Sale plan creation system, sale plan creation method, and program

The sales plan creation system addresses the challenge of creating flexible electricity sales plans for power generation BGs by using predictive power generation data and supplementary forecasts to align with demand BG settings, enhancing operational efficiency and reducing imbalances.

JP2024163499APending Publication Date: 2024-11-22KK TOSHIBA +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
JP2023079184
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-12
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

Power generation BGs face challenges in creating flexible sales plans that accommodate varying settings and submission deadlines of demand BGs, including business hours, business days, and holidays, necessitating a system to easily create electricity sales plans based on future power generation forecasts.

Method used

A sales plan creation system that includes an acquisition unit for predicting future power generation, a setting unit for determining generation timing and creation time, and a plan creation unit for generating sales plans tailored to specific demand BGs, utilizing supplementary power generation forecasts for unpredictable periods.

Benefits of technology

Enables the creation of flexible sales plans that align with demand BG requirements, reducing operational complexity and potential imbalances by incorporating accurate power generation predictions and supplementary forecasts.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024163499000001_ABST
    Figure 2024163499000001_ABST
Patent Text Reader

Abstract

To easily create a sale plan of electric power on the basis of a future power generation amount prediction result.SOLUTION: A sale plan creation system comprises: an acquisition unit which acquires a power generation amount prediction result during a future prescribed period, about a target power generation facility; a setting unit which sets creation timing, and a creation target period, about a power generation plan related to the power generation facility and a sale plan of electric power; and a plan creation unit which creates the power generation plan and the sale plan about the creation target period, on the basis of the power generation amount prediction result, at the creation timing.SELECTED DRAWING: Figure 5
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a sales plan creation system, a sales plan creation method, and a program. [Background technology]

[0002] In recent years, balancing groups (hereinafter referred to as "BG") have been used as a group of businesses that settle imbalances (differences between plans and actual results) in electricity trading. BGs include power generation BGs operated by power generation businesses and demand BGs operated by consumers (e.g., retail electricity businesses), and are operated by power generation businesses, retail electricity businesses, specified wholesale supply businesses (so-called aggregators), etc. For the sake of simplicity, hereafter, the operators of power generation BGs and demand BGs will be referred to simply as power generation BGs and demand BGs, respectively.

[0003] Since the power generation BG works to balance the amount of electricity simultaneously across the board, it can reduce the risk of imbalances caused by non-regulated power sources such as solar and wind power. In addition, the power generation BG can sell the electricity it generates to the Japan Electric Power Exchange (JEPX) or to the demand BG, which is its counterparty.

[0004] In addition, power generation BGs are required to submit daily power generation and sales plans to the Organization for Cross-regional Coordination of Transmission Operators (OCCTO).

[0005] In addition, the demand BG that purchases electricity from the generation BG in bilateral transactions must reflect the "amount of electricity purchased from the generation BG in bilateral transactions and the source of electricity" in the demand procurement plan that it submits to OCCTO on a daily basis. For this reason, the demand BG creates a demand procurement plan after receiving the electricity sales plan (hereinafter simply referred to as the "sales plan") from the source generation BG to the demand BG.

[0006] In addition, for renewable energy power generation businesses and specified wholesale suppliers (so-called aggregators) that submit power generation and sales plans to OCCTO on behalf of renewable energy power generation businesses, it is important to create power generation and sales plans for non-regulated power sources such as solar and wind power based on highly accurate power generation forecasts in order to increase profits.

[0007] When forecasting power generation, highly accurate results can be obtained by forecasting as close as possible to the time of the target forecast. In addition, businesses that do not have the technology to forecast power generation may contract with other companies that have power generation forecasting systems to receive power generation forecast results. Summary of the Invention [Problem to be solved by the invention]

[0008] Currently, power generation BG operators create power generation plans based on future power generation forecast results, and also create and provide sales plans for each of the multiple demand BGs with which they trade. However, each demand BG has different settings for business hours, business days, holidays (especially long holidays), etc. For this reason, power generation BGs are required to be able to flexibly respond to the timing and period for which sales plans for bilateral transactions are created according to the convenience of the demand BGs for creating demand procurement plans.

