Method of installing steel pipe with connecting mechanism for reinforcing ground, and connecting jig
Patent Information
- Application Number
- JP2023073296
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-27
- Publication Date
- 2024-11-08
AI Technical Summary
【0012】 本発明によれば、鋼管をトンネル周壁部の地山に埋設して地山を補強する施工方法において、後続の鋼管を前進させて、先行の鋼管と連結することができ、しかも、鋼管を押すための治具等の取り付け、取り外し不要な施工方法を提供できる。
Smart Images

Figure 2024158252000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a steel pipe that is driven into natural ground to reinforce the natural ground in tunnel construction or the like. [Background technology]
[0002] In tunnel construction, to reinforce the natural ground around the tunnel walls, steel pipes for natural ground reinforcement (hereafter referred to as "steel pipes") are buried in the natural ground and a cementing agent is injected into the buried steel pipes. The steel pipes have discharge holes for the cementing agent along their entire length, and the cementing agent penetrates the natural ground from the discharge holes and settles in the natural ground, reinforcing and stabilizing the natural ground.
[0003] When driving a steel pipe into the natural ground, a rock drill is used, as described in Patent Documents 1 and 2. The rock drill has a guide shell, and a drifter is attached to the guide shell. A rod with a drilling tool called a bit attached to its tip is connected to the drifter, and the rod is arranged to penetrate the steel pipe, with the bit protruding from the tip of the steel pipe. The drifter applies impact force and propulsion force to the rod, and at the same time, the natural ground is excavated by the bit, and the steel pipe located between the tip of the rod and the drifter is buried in the hole formed by the excavation.
[0004] Generally, the length of a single steel pipe is about 3m, but the length required to reinforce the ground is longer than 3m, so each time a steel pipe is cast, a new steel pipe is connected to the end and cast again, and the process is repeated.
[0005] A threaded connection is generally used as the structure of the connection part that connects steel pipes to each other. The leading steel pipe has a male thread at the rear end and the trailing steel pipe has a female thread at the front end. The trailing steel pipe is rotated by hand, and the female thread at the front end is screwed into the male thread at the rear end of the leading steel pipe, connecting them.
[0006] On the other hand, in order to reduce the burden on the worker who connects the leading steel pipe and the following steel pipe by screwing them together, to reduce the time required for connection, and to realize a quick connection, Patent Document 2 discloses a steel pipe with a connection mechanism that can be connected simply by moving the following steel pipe forward. In this connection mechanism, a groove is provided along the circumferential direction on the outer circumferential surface of the rear end of the leading steel pipe, and a C-shaped ring is attached in the groove. Meanwhile, a groove is also provided along the circumferential direction on the inner circumference of the tip of the following steel pipe. When the tip of the following steel pipe is moved forward so as to cover the rear end of the leading steel pipe, the C-shaped ring at the rear end of the leading steel pipe engages with the groove on the inner circumference of the tip of the following steel pipe, and the leading steel pipe and the following steel pipe are connected.
[0007] Since it is necessary to apply force to the following steel pipe while moving it forward, the structure of Patent Document 2 discloses a structure in which a removable jig is placed between the rear end of the following steel pipe and a drifter, and the following steel pipe is moved forward by pushing the jig with the drifter. Patent Document 2 also discloses a configuration in which a removable jig is placed between a centralizer that supports the following steel pipe on a guide shell and the tip of the steel pipe, and the guide shell is moved forward to push the step at the tip of the steel pipe with the centralizer, thereby moving the following steel pipe forward. [Prior art documents] [Patent documents]
[0008] [Patent Document 1] JP 2019-203362 A [Patent Document 2] JP 2022-100190 A Summary of the Invention [Problem to be solved by the invention]
[0009] However, in the structure of Patent Document 2, in which a jig is used to push the step at the rear end or front end of the following steel pipe, the jig needs to be attached only when the following steel pipe is to be connected to the preceding steel pipe. Therefore, every time a following steel pipe is added, the jig needs to be manually attached to the steel pipe, and after the connection of the steel pipes is completed, the jig needs to be removed, which is time-consuming. In addition, since the connection work of the steel pipes is performed in a state where the guide shell on which the drifter and the steel pipes are mounted is raised to the casting point in the ground, it is also necessary to ensure the safety of the worker and prevent the jig from falling when attaching and removing the jig.
