Operational planning system, and operational planning method
The operation planning system efficiently plans energy generation and storage equipment operations by considering time, continuity, and consistency, addressing the limitations of existing technologies in dynamic environments.
Patent Information
- Application Number
- JP2023059811
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-03
- Publication Date
- 2024-10-16
AI Technical Summary
Existing technologies fail to provide efficient and accurate operation planning for energy generation and storage equipment, particularly in dynamic external environments, neglecting the importance of time, continuity, and consistency of equipment operation, and do not account for the influence of previous and subsequent plans on initial values.
An operation planning system and method that includes a processing section to collect and generate initial values for formulating an operation plan using optimization calculation, considering equipment, external environment, and user input information to determine when and at what load energy generation and storage equipment should be operated.
Enables quick and accurate formulation of operation plans for energy generation and storage equipment over a day or more, ensuring continuity and consistency, thereby optimizing operating costs and efficiency.
Smart Images

Figure 2024147046000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a configuration of an operation plan creation system and a method thereof, and in particular to a technique that is effective when applied to operation plan creation for energy generation facilities and energy storage facilities. [Background technology]
[0002] With the liberalization of the electric power market, many energy suppliers and consumers have emerged who own multiple energy generation and storage facilities and consume the energy they generate in their own facilities, sell surplus energy at certain times of the day, and purchase energy shortfalls to operate their own facilities.
[0003] For these energy suppliers and consumers, the decision of when and at what load to operate their own energy generation and storage facilities, given the seasonal changes in external environments such as the capacity of renewable energy generation facilities including solar power generation facilities and the prices at which electricity is sold and purchased, is an issue that greatly affects the facility operating costs.
[0004] However, it is difficult to plan the operation of multiple energy generating facilities and energy storing facilities under low load processing.
[0005] Background art in this technical field includes, for example, a technique such as Patent Document 1. Patent Document 1 points out the background that even if the operation plan is limited to the start and stop problem of generators, the total number of combinations of start and stop for 24 hours with 10 thermal power generators is 10 to the power of 72, and even if one plan can be evaluated in 1 microsecond, it would take 10 to the power of 59 years to evaluate all the plans, and it is virtually impossible to check all of them and find the optimal solution. Then, it presents a technique for relaxing the start and stop planning problem of thermal power generators from a combinatorial problem to a problem of finding the optimal solution using quadratic programming and linear programming of real variables, and further providing initial values for start and stop, thereby generating a start-up plan for multiple generators that satisfies the power demand forecast and various constraints in an appropriate manner and with a low processing load.
[0006] Moreover, Patent Document 2 discloses an energy management system, an electricity supply and demand plan optimization method, and an electricity supply and demand plan optimization program that can shorten the time required to obtain an optimal solution. [Prior art documents] [Patent documents]
[0007] [Patent Document 1] JP 2011-188590 A [Patent Document 2] JP 2016-40997 A Summary of the Invention [Problem to be solved by the invention]
[0008] The technology of Patent Document 1 mentioned above is limited to creating a start / stop schedule for energy generation equipment, and does not provide a method for creating detailed plans such as when and at what load the energy generation equipment and energy storage equipment will be operated under an external environment that changes with the seasons.
[0009] However, for energy suppliers and consumers who constantly procure and sell energy according to the surplus or shortage of energy generation and consumption, the details of what time to operate energy generation equipment and at what load, as well as what time to store and release energy in energy storage equipment, can make a big difference in operating costs.
[0010] Furthermore, the technique of Patent Document 1 does not provide a method for efficiently creating continuous operation plans having a time span of one day or more.
[0011] More specifically, the technology of Patent Document 1 provides a method for formulating an optimal start-up and shutdown plan by providing initial values for the start-up and shutdown of each piece of equipment based on a time-series forecast value of power demand and improving these initial values through iterative calculations; however, little consideration is given to the influence of the plans before and after the initial values of the start-up and shutdown variables at each time and the subsequent iterative calculations.
[0012] However, for energy suppliers and consumers who own energy storage facilities with finite capacity, the times at which energy is stored and released over a planning period of one day or more will interfere with each other, so it is necessary to create plans that are consistent over the entire planning period.