[0009] Therefore, an object of an embodiment of the present invention is to provide a sales plan creation system, a sales plan creation method, and a program that can easily create an electricity sales plan based on the results of predicting future power generation. [Means for solving the problem]

[0010] The sales plan creation system of the embodiment includes an acquisition unit that acquires power generation forecast results for a specified future period for a target power generation facility, a setting unit that sets the creation timing and the target period for the creation of a power generation plan and a power sales plan for the power generation facility, and a plan creation unit that creates the power generation plan and the sales plan for the target period at the creation timing based on the power generation forecast results. [Brief description of the drawings]

[0011] [Figure 1] Figure 1 is a flowchart outlining the daily operations of the generation BG and the demand BG. [Diagram 2] FIG. 2 is a block diagram illustrating a functional configuration of the information processing apparatus according to the embodiment. [Diagram 3] FIG. 3 is an explanatory diagram of an example of creating a long-term sales plan before a long holiday or the like in the embodiment. [Figure 4] FIG. 4 is a diagram illustrating an example of a format of sales plan data in the embodiment. [Diagram 5] FIG. 5 is a flowchart illustrating a process performed by the information processing apparatus according to the embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0012] A sales plan creation system, a sales plan creation method, and a program according to an embodiment will be described below with reference to the drawings.

[0013] First, an overview of the daily operations of the power generation BG 100 and the demand BG 200 will be described with reference to Fig. 1. Fig. 1 is a flowchart showing an overview of the daily operations of the power generation BG 100 and the demand BG 200.

[0014] The power generation BG100 is a BG consisting of multiple power generation businesses. The power generation business has, for example, regulated power sources (power generation facilities using thermal, nuclear, hydroelectric, etc.) and non-regulated power sources (power generation facilities using solar, wind, etc.) as power generation facilities. Among these, non-regulated power sources are mainly power generation facilities using renewable energy such as solar and wind. They may further have storage batteries.

[0015] The demand BG 200 is a BG provided by a consumer (which may include a retail electricity supplier). The consumer includes, for example, a load and a storage battery. The load is a device or equipment that consumes power.

[0016] A bilateral contract for power trading is concluded between the power generation BG 100 and the demand BG 200. The power generation BG 100 can sell the generated power to the JEPX (market trading in the spot market, the hourly market, etc.) or to the demand BG, which is the counterparty of the bilateral trade.

[0017] In step S101, the power generation BG 100 transmits a sales plan for the next day, which is created based on the power generation amount forecast result, to the demand BG 200 by email or the like, for example, at around 9:00 on the day before the power delivery date. Usually, only data related to the amount sold to the demand BG 200 is transmitted to the demand BG 200, and data on the amount traded in the market and the amount sold to other demand BGs is not included. Therefore, the sales plan created by the time of transmitting data to the demand BG 200 may be a partial one that does not include the amount sold in the market and the amount traded with other demand BGs. In this case, the power generation BG 100 creates a plan that reflects other sales before submitting the sales power generation sales plan to OCCTO.

[0018] Next, in step S102, the power generation BG 100, as an obligation of the power generation business operator, submits to OCCTO, for example, by noon on the day before the power delivery date, a power generation sales plan for the next day created based on the power generation amount forecast result. The power generation sales plan submitted to OCCTO includes all the sales to the demand BG 200 (all of them if sales to multiple demand BGs), sales in market transactions, etc.

[0019] After step S101, in step S103, the demand BG200, as an obligation of the consumer, submits a demand procurement plan created based on the sales plan received from the power generation BG100 to the OCCTO.

[0020] In the conventional technology, the operator of the power generation BG 100 creates a power generation plan based on the future power generation forecast result, and creates and provides a power sales plan for each of the multiple demand BGs of the bilateral trading counterparty. However, the settings of the operation of demand procurement plan submission, business hours, business days, holidays (especially long holidays), etc. are different for each demand BG. The setting of the operation of demand procurement plan submission refers to the determination of when the plan submission is basically performed in the demand BG so that the deadline for plan submission is surely met (for example, 9:00 a.m. on the day of the deadline, 5:00 p.m. on the previous day, etc.), and is generally set. Then, the demand BG takes into consideration the work time to reflect the amount of power purchased in bilateral trading in the demand procurement plan. On the other hand, since the power generation forecast and demand forecast are generally more accurate when they are closer to the actual supply and demand time, it is not preferable to set the plan creation unnecessarily early with respect to the deadline for plan submission.

