Production plan generating system

The production plan generation system addresses inefficiencies in conventional devices by prioritizing post-processes, optimizing the mounting process, and using common setups to enhance overall production efficiency.

JP2024155057AActive Publication Date: 2024-10-31YAMAHA MOTOR CO LTD

Patent Information

Application Number
JP2023069445
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-20
Publication Date
2024-10-31
Estimated Expiration
2043-04-20

AI Technical Summary

Technical Problem

Conventional production plan creation devices prioritize the efficiency of the mounting process over subsequent processes, leading to inefficient production plans when creating plans for board devices that require both mounting and post-processing.

Method used

A production plan generation system that considers post-processes by adjusting the mounting process to allow for earlier start times, dividing production lots, optimizing the mounting order, and using common setups for component supply units to ensure efficient completion of both processes.

Benefits of technology

Generates a production plan that allows for earlier completion of post-processes, reducing overall production time and improving efficiency by minimizing setup changes and optimizing resource allocation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024155057000001_ABST
    Figure 2024155057000001_ABST
Patent Text Reader

Abstract

To provide a production plan generating system capable of generating a production plan for efficiently producing board devices.SOLUTION: A production plan generating system comprises: an acquisition unit for acquiring implementation information on an implementation process of implementing electronic components on a plurality of types of boards and post-process information on a post-process to be started after completion of part of the implementation process; and a generation unit for generating a production plan. The generation unit performs the implementation process in a mode in which a required number of electronic components required for producing a target number of board devices are implemented in order for respective board types, acquires post-process start time in a reference plan for starting the post-process at the time point at which all board types are prepared from the implementation information and the post-process information, and adjusts the implementation process so that the post-process can be started at time earlier than the post-process start time in the reference plan, to generate a post-process start priority plan for making termination time of the post-process be earlier than termination time of the post-process in the reference plan, as the production plan.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a production plan generation system. [Background technology]

[0002] Conventionally, there is known a device that generates a plan that can efficiently proceed with a mounting process in which electronic components are mounted on multiple types of boards. For example, Patent Document 1 discloses a production plan creation device that creates a production plan for producing multiple types of mounted boards (substrates). This production plan creation device divides the types of mounted boards into multiple production lots based on production information including the production volume and production delivery date for each type of mounted board to be produced, production line information including information on production equipment, and the operating time of the production line. Then, the divided multiple production lots are assigned to the operating times of multiple production lines based on a predetermined assignment guideline, thereby creating a production plan with high production efficiency. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2020-098509 A Summary of the Invention [Problem to be solved by the invention]

[0004] The production plan creation device described in Patent Document 1 may generate an inefficient production plan because it prioritizes the efficient progress of the mounting process. Specifically, the production plan creation device does not consider how the post-process will proceed when creating a production plan. The post-process refers to electrical tests performed on various boards produced in the mounting process, and a process of assembling a board device using various boards produced in the mounting process together with other components. Therefore, when the production plan creation device is made to create a production plan for a device (board device) that is produced through a mounting process and a post-process, a production plan may be generated in which the mounting process proceeds efficiently while the post-process proceeds inefficiently.

[0005] The present invention has been made in consideration of the above-mentioned problems, and has an object to provide a production plan generation system capable of generating a production plan that enables efficient production of board devices. [Means for solving the problem]

[0006] A production plan generation system according to one aspect of the present invention is a production plan generation system that generates a production plan for producing two or more target quantities of board devices having multiple types of boards as constituent members, and includes an acquisition unit that acquires mounting information of a mounting process in which electronic components are mounted on the multiple types of boards and post-process information of a post-process that is started after part of the mounting process is completed, and a generation unit that generates the production plan, wherein the generation unit performs the mounting process in a manner in which a required quantity necessary to produce the target number of board devices is mounted sequentially for each board type, acquires from the mounting information and the post-process information a post-process start time in a master plan for starting the post-process when all board types are ready, and generates as the production plan a post-process start priority plan that makes the end time of the post-process earlier than the end time of the post-process in the master plan by adjusting the mounting process so that the post-process can be started at a time earlier than the post-process start time in the master plan.

[0007] According to this production plan generation system, a post-process start priority plan is generated, which is a production plan that takes the post-process into consideration. Specifically, in the present invention, a post-process start priority plan is generated based on the mounting information and the post-process information acquired by the acquisition unit. This post-process start priority plan is a plan in which the mounting process is adjusted so that the post-process can be started at a time earlier than the post-process start time of the master plan in order to end the post-process earlier than the end time of the post-process in the master plan. Therefore, according to the production plan generation system of the present invention, a production plan that enables efficient production of board devices can be generated.

[0008] In the above-mentioned production plan generation system, it is preferable that the production plan generation system further includes an output unit that outputs the production plan, and when the generation unit cannot generate a subsequent process start priority plan in which the end time of the subsequent process is earlier than the end time of the subsequent process in the base plan, the output unit outputs the base plan as the production plan.

[0009] According to this configuration, if it is not possible to generate a post-process start priority plan in which the post-process ends earlier than the end time of the post-process in the master plan, the master plan is output as the production plan. This makes it possible to more reliably provide a production plan that enables efficient production of board devices to users of the production plan generation system.

