Work improvement support device and program
The business improvement support device identifies and visualizes the longest process in a multi-step workflow, facilitating resource optimization and time reduction by associating nodes with their execution times.
Patent Information
- Application Number
- JP2023062073
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-06
- Publication Date
- 2024-10-18
AI Technical Summary
Existing business flow systems struggle to identify the process that takes the longest time to execute in a workflow with multiple steps, making it difficult to understand and optimize the total time required for each process.
A business improvement support device and program that associates nodes in a business flow with their execution times, determines the process requiring the longest time, and displays this information for analysis.
Enables the identification and visualization of the process that takes the longest time, allowing for targeted business improvements by optimizing resource allocation and reducing execution time.
Smart Images

Figure 2024148705000001_ABST
Abstract
Description
[Technical field]
[0001] An embodiment of the present invention relates to a business improvement support device and a program. [Background technology]
[0002] For example, in the field of production and manufacturing of goods, or in the field of product acceptance and inspection, various tasks are performed during the process. In such fields, in order to efficiently carry out various tasks sequentially, business flows are sometimes created that are expressed based on IPO notation (Input-Process-Output chains) such as BPMN (Business Process Model and Notation). For example, technology has been proposed that can automatically create business flows so that the input-output relationships between adjacent tasks are continuous.
[0003] By using the above-mentioned business flow, it is possible to confirm the procedure for performing each business and the relationship between the businesses. However, in a business flow that has multiple processes, such as branching into multiple processes midway, the total man-hours (the total time required to perform each process from start to finish) may differ in each process, and it is not easy to grasp which process is taking time, so there is room for further improvement. Summary of the Invention [Problem to be solved by the invention]
[0004] The problem to be solved by the present invention is to provide a business process improvement support device and program that are capable of identifying the process that takes the longest time to execute a business process in a business flow having multiple processes. [Means for solving the problem]
[0005] The business improvement support device of the embodiment includes a memory unit that associates multiple nodes related to the execution of a business process with each of the nodes of a business process flow having multiple processes, and stores attribute information including the time required to execute the business process of the node, a determination means that determines which of the multiple processes requires the longest time to execute the business process based on the time for each node stored in the memory unit, and an output means that displays and outputs the business process in which the determined process is identified from other processes. [Brief description of the drawings]
[0006] [Figure 1] FIG. 1 is a diagram illustrating an example of a configuration of a business improvement support system according to an embodiment. [Diagram 2] FIG. 2 is a diagram illustrating an example of a hardware configuration of the terminal device according to the embodiment. [Diagram 3] FIG. 3 is a diagram illustrating an example of a hardware configuration of the server device according to the embodiment. [Figure 4] FIG. 4 is a diagram illustrating an example of a visualized business flow according to the embodiment. [Diagram 5] FIG. 5 is a diagram illustrating an example of a data configuration of the attribute storage unit according to the embodiment. [Figure 6] FIG. 6 is a diagram illustrating an example of another data configuration of the attribute storage unit according to the embodiment. [Figure 7] FIG. 7 is a diagram illustrating an example of a functional configuration of a terminal device and a server device according to the embodiment. [Figure 8] FIG. 8 is a diagram showing an example of a created binary table according to the embodiment. [Figure 9] FIG. 9 is a diagram showing another example of a binary table created according to the embodiment. [Figure 10] FIG. 10 is a diagram illustrating an example of a data configuration of the attribute storage unit in a state in which information on task ratios and man-hours has been updated in the server device of the embodiment. [Figure 11] FIG. 11 is an explanatory diagram showing the man-hours of nodes for each process and the calculated total man-hours. [Figure 12]FIG. 12 is a diagram showing an example of a visualized business flow in which the process with the longest man-hours is highlighted. [Figure 13] FIG. 13 is a flowchart illustrating an example of a process related to attribute information generation executed by the server device according to the embodiment. [Figure 14] FIG. 14 is a flowchart illustrating an example of a process related to automatic assignment of a process number executed by the server device of the embodiment. [Figure 15] FIG. 15 is a flowchart illustrating an example of a process for creating and modifying a binary table executed by the server device according to the embodiment. [Figure 16] FIG. 16 is a diagram illustrating an example of a process of determining the maximum number of man-hours executed by the server device according to the embodiment. [Figure 17] FIG. 17 is a flowchart illustrating an example of a control process of the terminal device according to the embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0007] Hereinafter, the embodiments will be described in detail with reference to the drawings. Note that the present invention is not limited to the embodiments described below.
[0008] Fig. 1 is a diagram showing an example of the configuration of a business improvement support system according to an embodiment. As shown in Fig. 1, the business improvement support system 1 includes one or more terminal devices 10 (multiple devices in the embodiment) and a server device 20. The terminal devices 10 and the server device 20 are communicatively connected via a network N such as a LAN (Local Area network).
[0009] The terminal device 10 is a terminal device used by a user of the business improvement support system 1. The terminal device 10 executes various processes in response to user operations. For example, the terminal device 10 cooperates with the server device 20 to support the creation of a business flow (described later) and to display the business flow. The terminal device 10 can be realized by, for example, a stationary information processing device such as a PC (Personal Computer) or a portable information processing device such as a notebook PC, a tablet terminal, or a smartphone.
[0010] The server device 20 is an example of a business improvement support device. The server device 20 supports the creation and viewing of business flows. The server device 20 also provides a user with attribute information associated with the business flow and necessary for executing the business. The server device 20 also supports the creation of a binary table 90 (see Figs. 8 and 9) described below and the determination of the longest process in the business flow.
[0011] Furthermore, the server device 20 provides the terminal device 10 with a business flow, attribute information and binary table information, which will be described later, in response to a request from a user of the terminal device 10.
[0012] In this embodiment, an example is described in which the server device 20 is realized by a single device, but this is not limited to the above, and the server device 20 may be realized by multiple devices, for example, by using a technology such as cloud computing.
[0013] Next, the configurations of the above-mentioned terminal device 10 and server device 20 will be described.
[0014] Fig. 2 is a diagram showing an example of a hardware configuration of the terminal device 10. As shown in Fig. 2, the terminal device 10 includes a computer configuration including a CPU (Central Processing Unit) 11, a ROM (Read Only Memory) 12, and a RAM (Random Access Memory) 13.
[0015] The CPU 11 is an example of a processor, and performs overall control of each unit of the terminal device 10. The ROM 12 stores various programs. The RAM 13 is a workspace in which programs and various data are expanded.
[0016] The terminal device 10 also includes a display unit 14 , an operation unit 15 , a storage unit 16 , and a communication unit 17 .
[0017] The display unit 14 is composed of a display device such as an LCD (Liquid Crystal Display). The display unit 14 displays various information under the control of the CPU 11. The operation unit 15 has a keyboard, a pointing device, etc. The operation unit 15 outputs operation contents accepted by a user's operation to the CPU 11. The operation unit 15 may be a touch panel provided on the display screen of the display unit 14.
