation container CA in the substrate processing apparatus WP. The final unloading time corresponds to the time length of the time schedule.

[0137] As shown in Fig. 13, reward functions 2 and 3 define the relationship between the time length of the time schedule and the reward value so that the shorter the time length of the time schedule, the higher the reward value. In addition, reward functions 2 and 3 define the minimum reward value rw1, the maximum reward value rw2, the time length of the time schedule corresponding to the minimum reward value rw1 (final payout time t22), and the time length of the time schedule corresponding to the maximum reward value rw2 (final payout time t21).

[0138] As shown in FIG. 13, reward function 3 includes a function whose gradient in the target section TS is larger than that of reward function 2. For example, reward function 2 includes a linear function. Reward function 3 includes a nonlinear function. In the example shown in FIG. 13, reward function 2 includes a linear function, and monotonically decreases the reward value from a maximum value rw2 to a minimum value rw1 from the final dispensing time t21 to the final dispensing time t22. Reward function 3 includes a logistic curve function whose gradient in the target section TS is larger than that of a linear function.

[0139] The target section TS indicates a part of the time range from the final dispensing time t21 to the final dispensing time t22. The target section TS may be set to correspond to the section where the reward value is saturated, for example, within the time range from the final dispensing time t21 to the final dispensing time t22.

[0140] In detail, when reinforcement learning is performed by defining the relationship between the time length of the time schedule and the reward value as a linear function, such as reward function 2, the difference in evaluation value between trials may become small and the reward value may become saturated before the time length of the time schedule (reward value) reaches the target value. This is thought to be due to the fact that the substrate processing apparatus WP includes components with greatly different processing times PT.

[0141] Specifically, the processing time PT (processing time X7) of the substrate processing unit PU is significantly different from the processing time PT of the transport unit (indexer robot IR and transport robot CR). Therefore, as shown in FIG. 5, the time length of the second plan element BL2 is longer than the other plan elements BL (first plan element BL1, third plan element BL3, and fourth plan element BL4). Therefore, when the relationship between the time length of the time schedule and the reward value is specified by a linear function, action selections with small evaluation value differences and action selections with large evaluation value differences are mixed. As learning progresses and the reward value approaches the target value, action selections with small evaluation value differences are repeated, and it is considered that the reward value is saturated before reaching the target value.

[0142] In contrast, according to the present embodiment, the gradient of the reward function in the target section TS is increased, so that the difference in the evaluation value between trials can be expanded in the target section TS. As a result, even if trials are repeated in the target section TS, the parameters (weighting coefficients) of the behavior selection neural network 121 can be changed more greatly (more dynamically). Therefore, by setting the section in which the reward value saturates when a linear function is used as the reward function to the target section TS, and emphasizing the difference in the evaluation value between trials, it is possible to prevent the reward value from saturating before the time length (reward value) of the time schedule reaches the target value.

[0143] Therefore, according to this embodiment, by changing the reward function while reinforcement learning is being performed, it is possible to generate a schedule creation program PL2 that can bring the time length of the time schedule closer to the target value.

[0144] Fig. 14 is a diagram showing another example of the first change process. In detail, Fig. 14 shows the initial reward function 2 and reward functions 3a to 3f after multiple first change processes. In Fig. 14, the horizontal axis indicates the final payout time, and the vertical axis indicates the reward.

[0145] As shown in Fig. 14, reward functions 3a to 3f include functions whose gradient in the target section TS is larger than that of reward function 2. In particular, reward functions 3a to 3f have larger gradients in the target section TS in this order. In this manner, calculation processing unit 105 may execute the first change process multiple times to gradually increase the gradient in the target section TS. Specifically, calculation processing unit 105 may change the reward function to one whose gradient in the target section TS is larger than the current gradient each time it executes the first change process.

[0146] For example, the reward functions 3a to 3f include nonlinear functions. In the example shown in Fig. 14, the reward functions 3a to 3f include a logistic curve function whose gradient in the target section TS is larger than that of a linear function. More specifically, the reward functions 3a to 3f include a gradient-variable logistic curve function. In this case, the calculation processing unit 105 changes a constant included in the gradient-variable logistic curve function each time the first change process is executed, gradually increasing the gradient in the target section TS.