[0010] An object of the present invention is to provide a structure that allows a subsequent steel pipe to be advanced and connected to a preceding steel pipe, without the need to attach or detach a jig or the like for pushing the steel pipe. [Means for solving the problem]
[0011] In order to achieve the above object, the present invention provides a construction method for reinforcing the natural ground of the tunnel peripheral wall using steel pipes. This construction method uses a rock drill equipped with a drifter that applies impact force to a connected rod, a guide shell that supports the drifter so that it can move in the axial direction of the rod, a centralizer fixed to the tip side of the guide shell, a sub-centralizer arranged at an interval in the axial direction, a support device that supports the guide shell, and a boom that supports the support device so that it can be raised and lowered. This construction method involves the following steps in order. First, a first steel pipe is mounted on the centralizer, the rear end of the rod inserted into the steel pipe is connected to the drifter, and the drifter is advanced on the guide shell while applying an impact force to the rod with the drifter, and the first steel pipe is inserted into the formed hole while drilling a hole in the natural ground with a bit attached to the tip of the rod. Next, with the rear end of the first steel pipe protruding outward from the hole in the natural ground, the forward movement of the drifter is stopped, the guide shell is retreated, the drifter is moved backward on the guide shell, and the guide shell is lowered by the boom. Next, a second steel pipe, which has a socket portion at its tip whose outer radius is larger than that of the steel pipe body, is mounted on the centralizer and subcentralizer of the guide shell so that the socket portion is located closer to the tip of the guide shell than the centralizer. The boom is raised and the guide shell on the support device is advanced in the axial direction, causing the centralizer to push against the step on the outer periphery between the socket portion of the second steel pipe and the steel pipe body, and the inner periphery of the socket portion at the tip of the second steel pipe is placed over the outer periphery of the rear end of the first steel pipe to connect them. Effect of the Invention
[0012] According to the present invention, in a construction method for reinforcing the natural ground by burying steel pipes in the natural ground of the surrounding wall of a tunnel, a construction method can be provided in which a subsequent steel pipe can be advanced and connected to the preceding steel pipe, and moreover, a construction method can be provided in which it is not necessary to attach or remove jigs or the like for pushing the steel pipes. [Brief description of the drawings]
[0013] [Figure 1]1 is a side view showing the overall configuration of a rock drill 200 according to an embodiment of the present invention. [Diagram 2] FIG. 2 is a block diagram showing the arrangement of the centralizer 304 and the steel pipe 100 on the guide shell 301 of the rock drill 200 according to the embodiment. [Diagram 3] FIG. 2 is a front view of a steel pipe 100 used in the embodiment. [Figure 4] 1A and 1B are front and side views of a centralizer 304 according to an embodiment of the present invention. [Diagram 5] 13 is a photograph of the centralizer 304 according to the embodiment taken from an oblique angle. [Figure 6] 1A and 1B are photographs of the centralizer 304 according to the embodiment taken from the front and obliquely, respectively. [Figure 7] FIG. 4 is a left side view of the steel pipe 100 of FIG. 3. [Figure 8] FIG. 4 is a right side view of the steel pipe 100 of FIG. 3. [Figure 9] FIG. 2 is an axial cross-sectional view of a steel pipe 100 used in the embodiment. [Figure 10] 1A is an axial cross-sectional view of a socket portion 10 of a steel pipe 100 used in an embodiment, and FIG. 1B is an axial cross-sectional view of an insertion portion 30 thereof. [Figure 11] FIG. 2 is an axial cross-sectional view of a connection portion when two steel pipes 100 used in the embodiment are connected. [Figure 12] FIG. 2 is an axial cross-sectional view showing a state in which steel pipes 100 are aligned and connected in an embodiment. [Figure 13] FIG. 2 is an enlarged cross-sectional view in the axial direction of a connecting portion that connects two steel pipes 100 in an embodiment. [Figure 14] FIG. 2 is a diagram for explaining a method of driving a steel pipe 100 according to an embodiment into natural ground. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0014] An embodiment of the present invention will now be described.
[0015] First, a rock drill 200 of this embodiment will be described with reference to the drawings. Fig. 1 is a side view showing the overall configuration of the rock drill, and Fig. 2 is a diagram showing the arrangement of centralizers 304 and steel pipes 100 on a guide shell 301.
[0016] The rock drill 200 is configured to include a main body 540 equipped with a hydraulic mechanism, a boom 510 having one end supported by the main body 540, a support device 400 supported at the tip of the boom 510, and a guide shell set 300 mounted on the support device 400. The rock drill 200 also includes a second boom 550 having one end supported by the main body 540, and a charging cage 551 supported at the tip of the second boom 550.
[0017] The main body 540 is equipped with wheels 530 that enable self-propelling, a fixing device 520 that fixes the main body 540 to the ground during construction, an operating device (not shown), a control device (not shown), etc. The main body 540 can apply hydraulic driving force to the boom 510, the support device 400, and the guide shell set 300 under the control of the control device in accordance with the operation received from the operator by the operating device, thereby causing the main body 540 to perform a predetermined operation.
