Construction method of structure
The method enhances the construction of complex structures by using a fixing member and outer shell configuration to increase rigidity, addressing mold rigidity issues and enabling the construction of complex shapes without additional support.
Patent Information
- Application Number
- JP2023057923
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-31
- Publication Date
- 2024-10-15
AI Technical Summary
Existing methods using additive manufacturing for constructing structures with diagonal or complex shapes face issues of mold rigidity, leading to potential collapse and limitations in constructing complex structures.
A method involving the use of a fixing member constructed from wire rods, an outer shell formed by spraying modeling material onto the fixing member, and filling the space with a filler material, which increases the rigidity and strength of the formwork, allowing for the construction of complex shapes without the need for shoring or separators.
The method enables the construction of complex-shaped structures with enhanced yield strength and rigidity, facilitating the construction of structures with complex geometries by leveraging the increased strength of the outer shell as formwork.
Smart Images

Figure 2024145530000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a method for constructing a structure. [Background technology]
[0002] A method has been proposed in which a formwork is created by layering concrete using an additive manufacturing device such as a 3D printer, and concrete is then poured into the space enclosed by the formwork to construct a concrete structure (see, for example, Patent Document 1 below). [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2020-111941 A Summary of the Invention [Problem to be solved by the invention]
[0004] However, when using the method disclosed in Patent Document 1 to fabricate a form for a structure with an external shape in which the outer surface of the structure gradually slopes outward as it approaches the top, the form has low rigidity and may collapse. In addition, structures with complex shapes such as shell shapes also have the problem of being limited in terms of rigidity.
[0005] Therefore, the present invention has been made in consideration of the above circumstances, and provides a structure construction method that can easily construct a structure having a complex shape. [Means for solving the problem]
[0006] In order to achieve the above object, the present invention employs the following means. In other words, the method for constructing a structure according to the present invention includes a fixing member construction step of constructing a planar fixing member formed from a plurality of wires so that a space is formed inside, an outer shell construction step of ejecting a molding material from an outer shell additive manufacturing device and spraying the molding material onto at least one side surface of the fixing member to construct an outer shell, and an internal filling step of filling the space formed by the fixing member with a filling material to construct a hardened filling material body.
[0007] In the method for constructing a structure configured in this manner, the outer shell that serves as a formwork when the filling material is filled is configured by spraying the molding material onto at least one surface of a planar fixing member formed by a plurality of wires. The outer shell has higher strength and rigidity than when it is composed only of the molding material. Therefore, even if supports and separators are omitted, the outer shell that serves as a formwork alone can withstand the pressure from the filling material, making it easy to construct a structure of a complex shape.
[0008] In addition, in the method for constructing a structure according to the present invention, the fixing member may be constructed by an additive manufacturing apparatus for a fixing member.
[0009] In the method for constructing a structure configured in this manner, the fixing member is constructed by an additive manufacturing apparatus for the fixing member, so that the construction of the fixing member can be automated.
[0010] In the method for constructing a structure according to the present invention, the fixing member constructing step may include installing the fixing member formed in a lattice shape using a plurality of wires.
[0011] In the method for constructing a structure configured in this way, the anchoring member construction step involves installing an anchoring member formed in a lattice shape using a plurality of wire rods. This anchoring member can be made of commercially available products such as metal lath and welded wire mesh, or rebar assembled in a lattice shape, making it easy to procure and construct the anchoring member.
[0012] In addition, the method for constructing a structure according to the present invention may include a reinforcement construction step of constructing a reinforcement material that reinforces the hardened filling material body within the space formed by the fixing member.
[0013] The reinforcing material includes the main reinforcement (axial reinforcing bar) of the structure and shear reinforcement, and has the function of reinforcing the hardened body of the filling material. Therefore, the hardened body of the filling material is structured such that the filling material is integrated with the reinforcing material, and the strength and rigidity of the hardened body of the filling material can be increased.
[0014] In addition, in the method for constructing a structure according to the present invention, the reinforcing material may be constructed in a lattice shape by the additive manufacturing apparatus for the fixing member.