[0147] According to this embodiment, as shown in Fig. 14, by gradually increasing the gradient of the target section TS, the difference in evaluation value between trials is gradually emphasized. As a result, the parameters of the behavior selection neural network 121 can be gradually changed. Therefore, the learning efficiency of reinforcement learning can be improved.

[0148] Next, the second change process will be described with reference to Fig. 15. Fig. 15 is a diagram showing an example of the second change process. In detail, Fig. 15 shows an initial reward function 2 and reward functions 4a to 4c after multiple second change processes. In Fig. 15, the horizontal axis indicates the final payout time, and the vertical axis indicates the reward.

[0149] As shown in Fig. 15, reward functions 4a to 4c define the relationship between the time length of the time schedule and the reward value so that the shorter the time length of the time schedule, the higher the reward value. In addition, reward functions 4a to 4c define the minimum reward value rw1, the maximum reward value rw2, the time length of the time schedule corresponding to the minimum reward value rw1 (final payout time t22), and the time length of the time schedule corresponding to the maximum reward value rw2 (final payout time t21).

[0150] As shown in FIG. 15, the reward functions 4a to 4c include a function in which the gradient of the target section TS becomes larger than that of the reward function 2. The reward functions 4a to 4c have different sections (target sections TS) in which the gradient becomes larger. In detail, the position of the target section TS becomes closer to the final dispensing time t21 in the order of the reward functions 4a to 4c. In this way, the calculation processing unit 105 may execute the second change process multiple times to shift the target section TS from the final dispensing time t22 side to the final dispensing time t21 side.

[0151] For example, the reward functions 4a to 4c include nonlinear functions. In the example shown in FIG. 15, the reward functions 4a to 4c include a logistic curve function whose gradient in the target section TS is larger than that of a linear function. More specifically, the reward functions 4a to 4c include an X-axis variable logistic curve function. In this case, the calculation processing unit 105 changes the constant included in the function of the X-axis variable logistic curve each time the second change process is executed, and shifts the target section TS from the final take-off time t22 side to the final take-off time t21 side.

[0152] According to this embodiment, it is possible to generate a schedule creation program PL2 that can bring the length of time in the time schedule closer to the target value without predetermining the interval where the reward value saturates when a linear function is used as the reward function.

[0153] In the example shown in Figure 15, the target section TS is shifted while keeping the gradient in the target section TS constant, but the gradient in the target section TS may be gradually increased while shifting the target section TS, as described with reference to Figure 14.

[0154] 13 to 15, the reward functions 3, 3a to 3f, and 4a to 4c after the change process are non-linear functions, but the reward functions after the change process are not limited to non-linear functions as long as the gradient in the target section TS is greater than the gradient of the reward function 2. For example, the reward function after the change process may include a linear function whose gradient in the target section TS is greater than the gradient of the reward function 2.

[0155] Fig. 16 is a diagram showing another example of the change process. In detail, Fig. 16 shows an initial reward function 2 and a reward function 5 after the change process. In Fig. 16, the horizontal axis indicates the final payout time, and the vertical axis indicates the reward.

[0156] As shown in Fig. 16, the reward function 5 specifies the relationship between the time length of the time schedule and the reward value so that the reward value increases as the time length of the time schedule decreases in the time range from the final payout time t31 to the final payout time t32. In addition, the reward function 5 specifies the minimum reward value rw1, the maximum reward value rw2, the time length of the time schedule corresponding to the minimum reward value rw1 (the range from the final payout time t32 to the final payout time t22), and the time length of the time schedule corresponding to the maximum reward value rw2 (the range from the final payout time t21 to the final payout time t31).

