Resource allocation / work process procedure planning apparatus, resource allocation / work process procedure planning method, and program
The resource allocation system optimizes transport task allocation using constraint expressions and mixed integer programming to balance workload and minimize delivery delays, improving transport efficiency in warehouses.
Patent Information
- Application Number
- JP2023055038
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-30
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2043-03-30
AI Technical Summary
Existing resource allocation methods for transport vehicles in warehouses focus on minimizing transport time but do not consider workload balancing and delivery delays, leading to inefficiencies.
A resource allocation system that acquires layout and schedule information, applies constraint expressions to allocate tasks to transport devices, and optimizes plans using mixed integer programming to minimize delivery delays and workload deviations.
The system creates allocation plans that balance workload among transport vehicles and reduce delivery delays, enhancing overall transport work efficiency.
Smart Images

Figure 2024142736000001_ABST
Abstract
Description
[Technical field]
[0001] The present disclosure relates to a resource allocation and work process sequence planning device, a resource allocation and work process sequence planning method, and a program. [Background technology]
[0002] Patent Document 1 discloses a device that uses a simulation to calculate how pallets should be allocated to the transport carts that carry pallets in and out of a warehouse in order to optimally operate the transport carts. This device uses the layout data of the automated warehouse, simulation conditions, and pallet time series data as inputs to create multiple pallet transport allocation patterns, and calculates the allocation pattern that minimizes the time until transport is completed as the optimal pallet transport allocation. In the technology of Patent Document 1, the pallet time series data is fixed data for the simulation, and the pallet transport allocation pattern is created using rule-based heuristics at the timing when a pallet to be transported is generated. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] Patent No. 2020-111455 Summary of the Invention [Problem to be solved by the invention]
[0004] The method disclosed in Cited Document 1 finds an optimal solution to be an allocation pattern that minimizes the time required to complete pallet transportation, and does not generate an allocation plan that takes into consideration the efficiency of the entire transportation work (e.g., reducing uneven work loads between transportation vehicles and delivery delays).
[0005] The present disclosure provides a resource allocation and work process sequence planning device, a resource allocation and work process sequence planning method, and a program that can solve the above problems. [Means for solving the problem]
[0006] The resource allocation and task processing sequence planning device disclosed herein includes a data acquisition unit that acquires layout information of a location where luggage is to be transported, schedule information for transporting the luggage, and information on a plurality of transport devices that transport the luggage, a constraint equation that constrains the allocation of luggage to be transported, which is included in the schedule information, to any one of the plurality of transport devices, a constraint equation that constrains that the time required for the transport work included in the schedule information is the sum of the travel time from a location where the transport device exists before the transport work to a location from which the transport work originates and the time required for the transport work, and a constraint equation that constrains that the operation time of the plurality of transport devices in an arbitrary evaluation section is the operation time of the transport device in the evaluation section. the constraint condition definition unit sets as constraint conditions: a constraint equation that constrains the working time of the transport equipment in any one of the evaluation sections to be equal to or less than a maximum value, and a constraint equation that constrains the value obtained by subtracting the amount of delivery delay in the evaluation section from the working time of the transport equipment in that evaluation section to be equal to or less than the available time for work in that evaluation section; an objective function definition unit sets as an objective function a weighted sum of a formula that calculates the sum of the maximum working times of the transport equipment in multiple evaluation sections and a formula that calculates the sum of the amount of delivery delay of the transport equipment in multiple evaluation sections; and an allocation plan optimization unit that calculates an allocation plan for the transport work to the transport equipment that minimizes the objective function while satisfying the constraint conditions.
[0007] The resource allocation and task processing sequence planning method disclosed herein includes a step of acquiring layout information of a location where luggage is to be transported, schedule information of the luggage transport work, and information on a plurality of transport devices that transport the luggage, a constraint equation that constrains the allocation of the luggage to be transported, which is included in the schedule information, to any one of the plurality of transport devices, a constraint equation that constrains that the time required for the transport work included in the schedule information is the sum of the travel time from a location where the transport device exists prior to the transport work to a location from which the transport work originates and the time required for the transport work, and a constraint equation that constrains that the operation time of the plurality of transport devices in an arbitrary evaluation section is the sum of the travel time of the transport devices in the evaluation section and the time required for the transport work. The method includes a step of setting as constraint conditions: a constraint equation that constrains the working time of the transport equipment in any one of the evaluation sections to be equal to or less than the maximum working time; and a constraint equation that constrains the working time of the transport equipment in any one of the evaluation sections minus the amount of delivery delay in that evaluation section to be equal to or less than the available time for work in that evaluation section; a step of setting as an objective function a weighted sum of a formula that calculates the sum of the maximum working times of the transport equipment in multiple evaluation sections and a formula that calculates the sum of the amount of delivery delay in that evaluation section; and a step of calculating an allocation plan for the transport work to the transport equipment that minimizes the objective function while satisfying the constraint conditions.
