Natural ground improvement material injection system
The soil improvement material injection system electronically measures and calculates the liquid level of ground improvement material, automating the recording process to improve efficiency and reduce manual labor in daily reports.
Patent Information
- Application Number
- JP2023077820
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-05-10
- Publication Date
- 2024-11-21
AI Technical Summary
The manual calculation and recording of the remaining amount of ground improvement material in tanks during injection processes are time-consuming and inefficient.
A soil improvement material injection system that measures the liquid level of the ground improvement material in tanks electronically, calculates the amount automatically, and records the start and end amounts in a daily injection report.
Automatically determines the amount of ground improvement material, eliminating manual calculations and facilitating easy entry of remaining amounts in daily reports, thereby enhancing efficiency.
Smart Images

Figure 2024162378000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to an injection system for ground improvement material used in a pre-excavation ground reinforcement method during tunnel excavation. [Background technology]
[0002] When excavating a tunnel, a method known as long steel pipe forepiling is known in which long steel pipes are cast into the ground surrounding the tunnel in front of it and ground improvement material is injected from within the long steel pipes to improve the ground.
[0003] For example, in the method shown in Patent Document 1, multiple steel pipes of about 3 m each are connected to cast multiple long steel pipes of about 10 to 20 m around the periphery of a tunnel, and after casting the long steel pipes, a ground improvement material is injected into each long steel pipe. The ground improvement material injected into the long steel pipe penetrates into gaps and cracks in the ground around the long steel pipe through multiple discharge holes provided on the periphery of the long steel pipe, and hardens to reinforce the ground. As this ground improvement material, a urethane-based ground improvement material is widely used in terms of improvement effect and workability. In many cases, two liquids are mixed together and used, and the injector for the urethane-based ground improvement material is equipped with two tanks for supplying the urethane-based ground improvement material. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] Japanese Patent Application Publication No. 08-121073 Summary of the Invention [Problem to be solved by the invention]
[0005] The amounts of the two liquids used at the start and end of injection (i.e. the remaining amounts in the tank) are to be entered in the daily injection report, and conventionally, the distance from the top of the tank 104 to the liquid level was measured with a ruler 106 or the like (see Figure 6), the amount of ground improvement material in the tank was calculated from the tank's volume, and this calculated amount of ground improvement material was entered in the daily injection report. These tasks were done manually, and were time-consuming, as the amount of ground improvement material had to be calculated and entered by hand on a printed daily injection report.
[0006] The present invention has been developed in consideration of the above-mentioned problems, and aims to provide a ground improvement material injection system that allows the remaining tank amount at the start and end of injection to be easily recorded in the daily injection report. [Means for solving the problem]
[0007] The present invention is as follows. 1. A construction method in which multiple long steel pipes are cast into unexcavated ground in a tunnel, and ground improvement material is allowed to penetrate through the inner space of the long steel pipes and into cracks in the surrounding ground from discharge holes provided on the outer periphery of the long steel pipes to reinforce the ground, characterized in that the amount of ground improvement material in the tank is calculated by measuring the liquid level of the ground improvement material poured into a tank that supplies the ground improvement material to an injection machine that injects the ground improvement material in the form of electronic data, and the amount of ground improvement material at the start and end of injection is stored. 2. The ground improvement material injection system described in 1 above, characterized in that it comprises a measurement unit that measures the liquid level of the ground improvement material poured into the tank in the form of electronic data, a calculation unit that calculates the amount of the ground improvement material in the tank based on the liquid level, and a memory unit that stores the amount of the ground improvement material at the start of injection and at the end of injection. 3. The ground improvement material injection system according to claim 2, further comprising an entry unit for entering the amount of said ground improvement material stored in said memory unit into a daily injection report. Effect of the Invention