[0157] As shown in FIG. 16, reward function 5 includes a function whose gradient in the target section TS is greater than that of reward function 2. At least a portion of the target section TS is included within the time range from the final dispensing time t31 to the final dispensing time t32. In detail, reward function 5 includes a linear function whose gradient is greater than that of reward function 2 (linear function). The linear function included in reward function 5 linearly changes the value of the reward for the final dispensing time in the time range from the final dispensing time t31 to the final dispensing time t32.

[0158] According to reward function 5 shown in Figure 16, the gradient of the target section TS is larger than that of reward function 2, so that a schedule creation program PL2 can be generated that can bring the length of the time schedule closer to the target value, similar to reward functions 3, 3a to 3f, and 4a to 4c described with reference to Figures 13 to 15.

[0159] Next, the substrate processing apparatus 200 of this embodiment will be described with reference to Fig. 17. Fig. 17 is a diagram showing a substrate processing system 200A including the substrate processing apparatus 200 of this embodiment.

[0160] 17, the substrate processing system 200A includes a recording medium 110 and a substrate processing apparatus 200. The substrate processing apparatus 200 includes an interface unit 201, a plurality of load ports LP, an indexer robot IR, a transport robot CR, a plurality of substrate processing units PU, a memory unit 202, and a control unit 203a.

[0161] The interface unit 201 exchanges information, data, or signals with the recording medium 110. Specifically, the recording medium 110 stores the schedule creation program PL2 described with reference to Figures 1 to 16. The interface unit 201 reads out the schedule creation program PL2 from the recording medium 110 and inputs it to the control unit 203a.

[0162] The configuration of the interface unit 201 is similar to that of the interface unit 103 described with reference to Fig. 1, and therefore a detailed description thereof will be omitted. Also, the configurations of the load port LP, the indexer robot IR, the transport robot CR, and the substrate processing unit PU are similar to those of the load port LP, the indexer robot IR, the transport robot CR, and the substrate processing unit PU described with reference to Fig. 2, and therefore a description thereof will be omitted.

[0163] The storage unit 202 stores various information for controlling the operation of the substrate processing apparatus 200. For example, the storage unit 202 stores data and computer programs. The data includes various recipe data. The recipe data includes, for example, a process recipe. The process recipe is data that defines a procedure for substrate processing. The storage unit 202 also stores a schedule creation program PL2 read out from the recording medium 110. The storage unit 202 further stores a processing procedure PD, a processing time PT, a planning element BL, and constraint conditions.

[0164] The storage unit 202 includes a main storage device. The main storage device is, for example, a semiconductor memory. The storage unit 202 may further include an auxiliary storage device. The auxiliary storage device includes, for example, at least one of a semiconductor memory and a hard disk drive. The storage unit 202 may include a removable medium.

[0165] The control unit 203a has, for example, a processor. The control unit 203a may have a CPU or MPU as the processor. Alternatively, the control unit 203a may have a general-purpose computing device or a dedicated computing device. The control unit 203a controls the operation of each unit of the substrate processing apparatus 200 based on various information stored in the storage unit 202. For example, the control unit 203a controls the interface unit 201, the load port LP, the indexer robot IR, the transport robot CR, the substrate processing unit PU, and the storage unit 202.

[0166] Furthermore, when processing a plurality of substrates W, the control unit 203a executes the schedule creation program PL2 to create a time schedule according to which the plurality of substrates W sequentially occupy a plurality of components (the indexer robot IR, the transfer unit PS, the transport robot CR, and the substrate processing unit PU) included in the substrate processing apparatus 200. Then, the control unit 203a controls the load port LP, the indexer robot IR, the transport robot CR, and the substrate processing unit PU based on the created time schedule.

[0167] Specifically, the schedule creation program PL2 includes the behavior selection neural network 121 whose parameters (weighting coefficients) have been adjusted, as described with reference to Figures 1 to 16. The control unit 203a creates a time schedule according to steps S1 to S5 described with reference to Figure 6, based on the schedule creation program PL2, the processing procedure PD, the processing time PT, the planning elements BL, and the constraint conditions.

[0168] 1 to 16, according to this embodiment, the schedule creation program PL2 can bring the time length of the time schedule closer to the target value, and therefore the substrate processing apparatus 200 can create a time schedule that completes the processing of a predetermined number of substrates W in a shorter period of time.