[0018] The guide shell set 300 is configured to include a guide shell 301, a drifter 302 mounted on the guide shell 301, a centralizer 304 fixed on the guide shell 301, and a sub-centralizer 305 movably mounted on the guide shell 301.
[0019] One end of a rod 303 is connected to the drifter 302. The drifter 302 applies a striking force to the rod 303.
[0020] The guide shell 301 supports the drifter 302 so as to be movable in the axial direction (L direction) of the rod 303 .
[0021] The centralizer 304 is fixed to the tip side of the guide shell 301, and the sub-centralizer 305 is disposed on the guide shell 301 at a distance from the centralizer 304 along the axial direction (L direction). The sub-centralizer 305 is movable in the axial direction of the guide shell 301.
[0022] Moreover, the support device 400 supports the guide shell 301 so as to be movable in the axial direction (L direction).
[0023] The centralizer 304 and the sub-centralizer 305 each have a U-shaped opening in which the steel pipe 100 is placed and supports the steel pipe 100. When the steel pipe 100 is placed in the U-shaped opening, the curved surface at the bottom of the U-shaped opening contacts the side of the steel pipe 100 to support the steel pipe 100.
[0024] As shown in Fig. 3, the steel pipe 100 is provided at its tip with a socket portion 10 whose outer circumferential radius is larger than the radius of the steel pipe body 20. The detailed structure of the steel pipe 100 will be described later.
[0025] The curved surface at the bottom of the U-shaped opening of the centralizer 304 has a predetermined radius of curvature, which is designed to be smaller than the radius of the outer periphery of the socket portion 10 of the steel pipe 100 and larger than the radius of the outer periphery of the steel pipe body 20.
[0026] Here, as shown in Figures 4 to 6, the centralizer 304 has a configuration including a centralizer body 314 with a U-shaped opening, and a pressing member 320 fixed to the centralizer body 314. As shown in Figure 4, the pressing member 320 is configured to narrow the radius of curvature r1 of the bottom of the U-shaped opening of the centralizer body 314 to a radius of curvature r2. The radius of curvature r2 is a value smaller than the radius of the outer periphery of the socket portion 10 of the steel pipe 100 and larger than the radius of the outer periphery of the steel pipe body 20.
[0027] Specifically, the pressing member 320 is a plate-like member of a predetermined thickness, and is firmly fixed to the front surface of the centralizer body 314 by bolts 321. The plate-like member has a U-shaped opening with a curvature radius smaller than the outer periphery radius of the socket portion 10 of the steel pipe 100 and larger than the outer periphery radius of the steel pipe body 20. The material of the plate-like member constituting the pressing member 320 is preferably one having a strength equal to or greater than that of the steel pipe 100, and as an example, carbon steel for mechanical structure S45C (JIS standard) can be used.
[0028] The method of fixing the pressing member 320 to the front surface of the centralizer body 314 is not limited to the bolt 321, but may be a method using a fastener other than a bolt, or a method of fixing without using a fastener such as welding.
[0029] Although the pressing member 320 is fixed to the front surface of the centralizer body 314 here, the pressing member 320 may be structured to stand on the guide shell 301.
[0030] In this way, by using the centralizer 304 with a designed radius of curvature for the bottom of the U-shaped opening, the steel pipe 100 is mounted so that the socket portion 10 is located closer to the tip of the guide shell 301 than the centralizer 304, and when the guide shell 301 is advanced in the axial direction (L direction), the centralizer 304 pushes the step 101 on the outer periphery between the socket portion 10 of the steel pipe 100 and the steel pipe body 20, and advances it. This makes it possible to connect the steel pipe 100 (steel pipe 100-2 in Fig. 2) mounted on the centralizer 304 to the rear end of another steel pipe 100 (steel pipe 100-1 in Fig. 2) that has been buried in the natural ground previously and whose rear end protrudes from the face of the natural ground.
[0031] The pressing member 320 in this embodiment is fixed to the centralizer body 314 and does not need to be detached, so there is no risk of it falling off the centralizer body 314, and the worker does not need to perform any work on the pressing member 320 when connecting.
[0032] <Steel pipe with connecting mechanism> Next, the steel pipe 100 used in this embodiment will be described below with reference to the drawings.
[0033] Fig. 3 is a front view of a steel pipe 100 with a connecting mechanism using a ring, Fig. 7 and Fig. 8 are left side and right side views, Fig. 9, Fig. 10(a) and Fig. 10(b) are cross-sectional views along the axial direction, Fig. 11, Fig. 12 and Fig. 13 are enlarged views of a connecting portion connecting two steel pipes 100.