[0015] In the method for constructing a structure configured in this manner, the reinforcement material is constructed in a lattice shape by the additive manufacturing device for the fixing member, so that the installation of the reinforcement material can be automated. Furthermore, if the reinforcement material is constructed at the same time as the fixing member, the construction can be carried out efficiently.
[0016] In addition, in the method for constructing a structure of the present invention, the fixing member construction process and the outer shell construction process may be repeated to construct a new fixing member on at least one side surface of the outer shell, and the molding material may be sprayed onto at least one side surface of the fixing member to construct the new outer shell.
[0017] In the method for constructing a structure configured in this manner, by repeating the fixing member construction process and the outer shell construction process, the outer shell, which acts as a formwork when the filling material is filled, can be thickened, thereby increasing its strength and rigidity.
[0018] In addition, the method for constructing a structure according to the present invention may include a fixing member construction process for constructing a fixing member in a shell shape, and a filling material hardened body construction process for ejecting a modeling material from an additive manufacturing device and spraying the modeling material onto at least one side surface of the fixing member to construct a filling material hardened body.
[0019] In the method for constructing a structure configured in this manner, the molding material is sprayed onto at least one surface of the lightweight fixing member constructed in a shell shape to construct a hardened filling material body. Therefore, it is possible to easily construct a shell-shaped structure while increasing the strength and rigidity compared to when the hardened filling material body is composed of only the molding material.
[0020] In addition, in the method for constructing a structure according to the present invention, the fixing member construction process and the filling material hardened body construction process may be repeated to construct a new fixing member on at least one side of the filling material hardened body, and the molding material may be sprayed onto both sides of the fixing member to construct a new filling material hardened body.
[0021] In the method for constructing a structure configured in this manner, the filling material hardened body can be thickened and its strength and rigidity increased by repeating the fixing member construction step and the filling material hardened body construction step. Effect of the Invention
[0022] According to the method for constructing a structure of the present invention, even a structure having a complex shape can be easily constructed. [Brief description of the drawings]
[0023] [Figure 1] FIG. 2 is a perspective view showing a fixing member construction step of the method for constructing a structure according to the first embodiment of the present invention. [Diagram 2] FIG. 2 is a perspective view showing the outer shell construction process of the method for constructing a structure according to the first embodiment of the present invention. [Diagram 3] 1 is a cross-sectional view of a structure constructed by a method for constructing a structure according to a first embodiment of the present invention. [Figure 4] 6 is a cross-sectional view of a structure constructed by a method for constructing a structure according to a second embodiment of the present invention. FIG. [Diagram 5] FIG. 11 is a perspective view showing a fixing member construction step of a method for constructing a structure according to a third embodiment of the present invention. [Figure 6] FIG. 11 is a perspective view showing the outer shell construction process of the method for constructing a structure according to the third embodiment of the present invention. [Figure 7] FIG. 11 is a perspective view showing an internal filling step of a method for constructing a structure according to a third embodiment of the present invention. [Figure 8] A cross-sectional view of a structure constructed by a method for constructing a structure according to a third embodiment of the present invention. [Figure 9] 11 is a cross-sectional view of a structure constructed by a method for constructing a structure according to a fourth embodiment of the present invention. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0024] First embodiment A method for constructing a structure according to a first embodiment of the present invention will be described with reference to the drawings. Fig. 1 is a perspective view showing a fixing member construction step of the method for constructing a structure. Fig. 2 is a perspective view showing an outer shell construction step of the method for constructing a structure. Fig. 3 is a cross-sectional view of a structure constructed by the method for constructing a structure.
[0025] The method for constructing a structure includes a fixing member construction step, an outer shell construction step, and an interior filling step. The structure constructed by the method for constructing a structure according to this embodiment can also be used for pillars, beams, walls, etc.
[0026] In the following description, when the completed structure 1 is installed, the horizontal direction along the surface 1a (see FIG. 3, the same applies below) is the first direction X and the second direction Y, and the up-down direction is the up-down direction Z.