[0169] The first embodiment of the present invention has been described above with reference to Figs. 1 to 17. According to this embodiment, there is no need to develop the entire flow of processing executed by a processor. Specifically, the developer only needs to develop the processing procedure PD, the processing time PT, the schedule element BL, and the constraint conditions. This reduces the burden on the developer.

[0170] Furthermore, according to this embodiment, it is possible to generate a schedule creation program PL2 that can bring the time length of the time schedule closer to the target value.

[0171] Furthermore, according to this embodiment, a linear function can be used as the initial reward function of reinforcement learning, thereby improving the learning efficiency of reinforcement learning.

[0172] Specifically, in the early stage of reinforcement learning, a time schedule with a relatively late final payout time is created. Therefore, when reward function 3, reward functions 3a to 3f, reward functions 4a to 4c, or reward function 5 described with reference to Figs. 13 to 16 are used as the reward function in the early stage of reinforcement learning, the difference in evaluation value between trials in the early stage of reinforcement learning becomes small. Therefore, the reward value is unlikely to become large. As a result, the learning efficiency of reinforcement learning decreases. In contrast, when a linear function is used as the reward function in the early stage of reinforcement learning, even if a time schedule with a relatively late final payout time is created, the difference in evaluation value between trials can be made large compared to reward function 3, reward functions 3a to 3f, reward functions 4a to 4c, or reward function 5. Therefore, the learning efficiency of reinforcement learning can be improved.

[0173] [Embodiment 2] Next, a second embodiment of the present invention will be described with reference to Fig. 18. However, differences from the first embodiment will be described, and a description of the same matters as in the first embodiment will be omitted. The second embodiment differs from the first embodiment in that the substrate processing apparatus 200 generates a schedule creation program PL2.

[0174] Fig. 18 is a diagram showing a substrate processing system 200A including a substrate processing apparatus 200 of this embodiment. As shown in Fig. 18, the substrate processing system 200A includes a recording medium 110 and a substrate processing apparatus 200. The substrate processing apparatus 200 includes an interface unit 201, a plurality of load ports LP, an indexer robot IR, a transport robot CR, a plurality of substrate processing units PU, a memory unit 202, and a control unit 203b.

[0175] The recording medium 110 stores the generating program PL1 described with reference to Figures 1 to 16. The interface unit 201 of the substrate processing apparatus 200 reads out the generating program PL1 from the recording medium 110 and inputs it to the control unit 203b.

[0176] The storage unit 202 stores the generation program PL1 read from the recording medium 110. The storage unit 202 also stores the processing procedure PD, the processing time PT, the plan element BL, and the constraint conditions, as described with reference to FIG.

[0177] The control unit 203b has a processor. The control unit 203b may have a CPU, an MPU, a GPU, an NPU, or a quantum computer as a processor. Alternatively, the control unit 203b may have a general-purpose computer or a dedicated computer. The control unit 203b controls the operation of each unit of the substrate processing apparatus 200 based on various information stored in the storage unit 202. For example, the control unit 203b controls the interface unit 201, the load port LP, the indexer robot IR, the transport robot CR, the substrate processing unit PU, and the storage unit 202.

[0178] 1 to 16, the control unit 203b executes the generation program PL1 to generate a schedule creation program PL2. The schedule creation program PL2 is stored in the storage unit 202. When processing a plurality of substrates W, the control unit 203b executes the schedule creation program PL2 to create a time schedule, similar to the control unit 203a described with reference to FIG. 17. Then, the control unit 203b controls the load port LP, the indexer robot IR, the transport robot CR, and the substrate processing unit PU based on the created time schedule.

[0179] The second embodiment of the present invention has been described above with reference to Fig. 18. According to the second embodiment, like the first embodiment, the burden on the developer can be reduced. Furthermore, according to the second embodiment, like the first embodiment, a schedule creation program PL2 can be generated that can bring the time length of a time schedule closer to a target value. Therefore, the substrate processing apparatus 200 can create a time schedule that completes the processing of a predetermined number of substrates W in a shorter period of time.