[0013] Energy generation facilities also require continuous operation plans with a time span of one day or more. The background to this is that in many energy generation facilities, the operating load and energy generation efficiency that can be assumed at a certain time are affected by the operating load at the time immediately preceding it. Repeated starts and stops in a short period of time cause efficiency to drop, but there are cases where efficiency is stable when operated stably at the same operating load, and cases where the facility has hysteresis characteristics in which energy efficiency changes depending on the operating load at the previous time.
[0014] Furthermore, energy procurement costs such as the unit price of purchased electricity and external environments such as solar power generation vary greatly depending on the time period in a planning range of one day or more. In view of these circumstances, in order to create an optimal operation plan for energy generation equipment and energy storage equipment, a technology is needed to create a plan taking into consideration the time period and the continuity and consistency of equipment operation, but Patent Document 1 does not provide this.
[0015] Furthermore, the technology of Patent Document 2 does not sufficiently consider the continuity and consistency of facility operations, such as the operation priority of the facilities, and there is room for improvement in terms of the accuracy of facility operation plans.
[0016] Therefore, an object of the present invention is to provide an operation planning system and an operation planning method that can create operation plans for energy generation equipment and energy storage equipment with low-load processing while taking into account time periods and the continuity and consistency of equipment operation. [Means for solving the problem]
[0017] In order to solve the above problems, the present invention provides an operation planning system that creates an operation plan for a facility, comprising a processing unit, which accepts facility information, external environment information, demand information, and user input information as input information, generates initial values for creating an operation plan for the facility for each time in a planning range for a specified period based on a user request, and creates an operation plan for the facility by optimization calculations using the input information and the initial values.
[0018] The present invention also provides an operation planning method for creating an operation plan for a facility, comprising: (a) a step of accepting facility information, external environment information, demand information, and user input information as input information; (b) a step of generating initial values for creating an operation plan for the facility for each time in a planning range for a predetermined period based on a user request; and (c) a step of outputting an operation plan for the facility by optimization calculation using the input information and the initial values. Effect of the Invention
[0019] According to the present invention, it is possible to realize an operation planning system and an operation planning method that can create operation plans for energy generation equipment and energy storage equipment with low-load processing while taking into account time periods and continuity and consistency of equipment operation.
[0020] This makes it possible to quickly and accurately provide operational plans that include details such as when and at what load energy generation and storage facilities will be operated for planning periods spanning one day or more.
[0021] Problems, configurations and effects other than those described above will become apparent from the following description of the embodiments. [Brief description of the drawings]
[0022] [Figure 1] 1 is a block diagram showing an operational plan creation system according to a first embodiment of the present invention. [Diagram 2] 2 is a diagram showing an example of an equipment configuration information storage table 121 in FIG. 1. [Diagram 3] 2 is a diagram showing an example of a facility catalog information storage table 122 of FIG. 1. FIG. [Figure 4] 2 is a diagram showing an example of an external environment information storage table 123 in FIG. 1. [Diagram 5] 2 is a diagram showing an example of a demand information storage table 124 in FIG. 1. FIG. [Figure 6] 2 is a diagram showing an example of a user input information storage table 125 in FIG. 1. [Figure 7] 2 is a diagram showing an example of a user input information input screen output by the operational planning system 100 of FIG. 1. FIG. [Figure 8] 4 is a flowchart showing a process of a main routine in the operation plan creation method according to the first embodiment of the present invention. [Figure 9] 9 is a flowchart showing an example of the model generation process of FIG. 8. [Figure 10] 9 is a flowchart showing an example of the initial value generation process of FIG. 8. [Figure 11] 9 is a flowchart showing an example of the optimization execution process of FIG. 8. [Figure 12] FIG. 11 is a diagram showing an example of an initial value list shown in FIG. [Figure 13] FIG. 11 is a diagram illustrating an example of generating an initial value based on equipment priority levels obtained by machine learning according to the second embodiment of the present invention. [Figure 14] FIG. 11 is a diagram illustrating an example of generating an initial value based on equipment priority levels obtained by machine learning according to the second embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0023] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. In the drawings, the same components are designated by the same reference numerals, and detailed description of overlapping parts will be omitted. EXAMPLES
[0024] First Embodiment An operational planning system and an operational planning method according to a first embodiment of the present invention will be described with reference to FIGS.
