【0008】 本発明の貼着装置によれば、基板に対するACFの貼着状態の検査をしつつ、生産効率を高めることができる。
Smart Images

Figure 2024144182000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a bonding device and an inspection method. [Background technology]
[0002] When electronic components such as ICs (Integrated Circuits), COFs (Chip on Films) with ICs mounted, and FPCs (Flexible Printed Circuits) are bonded to a substrate such as a display panel via ACFs (Anisotropic Conducting Films), the ACF is first bonded to the substrate using an ACF bonding device, and then the electronic components are crimped (bonded). The ACF to be bonded to the panel must be properly bonded in a predetermined position. For this reason, after the ACF is bonded, the bonding condition is conventionally inspected based on an image of the ACF. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] Japanese Patent Application Publication No. 9-34372 Summary of the Invention [Problem to be solved by the invention]
[0004] In such a bonding device, from the viewpoint of inspection efficiency and reflection of the inspection results in the bonding process, it is considered to inspect the bonding state on the bonding device. Also, from the viewpoint of bonding efficiency, it is considered to feed and process a plurality of boards. For example, it is considered to improve production efficiency by holding two boards on one stage and bonding ACF to the two boards. However, in this case, there is a misalignment in the postures of the two boards held on the stage, which may affect the inspection and cause problems in the inspection. For this reason, if the posture of the board is corrected and then an image is taken to inspect the bonding state, the takt time is not improved and production efficiency is suppressed.
[0005] The embodiments of the present invention have been made to solve the above-mentioned problems, and an object of the present invention is to provide an attachment device and attachment method that can improve production efficiency while inspecting the attachment state of an ACF to a substrate. [Means for solving the problem]
[0006] An embodiment of the present invention is an attachment device that attaches an ACF to a substrate, the attachment device comprising: a stage that holds a plurality of substrates; a bonding unit that bonds an ACF to each of the plurality of substrates; a supply unit that supplies the ACF to the bonding unit; a drive mechanism that aligns the substrate and the bonding unit by changing the relative position of the stage with respect to the bonding unit; an imaging unit that images the ACF attached to the substrate; a determination unit that determines the inclination of the substrate in an image of another substrate captured by the imaging unit while the bonding unit is pressing the ACF onto the substrate; a correction unit that corrects the inclination of the substrate in the image based on the inclination determined by the determination unit; and an inspection unit that inspects the attachment state of the ACF based on the image whose inclination has been corrected by the correction unit.
[0007] The mounting method of the embodiment includes a holding process in which a stage holds multiple substrates, a first bonding process in which a bonding unit bonds an ACF to the substrate, and a second bonding process in which the bonding unit bonds an ACF to another substrate. During the second bonding process, the following processes are performed: a tilt determination process in which a determination unit determines the tilt of the substrate in an image captured by an imaging unit of the ACF affixed to the substrate; a correction process in which a correction unit corrects the tilt of the substrate in the image based on the tilt determined by the determination of the determination unit; and an inspection process in which the attachment state of the ACF is inspected based on the image in which the tilt has been corrected by the correction unit. Effect of the Invention
[0008] According to the bonding device of the present invention, it is possible to improve production efficiency while inspecting the state in which the ACF is bonded to the substrate. [Brief description of the drawings]
[0009] [Figure 1] 1 is a plan view showing a substrate and an ACF to be pressure-bonded in an embodiment. FIG. [Diagram 2] FIG. 2 is a front view showing the crimping device according to the embodiment. [Diagram 3] FIG. 2 is a side view showing the crimping device according to the embodiment. [Figure 4] 1A is an explanatory diagram showing image processing during an inspection, and FIG. 1B is an example of a screen before correction and FIG. [Diagram 5] 1A is an explanatory diagram showing the judgment process in the inspection, and shows an example of a screen in a normal case (A), an example of a screen in a case where there is a turnover (B), and an example of a screen in a case where there is a misalignment (C). [Figure 6] FIG. 1 is an explanatory diagram showing the procedure for crimping and inspecting an ACF. [Figure 7] 4 is a flowchart showing a procedure of crimping by the crimping device. [Figure 8] 10 is a flowchart showing a procedure of inspection by the crimping device. [Figure 9] FIG. 13 is an explanatory diagram for determining the inclination of the substrate from the alignment marks. [Figure 10] FIG. 13 is an explanatory diagram of a mode in which a plurality of ACFs are attached to a substrate and then inspected. [Figure 11] FIG. 1 is an explanatory diagram of an embodiment in which ACF is attached to three substrates. [Figure 12] FIG. 13 is an explanatory diagram of an embodiment in which one pressure-bonding part bonds ACF to multiple substrates. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0010] An embodiment of the present invention (hereinafter, referred to as the present embodiment) will be specifically described with reference to the drawings. Note that the drawings are schematic diagrams, and the sizes, ratios, and the like of each part include exaggerated parts for ease of understanding.
[0011] [Applicable object] With reference to FIG. 1, a substrate 1 and an ACF 2 to be attached according to this embodiment will be described. The substrate 1 is a display panel having a display area such as an organic EL display. A plurality of ACFs 2 are attached to the substrate 1 of this embodiment. However, a single ACF 2 may be attached. An electrode, which is a conductive portion, is provided along one side of one surface of the substrate 1. The area where the electrode is provided is the attachment area AR to which the ACF 2 is attached. In this embodiment, the substrate 1 has a plurality of attachment areas AR set in a direction along the edge of the substrate 1. For example, in FIG. 1, a substrate 1A is held on the left side L when viewed from the front, and a substrate 1B is held on the right side R on a stage 20 described later, and four attachment areas AR1 to AR4 are set on each substrate 1. An alignment mark is provided on the substrate 1 (see FIG. 9), and the positions of the plurality of attachment areas AR are set based on the position of the alignment mark.
[0012] ACF2 is an anisotropic conductive material, a film made by dispersing conductive particles in a base material. A thermosetting resin that hardens when heated is used as the base material. ACF2 can be sandwiched between electronic components and heat-pressed to achieve electrical and mechanical connection between the electronic components and the board 1. ACF2 is in the form of a long, thin tape, with release tape attached to one side and an adhesive surface on the other side. It is cut to an appropriate length and the adhesive surface is attached to the board 1.