[0027] First, a fixing member construction step is performed. As shown in FIG. 1, planar fixing members 11 are constructed along the inside of the four faces 1a that form the outer edge of the structure 1. In this embodiment, a first additive manufacturing device (additive manufacturing device for fixing members) 91 such as a 3D printer is used to construct the fixing members 11 that form the outer shell. The fixing members 11 are formed, for example, of a plate-shaped mesh body. Four fixing members 11 are arranged along the inside of the four faces 1a of the structure 1. A plurality of holes H are formed in the fixing members 11. The four fixing members 11 form a space S that communicates in the vertical direction inside. The fixing members 11 may also be arranged on the bottom surface along the XY plane.
[0028] The fixing member 11 is formed in a planar shape by a plurality of wires. The fixing member 11 is made of wires made of metal, synthetic resin, thermoplastic plastic, thermosetting plastic, FRP (fiber reinforced plastic), glass, ceramic, wood, cement-based material, cement-based material, etc., arranged in a lattice shape, and a combination of a plurality of types of wires may be used as necessary. The fixing member 11 is formed in a lattice shape, a diagonal lattice shape, a mesh shape, a lattice shape, etc. The fixing member 11 is formed in a flat shape or a curved shape.
[0029] Next, the shell construction step is carried out. As shown in Fig. 2, the modeling material 21 is discharged from a second additive manufacturing device (additive manufacturing device for outer shell) 92 and sprayed onto the outer surface 11a of the fixing member 11. When a predetermined thickness is reached, spraying of the modeling material 21 is stopped and the outer shell 22 is constructed. Note that the modeling material 21 may also be sprayed onto the inner surface 11b (see Fig. 3) of the fixing member 11 to increase the thickness of the outer shell 22.
[0030] The modeling material 21 includes, for example, hydraulic mixtures such as cement paste, mortar, and concrete, geopolymer compositions, resin materials, and fiber-reinforced cement-based composite materials in which synthetic fibers, steel fibers, and the like are added to hydraulic mixtures. In addition, other materials may be used as long as they are materials that are ejected from the print head and can be hardened under predetermined conditions (for example, when a predetermined time has passed after ejection, when heat is applied, when ultraviolet rays are irradiated, etc.). A combination of multiple types of these materials may be used as necessary.
[0031] After the molding material 21 is sprayed, the outer surface 22a may be smoothed with a trowel, patterned, or otherwise surface-treated before it is hardened.
[0032] Next, the reinforcing material construction process is carried out. As shown in Fig. 3, main reinforcements (reinforcements) 31 and tie bars (reinforcements) 32 are constructed in the space S formed by the anchoring member 11. A plurality of main reinforcements 31 are installed at intervals in the first direction X and the second direction Y. A plurality of tie bars 32 are installed at intervals in the vertical direction Z to connect the plurality of main reinforcements 31. If it is difficult for the main reinforcements 31 and tie bars 32 to stand on their own, they are supported by support members (not shown) or the like so that they can stand on their own. The size (length) of the hole H in the anchoring member 11 is smaller than the length of the gap T between adjacent main reinforcements 31.
[0033] Next, the internal filling step is carried out. The filling material 41 is filled into the space S formed by the fixing member 11. The filling material 41 hardens to form a filling material hardened body 42. The filling material hardened body 42 is integrated with the outer shell 22 via the fixing member 11 and the molding material 21. The filling material 41 includes, for example, hydraulic mixtures such as mortar and concrete, geopolymer compositions, and fiber-reinforced cement-based composite materials in which synthetic fibers or steel fibers are added to hydraulic mixtures. The material to be filled into the space S can be any material as long as it can reinforce the outer shell, and is not limited to the above-mentioned material. It is preferable to select a material that has sufficient fluidity for filling and has sufficient compressive strength, shear strength, and bending strength as a structural member.
[0034] The structure 1 may be constructed on-site and installed directly on-site by carrying out the above steps, or may be constructed as precast members in a factory, or the shell 22 may be manufactured as precast members in a factory, with reinforcements inserted and filled with the filler material 41 on-site.