[0021] Taking the above into consideration, the demand BG and the power generation BG decide the timing of sending the sales plan to the demand BG 200 (basic conditions are generally determined in advance in a bilateral trading contract, etc.). For this reason, the power generation BG needs to be able to create and send sales plans for each demand BG with which it is trading, and to be able to handle the timing and period for which they are created.

[0022] Therefore, hereinafter, a technique that enables a sales plan for each demand BG 200 to be easily created based on the results of prediction of future power generation amount will be described.

[0023] 2 is a block diagram showing a functional configuration of the information processing device 1 according to the embodiment. The information processing device 1 is, for example, a PC (Personal Computer) used by an operator of the power generation BG 100. The information processing device 1 includes a storage unit 2, an input unit 3, a display unit 4, a communication unit 5, and a processing unit 6.

[0024] The storage unit 2 is realized by, for example, a random access memory (RAM), a read only memory (ROM), a solid state drive (SSD), a hard disk drive (HDD), etc., and stores various information. The storage unit 2 stores, for example, weather data 21, power generation performance 22, bilateral transaction information 23, power generation plan 24, sales plan 25, power generation sales plan 26, sales plan creation schedule 27, etc.

[0025] The weather data 21 is, for example, data relating to future weather (for example, up to one week from the present) acquired from an external organization.

[0026] The power generation performance 22 is data on the past power generation performance of the power generation facility.

[0027] The bilateral transaction information 23 includes information such as the trading partner code, name (trading partner name), and amount of electricity requested to be sold for each demand BG 200 of the bilateral transaction partner (for example, X kWh to be sold to demand BG "A", and the entire amount of electricity generated by power plant Z to be sold to demand BG "B").

[0028] The power generation plan 24 is data of a power generation plan created by the plan creating unit 64 .

[0029] The sales plan 25 is data of a sales plan for each demand BG 200 created by the plan creation unit 64 .

[0030] The power generation and sales plan 26 is data of a power generation and sales plan prepared by the plan preparation unit 64 for submission to the OCCTO.

[0031] The sales plan creation schedule 27 is data of the sales plan creation schedule set by the setting unit 63. Note that under the current system, the deadline for the demand BG 200 to submit a demand procurement plan to OCCTO is noon on the day before actual supply and demand. In addition, OCCTO accepts changes to the plan up until GC (gate close: one hour before actual supply and demand). Therefore, the deadline for actually submitting the demand procurement plan (including plan changes) to OCCTO differs for each demand BG 200. Therefore, the sales plan creation schedule 27 is data in which the timing of sales plan creation, the period for creation, the transmission timing, etc. are set for each demand BG 200.

[0032] The input unit 3 is a means for an operator to input various operations, and is, for example, a mouse, a keyboard, a touch panel, or the like.

[0033] The display unit 4 is a means for displaying information, and is, for example, an LCD (Liquid Crystal Display), a touch panel, or the like.

[0034] The communication unit 5 is a communication interface for communicating with an external device.

[0035] The processing unit 6 is realized by, for example, a CPU (Central Processing Unit) and executes various calculation processes. The processing unit 6 includes, for example, an acquisition unit 61, a power generation amount prediction unit 62, a setting unit 63, a plan creation unit 64, a complementation processing unit 65, a display control unit 66, and a transmission control unit 67 as functional units.

[0036] The acquisition unit 61 acquires various information from an external device, the storage unit 2, each unit 62 to 65, etc. The acquisition unit 61 acquires, for example, from the power generation amount prediction unit 62, a power generation amount prediction result for a predetermined future period (for example, up to one week from the present) for the target power generation facility.

[0037] The power generation amount prediction unit 62 predicts the amount of power generated by the power generation facility based on the weather data 21, the power generation record 22, etc. However, there is a limit to the period during which the power generation amount can be predicted by the power generation amount prediction unit 62. Basically, a more accurate prediction result can be obtained by making a prediction closer to the prediction target date.