[0013] [composition] The configuration of the bonding device 10 of this embodiment will be described with reference to Figs. 2 and 3. The bonding device 10 is a device for bonding the ACF 2 to the substrate 1. In Figs. 2 and 3, the bonding direction by the bonding device 10 is the Z direction, and the directions perpendicular to each other in a plane perpendicular to the Z direction are the X direction and the Y direction. The Y direction is the direction between the front and the back in Fig. 2. When the bonding device 10 is installed so that the Z direction is the vertical direction, the XY plane becomes a horizontal plane. In this case, the Z direction is the height direction, and the installation surface side is called the bottom and the opposite side is called the top. The rotation direction parallel to the XY plane is called the θ direction. Furthermore, in the figure, the side indicated by the white arrow is the front, and the left side from the front is called the L side and the right side is called the R side. The bonding device 10 has a stage 20, a bonding unit 30, a supply unit 40, a drive mechanism 50, an imaging unit 60, and a control device 100. In this embodiment, an example in which two (a pair of) substrates are fed into the bonding device 10 will be described below.
[0014] [stage] As shown in Figs. 1 to 3, the stage 20 holds a pair of substrates 1. More specifically, the stage 20 is a flat rectangular platform that supports the substrates 1 in the horizontal direction. Although not shown, the stage 20 has a plurality of holes connected to a vacuum source formed on the upper surface. This allows the stage 20 to adsorb and hold the pair of substrates 1 arranged at intervals in the X direction. Each substrate 1 is held such that the area where the ACF 2 is pressure-bonded protrudes from the edge of the stage 20. The area where the L-side substrate 1 is held is defined as holding position P1, and the area where the R-side substrate 1 is held is defined as holding position P2. The substrate 1 held at holding position P1 is defined as substrate 1A, and the substrate 1 held at holding position P2 is defined as substrate 1B.
[0015] [Crimping part] The pressure bonding unit 30 pressure bonds the ACF 2 to the substrate 1. The pressure bonding unit 30 includes a pressure bonding head 31, a head moving mechanism 32, and a backup unit 33.
[0016] In this embodiment, one pressure bonding unit 30 is provided for each of the pair of substrates 1. That is, a pair of two pressure bonding units 30 corresponding to each of the pair of substrates 1 is provided. The pressure bonding head 31, head moving mechanism 32, supply unit 40 (described later), and imaging unit 60 of each pressure bonding unit 30 are supported by a base 35 provided individually for each of the pair of substrates 1. The base 35 is provided with a detection unit such as a linear scale (linear encoder) and a rotary scale (rotary encoder) on the XY axis, and is moved independently in the X direction and the Y direction by a base moving mechanism 36 constituted by a ball screw mechanism driven by a motor, for example, to perform positioning with respect to the adhesion area AR of the corresponding substrate 1. Hereinafter, the base 35 corresponding to the substrate 1A is referred to as base 35A, and the base 35 corresponding to the substrate 1B is referred to as base 35B. The base moving mechanism 36 corresponding to the substrate 1A is referred to as 36A, and the base moving mechanism 36 corresponding to the substrate 1B is referred to as 36B.
[0017] (Crimping head) The compression head 31 sandwiches the ACF 2 supplied between the substrate 1 by a supply unit 40 described later and the compression head 31, and compresses the ACF 2 onto the substrate 1. The compression head 31 is a rectangular parallelepiped block. A flat pressure surface is provided horizontally on the bottom surface of the compression head 31. The compression heads 31 are aligned in the X direction and provided for each of the pair of substrates 1. The L side is referred to as compression head 31A, and the R side is referred to as compression head 31B.
[0018] (Head movement mechanism) The head moving mechanism 32 moves the pressure bonding head 31 in a direction toward and away from the substrate 1. The head moving mechanism 32 of this embodiment moves the pressure bonding head 31 in the Z direction. The head moving mechanism 32 is, for example, a ball screw mechanism driven by a motor.
[0019] (Backup Department) Backup unit 33 holds ACF 2 and substrate 1 between it and compression head 31, and supports substrate 1 when ACF 2 is compressed onto substrate 1. Backup unit 33 has a flat support surface that faces the pressure surface of compression head 31.
[0020] [Supply Department] The supply unit 40 supplies ACF 2 between the compression bonding unit 30 and the substrate 1. The supply units 40 are provided on the L side and the R side corresponding to the compression bonding heads 31A and 31B. The supply unit 40 has a supply reel 41, a recovery reel 42, a guide roller 43, and a cutting unit 44.
[0021] (Supply reel) The supply reel 41 is a reel on which the ACF 2 is wound and which rotates to feed out the ACF 2. The supply reel 41 is rotatably supported by the base body . (Recovery reel) The recovery reel 42 is a reel that winds up and recovers the release tape of the ACF 2. The recovery reel 42 is supported by the base 35 so as to be rotatable.
[0022] (Guide roller) Guide roller 43 is a roller that guides ACF 2 supplied from supply reel 41 so that the ACF 2 passes between pressure bonding unit 30 and substrate 1 and is collected by collection reel 42. A plurality of guide rollers 43 are attached to base 35. Although not shown, the path through which ACF 2 passes is provided with a feed mechanism that feeds out ACF 2, a tension mechanism that applies tension to ACF 2, and a peeling mechanism that peels off the release tape of ACF 2.
[0023] (cutting part) The cutting unit 44 cuts (half-cuts) the ACF 2 to a degree that does not cut the release tape. The cutting unit 44 has a cutter 44a and a backup member 44b. The cutter 44a is a member that comes into contact with the ACF 2 and cuts it. The cutter 44a has a blade at its tip that moves toward and away from the ACF 2 by an elevation mechanism (not shown). The backup member 44b is a rectangular parallelepiped block. The backup member 44b has a flat surface on the bottom surface of the block that contacts the ACF 2 and sandwiches it between the backup member 44b and the cutter 44a. The ACF 2 is cut by the cutter 44a to a length that allows it to be attached to the substrate 1.
[0024] [Drive mechanism] The driving mechanism 50 aligns the pressure-bonding part 30 and the substrate 1 by changing the relative position of the stage 20 with respect to the pressure-bonding part 30. The driving mechanism 50 is a device that moves the stage 20 in the X direction, the Y direction, and the θ direction. For example, an XYθ-axis stage mechanism driven by a ball screw mechanism and a rotation mechanism using a servo motor as a driving source can be used as the driving mechanism 50. Although not shown, the driving mechanism 50 is provided with detection units such as a linear scale (linear encoder) and a rotary scale (rotary encoder) on the XYθ axes, and is configured to be able to detect and control the amount of movement in the XYθ directions.
[0025] [Imaging unit] The imaging section 60 images the substrate 1. The imaging section 60 has a camera 61. The camera 61 is disposed above the surface of the substrate 1 to which the ACF 2 is attached, is positioned relative to the substrate 1 by the movement of the substrate 35 by the substrate movement mechanism 36, and images the substrate 1 facing downward. When imaging the substrate 1, the imaging is performed so that the alignment mark of the substrate 1 falls within the field of view, and when imaging the ACF 2 attached to the substrate 1, the imaging is performed so that the edge line (outline) of the substrate 1 is included along with the entire ACF 2. Hereinafter, the camera 61 corresponding to the substrate 1A is referred to as camera 61A, and the camera 61 corresponding to the substrate 1B is referred to as camera 61B.