[0018] The storage unit 16 is composed of a storage medium such as a hard disk drive (HDD) or a flash memory, and maintains the stored contents even when the power is cut off. The storage unit 16 stores programs that can be executed by the CPU 11 and various setting information. For example, the storage unit 16 stores an application program such as a web browser that can access the server device 20 and display and operate various operation support screens provided by the server device 20.
[0019] The CPU 11 operates according to a program stored in the ROM 12 or the storage unit 16 and loaded into the RAM 13, thereby functioning as a functional unit and executing various types of processing.
[0020] The communication unit 17 is a communication interface that can be connected to the network N. The communication unit 17 communicates with an external device such as a server device 20 via the network N.
[0021] Fig. 3 is a diagram showing an example of a hardware configuration of the server device 20. As shown in Fig. 3, the server device 20 includes a computer configuration including a CPU 21, a ROM 22, and a RAM 23.
[0022] The CPU 21 is an example of a processor, and performs overall control of each unit of the server device 20. The ROM 22 stores various programs. The RAM 23 is a workspace in which programs and various data are expanded.
[0023] The server device 20 also includes a display unit 24, an operation unit 25, a storage unit 26, and a communication unit 27.
[0024] The display unit 24 is composed of a display device such as an LCD. The display unit 24 displays various information under the control of the CPU 21. The operation unit 25 has a keyboard, a pointing device, etc. The operation unit 25 outputs the operation content received from the user to the CPU 11. The operation unit 25 may be a touch panel provided on the display screen of the display unit 24.
[0025] The storage unit 26 is an example of a storage device. The storage unit 26 is composed of a storage medium such as a HDD or a flash memory, and maintains the stored contents even when the power is cut off. The storage unit 26 stores programs that the CPU 21 can execute and various setting information. For example, the storage unit 26 stores a web application program, etc. The CPU 21 executes various processes by functioning as various functional units according to the programs stored in the ROM 22 or the storage unit 26 and deployed in the RAM 23.
[0026] The storage unit 26 also includes a workflow DB 261 and a table storage unit 262. The workflow DB 261 is a database for storing and managing workflows. The workflow DB 261 includes a workflow storage unit 2611, an attribute storage unit 2612, and a longest time process unit 2613.
[0027] The business flow storage unit 2611 stores information about business flows. Here, a business flow is a data file in which the business to be executed at each node related to the performance of the business and the execution contents executed in the business are described as a series of procedures. For example, the business flow describes the execution contents and procedures executed by the business related to the acceptance, inspection, and storage of products and parts. The information stored in the business flow storage unit 2611 will be described later with reference to FIG. 4.
[0028] The attribute storage unit 2612 stores attribute information related to multiple tasks executed sequentially in a business flow. The attribute storage unit 2612 stores attribute information related to tasks executed at each node in the business flow, in association with each node. The attribute information stored in the attribute storage unit 2612 will be described later with reference to Figs. 5 and 6. When a business flow has multiple steps, the longest time process unit 2613 stores a business flow in which the process that requires the longest total time to execute tasks executed at each node is highlighted and made distinguishable from other processes. The time required to execute tasks executed at each node is stored in the attribute information corresponding to each node.
[0029] Fig. 4 is a diagram showing an example of a state in which a business flow is visualized based on the business flow information stored in the business flow storage unit 2611. As shown in Fig. 4, the business flow storage unit 2611 stores information on business flows that can be visualized. Note that in this embodiment, as an example, it is assumed that information on business flows related to the receipt and storage of goods or products is stored in the business flow storage unit 2611.
[0030] As shown in Fig. 4, the workflow storage unit 2611 stores a workflow including pool names of pools indicating workflow areas obtained by dividing a series of workflows into a predetermined granularity, and nodes indicating the types of workflows executed within the pools for each pool. Here, the pool name is a higher-level concept than the node name (work name), and in the example shown in Fig. 4, "receiving inspection" and "storage" of goods, articles, parts, products, etc. correspond to the pool name. In the example of Figure 4, the following nodes are stored as nodes for tasks performed in the pool named "receiving inspection": node Aa for the task "delivery", node Ab for the task "delivery note confirmation", node Ac for the task "lot, item, and quantity check", node Ad for the task "specification search", node Ae for the task "sampling inspection 1 (weight)", node Af for the task "sampling inspection 1 (external dimensions)", node Ag for the task "sampling inspection 1 (surface roughness)", node Ah for the task "inspection completion", node Aj for the task "sampling inspection 2 (infrared analysis)", node Ak for the task "sampling inspection 2 (scanning microscope)", and node Am for the task "sampling inspection 2 (film thickness measurement)".
[0031] In addition, the nodes for tasks performed in the pool named "storage" are stored as follows: node Ba for task "inspected items", node Bb for task "check storage instructions and print list", node Bc for task "acceptance processing of approved items", node Bd for task "attach approved inspection data", node Be for task "find shelf number and store", node Bf for task "enter storage quantity in list", node Bg for task "put list in completion box", node Bh for task "storage complete", node Bj for task "rejection processing", and node Bk for task "return processing of rejected items". In addition, the following are the node names for each node: "Delivery", "Check delivery note", "Check lot / item / quantity", "Search specifications", "Sampling inspection 1 (weight)", "Sampling inspection 1 (external dimensions)", "Sampling inspection 1 (surface roughness)", "Inspection completed", "Sampling inspection 2 (infrared analysis)", "Sampling inspection 2 (scanning microscope)", "Sampling inspection 2 (film thickness measurement)", "Inspection completed", "Check storage instructions and print list", "Acceptance process for passed products", "Attach passed inspection data", "Find shelf number and store", "Enter storage quantity on list", "Storage complete", "Rejection process", and "Return process for rejected products".
[0032] The workflow storage unit 2611 also stores information indicating the order in which tasks are executed at each node. The workflow storage unit 2611 stores information indicating the order in which tasks are executed for each of a plurality of steps related to the workflow. In FIG. 4, as an example, information indicating the order in which tasks are executed for each of four types of steps is stored. The four types of patterns are a process (pattern A) in which tasks are executed in the order of node Aa → node Ab → node Ac → node Ad → node Ae → node Af → node Ag → node Ah → node Ba → node Bb → node Bc → node Bd → node Be → node Bf → node Bg → node Bh, a process (pattern B) in which tasks are executed in the order of node Aa → node Ab → node Ac → node Ad → node Aj → node Ak → node Am → node Ah → node Ba → node Bb → node Bc → node Bd → node Be → node Bf → node Bg → node Bh, and a process (pattern C) in which tasks are executed in the order of node Aa → node Ab → node Ac → node Ad → node Aj → node Ak → node Am → node Ah → node Ba → node Bb → node Bc → node Bd → node Be → node Bf → node Bg → node Bh. The process is carried out in the order of Node Aa → Node Ab → Node Ac → Node Ad → Node Ae → Node Af → Node Ag → Node Ah → Node Ba → Node Bb → Node Bj → Node Bk → Node Be → Node Bf → Node Bg → Node Bh (Pattern C); and the process is carried out in the order of Node Aa → Node Ab → Node Ac → Node Ad → Node Aj → Node Ak → Node Am → Node Ah → Node Ba → Node Bb → Node Bj → Node Bk → Node Be → Node Bf → Node Bg → Node Bh (Pattern D).