[0025] Fig. 1 is a block diagram showing an operation planning system according to the present embodiment. Fig. 1 shows a configuration example of an optimal operation planning system 100 for an energy generation facility and an energy storage facility (hereinafter simply referred to as the "optimal operation planning system").
[0026] The optimal operation planning system 100 of this embodiment is a system for creating an operation plan for energy generation equipment and energy storage equipment with low load processing, including details such as when and at what load the energy generation equipment and energy storage equipment will be operated, taking into consideration the time period and the continuity and consistency of equipment operation.
[0027] The optimal operation planning system 100 includes an optimal operation planning device 101 for energy generation facilities and energy storage facilities (hereinafter simply referred to as the "optimal operation planning device"), and a network 190. Power generation facilities and power storage facilities 192 are connected to the network 190 via a control device 191. The optimal operation planning device 101 is configured to be capable of communicating with the power generation facilities and power storage facilities 192 via the network 190 and the control device 191.
[0028] The optimal operation plan planning device 101 has a storage device 110, a processor 150 constituted by a central processing unit (CPU) or the like, a random access memory (RAM) 165, an input device 170, an output device 175, a recording medium reading device 180, and a communication interface 185.
[0029] The storage device 110 is a device that stores information necessary for planning an energy generating facility and an energy storing facility operation plan with low load processing, including details of when and at what load the energy generating facility and the energy storing facility (power generating facility and power storing facility 192) are to be operated, taking into consideration the time period and the continuity and consistency of facility operation, and is, for example, a device such as an HDD (Hard Disk Drive). The storage device 110 may be an SSD (Solid State Drive) using a flash memory or the like.
[0030] The storage device 110 has at least a facility configuration information storage table 121 , a facility catalog information storage table 122 , an external environment information storage table 123 , a demand information storage table 124 , and a user input information storage table 125 as tables 120 .
[0031] The storage device 110 also includes, as programs 130, at least a model generation program 131, an optimization engine program 132, a user input information acquisition program 133, and an initial value generation program 134.
[0032] The processor 150 is a calculation device that executes programs and the like, and includes a model generation unit 151 , an initial value generation unit 152 , an optimal plan formulation unit 153 , and a user input acquisition unit 154 .
[0033] The RAM 165 is a memory that stores the programs executed by the processor 150, data necessary for executing the programs, and the like.
[0034] The input device 170 is a device for inputting various instructions to the optimal operation plan planning system 100, and is, for example, a keyboard, a mouse, a microphone, or the like.
[0035] The output device 175 is a device that outputs an operation plan information input screen and the like, and is, for example, a device such as a CRT (Cathode Ray Tube) display, an LCD (Liquid Crystal Display) or an organic EL (Electro-Luminescence) display, a speaker, a printer, etc.
[0036] The recording medium reading device 180 is a device that reads information from a portable storage medium having portability. Examples of the portable storage medium include a flexible disk, a CD-ROM, a DVD-ROM, a semiconductor memory, a server, and a communication path such as a LAN. The recording medium reading device 180 may be built into the optimal operation plan formulation device 101 or may be attached externally.
[0037] The model generation program 131, the optimization engine program 132, the user input information acquisition program 133, and the initial value generation program 134 are loaded from the program 130 into the RAM 165 and executed by the processor 150, thereby realizing the processing of each program. The realized processing will be described later with reference to FIG. 8.
[0038] Each of the above programs is, for example, an application program that can be executed on an OS (Operating System) program.
[0039] Furthermore, each of the above programs may be input from the network 190 via the communication interface 185 and then installed.
[0040] In addition, a part or all of the optimal operation plan formulation device 101 may be realized as hardware using circuits or the like.
[0041] FIG. 2 is a diagram showing an example of the equipment configuration information storage table 121 of FIG.
