Elevator lifting machine and elevator shaft structure

The elevator hoisting machine with telescoping legs and non-interfering rail system addresses the challenge of installing temporary elevators without obstructing construction, enabling efficient use of space for both temporary and permanent elevators, thus enhancing construction efficiency.

JP2024157825APending Publication Date: 2024-11-08SHIMIZU CORP
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023072422
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-26
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

Conventional temporary elevators installed in open spaces interfere with construction work and require complex mechanisms for installation, leading to inefficiencies and wide-ranging impact on construction areas, especially in high-rise buildings.

Method used

An elevator hoisting machine with telescoping legs that can be installed between structural parts around an opening space, allowing easy installation and adjustment, and a rail system that avoids interference with the hoisting machine, enabling construction to proceed without obstructing surrounding work.

Benefits of technology

The solution allows for efficient installation and repositioning of the elevator hoisting machine during construction, minimizing interference with construction activities and facilitating the use of the same space for both temporary and permanent elevators, thereby improving construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024157825000001_ABST
    Figure 2024157825000001_ABST
Patent Text Reader

Abstract

To provide an elevator lifting machine and an elevator shaft structure that can be easily installed in an opening space for an elevator arrangement and that are less likely to become a construction obstacle in a surrounding construction work and can improve a construction efficiency.SOLUTION: An elevator lifting machine 10 is arranged in an opening space 12 for an elevator installation formed in a structure, and suspends and supports a carrier so that it can be driven up and down. The elevator lifting machine comprises a hoist 21 to support a wire rope 14 connected to the carrier so that it can be hoisted and a frame part 20 to support the hoist. The frame part has telescopic legs 27 that can be expanded and contracted in a plan view. The frame part can be constructed on a surrounding structure 11 in the opening space in the extended state of the telescopic legs and the outer shape in a plan view becomes smaller than the opening space in the contracted state of the telescopic legs.SELECTED DRAWING: Figure 4
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an elevator lifting machine and an elevator shaft structure. [Background technology]

[0002] In recent years, when constructing a high-rise building, a temporary elevator is sometimes installed in an opening space provided across multiple floors of the structure. For example, in the lifting device described in the following Patent Document 1, a temporary lift and a temporary elevator are arranged vertically in an opening space extending vertically across multiple floors. The temporary elevator is installed between the first floor of the structure and the floor where the framework construction is completed, and the elevator hoist is configured by mounting a top sheave and a drive unit on a lotus pedestal arranged at a corresponding position of the elevator mast. In addition, a wire for hoisting the carrier and the weight is supported by the elevator hoist so that it can be hoisted up. A technology is disclosed in which, as the construction work progresses, the elevator mast is extended upward and the elevator hoist is moved to the top of the elevator mast to expand the temporary elevator area upward. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2007-284179 A Summary of the Invention [Problem to be solved by the invention]

[0004] However, most of the conventional temporary elevators installed in the opening space were fixed in the opening space for the temporary elevator or the opening space for the permanent elevator. Therefore, the construction around the opening of each floor where the temporary elevator was installed could not be carried out until the temporary elevator was dismantled and removed. In particular, when an opening space for the temporary elevator is provided or in a high-rise building, the construction area after dismantling becomes wide, which has a large impact on the construction process. In addition, the lifting device of Patent Document 1 has a problem that it is difficult to install in the opening space because the elevator mast installed in the opening space needs a mechanism for moving the elevator hoist, etc., upward.

[0005] The present invention has been made in consideration of the above-mentioned circumstances, and aims to provide an elevator hoisting machine and elevator shaft structure that can be easily installed in an opening space for elevator placement, is less likely to interfere with surrounding construction work, and can improve construction efficiency. [Means for solving the problem]

[0006] The elevator hoist of the present invention, which solves the above-mentioned problems, is an elevator hoist that is placed in an opening space for installing an elevator formed in a structure, and suspends and supports a carriage so that it can be driven up and down, and is equipped with a hoist that supports a wire rope connected to the carriage so that it can be wound, and a base unit that supports the hoisting machine, wherein the base unit has telescopic legs that are extendable and retractable in a planar view, and the base unit can be erected on a structural part surrounding the opening space with the telescopic legs extended, and when the telescopic legs are contracted, the outer shape in a planar view is smaller than the opening space.