[0038] Therefore, the period for which the power generation amount can be predicted by the power generation amount prediction unit 62 is, for example, up to about one week in the future. Therefore, when creating a sales plan for a long period (for example, about 10 days) before a long holiday, the period for which the sales plan is created may exceed the period for which the power generation amount can be predicted. Countermeasures for this will be described later.

[0039] In the present embodiment, the information processing device 1 includes the power generation amount prediction unit 62, but is not limited to this. For example, the information processing device 1 may not include the power generation amount prediction unit 62 and may acquire the power generation amount prediction result from an external system.

[0040] The setting unit 63 sets the creation timing, creation period, transmission timing, etc., for the power generation plan related to the power generation facility and the power sales plan based on, for example, an operator's operation input using the input unit 3. In this case, the creation timing can be set to any date and time, and also a day of the week can be set. Also, the creation period can be set to any period starting from the current day.

[0041] In addition, the transmission timing can be set to any timing, for example, 9:00 on the day before actual supply and demand, 15:00 on the day before, 9:00 on the day before, or any time on the day before a long holiday.

[0042] Specifically, for example, in the case of a long consecutive holiday, a sales plan must be created until the end of the consecutive holiday by the day before the holiday and transmitted to the demand BG 200. Therefore, for example, the timing of creation is determined based on the business days and business hours of the power generation BG 100. Also, the creation target period and transmission timing are determined based on the business days and business hours of the demand BG 200.

[0043] The setting unit 63 may automatically set the creation timing, the creation target period, and the transmission timing of the sales plan to the demand BG based on, for example, business day information of the power generation BG 100 and business day information of the demand BG 200 registered in the storage unit 2. This can reduce the burden on the operator or eliminate the need for operator work.

[0044] When the creation timing set by the setting unit 63 arrives, the plan creation unit 64 creates a power generation plan and a sales plan for the creation target period based on the power generation amount prediction result by the power generation amount prediction unit 62. In this case, the plan creation unit 64 creates a sales plan for each demand BG200 by referring to the bilateral transaction information 23.

[0045] In addition, when the complementary processing unit 65 described later creates complementary power generation forecast information, the plan creation unit 64 creates a power generation plan and a sales plan for the target period based on the power generation forecast result and the complementary power generation forecast information at the time of creation.

[0046] Furthermore, when creating a sales plan, the plan creation unit 64 sets the amount of energy to be sold for a time period in which the amount of energy to be sold could not be calculated to 0. For example, when power generation is stopped for regular inspection at the power generation facility, when the power generation facility system goes down, or when the power generation amount prediction result cannot be obtained, the amount of energy to be sold in the sales plan for the corresponding time period (for example, all 48 frames, assuming one frame is 30 minutes) is set to 0. Since missing data is not permitted for any of the 48 frames in a power generation sales plan or a demand procurement plan, this is done as an alternative measure when the amount of power generation cannot be reasonably estimated.

[0047] In addition, the plan creation unit 64 creates a market trading plan for selling electricity in a market such as JEPX. For example, the market trading plan is created by subtracting the amount of electricity sold in bilateral transactions from the amount of electricity generated and setting the amount as the subject of market trading.

[0048] In addition, the plan creation unit 64 creates the power generation and sales plan 26 to be submitted to the OCCTO.

[0049] When the period for which the sales plan is to be created includes a period beyond a specified period corresponding to the power generation forecast result, the complementary processing unit 65 creates complementary power generation forecast information to replace the power generation forecast result for the period beyond the specified period.

[0050] Specifically, for example, if the specified period corresponding to the power generation prediction result is up to one week from now, the complementation processing unit 65 creates complementary power generation prediction information to replace the power generation prediction result for the period beyond that by the following method.

[0051] Use the value from the previous week. - Using regular weather forecasts (weekly, monthly, etc.) as a reference, use the actual power generation values ​​for days with similar conditions. Use the data from the power generation forecast results for the day with the most similar conditions. · Use operator input information.