[0034] As shown in Fig. 3, the steel pipe 100 is composed of a steel pipe body 20, a socket portion 10 provided at one end of the steel pipe body 20, and an insertion portion 30 provided at the other end. As shown in Fig. 11, the socket portion 10 and the insertion portion 30 are provided for connection to a second steel pipe 100 (100-2) of the same shape.
[0035] As shown in Figures 7 and 8, the socket portion 10 and the insertion portion 30 are cylinders coaxial with the steel pipe body 20, and the outer diameter of the socket portion 10 is larger than the outer diameter of the steel pipe body 20, and the inner diameter of the socket portion 10 is equal to or larger than the outer diameter of the insertion portion 30.
[0036] In this way, by providing a socket portion 10 having an outer diameter larger than that of the steel pipe body 20, the insertion portion 30 can be inserted into and connected to the socket portion 10 even if the outer diameter of the insertion portion 30 is made approximately equal to the outer diameter of the steel pipe body 20.
[0037] As shown in FIGS. 9 and 10, two or more first grooves 11 are provided in the inner circumferential surface of the socket portion 10 in the circumferential direction.
[0038] On the other hand, two or more second grooves 31 are provided in the circumferential direction on the outer circumferential surface of the insertion portion 30. A C-shaped ring 32 is disposed in each of the second grooves 31 so that at least a portion of the ring protrudes from the outer circumferential surface 33 of the insertion portion (see Figs. 3, 9 and 10). The C-shaped ring 32 is partially cut out and therefore acts as a spring member. It is desirable that the material of the ring 32 is harder than the materials of the insertion portion 30 and the socket portion 10.
[0039] Therefore, as shown in Figure 12, when the socket portion 10 of a second steel pipe 100-2, which has the same shape, is placed over the insertion portion 30 of a first steel pipe 100-1 while aligning the axes and then pressed in the axial direction, the two rings 32 of the insertion portion 30 are pressed into the inside of the second groove 31 by the inner surface of the second steel pipe 100-2, and when the first groove 11 of the socket portion 10 of the second steel pipe 100-2 reaches the position of the rings 32, the rings 32 protrude from the outer surface 33 of the insertion portion 30 and engage with the first groove 11.
[0040] This allows the two steel pipes 100-1 and 100-2 to be easily connected by aligning the insertion portion 30 of the first steel pipe 100-1 and the socket portion 10 of the second steel pipe 100-2 and pushing them together, as shown in Figure 11.
[0041] Furthermore, by providing an inclined surface 12 on the inner peripheral surface of end 16 of socket portion 10 as shown in Figure 4 and widening the inner diameter at end 16 of socket portion 10, even if there is an error in the height difference of inclined surface 12 when aligning the axes during connection, socket portion 10 can be placed over insertion portion 30, and the alignment tolerance can be increased.
[0042] In addition, the steel pipe 100 has a socket portion 10, and since the outer diameter of the socket portion 10 is larger than the outer diameter of the steel pipe body 20, it is possible to make the outer diameter of the insertion portion 30 approximately the same as the outer diameter of the steel pipe body 20.
[0043] As shown in FIG. 9, the socket portion 10 is formed of a separate member from the steel pipe body 20. A female thread is provided on the inner peripheral surface of the end of the socket portion 10 facing the steel pipe body 20. Meanwhile, a male thread is provided on the outer peripheral surface of the end of the steel pipe body 20 facing the socket portion 10. The socket portion 10 is fixed to the steel pipe body 20 by screwing the female thread of the socket portion 10 into the male thread of the steel pipe body 20. Note that the method of fixing the socket portion 10 to the steel pipe body 20 is not limited to fixing by screws, and other fixing methods such as welding can also be used.
[0044] In this way, by making the socket portion 10 a separate member from the steel pipe body 20, it is possible to easily manufacture the socket portion 10 having a larger outer diameter than the steel pipe body 20.
[0045] The shapes of the ring 32, the first groove 11 and the second groove 31 will be described in further detail with reference to FIG.
[0046] The ring 32 has a wedge-shaped axial cross section, with an end face 34 closer to the steel pipe body 20 being thicker than an end face 35 closer to the end 36 of the insertion portion 30 .
[0047] Moreover, the end face 34 is a surface perpendicular to the central axis of the insertion portion 30. Moreover, the upper surface of the end of the ring 32 on the end face 34 side is configured to protrude from the second groove 31 onto the outer circumferential surface 33 when no force is applied to the ring 32.
[0048] The first groove 11 of the socket portion 10 is formed so that a bottom surface 13 on the side closer to the end 16 of the socket portion 10 is deeper than a bottom surface 14 on the side closer to the steel pipe body 20 .