[0007] In this way, the frame part supporting the hoist can be installed between the structural parts around the opening space of the structure with the telescopic legs extended, so there is no need to provide a separate structure for fixing the elevator hoist inside the opening space, and the elevator hoist can be easily and stably installed in the opening space. Moreover, by contracting the telescopic legs, the outer shape of the frame part can be made smaller than the opening space, so the elevator hoist can be easily moved up and down inside the opening space, and no special structure is required for moving the elevator hoist. Therefore, the elevator hoist can be easily installed in the opening space for arranging the elevator of the structure, and the construction can be carried out while changing the installation position of the elevator hoist during construction. In other words, the elevator hoist is less likely to be an obstacle to construction work around the opening space, and construction efficiency can be improved.

[0008] In the elevator hoist of the present invention, the telescopic leg may include a leg main body fixed to the base portion, and a leg body that is movable horizontally relative to the leg main body. By configuring it in this way, the extendable leg portion can be constructed with a simple structure, and the length of the leg body can be easily adjusted.

[0009] In the elevator hoist of the present invention, a support part supported by the structural part may be provided at the tip of the leg body. By providing the support portion in this manner, the elevator hoist can be reliably supported and fixed to the structural portion surrounding the open space.

[0010] In the elevator shaft structure of the present invention, a rail portion for guiding the ascent and descent of the carrier is provided in the opening space, and the rail portion and any of the above-mentioned elevator hanging machines are positioned so as not to interfere with each other when viewed in a plan view. With this configuration, when the temporary elevator is extended upward as the construction progresses, a new rail can be connected above the lower rail that has already been installed while the elevator hoist remains installed in the opening space. In other words, the construction of the rail section can be completed in a short period of time.

[0011] In the elevator shaft structure of the present invention, the open space may be an elevator shaft for a permanent elevator. With this configuration, the temporary elevator can be installed using the opening space for constructing the permanent elevator shaft, eliminating the need to provide a separate opening space for the temporary elevator. This eliminates the need to close off the opening space for the temporary elevator to carry out various construction works until the construction work is completed, thereby improving construction efficiency.

[0012] In the elevator shaft structure of the present invention, a vertically continuous shaft partition wall may be formed around the opening space in a position that does not interfere with the elevator hanging machine in a plan view. By configuring in this manner, the shaft partition wall can be constructed while the elevator hoist remains installed in the opening space, thereby improving construction efficiency. Effect of the Invention

[0013] The elevator hoisting machine and elevator shaft structure of the present invention can be easily installed in the opening space for arranging the elevator, and is less likely to interfere with the construction of surrounding construction work, thereby improving construction efficiency. [Brief description of the drawings]

[0014] [Figure 1] 1 is a schematic front view showing an elevator hoisting machine according to an embodiment of the present invention installed in an opening space for arranging an elevator in a structure. FIG. [Diagram 2] FIG. 2 is a partially enlarged view of FIG. [Diagram 3] FIG. 1 is a schematic plan view showing an elevator hoisting machine according to an embodiment of the present invention. [Figure 4] FIG. 2 is a side view showing the elevator hoisting machine according to the present embodiment. [Diagram 5] FIG. 2 is a front view showing the elevator hoisting machine according to the present embodiment. [Figure 6]4A and 4B are plan views of the telescopic legs of the platform of the elevator hoisting machine according to the present embodiment, in which (a) shows the telescopic legs in an extended state, and (b) shows the telescopic legs in a retracted state. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0015] Hereinafter, an embodiment of the present invention will be described in detail with reference to the drawings. In this embodiment, an elevator hoisting machine is installed in an elevator shaft for installing a permanent elevator in a high-rise building under construction to install a temporary elevator for construction work.

[0016] FIG. 1 is a schematic front view showing the elevator hoist of this embodiment installed in an opening space for arranging an elevator in a structure, and FIG. 2 and FIG. 3 are schematic front and plan views showing the elevator hoist of this embodiment.