[0026] [Control device] The control device 100 is a device that controls the bonding device 10. The control device 100 is configured, for example, by a dedicated electronic circuit or a computer that operates according to a predetermined program. In other words, the control device 100 controls the operations of the stage 20, the pressure bonding unit 30, the supply unit 40, the drive mechanism 50, and the imaging unit 60.
[0027] The control device 100 stores programs that control the operation timing and amount of the vacuum source of the stage 20, the head moving mechanism 32 of the bonding unit 30, the base moving mechanism 36, the cutting unit 44 of the supply unit 40, the delivery mechanism, the tension mechanism, the peeling mechanism, the drive mechanism 50, and the camera 61. The control device 100 controls each unit by reading and executing the programs and data using a processing device such as a PLC or a CPU. By changing the programs and data, it is possible to accommodate a wide variety of specifications for the substrate 1 and ACF 2 to be bonded.
[0028] The control device 100 of this embodiment has a determination unit 110, a correction unit 120, and an inspection unit 130. The determination unit 110 determines the inclination of the substrate 1 in the image of the substrate 1. In this embodiment, a virtual line VL that serves as a reference when adhering the ACF 2 is set in advance. The virtual line VL is one of the coordinate systems set in the adhering device, and is parallel to the X direction in the adhering device 10 of this embodiment. The adhering area AR of the substrate 1 is provided so as to be parallel to the virtual line VL, and the ACF 2 is supplied between the pressure bonding unit 30 and the substrate 1 so as to be parallel to the virtual line VL, and is adhered onto the adhering area AR.
[0029] The virtual line VL is set at the design position of the outer edge of the substrate 1 when the ACF 2 is attached. The outer edge is the edge to which the ACF 2 is attached (see FIG. 1). The substrate 1 placed and held on the stage 20 is not necessarily placed at the design position, and may be tilted in the rotation direction in the horizontal plane. For example, as shown in FIG. 4(A), the substrate 1 may be placed on the stage 20 tilted with respect to the virtual line VL. The determination unit 110 detects the angle θ between the virtual line VL and the edge line of the substrate 1 (the outer periphery of the substrate 1) as the tilt. The determination unit 110 also detects the angle θ between the virtual line VL and the substrate 1 as the tilt from an image of an alignment mark provided on the substrate 1. In other words, the determination by the determination unit 110 means determining the relative angle (angle θ) between the reference line, which is the virtual line VL, and the substrate 1.
[0030] The correction unit 120 corrects the inclination of the substrate 1 in the image. As described later, whether the ACF 2 is attached correctly is judged by comparing the image of the captured ACF 2 with a template showing a normal state. An image captured when the substrate 1 is in the state shown in FIG. 4(A) corresponds to the field of view S shown by the two-dot chain line. Since the template is based on the design position, a correct comparison cannot be made even if this image is compared with the template because the ACF 2 in the image is inclined. Therefore, as shown in FIG. 4(B), the image is rotated by the inclination (angle θ) calculated by the judgment unit 110, and the edge line of the substrate 1 is aligned with the virtual line VL, so that the ACF 2 in the image can be compared with the template (image G after rotation is shown by the dotted line). Including the reference position of the substrate 1 in the captured image allows the deviation from the virtual line VL in the XY direction to be corrected. For example, as shown in FIG. 4(A), the deviation in the XY directions can be corrected based on the designed angle VL0 when the substrate 1 is placed on the stage 20 and the position P' (FIG. 4(B)) after rotation of the angle P of the substrate 1 in the captured image.
[0031] The inspection unit 130 inspects the attachment state of the ACF2 based on the image corrected by the correction unit 120. The inspection unit 130 prepares a template with an image size equal to the image capture size, for example. In this template, as shown in FIG. 5(A), the area where the ACF2 is attached is set as a reference area RA indicated by a white two-dot chain line. That is, the reference area RA is set to a similar shape and the same size as the ACF2 to be attached (it is drawn exaggerated for the purpose of explanation). This reference area RA is set at the center of the template, which is a predetermined area. Therefore, the image of the ACF2 on the board 1 that is correctly attached coincides with this reference area RA. By binarizing the captured image, the area of the image where the ACF2 is attached is set to white, and the area of the image other than the area where the ACF2 is attached is set to black as the luminance of the board 1.
[0032] Therefore, as shown in FIG. 5(B), if the ACF 2 is correctly attached, the white part of the ACF 2 fits within the reference area RA in the image. In other words, the reference area RA is 100% white. The inspection unit 130 inspects the attachment state based on the ratio of white or black in the reference area RA, that is, the area ratio. For example, if the ACF 2 is not rectangular (ACF 2 is turned up) as shown in FIG. 5(C) or is shifted or tilted from the correct position as shown in FIG. 5(D), the black part in the reference area RA becomes large. For this reason, the ratio of the black part to the entire reference area RA is set as a threshold value, and if this threshold value is exceeded, it is determined that the attachment is abnormal. If it is determined that the attachment is abnormal, the operator can stop the attachment device 10, remove the ACF 2, and attach it again (repair work).
[0033] Although not shown, the control device 100 has a memory unit that stores information necessary for the control of this embodiment, an input unit that inputs information, and a display unit that displays information. The memory unit stores the virtual line VL, the reference area RA, a threshold value, etc. The display unit displays the captured image, the virtual line VL, and the reference area RA. The display unit can also display the inspection results of the inspection unit 130. For example, if the inspection result is abnormal, the display unit will display that fact, and an operator who sees this can stop the bonding device 10 and perform repair work.
[0034] [Operation] An operation example of this embodiment will be described with reference to Figs. 6 to 8 in addition to Figs. 1 to 5. Fig. 6 is an explanatory diagram showing the procedure for pressing and inspecting the ACF 2. Fig. 7 is a flow chart showing the operation procedure of the adhering device 10, and Fig. 8 is a flow chart showing the inspection procedure.
[0035] 6(A), a pair of substrates 1A and 1B are placed on holding positions P1 and P2 on a stage 20 by a transport device (not shown) so that the adhesion area AR of the substrate 1 protrudes from the edge of the stage 20, and are adsorbed and held by negative pressure (holding step). At this time, a difference in attitude (angle, position) between the substrates 1A and 1B may occur due to inclination or deviation from the holding positions P1 and P2.
