AI Technical Summary

Technical Problem

Conventional waste treatment equipment is difficult to manage remotely, particularly in terms of temperature monitoring and abnormal temperature handling.

Method used

An upcycle plant system with a heating means and a server that can communicate freely with the plant, transmitting temperature and other operational information for remote control and monitoring, including sensors for weight, volume, humidity, vibration, and metal detection.

Benefits of technology

Enables remote management of plant temperatures, identifies abnormal conditions promptly, and optimizes operations by controlling plant functions from a distance, improving efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024167585000001_ABST
    Figure 2024167585000001_ABST
Patent Text Reader

Abstract

To provide an upcycle plant system that enables an administrator to control a temperature of a plant even in a remote area away from the plant.SOLUTION: An upcycle plant system 100 comprises a plant 110, a temperature sensor that is provided in the plant 110, and a server 120 capable of communicating with the plant 110. During an operation of the plant 110, temperature information is transmitted to the server 120 from the plant 110, and the server 120 controls the operation of the plant 110.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an upcycle plant system and a program for controlling a plant having a heating means for heating a raw material to generate something more valuable than the original raw material. [Background technology]

[0002] Conventionally, a waste treatment device is known in which a tapered section is formed at one end of a furnace body, the inner diameter of which decreases as it approaches the opening, and a spiral blade is provided on the inner wall surface of this tapered section so as to feed the material to be treated from the opening of the furnace body in the axial direction inward when the furnace body rotates in the forward direction, and to feed the material to be treated from the inner axial direction of the furnace body toward the opening when the furnace body rotates in the reverse direction (for example, Patent Document 1). [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Patent No. 7246839 (see especially paragraph 0022) Summary of the Invention [Problem to be solved by the invention]

[0004] However, the conventional waste treatment devices described above were configured to be operated by a standalone waste treatment device, and therefore required monitoring near the waste treatment device, making it difficult to manage them from a remote location away from the waste treatment device. In particular, there has been a problem in that it is difficult to respond when an abnormality in temperature occurs during operation of the waste treatment device.

[0005] Therefore, the present invention is intended to solve the problems of the prior art as described above, that is, the object of the present invention is to provide an upcycle plant system and a program therefor that enable an administrator to manage the temperature of a plant even if he or she is in a remote location away from the plant. [Means for solving the problem]

[0006] The invention of claim 1 is an upcycling plant system that controls a plant having a heating means for heating raw materials to produce something more valuable than the original raw materials, and comprises the plant, a temperature sensor provided in the plant, and a server capable of communicating with the plant, wherein temperature information is transmitted from the plant to the server during operation of the plant, and the server is capable of freely controlling the operation of the plant, thereby solving the above-mentioned problem.

[0007] The invention of claim 2 further solves the above-mentioned problem by having, in addition to the configuration of the upcycling plant system described in claim 1, a plurality of the plants, each plant having identification information, and the server communicating with each plant based on the identification information.

[0008] The invention of claim 3 further solves the above-mentioned problem by configuring the upcycling plant system as described in claim 2, in addition to the above-mentioned problem, in such a manner that the plant has a weight measuring sensor or a volume measuring sensor, and weight information obtained by the weight measuring sensor or volume information obtained by the volume measuring sensor is transmitted from the plant to a server.

[0009] The invention of claim 4 further solves the above-mentioned problem by configuring the upcycling plant system as described in claim 3, in addition to the configuration of the plant, which has a humidity sensor and humidity information obtained by the humidity sensor is transmitted from the plant to a server.

[0010] The invention of claim 5 further solves the above-mentioned problem by configuring the upcycling plant system as described in claim 4, in addition to the above-mentioned problem, in such a manner that the plant has a vibration sensor, vibration level information obtained by the vibration sensor is transmitted from the plant to a server, and when the vibration level information reaches or exceeds a predetermined value, the server determines that it is time for maintenance of the plant and notifies a predetermined contact point of the identification information and that the vibration level is above a predetermined value.

[0011] The invention of claim 6 further solves the above-mentioned problem by configuring the upcycling plant system as described in claim 5, in addition to the above-mentioned problem, in such a manner that the plant has a metal detection sensor and a buzzer in the path in front of the plant's inlet, and when the metal detection sensor detects metal, the buzzer sounds and information that metal has been detected is sent from the plant to a server.