[0017] As shown in Figures 1 to 3, the structure 1 to which the elevator hoist 10 of this embodiment is attached is a high-rise building under construction. In detail, it is a framework in which the number of floors is increasing as the construction progresses, and each floor is provided with a floor structure portion 11 that constitutes the floor.

[0018] An opening 12a penetrating vertically is formed in the floor structure 11 of each floor, and the openings 12a of each floor are arranged at substantially the same position in the vertical direction to form an opening space 12. In this embodiment, the opening space 12 is ultimately used as an elevator shaft for a permanent elevator.

[0019] The elevator hoist 10 of this embodiment is installed at a height position along the construction progress of the open space 12. A carriage 13 and a weight (not shown) are arranged so as to be able to rise and fall below the elevator hoist 10 in the open space 12. The carriage 13 and the weight are connected by a wire rope 14, and the wire rope 14 is supported by the elevator hoist 10 so as to be able to be driven to rise and fall.

[0020] In the open space 12 below the elevator hoist 10, a rail section 15 for guiding the lifting and lowering of the carriage 13 and weight is installed continuously in the vertical direction from the lower end to the height position of the elevator hoist 10. The rail section 15 may be a rack gear, or may be installed separately for the carriage 13 and the weight. Furthermore, on at least one side of the open space 12, preferably the entire surface, a shaft partition wall 16 is provided continuously from top to bottom. As the construction of the structure 1 progresses, the open space 12 is also extended upward, so the rail section 15 and the shaft partition wall 16 are also extended accordingly (see FIG. 1).

[0021] The elevator lifting machine 10 is disposed in the opening space 12 and comprises a base section 20 which is fixed to the floor structure section 11 surrounding the opening 12a, and a hoisting machine 21 which is placed on the base section 20 and supports the wire rope 14 connected to the carrier 13 in a manner that allows it to be hoisted.

[0022] The hoist 21 includes a top sheave 22 that supports the wire rope 14, a drive device 23 that rotates and drives the top sheave 22, and a deflector sheave 24 around which the wire rope 14 is wound together with the top sheave 22.

[0023] 4 and 5 are a side view and a front view showing the elevator hoisting machine 10 of this embodiment, and FIGS. 6(a) and 6(b) are plan views of the telescopic leg portion of the frame unit.

[0024] As shown in FIGS. 4 and 5, the frame unit 20 has a frame body 26 to which the hoisting machine 21 is fixed, and an extendable leg unit 27 connected to the lower side of the frame body 26.

[0025] The telescopic legs 27 are provided at the bottom of the frame body 26 and are provided so as to be telescopic so that the maximum width can be enlarged or reduced in a plan view. The telescopic legs 27 are made of outriggers and include a plurality of leg bodies 27a provided at the bottom of the frame body 26 and a plurality of leg bodies 27b each having one end inserted into the leg body 27a and a support part 27c for the floor structure part 11 provided at the other end. In this embodiment, two telescopic legs 27 are provided. Each leg body 27b can be telescopically extended and retracted linearly in the approximately horizontal direction by changing the length of one end side accommodated in the leg body 27a, and is configured to be fixed to the leg body 27a in an extended or contracted state. The method of fixing the leg body 27b to the leg body 27a is arbitrary, and for example, it may be fixed using a bolt.

[0026] 6(a), by extending the telescopic legs 27, the platform 20 can have a maximum width in plan view larger than the opening 12a of the floor structure 11. By fixing each support 27c to the floor structure 11 in this state, the elevator hoist 10 can be installed on the structure 1 between the floor structure 11 around the opening 12a.

[0027] In the elevator lifting machine 10 of this embodiment, when it is mounted over the opening 12a by the platform portion 20, the carrier 13 and the weight rail portion 15 are positioned in such a way that they do not interfere with each other when viewed in a plan view, on the one hand, and the platform portion 20 and the hoisting machine 21 are positioned in such a way that they do not interfere with each other.