[0033] The order of operations at each node is determined by displaying the nodes that perform the operations on a screen and connecting the nodes with arrows in the order in which the operations are performed, so that the operations are performed in order from the upstream side of the arrow to the downstream side. The business flow of the embodiment branches midway and then merges. When the business branch into two or more operations during the execution of the business (for example, when the business branch is performed from node Ad to node Ae and when the business branch is performed from node Ad to node Aj), arrows are connected from the node that is the starting point of the branch (for example, node Ad) to both of the branch destination nodes (nodes Ae and Aj). When the branched operations merge midway, arrows are connected from the last branched nodes (for example, nodes Bd and Bk) to the merge destination node (node Be). It should be noted that the order of operations to be performed in this manner can be determined by using a known method for creating a business flow, such as a flowchart or BPMN (Business Process Modeling Notation).
[0034] Further, each node is associated with attribute information related to the business of the node. The attribute storage unit 2612 stores attribute information related to the business of each node in association with each node stored in the business flow storage unit 2611. For example, the attribute information includes information necessary to execute the business of each node.
[0035] Attribute information related to "Delivery" of the node Aa shown in FIG. 4 is illustrated in FIG. 5. The attribute information related to "Delivery" includes a node name 26121, a process number 26122, resource information 26123, an Input node 26124, an Output node 26125, a pool name 26126, and an analysis 26127. The node name 26121 is information indicating the node name of the node associated with the attribute information. The process number 26122 is information indicating the execution order of the tasks executed by the node in the pool to which the node belongs. The resource information 26123 is information indicating the resources used in executing the tasks of the node. The resources include physical resources and human resources. The Input node 26124 is information indicating the process number indicating the execution order of the tasks of the node executed immediately before the node. The Output node 26125 is information indicating the process number indicating the execution order of the tasks of the node executed immediately after the node. The pool name 26126 is information indicating the pool name of the pool to which the node's business belongs. The analysis 26127 is information indicating whether or not work is involved in executing the node's business. If work is involved, it is written as "target", and if no work is involved, it is written as "not target". Whether the analysis is target or not can be set on a pool name basis or on a node basis.
[0036] In the attribute information related to "Delivery" shown in FIG. 5, information on "Delivery" is stored as node name 26121. Information on "A001" is stored as process number 26122 indicating the "Delivery" node. Information on "Supplier", "EDI System", and "Parts Warehouse" is stored as resource information 26123 (physical resource "Facilities") of resources used to execute the task at the "Delivery" node, and "Warehouse Manager" is stored as resource information 26123 (human resource "Executor"). Since there is no node that executes the task immediately before the "Delivery" node, a blank is stored in Input node 26124, which is a process number indicating the execution order of the task at the node where the task is executed immediately before the node. Furthermore, "A002" is stored as Output node 26125, which is a process number indicating the execution order of the task at the node where the task is executed immediately after the "Delivery" node (i.e., the "Delivery Note Confirmation" node). Also, as the analysis 26127, information of "not applicable" is stored, which indicates that the node does not involve any work related to the business.
[0037] FIG. 6 also illustrates an example of attribute information related to node Ab “Delivery Note Check”. As attribute information related to “Delivery Note Check”, information on “Delivery Note Check” is stored as node name 26121. Information on “A002” is stored as process number 26122 indicating the “Delivery Note Check” node. Information on “Inspection Department” and “Part-time Worker” is stored as resource information 26123 (human resource “Executor”) of resources used to execute the task at the “Delivery Note Check” node, and information on “EDI System”, “Scanner” and “Multifunction Printer” is stored as material resource “Equipment”. Input node 26124 also stores “A001”, which is the process number of the “Delivery” node, which is the node that executed the task immediately before the “Delivery Note Check” node. Output node 26125 also stores “A003”, which is the process number of the “Lot, Item and Quantity Check” node, which is the node that executes the task next to the “Delivery Note Check” node. Also, as the analysis 26127, information on "target" indicating that the node involves work related to the business is stored.
[0038] In the attribute information shown in Figures 5 and 6, the resource information 26123 includes the man-hours required to execute the node's business (i.e., information on the time required to execute (complete) the node's business). Since the content of the business performed at each node is different, the time required to execute the business varies. The time required to execute the business also varies depending on the experience and ability of the person in charge of the business. For this reason, the resource information 26123 stores, for example, the average time it takes multiple people to execute the business, or the standard time expected to execute the business.
[0039] The workflow and attribute information are created by the workflow creation support unit 211, which is realized by cooperation between the CPU 21 and an application program stored in the memory unit 26 and will be described later. A user can access the server device 20 via the terminal device 10, for example, to create a workflow and attribute information using the creation support function of the workflow creation support unit 211 (for example, the user can set the creation and execution order of nodes while operating a visualized workflow). The created workflow and attribute information are stored in association with each other. The memory unit 26 may also store workflows and attribute information created by another terminal device 10.
[0040] Returning to the explanation of Fig. 3, the table storage unit 262 stores information of a binary table 90 (see Figs. 8 and 9) that is automatically created by the server device 20 based on the attribute information stored in the attribute storage unit 2612. The binary table 90 is a table formed in a matrix shape with a horizontal axis (X axis) and a vertical axis (Y axis), for example, in which node names indicating the contents of a task are arranged in the order of task execution in one column (for example, along the X axis), and resources used in the task are arranged in the other column (for example, along the Y axis), thereby indicating the relationship between the task and the resources used in the task. Details of the binary table 90 will be described later with reference to Figs. 8 and 9.
[0041] Next, the functional configuration of the terminal device 10 and the server device 20 will be described with reference to Fig. 7. Fig. 7 is a diagram (functional block diagram) showing an example of the functional configuration of the terminal device 10 and the server device 20.
[0042] As shown in FIG. 7, the terminal device 10 includes a display control unit 111 and an operation receiving unit 112 as functional units.
[0043] A part or all of the functional units of the terminal device 10 may be a software configuration realized by cooperation between the CPU 11 of the terminal device 10 and a program stored in a memory (e.g., the ROM 12 or the storage unit 16). Also, a part or all of the functional units of the terminal device 10 may be a hardware configuration realized by a dedicated circuit or the like mounted on the terminal device 10.
[0044] The display control unit 111 of the terminal device 10 controls the display unit 14 to display various screens on the display unit 14. For example, the display control unit 111 displays various operation support screens provided by the server device 20 on the display unit 14. A user can access the server device 20 via the terminal device 10, for example, obtain information on an input screen for business flows and attribute information from the server device 20, and display the information on the display unit 14 to create and modify business flows and attribute information. The display control unit 111 also displays the created two-dimensional table on the display unit 14.
