Construction management method

The construction management method addresses water content ratio management in roadbeds by measuring and adjusting it at key stages, ensuring optimal water content for efficient construction and improved soil permeability.

JP2024157286APending Publication Date: 2024-11-07CIMA CONSULTANT +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
JP2023071562
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-25
Publication Date
2024-11-07

AI Technical Summary

Technical Problem

Existing construction management methods for roadbeds and roadbeds do not effectively manage the water content ratio, leading to issues such as non-conforming products, destruction of aggregate structure, and inefficient construction processes.

Method used

A construction management method that includes measuring and adjusting the water content ratio of raw material soil at various stages, using a polymer compound for agglomeration, and employing a mixture of cement-based and magnesium-based solidifying agents to maintain the water content within predetermined ranges.

Benefits of technology

The method ensures the water content ratio is managed within optimal limits, preventing issues related to high or low water content, thereby enhancing construction efficiency and improving air and water permeability of the soil.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024157286000001_ABST
    Figure 2024157286000001_ABST
Patent Text Reader

Abstract

To provide a construction management method for a roadbed and a subgrade capable of appropriately managing a water content ratio.SOLUTION: A construction management method, at the time of a field test, comprises the steps of: measuring the water content of a raw material soil before improvement and adjusting the water content of the raw material soil before improvement to be within a predetermined range (step S211); measuring the water content of the raw material soil after improvement and adjusting the water content of the raw material soil after improvement to be within a predetermined range (step S213); measuring the water content of the raw material soil under curing after improvement and adjusting the water content of the raw material soil under curing to be within a predetermined range (step S214); and measuring the water content of the raw material soil after curing and adjusting the water content of the raw material soil after curing to be within a predetermined range (step S215).SELECTED DRAWING: Figure 3
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a construction management method for roadbeds and subgrades constructed on grounds, squares, parks, etc. [Background technology]

[0002] There are various types of roadbeds and subgrades that are constructed on site, such as on grounds. If the soil quality of the site is poor, soil conditioners are mixed into the soil on site to improve compaction. Examples of such soil improvement techniques are described in Patent Documents 1 and 2.

[0003] Patent Document 1 describes a soil improvement technique aimed at improving the air permeability, water permeability, and water retention of soil. Specifically, the patent describes a soil improvement method including a step of spraying an aqueous solution containing a polymeric compound having an aggregate forming effect on soil and stirring the soil, and a step of spreading and compacting the soil.

[0004] According to this soil improvement method, when an aqueous solution containing a polymer compound comes into contact with soil, the soil particles are bound together through the agglomeration process to form a three-dimensional network structure, and over time, the binding and connection progresses further to form porous coarse particles with small and large gaps. Finally, these coarse particles form a solidified structure, which improves the air permeability, water permeability, and water retention of the soil.

[0005] On the other hand, Patent Document 2 describes a construction management method for roadbeds and subgrades in which the relationship between the curing period and strength when a soil conditioner is mixed with a specific soil is determined by laboratory testing, and based on the test results, the relationship between the strength after a standard curing period and the strength after a desired shortened curing period is determined, and from this relationship, a strength β for the shortened period at which the strength after the standard curing period becomes the design standard strength α is obtained, and if the strength after the shortened period at the site is greater than the above strength β, it can be considered that the standard strength is met.

[0006] The purpose of this roadbed and subgrade construction management method is to accurately estimate whether or not a hardness conforming to the JIS standard will be achieved in a short period of time without curing for the specified period of time specified by the JIS when a hardening agent is mixed into the roadbed or subgrade material to achieve a hardness conforming to the JIS standard. [Prior art documents] [Patent documents]

[0007] [Patent Document 1] JP 2013-100638 A [Patent Document 2] Japanese Patent Application Publication No. 62-228513 Summary of the Invention [Problem to be solved by the invention]

[0008] However, while there is a demand for soil improvement techniques such as the invention described in Patent Document 1, there is also a demand for construction management methods that can realize more efficient construction, such as the invention described in Patent Document 2.