[0010] In the above production plan generation system, it is desirable that the multiple types of boards include at least a first board and a second board different from the first board, the generation unit includes a layout plan generation unit that generates a layout plan for a component supply unit for supplying the electronic components to be mounted on the first board and the second board in the mounting process, and the layout plan generation unit generates the layout plan that can be shared for mounting the first board and the second board in the post-process start priority plan.

[0011] According to this configuration, in the post-process start priority plan, a layout plan of component supply units that can be used for mounting the first board and the second board is generated. Therefore, in the post-process start priority plan, it is not necessary to change the setup of the component supply units every time the type of board to be mounted in the mounting process is switched from the first board to the second board. This makes it possible to reduce the time required for the setup change compared to a case in which the mounting process is carried out in a manner in which the setup of the component supply units is changed every time the type of board is changed.

[0012] In the above-mentioned production plan generation system, the generation unit has a lot division unit that divides a production lot of the substrate device in the post-processing into two or more post-processing lots, and it is desirable that the lot division unit sets the two or more post-processing lots in the post-processing start priority plan so that the timing when a feasible quantity of the multiple types of substrates that can be used to execute one of the post-processing lots is available and the timing when the post-processing lot starts are close to each other.

[0013] According to this configuration, the post-processing is divided into lots so that the mounting process and the post-processing can proceed efficiently. Specifically, the post-processing lot starts as soon as the possible number of boards is prepared, and before the post-processing lot is completed, the possible number of boards is prepared again and the next post-processing lot starts. In this manner, the mounting process and the post-processing proceed simultaneously in parallel. Therefore, a more efficient production plan can be generated.

[0014] In the above-mentioned production plan generation system, it is preferable that the generation unit further has a required time calculation unit that calculates a required time required to prepare the feasible quantities of the multiple types of boards in the mounting process based on the mounting information, and a determination unit that determines a post-processing start time, which is the earliest time at which the earliest post-processing lot among the two or more post-processing lots can be started based on the required time.

[0015] According to this configuration, it is possible to specify the earliest time when the earliest post-processing lot among two or more post-processing lots can be started, i.e., the post-processing possible start time, which is the time when the post-processing can be started earliest. By having the generating unit generate a post-processing start priority plan in which the post-processing starts at this post-processing possible start time, it is possible to make the end time of the post-processing in the post-processing start priority plan as early as possible. As a result, it is possible to generate a more efficient production plan.

[0016] In the above-mentioned production plan generation system, it is preferable that the multiple types of boards include at least a first board and a second board that is a different type from the first board, and the generation unit includes a mounting order adjustment unit that adjusts a mounting order in which the first board and the second board are mounted so as to shorten the end time of the post-process.

[0017] According to this configuration, the mounting order adjustment unit adjusts the mounting order so that the end time of the post-process is as early as possible, thereby making it possible to generate a more efficient production plan. Effect of the Invention

[0018] According to the present invention, there is provided a production plan generation system capable of generating a production plan that enables efficient production of substrate devices. [Brief description of the drawings]

[0019] [Figure 1] 1 is a diagram illustrating an outline of a configuration of a production plan generating system according to an embodiment of the present invention. [Diagram 2] FIG. 2 is a diagram showing a schematic flow of a process for producing a substrate device; [Diagram 3] FIG. 2 is a plan view showing a configuration of the component mounting apparatus. [Figure 4] FIG. 2 is a block diagram showing an electrical configuration of the production plan generating device. [Diagram 5] 1A is a time chart showing an example of a standard schedule, and FIG. 1B is a time chart showing an example of a subsequent-process start priority schedule. [Figure 6] 13A is a time chart showing another example of the master schedule, and FIG. 13B is a time chart showing another example of the subsequent-process start priority schedule. [Figure 7] 11 is a flowchart showing an example of a process in a production plan generating device. [Figure 8] 1A is a time chart showing an example of a standard plan according to a modified embodiment, FIG. 1B is a time chart showing an example of a balanced plan, and FIG. 1C is a time chart showing an example of a post-process start priority plan according to a modified embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0020] Hereinafter, embodiments of the present invention will be described with reference to the drawings. Note that the following embodiments are specific examples of the present invention and do not limit the technical scope of the present invention.

[0021] [Overall configuration of production plan generation system 10] FIG. 1 is a diagram showing a schematic configuration of a production plan generation system 10 according to an embodiment of the present invention, and FIG. 2 is a diagram showing a schematic flow until a substrate device 100 is produced. The production plan generation system 10 is a system for generating a production plan for producing a target number of substrate devices 100 having a first substrate A, a second substrate B, and a third substrate C, each of which is different from the other substrate devices 100, as components. As shown in FIG. 1 and FIG. 2, the substrate device 100 is a device that is produced through a mounting process, which will be described later, and a post-process, which will be described later. The production plan generation system 10 generates a production plan that allows the mounting process and the post-process to proceed efficiently. As shown in FIG. 1, the production plan generation system 10 includes a production system 1 and a production plan generation device 4.