[0180] [Embodiment 3] Next, a third embodiment of the present invention will be described with reference to Fig. 19. However, differences from the first and second embodiments will be described, and a description of the same matters as the first and second embodiments will be omitted. The third embodiment differs from the first and second embodiments in that a substrate processing system 200B includes a schedule creation device 300.

[0181] 19 is a diagram showing a substrate processing system 200B of the present embodiment. As shown in FIG. 19, the substrate processing system 200B includes a schedule creation device 300 and a substrate processing apparatus 200.

[0182] The schedule creation device 300 creates a time schedule based on a schedule creation program PL2. Specifically, the schedule creation device 300 includes an input unit 301, a storage unit 302, a communication unit 303, and a calculation processing unit 304. The schedule creation device 300 is, for example, a server.

[0183] The input unit 301 includes a user interface device operated by a worker. The input unit 301 inputs a signal according to the operation of the worker to the calculation processing unit 304. The configuration of the input unit 301 is similar to that of the input unit 101 described with reference to Fig. 1, and therefore the description thereof will be omitted. For example, the worker can operate the input unit 301 to instruct the start of creation of a time schedule.

[0184] The storage unit 302 has a main storage device. The main storage device includes, for example, a semiconductor memory. The storage unit 302 may further have an auxiliary storage device. The auxiliary storage device includes, for example, at least one of a semiconductor memory and a hard disk drive. The storage unit 302 may include a removable medium. The storage unit 302 stores various computer programs and various data. Specifically, the storage unit 302 stores a schedule creation program PL2. As described with reference to FIGS. 1 to 16, the schedule creation program PL2 is generated based on the generation program PL1.

[0185] The arithmetic processing unit 304 includes a processor. The arithmetic processing unit 304 may include a CPU or an MPU as a processor. Alternatively, the arithmetic processing unit 304 may include a general-purpose computer or a dedicated computer. The arithmetic processing unit 304 executes the schedule creation program PL2 stored in the storage unit 302, similar to the control unit 203a described with reference to Fig. 17, to create a time schedule in which multiple substrates W sequentially occupy multiple components (the indexer robot IR, the transfer unit PS, the transport robot CR, and the substrate processing unit PU) included in the substrate processing apparatus 200.

[0186] The communication unit 303 is connected to a network and performs communication with the substrate processing apparatus 200. The network includes, for example, the Internet, a LAN (Local Area Network), a public telephone network, and a short-range wireless network. The communication unit 303 includes a communicator. The communication unit 303 is, for example, a network interface controller. The communication unit 303 is controlled by the arithmetic processing unit 304, and transmits a time schedule created by the arithmetic processing unit 304 to the substrate processing apparatus 200. The communication unit 303 is an example of a "transmission unit."

[0187] The substrate processing apparatus 200 includes a plurality of load ports LP, an indexer robot IR, a transport robot CR, a plurality of substrate processing units PU, a storage unit 202, a control unit 203c, and a communication unit 204.

[0188] The communication unit 204 is connected to a network and executes communication with the communication unit 303 of the schedule creation device 300. The communication unit 204 includes a communication device. The communication unit 204 is, for example, a network interface controller. The communication unit 204 receives the time schedule transmitted from the communication unit 303 of the schedule creation device 300. The communication unit 204 is an example of a "receiving unit."

[0189] The control unit 203c has, for example, a processor. The control unit 203c may have a CPU or MPU as the processor. Alternatively, the control unit 203c may have a general-purpose computing device or a dedicated computing device. The control unit 203c controls the operation of each unit of the substrate processing apparatus 200 based on various information stored in the storage unit 202. For example, the control unit 203c controls the load port LP, the indexer robot IR, the transport robot CR, the substrate processing unit PU, the storage unit 202, and the communication unit 204.

[0190] Specifically, the control unit 203c instructs the schedule creation device 300 to create a time schedule when processing multiple substrates W. As a result, the communication unit 204 receives the time schedule from the schedule creation device 300. The control unit 203c controls the load port LP, the indexer robot IR, the transport robot CR, and the substrate processing unit PU based on the time schedule received by the communication unit 204.