[0045] The operation acceptance unit 112 of the terminal device 10 accepts a user operation via the operation unit 15. For example, when the operation acceptance unit 112 accepts an operation on the operation assistance screen displayed on the display unit 14, the operation acceptance unit 112 notifies the server device 20 of the content of the operation.
[0046] On the other hand, as shown in FIG. 7, the server device 20 includes a business flow creation support unit 211, a binary table creation unit 212, a transmission unit 213, and a determination unit 214 as functional units.
[0047] A part or all of the functional units of the server device 20 may be a software configuration realized by cooperation between the CPU 21 of the server device 20 and a program stored in a memory (e.g., the ROM 22 or the storage unit 26). Also, a part or all of the functional units of the server device 20 may be a hardware configuration realized by a dedicated circuit or the like mounted on the server device 20.
[0048] The workflow creation support unit 211 of the server device 20 provides an operation support screen for supporting the creation (or editing) and viewing of a workflow.
[0049] For example, the workflow creation support unit 211 provides an operation support screen on which drawing parts and the like corresponding to the notation rules of BPMN are arranged. Furthermore, when the workflow creation support unit 211 receives an operation to create a workflow via the operation support screen, it creates a data file representing the workflow according to the operation content and stores it in the workflow storage unit 2611.
[0050] In addition, when a business flow to be displayed or edited is specified from among the business flows stored in the business flow DB 261, the business flow creation support unit 211 reads the specified business flow and creates information that can be displayed on the terminal device 10 with the flow diagram of the business flow visualized.
[0051] There is no particular restriction on the method of selecting a business flow. For example, the names of business flows stored in the business flow DB 261 may be displayed as a list, and the selection of a business flow may be accepted from the displayed list. Also, for example, the flow diagrams representing each business flow stored in the business flow DB 261 may be displayed as a list using thumbnails, and the selection of a business flow may be accepted from the displayed list.
[0052] In addition, the business flow creation support unit 211 automatically assigns a process number to each node related to the created business flow in the order in which the business is performed. If a node related to the business flow branches midway, a process number is also automatically assigned to the branched node. The method of assigning the process number can be any known method, and there is no particular restriction.
[0053] Furthermore, the workflow creation support unit 211 supports the creation of attribute information. For example, when a node is selected, the workflow creation support unit 211 displays a creation support screen for inputting attribute information related to the business of the node.
[0054] The display unit 14 of the terminal device 10 displays the node name of the selected node, process number, input node, output node, pool name, etc. as a creation support screen, and resource information, analysis, etc. can be input.
[0055] In addition, the business flow creation support unit 211 stores the assigned process number in the attribute storage unit 2612 as attribute information of the node (stores it as process number 26122), thereby associating the node to which the process number was assigned with the stored attribute information.
[0056] Furthermore, the workflow creation support unit 211 displays part of the associated attribute information at the node related to the visualized workflow. The part of the information can be selectively set from the attribute information, for example, "node name" can be selected. When "node name" is selected, the node name representing the node is displayed together with the node as a workflow (see FIG. 4).
[0057] The binary table creation unit 212 is an example of a creation means. Based on the nodes set in the business flow and attribute information related to the nodes, the binary table creation unit 212 creates a binary table 90 in which the node names (business names) 92 of each node are arranged in one column (e.g., the X-axis direction) in the order of process numbers, and the resource names 95 of all resources related to the business executed at each node are arranged in the other column (e.g., the Y-axis direction). In addition, the binary table creation unit 212 clearly indicates the relationship between the business and the resources by attaching a mark (specific information) to the intersection of the arranged node name and the resource name 95 of the resource used in the business of the node name in the created binary table 90.
[0058] Specifically, the binary table creation unit 212 arranges the pool names, process numbers, and node names related to each node in one column (e.g., horizontal column) in the order in which the tasks are performed in the business flow (i.e., in the order of the process numbers assigned to each node), and arranges the resource names of the resources used by each node to perform the tasks in the other column (e.g., vertical column) by dividing them into pairs of physical resources and human resources. That is, a binary table 90 is created in which the node names and resource names are arranged in a matrix. Then, the binary table creation unit 212 marks the intersection of each arranged node name with the resource names (physical resources and human resources) used to perform the tasks at the node in question, based on the attribute information, in the created binary table 90. The created binary table 90 is stored in the table storage unit 262.
[0059] Fig. 8 is an example of a binary table 90 created by the binary table creation unit 212. In the binary table 90, pool names 91 ("receiving inspection" and "storage" in Fig. 8 (these pool names are just examples)) which are business domain names are arranged in the horizontal direction (X-axis direction). In addition, in correspondence with each pool name 91, node names 92 which are names of tasks included in each pool name 91 (for example, in FIG. 8, “Delivery”, “Confirm delivery note”, “Check lot / item / quantity”, “Search specifications”, “Sampling inspection 1 (weight)”, “Sampling inspection 1 (external dimensions)”, “Sampling inspection 1 (surface roughness)”, “Sampling inspection 2 (infrared analysis)”, “Sampling inspection 2 (scanning microscope)”, “Sampling inspection 2 (film thickness measurement)”, “Inspection completed”, “Inspection completed item”, “Check storage instruction and print list”, “Acceptance process for passed items”, “Attach passed inspection data”, “Code processing”, “Return process for rejected items”, “Find shelf number and store”, “Enter storage quantity in list”, “Storage completed”) and process numbers 93 assigned to each node (in FIG. 8, “A001” to “A008”, “A101” to “A103”, “B001” to “B008”, “B101”, and “B102”) are arranged in the order of task execution. Process numbers are automatically assigned in the order in which tasks are performed. Branching nodes are also automatically numbered in the order in which tasks are performed.
[0060] In addition, in the binary table 90, business area names 94 (in FIG. 8, "resource 1" (physical resource), "resource 2" (human resource), and "worker") are arranged in the vertical direction (Y-axis direction). In addition, in the binary table 90, in correspondence with each business area name 94, resource names 95 included in each business area name 94 (in FIG. 8, "supplier," "EDI system," "production system," "scanner," "multifunction printer," "handy terminal," "parts warehouse," and "completed box" (all of which are physical resources), "inspection department staff," "warehouse staff," and "part-time staff" (all of which are human resources) (these resource names are just examples) are arranged.
[0061] That is, the binary table creator 212 creates a binary table 90 in which pool names 91, node names 92, and process numbers 93 are arranged along the X-axis, and business domain names 94 and resource names 95 are arranged along the Y-axis.
[0062] 8, the created binary table 90 has an "*" mark (an example of identifying information, which is an example of identifying information) added to the column of the intersection between the node name 92 and the resource name 95 of the resource used in executing the task at each node based on the created attribute information. That is, in each node name 92, identifying information that can identify the resource used in the task indicated by the node name 92 is added. For example, in the node with the task name "Delivery", an "*" mark is added to the intersection with the resources used, "Supplier", "EDI System", "Parts Warehouse", and "Warehouse Manager", based on the "resource information" included in the attribute information shown in FIG. 5.