[0008] The program of the present disclosure includes a step of causing a computer to acquire layout information of a location where luggage is to be transported, schedule information for transporting the luggage, and information on a plurality of transport devices that transport the luggage, a constraint equation that constrains the allocation of a luggage to be transported, which is included in the schedule information, to any one of the plurality of transport devices, a constraint equation that constrains that the time required for the transport work included in the schedule information is the sum of the travel time from a location where the transport device exists before the transport work to a location from which the transport work originates and the time required for the transport work, and a constraint equation that constrains that the operation time of the plurality of transport devices in an arbitrary evaluation section is the maximum of the operation time of the transport devices in the evaluation section. The method executes a process including the steps of: setting as constraint conditions: a constraint equation that constrains the maximum value of the work time of the transport equipment in any one evaluation section to be equal to or less than a maximum value; and a constraint equation that constrains the value obtained by subtracting the amount of delivery delay in the evaluation section from the working time of the transport equipment in that evaluation section to be equal to or less than the available time for work in that evaluation section; setting as an objective function a weighted sum of a formula that calculates the sum of the maximum values of the work times of the transport equipment in multiple evaluation sections and a formula that calculates the sum of the amount of delivery delay of the transport equipment in multiple evaluation sections; and calculating an allocation plan for the transport work to the transport equipment so as to minimize the objective function while satisfying the constraint conditions. Effect of the Invention
[0009] According to the resource allocation and work process sequence planning device, resource allocation and work process sequence planning method and program described above, a plan for allocating transport tasks to transport equipment can be created in consideration of the work efficiency of the entire transport task. [Brief description of the drawings]
[0010] [Figure 1] FIG. 1 is a block diagram illustrating an example of a planning system according to an embodiment. [Diagram 2] FIG. 1 is a diagram illustrating modeling of a problem according to an embodiment. [Diagram 3] FIG. 10 is a diagram illustrating a method for estimating a task time according to an embodiment. [Figure 4] FIG. 11 is a diagram illustrating the leveling of work time according to an embodiment. [Diagram 5] FIG. 1 is a diagram illustrating a method for reducing delivery delays according to an embodiment. [Figure 6] 11 is a flowchart illustrating an example of a plan creation process according to the embodiment. [Figure 7] FIG. 2 is a diagram illustrating an example of a hardware configuration of the planning system according to the embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0011] <Embodiment> Hereinafter, the planning system according to each embodiment will be described in detail with reference to FIGS. (composition) FIG. 1 is a block diagram showing an example of a planning system according to an embodiment of the present invention. In this embodiment, the planning system is configured by a computer device such as a single PC or a server device. The planning system 10 creates an allocation plan that takes into consideration the work efficiency of the entire transport work, and allocates the transport work of transporting luggage brought into a warehouse or the like to a storage location and unloading luggage stored in the storage location to one of multiple transport devices. The allocation plan that takes into consideration the work efficiency of the entire transport work is an allocation plan that can level out the work load between transport vehicles and reduce delivery delays.
[0012] As shown in FIG. 1, the planning system 10 includes a data acquisition unit 11, a planning unit 12, an output unit 13, and a memory unit 14. The data acquisition unit 11 has the function of acquiring information necessary for creating an allocation plan, such as the layout of the facility, scheduled information for transportation work, initial inventory, and information on transportation equipment, and formatting the information so that it can be handled in the optimization process described below, and the function of writing and recording the acquired information and formatted information in the memory unit 14.
[0013] The planning unit 12 creates an optimal allocation plan for allocating scheduled transportation tasks to transportation devices. The planning unit 12 includes a constraint condition definition unit 121, an objective function definition unit 122, and an allocation plan optimization unit 123. The constraint condition definition unit 121 has the function of defining six types (eight) of constraint conditions (described later), such as always assigning a transportation task to a transportation device and observing the chronological relationship with the preceding task, based on the information acquired by the data acquisition unit 11. The objective function definition unit 122 has a function of defining an objective function including minimizing the amount of delay in delivery of the transportation work and leveling out the operation time of each transportation device. The allocation plan optimization unit 123 has a function of complying with the constraint conditions defined by the constraint condition definition unit 121, formulating the objective function defined by the objective function definition unit 122 as a mixed integer programming problem, and performing optimization calculations using a commonly available solver.
[0014] The output unit 13 has a function of outputting an allocation plan indicating how to allocate transportation tasks to each transportation device based on the result obtained by the optimization calculation performed by the allocation plan optimization unit 123 . The storage unit 14 stores various information necessary for creating an allocation plan.
[0015] (Contents of input data) The layout of the facility includes information such as the locations of where luggage will be placed and the distance of each location from the loading and unloading entrance. The transportation work schedule information includes information such as the order ID (identification information of the transportation work), work type (carrying in work, carrying out work, moving luggage within the premises), origin location, destination location, possible start date and time, and delivery date for transportation work that will occur during the period for which the allocation plan is created. For example, if the work type is carrying in, the possible start date and time is the date and time when carrying in work is possible. The transportation work schedule information may also include information on transportation work for which the possible start date and time or delivery date are set before the period for which the allocation plan is created (order ID, work type, origin, destination, possible start date and time, delivery date, etc.). The initial inventory information includes information indicating what items have already been placed in which locations at the start of the period for which the allocation plan is to be created. The information on the transportation equipment includes information such as the ID of the transportation equipment, the type of the transportation equipment, the number of packages that can be transported simultaneously, the moving speed, and the initial position of the transportation equipment.