[0022] [Production System 1 Configuration] The production system 1 is a system for producing a substrate device 100. The production system 1 has a component mounting line 2 and a post-process line 3, as shown in FIG.

[0023] The component mounting line 2 is a production line for mounting various electronic components on a board. Note that hereinafter, electronic components may be simply referred to as "components." The component mounting line 2 according to this embodiment mounts various components on a board to individually produce a first board A, a second board B, or a third board C, each of which is different. Note that the component mounting line 2 is also compatible with a production method in which components for producing the first board A to the third board C are mounted on a so-called multi-panel board.

[0024] 1, the component mounting line 2 has a pattern forming device 21, a pattern inspection device 22, a plurality of component mounting devices 23, a mounting inspection device 24, a reflow device 25, a reflow inspection device 26, and a mounting management device 27. In this embodiment, a series of processes performed by these processing devices in the component mounting line 2 is called a mounting process. The mounting process can also be referred to as a process for mounting electronic components on the first board A, the second board B, or the third board C.

[0025] The pattern forming device 21 is a processing device that performs a pattern forming process to form a solder paste pattern on a board that has been brought into a predetermined work area.

[0026] The pattern inspection device 22 is disposed downstream of the pattern formation device 21 and is a processing device that inspects the processing state of the pattern formation process in the pattern formation device 21 .

[0027] The multiple component mounting devices 23 are processing devices that perform a component mounting process for mounting components on a board on which a solder paste pattern is formed. FIG. 1 shows an example in which the multiple component mounting devices 23 are configured with a first component mounting device 23a, a second component mounting device 23b, a third component mounting device 23c, and a fourth component mounting device 23d. Each of the component mounting devices 23a to 23d is configured to be able to mount various components on a board moving through the component mounting line 2. Hereinafter, the configuration of the first component mounting device 23a will be described with reference to FIG. 3. Note that the configurations of the second component mounting device 23b to the fourth component mounting device 23d are similar to that of the first component mounting device 23a, and therefore will not be described.

[0028] Fig. 3 is a plan view showing the overall configuration of component mounting apparatus 23. In Fig. 3, directional relationships are shown using XY orthogonal coordinate axes. The X-axis direction is parallel to the horizontal plane, and the Y-axis direction is perpendicular to the X-axis direction on the horizontal plane. Component mounting apparatus 23 includes a mounting machine main body 230 mainly including a base 231, a conveyor 232, a component supply area 233, and a head unit 234, and a component supply unit 235 arranged in the component supply area 233 of this mounting machine main body 230.

[0029] The base 231 is a mounting base for various devices included in the component mounting device 23. The conveyor 232 is a board transport line installed on the base 231 so as to extend in the X direction, and is composed of a pair of belt-type conveyors 232a. FIG. 3 shows an example in which the first board A is carried in. The conveyor 232a carries the first board A from outside the machine to a predetermined mounting work position, and after the head unit 234 carries out the component mounting work, carries the first board A out of the machine from the mounting work position. The position of the first board A shown in FIG. 3 is the mounting work position.

[0030] The component supply areas 233 are provided on both sides of the conveyor 232a in the Y direction. A plurality of component supply units 235 are arranged in parallel in each component supply area 233. The plurality of component supply units 235 supply various types of components to the component supply area 233. The types of components supplied by each component supply unit 235 and the arrangement of each component supply unit 235 can be changed as appropriate.

[0031] The head unit 234 is configured to be movable in the horizontal direction (X and Y directions) at least in the space above between the component supply area 233 and the first board A arranged at the mounting work position by a known head unit drive mechanism. The head unit 234 picks up components supplied to the component supply area 233 by the component supply unit 235, moves to the mounting work position, and mounts the components on the first board A. The head unit 234 is equipped with a plurality of shaft-shaped heads 237 that adsorb and hold the components when picking and release the held components when mounting. The heads 237 are capable of moving up and down relative to the head unit 234 and rotating around the shaft, and are driven by a head drive mechanism (not shown) that uses a motor as a drive source.

[0032] 1, the mounting inspection device 24 is disposed downstream of the component mounting device 23 and inspects the processing state of the component mounting process by the component mounting device 23. The board after inspection by the mounting inspection device 24 is carried into the reflow device 25. The reflow device 25 performs a reflow process in which the solder on the board is melted and then hardened. The board after this reflow process is carried into the reflow inspection device 26. The reflow inspection device 26 is disposed downstream of the reflow device 25 and inspects the processing state of the reflow process by the reflow device 25.

[0033] The mounting management device 27 is connected to each of the processing devices in the component mounting line 2 so as to be capable of communicating information with each other, and is a device that manages the operation of each processing device. The mounting management device 27 is, for example, a personal computer having a first storage unit 27a (see FIG. 4).

[0034] The first storage unit 27a stores mounting information related to the mounting process. The mounting information includes, for example, information on the target number of board devices 100, information on the types of boards required to produce the board devices 100, information on the required quantity for each type of board required to produce the target number of board devices 100, information on the production quantity that can be produced per unit time for each type of board, information on the time required for changing the setup of the component supply unit 235, and the like.