[0012] The invention of claim 7 further solves the above-mentioned problems by configuring the upcycling plant system according to any one of claims 3 to 6, in addition to the configuration of the upcycling plant system described in any one of claims 3 to 6, in which the plant has a raw material type selection means, the server has a timer function, and type selection information by the type selection means and weight information by a weight measurement sensor are transmitted from the plant to the server, and based on these, the server determines the heating time and controls the heating means of the plant.

[0013] The invention of claim 8 further solves the above-mentioned problem by configuring the upcycling plant system according to any one of claims 2 to 6, in addition to the configuration of the plant, which has a measuring means for measuring the weight or volume of the raw materials before they are input, and measurement result information by the measuring means is transmitted from the plant to a server, and the server calculates waiting time information for the raw materials awaiting processing based on the operating status information of each plant, the processing capacity information of each plant, and the measurement result information, and transmits information to a specified terminal instructing the transportation of raw materials from a plant with a long waiting time to a plant with a short waiting time based on the previously registered location information of each plant and the calculated waiting time information for the raw materials awaiting processing at each plant.

[0014] The invention of claim 9 is a program for an upcycling plant system that controls a plant having a heating means for heating raw materials to produce something more valuable than the original raw materials, and solves the above-mentioned problem by having a transmission step in which, during operation of the plant, the plant transmits temperature information obtained by a temperature sensor installed in the plant to a server, a determination step in which the temperature information received from the plant is above a predetermined threshold value, and a stop control step in which the server controls to stop operation of the plant when it is determined that the temperature information is above the predetermined threshold value. Effect of the Invention

[0015] Since the upcycle plant system of the present invention has a heating means for heating the raw materials, it can not only generate something more valuable than the original raw materials, but also has the following unique effects.

[0016] According to the upcycling plant system of the invention of claim 1, temperature information is transmitted from the plant to the server, allowing an administrator to manage the temperature of the plant even if he or she is in a remote location far from the plant. If there is a temperature abnormality, the temperature information is sent to the server, so that an administrator can be notified of the temperature abnormality and take action immediately.

[0017] According to the upcycling plant system of the invention of claim 2, in addition to the effect of the invention of claim 1, information on the status of all plants is sent to the server on a plant-by-plant basis, so that the manager can grasp the status of all plants. If a temperature abnormality occurs, the identification information is sent to the server, enabling the manager to know in which plant the temperature abnormality occurred.

[0018] According to the upcycle plant system of the invention of claim 3, in addition to the effect of the invention of claim 2, weight information and volume information of the input raw material before heating are recorded in the server database, and weight information and volume information of the bio-coal generated by heating are recorded in the server database, so that the ratio of the weight of the raw material to the weight of the waste can be calculated. It is also possible to calculate the costs that would have been incurred if the work had been requested from a waste disposal company. Furthermore, it is possible to calculate the degree of decarbonization effect achieved compared to existing municipal waste disposal methods in the plant's installation area.

[0019] According to the upcycling plant system of the invention of claim 4, in addition to the effect of the invention of claim 3, humidity information is transmitted from the plant to the server, allowing the manager to manage the humidity of the plant.

[0020] According to the upcycling plant system of the invention of claim 5, in addition to the effect of the invention of claim 4, information identifying the plant and information indicating that maintenance is required are notified to the designated contact, who is a maintenance person, so that the maintenance person can immediately go to the plant and make repairs as necessary.

[0021] According to the upcycling plant system of the invention of claim 6, in addition to the effect of the invention of claim 5, when a user inputs raw waste material into the plant, if metal is mixed in, a buzzer will sound to alert the user, allowing the user to stop inputting the waste material and remove the metal. In addition, information about metal contamination is recorded in the server database, allowing managers to identify plants with high levels of metal contamination.

[0022] According to the upcycle plant system of the invention of claim 7, in addition to the effects of any one of the inventions of claims 3 to 6, the amount of energy to be added is determined according to the type and amount of waste, so that the quality of the generated bio-coal can be stabilized.