[0016] (Problem definition and modeling) In this embodiment, the process of creating an allocation plan is defined as a problem of calculating an allocation method that minimizes the amount of delivery delay and minimizes the deviation of work time when two or more transport tasks are allocated to two or more transport devices. Then, the problem of allocating transport tasks to transport devices is modeled as a bipartite matching problem. FIG. 2 shows a model in which tasks No. 1 to No. 5 are allocated to three transport devices A to C. The task list 20 includes the order ID (No. in the figure) and task type included in the schedule information of the transport tasks, and the task time (including the time required for the transport task and the travel time to the transport source) obtained by calculation. The solid lines connecting the transport devices A to C and the No. in the task list 20 indicate an example of allocation, and the dashed lines indicate other allocation candidates. In the allocation example shown in FIG. 2, the transport tasks No. 1 to No. 2 are allocated to the transport device A, the transport task No. 3 is allocated to the transport device B, and the transport tasks No. 4 to No. 5 are allocated to the transport device C. As a result, the total working time of transport equipment A is 4 minutes, the total working time of transport equipment B is 5 minutes, and the total working time of transport equipment C is 5 minutes.
[0017] (Estimated work time) Next, a method for estimating the work time of the transport work will be described with reference to FIG. 3. In the allocation plan creation process of this embodiment, the most efficient work processing order is not sought in order to perform calculations in a practical time. Not seeking the most efficient work processing order means that, for example, in a case where transport work 1 occurs at 9:00 (the start possible date and time is 9:00), transport work 2 occurs at 9:15, and transport work 3 occurs at 9:30, the transport work is started in the order in which it occurred without considering a work processing order in which transport work 2 is started first and transport work 1 is executed later, or a work processing order in which transport work 3 is started first and transport work 1 and 2 are executed later (even if there is a possibility that working in such an order would be more efficient). Furthermore, in this embodiment, in addition to the start possible date and time, the work time is estimated by giving priority to transport work with a delivery date that is close (or the start order of the transport work may be determined by the user). In addition, the "empty transportation" time when the transport equipment moves without loading the cargo is calculated as the time required to move from the location where the work of the preceding order is completed to the location where the work of the subsequent order is started. Figure 3 shows an example of a method for calculating the operation time when the transport work with order IDs a to f is assigned to the transport equipment C1 and C2. The initial position of the transport equipment C1 is H1, and the initial position of the transport equipment C2 is H2. Table 30 in Figure 3 stores information on the order ID, transport source, transport destination, and operation priority of each operation. The operation priority order based on the available start date and time and the due date is in the order of order ID=a, b, c, d, e, f. In addition, the operations with order ID=a, c, f are assigned to the transport equipment C1, and the operations with order ID=b, d, e are assigned to the transport equipment C2. Table 31 shows the operation time of the transport equipment C1.
[0018] The work of the transport equipment C1 includes movement from the initial position H1 of the transport equipment C1 to the source P1, which is the work start position for order ID=a (movement order on table 31=1), movement from the source P1 for order ID=a to the destination P2 (movement order on table 31=2), movement from the destination P2 to the source P3, which is the work start position for the next order ID=c (movement order on table 31=3), the transport work of order ID=c, that is, movement from the source P3 to the destination P4 (movement order on table 31=4), movement from the destination P4 to the source P1, which is the work start position for the next order ID=f (movement order on table 31=5), the transport work of order ID=f, that is, movement from the source P1 to the destination P6 (movement order on table 31=6), and movement from the destination P6 to the original position H1 (movement order on table 31=7). The time required for movement between locations can be calculated, for example, by calculating the distance between the origin and destination based on the location of the luggage placement location included in the layout of the facility in the input data, and dividing this distance by the movement speed included in the transportation equipment in the input data. In the case of empty transportation (movement order in table 31 = 3, 5), the work time is calculated as the time it takes to move from the location where the work of the preceding order is completed to the location where the work of the succeeding order starts.
[0019] The operation time required for each transport task by the transport device C2 can be calculated in the same manner as for the transport device C1. Table 32 shows the operation time of the transport device C2.
[0020] It is difficult to grasp the working time and delay status of each piece of transport equipment simply by allocating transportation tasks to the transport equipment using the bipartite matching problem model illustrated in Fig. 2. Therefore, as explained below, the period for which the allocation plan is created is divided into small intervals to evaluate the working time and delay.
[0021] (Leveling of work hours) With reference to FIG. 4, a method for achieving the leveling of operation times will be described. In this embodiment, taking into consideration that the possible start dates and times differ for each order, the operation times of orders allocated to the transport equipment in each time period are leveled as much as possible. First, the planning period is divided into N small sections. The planning period is a target period for calculating an allocation plan, and N is an arbitrary integer. The divided small sections are called section 1 to section N in order of the earliest time period. Next, an evaluation section is set. The evaluation section is a period for evaluating operation times. In this embodiment, for example, one small section with section N as the last small section or the entire range of multiple consecutive (adjacent) small sections is set as the evaluation section. In this embodiment, the number of consecutive (adjacent) small sections is changed by 1 to set N evaluation sections. The evaluation sections set in this manner are called Group 1 to N. For example, Group 1 includes section 1 to section N. Group 2 includes section 2 to section N. Group N-1 includes section N-1 to section N. Group N includes section N (upper diagram of FIG. 4). In the case of Group 2, transportation work whose possible start date and time exists in Section 2 to Section N is evaluated for work time. In addition, transportation work whose possible start date and time exists in the past than the planning period, transportation work whose possible start date and time exists in Section 1, transportation work whose possible start date and time exists in the future than the planning period, etc. are not evaluated (lower diagram in Figure 4).