[0036] In this embodiment, a pair of pressure bonding units 30 are prepared corresponding to the pair of substrates 1, respectively. The bonding area AR for bonding the ACF2 of one substrate 1 is positioned parallel to the imaginary line VL, and one pressure bonding unit 30 is positioned directly above it to bond the ACF2. Next, the bonding area AR for bonding the ACF2 of the other substrate 1 is positioned parallel to the imaginary line VL, and the other pressure bonding unit 30 is positioned directly above it to bond the ACF2. While the ACF2 is being bonded to the other substrate 1, new ACF2 is supplied from a supply unit 40 to one pressure bonding unit 30.
[0037] Also, the ACF 2 attached to one of the substrates 1 is imaged, and the captured image is used to inspect whether the ACF 2 has been attached correctly. After the ACF 2 has been attached to the other substrate 1, the attachment area AR of one of the substrates 1 where the ACF 2 is attached is positioned parallel to the imaginary line VL, and one of the pressure bonding units 30 is repositioned directly above it to attach the next ACF 2 to the one of the substrates 1. At this time, new ACF 2 is supplied to the other pressure bonding unit 30. At the same time, the ACF 2 attached to the other substrate 2 is imaged, and the captured image is used to inspect whether the ACF 2 has been attached correctly.
[0038] In this manner, application of ACF2 to one substrate 1 and application of ACF2 to the other substrate are alternately performed, while ACF2 is supplied and inspected at the same time. This operation is repeated until application of ACF2 to all of the ACF2 application areas AR is completed. Once application of all of the ACF2 is completed, the pair of substrates 1 is transported by the transport device, and a new pair of substrates 1 is supplied. This is an outline of the operation of this embodiment, which will be described in detail below.
[0039] As described above, when the substrate 1 is placed on the stage by the transport device, the ACF 2 supplied from the supply reel 41 is cut to an appropriate length by the cutting section 44 and sequentially fed between the crimping head 31 and the substrate 1 by the feeding mechanism.
[0040] In this state, the base 35A is moved by the base moving mechanism 36A, and the camera 61A captures an image of the substrate 1A. Then, the determination unit 110 detects the alignment mark of the substrate 1A from the captured image, obtains the inclination of the substrate 1A from the position of the alignment mark, and rotates the stage 20 by the drive mechanism 50 so that the inclination of the substrate 1A becomes parallel to the pressure bonding head 31A (parallel to the virtual line VL).
[0041] In addition, the position of the attachment area AR1 of the substrate 1A (L side) is obtained from the position of the alignment mark, and the driving mechanism 50 moves the stage 20 so that the attachment area AR1 of the substrate 1A (L side) is positioned on the support surface of the backup unit 33. Next, the driving mechanism 50 lowers the stage 20, and the bottom surface of the substrate 1A is placed on the support surface of the backup unit 33.
[0042] At the same time, the base 35A is moved by the base moving mechanism 36A so that the pressure bonding head 31A is located directly above the bonding area AR1 of the substrate 1A (L side). Thereafter, as shown in Fig. 7, the pressure bonding head 31A is lowered to bond the ACF2 to the bonding area AR1 (first pressure bonding step: step S101). After bonding, the pressure bonding head 31A rises, and the stage 20 is also raised by the drive mechanism 50, and the substrate 1A is separated from the backup unit 33.
[0043] Next, the base 35B is moved by the base moving mechanism 36B, and the camera 61B captures an image of the R-side substrate 1B. Then, the position of the alignment mark of the substrate 1B is detected from the captured image, and the inclination of the substrate 1B is obtained from the position of the alignment mark. Then, the driving mechanism 50 rotates the stage 20 so that the inclination of the substrate 1B becomes parallel to the pressure bonding head 31B (so that the inclination becomes parallel to the virtual line VL) as shown in FIG. 6(B).
[0044] In addition, the position of the attachment area AR1 of the substrate 1B (R side) is obtained from the position of the alignment mark, and the driving mechanism 50 moves the stage 20 so that the attachment area AR1 of the substrate 1B (R side) is positioned on the support surface of the backup unit 33. Next, the driving mechanism 50 lowers the stage 20, and the bottom surface of the substrate 1B is placed on the support surface of the backup unit 33.
[0045] At the same time, the base 35B is moved by the base moving mechanism 36B so that the pressure bonding head 31B is located directly above the bonding area AR1 of the substrate 1B (R side). Thereafter, as shown in Fig. 7, the pressure bonding head 31B is lowered to bond the ACF2 to the bonding area AR1 (second pressure bonding step: step S102). After bonding, the pressure bonding head 31B rises, and the stage 20 is also raised by the drive mechanism 50, and the substrate 1B is separated from the backup unit 33.
[0046] Then, while the substrate 1B (R side) is being attached, as shown in Fig. 6(C), the substrate moving mechanism 36A moves the substrate 35A, and the camera 61A comes directly above the attachment area AR1 of the substrate 1A (L side) held at the holding position P1, and captures an image of the ACF2 attached to the attachment area AR1 of the substrate 1A (ACF2 attached in the first pressure bonding step: step S101). The inspection unit 130 performs an inspection based on the captured image. The imaging area of the camera 61A is indicated by a dashed line in Fig. 6(C).
[0047] That is, as shown in the flow chart of FIG. 8, the determination unit 110 determines the inclination angle θ of the edge line of the substrate 1A in the captured image with respect to the virtual line VL (see FIG. 4(A)) (determination step: step S201), and the correction unit 120 rotates the image (see FIG. 4(B)) so as to correct the inclination (correction step: step S202). Then, as shown in FIG. 5(B) for the template (see FIG. 5(A)), if the ratio of the black portion of the binarized image in the reference area RA is equal to or less than a threshold value (YES in step S203), the adhesion state is determined to be normal (inspection step: step S204). As shown in FIG. 5(C) and (D), if the ratio exceeds the threshold value (NO in step S203), the adhesion state is determined to be abnormal (inspection step: step S205).
[0048] That is, the inspection unit 130 superimposes the image of the ACF 2 captured on the board 1A, which has been corrected by the correction unit 120, on the template, and judges whether the superposition is normal or abnormal, thereby inspecting the attachment state of the ACF 2.
[0049] As shown in the flowchart of Fig. 7, if an abnormality is determined (YES in step S103), the bonding device 10 is stopped (step S114) and repair work is performed. If an abnormality is determined (NO in step S103), it is checked whether there is a next bonding area AR (step S104). If there is a bonding area AR2 on the L-side substrate 1A that is the next bonding area AR (YES in step S104), bonding of that area is performed.