[0008] According to the present invention, by measuring the liquid level of the ground improvement agent poured into a tank that supplies the ground improvement agent in the form of electronic data, it is possible to automatically calculate the amount of ground improvement agent in the tank, thereby eliminating the need for the conventional manual calculation work. Furthermore, by recording the amount of ground improvement material in the tank when injection begins and when injection ends, the remaining amount in the tank at the start and end of injection can be easily entered in the daily injection report. [Brief description of the drawings]
[0009] The present invention will be further described in the following detailed description by way of non-limiting examples of exemplary embodiments according to the invention and with reference to the several drawings mentioned, in which like reference numerals refer to like elements throughout the several views of the drawings. [Figure 1] FIG. 2 is a schematic diagram of an injector of an injection system according to an embodiment. [Diagram 2] FIG. 2 is a schematic diagram of the tank of the injection machine. [Diagram 3] FIG. 2 is a block diagram of the control unit of the injection machine. [Figure 4] FIG. 13 is an explanatory diagram for explaining a daily injection report according to the embodiment. [Diagram 5] 1A and 1B are explanatory diagrams for explaining a natural ground reinforcement method according to an embodiment, in which (a) shows a cross section substantially perpendicular to the axial direction of a tunnel, and (b) shows a vertical section along the axial direction of the tunnel. [Figure 6] FIG. 1 is an explanatory diagram for explaining a conventional method for measuring a liquid level in a tank. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0010] The matters shown herein are illustrative and are intended to exemplify the embodiments of the present invention, and are described for the purpose of providing what is believed to be the most effective and easily understandable explanation of the principles and conceptual features of the present invention. In this respect, it is not intended to show structural details of the present invention beyond the extent necessary for a fundamental understanding of the present invention, and the description in conjunction with the drawings will make it clear to those skilled in the art how some forms of the present invention can be actually embodied.
[0011] Hereinafter, the present invention will be described in detail with reference to the drawings and embodiments.
[0012] The ground improvement material injection system of this embodiment is used for a preliminary ground reinforcement method during tunnel excavation. The preliminary ground reinforcement method is a method in which, as shown in Fig. 5, multiple long steel pipes 32 (17 in Fig. 5(b)) are cast into the unexcavated ground of a tunnel 31, and the ground improvement material is allowed to penetrate into cracks in the surrounding ground from discharge holes (not shown) provided on the outer periphery of the long steel pipes 32 through the inner space of the long steel pipes 32, thereby reinforcing the ground.
[0013] In the advance ground reinforcement method, the ground improvement material stored in tanks 4a, 4b is supplied to an injection machine 1 (see FIG. 1), which then injects the ground improvement material into steel pipes 32. As the ground improvement material, for example, a urethane-based foaming resin such as silica resin is used. In this case, two types of liquid A and B are mixed and injected into the ground while foaming, and then hardened, improving the ground around the tunnel. However, instead of the urethane-based ground improvement material, an inorganic ground improvement material (for example, cement-based, water glass-based, etc.) may also be used. For construction management purposes, the multiple steel pipes 32 are assigned injection numbers in the order of their arrangement along the arch section.
[0014] As shown in FIG. 1, the injection machine 1 is composed of a pump unit 2 that pumps out ground improvement material, a control unit 3 to which the pump unit 2 is connected, and tanks 4A and 4B that supply ground improvement material to the pump unit 2.
[0015] The pump unit 2 has multiple pairs of injection pumps 5A, 5B (three pairs in FIG. 1) for pumping and mixing two types of liquid A and liquid B for each steel pipe 32. A tank 4A into which liquid A is fed is connected to the supply port of the injection pump 5A for liquid A, and a tank 4B into which liquid B is fed is connected to the supply port of the injection pump 5B for liquid B.
[0016] A laser sensor is installed at the upper ends of the tanks 4A and 4B as the sensor 15 for measuring the distance to the liquid level of the ground improvement material 35 (see Figure 2), and is connected to the control unit 3. However, the sensor 15 for measuring the liquid level of the ground improvement material 35 is not limited to a laser sensor, and any known technology can be used as long as it can measure the liquid level as data that can be processed by calculation, such as a level sensor using a float.
[0017] The control unit 3 is equipped with a management screen 7 that displays the injection amount and injection pressure during injection, and a control panel 8 that starts and stops the pumps 5A and 5B and adjusts the flow rate. The control unit 3 further includes an input section 9 such as a touch panel for inputting the set values for the injection amount and injection pressure prior to injection, and a processing section 10 that performs a calculation process of the remaining tank amount, which will be described later.