[0052] Furthermore, the complementation processing unit 65 may adopt data created by the above method multiplied by a coefficient (such as 0.8) to avoid imbalances due to insufficient power generation. This coefficient may be set based on data on past predicted power generation values ​​and actual power generation values ​​for the target power generation facility. The lower the coefficient, the lower the risk of insufficient imbalances occurring, but an excessively low coefficient increases the disadvantage of reduced revenue from selling electricity. Therefore, the coefficient can be set based on data on the difference between past predicted power generation values ​​and actual power generation values. For example, a simulation is performed in which the coefficient is multiplied by the past predicted power generation values ​​to set the power generation plan values, and the coefficient that minimizes the sum of the imbalance fee and the revenue reduction is selected.

[0053] In addition, when a storage battery is later installed in a non-regulated power source (for example, a power generation facility using solar or wind power), it is possible to create corrected actual power generation data through a simulation based on the power generation forecast and actual power generation data from past data, assuming that a storage battery had been installed in the past and imbalance suppression operation could be performed, and to set a coefficient based on the power generation forecast and corrected actual power generation data.

[0054] The display control unit 66 displays various information on the display unit 4. For example, when the target period for creation includes a period beyond a predetermined period corresponding to the power generation amount prediction result, the display control unit 66 displays on the display unit 4 a request for the operator to create a power generation plan and a sales plan for a period beyond the predetermined period. In this case, the processing by the complementation processing unit 65 is not required.

[0055] The transmission control unit 67 transmits various information to the outside. For example, the transmission control unit 67 transmits a sales plan created by the plan creation unit 64 to a preset demand BG200. As described above, the sales plan transmitted to the demand BG200 usually includes data on sales to the demand BG200 (sales in bilateral transactions in each of the 48 frames) and does not include unnecessary data (for example, sales to other demand BG200 or sales in market transactions).

[0056] In addition, after the transmission control unit 67 transmits the sales plan to the demand BG 200, if the acquisition unit 61 acquires a new power generation amount forecast result for the creation target period, the plan creation unit 64 creates a new power generation plan and a new sales plan for the creation target period based on the new power generation amount forecast result. In this case, the transmission control unit 67 transmits the new sales plan to the demand BG 200.

[0057] As mentioned above, after submitting a demand procurement plan to OCCTO, the demand BG 200 can change the plan up to GC. Therefore, depending on the demand BG 200, even after submitting a demand procurement plan to OCCTO, there may be cases where the demand BG 200 wishes to obtain a new sales plan for plan changes. For example, if the operator of the power generation BG 100 and the demand BG 200 is the same, there is a high possibility that this plan change will be implemented.

[0058] Next, an example of creating a long-term sales plan before a long holiday etc. will be described with reference to Fig. 3. Fig. 3 is an explanatory diagram relating to an example of creating a long-term sales plan before a long holiday etc. in the embodiment.

[0059] The conditions are as follows: <Demand BG200> Demand BG200 usually submits a demand procurement plan to OCCTO two days before the day before (for example, submitting a demand procurement plan for 12 / 31 on 12 / 29). However, due to the New Year's holiday, demand BG200 requests power generation BG100 to transmit a sales plan for bilateral transactions from 1 / 1 to 1 / 10 on 12 / 30. In other words, the period for which the sales plan is created is as shown by the arrow A in Figure 3.

[0060] <Energy generation forecast for BG100> The power generation forecast for the current day is made at 8:00 a.m. Also, it is possible to make forecasts up to four days in advance. In other words, if December 30th is used as the base date, the power generation forecastable period is as shown by the arrow B in Figure 3.

[0061] In this case, the period (symbol A) for which the sales plan is to be created is a period (symbol C) other than the period (symbol B) for which the amount of power generation is predictable. For this period (symbol C) for which the amount of power generation is predictable, the complementary processing unit 65 creates complementary power generation prediction information in place of the power generation prediction result.

[0062] In this manner, the plan creation unit 64 can create power generation plans and sales plans for the entire period (symbol A) for which the sales plans are to be created.

[0063] Next, an example of the format of the sales plan data will be described with reference to Fig. 4. Fig. 4 is a diagram showing an example of the format of the sales plan data in the embodiment.

[0064] The sales plan data is created, for example, in a csv file and is sent by email from the power generation BG 100 to the demand BG 200. The contents of each line of the sales plan data are as follows:

[0065] The first line is the revision (REV.) number. The second line is the creation date and time. The third line is the date of power delivery.