[0022] Then, for transportation tasks that have available start dates and times within each group, an allocation plan is calculated for each group (each evaluation section) such that the sum of the working times of each transport device within the group is leveled. In other words, an allocation plan is calculated such that the working times of each transport device are leveled across sections 1 to N, the working times of each transport device are leveled across sections 2 to N, ..., the working times of each transport device are leveled across sections N-1 to N, and the working times of each transport device are leveled in section N. This prevents the calculation of an allocation plan in which, for example, when two transport devices C1 and C2 are present, only the transport device C1 is operated without using the transport device C2 in the first half of the section 1 to section N, and only the transport device C2 is operated without using the transport device C1 in the second half, so that the work times of the transport devices C1 and C2 are leveled when looking at the entire section 1 to N, but the work is biased toward the transport device C2 when looking at only section N, and prevents the calculation of an allocation plan in which the work times of the transport devices C1 and C2 are leveled throughout the entire planning period and in local evaluation sections. In addition, when trying to level the work times in small sections for each of sections 1, 2, ..., N, for example, when there is only one work in each of section 1 and section 2 (when the work time in the small section is biased no matter how it is allocated), the result may be that the transport work is assigned to the transport device C1 in both sections 1 and 2, but by setting Groups 1 to N as shown in Figure 4 and aiming for leveling in each evaluation section, such bias can be prevented. In addition, the scale of calculations can be reduced by dividing the data into multiple small sections and considering leveling on a group basis.
[0023] (Reduction of delivery delays) Next, a method for reducing delivery delays will be described with reference to FIG. 5. In this embodiment, taking into consideration that delivery dates differ for different orders, a plan is created to allocate transport tasks to transport equipment so that delivery delays do not occur in each time period. As described in FIG. 4, the target period is divided into small sections, Section 1 to Section N. Then, using Section 1 as a reference, the period before the planning period is set as Group 1-1, the section combining the period before the planning period and Section 1 as Group 1-2, the section combining the period before the planning period and Sections 1 to 2 as Group 1-3, ..., and the section combining the period before the planning period and Sections 1 to N as Group 1-N+1. Also, only Section 1 is set as Group 2-1, the section combining Sections 1 to 2 as Group 2-2, ..., the section combining Sections 1 to N as Group 2-N, and only Section N as Group N-1 (upper diagram in FIG. 5). For example, in the case of Group 2-1, transport tasks that have a possible start date and time and delivery date in Section 1 are evaluated for delivery delays. Transportation work that has a possible start date and time and due date that falls in the past of the planning period, transportation work that has a possible start date and time that falls in the past of the planning period and the due date falls in section 1, transportation work that has a possible start date and time that falls in section 1 and the due date falls in section 2, etc. are not evaluated when evaluating delivery date delays for Group 2-1 (lower diagram in Figure 5). For example, delivery date delays for transportation work that has a possible start date and time that falls in section 1 and the due date falls in section 2 are evaluated in Group 2-2. This makes it possible to calculate an allocation plan that minimizes delays not only when transportation work starts in section 1, but also when transportation work starts in section 2.
[0024] Then, for transportation tasks that have possible start dates and due dates within each group, it evaluates whether the transportation tasks can be completed within that group, and calculates how to allocate tasks that minimize the amount of delay in the delivery date. In addition, orders with due dates that are later than the planning period are treated as one evaluation section (Group 1-1 in Figure 5) as they need to be completed early, and the penalty for delivery date delays is made larger than in other evaluation sections. In addition, in the case of an evaluation section that includes the first section 1 of the planning period, it also includes those whose possible start dates and times were set before the planning period and whose due dates are set within the evaluation section (Group 1-2, 1-3, etc.). In this way, an allocation plan that minimizes delivery date delays is calculated, including tasks whose due dates and possible start dates and times are before the planning period.
[0025] (Mixed integer programming problems) Based on the model in FIG. 2, the method of estimating the work time in FIG. 3, and the various evaluation methods in FIG. 4 and FIG. 5 (work leveling, delivery delay), the above problem is formulated as a mixed integer programming problem whose objective function includes minimizing the amount of delivery delay and leveling the total work time. The mixed integer programming problem can be solved by using a solver that is generally available. By the above modeling and various evaluation methods, it is possible to formulate which transportation equipment is to be assigned to the transportation work as a decision variable, and it is no longer necessary to use the start date and completion date and time of the work as variables, making it possible to reduce the scale of the problem. In addition, since the work allocation is considered by looking at the entire planning period, it becomes possible to find an efficient work allocation that could not be found with the conventional technology. For example, when a task of carrying out another piece of luggage from a nearby location occurs after placing the luggage at a specified location, in the conventional technology, a different transportation equipment from the one used for carrying it in may be assigned. However, according to the present embodiment, since an objective function (Equation (11) described later) that shortens the work time as much as possible is set, it is possible to obtain a plan in which the same transportation equipment is assigned to these tasks. Next, we will write down the constants, variables, constraints, objective functions, etc. related to the mixed integer programming problem.
[0026] (constant) For example, the following constants are defined: (1) c_work_time is a non-negative real number that represents the time required for a transportation device to perform transportation work of a given order, and its arguments are the transportation device and the order.
[0027] (2) c_move_time is a non-negative real number that represents the time required to move from the end location of any order 1 to the start location of any order 2, and its arguments are the order IDs of order 1 and order 2.
[0028] (3) c_max_time is a non-negative real number that represents the time available for work within the evaluation interval (Group), and its argument is the evaluation interval.
[0029] (4) c_priority is a non-negative real number that indicates the execution priority of an order, and its argument is the order ID. Basically, values are assigned in sequential order according to the available start date and time, but if the available start date and time are the same, the order with the earliest due date is given priority.
[0030] (5) c_first_order is a non-negative integer that represents the first order to be executed by any transport equipment, and the argument is the ID of the transport equipment. This order is not an actual order (called a real order), but a virtual one.