[0023] According to the upcycling plant system of the invention of claim 8, in addition to the effects of any one of the inventions of claims 2 to 6, instructions to transport raw waste materials are sent to a specified terminal, taking into account the plant's processing capacity and operating rate. Therefore, for example, waste materials can be transported from a plant with a long waiting time in a nearby area to a plant with a short waiting time, thereby sharing waste processing time.

[0024] According to the program for the upcycling plant system of the invention of claim 9, similar to the effect achieved by the invention of claim 1, temperature information is transmitted from the plant to the server, so that an administrator can manage the temperature of the plant even if he or she is in a remote location far from the plant. If there is a temperature abnormality, the temperature information is sent to the server, so that an administrator can be notified of the temperature abnormality and take action immediately. [Brief description of the drawings]

[0025] [Figure 1] 1 is a diagram showing the concept of an upcycle plant system according to an embodiment of the present invention. [Diagram 2] FIG. 2 is a chart showing an example of the operation of the upcycle plant system according to the embodiment of the present invention. [Diagram 3] 1 is a conceptual diagram showing an example of a plant of an upcycle plant system according to an embodiment of the present invention. [Figure 4] FIG. 1 is a conceptual diagram showing an example of cooperation between multiple plants in an upcycle plant system according to an embodiment of the present invention through raw material transportation. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0026] The upcycling plant system of the present invention comprises a plant, a temperature sensor installed in the plant, and a server capable of communicating with the plant, and temperature information is transmitted from the plant to the server while the plant is operating, and the server is configured to be able to freely control the operation of the plant. This allows a manager to manage the temperature of the plant even if he is in a remote location away from the plant, and if an abnormality in temperature occurs, the manager can know the abnormality and take prompt action. As long as this is the case, the specific implementation of the system can be any one. In addition, the program for the upcycling plant system of the present invention includes a transmission step in which, during operation of the plant, the plant transmits temperature information obtained by a temperature sensor installed in the plant to a server, a determination step in which the temperature information received from the plant is above a predetermined threshold value or not, and a stop control step in which the server controls to stop operation of the plant when it is determined that the temperature information is above the predetermined threshold value, thereby allowing a manager to manage the temperature of the plant even if he is in a remote location away from the plant, and if an abnormality in temperature occurs, the manager can know the abnormality in temperature and respond quickly, so long as the specific embodiment is any one.

[0027] For example, the plant may be any type of plant, such as a carbonizer that produces bio-coal, a bio-coke production device, a methane fermenter, or a subcritical water treatment device, that uses waste as a raw material, has a heating means for heating the raw material, and produces something more valuable than the original raw material. Also, the server may be a single server or multiple servers on a cloud. EXAMPLES

[0028] An upcycle plant system 100 according to an embodiment of the present invention will now be described with reference to FIGS. 1 to 4. FIG. Here, Figure 1 is a diagram showing the concept of an upcycle plant system 100 which is an embodiment of the present invention, Figure 2 is a chart showing an example of the operation of the upcycle plant system 100 which is an embodiment of the present invention, Figure 3 is a conceptual diagram showing an example of a plant 110 of the upcycle plant system 100 which is an embodiment of the present invention, and Figure 4 is a conceptual diagram showing an example of cooperation between multiple plants 110 of the upcycle plant system 100 which is an embodiment of the present invention through the transportation of raw materials.

[0029] An upcycle plant system 100 which is an embodiment of the present invention is also referred to as an upcycle plant utilization system with an IoT (Internet of Things) sensor, and as shown in FIG. 1, comprises a plant 110, a temperature sensor 114 (see FIG. 3) which is an example of an IoT sensor provided in the plant 110, and a server 120 which can communicate freely with the plant 110. Among these, the plant 110 has a heating means for heating the raw material waste WT, and produces something (such as bio-coal BC) that is more valuable than the original raw material waste WT. The size of the plant 110 is relatively small, and is small enough to be installed, for example, on the grounds of a hospital, a food manufacturing plant, or an automobile parts manufacturing plant. In this embodiment, temperature information is transmitted from the plant 110 to the server 120 during operation of the plant 110 . The server 120 is configured to be able to freely control the operation of the plant 110 .