[0028] Furthermore, the shaft partition wall 16 installed in the open space 12 is disposed at a position that does not interfere with the frame portion 20 and the hoisting machine 21 other than the telescopic leg portion 27 in a plan view.

[0029] As shown in FIG. 6(b), when the telescopic legs 27 are contracted, the maximum width in plan view can be reduced below the opening 12a of the floor structure 11, and the outer shape can be made smaller than the opening space 12.

[0030] If an elevator hoist 10 having such a structure is attached to a high-rise building under construction and a temporary elevator is set up for use in the construction, the temporary elevator can be installed and used in the elevator shaft for the permanent elevator.

[0031] As construction of the structure 1 progresses and construction above the location where the elevator hoist 10 is installed progresses, construction of the shaft partition wall 16 around the opening space 12 can be carried out. After construction of the shaft partition wall 16 is completed, construction of the rail section 15 above the location where the elevator hoist 10 is installed can be carried out. This construction of the rail section 15 can be carried out in parallel with the use of the temporary elevator.

[0032] When the number of floors increases with the progress of construction, it becomes necessary to extend the range of use of the temporary elevator upward. To extend the range of use of the temporary elevator, while the carriage 13 and the weight are held in a fixed position, the support part 27c of the telescopic leg part 27 is removed from the floor structure part 11 around the opening 12a, the fixation between the leg body 27b and the leg body 27a is released, and one end side of the leg body 27b is moved in the direction of being accommodated in the leg body 27a, thereby contracting the entire length of the telescopic leg part 27 (see FIG. 6(b)).

[0033] In this state, the elevator hoist 10 is lifted by a crane or the like and raised within the opening space 12. After the elevator hoist 10 is raised to a predetermined position, the telescopic legs 27 are extended again and fixed to the floor structure 11 around the opening 12a on an appropriate floor according to the increase in the number of floors, thereby increasing the operating range of the temporary elevator. The movement range of the carriage 13 can be increased by unwinding the wire rope 14 from an excess drum (not shown). In this way, the elevator hoist 10 is repeatedly raised to increase the operating range of the temporary elevator, making it possible to use the temporary elevator while utilizing the elevator shaft of the permanent elevator until the high-rise building (structure 1) is completed.

[0034] According to the elevator hoist 10 of this embodiment, the frame 20 supporting the hoist 21 can be erected between the floor structure parts 11 around the opening space 12 of the structure with the telescopic legs 27 extended. Therefore, there is no need to provide a structure for fixing the elevator hoist 10 inside the opening space 12 of a building under construction, and the elevator hoist 10 can be easily and stably installed in the opening space 12. Moreover, by contracting the telescopic legs 27, the outer shape of the frame 20 can be made smaller than the opening space 12, so the elevator hoist 10 can be easily raised and lowered through the opening space 12.

[0035] Therefore, it is possible to easily install the elevator hoisting machine 10 in the opening space 12 of a building under construction, and the installation position of the elevator hoisting machine 10 can be easily changed and installed within the opening space 12. This makes it possible to proceed with the construction work while changing the installation position of the elevator hoisting machine 10 during construction, and the elevator hoisting machine 10 is unlikely to become an obstacle to construction work around the opening space 12.

[0036] In the elevator hoist 10 of this embodiment, the telescopic leg section 27 comprises a leg main body 27a fixed to the frame main body 26 and a leg body 27b that is movable horizontally relative to the leg main body 27a, so that the telescopic leg section 27 can be constructed with a simple structure and the length of the leg body 27b can be easily adjusted.

[0037] In the elevator hoisting machine 10 of this embodiment, the support portion 27c supported by the floor structure portion 11 is provided at the tip of the leg body 27b, so that the elevator hoisting machine 10 can be reliably supported and fixed to the floor structure portion 11 around the opening space 12. Although the support portion 27c has been described as being supported by the floor structure portion 11, the support portion 27c may be supported at a location other than the floor structure portion 11.