[0063] The binary table 90 also has each task area name 94 of "worker" in the column direction (Y-axis direction). In the binary table 90, "inspection department staff", "warehouse staff", "part-time worker", "man-hours", and "task subtotal by pool" (these resource names are examples) are arranged as resource names 95 included in each task area name 94 in association with each task area name 94 of "worker". In the resource name 95 "inspection department staff", "warehouse staff", and "part-time worker" related to "worker", a task ratio (%) indicating the ratio of time that the worker engages in the task related to the node name 92 written on the horizontal axis is entered. Since the "inspection department staff", "warehouse staff", and "part-time worker" each have their own post, the task ratio of each may be different. In the resource name 95 "man-hours" column, for example, the average time required for the worker to perform the task of the node is entered. In the "task subtotal by pool", the total time entered in the process column is entered.
[0064] The binary table 90 created in this way can be displayed on the display unit 14 in response to a request from the terminal device 10. For example, a user of the terminal device 10 looks at the binary table 90 shown in Fig. 8 and confirms the resources marked (displayed) with an "*" mark for each node name. This makes it possible to consider business improvements, such as reviewing the resources used in the business. The binary table 90 supports such business improvements.
[0065] Returning to the description of Fig. 7, the transmission unit 213 is an example of an output means. The transmission unit 213 outputs information about the created binary table 90 in a displayable manner. In the embodiment, the transmission unit 213 transmits (outputs) information related to the binary table 90 created by the binary table creation unit 212 to the terminal device 10 that has issued a display request in a manner that the terminal device 10 can display it.
[0066] The display control unit 111 of the terminal device 10 that has received the information related to the binary table 90 displays, for example, the binary table 90 shown in FIG. 8 on the display unit 14 based on the received information. In this state, the terminal device 10 is able to input information from the operation unit 15. For example, a user of the terminal device 10 can input information related to the task ratio and the man-hours into the worker column 97 of the displayed binary table 90. The information related to the task ratio and the man-hours is input by a person operating the operation unit 15. The operation reception unit 112 of the terminal device 10 receives the input information related to the task ratio and the man-hours. The information of the binary table 90 that has been changed based on the information received by the operation reception unit 112 is transmitted from the terminal device 10 to the server device 20. The binary table 90 may be displayed on the display unit 24 of the server device 20. In this case, the information related to the task ratio and the man-hours is input from the operation unit 25 of the server device 20.
[0067] The server device 20 updates the information of the binary table 90 stored in the table storage unit 262 based on the change information received from the terminal device 10. Also, the information of the relevant portion of the associated attribute information stored in the attribute storage unit 2612 is updated. Note that in the example of Fig. 8, the area 96 shown in black is set as "not applicable" in the analysis 26127, and input is not possible because no work is required by the operator.
[0068] FIG. 9 shows an example of a binary table 90 in an updated state in which the operation reception unit 112 has received input of information related to business ratios and information related to labor hours, the terminal device 10 has sent binary table change information in which the binary table 90 has been modified, the server device 20 has received the binary table change information, and the binary table creation unit 212 has stored and updated the information in the table memory unit 262.
[0069] As shown in FIG. 9, in a worker column 97 corresponding to each node, the work ratio by type of worker at each node (for example, the proportion of time spent on the work of the node) is input and stored.
[0070] Also, as shown in FIG. 9, in the updated binary table 90, man-hours indicating the time required to execute a task at each node are input and stored in association with each node.
[0071] The binary table creation unit 212 highlights, for example, the point (intersection) with the largest task ratio in the information on task ratios and man-hours in the updated binary table 90. The highlighting is performed, for example, by hatching the area of the intersection or by making the background color different from that of the other intersections (making it stand out), so that the intersection can be displayed in a recognizable manner and distinguished from the other intersections. In Fig. 9, the intersection 98 between the node A005 of "sampling inspection work" and the inspection department worker who is an operator, the intersection B003 between the node B003 of "find and store the shelf number" and the warehouse worker who is an operator, and the intersection 100 between the node B003 of "find and store the shelf number" and the part-time worker who is an operator have a larger ratio than the task ratios of the other intersections, and are stored so as to be able to be highlighted.
[0072] In addition, as the binary table 90 is updated, the information on the task ratio and labor hours entered at the terminal device 10 is reflected and stored in the attribute information corresponding to each node, which is associated with the binary table 90 and stored in the attribute memory unit 2612.
[0073] Fig. 10 is an example of attribute information stored in the attribute storage unit 2612 for node Ab of "Delivery Note Confirmation" reflecting the input task ratio and man-hours. As shown in Fig. 10, after the resource information "Inspection Department", information of "10%" is updated (stored) as the task ratio of the inspection department in the task, and after "Part-time Worker", information of "10%" is updated (stored) as the task ratio of part-time work in the task. In addition, "1h (1 hour)" is updated (stored) as the man-hours for node Ab (the time required to perform the task of node Ab).
[0074] Returning to the explanation of Fig. 7, the determination unit 214, which is an example of a determination means, determines the process that requires the longest time to perform a task in a task flow from among multiple processes (four processes of pattern A, pattern B, pattern C, and pattern D in this embodiment) based on the man-hours (time required to perform a task related to the node) of each node stored in the attribute storage unit 2612. Specifically, the determination unit 214 extracts the man-hours (time required to perform a task of each node) from the attribute information corresponding to each node in each of the multiple processes (four processes of pattern A, pattern B, pattern C, and pattern D), calculates the total man-hours by adding them up by pattern, and determines the one process with the longest total man-hours (requiring the longest time).
[0075] FIG. 11 is an explanatory diagram in which the determining unit 214 extracts the man-hours at each node and calculates the total man-hours in the patterns A, B, C, and D.
[0076] Pattern A is shown in box Pa. As shown in box Pa, the determination unit 214 extracts the man-hours from nodes Aa to Ah and nodes Ba to Bh, and calculates the total man-hours (total time) by adding up the man-hours for each node. The total man-hours for pattern A is 16.5h (16.5 hours).
[0077] Pattern B is shown in a box Pb. As shown in box Pb, the determination unit 214 extracts the man-hours from nodes Aa to Ad, nodes Aj to Am, nodes Ah, and nodes Ba to Bh, and calculates the total man-hours by adding up the man-hours for each node. The total man-hours for pattern B is 14.5h (14.5 hours).
[0078] Pattern C is shown in box Pc. As shown in box Pc, the determination unit 214 extracts the man-hours of nodes Aa to Ah, Ba, Bb, Bj, Bk, and Be to Bh, and calculates the total man-hours by adding up the man-hours of each node. The total man-hours of pattern C is 16h (16 hours).
[0079] Pattern D is shown in box Pd. As shown in box Pd, the determination unit 214 extracts the man-hours from nodes Aa to Ad, nodes Aj to Am, nodes Ah, nodes Ba, nodes Bb, nodes Bj, nodes Bk, and nodes Be to Bh, and calculates the total man-hours by adding up the man-hours for each node. The total man-hours for pattern D is 14h (14 hours).