[0066] The fourth line is the demand BG customer code. The fifth line is the demand BG customer name. The sixth line is the power generation BG customer code. The seventh line is the name of the power generation BG business partner. The tenth line and onwards show the planned amount of electricity to be sold for each period (time period).

[0067] Next, a process performed by the information processing device 1 will be described with reference to Fig. 5. Fig. 5 is a flowchart showing a process performed by the information processing device 1 according to the embodiment.

[0068] In step S1, the power generation amount prediction unit 62 predicts the amount of power generated by the power generation facility for a predetermined future period based on the meteorological data 21, the power generation record 22, and the like.

[0069] Next, in step S2, the plan creation unit 64 reads out the sales plan creation schedule 27. The sales plan creation schedule 27 includes information such as the creation timing, creation target period, and transmission timing of a sales plan for each demand BG 200. In the following, for simplicity, the description will be given mainly focusing on one demand BG 200.

[0070] When the creation timing set for demand BG200 arrives, in step S3, the plan creation unit 64 determines whether or not there are power generation forecast results for the entire creation period, and if Yes, proceeds to step S5, and if No, proceeds to step S4.

[0071] In step S4, the complementary processing unit 65 creates complementary power generation forecast information to replace the power generation forecast result for a period for which there is no power generation forecast result (power generation forecast unpredictable period (symbol C) in FIG. 3) during the period for which the sales plan is created (symbol A in FIG. 3). Then, the process proceeds to step S5.

[0072] In step S5, the plan creation unit 64 reads out the bilateral transaction information 23. This makes it possible to recognize the amount of electricity sold to the demand BG200.

[0073] Next, in step S6, the plan creation unit 64 creates a power generation plan for the target period based on the power generation forecast result (and the complementary power generation forecast information, if available), and creates a sales plan for demand BG200 in accordance with the bilateral transaction information 23.

[0074] Next, when the transmission timing set for the demand BG 200 arrives, the transmission control unit 67 transmits the sales plan data (FIG. 4) to the demand BG 200 in step S7.

[0075] Next, in step S8, the plan creation unit 64 creates a market trading plan by subtracting the sales volume in bilateral trading from the power generation volume as the subject of market trading.

[0076] Next, in step S9, the plan creation unit 64 creates the power generation and sales plan 26 to be submitted to the OCCTO.

[0077] Next, in step S10, the transmission control unit 67 transmits the power generation and sales plan 26 created in step S9 to the OCCTO.

[0078] The processing of steps S8 to S10 is executed after the creation of sales plans for all demands BG200 of the bilateral trading partner for the target time period is completed.

[0079] In this way, according to the information processing device 1 of this embodiment, it is possible to easily create an electricity sales plan for each demand BG200 of a trading partner based on the future power generation forecast results, the set creation timing, the target creation period, etc.

[0080] Even if the target period for which the power generation amount prediction is impossible (symbol C in FIG. 3) is included in the period for which the power generation amount prediction is impossible, the power sales plan can be created by using the supplementary power generation amount prediction information created by the supplementary processing unit 65.

[0081] In addition, if the period to be created includes a period during which power generation cannot be predicted (symbol C in Figure 3), a display is displayed on the display unit 4 requesting the operator to create a power generation plan and a sales plan for that period, so that the operator can create the power generation plan and the sales plan.

[0082] Furthermore, by registering business day information of the power generation BG 100 and business day information of the demand BG 200 in advance in the storage unit 2, the timing of creating the sales plan, the period for which the sales plan is created, the timing of transmission, and the like can be automatically set.

[0083] Also, for example, when the operator of the power generation BG 100 and the demand BG 200 is the same, after transmitting the sales plan to the demand BG 200, a new sales plan may be created and transmitted to the demand BG 200. In this way, the demand BG 200 can change the demand procurement plan based on the new sales plan and submit the changed demand procurement plan to OCCTO before GC. This can be expected to have the effect of reducing imbalances.

[0084] In addition, when creating a sales plan, for time periods in which the amount of energy to be sold could not be calculated, the amount of energy to be sold can be set to 0 in accordance with the actual situation.