[0031] (6) c_last_order is a non-negative integer that represents the last order to be executed by a transport device, and the argument is the ID of the transport device. This order is not a real order, but a virtual order.
[0032] (set) As a set, we define the following: (1) Order represents a set of orders. (2) Carrier represents a set of transport equipment. (3) DueDateGrp represents a set of evaluation intervals (Groups) for evaluating delivery date delays. (4) LevelingGrp represents a set of evaluation intervals (Groups) for evaluating work time leveling. (5) GrpOrder represents a set of orders included in any evaluation interval (Group) that takes an evaluation interval as an argument.
[0033] (variable) Define the variables x, y, z, p, and q. These variables are values calculated by optimization calculations. Among these, x is the decision variable, and the rest are auxiliary variables. (1) x is a 0-1 variable (1: execute, 0: do not execute) indicating whether a given transport device executes a given task. The arguments are the transport device ID and the task ID.
[0034] (2) y is a 0-1 variable (1: execute, 0: do not execute) indicating whether a transport device executes another transport task 2 in succession after executing transport task 1. The arguments are the transport device ID, the order ID of transport task 1, and the order ID of transport task 2.
[0035] (3) z is a variable that represents the sum of the time required for a transport device to move to the location where the transport task is to be started in order to perform a transport task, and the time required for the actual task. The arguments are the transport device ID and the transport task order ID.
[0036] (4) p is a variable that represents the amount of delivery delay for an arbitrary evaluation interval (Group). The argument is the evaluation interval.
[0037] (5) q is a variable that represents the maximum operation time of a transportation device in an arbitrary evaluation section (Group). The argument is the evaluation section.
[0038] (constraints) The following six types and eight constraints are set. (Constraint 1: Allocation to transport equipment) Constraint condition 1 restricts that the transport equipment must be assigned to any one of the operations. The constraint equation of constraint condition 1 can be expressed by the following equation (1).
[0039]
number
[0040] (Constraint 2: Consistency of work hours) Constraint condition 2 restricts that for any transport equipment and any order (transportation work), the total time required to move from another location to execute the order and the time to actually execute the order must be counted as task time z. The constraint formula for constraint condition 2 can be expressed as the following formula (2). c_assign_priority is a constant that indicates the priority order using the order ID as an argument.
[0041]
number
[0042] (Constraint 3: Leveling work hours) Constraint condition 3 restricts the total operation time of the transport equipment in any evaluation section (Group) to be equal to or less than the value of variable q. The constraint equation for constraint condition 3 can be expressed as the following equation (3). By minimizing this variable q with the objective function, work that can be started is assigned so that operation times are leveled out, and at the same time, operation times are minimized.
[0043]
number
[0044] (Constraint 4: Delivery date) Constraint condition 4 restricts that the transportation equipment is assigned to the transportation task in any evaluation section (Group) so that delivery delays are minimized as much as possible. The constraint equation of constraint condition 4 can be expressed as the following equation (4).
[0045]
number
[0046] (Constraint 5: Relationship with preceding operations) Constraint condition 5 specifies that when a transport device performs any transport task, another task must be performed beforehand. Constraint formula (5) constrains that there must be a transport task (actual order) that precedes an actual order in the target period, and constraint formula (6) constrains that there must be a transport task that precedes the first actual order in the target period.
[0047]
number
[0048]
number
[0049] (Constraint 6: Relationship with subsequent operations) Constraint condition 6 specifies that when a transport device performs any transport task, it must perform another task after it. Constraint formula (7) specifies that there must be a subsequent transport task (actual order) for each actual order within the target period, and constraint formula (8) specifies that there must be a subsequent transport task for the last actual order within the target period.
[0050]
number
[0051]
number
[0052] (Objective function) The objective function is defined by the following formula (9), where the identification information of the objective function item is c_object, the objective function item is Object[c_object], and the weighting of the objective function item is c_objective_weight[c_object]. In the optimization calculation, the combination of variables x, y, z, p, and q that minimizes this objective function is calculated. c_objective_weight[c_object] can be set by the user as desired.
[0053]
number
[0054] The objective function item Object[c_object] has the following two items.
[0055] (Objective function item 1: Minimizing delivery delays) This item represents the total amount of delay in delivery for any group. Objective function item 1 can be expressed by the following calculation formula (10).
[0056]
number
[0057] (Objective function item 2: Leveling out work hours) This item represents the total operation time of any group. Objective function item 2 can be expressed by the following calculation formula (11). In formula (11), the operation time of the transport equipment with the longest operation time in a certain evaluation section (group) is represented as q[grp], and by minimizing this, minimization and leveling of operation time is achieved.
[0058]
number
[0059] (operation) Next, the flow of the process of creating an allocation plan in this embodiment will be described. FIG. 6 is a flowchart illustrating an example of a plan creation process according to the embodiment. First, the data acquisition unit 11 acquires data necessary for creating a plan, such as the layout of the facility, scheduled information for transport work, initial inventory, information on transport equipment, and the planned period (step S1). For example, the data acquisition unit 11 acquires the constants and sets described above. The data acquisition unit 11 writes and stores the acquired various data in the storage unit 14.