[0030] This causes temperature information to be transmitted from the plant 110 to the server 120. As a result, the manager can manage the temperature of the plant 110 even if he or she is in a remote location far from the plant 110. If there is a temperature abnormality, the temperature information is sent to the server 120. As a result, the manager can be made aware of the temperature abnormality and take immediate action. The upcycle plant system 100 may have a configuration including a plurality of plants 110, or may have a configuration including only one plant 110.

[0031] Next, an example of the operation of the upcycle plant system 100 will be described in more detail. As shown in FIG. 2, in step S1, as an operation determination step, the plant 110 determines whether or not the plant 110 has started operation. The start of operation may be performed by operating a switch such as an operation start button on an operation panel installed in the plant 110, or may be performed by the server 120 sending command information to start operation to the plant 110. If it is determined that operation has started, the process proceeds to step S2. On the other hand, if it is determined that operation has not started yet, step S1 is repeated.

[0032] In step S2, as a measurement step, the plant 110 obtains temperature information by the temperature sensor 114 provided in the plant 110. For example, as shown in FIG. 3, a plant 110 is a carbonization furnace including a furnace body 111, an inlet 111a provided in the furnace body 111, and a discharge outlet 111b provided in the furnace body 111. The plant 110, which is a carbonization furnace, has, as an example, an electric heating means, and is configured to heat the raw material waste WT that is input (transported) into the inside of the furnace body 111 using the heating means to produce bio-coal BC from the raw material waste WT. Furthermore, the heating means is provided so as to control the temperature inside the furnace body 111 to fall within a predetermined temperature range that is a lower temperature range than a predetermined threshold value, which will be described later.

[0033] The waste WT, which is the raw material, is charged (carried) into the inside of the furnace body 111 through the charge port 111a, and is heated to become bio-coal BC inside, which is then discharged from the discharge port 111b. The raw materials, waste WT and bio-coal BC, are transported inside the furnace body 111 in a transport direction from an inlet 111a to an outlet 111b by a transport means 112, such as a conveyor, for example, but the configuration may not include the transport means 112. The conveying means 112 is not limited to a conveyor, and may be configured to push out the material using a screw, or may be configured to convey the material by applying vibration.

[0034] The temperature sensor 114 is provided inside the furnace body 111, for example. The temperature sensor 114 may be installed anywhere inside the furnace body 111, but it is particularly preferable that the temperature sensor 114 be installed at the same height as the waste WT, which is the raw material. The reason for this is that by arranging it at the same height as the raw material waste WT under conditions where temperature differences are likely to occur between high and low positions inside the furnace body 111 due to thermal convection, it is possible to capture the chemical reactions (chemical changes) that occur when bio-coal BC is produced from the raw material waste WT.

[0035] In step S3, as a transmission step, the plant 110 transmits the temperature information obtained by the temperature sensor 114 to the server 120. In step S4, as a temperature information determination step, the server 120 determines whether the temperature information received from the plant 110 is equal to or greater than a predetermined threshold value that is set in advance. If it is determined that the difference is equal to or greater than the predetermined threshold, the process proceeds to step S5. On the other hand, if it is determined that the difference is less than the predetermined threshold, the process proceeds to step S7.

[0036] In step S5, as a shutdown control step, the server 120 transmits command information to the plant 110 to shut down the operation of the plant 110. In step S6, which is an example of a notification step, server 120 notifies a predetermined terminal, that there is an abnormality in temperature, the terminal being a manager terminal, which is a preset predetermined terminal. As a result, as described above, if there is a temperature abnormality, the temperature information is transmitted to the server 120. As a result, the manager can be made aware of the temperature abnormality and take immediate action.

[0037] In step S7, as an operation end determination step, the server 120 determines whether or not the operation control of the plant 110 has ended based on a timer function that has been started from the start of the operation. If it is determined that the operation has ended, the sequence ends, and if it is determined that the operation has not yet ended, the process returns to step S2. When the operation is terminated, the bio-coal BC is cooled and discharged using a sprinkler 113 before the operation is terminated.

[0038] Furthermore, in this embodiment, the upcycle plant system 100 includes a plurality of plants 110 as shown in FIG. Each plant 110 has identification information. The identification information may be, for example, a unique serial number or other information, or may be location information obtained by a GPS function of each plant 110 . The server 120 is then configured to communicate with each plant 110 based on the identification information.