[0018] As shown in Fig. 3, the control unit 3 (specifically the control panel 8) is provided with a measurement switch 11 that instructs the processing unit 10 to measure the distance to the liquid level of the ground improvement material in the tanks 4A, 4B, and a memory switch 12 that instructs the processing unit 10 to store the calculated remaining tank amount. The control unit 3 is further provided with a total button 13 that instructs the processing unit 10 to input the stored remaining tank amount into the daily injection report 27 (see Fig. 4), etc. Note that the switches 11, 12 and button 13 may be formed by the input unit 9, or may be provided in a portion of the injection machine 1 other than the control unit 3.
[0019] The processing unit 10 is equipped with a measuring unit 21 that measures the liquid level of the ground improvement agent put into the tanks 4A, 4B in the form of electronic data, a calculation unit 22 that calculates the amount of ground improvement agent in the tanks 4A, 4B (i.e., the remaining amount in the tank) from the liquid level, and a memory unit 23 that stores the remaining amount in the tank when injection starts and when injection ends. The processing unit 10 further includes an entry unit 24 that enters the remaining amount in the tank stored in the memory unit 23 into an injection daily report 27.
[0020] The processing by the processing unit 10 may be realized by either hardware or software, and can be preferably configured by incorporating a microcontroller (microcomputer) having a CPU, memory device (ROM, RAM, etc.), input / output circuits, etc., as a core, with peripheral circuits such as an input / output interface.
[0021] Next, the effects of the injection system for ground improvement material configured as above will be explained. Before starting injection of the ground improvement material, the measurement switch 11 on the control panel 8 of the injection machine 1 is turned on, and the liquid level of the ground improvement material in the two tanks 4A, 4B is measured by the measurement unit 21. The measured data is sent to the calculation unit 22. The calculation unit 22 calculates the volume of each of the ground improvement materials in each of the tanks 4A, 4B, and further calculates the weight by multiplying it by the specific gravity of each of the ground improvement materials. The calculated weight of each of the ground improvement materials is displayed on the management screen 7. Next, the memory switch 12 on the control panel 8 is turned on, and the weight of each of the ground improvement materials displayed on the management screen 7 is stored in the memory unit 23. This value measured before the start of injection is called the remaining amount before injection C1.
[0022] Once the required amount of ground improvement material has been injected, the measurement switch 11 on the control panel 8 of the injection machine 1 is turned on again, and the liquid height of the ground improvement material in the two tanks 4A, 4B is measured by the measurement unit 21. The measured data is sent to the calculation unit 22. The calculation unit 22 calculates the volume of each of the ground improvement materials in each of the tanks 4A, 4B, and then calculates the weight by multiplying this by the specific gravity of each material. The calculated weight of each of the ground improvement materials is displayed on the management screen 7. Next, the memory switch 12 on the control panel 8 is turned on, and the weight of each of the ground improvement materials displayed on the management screen 7 is stored in the memory unit 23. The numerical value measured after this injection is called the remaining amount after injection C2.
[0023] The memory unit 23 stores both the remaining amount C1 before injection and the remaining amount C2 after injection. By pressing the total button 13 on the control panel 8 of the injection machine 1, the remaining amount C1 before injection and the remaining amount C2 after injection of each tank 4A, 4B, along with the injection amount and injection pressure for each injection point (i.e., steel pipe 32) and the total injection amount for the cross section, are input into the daily injection report 27 (see Figure 4). The daily injection report 27 (i.e., image data) is available via wired or wireless communication or a recording medium such as a USB memory.
[0024] In addition, in Fig. 4, the input amount D in the daily injection report 27 is the amount of chemical solution put into the tanks 4A and 4B. Since the chemical solution is added in one-gallon cans (18 kg or 20 kg, etc.), the input amount D is the number of one-gallon cans added times the number of cans filled. Therefore, the input amount D is calculated manually by counting the number of empty one-gallon cans. Furthermore, the usage amount E in the daily injection report 27 is calculated by the remaining amount before injection C1 + input amount D - remaining amount after injection C2.