[0080] Returning to the explanation of Fig. 7, the determination unit 214 compares the total man-hours of the patterns A, B, C, and D, and determines one process with the longest man-hours (taking the longest time). In the example of Fig. 11, the determination unit 214 determines the process of the pattern A with a total man-hours of 16.5 hours.
[0081] The transmission unit 213 distinguishes the process determined by the determination unit 214 (pattern A in this embodiment) from other processes in the workflow stored in the workflow storage unit 2611. For example, the transmission unit 213 distinguishes the determined process from other processes by emphasizing it more than other processes. As an example of emphasis, for example, the frame of the determined process or the arrow connecting the node is made thicker than the other processes. For example, the color of the frame of the determined process or the arrow connecting the node is made different from the other processes. For example, the frame of the node of the determined process is made different from the other processes by shading it. Note that the determined process may be distinguished from the other processes by a method other than emphasis.
[0082] The sending unit 213 stores the workflow in which the process determined by the determination unit 214 is highlighted in the longest time process unit 2613 .
[0083] Fig. 12 shows a workflow in which the process determined by the determination unit 214, which is stored in the longest time process unit 2613, is highlighted by the transmission unit 213 to distinguish it from other processes. As shown in Fig. 12, in the embodiment, the nodes and arrows of the process determined by the determination unit 214 (pattern A) are highlighted in bold.
[0084] The transmission unit 213 outputs a workflow in which the determined process is distinguished from other processes (the workflow stored in the longest time process unit 2613) in a displayable manner. In the embodiment, information on the workflow in which the process taking the longest time shown in FIG. 12 is highlighted is transmitted to the terminal device 10 so that the terminal device 10 can display it.
[0085] The updated and stored binary table 90 can be displayed on the terminal device 10. For example, when looking at the binary table 90 shown in Fig. 9, it can be determined that the highlighted intersections (intersection 98, intersection 99, intersection 100) are tasks that have a high task ratio and are tasks that place a heavy burden on workers, executed at the node. For this reason, it is possible to consider task improvements, such as reviewing the resources used in the task. The binary table 90 supports such task improvements.
[0086] For example, the work ratio of the inspection department staff for the task of "Sampling inspection 1 (weight)" is high at 19%. Currently, the physical resource used for the task "Sampling inspection 1 (weight)" is a scanner, but it can be considered whether it is possible to reduce the work ratio by changing this scanner to another (or new) resource. Additionally, currently, the human resource used for the task "Sampling inspection 1 (weight)" is the inspection department staff, but it can be considered whether it is possible to reduce the work ratio by changing the inspection department staff to another staff member or by increasing the number of inspection department staff members.
[0087] Furthermore, the terminal device 10 visually displays the business process flow (business process flow shown in FIG. 12) stored in the longest time process unit 2613 on the display unit 14. Therefore, by looking at the displayed business process flow, it is possible to grasp which process takes the most time (the process that takes the longest time to execute the business). Therefore, it is possible to focus on the identified longest process and use this to improve the business process.
[0088] From here, the control process of the server device 20 will be described. FIG. 13 is a flowchart showing an example of a process related to the creation of attribute information executed by the server device 20 of the embodiment. As shown in FIG. 13, the CPU 21 of the server device 20 calls attribute information related to a specified node from the attribute storage unit 2612. Then, the CPU 21 displays the called attribute information on the display unit 24 (S11). For the displayed attribute information, the person in charge operates the operation unit 25 to input information related to the node name 26121, resource information 26123, pool name 26126, and analysis 26127. If the task ratio and man-hours for each node are known, they may be input here. The process number 26122, the Input node 26124, and the Output node 26125 are automatically input with an automatically assigned process number, which will be described later in FIG. 12.
[0089] Next, CPU21 judges whether information has been input for the displayed attribute information (S12). This judgment is made, for example, by judging whether the person in charge has operated an input end button (not shown). The CPU21 waits until information is input (No in S12), and if it judges that information has been input for the displayed attribute information (Yes in S12), the CPU21 stores attribute information including the input information in attribute storage unit 2612, and updates the storage of the attribute information (S13). Then, CPU21 ends the processing. In this state, the attribute information stores a process number, thereby associating each node with the attribute information, which is information on the node.
[0090] In addition, when there is a display request of the attribute information from the terminal device 10 and the attribute information is input in the terminal device 10, FIG. 11 is reinterpreted as follows. That is, in S11, the CPU 21 transmits the attribute information called from the attribute storage unit 2612 to the terminal device 10. The CPU 11 of the terminal device 10 displays the received attribute information on the display unit 14. Then, in the terminal device 10, the user operates the operation unit 15 to input information related to the node name 26121, the resource information 26123, the pool name 26126, and the analysis 26127. If the task ratio and the man-hours in each node are known, they are input here. The CPU 11 transmits the attribute information including the input information to the server device 20. The server device 20 judges whether the attribute information has been received from the terminal device 10 (S12), and if it is judged that the attribute information has been received (Yes in S12), it stores the attribute information in the attribute storage unit 2612 and updates the storage of the attribute information (S13). In this case as well, the process number 26122, the input node 26124, and the output node 26125 are automatically stored in the attribute storage unit 2612 as automatically assigned process numbers, which will be described later with reference to FIG.
[0091] Next, the automatic assignment of process numbers will be described. FIG. 14 is a flowchart showing an example of a process related to the automatic assignment of process numbers executed by the server device 20 of the embodiment. As shown in FIG. 14, the CPU 21 judges whether there is an instruction to assign a process number to the created business flow (S21). This instruction is issued, for example, when an operation to assign a process number to the created business flow is performed, or automatically when the business flow is created. If it is judged that there is an instruction to assign a process number (Yes in S21), the CPU 21 assigns a process number to each node in the created business flow in the order of business execution (S22). If the business flow branches midway, a process number is also assigned to the branched node. In this case, the branched node may be numbered with a serial number, or a number different from the serial number may be assigned so that the branch is known. In the embodiment, a number different from the serial number is assigned so that the branch is known. The assigned process number is then stored in each node of the business flow stored in the business flow storage unit 2611 and in the process number 26122 of the attribute information associated with each node and stored in the attribute storage unit 2612 (S23), the process number immediately preceding the assigned process number is stored in the Input node 26124 (S23), and the process number immediately following the assigned process number is stored in the Output node 26125 (S23).The CPU 21 then terminates the processing.
[0092] Furthermore, if it is determined in S21 that the instruction is not to assign a process number (No in S21), it is determined whether the workflow stored in the workflow storage unit 2611 has been changed, such as whether some nodes have been deleted, or new nodes have been added, or whether some nodes have been deleted and new nodes have been added (S24). The workflow is changed, for example, by the terminal device 10. The CPU 21 determines whether the workflow has been changed based on whether there has been an instruction to change from the terminal device 10. If it is determined that the workflow has been changed (Yes in S24), the CPU 21 reassigns a new process number to the entire workflow after the change (S25). In the process of S25, a process is performed to store the new process number in the attribute information. Then, the CPU 21 ends the process.