[0035] Note that the changeover refers to, when the type of board produced in the component mounting line 2 is changed, for example, from the first board A to the second board B, rearranging the component supply units 235 so that the arrangement is suitable for mounting the second board B. In other words, it refers to rearranging the component supply units 235 so that the takt time for producing a certain type of board is shortened.

[0036] Next, the configuration of the post-process line 3 will be described. The post-process line 3 is a production line for performing various processes on the boards that have passed through the component mounting line 2. The post-process line 3 has a dividing device (not shown), an electrical test device (not shown), a plurality of assembly devices 31, or a post-process management device 32. In this embodiment, the processes performed by the processing devices of the post-process line 3 are called post-processes. The post-processes can also be referred to as processes for completing the board device 100, which are started after part of the mounting process is completed.

[0037] The dividing device is a processing device that divides a substrate. When any one or more of the first substrate A to the third substrate C are substrates produced using a multiple substrate, the multiple substrate is divided by the dividing device.

[0038] The electrical testing device is a processing device that performs various electrical tests on the first substrate A to the third substrate C in order to check whether the first substrate A to the third substrate C operate normally.

[0039] The assembly device 31 is a processing device that uses the first substrate A to the third substrate C and other components to assemble the substrate device 100. Note that, although three robot arms are shown in Fig. 1 as an example of the assembly device 31, this is merely an example, and the configuration and number of the assembly device 31 can be appropriately selected.

[0040] The post-process control device 32 is connected to each of the processing devices in the post-process line 3 so as to be capable of communicating information with each other, and is a device that controls the operation of each processing device. The post-process control device 32 is, for example, a personal computer having a second storage unit 32a (see FIG. 4).

[0041] The second storage unit 32a stores post-process information related to the post-process. The post-process information includes, for example, information on the model, number, and arrangement of the processing devices arranged in the post-process line 3, information on the number of substrates that can be stored on the intermediate shelf 60 described later, information on the time required to complete the post-process, and the like.

[0042] [Configuration of production plan generation device 4] The production plan generating device 4 will be described with reference to FIG. 4. FIG. 4 is a block diagram showing the electrical configuration of the production plan generating device 4. The production plan generating device 4 is an information processing device including a CPU that performs various arithmetic processing and control processing, a non-volatile memory (not shown) such as a ROM in which a predetermined control program is stored, a RAM (not shown) for temporarily storing data, and peripheral circuits thereof. Specifically, the production plan generating device 4 according to this embodiment is a cloud server consisting of one or more computers, and is connected to the mounting management device 27 and the post-process management device 32 via a network NW so as to be able to communicate information. The production plan generating device 4 functionally includes an acquisition unit 41, a generation unit 42, a second judgment unit 43, and an output unit 44 by causing the CPU to execute a control program stored in the ROM or the like.

[0043] The acquisition unit 41 communicates with the mounting management device 27 and the post-process management device 32, and acquires the mounting information and the post-process information from the first storage unit 27a and the second storage unit 32a.

[0044] The generation unit 42 generates a production plan for producing the board device 100. The generation unit 42 functionally includes a master plan generation unit 421, a first determination unit 422, a lot division unit 423, a feasible quantity calculation unit 424, a mounting order adjustment unit 425, a placement plan generation unit 426, a required time calculation unit 427, a specification unit 428, and a post-process start priority plan generation unit 429.

[0045] The master schedule generating unit 421 generates a master schedule that prioritizes the efficient completion of the mounting process without considering the efficient completion of the post-process based on the mounting information and the post-process information. For example, the master schedule generating unit 421 according to this embodiment generates a master schedule as shown in FIG. 5(a). FIG. 5(a) is a diagram showing the master schedule in the form of a time chart. In the vertical axis of FIG. 5(a), the upper chart corresponds to the mounting process, the middle chart corresponds to the intermediate shelf standby process, and the lower chart corresponds to the post-process. In FIG. 5(a), the horizontal axis represents time divided into unit times. In FIG. 5(a), time progresses as one moves to the right. In FIG. 5(a), A is attached to the cell in which the process related to the first board A is being performed, B is attached to the cell in which the process related to the second board B is being performed, and C is attached to the cell in which the process related to the third board C is being performed. For example, the cell shown at X1 in FIG. 5(a) indicates that the process for producing the first board A is being performed. 5(a) indicate that the process for producing the second substrate B and the process for producing the third substrate C are performed in the mounting process. Hereinafter, the process for producing the first substrate A, the process for producing the second substrate B, and the process for producing the third substrate C in the mounting process may be referred to as the first mounting process, the second mounting process, and the third mounting process, respectively.

[0046] In FIG. 5(a), the black cells indicate that the component supply unit 235 is being re-arranged. Also, the connected cells indicate that a predetermined process continues for a predetermined unit time. For example, the cell indicated by X2 in FIG. 5(a) indicates that the first second mounting process continues from T6 to T7. That is, it indicates that the first lot for producing the second board B continues from T6 to T7. Similarly, the cell indicated by X4 indicates that the first production lot for producing the board device 100 in the post-process continues from T15 to T24.