[0050] If there is no next adhesion area AR (NO in step S104), the last adhesion area AR on the R side that was adhered is inspected in the same manner as described above (step S112), and if it is determined to be abnormal (YES in step S113), the adhesion device 10 is stopped (step S114) and repair work is performed. If it is determined to be normal (NO in step S113), the process ends.
[0051] Continuing with the explanation of the case where there is a next adhesion area AR. In order to perform adhesion in adhesion area AR2 on substrate 1A on the L side, which is the next adhesion area AR, substrate moving mechanism 36A moves substrate 35A and camera 61A captures an image of substrate 1A, as shown in Fig. 6(D). Then, from the captured image, the position of the alignment mark on substrate 1A is detected, and the inclination of substrate 1A is found from the position of the alignment mark. Then, drive mechanism 50 rotates stage 20 so that the inclination of substrate 1A becomes parallel to pressure bonding head 31A (so that it becomes parallel to virtual line VL).
[0052] In addition, the position of the adhesion area AR2 of the substrate 1A (L side) is obtained from the position of the alignment mark, and the stage 20 is moved by the driving mechanism 50 so that the adhesion area AR2 of the substrate 1A is positioned on the support surface of the backup section 33, and the base 35A is moved by the base moving mechanism 36A so that the bonding head 31A is directly above the adhesion area AR2 of the substrate 1A (step S105).
[0053] The rotation of stage 20 and the positioning of adhesion area AR2 at this time may be performed based on the image captured when ACF2 is adhered to adhesion area AR1 in step 101, or the position of the alignment mark on substrate 1A and the rotational position of stage 20 at that time may be stored and the rotation may be performed based on those positions.
[0054] Thereafter, as shown in FIG. 7, the pressure bonding head 31A descends to bond the ACF2 to the bonding area AR2 (first pressure bonding step: step S106). After bonding, the pressure bonding head 31A rises, and the stage 20 also rises by the drive mechanism 50, and the substrate 1A is separated from the backup unit 33. During this bonding, as shown in FIG. 6(E), the base 35B is moved by the base moving mechanism 36B, and the camera 61B comes directly above the bonding area AR1 of the substrate 1B (R side) held at the holding position P2, and captures an image of the ACF2 (ACF2 bonded in the second pressure bonding step: step S102) bonded to the bonding area AR1 of the substrate 1B, and the inspection unit 130 performs inspection based on this image. The imaging area of the camera 61B is indicated by a dashed line in FIG. 6(E). This inspection procedure is similar to the procedure shown in FIG. 8 above.
[0055] 7, if it is determined that there is an abnormality (YES in step S107), the bonding device 10 is stopped (step S114) and repair work is performed. If it is determined that there is a normality (NO in step S107), the base 35B is moved by the base moving mechanism 36B, and the camera 61B captures an image of the substrate 1B. Then, from the captured image, the position of the alignment mark of the substrate 1B is detected, and the inclination of the substrate 1B is found from the position of the alignment mark, and the driving mechanism 50 rotates the stage 20 so that the inclination of the substrate 1B becomes parallel to the pressure bonding head 31B (so that it becomes parallel to the virtual line VL).
[0056] The substrate 1 is bonded to a pair of substrates 1. Therefore, it is necessary to check whether there is a next bonding area only on the side of one substrate 1 where bonding started first, and after bonding to one substrate 1, a bonding area is always left on the other substrate 1. Therefore, it is not necessary to check whether there is a bonding area on substrate 1B.
[0057] The position of the adhesion area AR2 of the substrate 1B (R side) is obtained from the position of the alignment mark, and the stage 20 is moved by the drive mechanism 50 so that the adhesion area AR2 of the substrate 1B is positioned on the support surface of the backup part 33, and the base moving mechanism 36B moves the base 35B so that the pressure bonding head 31B is located directly above the adhesion area AR2 of the substrate 1B (step S108).
[0058] The rotation of stage 20 and the positioning of adhesion area AR2 at this time may be performed based on the image captured when ACF2 is adhered to adhesion area AR1 in step 102, or the positions of the alignment mark on substrate 1A and the rotational position of stage 20 at that time may be stored and the positions may be performed based on those positions.
[0059] Thereafter, the pressure bonding head 31B descends to bond the ACF2 to the bonding area AR2 (second pressure bonding step: step S109). After bonding, the pressure bonding head 31B rises, and the stage 20 also rises due to the drive mechanism 50, and the substrate 1B is separated from the backup part 33.
[0060] During this bonding, as described above, the base 35A is moved by the base moving mechanism 36A, and the camera 61A is positioned directly above the bonding area AR2 of the substrate 1A (L side) held at the holding position P1, and an image of the ACF2 bonded to the bonding area AR2 of the substrate 1A (ACF2 bonded in the first pressure bonding step: step S106) is captured, and the inspection unit 130 performs an inspection. The inspection procedure is the same as that shown in FIG. 8 above.
[0061] If it is determined that there is an abnormality (YES in step S110), the bonding device 10 is stopped (step S114) and repair work is performed. If it is determined that there is a normal bonding area (NO in step S110), it is checked whether there is a next bonding area AR (step S111). If there is a next bonding area AR3 (L-side substrate 1A) (YES in step S111), the processes from step S105 to step S111 are repeated.
[0062] If there is no next adhesion area AR (NO in step S111), the last adhesion area AR4 on the R side that was adhered is inspected in the same manner as described above (step S112), and if it is determined to be abnormal (YES in step S113), the adhesion device 10 is stopped (step S114) and repair work is performed. If it is determined to be normal (NO in step S113), the process ends.
[0063] [effect] (1) This embodiment relates to a bonding device 10 that bonds an ACF2 to a substrate 1, and includes a stage 20 that holds multiple substrates 1, a bonding section 30 that bonds an ACF to each of the multiple substrates 1, a supply section 40 that supplies ACF2 to the bonding section 30, a drive mechanism 50 that aligns the substrate 1 and the bonding section 30 by changing the relative position of the stage 20 with respect to the bonding section 30, an imaging section 60 that images the ACF bonded to the substrate 1, a determination section 110 that determines the inclination of the substrate 1 in an image of another substrate 1 captured by the imaging section 60 while the bonding section 30 is bonding the ACF2 to the substrate 1, a correction section 120 that corrects the inclination of the substrate 1 in the image based on the inclination determined by the determination of the determination section 110, and an inspection section 130 that inspects the bonding state of the ACF2 based on the image corrected by the correction section 120.