[0039] This allows information about the status of all plants 110 to be sent to the server 120 on a plant-by-plant basis. As a result, the manager can grasp the status of all plants 110. If there is a temperature abnormality, the identification information is sent to the server 120. As a result, the manager can know in which plant 110 the temperature abnormality has occurred.

[0040] In this embodiment, as shown in FIG. 3, the plant 110 has a first weight measuring sensor 115A and a second weight measuring sensor 115B as an example of a weight measuring sensor or a volume measuring sensor. Here, upstream of the inlet 111a of the plant 110 in the conveying direction, a pre-inlet path 111c is provided. A first weight measuring sensor 115A is provided on the inlet front path 111c.

[0041] On the other hand, downstream of the discharge port 111b of the plant 110 in the transport direction, a post-discharge port path 111d is provided. A second weight measuring sensor 115B is provided in the post-discharge-port path 111d. Furthermore, weight information from the first weight measuring sensor 115A and weight information from the second weight measuring sensor 115B, which are examples of weight information or volume information, are configured to be transmitted from the plant 110 to the server 120.

[0042] As a result, weight information and volume information of the waste WT, which is the raw material before heating, is recorded in the database of the server 120, and weight information and volume information of the bio-coal BC generated by heating are recorded in the database of the server 120. As a result, the ratio of the weight of garbage to the total weight of garbage can be calculated. It is also possible to calculate the costs that would have been incurred if the work had been requested from a waste disposal company. Furthermore, it is possible to calculate the degree of decarbonization effect achieved compared to existing municipal waste disposal methods in the plant's installation area. Although the configuration in which the first weight measuring sensor 115A and the second weight measuring sensor 115B are provided has been described as an example, a configuration in which a first volume measuring sensor and a second volume measuring sensor are provided instead of these may also be used. The volume measurement sensor may be, for example, one that uses a camera to capture an object in three dimensions and calculates (estimates) the volume.

[0043] Additionally, in this embodiment, the plant 110 includes a humidity sensor 116 . The humidity sensor 116 , like the temperature sensor 114 , is provided inside the furnace body 111 , for example. The humidity sensor 116 may be installed anywhere inside the furnace body 111, but it is particularly preferable that the humidity sensor 116 be installed at the same height as the waste WT, which is the raw material. The reason for this is that by placing it at the same height as the raw material waste WT, it is possible to capture the chemical reactions (chemical changes) that occur when bio-coal BC is produced from the raw material waste WT.

[0044] The humidity information obtained by the humidity sensor 116 is configured to be transmitted from the plant 110 to the server 120. This causes humidity information to be transmitted from the plant 110 to the server 120. As a result, the manager can control the humidity of the plant 110. For example, if the plant 110 is a bio-coke manufacturing apparatus, humidity control of the raw material waste WT affects the quality of the product bio-coke, and it is therefore necessary to control the heating temperature and heating time.

[0045] In this embodiment, the plant 110 also includes a vibration sensor 117 . The vibration sensor 117 is disposed, for example, near a motor that is a drive source for a conveyor that is the transport means 112 . Then, vibration level information obtained by the vibration sensor 117 is transmitted from the plant 110 to the server 120 . The server 120 determines whether the received vibration level information is equal to or greater than a predetermined value. When the vibration level information reaches or exceeds a predetermined value, the server 120 determines that it is time for maintenance of the plant 110.

[0046] Furthermore, the server 120 is configured to notify the identification information of the plant 110 and information indicating that the vibration level is equal to or greater than a predetermined value to a terminal of a maintenance contractor, which is an example of a predetermined contact point. As a result, information identifying the plant 110 and information indicating that maintenance is required are notified to the maintenance person who is the specified contact point. As a result, maintenance personnel can quickly rush to the plant 110 to make repairs as needed.

[0047] Furthermore, in this embodiment, the plant 110 has a first metal detection sensor 118A and a first buzzer (not shown) on the inlet front path 111c. When the first metal detection sensor 118A detects a metal, the first buzzer is sounded and information indicating that a metal has been detected is transmitted from the plant 110 to the server 120.