[0191] In detail, the control unit 203c causes the communication unit 204 to transmit a command instructing creation of a time schedule to the schedule creation device 300. As a result, the communication unit 204 receives the time schedule from the schedule creation device 300. When instructing creation of a time schedule, the control unit 203c may cause the communication unit 204 to transmit information indicating the processing procedure PD, information indicating the processing time PT, information indicating the plan element BL, and the constraint conditions to the schedule creation device 300.

[0192] The third embodiment of the present invention has been described above with reference to Fig. 19. According to the third embodiment, as in the first and second embodiments, the burden on the developer can be reduced. Furthermore, according to the third embodiment, as in the first and second embodiments, a schedule creation program PL2 can be generated that can bring the time length of a time schedule closer to a target value. Therefore, the substrate processing apparatus 200 can create a time schedule that completes the processing of a predetermined number of substrates W in a shorter period of time.

[0193] [Embodiment 4] Next, a fourth embodiment of the present invention will be described with reference to Fig. 20. However, differences from the first to third embodiments will be described, and a description of the same matters as the first to third embodiments will be omitted. The fourth embodiment differs from the first to third embodiments in that a substrate processing system 200C includes a schedule creation program generating apparatus 100.

[0194] Fig. 20 is a diagram showing a substrate processing system 200C of the present embodiment. As shown in Fig. 20, the substrate processing system 200C includes a schedule creation program generating device 100 and a substrate processing apparatus 200. The schedule creation program generating device 100 is, for example, a server.

[0195] The schedule creation program generation device 100 includes an input unit 101, a storage unit 102, a calculation processing unit 105, and a communication unit 106. The calculation processing unit 105 executes the generation program PL1 stored in the storage unit 102 to generate the schedule creation program PL2, as described with reference to Figs. 1 to 16.

[0196] The communication unit 106 is connected to a network and communicates with the substrate processing apparatus 200. The communication unit 106 is controlled by the arithmetic processing unit 105 and transmits the schedule creation program PL2 created by the arithmetic processing unit 105 to the substrate processing apparatus 200. The communication unit 106 is an example of a "transmission unit." Note that the configuration of the communication unit 106 is similar to that of the communication unit 303 described with reference to FIG. 19, and therefore a description thereof will be omitted.

[0197] The substrate processing apparatus 200 includes a plurality of load ports LP, an indexer robot IR, a transport robot CR, a plurality of substrate processing units PU, a storage unit 202, a control unit 203a, and a communication unit 204.

[0198] The communication unit 204 is connected to a network and communicates with the communication unit 106 of the schedule creation program generation device 100. The communication unit 204 receives the schedule creation program PL2 transmitted from the communication unit 106 of the schedule creation program generation device 100. The schedule creation program PL2 received by the communication unit 204 is stored in the storage unit 202.

[0199] The control unit 203a executes the schedule creation program PL2 to create a time schedule when processing a plurality of substrates W. Then, the control unit 203a controls the load port LP, the indexer robot IR, the transport robot CR, and the substrate processing unit PU based on the created time schedule.

[0200] The fourth embodiment of the present invention has been described above with reference to Fig. 20. According to the fourth embodiment, similar to the first to third embodiments, the burden on the developer can be reduced. Furthermore, according to the fourth embodiment, similar to the first to third embodiments, a schedule creation program PL2 can be generated that can bring the time length of a time schedule closer to a target value. Therefore, the substrate processing apparatus 200 can create a time schedule that completes the processing of a predetermined number of substrates W in a shorter period of time.

[0201] The embodiments of the present invention have been described above with reference to the drawings (FIGS. 1 to 20). However, the present invention is not limited to the above embodiments, and can be implemented in various aspects without departing from the gist of the present invention. In addition, the components disclosed in the above embodiments can be modified as appropriate. For example, a certain component among all the components shown in one embodiment may be added to a component of another embodiment, or some of all the components shown in one embodiment may be deleted from the embodiment.