[0049] Further, a side surface 15 of the first groove 11 of the socket portion 10 that is closer to an end portion 16 of the socket portion 10 is a surface that is perpendicular to the central axis of the socket portion 10 .
[0050] As a result, when the insertion portion 30 of the first steel pipe 100-1 is covered with the socket portion 10 of the second steel pipe having the same shape and the first steel pipe 100-1 is moved in the direction of pulling the second steel pipe 100-2, the side surface 15 on the tip side of the first groove 11 of the socket portion 10 of the second steel pipe 100-2 comes into contact with the end face 34 of the wedge-shaped ring 32 on the side closer to the steel pipe body 20. As a result, the side surface 15 of the first groove 11 of the second steel pipe 100-2 engages with the end face 34 of the wedge-shaped ring 32. When the first steel pipe 100-1 moves in the direction of pulling the second steel pipe 100-2, the side surface 15 gets caught on the end face 34 of the ring 32, and the second steel pipe 100-2 also moves with the movement of the first steel pipe 100-1.
[0051] At this time, since two rings 32 are arranged, the force can be distributed at the two end faces 34 and transmitted to the second steel pipe 100-2, thereby increasing the tensile strength of the connection portion.
[0052] In addition, the first groove 11 of the socket portion 10 has a bottom surface 13 that is closer to the end portion 16 of the socket portion 10 dug down one step deeper. This makes it possible to ensure a wide area for the vertical side surface 15, widening the contact area with the end surface 34 of the ring 32 and ensuring engagement.
[0053] Furthermore, the bottom surface of the second groove 31 of the insertion portion 30 is inclined in a region 37 close to the end 36 of the insertion portion 30. This makes the side of the second groove 31 close to the end 36 of the insertion portion 30 shallower than the bottom surface on the side close to the steel pipe body 20.
[0054] By providing the region 37 with an inclined bottom surface, when the first steel pipe 100-1 moves in a direction pulling the second steel pipe 100-2, the side surface 15 of the first groove 11 engages with the end surface 34 of the wedge-shaped ring 32, applying a force in a direction pressing the wedge-side ring 32 against the inclined region 37. At this time, the wedge-shaped ring 32 moves along the inclined region 37 and is lifted upward (in a direction protruding from the outer circumferential surface 33), so that the end surface 34 of the wedge-shaped ring 32 protrudes further upward from the second groove 31, and the contact area with the side surface 15 of the first groove 11 becomes larger. This makes it possible to strengthen the joint between the first steel pipe 100-1 and the second steel pipe 100-2.
[0055] 13, the inner circumferential surface of the socket portion 10 is provided with a step portion 17 against which the end portion 36 of the insertion portion 30 abuts when the insertion portion 30 of the second steel pipe 100-1 is inserted. The region 18a between the step portion 17 on the inner circumferential surface of the socket portion 10 and the first groove 11, the region 18b between the two first grooves 11, and the region 18c between the first groove 11 and the end portion 16 and adjacent to the first groove 11 are designed to have clearances (gaps) of 0.5 mm or less between the corresponding regions 38a, 38b, and 38c of the inserted insertion portion 30.
[0056] In this way, by making the clearance between region 18 and region 38 0.5 mm or less, when the socket portion 10 of the second steel pipe 100-2 is placed over the insertion portion 30 of the first steel pipe 100-1, even if the axes are not completely aligned and the socket portion 10 is placed over the insertion portion 30 in a bent state, the contact between region 18 and region 38 acts as a guide to align the axes. This makes it easier to connect the insertion portion 30 of the first steel pipe 100-1 to the socket portion 10 of the second steel pipe 100-2 compared to when the clearance between region 18 and region 38 is not 0.5 mm or less.
[0057] As described above, the steel pipe with connecting mechanism 100 (100-1, 100-2) used in this embodiment can easily connect the ends of two steel pipes 100 and has a high connecting strength, making it suitable for a construction method in which a rock drill bit is attached near the tip of the steel pipe to proceed with drilling.
[0058] <Construction method> A construction method for reinforcing the natural ground by driving steel pipes 100 into the natural ground 75 of the tunnel peripheral wall will be described with reference to Figures 1, 2, 14, etc. Figure 14 shows a state in which a first steel pipe 100-1 has been driven into the natural ground 75 and a second steel pipe 100-2 has been mounted on a guide shell 301.
[0059] First, a rock drilling bit is attached near the tip of the first steel pipe 100-1. The steel pipe 100-1 is mounted on the centralizer 304 and sub-centralizer 305 of the guide shell 301 of the rock drill 200 installed near the driving point of the natural ground 75 (here, the face 75a). A drifter 80 (drive source for the bit) is mounted at the rear. The rear end of the rod 303-1 is connected to the shank sleeve 83 of the drifter 302. The tip of the rod 303-1 is inserted into the steel pipe 100 and connected to the bit fixed to the first steel pipe 100-1. The rod 303-1 is of approximately the same length as the steel pipe 100-1.