[0038] Furthermore, in the elevator hoisting machine 10 of this embodiment, the open space 12 is provided with a rail section 15 that guides the lifting and lowering of the carriage 13, and the rail section 15, the frame section 20, and the hoisting machine 21 are disposed in a position where they do not interfere with each other in a plan view. Therefore, when extending the temporary elevator upward as the construction progresses, construction can be performed to connect a new rail section 15 above the lower rail section 15 that has already been installed while the elevator hoisting machine 10 remains installed in the open space 12. This makes it easy to extend the rail section 15.

[0039] Furthermore, in the elevator hoist 10 of this embodiment, the opening space 12 is an elevator shaft for a permanent elevator, so a temporary elevator can be installed using the opening space 12 for constructing an elevator shaft. Therefore, there is no need to provide an opening space for the temporary elevator, and there is no need to close off the opening space for the temporary elevator and perform various construction works until the construction work is completed.

[0040] Moreover, in the elevator hoisting machine 10 of this embodiment, the open space 12 is provided with the shaft partition wall 16 that is continuous vertically at a position where it does not interfere with the frame part 20 and the hoisting machine 21, excluding the telescopic leg part 27, in a plan view. Therefore, the installation work for the shaft partition wall 16 can be performed with the elevator hoisting machine 10 installed in the open space 12.

[0041] The above embodiment can be modified as appropriate within the scope of the present invention. For example, in the above embodiment, the elevator hoisting machine 10 is attached to the elevator shaft of a high-rise building under construction, but there is no limitation on the structure on which the elevator hoisting machine 10 is installed. For example, the structure may be a dam or bridge under construction, or may be various types of completed buildings.

[0042] In the above embodiment, the telescopic leg 27 is configured by the leg body 27a and the leg body 27b inserted linearly into the leg body 27a so as to be telescopic, but this is not particularly limited and can be modified as appropriate. For example, the telescopic leg 27 is telescopic only in one width direction, but it may be telescopic in different directions. It is also possible to connect the leg bodies 27b arranged adjacent to each other in parallel. It is also possible to configure the telescopic leg 27 by a leg body rotatably attached to the frame body 26.

[0043] In the above embodiment, the opening 12a and the open space 12 on each floor are surrounded, but they may be formed in a concave shape with a part open outward. Furthermore, the arrangement of the telescopic legs 27 and the rails 15 in the opening 12a and the open space 12 is not limited in any way and can be changed as appropriate. [Explanation of symbols]

[0044] 10 Elevator lifting machine 11 Floor structure section (structure section) 12 Open space 12a opening 13 Transporter 14 Wire Rope 15 Rail section 16 Shaft partition wall 20 Stand section 21 Hoisting machine 22 Top Sheave 23 Drive unit 24 Deflector 26 Stand body 27 Telescopic legs 27a Leg body 27b Leg body 27c Support part

Claims

1. An elevator hoisting machine that is disposed in an opening space for installing an elevator formed in a structure and suspends and supports a carriage so as to be capable of being driven up and down, A hoist that supports the wire rope connected to the carriage so as to be capable of hoisting the wire rope; A frame portion supporting the hoisting machine, The stand unit has a telescopic leg unit that is telescopic in a plan view, The base unit can be erected on a structural portion surrounding the opening space with the telescopic legs extended, and the elevator hoist has an outer shape in a plan view that is smaller than the opening space with the telescopic legs contracted.

2. The elevator hoisting machine according to claim 1 , wherein the telescopic leg portion comprises a leg main body fixed to the base portion and a leg body that is movable horizontally relative to the leg main body.

3. 3. The elevator hoisting machine according to claim 2, wherein a support portion supported by the structural portion is provided at a tip of the leg body.

4. An elevator shaft structure in which a rail portion for guiding the lifting and lowering of the carrier is provided in the opening space, and the rail portion and the elevator hoisting machine described in any one of claims 1 to 3 are positioned in a position where they do not interfere with each other when viewed in a plan view.

5. 5. The elevator shaft structure according to claim 4, wherein the open space is an elevator shaft for a permanent elevator.

6. 5. The elevator shaft structure according to claim 4, wherein a vertically continuous shaft partition wall is formed around the opening space at a position that does not interfere with the elevator hoist in a plan view.

Citation Information

Patent Citations

  • Lifting device and its climbing method

    JP2007284179A