[0042] 2 is a table for registering target facilities for which the optimal operation plan planning device 101 plans an operation plan, and is composed of a site ID 210, a facility type 220, a facility ID 230, and a facility catalogue ID 240. One record is generated for each facility.
[0043] The site ID 210 is information that uniquely identifies the site where the equipment is installed. The equipment type 220 is information that identifies the type of the equipment. The equipment ID 230 is information that uniquely identifies the equipment. The equipment catalog ID 240 is information that uniquely identifies the characteristics of the equipment.
[0044] FIG. 3 is a diagram showing an example of the facility catalog information storage table 122 of FIG.
[0045] 3 is a table for registering input / output characteristics of equipment for each equipment catalog ID 310, and is composed of equipment catalog ID 310, number of inputs 321, number of outputs 322, resource type for input 1 331, resource type for output 1 332, relational equation 340 for input to output, minimum operating input value 351, maximum operating input value 352, minimum operating output value 361, maximum operating output value 362, etc. One record is generated for each equipment catalog ID 310.
[0046] FIG. 4 is a diagram showing an example of the external environment information storage table 123 of FIG.
[0047] The external environment information storage table 123 shown in Figure 4 is a table for registering external environment information for each date and time included in the planning range for which the optimal operation plan planning device 101 plans an operation plan, and is composed of date and time 410, solar power generation amount 420, power purchase price 430, etc.
[0048] The date and time 410 is for registering a time included in a planning range for which the optimal operation plan planning device 101 plans an operation plan, and for example, 48 records are required when planning a 24-hour operation plan for load distribution of energy generation facilities and energy storage facilities in 30-minute intervals. The photovoltaic power generation amount 420 is for registering the amount of photovoltaic power generation at the time specified by the date and time 410. The photovoltaic power generation amount 420 may be a predicted value. The power purchase price 430 is for registering information on the power purchase price at the time specified by the date and time 410.
[0049] FIG. 5 is a diagram showing an example of the demand information storage table 124 of FIG.
[0050] The demand information storage table 124 shown in FIG. 5 is a table for registering demand information at each date and time included in the planning range for which the optimal operation plan planning device 101 plans an operation plan, and is composed of date and time 510, power demand 520, heat demand 530, etc.
[0051] Date and time 510 is for registering a time included in the planning range for which the optimal operation plan planning device 101 plans an operation plan, and for example, 48 records are required when planning a 24-hour operation plan for load distribution of energy generation facilities and energy storage facilities in 30-minute increments. Power demand 520 is for registering power demand information at the time specified by date and time 510. Power demand 520 may be a predicted value. Heat demand 530 is for registering heat demand information at the time specified by date and time 510. Heat demand 530 may be a predicted value.
[0052] FIG. 6 is a diagram showing an example of the user input information storage table 125 of FIG.
[0053] The user input information storage table 125 shown in FIG. 6 is for registering user input information for generating one or more optimization search initial values, and is composed of date and time 610, equipment operation priority list 620, minimum operation input value list 631, maximum operation input value list 632, etc.
[0054] The date and time 610 is for registering the time included in the planning range for which the optimal operation plan making device 101 makes an operation plan. For example, when planning a 24-hour operation plan for load distribution of energy generation equipment and energy storage equipment in 30-minute increments, 48 records are required. The equipment operation priority list 620 is for registering the equipment operation priority at the time specified by the date and time 610 in list form, and may be given as a list of arrangements in which the operation priority of the equipment for which the optimal operation plan making device 101 makes an operation plan is listed in descending order. For example, in FIG. 6, two types of equipment operation priorities are registered for the date and time "2022 / 4 / 1 0:00-0:30", namely, gas boiler 001, gas boiler 002, and gas cogeneration 001, in that order. Also, gas boiler 002, gas boiler 001, and gas cogeneration 001, in that order.
[0055] The minimum operation input value list 631 is obtained by arranging the minimum operation input values 351 of the equipment in an array format according to the order of the equipment specified in the equipment operation priority list 620. The maximum operation input value list 632 is obtained by arranging the maximum operation input values 352 of the equipment in an array format according to the order of the equipment specified in the equipment operation priority list 620.
[0056] FIG. 7 is a diagram showing an example of a user input information input screen output by the operational planning system 100 of FIG.