[0060] Next, the user performs an operation to instruct the planning system 10 to create an allocation plan. The planning system 10 accepts this instruction operation and instructs the planning unit 12 to execute the process of creating an allocation plan. Then, the planning unit 12 executes the following process using the constraint condition definition unit 121, the objective function definition unit 122, and the allocation plan optimization unit 123. First, the constraint condition definition unit 121 sets the constraint conditions (step S2). For example, the constraint condition definition unit 121 sets the above-described eight constraint expressions as the constraint conditions. Next, the objective function definition unit 122 sets an objective function (step S3). The objective function definition unit 122 reads out the weighting coefficient c_objective_weight stored in the storage unit 14 in step S1, and sets the objective function using equations (9) to (11).
[0061] Next, the allocation plan optimization unit 123 executes a calculation to optimize the placement plan of the goods (step S4). Here, the allocation plan optimization unit 123 is a general solver that solves optimization problems. The allocation plan optimization unit 123 solves a mixed integer planning problem formulated by the constraint conditions set in step S2 and the objective function set in step S3, and calculates variables x, y, z, p, and q that minimize the value of the objective function set in step S3 while satisfying the constraint conditions set in step S2. For example, the allocation plan optimization unit 123 sets the evaluation intervals (Group 1 to N) as described using FIG. 4, and calculates the work time of each evaluation interval as described using FIG. 3. The allocation plan optimization unit 123 sets the evaluation intervals (Group 1-1 to N-1) as described using FIG. 5, and calculates the amount of delivery delay for each evaluation interval. Then, it calculates variables x, y, z, p, and q that minimize these.
[0062] Next, the output unit 13 outputs the created plan (step S5). For example, the output unit 13 displays which order is to be assigned to which transport device based on the variable x.
[0063] (effect) As described above, according to this embodiment, it is possible to plan the allocation of transport tasks to transport devices, taking into consideration the work efficiency of the entire transport tasks, including not only the immediate transport tasks but also future transport tasks. More specifically, it is possible to create an allocation plan that minimizes the amount of delivery delay and the bias in work time. This reduces the risk of delivery delays due to concentrated allocation of tasks to some transport devices. Furthermore, according to this embodiment, it is possible to calculate an exact solution for the placement of luggage using mixed integer programming.
[0064] The planning method of this embodiment can be applied not only to situations where it is necessary to plan the allocation of transport tasks to transport equipment when loading and unloading luggage into and from a typical logistics warehouse, but also to processes such as allocating transport tasks to transport equipment such as cranes when transporting containers, etc. at container terminals, etc.
[0065] FIG. 7 is a diagram illustrating an example of a hardware configuration of the planning system according to the embodiment. The computer 900 includes a CPU 901, a main memory device 902, an auxiliary memory device 903, an input / output interface 904, and a communication interface 905. The planning system 10 described above is implemented in the computer 900. The above-described functions are stored in the auxiliary memory device 903 in the form of a program. The CPU 901 reads the program from the auxiliary memory device 903, loads it in the main memory device 902, and executes the above-described processing according to the program. The CPU 901 also secures a storage area in the main memory device 902 according to the program. The CPU 901 also secures a storage area in the auxiliary memory device 903 for storing data being processed according to the program.
[0066] In addition, a program for realizing all or part of the functions of the planning system 10 may be recorded on a computer-readable recording medium, and the program recorded on the recording medium may be read into a computer system and executed to perform processing by each functional unit. The term "computer system" as used herein includes hardware such as an OS and peripheral devices. In addition, if a WWW system is used, the term "computer system" also includes a homepage providing environment (or display environment). In addition, the term "computer-readable recording medium" refers to a portable medium such as a CD, DVD, or USB, or a storage device such as a hard disk built into a computer system. In addition, if the program is distributed to the computer 900 via a communication line, the computer 900 that receives the program may deploy the program in the main storage device 902 and execute the above processing. In addition, the above program may be for realizing part of the above-mentioned functions, and may further be capable of realizing the above-mentioned functions in combination with a program already recorded in the computer system.
[0067] As described above, several embodiments according to the present disclosure have been described, but all of these embodiments are presented as examples and are not intended to limit the scope of the invention. These embodiments can be implemented in various other forms, and various omissions, substitutions, and modifications can be made without departing from the gist of the invention. These embodiments and their modifications are included in the scope of the invention and its equivalents as described in the claims, as well as in the scope and gist of the invention.
[0068] <Additional Notes> The resource allocation and work process sequence planning device, the resource allocation and work process sequence planning method, and the program described in each embodiment can be understood, for example, as follows.
[0069] (1) A resource allocation and task processing sequence planning device (planning system 10) according to a first aspect includes a data acquisition unit that acquires layout information of a location where luggage is to be transported, schedule information of the luggage transport work, and information on a plurality of transport devices that transport the luggage, a constraint equation that constrains the allocation of a luggage to be transported, which is included in the schedule information, to any one of the plurality of transport devices, a constraint equation that constrains that a time required for a transport work included in the schedule information is the sum of a travel time from a location where the transportation device exists before the transport work to a location from which the transport work originates and a time required for the transport work, and a constraint equation that constrains that a work time of the plurality of transport devices in an arbitrary evaluation section is a time required for the transportation devices in the evaluation section. a constraint condition definition unit that sets as constraint conditions a constraint equation that constrains the working time of the transport equipment in any one of the evaluation sections to be equal to or less than the maximum working time of the transport equipment in that evaluation section, and a constraint equation that constrains the working time of the transport equipment in any one of the evaluation sections to be equal to or less than the available time for work in that evaluation section; an objective function definition unit that sets as an objective function a weighted sum of a calculation formula that calculates the sum of the maximum working times of the transport equipment in multiple evaluation sections and a calculation formula that calculates the sum of the delivery delay amounts of the transport equipment in multiple evaluation sections; and an allocation plan optimization unit that calculates an allocation plan for the transport work to the transport equipment that minimizes the objective function while satisfying the constraint conditions. This makes it possible to plan the allocation of transport tasks to transport equipment while taking into account the overall efficiency of the transport tasks. Specifically, it is possible to create an allocation plan that minimizes the amount of delivery delay and the bias in work time.