[0048] With this, when the user inputs the waste WT as the raw material into the plant 110, if metal is mixed in, the first buzzer will sound to notify the user. As a result, the user can interrupt the input of waste WT and remove the metal. In addition, information indicating that metal has been mixed in is recorded in the database of server 120. As a result, the manager can identify plants 110 with high levels of metal contamination.

[0049] A second metal detection sensor 118B and a second buzzer (not shown) may be provided in post-discharge-outlet path 111d. When the second metal detection sensor 118B detects metal, it sounds a second buzzer and transmits information to the effect that metal has been detected from the plant 110 to the server 120. As a result, if metal is mixed into the bio-coal BC, which is the product passing through the post-discharge outlet path 111d, a buzzer sound from the second buzzer will be generated to notify the user. As a result, users can selectively remove bio-coal BC containing metals. In addition, information that metals were mixed into the product bio-coal BC is recorded in the database of the server 120. As a result, the manager can identify plants 110 whose products contain a large amount of metal. Then, for example, an inspection can be performed to check whether a part such as a screw from the plant 110 has been mixed in.

[0050] In this embodiment, the plant 110 also has an image recognition sensor 119 as an example of a type selection means for the waste WT that is the raw material. For example, the image recognition sensor 119 recognizes the image of the raw material waste WT, and recognizes the type of material, such as plastic waste WT, cloth waste WT, etc. Furthermore, the server 120 has a timer function. Type selection information recognized by the image recognition sensor 119, which is a type selection means, and weight information obtained by the first weight measuring sensor 115A are transmitted from the plant 110 to the server 120. Based on these, the server 120 determines the heating time and controls the heating means of the plant 110 using a timer function.

[0051] This determines the amount of energy to be added depending on the type and amount of waste WT. As a result, the quality of the produced bio-coal BC can be stabilized. Although the configuration using the image recognition sensor 119 as an example of a means for selecting the type of raw waste WT has been described, as an example of a means for selecting the type of raw waste WT, a configuration may also be adopted in which buttons for each type of raw waste WT are provided on an operation panel, and type selection information is transmitted from the plant 110 to the server 120 by the button operation of a user who inputs the raw waste WT.

[0052] Furthermore, in this embodiment, the plant 110 has a first weight measuring sensor 115A as an example of a measuring means for measuring the weight or volume of the waste WT, which is the raw material before it is input. Weight information, which is measurement result information by the first weight measuring sensor 115A, is transmitted from the plant 110 to the server 120. Then, the server 120 calculates waiting time information for the waste WT, which is a material waiting to be processed, based on the operating status information of each plant 110, the processing capacity information of each plant 110, and the weight information, which is the measurement result information. Furthermore, the server 120 is configured to transmit information to a transporter's terminal, which is an example of a specified terminal, instructing the transport of the raw material waste WT from the plant 110 with the long waiting time to the plant 110 with the short waiting time, based on the location information of each plant 110 registered in advance and the calculated waiting time information for the waste WT, which is the raw material waiting to be processed at each plant 110.

[0053] As a result, as shown in FIG. 4, an instruction to transport the raw waste WT taking into consideration the processing capacity and operation rate of the plant 110 is sent to the terminal of the transporter, which is an example of a predetermined terminal. As a result, for example, waste WT can be transported by a transport vehicle TR such as a truck from a plant 110 with a long waiting time in a neighboring area to a plant 110 with a short waiting time, thereby allowing for the sharing of waste treatment.

[0054] Furthermore, a business operator that does not have the plant 110 may communicate with the server 120 using a terminal. Specifically, when a certain amount of waste WT has accumulated on the business's premises, the business uses its terminal to transmit to the server 120 information indicating that a certain amount of waste WT has accumulated and that the business would like to request collection, together with location information or identification information. Here, the trigger for the business operator's terminal to send a collection request to the server 120 may be an operation by the business operator, or it may be when an ultrasonic sensor or weight sensor installed in the waste WT storage area detects that the amount of waste WT has reached a predetermined amount. The location information may be current location information obtained by GPS or may be location information such as a previously registered location. The server 120 may identify the location of the business operator by checking against location information such as a pre-registered address based on the received identification information.