[0057] 7 is a screen on which a user of the optimal operation plan making system 100 inputs equipment operation priorities at times included in a planning range for which the optimal operation plan making device 101 makes an operation plan, and is displayed, for example, by the output device 175 of the optimal operation plan making device 101. The user input information input screen 700 is made up of a time range designation section 710, an equipment operation priority input section 720 for each time range, and the like.
[0058] In the user input information input screen 700 in Fig. 7, the user of the optimal operation plan making system 100 may input the equipment operation priority for each time included in the planning range for which the optimal operation plan making device 101 makes an operation plan, or may input the equipment operation priority for each time range specified in the time range specification unit 710 all at once. In addition, the user of the optimal operation plan making system 100 can input one or more equipment operation priorities for each time range in the equipment operation priority input unit 720 for each time range. Furthermore, the user of the optimal operation plan making system 100 can specify an energy type such as electricity or heat as the equipment operation priority for each time range in the equipment operation priority input unit 720 for each time range, and then select, for example, "generate in order of energy generation efficiency."
[0059] 8 is a flowchart showing the processing of a main routine in the operation planning method according to the embodiment 1 of the present invention. 8 shows the processing of a main routine of the program 130 in the optimal operation planning device 101 of FIG.
[0060] This process is executed by the processor 150 in accordance with the model generation program 131, the optimization engine program 132, the user input information acquisition program 133, and the initial value generation program 134 in order to create an optimal operation plan for the energy generation equipment and the energy storage equipment (the power generation equipment and the energy storage equipment 192).
[0061] When the process starts, the processor 150 first receives an instruction to create and execute an optimal operation plan for the energy generation facility and the energy storage facility from a user of the optimal operation plan creation system 100 (step S810).
[0062] Next, the processor 150 executes the model generation program 131 and generates a model required for formulating an optimal operation plan for the energy generation facility and the energy storage facility according to a model generation process described in detail in FIG. 9 (step S820).
[0063] Next, the processor 150 executes the initial value generation program 134 and generates search initial values required to formulate an optimal operation plan for the energy generation equipment and the energy storage equipment according to the initial value generation process described in detail in FIG. 10 (step S830).
[0064] Next, the processor 150 executes the optimization engine program 132, and executes the optimization process to formulate an optimal operation plan for the energy generation facility and the energy storage facility according to the optimization execution process described in detail in FIG. 11 (step S840).
[0065] Finally, the processor 150 registers the optimal operation plan for the energy generating facility and the energy storing facility (step S850), and ends the process.
[0066] FIG. 9 is a flowchart showing an example of the model generation process of FIG.
[0067] When the model generation process starts, the processor 150 first reads the facility configuration information storage table 121, the facility catalog information storage table 122, the external environment information storage table 123, and the demand information storage table 124 (step S910).
[0068] Next, the processor 150 generates decision variables for optimal operation planning of the energy generating equipment and the energy storage equipment based on existing modeling technology. The decision variables may be input values and output values of the energy generating equipment and the energy storage equipment at each time (step S920).
[0069] Next, the processor 150 generates constraint conditions for optimal operation planning of the energy generation facility and the energy storage facility based on an existing modeling technique. The constraint conditions include input / output relationships for each facility, minimum operating input / output conditions for the facility input / output values, etc. (step S930).
[0070] Finally, the processor 150 generates (sets) an objective function for optimal operation planning of the energy generating equipment and the energy storing equipment based on the existing modeling technology, and ends the model generation process. The objective function may be, for example, the operating cost of the energy generating equipment and the energy storing equipment (step S940).
[0071] FIG. 10 is a flowchart showing an example of the initial value generation process of FIG.
[0072] When the initial value generation process starts, the processor 150 first executes the user input information acquisition program 133, presents the user input information input screen 700 to the user of the optimal operation plan planning system 100, and acquires user input information (step S1010).
[0073] Next, the processor 150 generates the user input information storage table 125 from the user input information input by the user of the optimal operation plan formulation system 100 on the user input information input screen 700 (step S1020).