[0093] If it is determined that there is no change in the business flow (No in S24), the CPU 21 ends the process.
[0094] In this way, when a control flow is created, CPU21 assigns a process number to each node in the created business flow in the order in which the business is performed. The assigned process numbers are stored as attribute information. Then, when the business flow is changed, CPU21 assigns a new process number to the changed business flow. The assigned process number is stored as attribute information of each node and is associated with each node.
[0095] Next, a description will be given of the control of creating the binary table 90 based on the attribute information stored in the attribute storage unit 2612 in the server device 20, and the control of determining, storing, and transmitting the longest process based on the attribute information stored in the attribute storage unit 2612. FIG. 15 is a flowchart showing an example of the process related to creating and changing the binary table 90 executed by the server device 20 of the embodiment. As shown in FIG. 15, the CPU 21 judges whether an instruction to create the binary table 90 has been received (S31). The instruction to create the binary table 90 is issued by performing an operation to specify a business flow from the operation unit 25 of the server device 20. Alternatively, the instruction to create the binary table 90 is issued by receiving an instruction signal to create a binary table related to the business flow from the terminal device 10 in association with the specification of the business flow specified from the operation unit 15 of the terminal device 10.
[0096] When it is determined that an instruction to create a dual-value table 90 has been issued (Yes in S31), the CPU 21 reads all attribute information for the specified workflow from the attribute storage unit 2612 (S32). The dual-value table creation unit 212 (creation means) then creates the dual-value table 90 based on the read attribute information (S33). The dual-value table creation unit 212 then adds specific information to the resource name 95 used in correspondence with the business of each node name 92 in the dual-value table 90 created based on the read attribute information. That is, the dual-value table creation unit 212 creates a dual-value table 90 in which an * is added to the intersection with the resource name 95 used in correspondence with the business of each node name 92 in the dual-value table 90 created based on the read attribute information. The CPU 21 then stores the information of the created dual-value table 90 in the table storage unit 262 (S34). The CPU 21 then ends the process.
[0097] Furthermore, if it is determined that the instruction is not an instruction to create the dual element table 90 (No in S31), the CPU 21 determines whether or not information of a display request for the created dual element table 90 has been received from the terminal device 10 (S41). If it is determined that information of a display request for the dual element table 90 has been received from the terminal device 10 (Yes in S41), the transmission unit 213 transmits information of the dual element table 90 stored in the table storage unit 262 (information that allows the terminal device 10 to display the dual element table 90) to the terminal device 10 (S42). Furthermore, the transmission unit 213 transmits information of the business flow stored in the longest time process unit 2613 to the terminal device 10 (S43). Then, the CPU 21 ends the process.
[0098] Also, when it is determined that the request is not a display request for the dual-ary table 90 from the terminal device 10 (No in S41), the CPU 21 determines whether or not dual-ary table change information has been received from the terminal device 10 (S51). When the terminal device 10 inputs information on the task ratio or the labor hours into the dual-ary table 90 displayed on the terminal device 10, the terminal device 10 receives dual-ary table change information, which is information on the dual-ary table 90 reflecting the information on the task ratio or the labor hours. When it is determined that the dual-ary table change information has been received from the terminal device 10 (Yes in S51), the dual-ary table creation unit 212 stores the dual-ary table change information received from the terminal device 10 in the table storage unit 262 (S52). Furthermore, the dual-ary table creation unit 212 updates the attribute information stored in the attribute storage unit 2612 based on the received dual-ary table change information (S52). That is, the dual-ary table creation unit 212 stores new attribute information reflecting the information on the task ratio or the labor hours inputted by the terminal device 10 in the attribute storage unit 2612 (S52).
[0099] Next, the binary table creation unit 212 extracts the task with the largest workload among the tasks performed by each worker type from the stored task ratios in the updated binary table 90, and highlights the intersection with the extracted node with the largest workload (S53). Then, the CPU 21 ends the process. Next, the determination unit 214 determines the longest process based on the man-hour information included in the attribute information updated in S52 (S54). Furthermore, the transmission unit 213 stores the process determined by the determination unit 214 with emphasis.
[0100] Fig. 16 is a flowchart related to the determination, emphasis, and storage of the longest process to be executed in S54. As shown in Fig. 16, the determination unit 214 extracts the man-hours (time required for the work executed in each node) at each node based on the attribute information updated in S54 (S541). The determination unit 214 then adds up the extracted man-hours for each process to calculate the total man-hours (total time) for each process (S542). The determination unit 214 then determines the one process with the longest calculated total man-hours (S543).
[0101] Next, the transmission unit 213 calls up the workflow stored in the workflow storage unit 2611 and emphasizes the longest process (S544). The transmission unit 213 then stores the workflow with the emphasized longest process (workflow in FIG. 12) in the longest time process unit 2613 (S545). The CPU 21 then ends the process.
[0102] Returning to the description of Fig. 15, if the CPU 21 determines that the man-hours have already been stored for all of the attribute information read out in S32, after the process of S34, the process of S54 may be executed based on the man-hours.
[0103] From here, the control process of the terminal device 10 will be described. Fig. 17 is a flowchart showing an example of the control process of the terminal device 10 of the embodiment. As shown in Fig. 17, the CPU 11 of the terminal device 10 judges whether a display request operation has been made to display the binary table 90 on the terminal device 10 (S61). The display request operation of the binary table 90 is performed, for example, by operating the operation unit 15. If it is determined that a display request operation of the binary table 90 has been made (Yes in S61), the CPU 11 transmits information indicating a display request for the binary table 90 to the server device 20 (S62).
[0104] Next, the CPU 11 judges whether the information on the dual element table 90 and the business flow have been received from the server device 20 (S63). The CPU 11 waits until the information on the dual element table 90 and the business flow have been received from the server device 20 (No in S63), and if it is judged that the information on the dual element table 90 and the business flow have been received from the server device 20 (Yes in S63), the CPU 11 displays the dual element table 90 on the display unit 14 based on the received information on the dual element table 90 (S64). The CPU 11 also displays the received business flow on the display unit 14 (S65). If the received business flow is one in which the process with the longest man-hours is emphasized more than the other processes, the business flow shown in FIG. 12 is displayed (S65).
[0105] Next, the CPU 11 determines whether the content of the displayed binary table 90 has been changed (S66). If either or both of the task ratio information and the man-hour information have been entered into the displayed binary table 90, the CPU 11 determines that the content of the binary table 90 has been changed.
[0106] If it is determined that the contents of the binary table 90 have been changed (Yes in S66), the CPU 11 transmits binary table change information, which is information on the binary table 90 including the changed information (either or both of the input task ratio information and man-hour information), to the server device 20 (S67).Then, the CPU 11 ends the process.