[0055] When the business operator's terminal transmits the information to the server 120, the server 120 selects a plant 110 with a relatively short waiting time from among plants 110 in the neighboring area based on the location of the business operator (business establishment) that has made the request to pick up the waste WT. At the same time, the server 120 transmits information that a pickup request has been made, information on the amount of waste WT to be picked up, the location information of the business operator, and the location information of a plant 110 selected as a destination with a relatively short waiting time as a request to the terminal of a transporter in the nearby area. The transporter's terminal may be mounted on the transport vehicle TR or installed at the transporter's headquarters. When an operation to accept the request is performed on the transporter's terminal, the transporter's terminal transmits information to the server 120 to the effect that the request is being accepted. The server 120 then transmits to the business operator's terminal information that the pickup request has been accepted and that the transport company will come to pick up the item.

[0056] This allows waste WT from a business operator that does not have a plant 110 to be transported to a nearby plant 110 where the waiting time is relatively short. As a result, a waste WT transportation and treatment network can be formed using the upcycle plant system 100 having multiple small plants 110. In other words, not only businesses that have plants 110, but also businesses that do not have plants 110 can participate in upcycling to convert waste WT into something valuable and thereby participate in addressing environmental issues.

[0057] In the above-described embodiment, the plant 110 is a carbonization furnace that produces bio-coal BC, but the present invention is not limited to this. The plant 110 may be a bio-coke production plant, a methane fermenter, or a sub-critical water treatment plant. Of these, the bio-coke manufacturing apparatus is equipped with a cylinder in which the raw material waste WT is filled, a piston that pressurizes the waste WT filled in the cylinder from above, a heating means for heating the pressurized waste WT, and a cooling means for cooling the heated waste WT, and produces bio-coke from the waste WT. The methane fermentation tank has a fermentation tank and hydrolyzes the raw material waste WT, causing acid fermentation, and then produces hydrogen, acetic acid, and methane, thereby producing methane gas, which is a biogas, from the waste WT. Furthermore, the subcritical water treatment device is equipped with a pressure vessel, a boiler, and a motor-driven agitator, and generates useful substances by adding steam from the boiler to the waste WT (raw material), which is a biomass resource, placed in the pressure vessel and stirring it.

[0058] The upcycle plant system 100, which is an embodiment of the present invention obtained in this manner, comprises a plant 110, a temperature sensor 114 provided in the plant 110, and a server 120 capable of communicating with the plant 110. Temperature information is transmitted from the plant 110 to the server 120 while the plant 110 is in operation, and the server 120 is configured to be able to freely control the operation of the plant 110. This allows an administrator to manage the temperature of the plant 110 even if he or she is in a remote location far from the plant 110, and if an abnormality in temperature occurs, the administrator can know the abnormality and take prompt action.

[0059] Furthermore, since the upcycling plant system 100 has multiple plants 110, each plant 110 has its own identification information, and the server 120 communicates with each plant 110 based on the identification information, the administrator can grasp the status of all plants 110, and if a temperature abnormality occurs, the administrator can know which plant 110 the temperature abnormality occurred in.

[0060] In addition, since plant 110 is configured to have a weight measuring sensor or a volume measuring sensor, and weight information obtained by the weight measuring sensors, first weight measuring sensor 115A and second weight measuring sensor 115B, or volume information obtained by the volume measuring sensor, is transmitted from plant 110 to server 120, it is possible to calculate the costs that would have been incurred if the work had been requested from an industrial waste disposal company, and to calculate the extent to which decarbonization is being achieved compared to the existing municipal waste disposal methods in the area where the plant is installed.

[0061] Furthermore, the plant 110 has a humidity sensor 116, and humidity information obtained by the humidity sensor 116 is transmitted from the plant 110 to the server 120, thereby allowing an administrator to manage the humidity in the plant 110.

[0062] In addition, the plant 110 has a vibration sensor 117, and vibration level information obtained by the vibration sensor 117 is transmitted from the plant 110 to the server 120. When the vibration level information reaches or exceeds a predetermined value, the server 120 determines that it is time for maintenance of the plant 110 and notifies the terminal of a maintenance company, which is an example of a predetermined contact, of the identification information and the fact that the vibration level is above the predetermined value. This enables a maintenance technician to immediately head to the plant 110 and make repairs as necessary.