[0064] In addition, the inspection method of this embodiment includes a holding process in which the stage 20 holds multiple substrates 1, a first crimping process in which the crimping unit 30 crimps the ACF 2 onto the substrate 1, and a second crimping process in which the crimping unit 30 crimps the ACF 2 onto another substrate 1.The inspection method also includes a tilt determination process during which the determination unit 110 determines the tilt of the substrate 1 in an image captured by the imaging unit 60 of the ACF 2 attached to the substrate 1, a correction process in which the correction unit 120 corrects the tilt of the substrate 1 in the image based on the tilt determined by the determination of the determination unit 110, and an inspection process in which the attachment state of the ACF 2 is inspected based on the image corrected by the correction unit 120.
[0065] In this way, while the ACF 2 is being pressure-bonded to the substrate 1, the state of adhesion of the ACF 2 to the other substrates 1 can be inspected. In other words, as soon as the step of pressure-bonding the ACF 2 to the substrate 1 is completed, the step of pressure-bonding the ACF 2 to the other substrates 1 can be immediately performed. Therefore, even if the postures of the multiple substrates 1 held on the stage 20 are shifted and not aligned, the substrates 1 for which the pressure-bonding step has been completed can be accurately inspected, and production efficiency can be improved.
[0066] In the present embodiment, in order to increase productivity, when a plurality of substrates 1 are held on one stage 20, ACF 2 is attached, and the attached ACF 2 is inspected, the orientations of the plurality of substrates 1 held on the stage 20 are often not aligned. Since ACF 2 needs to be attached to a predetermined area of the substrate 1, the orientation of the substrate 1 is aligned with respect to the bonding section 30. That is, in order to position the attachment area AR of the substrate 1 at the bonding section 30, one side of the substrate 1 on which the attachment area AR is located is aligned with a reference line aligned with the bonding section 30. When the orientation of one substrate 1 is aligned with the bonding section 30, the other substrates 1 are not aligned with respect to the bonding section 30.
[0067] When inspecting the attached ACF 2, if ACF inspection is performed immediately after ACF attachment (processing) to the substrate 1 is completed, the stage 20 cannot be moved (substrate position correction) until the ACF inspection is finished. Therefore, ACF cannot be attached to other substrates 1 placed on the stage 20, and the effect of placing multiple substrates 1 on the stage 20 is diminished.
[0068] If priority is given to attaching the ACF 2 to the other substrate 1, and after the ACF attachment to the substrate 1 is completed, the stage 20 is moved (aligned with the pressure bonding part 30 of the other substrate 1) to attach the ACF, the posture of the substrate 1 to which the ACF has already been attached will not be aligned with the reference line, and the attachment position and attachment direction will deviate from the reference positions, making it impossible to perform accurate inspection as is, leading to erroneous inspection. Therefore, it is not possible to perform accurate inspection by capturing an image of the ACF 2 already attached to the substrate 1 at the same time as attaching the ACF 2 to the other substrate 1. This reduces the effect of increasing productivity.
[0069] Once ACF 2 has been applied to other boards 1, the position of board 1 is adjusted to a reference line for the next application, and accurate inspection can be performed by taking an image of the applied ACF 2 at this time. However, after ACF application to board 1, the stage must be moved for each board and inspection must be performed, and application of ACF 2 and inspection cannot be performed in parallel, which limits the effect of increasing productivity.
[0070] In other words, if you try to perform ACF2 attachment and inspection in parallel, accurate inspection will not be possible, and to perform accurate inspection, ACF2 attachment and inspection cannot be performed in parallel. In either case, the effect of increasing productivity will be suppressed.
[0071] In this embodiment, another substrate 1 is positioned at the other pressure bonding section 30, and while the ACF 2 is being attached to the other substrate 1, an image of the ACF 2 attached to one substrate 1 is taken, and inspection is performed using the image. This makes it possible to improve productivity by supplying and processing a plurality of substrates 1. At this time, the orientation of the substrate 1 with the ACF 2 attached at the time of the image capture is detected from the captured image, and the orientation is corrected to match the reference position. This allows accurate inspection to be performed. In other words, attachment of the ACF 2 to the substrate 1 and inspection can be performed simultaneously, and accurate inspection can be performed.
[0072] (2) The determination unit 110 determines the inclination of the substrate 1 based on the edge line of the substrate 1 in the image. This reduces the amount of calculation and increases the processing speed compared to when the inclination of the substrate 1 is calculated by computation.
[0073] (3) Every time the inspection unit 130 adheres the ACF 2 to one location on the substrate 1, it inspects the ACF 2 adhered to one location on another substrate 1. This allows repair work to be carried out immediately if an abnormality is found in the adhesion.
[0074] [Variations] (1) The determination unit 110 may determine the inclination of the substrate 1 based on the alignment marks of the substrate 1 imaged by the imaging unit 60. For example, a line segment connecting multiple alignment marks of the substrate 1 may be found, and the inclination of the image may be corrected so that the line segment coincides with the virtual line VL.
[0075] 9(A), a plurality of alignment marks are provided on the substrate 1. In this embodiment, two alignment marks are provided. Of the plurality of substrates 1, the substrate 1A on the L side is provided with an alignment mark M1, and the substrate 1B on the R side is provided with an alignment mark M2. A plurality of alignment marks M1 on substrate 1A placed on stage 20 are detected to determine the inclination θa of substrate 1A, and the rotational position θ1 of stage 20 at that time is stored. Then, as shown in Fig. 9(B), to make substrate 1A parallel to virtual line VL, stage 20 is rotated by the inclination θa of substrate 1A. The rotational position θ2 of stage 20 at this time is stored as the rotational position of stage 20 when ACF2 is attached to substrate 1A.
[0076] The inclination of substrate 1B is found by detecting a plurality of alignment marks M2 on substrate 1B placed on stage 20 in the state shown in Fig. 9(B). Then, to make substrate 1B parallel to virtual line VL as shown in Fig. 9(C), stage 20 is rotated by the inclination θb of substrate 1B. At this time, the rotational position θ3 of stage 20 becomes θ2-θb, and this is stored as the rotational position of stage 20 when ACF2 is attached to substrate 1B.
[0077] Based on the inclination of substrate 1 thus obtained, the image of ACF 2 is rotated and corrected for inspection. As described above, the relative angle between substrates 1A and 1B is θb (the inclination of one substrate 1 when the other substrate is parallel to virtual line VL), and this is used as the correction angle for the image of ACF 2 of substrate 1 and the amount of rotation for positioning stage 20. This embodiment can also be applied in cases where it is difficult to determine the deviation in the XY directions, such as when the edge line of substrate 1 is imaged but the corners are not included.
[0078] In this embodiment, the inclination of substrate 1 is determined using an alignment mark provided on substrate 1, but if there is also an alignment mark in each attachment area AR, it is possible to use an imaging unit 60 with a narrow field of view, whose field of view is the attachment area AR, rather than using an imaging unit 60 with a wide field of view as used in Figure 9, thereby making it possible to create a cost-effective device.