[0009] For example, moisture content is an important control item for roadbed and subgrade construction management methods. For example, during on-site testing, if the soil used for improvement is high in moisture content, the product may not be suitable. Also, when compacting the soil during construction, if the moisture content is high, the aggregate structure may be destroyed, and conversely, if the moisture content is low, watering using a water-adding device is required.

[0010] Therefore, an object of the present invention is to provide a construction management method for a roadbed and subgrade that can appropriately manage the moisture content. [Means for solving the problem]

[0011] The construction management method of the present invention includes, during on-site testing, the steps of measuring the moisture content of the raw soil before improvement and adjusting the moisture content of the raw soil before improvement so that it is within a predetermined range, measuring the moisture content of the raw soil after improvement and adjusting the moisture content of the raw soil after improvement so that it is within a predetermined range, measuring the moisture content of the raw soil after improvement and curing so that it is within the predetermined range, and measuring the moisture content of the raw soil after curing and adjusting the moisture content of the raw soil after curing so that it is within the predetermined range.

[0012] This allows the moisture content of the raw soil to be controlled within a specified range through measurement and adjustment at each process.

[0013] Furthermore, it is preferable that the construction management method includes, during construction, a step of measuring the moisture content of the material before paving and adjusting the moisture content of the material before paving so that it is within a predetermined range, and a step of measuring the moisture content of the material after paving and before compaction and adjusting the moisture content of the material before compaction so that it is within a predetermined range.

[0014] It is preferable that the predetermined ranges in each of these steps are determined based on the optimum moisture content of the raw soil.

[0015] The construction management method preferably includes a step of spraying and stirring an aqueous solution containing a polymer compound having an aggregate forming action when improving the raw soil during the on-site test.

[0016] It is particularly preferable to use a material obtained by mixing raw soil with at least one of the group consisting of a cement-based solidification material, a neutral solidification material, and a magnesium-based solidification material, and an aggregate forming agent.

[0017] Specifically, it is preferable to use, as the agglomerating agent, a polymer compound consisting of a complex of a magnesium salt of acrylic acid / dimethylaminoethyl methacrylate copolymer and polyethyleneimine. Effect of the Invention

[0018] With such a configuration, the construction management method of the present invention manages the moisture content of the raw soil at each process by measurement and adjustment so that it falls within a predetermined range, thereby making it possible to prevent problems that arise when the moisture content is outside the predetermined range (the moisture content is too high or too low), such as in the examples described above and below. [Brief description of the drawings]

[0019] [Figure 1] FIG. 1 is a schematic flow diagram showing a construction management method according to an embodiment of the present invention. [Diagram 2] FIG. 1 is a schematic flow diagram showing a construction management method according to an embodiment of the present invention. [Diagram 3] FIG. 1 is a schematic flow diagram showing a construction management method according to an embodiment of the present invention. [Figure 4] FIG. 1 is a schematic flow diagram showing a construction management method according to an embodiment of the present invention. [Diagram 5] FIG. 1 is a schematic flow diagram showing a construction management method according to an embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0020] The following describes an embodiment of the present invention in detail. However, the description of the components described below is an example (representative example) of an embodiment of the present invention, and the present invention is not limited to the following content as long as it does not deviate from the gist of the present invention.

[0021] [Construction management method] As shown in Fig. 1, the construction management method according to the embodiment of the present invention includes indoor testing (step S100), on-site testing (step S200), construction (step S300), and final inspection (step S400). The construction management method of the present invention relates to a construction management method for roadbeds and subgrades constructed on-site such as grounds, and in short, manages the process of conducting indoor and on-site tests when improving and curing raw soil, carrying out construction using the improved and cured materials, and finally carrying out a final inspection. The raw soil is soil or crushed stone, for example, crushed stone C-40 (crusher run) for roads.

[0022] Here, Figure 2 is a schematic flow diagram showing the steps performed during indoor testing, Figure 3 is a schematic flow diagram showing the steps performed during on-site testing, Figure 4 is a schematic flow diagram showing the steps performed during construction, and Figure 5 is a schematic flow diagram showing the steps performed during completion inspection. Hereinafter, a construction management method according to an embodiment of the present invention will be described with reference to the drawings.