[0060] While applying an impact force to the rod 303-1 by the drifter 302, the drifter 302 is pushed forward along the guide shell 301. This makes it possible to drill a hole in the natural ground 75 and at the same time insert the first steel pipe 100-1 into the drilled hole.
[0061] When the first steel pipe 100-1 has been driven almost into the ground 75 and the insertion portion 30 at the rear end of the steel pipe 100-1 protrudes forward of the face 75a of the ground 75 (Figure 9), the rod 303-1 is removed from the shank sleeve 83 of the drifter 302, and the drifter 302 is moved rearward along the guide shell 301.
[0062] The guide shell 301 is lowered by the boom 510, and the second steel pipe 100-2 with the rod 303-2 inserted therein is loaded onto the guide shell 301. At this time, the steel pipe 100-2 is loaded so that its socket portion 10 is positioned closer to the tip of the guide shell 301 than the centralizer 304. In particular, it is preferable to load the steel pipe 100-2 so that the step 101 between the socket portion 10 and the steel pipe body 20 comes into contact with the centralizer 304 (pressing member 320), as shown in FIG.
[0063] The rear end of the rod 303-2 is connected to the shank sleeve 83. The drifter 302 is advanced so that the tip of the rod 303-2 protrudes forward from the tip of the steel pipe 100-2.
[0064] The guide shell 301 is raised by the boom 510 and moved to the vicinity of the rear end of the first steel pipe 100-1. The rear end of the rod 303-1 of the first steel pipe 100-1 and the tip of the rod 303-2 of the second steel pipe 100-2 are aligned with each other and temporarily fixed using a rod sleeve. As a result, the first steel pipe 100-1 and the second steel pipe 100-2 are also almost aligned with each other.
[0065] By advancing the guide shell 301 on the support device 400 in the axial direction (L direction), the centralizer 304 pushes against the step 101 on the outer periphery between the socket portion 10 and the steel pipe body 20 of the second steel pipe 100-2, moving the second steel pipe 100-2 forward. At this time, the portion along the inner periphery of the U-shaped opening on the front side of the centralizer 304 (pressing member 320) comes into contact with and pushes against the step 101, as shown in Figure 4.
[0066] As a result, the opening at the tip of the socket portion 10 of the second steel pipe 100-2 is covered by the rear end of the insertion portion 30 of the first steel pipe 100-1 (see Figure 2), and by further advancing the guide shell 301 on the support device 400 in the axial direction (L direction), pressure is applied so that the socket portion 10 of the second steel pipe 100-2 is covered over the insertion portion 30 of the first steel pipe 100-1 as shown in Figure 11.
[0067] As a result, the two C-shaped rings 32 of the first steel pipe 100-1 engage with the two first grooves 11 of the socket portion 10 of the second steel pipe 100-2 as shown in Figure 13, and the tip of the second steel pipe 100-1 can be connected to the rear end of the first steel pipe 100-1.
[0068] In this manner, the step 101 of the second steel pipe 100-2 is pushed by the centralizer 304, and the two steel pipes 100-1, 100-2 can be easily connected by the action of moving forward and pushing in.
[0069] At the same time that the first steel pipe 100-1 and the second steel pipe 100-2 are connected, the rods 303-1 and 303-2 are also connected via a rod sleeve. Therefore, by again applying a striking force to the rods 303-1 and 303-2 with the drifter 302 and pushing the drifter 302 along the guide shell 301, it is possible to drill a hole in the natural ground 75 and at the same time drive the second steel pipe 100-2 into the drilled hole.
[0070] At this time, the second steel pipe 100-2 is pulled by the first steel pipe 100-1 and moves through the drilled hole, so a force is applied to the connecting portion in a direction that pulls the two steel pipes 100 apart. However, because the connecting strength of the steel pipes 100-1, 100-2 against tension is large, the pipes do not come loose.
[0071] By repeating this operation, the required number of steel pipes 100 can be driven sequentially into the natural ground.
[0072] In the above-mentioned construction method, a bit of a jackhammer is attached near the tip of the steel pipe 100-1, and the steel pipe 100-1 is pulled while the bit is drilling a hole, but the present invention is not limited to this. In a construction method in which the rear end of the steel pipe is pushed by a jackhammer to advance drilling, it is of course possible to use the construction method of this embodiment in which the centralizer 304 pushes the step 101 of the steel pipe 100-2 when the steel pipes 100-1 and 100-2 are connected.