[0085] The program executed by the information processing device 1 of this embodiment may be provided by being recorded in an installable or executable format on a computer-readable recording medium such as a CD-ROM, a flexible disk (FD), a CD-R, or a DVD (Digital Versatile Disk).

[0086] The program may be stored on a computer connected to a network such as the Internet and provided by being downloaded via the network.The program may be provided or distributed via a network such as the Internet.The program may be provided by being pre-installed in a ROM or the like.

[0087] Although an embodiment of the present invention has been described, this embodiment is presented as an example and is not intended to limit the scope of the invention. This novel embodiment can be implemented in various other forms, and various omissions, substitutions, and modifications can be made without departing from the spirit of the invention. This embodiment and its modifications are included in the scope and spirit of the invention, and are included in the invention and its equivalents described in the claims.

[0088] For example, the power generation BG 100 may utilize a storage battery to create an optimal sales plan by utilizing storage battery control and a predicted sales price of electricity.

[0089] In addition, in the flowchart of FIG. 5, the order of the processes may be changed as appropriate within the scope of not causing any problems, for example, by performing step S7 after step S10. [Explanation of symbols]

[0090] 1...information processing device, 2...storage unit, 3...input unit, 4...display unit, 5...communication unit, 6...processing unit, 21...weather data, 22...power generation performance, 23...bilateral transaction information, 24...power generation plan, 25...sales plan, 26...power generation sales plan, 27...sales plan creation schedule, 61...acquisition unit, 62...power generation forecasting unit, 63...setting unit, 64...plan creation unit, 65...complementation processing unit, 66...display control unit, 67...transmission control unit, 100...power generation BG, 200...demand BG

Claims

1. An acquisition unit that acquires a power generation amount prediction result for a predetermined future period for a target power generation facility; A setting unit that sets a creation timing and a creation target period for a power generation plan and a power sales plan for the power generation facility; a plan creation unit that creates the power generation plan and the sales plan for the target creation period based on the power generation amount prediction result at the creation timing.

2. When the generation target period includes a period beyond the predetermined period corresponding to the power generation amount prediction result, A complementary processing unit that creates complementary power generation prediction information that replaces the power generation prediction result for a period beyond the predetermined period, The sales plan creation system according to claim 1 , wherein the plan creation unit creates the power generation plan and the sales plan for the creation target period based on the power generation forecast result and the supplementary power generation forecast information at the creation timing.

3. When the generation target period includes a period beyond the predetermined period corresponding to the power generation amount prediction result, The sales plan creation system according to claim 1 , further comprising a display control unit that displays on the display unit a message requesting an operator to create the power generation plan and the sales plan for a period beyond the predetermined period.

4. The power generation facility is a power generation BG (Balancing Group) power generation facility, The sales plan creation system according to claim 1 , further comprising a transmission control unit that transmits the sales plan created by the plan creation unit to a preset demand BG.

5. The sales plan creation system of claim 4, wherein the setting unit sets the creation timing, the creation target period, and the timing of transmitting the sales plan to the demand BG based on business day information of the power generation BG and business day information of the demand BG registered in the memory unit.

6. When the acquisition unit acquires a new power generation amount forecast result for the generation target period, the plan creation unit creates a new power generation plan and a new sales plan for the creation target period based on the new power generation amount prediction result; The sales plan creation system according to claim 4 , wherein the transmission control unit transmits the new sales plan to the demand BG.

7. The sales plan creation system according to claim 1 , wherein the plan creation unit, when creating the sales plan, sets the amount of energy to be sold to zero for a time period in which the amount of energy to be sold could not be calculated.

8. An acquisition step of acquiring a power generation amount forecast result for a predetermined future period for a target power generation facility; A setting step of setting a creation timing and a creation period for a power generation plan and a power sales plan for the power generation facility; a plan creation step of creating the power generation plan and the sales plan for the target period based on the power generation amount forecast result at the creation timing.

9. Computer, An acquisition unit that acquires a power generation amount prediction result for a predetermined future period for a target power generation facility; A setting unit that sets a creation timing and a creation target period for a power generation plan and a power sales plan for the power generation facility; a program for causing the program to function as a plan creation unit that creates the power generation plan and the sales plan for the target creation period based on the power generation amount prediction result at the creation timing.