[0202] The drawings are mainly schematic illustrations of each component to facilitate understanding of the invention, and the thickness, length, number, spacing, etc. of each component shown in the drawings may differ from the actual ones due to the convenience of creating the drawings. Furthermore, the configurations of each component shown in the above embodiment are merely examples and are not particularly limited, and it goes without saying that various modifications are possible within a range that does not substantially deviate from the effects of the present invention.

[0203] For example, in the embodiment described with reference to FIGS. 1 to 20, the substrate processing apparatus WP and the substrate processing apparatus 200 are single-wafer type apparatuses, but the substrate processing apparatus WP and the substrate processing apparatus 200 may be batch type apparatuses.

[0204] Furthermore, the substrate processing apparatus 200 is not particularly limited as long as it is an apparatus for processing the substrate W. For example, the substrate processing apparatus 200 may be a chemical cleaning apparatus, a brush cleaning apparatus, a wet etching apparatus, a dry etching apparatus, a coating apparatus, a developing apparatus, an exposure apparatus, a coater developer, a baking apparatus, or a film forming apparatus.

[0205] 1 to 20, functions expressing curved graphs (reward functions 3, 3a to 3f, and 4a to 4c) and a function expressing a linear graph (reward function 5) have been exemplified as reward functions after the change process, but the reward function after the change process is not particularly limited as long as the gradient in the target section TS is greater than the gradient of reward function 2. For example, the reward function after the change process may be a step function that expresses a step-like graph. [Industrial Applicability]

[0206] The present invention is useful in an apparatus for processing a substrate. [Explanation of symbols]

[0207] 2, 3, 3a-3f, 4a-4c, 5: Reward functions 8A, 8B: Hand 13A, 13B: Hand 100: Schedule creation program generating device 100A: Schedule creation program generation system 102: Storage section 105: Processing unit 106: Communications Department 110: Recording media 120: Reinforcement learning system 200: Substrate processing device 200B: Substrate processing system 200C: Substrate processing system 202: Storage section 203a: Control section 203b: Control section 203c: Control section 204: Communications Department 300: Schedule creation device 302: Storage section 303: Communications Department 304: Processing unit BL, NBL, ABL: Planning elements BL1: First planning element BL2, BL2-1 to BL2-4: Second planning element BL3: Third planning element BL4: Fourth planning element PL1: Generator PL2: Schedule creation program PS1: Shelf PS2: Shelf PU: Substrate processing section PU1: First substrate processing section PU2: Second substrate processing section PU4: 4th substrate processing section TB: Timetable TS: Target section W: Substrate WP: Substrate processing equipment rw1 :minimum value rw2 :Maximum value t21: Final withdrawal time t22: Final withdrawal time

Claims

1. A schedule creation program generation method for generating a schedule creation program for creating a time schedule for a plurality of components included in a substrate processing apparatus by reinforcement learning, comprising: the plurality of components are occupied by a plurality of substrates during processing of the substrates; The schedule creation program generation method includes: a step of repeating an experience step including a placement step and a reward determination step by the reinforcement learning to increase a reward value; A modification step of modifying a reward function that defines a relationship between a time length of the time schedule and a value of the reward; Including, the placing step is a step of sequentially placing a plurality of planning elements, which are previously assigned to each of the substrates, on a time table for defining the time schedule, and sequentially changing a state of the time table; the reward determination step includes determining a value of the reward based on the reward function and a final state of the timetable in which all of the planning elements have been placed; the time schedule corresponds to a final state of the timetable; A method for generating a schedule creation program, the modification step including a step of modifying the reward function so that a gradient in a portion of a time range from a time length of the time schedule corresponding to a maximum value of the reward to a time length of the time schedule corresponding to a minimum value of the reward becomes larger than that before the modification.

2. 2. The schedule creation program generation method according to claim 1, wherein the change step includes a step of changing the reward function so that a gradient in a portion of the time range is greater than a gradient when the entire time range is defined by a linear function.