[0047] As described above, the master plan is a plan that prioritizes the efficient completion of the mounting process without considering the efficient completion of the post-process. Therefore, the master plan generating unit 421 generates the master plan so that the mounting plan is completed as soon as possible. As shown in FIG. 5(a), in the master plan, the mounting process is performed in such a manner that the required quantity required to produce the target number of board devices 100 is sequentially mounted for each board type. That is, in the master plan, the mounting process is performed in such a manner that the first mounting process is performed intensively, the second mounting process is performed intensively, and then the third mounting process is performed intensively. In addition, in this master plan, as shown in X5 and X6 in FIG. 5(a), a changeover is performed every time the mounting process of each board is completed. Specifically, in X5 in FIG. 5(a), the component supply unit 235 is changed over so that the arrangement is suitable for the second mounting process. In addition, in X6 in FIG. 5(a), the component supply unit 235 is changed over so that the arrangement is suitable for the third mounting process. In this way, in the master plan according to this embodiment, the mounting process progresses by repeating the following: changeover to appropriate placement → completion of mounting the required quantity → changeover to appropriate placement.... This generates a master plan that completes the mounting process as quickly as possible.

[0048] The intermediate shelf standby process is a process of moving the various boards A to C produced in the mounting process to an intermediate shelf 60 capable of storing the various boards A to C and causing them to wait. For example, a board on which components for producing a first board A are mounted at timing T3 in Fig. 5(a) is temporarily stored on the intermediate shelf 60 at timing T4. Similarly, a board on which components for producing a second board B are mounted at timings T6 to T7 in Fig. 5(a) is temporarily stored on the intermediate shelf 60 at timing T8.

[0049] In the post-processing, various boards A to C stored on the intermediate shelf 60 are taken out and subjected to the above-mentioned dividing process by the dividing device, the electrical test process by the electrical test device, and the assembly process by the multiple assembly devices 31. As shown by X4 in FIG. 5(a), in the master plan, the post-processing starts when all board types necessary for producing the board device 100 are prepared. In other words, the post-processing starts when enough board types are prepared to start the post-processing. Hereinafter, the start time of the post-processing in the master plan may be referred to as the master post-processing start time. As shown by T34 in FIG. 5(a), the post-processing ends when the target number of board devices 100 are produced. Hereinafter, the time when the post-processing ends in the master plan may be referred to as the master post-processing end time.

[0050] The first determination unit 422 shown in FIG. 4 determines whether there is room left to adjust the mounting process in the master plan so that the post-process ends at a time earlier than the reference post-process end time. That is, the first determination unit 422 determines whether there is room to generate a plan in which the post-process starts at a time earlier than the reference post-process start time, that is, a post-process start priority plan. Specifically, the first determination unit 422 acquires information on the reference post-process start time, the number of production lots of the board device 100, the arrangement of the component supply unit 235, and the mounting order of various boards from the master plan. Then, by referring to these pieces of information, it determines whether there is room to generate a post-process start priority plan. If it is determined that there is room to generate a post-process start priority plan, the processes of the lot division unit 423 to the post-process start priority plan generation unit 429 shown in FIG. 4 are performed to generate a post-process start priority plan.

[0051] The lot dividing unit 423 refers to a production lot for producing the substrate device 100 in the post-process of the master plan, and divides the production lot into two or more post-process lots. Specifically, the lot dividing unit 423 sets two or more post-process lots in the post-process start priority plan so that the timing when the later-described executable quantities of various substrates A to C are ready and the timing when the production of the substrate device 100 in the post-process lot starts are close to each other.

[0052] The executable quantity calculation unit 424 calculates the executable quantity, which is the number of various boards required to execute one post-process lot. Here, for example, it is assumed that the executable quantity calculation unit 424 calculates that the executable quantity of various boards A to C can be obtained by performing the first mounting process for one unit time, the second mounting process for two unit times, and the third mounting process for three unit times in the mounting process.

[0053] The mounting order adjustment unit 425 adjusts the mounting order of the first board A to the third board C so that the post-process is completed earlier than the reference post-process end time. The mounting order adjustment unit 425 according to this embodiment adjusts the mounting order so that the end time of the post-process is the earliest possible. Specifically, the mounting order is rearranged in such an order that the feasible quantity of various boards A to C can be prepared as quickly as possible.

[0054] The placement plan generating unit 426 generates a placement plan for adjusting the placement of the component supply unit 235 so that the post-processing is completed at a time earlier than the reference post-processing end time. The placement plan generating unit 426 according to the present embodiment generates a placement plan that allows the implementation quantity of various boards A to C to be prepared as quickly as possible. As the placement plan, the placement plan generating unit 426 generates a placement plan that can be used in common for the mounting process of the first board A to the third board C. In other words, the placement plan generating unit 426 generates a placement plan in which a so-called common setup is performed. The common setup refers to a setup in a production form in which multiple types of component supply units 235 used for the mounting process of multiple types of boards are placed in the component supply area 233 in advance, and only the component supply units 235 corresponding to the type of board to be actually produced are selectively operated. When the common setup is performed, it is not necessary to perform a setup change every time the type of board is changed. This reduces the time consumed for the setup change, and therefore the time required to prepare the implementation quantity of various boards A to C can be shortened.