[0070] (2) A resource allocation and work process sequence planning device (planning system 10) according to a second aspect is the resource allocation and work process sequence planning device of (1), in which the allocation plan optimization unit divides a target period for which the allocation plan is to be created into small intervals, and sets the entire range of any of a plurality of consecutive small intervals among the small intervals as the evaluation interval, thereby setting a plurality of evaluation intervals, and calculates the allocation plan so as to minimize the sum of the maximum values of the work times for each of the set evaluation intervals. This makes it possible to create an allocation plan that achieves both leveling out and minimizing work hours.
[0071] (3) A resource allocation and work process sequence planning device (planning system 10) according to a third aspect is a resource allocation and work process sequence planning device according to (1) to (2), wherein the allocation plan optimization unit divides a target period for which the allocation plan is to be created into small sections, and when the entire range of any of a plurality of consecutive small sections is set as the evaluation section, calculates the amount of delivery date delay of the transportation equipment for the transportation work whose start time and delivery date fall within the evaluation section. By creating an allocation plan for each evaluation section that covers tasks that can be started in that evaluation section and include the due date and time, it is possible to try out all allocation methods and then calculate the allocation method that minimizes the amount of delay in delivery.
[0072] (4) A resource allocation and work process sequence planning device (planning system 10) according to a fourth aspect is the resource allocation and work process sequence planning device of (3), wherein, when the evaluation section includes the first subsection of the target period, the allocation plan optimization unit sets the start time of the transportation work before the evaluation section and calculates the delivery date delay amount of the transportation equipment for the transportation work whose delivery date falls within the evaluation section. This makes it possible to create an allocation plan that minimizes delivery delays, including transportation work that can be started before the target period.
[0073] (5) A resource allocation and work process sequence planning device (planning system 10) according to a fifth aspect is a resource allocation and work process sequence planning device according to (3) to (4), in which the allocation plan optimization unit calculates the amount of delivery delay of the transportation equipment by treating the transportation operations whose delivery date is set before the target period as the transportation operations belonging to one group. This makes it possible to create an allocation plan that minimizes delivery delays, including transportation tasks with delivery dates set before the target period.
[0074] (6) A resource allocation and task processing sequence planning method according to a sixth aspect includes the steps of acquiring layout information of a location where luggage is to be transported, schedule information of the luggage transport work, and information on a plurality of transport devices that transport the luggage, a constraint equation that constrains the allocation of a luggage to be transported, which is included in the schedule information, to any one of the plurality of transport devices, a constraint equation that constrains that a time required for a transport work included in the schedule information is the sum of a travel time from a location where the transportation device exists before the transport work to a location from which the transport work originates and a time required for the transport work, and a constraint equation that constrains that a work time of the plurality of transport devices in an arbitrary evaluation section is equal to or less than the travel time of the transportation device in the evaluation section. The method includes a step of setting as constraint conditions: a constraint equation that constrains the working time to be equal to or less than the maximum value, and a constraint equation that constrains the value obtained by subtracting the amount of delivery delay in the evaluation section from the working time of the transport equipment in any one of the evaluation sections to be equal to or less than the available time for work in the evaluation section; a step of setting as an objective function a weighted sum of a formula that calculates the sum of the maximum values of the working times of the transport equipment in multiple evaluation sections and a formula that calculates the sum of the amount of delivery delay in the transport equipment in multiple evaluation sections; and a step of calculating an allocation plan for the transport work to the transport equipment that minimizes the objective function while satisfying the constraint conditions.