[0025] As described above, according to the ground improvement agent injection system of this embodiment, the amount of ground improvement agent in the tanks 4A and 4B is calculated by measuring the liquid level of the ground improvement agent in the tanks 4A and 4B that supply the ground improvement agent to the injection machine 1 that injects the ground improvement agent in the form of electronic data (specifically, by measuring using the sensor 15), and the amount of ground improvement agent in the tanks 4A and 4B is stored when injection is started and when injection is completed. In this way, the amount of ground improvement agent in the tanks 4A and 4B can be automatically calculated by measuring the liquid level of the ground improvement agent in the tanks 4A and 4B that supply the ground improvement agent in the form of electronic data, and the calculation work by manual calculation in the conventional method can be omitted. Furthermore, the amount of ground improvement agent in the tanks 4A and 4B when injection is started and when injection is completed is stored, and the tank remaining amount at the start and end of injection is automatically entered in the injection daily report 27 (specifically, the remaining amount C1 before injection and the remaining amount C2 after injection are automatically input into the image data of the injection daily report 27), thereby eliminating the trouble of transcribing to the conventional injection daily report.
[0026] Furthermore, in this embodiment, by operating the memory switch 12 (memory instruction operation unit), the remaining tank amount can be reliably stored in the memory unit 23 when injection is started (specifically, before injection is started) and when injection is completed (specifically, after injection is completed).
[0027] The present invention is not limited to the above embodiment, and various modifications may be made within the scope of the present invention depending on the purpose and application. That is, in the above embodiment, the tank remaining amount is automatically entered into the daily filling report 27 by the entry unit 24, but the present invention is not limited to this. For example, the entry unit 24 may not be provided, and the worker may enter the tank remaining amount displayed on the management screen 7 into the daily filling report (for example, by handwriting the amount into the printed daily filling report, or by inputting data into the image data of the daily filling report).
[0028] Furthermore, in the above embodiment, an injection system having a processing unit 10 in the control unit 3 of the injection machine 1 was exemplified, but this is not limited to this, and for example, an injection system having a processing unit 10 in a terminal that can be connected to the control unit 3 of the injection machine 1 (e.g., a mobile terminal such as a smartphone, a personal computer, etc.) may be adopted.
[0029] The present invention is not limited to the above-described embodiments, and various modifications and variations are possible within the scope of the claims of the present invention. [Industrial Applicability]
[0030] The present invention is widely used as a technology for injecting ground improvement materials in advance ground reinforcement methods during tunnel excavation. [Explanation of symbols]
[0031] 1; injection machine, 4A, 4B; tank, 10; processing unit, 21; measurement unit, 22; calculation unit, 23; memory unit, 24; entry unit, 27; daily injection report, 31; tunnel, 32; steel pipe, 35; ground improvement material.
Claims
1. A construction method in which a number of long steel pipes are cast into unexcavated ground in a tunnel, and ground improvement material is allowed to penetrate through the inner space of the long steel pipes and into cracks in the surrounding ground from discharge holes provided on the outer periphery of the long steel pipes, thereby reinforcing the ground, characterized in that the amount of ground improvement material in the tank is calculated by measuring the liquid level of the ground improvement material poured into a tank that supplies the ground improvement material to an injection machine that injects the ground improvement material in the form of electronic data, and the amount of ground improvement material at the start and end of injection is stored.
2. The ground improvement material injection system described in claim 1, characterized in that it comprises a measurement unit that measures the liquid level of the ground improvement material poured into the tank in the form of electronic data, a calculation unit that calculates the amount of the ground improvement material in the tank based on the liquid level, and a memory unit that stores the amount of the ground improvement material at the start of injection and at the end of injection.
3. 3. The ground improvement material injection system according to claim 2, further comprising an entry unit for entering the amount of said ground improvement material stored in said memory unit into a daily injection report.
Citation Information
Patent Citations
Prior reinforcement method by steel pipe, and device by use thereof
JP1996121073A