[0055] The required time calculation unit 427 calculates the required time required to prepare the feasible quantity of various boards based on the mounting order adjusted by the mounting order adjustment unit 425 and the placement plan generated by the placement plan generation unit 426.

[0056] The identifying unit 428 identifies the earliest time at which the earliest post-processing lot can be started, that is, the earliest time at which the post-processing can be started, based on the required time. Here, for example, the timing of T10 is assumed to be the post-processing possible start time.

[0057] A post-process start priority plan generating unit 429 generates a post-process start priority plan based on the number of post-process lots set by the lot dividing unit 423, the mounting order adjusted by the mounting order adjusting unit 425, the placement plan generated by the placement plan generating unit 426, and the post-process start possible time identified by the identifying unit 428.

[0058] For example, the post-process start priority plan generating unit 429 generates a post-process start priority plan as shown in Fig. 5(b). Fig. 5(b) is a time chart showing an example of a post-process start priority plan. As in Fig. 5(a), in Fig. 5(b), A is attached to a cell in which processing related to the first substrate A is being performed, B is attached to a cell in which processing related to the second substrate B is being performed, and C is attached to a cell in which processing related to the third substrate C is being performed. Note that the configurations of the vertical and horizontal axes in Fig. 5(b) are the same as those of the vertical and horizontal axes in Fig. 5(a), and therefore description thereof will be omitted.

[0059] In the post-process start priority plan, the lot division unit 423 divides the production lot for producing the substrate device 100 into three post-process lots Y1 to Y3 so that the timing when the possible number of various substrates A to C are ready and the timing when the post-process lot starts are close to each other. In other words, in this embodiment, the lot division is performed so that the time during which the mounting process and the post-process proceed simultaneously in parallel is secured longer than that in the standard plan. Specifically, in the post-process start priority plan according to this embodiment, the production of the substrate device 100 group belonging to the earliest post-process lot Y1 starts at the timing (timing T10) when the possible number of various substrates A to C are ready in the mounting process. Then, until the earliest post-process lot Y1 is completed, that is, between T10 and T17, the mounting process proceeds simultaneously in parallel with the earliest post-process lot Y1 to prepare the possible number of various substrates A to C. Then, at the timing when the first post-processing lot Y1 is finished (timing T17), production of the group of substrate devices 100 belonging to the next post-processing lot Y2 starts. The same procedure is followed for the post-processing lots Y2 and Y3. With this configuration, the mounting process and the post-processing are carried out simultaneously in parallel, so that it is possible to prevent waiting time from occurring in either the mounting process or the post-processing.

[0060] In the post-process start priority schedule according to this embodiment, the mounting order is rearranged so that the possible quantities of various boards A to C are prepared as quickly as possible. Specifically, the mounting order is rearranged in the following order: execute the first mounting process for one unit time (T3), execute the second mounting process for two unit times (T4-T5), execute the third mounting process for three unit times (T6-T8), execute the first mounting process for one unit time (T9), and so on.

[0061] In the post-process start priority plan according to this embodiment, the component supply units 235 are placed according to the placement plan that can assemble the feasible quantities of various boards A to C as quickly as possible, which is generated by the placement plan generating unit 426. Specifically, the placement of the component supply units 235 is made into a common setup so that time (black cells) required for setup changeover that occurs in the mounting process in the master plan does not occur.

[0062] Furthermore, in the post-process start priority schedule according to this embodiment, the post-process starts at the post-process start possible time (timing T10), which is the time when the post-process can be started earliest.

[0063] With the above configuration, in the post-process start priority plan according to this embodiment, the post-process starts earlier than the reference post-process start time and ends earlier than the reference post-process end time. In other words, a production plan is generated that can produce the target number of board devices 100 in a shorter time than the standard plan.

[0064] In addition, when the arrangement of the component supply unit 235 is commonized, the possible number of various boards A to C can be prepared efficiently, but the number of boards A to C produced per unit time decreases. Therefore, as shown in Figs. 5(a) and (b), the mounting process of the standard plan can prepare the required number of first boards A in two unit times, but the mounting process of the post-process start priority plan requires three unit times to prepare the required number of first boards A. Similarly, the time required to prepare the required number of second boards B and third boards C is increased in the post-process start priority plan compared to the standard plan. Therefore, as shown in Figs. 5(a) and (b), the time required to complete the mounting process is longer in the post-process start priority plan compared to the standard plan. However, even if the time required to complete the mounting process is longer, if the timing of the end of the post-process is advanced, it can be said that an efficient production plan has been generated.