[0079] 9, the inclination may be found based on the rotational position θ2 of the stage 20 when it is attached to the substrate 1, and then, by capturing an image of the alignment mark of the other substrate 1, the rotational position θ3 of the stage 20 when the stage 20 is positioned in the attachment area AR of the other substrate 1. According to this embodiment, the inclination can be found without finding the inclination from an image captured after the ACF 2 is attached.
[0080] (3) Each time the inspection unit 130 adheres the ACF 2 to multiple locations on a substrate 1, the inspection unit 130 may inspect the ACF 2 adhered to multiple locations on another substrate 1.
[0081] This will be explained with reference to Fig. 10. This embodiment has the same configuration as the above-mentioned embodiment, but the pair of substrates 1A, 1B has five adhesion areas AR1 to 5. In Fig. 10, the adhesion areas AR to which ACF2 is not attached are shown by dotted lines, and the adhesion areas AR to which ACF2 is attached are shown by solid lines.
[0082] As shown in FIG. 10(A), as in the above-described embodiment, the base 35A moves to capture an image of the substrate 1A, and then the stage 20 is moved to position the substrate 1A, and ACF2 is adhered to the multiple adhesion areas AR1 to AR5 of the substrate 1A.
[0083] Next, as shown in FIG. 10(B), after the base 35B moves and an image of the substrate 1B is taken, the stage 20 is moved to position the substrate 1B, and ACF2 is applied to the multiple application areas AR1 to AR5 of the substrate 1B.
[0084] Then, as shown in FIG. 10(C), while ACF2 is being adhered to adhesion areas AR1-AR5 of substrate 1B, camera 61A provided on base 35A captures images of the edge line of substrate 1A and the ACF2 adhered to adhesion areas AR1-5, and inspection unit 130 inspects the condition of ACF2 adhered to adhesion areas AR1-5 based on this image.
[0085] 10(D), after ACF2 is applied to a plurality of application areas AR1-AR5 of substrate 1B, camera 61B provided on base 35B captures an image of ACF2 applied to application areas AR1-5, and based on this image, inspection unit 130 inspects the state of ACF2 applied to application areas AR1-5 with an inclination of 0. After capturing the image, substrate 1 is transported. Of course, the same can be done when there are three or more substrates 1. This also improves production efficiency compared to the case where imaging unit 60 is positioned and the application state is inspected one by one after each application.
[0086] Note that the imaging unit 60 may have a visual field range capable of imaging one sticking area AR, rather than a visual field range capable of imaging a plurality of sticking areas AR. As in the above-described embodiment, the production efficiency can be improved.
[0087] (4) In the above embodiment, the bases 35 are provided for each substrate 1, and the bonding unit 30, the supply unit 40, and the imaging unit 60 are supported on each base 35, and each of them moves independently, but a configuration in which one base 35 supports the bonding units 30, the supply units 40, and the imaging units 60 corresponding to a plurality of substrates 1 may also be used. In this case, since the base movement mechanism 36 is not provided for each base 35, costs can be reduced.
[0088] (5) In the above embodiment, the stage 20 supports two substrates 1, but the number may be three or more. In this case, the number of bonding units 30 or the number of bonding heads 31 of the bonding unit 30 may correspond to the number of substrates 1. This also makes it possible to correct the tilt of the image of the substrate 1 to be inspected among the multiple substrates 1 and perform the inspection, as in the above embodiment.
[0089] 11 shows how ACF2 is applied to three substrates 1A, 1B, and 1C held by a stage 20. In this figure, the areas in the application area AR that are filled in black indicate areas where ACF2 has already been applied, the hatched areas indicate areas where ACF2 is being applied by a pressure head, and the dotted areas indicate areas where ACF2 will be applied in the future. That is, the application areas AR1 of the three substrates are filled in black, indicating that ACF2 has already been applied to all of them, and the application area AR2 of substrate 1A is also filled in black, indicating that ACF2 has already been applied. The application area AR2 of substrate 1B is hatched, indicating that ACF2 is being applied. The application area AR2 of substrate 1C is indicated by a dotted line, indicating the area where ACF2 will be applied in the future.
[0090] Although not shown in FIG. 11, similarly to the above embodiment, the bonding head 31, head moving mechanism 32, supply unit 40 and imaging unit 60 are supported by bases 35A, 35B and 35C respectively provided for the three substrates 1, and are moved independently in the X and Y directions by the base moving mechanism 36 to be positioned relative to the adhesion area AR of the corresponding substrate 1.
[0091] During this bonding, on the substrate 1A, the substrate 35A is moved by the substrate moving mechanism 36A, and the camera 61A mounted on the substrate 35A comes directly above the bonding area AR2 of the substrate 1A and captures an image of the ACF2 bonded to the bonding area AR2 of the substrate 1A (the imaging field of view is indicated by the dashed dotted line), and the inspection section 130 corrects the inclination of the image of the substrate 1 and performs the inspection.
[0092] Next, in order to adhere ACF2 to adhesion area AR2 of substrate 1C, substrate 35C is moved by substrate movement mechanism 36C, and camera 61C provided on substrate 35C images substrate 1C (the imaging field of view is indicated by a dashed line). Then, from the captured image, the alignment mark of substrate 1C is detected, and the inclination of substrate 1C is found from the position of the alignment mark.
[0093] Then, after inspection of the ACF2 attached to the attachment area AR2 of substrate 1A and attachment of ACF2 to the attachment area AR2 of substrate 1B are completed, the driving mechanism 50 rotates the stage 20 so that the inclination of substrate 1C becomes parallel to the imaginary line VL. Based on the position of attachment area AR2 of substrate 1C, the base moving mechanism 36C moves base 35C, and the pressure bonding head 31C is positioned directly above attachment area AR2 of substrate 1C.
[0094] In this embodiment, at this point, the substrate 1C is imaged by the camera 61C to determine the rotation angle of the stage 20 and the amount of movement of the base 35C, but the rotation angle of the stage 20 and the amount of movement of the base 35C may also be determined using an image captured when the ACF2 is attached to the attachment area AR1 of the substrate 1C, or the position of the alignment mark on the substrate 1C at that time may be stored and the rotation angle of the stage 20 and the amount of movement of the base 35C may be determined based on that position.
[0095] In this way, even if multiple substrates 1 are placed on stage 20, the adhesion state of ACF2 on one substrate 1 can be inspected while ACF2 is being pressed onto the other substrates 1, just as in the case of two substrates 1. Therefore, even if the postures of multiple substrates 1 held on stage 20 are shifted and not aligned, the substrates 1 for which the pressing process has been completed can be corrected and inspected, thereby improving production efficiency while performing accurate inspection.