[0074] Next, processor 150 generates an initial value list from user input information storage table 125 (step S1030). For the initial values at each time, one or more arbitrary values are generated for one of the priority orders stored in equipment operation priority list 620, such that the load distribution increases in the order of priority, and each equipment input / output variable is equal to or greater than the minimum operation input / output value and equal to or less than the maximum operation input / output value. If two or more different priority orders are registered in equipment operation priority list 620 at each time, one or more initial values are generated for each priority order, and all initial values are listed to generate an initial value list.
[0075] Finally, processor 150 registers the initial value list and ends the initial value generation process (step S1040).
[0076] Fig. 12 is a diagram showing an example of the initial value list of Fig. 10. Fig. 12 shows an example of a case where there are multiple similar facilities with different behaviors, and assumes a boiler as the energy generation facility, showing examples of the initial values of boiler 1, boiler 2, and boiler 3.
[0077] In this example, the user is prompted to input the priority for each time period. Then, the initial value is set to a large value in descending order of priority at each time.
[0078] FIG. 11 is a flowchart showing an example of the optimization execution process of FIG.
[0079] When the optimization execution process starts, the processor 150 first obtains an initial value list (step S1110).
[0080] Next, the processor 150 extracts one initial value from the initial value list, and executes optimization using this initial value and the model generated by the model generation program 131 (step S1120).
[0081] Next, processor 150 registers the optimization execution result for the initial value (step S1130).
[0082] Processor 150 then checks whether or not optimization results have been registered for all initial values (step S1140), and if yes, proceeds to step S1150, and if no, returns to step S1120 and repeats the processes from step S1120 onwards.
[0083] Next, the processor 150 selects, from all the registered optimization results, the operation plan that optimizes the objective function (step S1150).
[0084] By carrying out the processing shown in Figures 8, 9, 10, and 11 as described above, it is possible to quickly and accurately obtain an operation plan that includes details such as when and at what load the energy generation equipment and energy storage equipment will be operated for a planning period having a time span of one day or more. EXAMPLES
[0085] Second Embodiment An operational planning system and an operational planning method according to a second embodiment of the present invention will be described with reference to FIGS.
[0086] 13 and 14 are diagrams showing an example of generating initial values based on facility priorities obtained by machine learning.
[0087] As shown in the upper left diagram of Fig. 13, information regarding the operation record or operation plan of the equipment for a predetermined period is obtained. Also, as shown in the upper right diagram of Fig. 13, information regarding the operation state (e.g., load factor) of the equipment corresponding to the operation record or operation plan of the equipment is obtained. Based on this information, data for machine learning is generated as shown in the lower right diagram of Fig. 13.
[0088] The data for machine learning may be, for example, one year's worth of data, as shown in the upper diagram of Figure 14, or, if seasonal variations are expected, data from a specific month (such as August) over several years may be used.
[0089] For example, based on rules such as listing the priority order with a frequency of 30% or more, data for machine learning is generated as shown in the lower diagram of Figure 14.
[0090] It should be noted that there may be multiple priority orders at each time point. Also, the priority list generated in this manner may be used in place of a priority list generated from user input.
[0091] In this embodiment, the processor 150 of the optimal operation plan planning device 101 generates an initial value based on the equipment priority level learned by machine learning.
[0092] The present invention is not limited to the above-described embodiments, and includes various modified examples. For example, the above-described embodiments have been described in detail to clearly explain the present invention, and the present invention is not necessarily limited to those including all of the configurations described. It is also possible to replace a part of the configuration of one embodiment with the configuration of another embodiment, and it is also possible to add the configuration of another embodiment to the configuration of one embodiment. It is also possible to add, delete, or replace a part of the configuration of each embodiment with another configuration.
[0093] In addition, the above-mentioned configurations, functions, processing units, processing means, etc. may be realized in part or in whole by hardware, for example, by designing them as integrated circuits. In addition, the above-mentioned configurations, functions, etc. may be realized in software by a processor interpreting and executing a program that realizes each function. Information such as programs, tables, files, etc. that realize each function can be stored in a storage device such as a non-volatile semiconductor memory, a hard disk drive, or an SSD (Solid State Drive), or in a computer-readable non-transitory data storage medium such as an IC card, an SD card, or a DVD.