[0065] The second determination unit 43 shown in Fig. 4 refers to the reference plan and the post-process start priority plan, and determines whether the lead time from the start of the mounting process to the end of the post-process start priority plan has improved compared to the reference plan. Specifically, the second determination unit 43 compares the lead time L1 (see Fig. 5(a)) in the reference plan with the lead time L2 (see Fig. 5(b)) in the post-process start priority plan, and determines whether the lead time L2 is shorter than the lead time L1. In this embodiment, as shown in Figs. 5(a) and 5(b), the lead time L2 is shorter than the lead time L1, so the second determination unit 43 determines that the lead time has improved.

[0066] The output unit 44 outputs a production plan by referring to the judgment result by the second judgment unit 43. When the second judgment unit 43 judges that the lead time has been improved, the output unit 44 outputs the subsequent process start priority plan as the production plan. On the other hand, when the second judgment unit 43 judges that the lead time has not been improved, the output unit 44 outputs the standard plan as the production plan. That is, when the subsequent process start priority plan generating unit 429 generates a subsequent process start priority plan in which the subsequent process ends at a time earlier than the subsequent process end time in the standard plan, the output unit 44 outputs the subsequent process start priority plan as the production plan. When the subsequent process start priority plan generating unit 429 cannot generate a subsequent process start priority plan in which the subsequent process ends at a time earlier than the subsequent process end time in the standard plan, the output unit 44 outputs the standard plan as the production plan.

[0067] In this embodiment, since the second determination unit 43 has determined that the lead time has been improved, the output unit 44 outputs the post-process start priority plan as the production plan. The output unit 44 outputs the production plan to, for example, the display unit 5 (see FIG. 4). The display unit 5 is a monitor connected to the production plan generating device 4, or the like.

[0068] The case where the subsequent process start priority plan generating unit 429 cannot generate a subsequent process start priority plan in which the subsequent process ends at a time earlier than the subsequent process end time in the master plan is, for example, a case as shown in FIG.

[0069] FIG. 6(a) is a time chart showing another example of the master plan, and FIG. 6(b) is a time chart showing another example of the post-process start priority plan. Depending on the content of the processing performed in the post-process, as shown in FIGS. 6(a) and 6(b), it is possible that the time required for the post-process is short and the post-process is completed immediately. In this case, as shown in L11 in FIG. 6(a) and L12 in FIG. 6(b), the master plan that prioritizes efficient completion of the mounting process has a shorter lead time. Therefore, in such a case, the output unit 44 outputs the master plan as the production plan.

[0070] As described above, the production plan generation system 10 according to the present embodiment does not simply generate a post-process start priority plan and output the post-process start priority plan as a production plan as is, but refers to the final lead time and then determines the plan to be output as the production plan. With this configuration, a production plan that enables efficient production of the substrate device 100 can be more reliably provided to the user of the production plan generation system 10.

[0071] [Processing flow] The process flow of the production plan generating device 4 configured as described above will be described with reference to the flowchart of FIG.

[0072] In step S1, the acquisition unit 41 acquires mounting information and post-process information.

[0073] In step S2, the master plan generating unit 421 generates a master plan based on the mounting information and the post-process information.

[0074] In step S3, the first determination unit 422 acquires information related to the master schedule. Then, in step S4, the first determination unit 422 determines whether there is room to generate a post-process start priority schedule that takes into account the post-process. If there is room to generate a post-process start priority schedule (Yes in step S4), the process proceeds to step S5. If there is no room to generate a post-process start priority schedule (No in step S4), the process proceeds to step S14.

[0075] In step S5, the lot division unit 423 divides the production lot in the master plan into two or more post-process lots. At this time, the lot division unit 423 sets the post-process lots so that the timing when the executable quantity of substrates is ready and the timing when the post-process lot starts are close to each other.

[0076] In step S6, the possible quantity calculation unit 424 calculates the possible quantity.

[0077] In step S7, the mounting order adjustment unit 425 adjusts the mounting order so that the post-process is completed at a time earlier than the reference post-process end time.

[0078] In step S8, the placement plan generating unit 426 generates a placement plan for adjusting the placement of the component supply unit 235 so that the post-process is completed at a time earlier than the reference post-process completion time.

[0079] In step S9, the required time calculation unit 427 calculates the required time required to prepare the feasible quantities of various boards A to C based on the mounting order adjusted by the mounting order adjustment unit 425 and the placement plan generated by the placement plan generation unit 426.

[0080] In step S10, the specifying unit 428 specifies a post-process start possible time, which is the time at which the post-process can be started earliest, based on the required time.

[0081] In step S11, the post-process start priority plan generating unit 429 generates a post-process start priority plan based on various information identified by the processes in steps S5 to S9.

[0082] In step S12, the second judgment unit 43 judges whether the lead time has improved by referring to the lead time L1 in the master schedule and the lead time L2 in the post-process start priority schedule. If the lead time has improved (Yes in step S12), the process proceeds to step S13. If the lead time has not improved (No in step S12), the process proceeds to step S14.

[0083] In step S13, the output unit 44 outputs the post-process start priority plan as a production plan.

[0084] In step S14, the output unit 44 outputs the master plan as a production plan.