[0035] After carrying out the outer shell construction step to construct the first layer of fixing member 11 and outer shell 22, a fixing member construction step may be carried out to construct a second layer of new fixing member 11 on the outside of the outer shell 22. Then, an outer shell construction step is carried out to spray the molding material 21 from the outside of the second layer of fixing member 11 to construct a second layer of new outer shell 22. The fixing member construction step and the outer shell construction step may be repeated until a predetermined thickness and strength are obtained.
[0036] In the method for constructing a structure configured in this manner, the outer shell 22, which serves as a formwork when the filling material 41 is filled, is configured by spraying the molding material 21 onto the surface 11a of the planar fixing member 11 formed in a lattice shape. The outer shell 22 has higher resistance and rigidity than when it is composed only of the molding material 21. Therefore, even if supports and separators are omitted, the outer shell alone, which serves as a formwork, can withstand the pressure from the filling material 41 that is filled, and a structure 1 of a complex shape can be easily constructed.
[0037] Furthermore, since the fixing member 11 is constructed in a lattice shape by the first additive manufacturing apparatus 91, it is possible to automate the construction of the fixing member 11. Note that as the fixing member 11, commercially available products such as metal lath and welded wire mesh may be processed into a predetermined shape and installed.
[0038] Moreover, the main reinforcement 31 and the hoop reinforcement 32 are constructed in the space S formed by the fixing member 11. Therefore, the filling material hardened body 42 has a configuration in which the filling material 41 is integrated with the main reinforcement 31 and the hoop reinforcement 32, and the strength and rigidity of the filling material hardened body 42 can be increased.
[0039] Furthermore, by repeating the fixing member construction step and the outer shell construction step, the outer shell 22 which acts as a formwork when the filling material 41 is filled can be made thicker, thereby increasing its strength and rigidity.
[0040] Second Embodiment Next, a method for constructing a structure according to a second embodiment of the present invention will be described mainly with reference to Fig. 4. Fig. 4 is a cross-sectional view of a structure constructed by the method for constructing a structure according to the second embodiment of the present invention. In the following description of the embodiment, the same reference numerals are used for members and parts that are the same as or similar to those in the above-mentioned embodiment, and the description will be omitted, and configurations that differ from the embodiment will be described.
[0041] In this embodiment, a first additive manufacturing apparatus 91 is used to construct a reinforcing material 35 in the space S formed by the fixing member 11. The reinforcing material 35 is made of wires made of metal, FRP (fiber reinforced plastic), or the like, arranged in a lattice shape. The reinforcing material 35 is constructed by integrating a plurality of wires. The reinforcing material construction process may be performed simultaneously with the fixing member construction process, or the reinforcing material construction process may be performed after the fixing member construction process.
[0042] In the method for constructing a structure configured in this manner, the outer shell 22, which serves as a formwork when the filling material 41 is filled, is configured by spraying the molding material 21 onto the surface 11a of the planar fixing member 11 formed in a lattice shape. The outer shell 22 has higher resistance and rigidity than when it is composed only of the molding material 21. Therefore, even if supports and separators are omitted, the outer shell alone, which serves as a formwork, can withstand the pressure from the filling material 41 being filled, and a structure 1A of a complex shape can be easily constructed.
[0043] Moreover, since the reinforcing material 35 is constructed in a lattice pattern by the first additive manufacturing apparatus 91, the construction of the reinforcing material 35 can be automated. Moreover, if the reinforcing material 35 is constructed simultaneously with the fixing member 11, the construction can be carried out efficiently.
[0044] Third embodiment Next, the method for constructing a structure according to the third embodiment of the present invention will be described mainly with reference to Figs. 5 to 8. Fig. 5 is a perspective view showing a fixing member constructing step in the method for constructing a structure according to the third embodiment of the present invention. Fig. 6 is a perspective view showing an outer shell constructing step in the method for constructing a structure according to the third embodiment of the present invention. Fig. 7 is a perspective view showing an internal filling step in the method for constructing a structure according to the third embodiment of the present invention. Fig. 8 is a cross-sectional view of a structure constructed by the method for constructing a structure according to the third embodiment of the present invention.