[0073] In this embodiment, the construction method is such that the step 101 of the steel pipe 100-2 is pushed by the centralizer 304, and therefore the following effects can be obtained. (a) It is no longer necessary for the worker to attach or remove the jig for pushing the steel pipe 100, which reduces the worker's time and effort. This makes it possible to automate the work of driving the steel pipe. (b) Since the jig is no longer necessary, there is no risk of the jig falling, ensuring the safety of the worker. [Explanation of symbols]
[0074] 10 Socket section 12 Slope 13 Bottom 14 Bottom 15 Side 16 End 17 Step 18 areas 18a area 18b area 18c area 20 Steel pipe body 30 Insertion part 32 Ring 33 Outer surface 34 End face 35 End face 36 End 37 areas 38 areas 38a area 75 Natural ground 75a Face 80 Drifter 83 Shank Sleeve r1 radius of curvature r2 radius of curvature 100 steel pipe 100-1 steel pipe 100-2 Steel pipe 101 Step 200 Jackhammer 300 Guide Shell Set 301 Guide Shell 301 Centralizer 302 Drifter 303 Rod 304 Centralizer 305 Subcentralizer 314 Centralizer body 320 Pressing member 321 Volts 400 Support device 510 Boom 520 Fixation device 530 wheels 540 Body 551 Charging Cage
Claims
1. A construction method for reinforcing the ground of a tunnel wall using a steel pipe, comprising: a rock drill equipped with a drifter that applies impact force to a connected rod, a guide shell that supports the drifter movably in the axial direction of the rod, a centralizer fixed to the tip side of the guide shell, a sub-centralizer that is installed on the guide shell at a distance from the centralizer in the axial direction so as to be movably in the axial direction, and a support device that supports the guide shell movably in the axial direction, mounting a first steel pipe on the centralizer, connecting the rear end of the rod inserted into the steel pipe to the drifter, and advancing the drifter on the guide shell while applying an impact force to the rod, thereby drilling a hole in the natural ground with a bit attached to the tip of the rod and inserting the first steel pipe into the formed hole; a step of stopping the forward movement of the drifter, retracting the guide shell, and moving the drifter backward on the guide shell in a state in which the rear end of the first steel pipe protrudes to the outside through the hole in the natural ground; a step of mounting a second steel pipe having a socket portion at a tip end thereof, the socket portion having an outer circumferential radius larger than the radius of a steel pipe body, on the centralizer and the sub-centralizer of the guide shell such that the socket portion is located closer to the tip end of the guide shell than the centralizer; a step of advancing the guide shell in the axial direction, so that the centralizer pushes against a step between the outer periphery of the socket portion of the second steel pipe and the steel pipe body, thereby advancing the second steel pipe, and connecting the inner periphery of the socket portion at the front end of the second steel pipe to the outer periphery of the rear end of the first steel pipe by covering the inner periphery of the socket portion at the front end of the second steel pipe; A construction method characterized by having:
2. 2. The construction method according to claim 1, wherein the centralizer has a U-shaped opening, a curved surface at a bottom of the U-shaped opening has a predetermined radius of curvature, and the curved surface at the bottom contacts a side surface of the steel pipe to support the steel pipe, A construction method characterized in that the radius of curvature of the curved surface of the bottom is smaller than the radius of the outer periphery of the socket portion of the second steel pipe and larger than the radius of the outer periphery of the steel pipe body excluding the socket portion.
3. 3. The installation method according to claim 2, wherein the centralizer has a main body having a U-shaped opening and a pressing member fixed to the main body, This construction method is characterized in that the pressing member has a structure that narrows the radius of curvature of the bottom of the U-shaped opening of the main body to a radius smaller than the radius of the outer periphery of the socket portion of the second steel pipe and larger than the radius of the outer periphery of the steel pipe main body.
4. The construction method according to claim 1, wherein two or more first grooves are provided in a circumferential direction on an inner circumferential surface of the socket portion of the second steel pipe, At the rear end of the first steel pipe, two or more second grooves are provided in the circumferential direction on the outer circumferential surface, and a C-shaped ring with a portion cut out is arranged in each of the second grooves so that at least a portion of the ring protrudes from the outer circumferential surface of the steel pipe; A construction method characterized in that, in the connecting step, the ring of the first steel pipe engages with a first groove of a socket portion of the second steel pipe.