3. A plurality of the above-mentioned modifying steps are included, 3. The method for generating a schedule creation program according to claim 1, wherein each time the change step is performed, the reward function is changed so that a gradient in a portion of the time range is greater than a gradient at a current stage.

4. 3. The schedule creation program generating method according to claim 1, wherein the changing step further includes a step of shifting the part of the section.

5. The plurality of components include: A plurality of substrate processing units for processing the substrates; A transport unit that transports the substrate; Including, The plurality of planning elements include: a first planning element for carrying the substrate into any one of the substrate processing units by the transport unit and processing the substrate by any one of the substrate processing units; a second planning element for causing the transport unit to transport the substrate after the substrate processing unit has been processed by the substrate processing unit out of the substrate processing unit; 3. The method for generating a schedule creating program according to claim 1, further comprising:

6. 6. The method of claim 5, wherein the first planning element has a time length longer than the second planning element.

7. the plurality of plan elements include plan elements corresponding to each of the substrate processing units, 6. The schedule creation program generating method according to claim 5, wherein in said arranging step, one of the plan elements corresponding to each of said substrate processing units is selected.

8. A schedule creation program generating device that generates a schedule creation program for creating a time schedule for a plurality of components included in a substrate processing apparatus by reinforcement learning, A storage unit that stores a generation program that defines the schedule creation program generation method according to claim 1 or 2; a processing unit that executes the generation program to generate the schedule creation program; A schedule creation program generating device comprising:

9. A schedule creation device that creates a time schedule for a plurality of components included in a substrate processing apparatus, A storage unit that stores a schedule creation program generated based on the schedule creation program generation method according to claim 1 or 2; a processing unit that executes the schedule creation program to create the time schedule; A schedule creation device comprising:

10. 3. A computer-readable recording medium having a generating program that defines the schedule creation program generating method according to claim 1 or 2 recorded thereon.

11. 3. A computer-readable recording medium, the recording medium having a schedule creating program generated based on the schedule creating program generating method according to claim 1 or 2 recorded therein.

12. A generating program executable by a computer and defining the schedule creation program generating method according to claim 1 or 2.

13. A schedule creation program executable by a computer and generated based on the schedule creation program generation method according to claim 1 or 2.

14. a plurality of components that are occupied by the substrates during processing of the substrates; A storage unit that stores a generation program that defines the schedule creation program generation method according to claim 1 or 2; a processing unit that executes the generation program to generate a schedule creation program for creating a time schedule for the plurality of components; Equipped with The processing unit executes the schedule creation program to create the time schedule.

15. a plurality of components that are occupied by the substrates during processing of the substrates; A storage unit that stores a schedule creation program generated based on the schedule creation program generation method according to claim 1 or 2; a processing unit that executes the schedule creation program to create a time schedule for the plurality of components; The substrate processing apparatus includes:

16. A substrate processing apparatus; The schedule creation program generating device according to claim 8 , Equipped with the schedule creation program generating device further includes a transmission unit configured to transmit the schedule creation program to the substrate processing apparatus; The substrate processing apparatus includes: a plurality of components that are occupied by the substrates during processing of the substrates; a receiving unit that receives the schedule creation program transmitted from the transmitting unit of the schedule creation program generation device; a processing unit that executes the schedule creation program to create a time schedule for the plurality of components; A substrate processing system comprising:

17. A substrate processing apparatus; The schedule creation device according to claim 9 . Equipped with the schedule creation device further includes a transmission unit that transmits the time schedule to the substrate processing apparatus, The substrate processing apparatus includes: a plurality of components that are occupied by the substrates during processing of the substrates; a receiving unit that receives the time schedule transmitted from the transmitting unit of the schedule creation device; A substrate processing system comprising:

Citation Information

Patent Citations

  • Model-Based Scheduling for Substrate Processing Systems

    JP2022523870A

  • Schedule creation method, schedule creation device, substrate processor, substrate processing system, recording medium, and schedule creation program

    JP2023020264A

  • Scheduling method and program for substrate treating apparatus

    JP2009048320A