[0075] (7) A program according to a seventh aspect includes the steps of: instructing a computer 900 to acquire layout information of a location where an item is to be transported, schedule information for transporting the item, and information on a plurality of transport devices that transport the item; a constraint equation that constrains the allocation of an item to be transported, which is included in the schedule information, to any one of the plurality of transport devices; a constraint equation that constrains that a time required for a transport operation included in the schedule information is the sum of a travel time from a location where the transport device exists before the transport operation to a location from which the transport operation originates and a time required for the transport operation; and a constraint equation that constrains that a work time of the plurality of transport devices in an arbitrary evaluation section is the work time of the transport devices in the evaluation section. The method executes a process including the steps of: setting as constraint conditions: a constraint equation that constrains the working time of the transport equipment in any one evaluation section to be equal to or less than a maximum time; and a constraint equation that constrains the value obtained by subtracting the amount of delivery delay in the evaluation section from the working time of the transport equipment in that evaluation section to be equal to or less than the time available for work in that evaluation section; setting as an objective function a weighted sum of a formula that calculates the sum of the maximum working times of the transport equipment in multiple evaluation sections and a formula that calculates the sum of the amount of delivery delay in the transport equipment in multiple evaluation sections; and calculating an allocation plan for the transport work to the transport equipment so as to minimize the objective function while satisfying the constraint conditions. [Explanation of symbols]
[0076] 10. Planning System 11. Data acquisition section 12. Planning Department 121... Constraint definition section 122...Objective function definition part 123 Allocation Plan Optimization Unit 13 Output section 14...Storage section 900...Computer 901···CPU 902...Main memory 903...Auxiliary storage device 904 Input / Output Interface 905 Communication Interface
Claims
1. a data acquisition unit that acquires layout information of a location where the luggage is to be transported, schedule information of the luggage transport work, and information of a plurality of transport devices that transport the luggage; a constraint condition definition unit that sets the following constraint conditions as constraint conditions: a constraint equation that constrains allocation of a load to be transported, which is included in the schedule information, to any of the plurality of transport devices; a constraint equation that constrains that the time required for a transport operation included in the schedule information is the sum of the travel time from a location where the transport device exists before the transport operation to a location from which the transport operation originates and the time required for the transport operation; a constraint equation that constrains that the work time of the plurality of transport devices in any evaluation section is equal to or less than the maximum work time of the transport devices in the evaluation section; and a constraint equation that constrains that the value obtained by subtracting the amount of delivery delay in the evaluation section from the work time of the transport device in any evaluation section is equal to or less than the available work time in the evaluation section; an objective function definition unit that sets, as an objective function, a weighted sum of a formula for calculating a sum of maximum values of the operation times of the transportation devices in a plurality of the evaluation sections and a formula for calculating a sum of the delivery delay amounts of the transportation devices in a plurality of the evaluation sections; an allocation plan optimization unit that calculates an allocation plan of the transportation operations to the transportation devices that minimizes the objective function while satisfying the constraints; A resource allocation and work processing sequence planning device comprising:
2. the allocation plan optimization unit divides a target period for which the allocation plan is to be created into small sections, and sets the entire range of any plurality of consecutive small sections as the evaluation section, thereby setting a plurality of evaluation sections, and calculates the allocation plan so as to minimize a total value of the maximum values of the operation times for each of the set plurality of evaluation sections.
2. The resource allocation and work processing sequence planning device according to claim 1.
3. the allocation plan optimization unit divides a target period for which the allocation plan is to be created into small sections, and when the entire range of any plurality of consecutive small sections among the small sections is set as the evaluation section, calculates the amount of delivery delay of the transportation equipment for the transportation work whose start time and delivery date fall within the evaluation section; 2. The resource allocation and work processing sequence planning device according to claim 1.
4. When the evaluation section includes the first subsection of the target period, the allocation plan optimization unit calculates the amount of delivery delay of the transportation equipment for the transportation operation whose delivery date falls within the evaluation section and whose start time for the transportation operation is set before the evaluation section.
4. The resource allocation and work processing sequence planning device according to claim 3.
5. the allocation plan optimization unit calculates the amount of delivery delay of the transportation equipment by treating the transportation operations whose delivery dates are set before the target period as the transportation operations belonging to one group.
5. A resource allocation and work processing sequence planning device according to claim 3 or 4.
6. acquiring layout information of a location where the luggage is to be transported, schedule information of the luggage transport work, and information of a plurality of transport devices that transport the luggage; a step of setting, as constraint conditions, the following constraint equations: a constraint equation that constrains allocation of a load to be transported, which is included in the schedule information, to any of the plurality of transport devices; a constraint equation that constrains that the time required for a transport operation included in the schedule information is the sum of the travel time from the location where the transport device exists before the transport operation to the location of the transport source of the transport operation and the time required for the transport operation; a constraint equation that constrains that the work time of the plurality of transport devices in any evaluation section is equal to or less than the maximum work time of the transport devices in the evaluation section; and a constraint equation that constrains that the value obtained by subtracting the amount of delivery delay in the evaluation section from the work time of the transport device in any evaluation section is equal to or less than the available work time in the evaluation section; setting a weighted sum of a formula for calculating a sum of maximum values of the operation times of the transportation devices in the plurality of evaluation sections and a formula for calculating a sum of the delivery delay amounts of the transportation devices in the plurality of evaluation sections as an objective function; calculating an allocation plan of the transportation operations to the transportation devices that minimizes the objective function while satisfying the constraints; A resource allocation and work processing sequence planning method with
7. On the computer, acquiring layout information of a location where the luggage is to be transported, schedule information of the luggage transport work, and information of a plurality of transport devices that transport the luggage; a step of setting, as constraint conditions, the following constraint equations: a constraint equation that constrains allocation of a load to be transported, which is included in the schedule information, to any of the plurality of transport devices; a constraint equation that constrains that the time required for a transport operation included in the schedule information is the sum of the travel time from the location where the transport device exists before the transport operation to the location of the transport source of the transport operation and the time required for the transport operation; a constraint equation that constrains that the work time of the plurality of transport devices in any evaluation section is equal to or less than the maximum work time of the transport devices in the evaluation section; and a constraint equation that constrains that the value obtained by subtracting the amount of delivery delay in the evaluation section from the work time of the transport device in any evaluation section is equal to or less than the available work time in the evaluation section; setting a weighted sum of a formula for calculating a sum of maximum values of the operation times of the transportation devices in the plurality of evaluation sections and a formula for calculating a sum of the delivery delay amounts of the transportation devices in the plurality of evaluation sections as an objective function; calculating an allocation plan of the transportation operations to the transportation devices that minimizes the objective function while satisfying the constraints; A program that executes processing including
Citation Information
Patent Citations
System and method for warehouse work plan creation
JP2012086983A
Schedule preparation device, method, and program
JP2019191803A
Planning system, planning method, and program
JP2022045024A
Palette conveyance layout information generating device, generating method and generating program
JP2020111455A
Cited By
Order assignment control system and order assignment control method
WO2026088568A1