[0045] In the following description, as shown in FIG. 8, when one surface of the finished structure 1B is installed, the direction along the two opposing surfaces is defined as a first direction X, the horizontal direction perpendicular to the first direction X is defined as a second direction Y, and the up-down direction perpendicular to the first direction X and the second direction Y is defined as a up-down direction Z.
[0046] As shown in Fig. 5, in the fixing member construction step, the fixing member 12 is installed in a box shape that opens upward. The fixing members 12 are installed on two surfaces (only one surface is shown in Fig. 5), which are the XY surface that serves as the bottom surface, two surfaces facing the first direction X, and the XZ surface that serves as both ends in the longitudinal direction. In this embodiment, the first additive manufacturing apparatus 91 is not used, and the fixing members 12 that have been fabricated in advance are installed in predetermined positions.
[0047] The fixing member 12 is made of wires arranged in a lattice shape and made of metal, synthetic resin, FRP (fiber reinforced plastic), etc. The fixing member 12 is made of a plurality of wires integrated together.
[0048] Two surfaces of the fixing member 12 facing the first direction X (hereinafter referred to as fixing members 12A) have a curved shape that bulges out on both sides in the first direction X. The fixing member 12A is preferably made of a material such as metal or FRP (fiber reinforced plastic) so that it can be easily deformed into a curved shape. A space S is formed inside by the five fixing members 12. All of the fixing members 12 may be formed in a flat shape.
[0049] As shown in Fig. 6, in the outer shell construction process, the modeling material 21 is discharged from the second additive manufacturing device 92 and sprayed onto the outer surface 12a (see Fig. 8) of the fixing member 12. When a predetermined thickness is reached, the spraying of the modeling material 21 is stopped. The outer shell 24 is constructed. The thickness of the outer shell 24 is preferably such that it can stand on its own, but if it is difficult to stand on its own, it is supported by a support member.
[0050] 7, an internal filling step is performed. The space S formed by the fixing member 12 is filled with a filling material 41. The filling material 41 hardens to form a hardened filling material body 42. The hardened filling material body 42 is integrated with the outer shell 24 via the fixing member 12 and the molding material 21.
[0051] In the method for constructing a structure configured in this manner, the outer shell 24, which serves as a formwork when the filling material 41 is filled, is configured by spraying the molding material 21 onto the surface 12a of the planar fixing member 12 formed in a lattice shape. The outer shell 24 has higher resistance and rigidity than when it is composed only of the molding material 21. Therefore, even if supports and separators are omitted, the outer shell alone, which serves as a formwork, can withstand the pressure from the filling material 41 being filled, and a structure 1B of a complex shape can be easily constructed.
[0052] Furthermore, by arranging the fixing member 12A in a curved shape, the outer surface 24c of the outer shell 24 of the structure 1B facing the first direction X can be formed in a curved shape, thereby constructing the structure 1B having a curved surface.
[0053] (Fourth embodiment) Next, a method for constructing a structure according to a fourth embodiment of the present invention will be described mainly with reference to Fig. 9. Fig. 9 is a cross-sectional view of a structure constructed by the method for constructing a structure according to the fourth embodiment of the present invention.
[0054] As shown in Fig. 9, the structure 1C constructed in this embodiment is a shell-shaped structure. In the fixing member construction process, the fixing member 13 is installed in a shell shape (dome shape). The fixing member 13 is made of wires made of metal, synthetic resin, FRP (fiber reinforced plastic), etc., arranged in a lattice shape (lattice or truss shape). The fixing member 13 is constructed by integrating a plurality of wires.
[0055] In the filling material hardened body construction process, the modeling material 21 is ejected from an additive manufacturing device (not shown) and sprayed onto both the inner and outer surfaces of the fixing member 12 to construct a filling material hardened body 23.