[0107] If it is determined in S61 that the operation is not a request to display the binary table 90 (No in S61), the CPU 11 executes the determination in S66 without executing the processes in S62 to S65. If it is determined that the operation is not a change to the contents of the binary table 90 (No in S66), the CPU 11 ends the process without executing the process in S67.
[0108] Such a terminal device 10 requests the display of a binary table 90 including either or both of task ratio information and labor-hour information again in the process of S61, and displays the binary table 90 shown in Fig. 9 in the process of S64. Therefore, a user who sees the display can determine which tasks have a high task ratio and a heavy burden among the tasks executed at each node. Therefore, it is possible to consider improvements to the tasks, such as reviewing the resources used in the tasks.
[0109] In addition, such a terminal device 10 displays a business flow in which the process with the longest man-hours is emphasized more than the other processes. Therefore, a user who sees the display can understand which process requires the most man-hours, and can consider business improvements for that process.
[0110] As described above, the server device 20 of the embodiment includes a memory unit 26 that stores attribute information including the time required to execute the business of a node, associated with each of the nodes of a business flow branched into multiple processes, with the multiple nodes related to the execution of the business being defined in the order in which the business is performed, a determination unit 214 that determines the process that takes the longest time to execute the business from the multiple processes based on the time for each node stored in the memory unit 26, and a transmission unit 213 that outputs the business flow in which the determined process is distinguished from other processes in a displayable manner.
[0111] The server device 20 in this embodiment transmits a business flow in which the process that takes the longest time to execute a business operation is identified from the other processes so that the business flow can be displayed on the terminal device 10. The server device 20 in this embodiment can provide business improvement support that can identify the process that takes the longest time to execute a business operation in a business flow having multiple processes.
[0112] In addition, the server device 20 of the embodiment outputs a binary table 90 including either or both of task ratio information and labor-hour information, so that the output destination can visually grasp the resources used for each task and determine which tasks have a high task ratio or / and a large labor-hour and thus a heavy burden among the tasks executed at each node. In other words, the relationship between the time required to execute a task and the resources used can be seen. Therefore, for example, by reviewing the resources used in the task, it is possible to consider task improvements such as whether the time required to execute the task can be reduced. Therefore, it is possible to provide support for task improvement based on the task flow.
[0113] Although the embodiment of the present invention has been described above, this embodiment is presented as an example and is not intended to limit the scope of the invention. These new embodiments and their modifications can be implemented in various other forms, and various omissions, substitutions, and modifications can be made without departing from the gist of the invention. These embodiments and their modifications are included in the scope and gist of the invention, and are included in the scope of the invention and its equivalents described in the claims.
[0114] For example, in the embodiment, the server device 20 has been described as an example of a business improvement support device. However, the present invention is not limited to this, and for example, the terminal device 10 may be the business improvement support device. Furthermore, a system including the server device 20 and the terminal device 10 may be the business improvement support device.
[0115] In the embodiment, the information on the man-hours is input to the binary table 90 displayed on the terminal device 10. However, the present invention is not limited to this, and the man-hours may be input by other methods. For example, the man-hours may be input to the attribute information displayed on the server device 20 or the terminal device 10.
[0116] In the embodiment, the workflow is branched into two branches. However, the present invention is not limited to this, and the number of branches is not important. In the embodiment, four patterns of processes are shown. However, the present invention is not limited to this, and the number of processes in the workflow is not important.
[0117] In the embodiment, a workflow having multiple steps that branches and then merges is described. However, the present invention is not limited to this, and may be, for example, a workflow that starts with multiple steps and then merges, or a workflow that branches and then ends with multiple steps.
[0118] Also, in the embodiment, the transmission unit 213 transmits the information on the workflow stored in the binary table 90 and the longest time step unit 2613. However, the transmission unit 213 as the output means only needs to transmit the information on the workflow stored in the longest time step unit 2613, and transmission of the binary table 90 is not essential.
[0119] Also, in the embodiment, the server device 20 transmits information about a workflow to the terminal device 10, and considers improvements to the workflow based on the workflow displayed on the terminal device 10. However, the present invention is not limited to this, and the server device 20 may display the workflow on its own display unit 24, and may accept input of processes based on the displayed workflow to consider improvements to the workflow. [Explanation of symbols]
[0120] 1. Business improvement support system 10 Terminal Equipment 11 CPU 12 ROM 13 RAM 14 Display section 15 Control section 16 Memory section 17 Communications Department 20 Server device 21 CPU 22 ROM 23 RAM 24 Display section 25 Control section 26 Memory section 111 Display control unit 112 Operation reception section 211 Workflow Creation Support Department 212 Two-way table creation section 213 Transmitter 214 Decision Section 262 Table storage section 2611 Business flow memory unit 2612 Attribute storage 2613 Longest time process section [Prior art documents] [Patent documents]
[0121] [Patent Document 1] JP 2014-235470 A
Claims
1. a storage unit that stores attribute information including a time required for executing a task of a node in association with each of a plurality of nodes of a workflow having a plurality of steps, the plurality of nodes being defined in the order in which the tasks are performed; a determination means for determining, from the plurality of processes, a process that requires the longest time for performing a task, based on the time for each node stored in the storage unit; an output means for displayably outputting the business flow in which the determined process is identified from other processes; A business improvement support device equipped with the above.
2. a creation means for creating a binary table in which, based on said attribute information, task names of tasks executed at each node are arranged in one column in the order in which said tasks are performed, and resource names of all resources used in said tasks included in said attribute information of each node are arranged in another column, and specific information for identifying the resources used in said tasks is added for each task; Further equipped with the output means outputs the information of the created binary table in a displayable manner; the storage unit stores the time input for each node in the displayed binary table in such a manner that the time is reflected in the attribute information corresponding to the node. The business improvement support device according to claim 1.
3. the determining means calculates a total time by adding up the time at each of the nodes included in each of the processes, and determines one process having the longest calculated total time.
3. The business improvement support device according to claim 1 or 2.
4. The output means outputs the determined process so as to be displayed in an emphasized manner compared to the other processes.
3. The business improvement support device according to claim 1 or 2.
5. The specific information is mark information attached to the intersection of each arranged business name and the resource name of the resource used in the business of the business name. The business improvement support device according to claim 2.
6. Computers as business improvement support devices a storage unit that stores attribute information including a time required for executing a task of a node in association with each of a plurality of nodes of a workflow having a plurality of steps, the plurality of nodes being defined in the order in which the tasks are performed; a determination means for determining, from the plurality of processes, a process that requires the longest time for performing a task, based on the time for each node stored in the storage unit; an output means for displayably outputting the business flow in which the determined process is identified from other processes; A program to make it function as such.
Citation Information
Patent Citations
Method and device for assisting transaction analysis and transaction analytic table used for same
JP1995249024A
Data processing method and its processor
JP1997231280A
Business flowchart creating program and business flowchart creating device
JP2009110274A
Workflow improvement system, workflow improvement method, and workflow improvement program
JP2010146091A
Emergency command support server, scenario implementation method, computer program
JP2010204713A