[0023] [Laboratory testing] As shown in Fig. 2, in a laboratory test, a soil test is conducted on the parent material (raw soil) (step S101). Specifically, the grain size, density, degree of aggregates, etc. of the parent material are measured. In addition, in the laboratory test, a compaction test (a test of compacting the soil by compaction) is conducted to determine the optimal water content of the parent material (raw soil).

[0024] The optimum water content can be determined by the compaction test using, for example, the method described in the following reference. (References) General Building Research Corporation of Japan "Soil compaction test by ramming" https: / / www.gbrc.or.jp / assets / test_series / documents / so_09.pdf

[0025] The optimum moisture content of the base material (raw soil) obtained here can be used as a reference for the later on-site test or construction as a desirable moisture content. The specific procedure will be explained in the examples below. The desired range of moisture content (hereinafter also referred to as the "predetermined range") can be set appropriately depending on the type of raw soil, the process in which the moisture content is measured, the temperature, humidity, weather, and other regulations when the moisture content is measured, etc. For example, if raw soil with a high moisture content is used for improvement and production, it will be deemed a non-conforming product according to the regulations, so a value lower than the moisture content that would result in a non-conforming product is set as the maximum value.

[0026] [Field Test] (1. Machine Calibration Test) Next, as shown in Fig. 3, during the on-site test, a calibration test of the machine is performed (step S201). Specifically, a raw soil test (raw soil discharge test), a solidification material test (solidification material discharge test), a liquid test (liquid discharge test), etc. are performed.

[0027] Raw soil tests and solidification material tests are also called machine (self-propelled soil improvement machine) discharge tests, and involve comparing the volume of raw soil (e.g., crushed stone) and the weight of solidification material (e.g., cement) set by the machine with the actually measured values ​​to determine a correction coefficient and correct (calibrate) the machine error.

[0028] The liquid test, also known as the water adding device discharge test, involves connecting a water adding device to a machine (self-propelled soil improvement machine) and comparing the amount of water displayed on the machine's control panel with the amount of water actually coming out to determine a correction value and correct any machine errors.

[0029] In addition, the water content increase rate measurement test measures the water content of the crushed stone before mixing, and then after cement is added and mixed with the cement, in order to grasp the water reduction situation and to determine the target amount of water to be added in the water adding device.

[0030] Also, the amount of cement to be added in the mix design is the value for the compacted state, but the self-propelled soil improvement machine manages the loosened soil. Therefore, the volume change rate is confirmed by compacting the material in a loosened state (volume change rate test), and the amount of cement to be added by the self-propelled soil improvement machine is determined.

[0031] The test mixing is carried out to understand the mixing performance and mechanical characteristics of the inspected self-propelled soil improvement machine, as well as to determine the mixing conditions from the properties of the mixture produced based on the designated mix proportions.

[0032] (2. Water content measurement) As shown in FIG. 3, during the field test, the raw soil is improved (step S212) and cured (step S214), and the water content of the raw soil is measured at each timing. The moisture content is measured by an operator using a known measuring device, such as the "Simplified RI Moisture Meter WARP-mini (NETIS Registration Number: KK-210067-A)" manufactured by Soil and Rock Engineering Co., Ltd.

[0033] Specifically, first, the moisture content of the raw soil before improvement is measured (step S211). If the measured moisture content of the raw soil before improvement is outside a predetermined range, the moisture content of the raw soil before improvement is adjusted so that it falls within the predetermined range. The adjustment may be performed, for example, by spraying water using a water adding device when the moisture content is lower than a predetermined range, or by leaving the material until the moisture is removed and the moisture content falls within the predetermined range when the moisture content is higher than the predetermined range. Other known techniques may be used to adjust the moisture content in this manner. Of course, if the measured moisture content of the raw soil before improvement is within a specified range, there is no need to adjust it.