[0085] As described above, according to the production plan generating system 10 of this embodiment, a post-process start priority plan, which is a production plan that takes the post-process into consideration, is generated. Specifically, in this embodiment, a master plan is generated based on the mounting information and the post-process information acquired by the acquisition unit 41, and a post-process start priority plan is generated based on the master plan. This post-process start priority plan is a plan in which the mounting process is adjusted so that the post-process can be started at a time earlier than the post-process start time of the master plan in order to end the post-process earlier than the post-process end time of the master plan. In other words, it is a plan adjusted so that the production of the board device 100 can be completed earlier than the master plan. Therefore, according to the production plan generating system 10 of this embodiment, a production plan that can efficiently produce the board device 100 can be generated.

[0086] [Description of Modified Embodiments] Although the embodiment of the present invention has been described above, the present invention is not limited to this, and the following modified embodiments are possible.

[0087] (1) The generating unit may generate another plan in addition to the standard plan and the subsequent-process start priority plan. For example, the generating unit may generate a balanced plan as shown in FIG. 8(b). Note that the standard plan shown in FIG. 8(a) and the subsequent-process start priority plan shown in FIG. 8(c) are similar to those shown in FIG. 6(a) and (b), and therefore a description thereof will be omitted.

[0088] The balanced plan is a plan that shortens the time required for each mounting process by adjusting the mounting order so that the feasible quantities of various boards A to C are prepared early and changing the setup each time each mounting process is completed. In other words, the balanced plan is a plan that adopts the same mounting order as the post-process start priority plan and progresses the mounting process in a manner in which a change in setup is made each time the type of board changes, as in the standard plan. In this modified embodiment, the second judgment unit 43 compares the length of the lead time L21 in the standard plan, the length of the lead time L22 in the balanced plan, and the length of the lead time L23 in the post-process start priority plan. Then, the output unit 44 outputs the plan with the shortest lead time from these plans as the production plan.

[0089] (2) The master plan does not necessarily have to be generated by the master plan generating unit 421. For example, information related to the master plan may be stored in advance in a memory or the like of the production plan generating device 4. In this case, the generating unit does not need to include the master plan generating unit 421. [Explanation of symbols]

[0090] 1: Production system 2: Component mounting line 3: Post-processing line 4: Production plan generation device 10: Production planning system 41: Acquisition section 42 :Generation part 100: Substrate device 233: Parts supply area 235: Parts supply unit A: First board B: Second board C: Third board

Claims

1. A production plan generation system for generating a production plan for producing two or more target numbers of substrate devices having multiple types of substrates as components, comprising: an acquisition unit that acquires mounting information of a mounting process for mounting electronic components on the multiple types of boards and post-process information of a post-process that is started after a part of the mounting process is completed; A generation unit that generates the production plan, The generation unit is performing the mounting process in such a manner that a required quantity necessary for producing a target number of the substrate devices is sequentially mounted for each substrate type, and acquiring, from the mounting information and the substrate information, a post-process start time in a master plan for starting the post-process when all substrate types are ready; a production plan generation system that generates, as the production plan, a subsequent process start priority plan that makes the end time of the subsequent process earlier than the end time of the subsequent process in the master plan by adjusting the mounting process so that the subsequent process can be started at a time earlier than the start time of the subsequent process in the master plan.

2. An output unit that outputs the production plan, 2. The production plan generation system according to claim 1, wherein the output unit outputs the basic plan as the production plan when the generation unit cannot generate a subsequent process start prioritized plan in which the end time of the subsequent process is earlier than the end time of the subsequent process in the basic plan.

3. the plurality of types of substrates include at least a first substrate and a second substrate different from the first substrate, the generation unit includes a placement plan generation unit that generates a placement plan of a component supply unit for supplying the electronic components to be mounted on the first board and the second board in the mounting process, 3 . The production plan generating system according to claim 1 , wherein the placement plan generating unit generates the placement plan that can be shared for mounting the first board and the second board in the post-process start priority plan.

4. the generating unit has a lot dividing unit that divides a production lot of the substrate device in the post-process into two or more post-process lots, 3. The production plan generating system according to claim 1, wherein the lot dividing unit sets the two or more post-processing lots in the post-processing start priority plan so that a timing when a possible quantity of the multiple types of substrates that can be used to carry out one of the post-processing lots is ready and a timing when the post-processing lot starts are close to each other.

5. The generation unit is a required time calculation unit that calculates a required time required to prepare the feasible quantity of the plurality of types of boards in the mounting process based on the mounting information; 5. The production plan generating system according to claim 4, further comprising: a specification unit that specifies a post-processing start time that is the earliest time at which a first post-processing lot among the two or more post-processing lots can be started based on the required time.

6. the plurality of types of substrates include at least a first substrate and a second substrate that is a different type from the first substrate; 3. The production plan generating system according to claim 1, wherein the generation unit includes a mounting order adjustment unit that adjusts a mounting order in which the first board and the second board are mounted so that a finish time of the post-process is the earliest.

Citation Information

Patent Citations

  • Production control method

    JP2008028262A

  • Production schedule planning method

    JP2011013880A

  • Management device, mounted board manufacturing system, and production order determination method

    JP2020038857A

  • Production plan creating method, production plan creating device and production method

    JP2020098509A