[0056] If the thickness of the structure 1C is large, the anchoring member construction process and the filling material hardened body construction process are repeated. The anchoring member construction process is performed to construct a new second layer of anchoring members 13 on the outside of the first layer of anchoring members 13 and the filling material hardened body 23. After that, the molding material 21 is sprayed on both the inner and outer surfaces of the second layer of anchoring members 13 to construct the second layer of filling material hardened body 23. The anchoring member construction process and the shell construction process may be repeated until a predetermined thickness is obtained. The lightweight anchoring members 13 allow large span construction without supports, and the addition of concrete increases the weight as well as the strength and rigidity, so by making the structure multi-layered, it becomes possible to easily construct a large span structure with high strength without supports.
[0057] In the method for constructing a structure configured in this manner, the molding material 21 is sprayed onto both sides of the lightweight anchoring member 13 that is formed in a lattice shape and constructed in a shell shape to construct the filling material hardened body 23. Therefore, the shell-shaped structure 1C can be easily constructed while increasing the strength and rigidity compared to when the filling material hardened body 23 is constructed only from the molding material 21.
[0058] Furthermore, by repeating the fixing member construction step and the filling material hardened body construction step, the filling material hardened body 23 can be made thicker, thereby increasing its strength and rigidity.
[0059] The assembly procedures, shapes and combinations of the components, etc. shown in the above-described embodiment are merely examples, and various modifications can be made based on design requirements, etc., without departing from the spirit of the present invention.
[0060] For example, the fixing members may be commercially available products such as metal lath and welded wire mesh, or may be reinforcing bars assembled in a grid pattern, etc. In this case, the fixing members are easy to procure and construct.
[0061] In the fourth embodiment, the molding material 21 may be sprayed only onto the lower surface (one side surface) of the fixing member, and the filling material may be poured onto the upper surface (the other side surface).
[0062] The "Sustainable Development Goals (SDGs)" are among the 17 international goals adopted at the United Nations Summit in September 2015. The method for constructing a structure according to this embodiment can contribute to the achievement of, for example, "11. Sustainable cities and towns" among the 17 SDGs. [Explanation of symbols]
[0063] 1,1A,1B,1C Structure 11, 12, 12A, 13 Fixing member 21 Modeling materials 22 Outer shell 23 Filler material cured body 31 Main bar (reinforcement) 32 Tie bars (reinforcement) 35 Reinforcement 41 Filling material 42 Filler material cured product 91 First additive manufacturing equipment (additive manufacturing equipment for fixing members) 92 Second additive manufacturing equipment (additive manufacturing equipment for outer shell) S space
Claims
1. a fixing member constructing step of constructing a planar fixing member formed of a plurality of wires so that a space is formed inside; an outer shell construction process in which a modeling material is discharged from an additive manufacturing device for the outer shell and the modeling material is sprayed onto at least one side surface of the fixing member to construct the outer shell; and an internal filling step of filling the space formed by the fixing member with a filling material to construct a hardened filling material body.
2. The method of claim 1 , wherein the fixation member is constructed by a fixation member additive manufacturing device.
3. The method for constructing a structure according to claim 1 , wherein the fixing member forming step comprises installing the fixing member formed in a lattice shape using a plurality of wires.
4. The method for constructing a structure according to claim 2 , further comprising a reinforcing material constructing step of constructing a reinforcing material for reinforcing the hardened filling material body in the space formed by the fixing member.
5. The method for constructing a structure according to claim 4 , wherein the reinforcing material is constructed in a lattice shape by the additive manufacturing device for the anchoring member.
6. A method for constructing a structure as described in claim 1 or 2, in which the fixing member construction process and the outer shell construction process are repeated to construct a new fixing member on at least one side surface of the outer shell, and the molding material is sprayed onto at least one side surface of the fixing member to construct a new outer shell.
7. A fixing member construction process for constructing a fixing member in a shell shape; A method for constructing a structure, comprising: a filling material hardened body construction process, in which a building material is ejected from an additive manufacturing device and the building material is sprayed onto at least one side surface of the fixing member to construct a filling material hardened body.
8. The method for constructing a structure described in claim 7, wherein the fixing member construction process and the filling material hardened body construction process are repeated to construct a new fixing member on at least one side of the filling material hardened body, and the molding material is sprayed onto both sides of the fixing member to construct a new filling material hardened body.
Citation Information
Patent Citations
Construction method of concrete structure
JP2020111941A