[0034] Similarly, the moisture content of the improved raw soil is also measured (step S213). If the measured moisture content of the improved raw soil is outside the predetermined range, the moisture content of the improved raw soil is adjusted so that it falls within the predetermined range.

[0035] Furthermore, the moisture content of the improved raw soil being cured is also measured (step S214). If the measured moisture content of the raw soil being cured is outside the predetermined range, the moisture content of the raw soil being cured is adjusted so that it falls within the predetermined range.

[0036] The timing of measuring the water content during curing can be set appropriately. For example, if the curing period is 3 days, the water content may be measured halfway through (after 36 hours), or the measurement may be performed multiple times.

[0037] In addition, the moisture content of the cured raw soil is also measured (step S215). If the measured moisture content of the cured raw soil is outside the predetermined range, the moisture content of the cured raw soil is adjusted so that it falls within the predetermined range.

[0038] As described above, the measurement of moisture content and the adjustment of moisture content in the field test have been explained, but the timing of this measurement and adjustment can be changed as appropriate. For example, the measurement and adjustment at some times (measurement and adjustment during curing) can be omitted. In addition, the moisture content measured by the worker at each timing is stored in the storage means of a management terminal such as a PC, tablet, smartphone, etc. Such information is collected and stored in the management terminal, and is centrally managed (visualized and shared) using a spreadsheet software or the like.

[0039] In this way, the construction management method of the present invention is a construction management method for roadbeds and subgrades that can appropriately manage the moisture content, and is therefore a construction management method that can achieve more efficient construction than conventional methods. For example, if the material is applied to a school playground, puddles will easily form on the ground if the permeability is too low. Conversely, if the permeability is too high, the ground will dry out and it will be difficult to exercise on. According to the construction management method of the present invention, the water content is appropriately managed to be within a predetermined range through measurement and adjustment, so that such problems do not occur.

[0040] In the field test, when improving the raw soil (step S212), it is preferable to include a step of spraying and stirring an aqueous solution containing a polymeric compound having an aggregate forming effect. For example, GB-2000 manufactured by Global Research Institute, Ltd. can be used as the aqueous solution containing the polymeric compound.

[0041] As a result, when the aqueous solution containing the polymer compound comes into contact with the raw soil, the raw soil particles are bound together by the agglomeration action to form a three-dimensional network structure. Also, after paving (step S303) and rolling (step S305) are performed during construction, the binding and connection progresses over time, forming porous coarse particles with large and small gaps, and finally these coarse particles become solidified into a structure, which can improve the air permeability, water permeability and water retention of the soil (raw soil, material).

[0042] In particular, the construction management method of the present invention is extremely effective in methods such as the ATTAC method, which is being researched by the All Japan Tohsu Technical Association in Civil Engineering, in which water is poured into large gaps in the granular structure and retained in small gaps, where management of the moisture content is important.

[0043] [Construction]

[0044] Then, as shown in Fig. 4, during construction, material preparation (step S301), paving (step S303), rolling (step S305), unevenness leveling (step S306), etc. are performed. During construction, the moisture content of the material is also measured at each timing.

[0045] Specifically, before paving, the moisture content of the material is measured (step S302). If the measured moisture content of the material before paving is outside a predetermined range, the moisture content of the material before paving is adjusted so that it falls within the predetermined range.

[0046] Furthermore, before compaction, the moisture content of the material is measured (step S304). If the measured moisture content of the material before compaction is outside a predetermined range, the moisture content of the material before compaction is adjusted so that it falls within the predetermined range.

[0047] If compaction is performed when the moisture content is high, the granular structure may be destroyed (voids may be crushed); conversely, if the moisture content is low, watering using a water adding device will be necessary. According to the construction management method of the present invention, the water content is appropriately managed to be within a predetermined range through measurement and adjustment, so that such problems do not occur.

[0048] [Completion inspection] Finally, as shown in FIG. 5, at the time of the completion inspection, a Proctor penetration test, a permeability test, etc. are performed as a completion test (step S401).