5. A guide shell set is supported on a support device of a rock drill so as to be movable in the axial direction, the guide shell including a drifter that applies a striking force to a connected rod, a guide shell that supports the drifter so as to be movable in the axial direction, a centralizer fixed to a tip side on the guide shell, and a sub-centralizer that is spaced apart from the centralizer in the axial direction on the guide shell so as to be movable in the axial direction, the centralizer and the sub-centralizer each have a U-shaped opening, and when a steel pipe is placed in the U-shaped opening, a curved surface at the bottom of the U-shaped opening comes into contact with a side surface of the steel pipe to support the steel pipe, and the steel pipe has a socket portion at a tip end, the outer periphery of which has a radius larger than a radius of a steel pipe body, The curved surface of the bottom of the U-shaped opening of the centralizer has a predetermined radius of curvature, the radius of curvature being smaller than the radius of the outer periphery of the socket portion of the steel pipe and larger than the radius of the outer periphery of the steel pipe body; said centralizer, when the guide shell is moved forward in the axial direction by the support device, pushes against a step on the outer periphery between the socket portion and the steel pipe body of the steel pipe mounted so that the socket portion is located closer to the tip of the guide shell than the centralizer, thereby moving the steel pipe mounted on the centralizer forward and connecting the steel pipe mounted on the centralizer to the rear end of another steel pipe that has been previously buried in the ground and has its rear end protruding from the ground.
6. 6. The guide shell set according to claim 5, wherein the centralizer includes a body having a U-shaped opening and a pressing member fixed to the body, The pressing member narrows the radius of curvature of the bottom of the U-shaped opening of the main body to a radius of curvature smaller than the radius of the outer periphery of the socket portion of the steel pipe and larger than the radius of the outer periphery of the steel pipe main body.
7. 7. A guide shell set as described in claim 6, wherein the pressing member is a plate-shaped member of a predetermined thickness fixed to the front surface of the main body, and has a U-shaped opening with a radius of curvature smaller than the radius of the outer periphery of the socket portion of the steel pipe and larger than the radius of the outer periphery of the steel pipe main body.
8. A centralizer fixed to a guide shell supported axially movably on a support device of a rock drill, It has a U-shaped opening, When a steel pipe is placed in the U-shaped opening, the curved surface at the bottom of the U-shaped opening contacts the side surface of the steel pipe to support the steel pipe, and the steel pipe is provided at its tip with a socket portion whose outer circumferential radius is larger than the radius of the steel pipe body, The curved surface of the bottom of the U-shaped opening of the centralizer has a predetermined radius of curvature, the radius of curvature being smaller than the radius of the outer periphery of the socket portion of the steel pipe and larger than the radius of the outer periphery of the steel pipe body; The centralizer is characterized in that, when the guide shell is moved forward in the axial direction by the support device, the centralizer pushes against a step on the outer periphery between the socket portion and the steel pipe body of the steel pipe mounted so that the socket portion is located closer to the tip of the guide shell than the centralizer, thereby moving the steel pipe mounted on the centralizer forward and connecting the steel pipe mounted on the centralizer to the rear end of another steel pipe that has been previously buried in the ground and has its rear end protruding from the ground.
9. 9. The centralizer of claim 8, comprising a body having a U-shaped opening and a pressing member fixed to the body, A centralizer characterized in that the pressing member narrows the radius of curvature of the bottom of the U-shaped opening of the main body to a radius of curvature smaller than the radius of the outer periphery of the socket portion of the steel pipe and larger than the radius of the outer periphery of the steel pipe main body.
10. 10. The centralizer according to claim 9, wherein the pressing member is a plate-like member having a predetermined thickness fixed to the front surface of the main body, and has a U-shaped opening with a radius of curvature smaller than the radius of the outer periphery of the socket portion of the steel pipe and larger than the radius of the outer periphery of the steel pipe main body.
11. A pressing member fixed to a centralizer fixed to a guide shell supported by a support device of a rock drill, The centralizer has a U-shaped opening that supports a steel pipe, and the steel pipe has a socket portion at a tip portion, the socket portion having an outer circumferential radius larger than the radius of the steel pipe body, The pressing member is characterized in that it has a structure that narrows the radius of curvature of the bottom of the U-shaped opening of the centralizer to a radius of curvature that is smaller than the radius of the outer periphery of the socket portion of the steel pipe and larger than the radius of the outer periphery of the steel pipe body.
12. 12. The pressing member according to claim 11, which is a plate-like member of a predetermined thickness fixed to the front surface of the main body, and which has a U-shaped opening with a radius of curvature smaller than the radius of the outer periphery of the socket portion of the steel pipe and larger than the radius of the outer periphery of the steel pipe main body.
13. A set of the steel pipe and the pressing member for use in the construction method according to claim 3.
Citation Information
Patent Citations
Steel pipe for excision and tunnel excavation method using the same
JP2019203362A
Steel pipe with connecting mechanism using ring, connection body thereof, and construction method
JP2022100190A