[0096] (6) In the present embodiment, the bases 35 are provided in one-to-one correspondence with the substrates 1 placed on the stage, but bases 35 may be provided in correspondence with a plurality of substrates 1. For example, when four substrates 1 are placed on the stage 20, two bases 35 may adhere ACF 2 to two substrates 1 each.
[0097] FIG. 12 shows an embodiment in which four substrates 1A to 1D are placed on stage 20, and a base 35A equipped with a bonding head, camera, etc. is provided for bonding ACF2 to substrates 1A and 1B, and a base 35C is similarly provided for bonding ACF2 to substrates 1C and 1D.
[0098] In this figure, two adhesion areas AR are set on each of the four substrates 1, the black filled areas indicate adhesion areas AR where ACF2 has already been adhered, the hatched areas indicate adhesion areas AR where ACF2 is being adhered by the crimping head, and the dotted areas indicate adhesion areas AR where ACF2 will be adhered in the future.
[0099] That is, the attachment areas AR1 and AR2 of substrate 1A are filled in black to indicate that ACF2 is attached to substrate 1A by base 35A. Additionally, the attachment areas AR1 and AR2 of substrate 1C are hatched to indicate that ACF2 is attached by base 35C. Additionally, the attachment areas AR1 and AR2 of substrates 1B and 1D are indicated by dotted lines to indicate the areas where ACF2 will be attached to substrate 1B by base 35A and to substrate 1D by base 35C.
[0100] In this embodiment, the ACF 2 is applied to two application areas AR set on the substrate 1, and then the application state of the ACF 2 applied to another substrate 1 is inspected.
[0101] In this state, while ACF2 is being adhered to adhesion areas AR1 and AR2 of substrate 1C by base 35C, a camera (not shown) provided on base 35A comes directly above substrate 1A and captures an image of the edge line of substrate 1A and the ACF2 adhered thereto (the imaging field of view is shown by a dotted line), and inspection unit 130 inspects the adhesion state of ACF2 on substrate 1A.
[0102] The next substrate 1 to which ACF2 is attached is substrate 1B, and so after base 35A images substrate 1A, a camera (not shown) mounted on base 35A moves so that it is directly above substrate 1B, and images substrate 1B (base 35A after movement is shown by a dotted line, and the imaging field of view of the camera is shown by a two-dot chain line).
[0103] Then, the alignment marks on the substrate 1B are detected from the captured image, and the inclination of the substrate 1B is obtained from the positions of the alignment marks.
[0104] When the attachment of ACF2 to substrate 1C by base 35C, the imaging of substrate 1A, and the detection of the inclination of substrate 1B are completed, stage 20 is rotated based on the inclination of substrate 1B so that the inclination of substrate 1B becomes parallel to virtual line VL, and a bonding head (not shown) of base 35A is positioned at bonding area AR1 of substrate 1B.
[0105] Next, ACF2 is attached to attachment areas AR1 and AR2 of substrate 1B by base 35A. While the ACF2 is being attached, a camera (not shown) provided on base 35C comes directly above substrate 1C and captures images of the edge line of substrate 1C and the attached ACF2, and inspection unit 130 inspects the attachment state of ACF2 on substrate 1C. At this time, the image rotated by the angle of substrate 1B calculated above is used for inspection by inspection unit 130.
[0106] In this way, even if a base 35 corresponding to a plurality of substrates 1 is provided, while the ACF 2 is being pressure-bonded to a substrate 1, the bonding state of the ACF 2 on the other substrates 1 can be inspected. Therefore, even if the postures of the plurality of substrates 1 held on the stage 20 are shifted and not aligned, accurate inspection can be performed while improving production efficiency.
[0107] [Other embodiments] Although the embodiment of the present invention and the modified examples of each part have been described above, these embodiments and the modified examples of each part are presented as examples and are not intended to limit the scope of the invention. These novel aspects described above can be embodied in various other forms, and various omissions, substitutions, modifications, and combinations can be made without departing from the gist of the invention. These embodiments and their modifications are included in the scope and gist of the invention, and are included in the invention described in the claims. [Explanation of symbols]
[0108] 1, 1A, 1B Board 10 Pasting device 20 Stages 30 Crimping section 31, 31A, 31B Crimping head 32 Head movement mechanism 33 Backup Department 35, 35A, 35B base 36, 36A, 36B Base movement mechanism 40 Supply section 41 Supply reel 42 Recovery Reel 43 Guide roller 44 Cut section 44a Cutter 44b Backup material 50 Drive mechanism 60 Imaging unit 61, 61A, 61B Camera 100 Control device 110 Judgment section 120 Correction section 130 Inspection Department
Claims
1. An attachment device for attaching an ACF to a substrate, comprising: A stage for holding a plurality of the substrates; a pressure-bonding unit that presses an ACF onto each of the plurality of substrates; a supply unit that supplies the ACF to the pressure bonding unit; a drive mechanism that aligns the substrate and the pressure bonding portion by changing a relative position of the stage with respect to the pressure bonding portion; an imaging unit that images the ACF attached to the substrate; a determination unit that determines a tilt of the substrate in an image of another substrate captured by the imaging unit while the compression unit is compression-bonding the ACF to the substrate; a correction unit that corrects a tilt of the substrate in the image based on the tilt determined by the determination unit; an inspection unit that inspects the attachment state of the ACF based on the image whose tilt has been corrected by the correction unit; A bonding device comprising:
2. 2. The bonding device according to claim 1, wherein the determining unit determines the inclination of the board based on an edge line of the board in the image.
3. 2. The bonding apparatus according to claim 1, wherein the determining section determines the inclination of the substrate based on an alignment mark of the substrate imaged by the imaging section.
4. 2. The bonding apparatus according to claim 1, wherein the inspection section inspects the ACF bonded to one location on the substrate every time the ACF is bonded to one location on another substrate.
5. 2. The bonding apparatus according to claim 1, wherein the inspection section inspects the ACF attached to a plurality of locations on another of the substrates, every time the ACF is attached to a plurality of locations on the substrate.
6. a holding step in which a stage holds a plurality of substrates; a first bonding step in which a bonding unit bonds an ACF to the substrate; a second bonding step in which the bonding unit bonds the ACF to another substrate; Including, During the second crimping step, a tilt determination step in which a determination unit determines a tilt of the substrate in an image captured by an imaging unit of the ACF attached to the substrate; a correction step of correcting the inclination of the substrate in the image based on the inclination determined by the determination step by a correction unit; an inspection step of inspecting an attachment state of the ACF based on the image whose tilt has been corrected by the correction unit; An inspection method comprising the steps of:
Citation Information