[0049] (Example) Below, we will explain examples of the optimum moisture content of the base material (raw soil) and the desirable moisture content for each process. However, since field tests (outdoors) are affected by weather (rain, cloudy), temperature, and humidity, the percentages shown below are expressed as single digits and include one decimal place for convenience, but appropriate values ​​can be set according to the site.

[0050] In this embodiment, the raw soil is assumed to be "decomposed granite soil" and the optimum moisture content is assumed to be "XX%." The optimum moisture content is obtained from the test result report submitted by the producer when purchasing the raw soil, or by carrying out the above-mentioned compaction test.

[0051] First, the moisture content of the unimproved granite soil is measured (Step S211). The moisture content suitable for work is AA% to BB%. If the optimum moisture content is XX%, then if the measured moisture content of the raw soil (sand) exceeds BB%, production is not possible. This is because the ATTAC method requires a water addition process to create the aggregate structure.

[0052] At this time, the amount of water to be added is calculated from a formula established from the results of the water content increase rate measurement test (step S201).

[0053] Next, the moisture content of the improved granite soil is measured (step S213). The target (desirable) moisture content is CC% to DD%.

[0054] Then, the moisture content of the curing sand is measured (step S214). The target (desirable) moisture content is a value that is EE% to FF% less than the optimum moisture content of XX%.

[0055] Furthermore, the moisture content of the cured granite soil is measured (step S215). The target (desirable) moisture content is GG% to HH%, but even if it is less than GG%, it can be adjusted to within the specified range (GG% to HH%) by spraying water in the subsequent process.

[0056] The moisture content of the material before paving and the material before compaction is measured (steps S302, S304), and the target (desirable) moisture content at this time is GG% to HH%, the same as after curing.

[0057] Although the embodiment of the present invention has been described above, the described embodiment is merely an example, and the present invention is not limited to the contents thereof as long as it does not deviate from the gist of the present invention. For example, the flow (order) of the schematic flow diagrams showing the construction management methods according to the embodiments of the present invention shown in Figures 1 to 5 can be changed or carried out in parallel without departing from the spirit of the invention. [Industrial Applicability]

[0058] The present invention is a construction management method for roadbeds and subgrades that can achieve more efficient construction than conventional methods by properly managing the moisture content, and is industrially useful because it can be widely used for construction in various sites such as grounds, plazas, and parks.

Claims

1. During the on-site test, A step of measuring the moisture content of the raw soil before improvement and adjusting the moisture content of the raw soil before improvement so that the moisture content is within a predetermined range; A step of measuring the moisture content of the improved raw soil and adjusting the moisture content of the improved raw soil so that the moisture content is within a predetermined range; A step of measuring the moisture content of the improved raw soil during curing and adjusting the moisture content of the raw soil during curing so that it is within a predetermined range; and a step of measuring the moisture content of the raw soil after curing, and adjusting the moisture content of the raw soil after curing so that it is within a predetermined range.

2. During the on-site test, 2. The construction management method according to claim 1, further comprising the step of spraying and stirring an aqueous solution containing a polymeric compound having an aggregate forming effect when improving the raw soil.

3. The construction management method according to claim 2, wherein a material is used that is a mixture of the raw soil, at least one selected from the group consisting of a cement-based solidification material, a neutral solidification material, and a magnesium-based solidification material, and a granulation agent.

4. 4. The construction management method according to claim 3, wherein the granulating agent is a polymer compound consisting of a complex of a magnesium salt of an acrylic acid / dimethylaminoethyl methacrylate copolymer and polyethyleneimine.

5. During construction, A step of measuring the moisture content of the material before paving and adjusting the moisture content of the material before paving so that the moisture content is within a predetermined range; 2. The construction management method according to claim 1, further comprising the steps of: measuring the moisture content of the paved material before compaction; and adjusting the moisture content of the material before compaction so that it falls within a predetermined range.

6. The construction management method according to any one of claims 1 to 5, wherein the predetermined range in each step is determined based on an optimal water content of the raw soil.