[0094] In addition, the control lines and information lines are those considered necessary for the explanation, and not all control lines and information lines in the product are necessarily shown. In reality, it can be considered that almost all components are connected to each other. [Explanation of symbols]
[0095] 100...Optimal operation planning system 101...Optimal operation planning device 110...Storage device 120…Table 121...Facility configuration information storage table 122...Facility catalog information storage table 123...External environment information storage table 124...Demand information storage table 125...User input information storage table 130…Program 131…Model generation program 132…Optimization engine program 133...User input information acquisition program 134…Initial value generation program 150…processor 151…Model generation unit 152...Initial value generation unit 153…Optimal Planning Department 154...User input acquisition unit 165…RAM 170...Input device 175...Output device 180...Recording medium reader 185…Communication interface 190…Network 191...Control device 192…Power generation and storage facilities 210...site ID 220...Facility type 230…Equipment ID 240,310...Equipment catalog ID 321…Number of inputs 322…Number of outputs 331...Resource type of input 1 332…Resource type of output 1 340...Relationship between input and output 351: Minimum operating input value 352…Maximum operating input value 361…Minimum operating output value 362…Maximum operating output value 410,510,610…Date and time 420…Solar power generation 430…Electricity purchase price 520…Electricity demand 530…heat demand 620...Facility operation priority list 631...Minimum operating input value list 632...Maximum operating input value list 700...User input information input screen 710...Time range specification section 720...Equipment operation priority input section for each time range.
Claims
1. An operation planning system for creating an operation plan for a facility, comprising: A processing unit is provided, The processing unit receives facility information, external environment information, demand information, and user input information as input information, generating initial values for creating an operation plan for the equipment for each time in a planning range of a predetermined period based on a user request; an operation plan for the facility based on an optimization calculation using the input information and the initial values;
2. The operation planning system according to claim 1, An operational planning system comprising: a storage device connected to the processing unit for storing a program executed by the processing unit and an information storage table in which the input information is stored.
3. The operation planning system according to claim 1, The processing unit generates a predetermined objective function by modeling; An operational planning system characterized by executing the optimization calculation based on the generated objective function.
4. The operation planning system according to claim 1, The processing unit generates the initial value based on equipment priority levels learned by machine learning.
5. The operation planning system according to claim 1, The facilities include energy generation facilities and energy storage facilities; An operation planning system, wherein the operation plan includes a plan regarding the operation of the energy generation facility and the energy storage facility for supplying energy to consumers.
6. The operation planning system according to claim 1, The facility information includes at least one of the types, number, energy generation efficiency, facility capacity, and minimum output of energy generation facilities and energy storage facilities.
7. The operation planning system according to claim 1, The external environment information includes at least one of weather information and electricity purchase price information.
8. The operation planning system according to claim 1, 2. An operational planning system, wherein the user input information includes information regarding operation priorities of the equipment.
9. An operation plan creation method for creating an operation plan for a facility, comprising: (a) receiving facility information, external environment information, demand information, and user input information as input information; (b) generating initial values for creating an operation plan for the equipment for each time in a planning range of a predetermined period based on a request from a user; (c) outputting an operation plan for the equipment by optimization calculation using the input information and the initial values; An operation planning method comprising the steps of:
10. The operational planning method according to claim 9, (d) generating a predetermined objective function by modeling; (e) executing the optimization calculation based on the objective function generated in the (d) step; An operation planning method comprising the steps of:
11. The operational planning method according to claim 9, An operation planning method, characterized in that in the step (b), the initial value is generated based on equipment priority level learned by machine learning.
Citation Information
Patent Citations
Supply-and-demand control apparatus, power supply system, and supply-and-demand control method
JP2016093050A
Energy demand and supply planning apparatus and program
JP2017022939A
Operation plan creation device, operation plan creation method, and program
JP2018113079A
Generator operation plan determination device, method for determining generator operation plan, and generator operation plan determination program
JP2011188590A
Energy management system, power supply and demand plan optimization method, and power supply and demand plan optimization program
JP2016040997A