[0063] Furthermore, the plant 110 is configured to have a metal detection sensor and a buzzer on the path 111c in front of the inlet of the plant 110, and when the metal detection sensor detects metal, the buzzer sounds and information that metal has been detected is sent from the plant 110 to the server 120. Therefore, if metal is found to be mixed in, the user can stop the input of the waste WT and remove the metal, and the manager can identify plants 110 with a high level of metal contamination.

[0064] In addition, the plant 110 has a means for selecting the type of waste WT, which is the raw material, and the server 120 has a timer function. Type selection information by the image recognition sensor 119, which is an example of a type selection means, and weight information by the first weight measuring sensor 115A, which is an example of a weight measuring sensor, are transmitted from the plant 110 to the server 120, and based on these, the server 120 determines the heating time and controls the heating means of the plant 110, thereby stabilizing the quality of the generated bio-coal BC.

[0065] Furthermore, the plant 110 has a first weight measuring sensor 115A as an example of a measuring means for measuring the weight or volume of the waste WT, which is the raw material before it is input, and weight information, which is the measurement result information by the first weight measuring sensor 115A, is transmitted from the plant 110 to the server 120. The server 120 calculates waiting time information for the waste WT, which is the raw material waiting to be processed, based on the operating status information of each plant 110, the processing capacity information of each plant 110, and the weight information, which is the measurement result information, and transmits information to a transporter's terminal, which is an example of a specified terminal, instructing the transport of the raw material waste WT from the plant 110 with a long waiting time to the plant 110 with a short waiting time, based on the previously registered location information of each plant 110 and the calculated waiting time information for the waste WT, which is the raw material waiting to be processed, of each plant 110. For example, the waste WT can be transported from a plant 110 with a long waiting time in a neighboring area to a plant 110 with a short waiting time, thereby sharing waste processing.

[0066] In addition, the program of the upcycling plant system 100, which is an embodiment of the present invention, has a transmission step S3 in which, during operation of the plant 110, the plant 110 transmits temperature information obtained by a temperature sensor 114 installed in the plant 110 to the server 120, a determination step S4 in which the temperature information received from the plant 110 is determined to be equal to or higher than a predetermined threshold, and a stop control step S5 in which the server 120 controls to stop operation of the plant 110 when it is determined that the temperature information is equal to or higher than the predetermined threshold.This allows the manager to manage the temperature of the plant 110 even if he is in a remote location far from the plant 110, and if there is an abnormality in the temperature, the manager can know the abnormality and take immediate action, thereby providing significant benefits. [Explanation of symbols]

[0067] 100 ··· Upcycle Plant System 110 Plant 111 Furnace body 111a... Inlet 111b... Outlet 111c... Route in front of the inlet 111d... After exhaust port 112 Transportation means 113 Sprinkler 114 Temperature Sensor 115A First weight measuring sensor (measurement means) 115B: Second weight measuring sensor (measurement means) 116 Humidity Sensor 117 Vibration Sensor 118A··· 1st metal detection sensor 118B Second metal detection sensor 119 Image recognition sensor (type selection means) 120 Server TR ··· Transport vehicle WT ··· Waste (raw materials) BC Bio-coal (product)

Claims

1. An upcycle plant system that controls a plant having a heating means for heating a raw material to produce something more valuable than the original raw material, The plant; A temperature sensor provided in the plant; A server capable of communicating with the plant, Temperature information is transmitted from the plant to a server during operation of the plant; An upcycle plant system, wherein the server is configured to be able to freely control the operation of the plant.

2. The plant includes a plurality of plants, each of the plants having identification information; 2. The upcycle plant system according to claim 1, wherein the server is configured to communicate with each plant based on the identification information.

3. the plant has a gravimetric or volumetric sensor, The upcycle plant system according to claim 2, characterized in that weight information obtained by the weight measuring sensor or volume information obtained by the volume measuring sensor is transmitted from the plant to a server.

4. the plant has a humidity sensor; 4. The upcycle plant system according to claim 3, wherein humidity information obtained by the humidity sensor is transmitted from the plant to a server.

5. the plant has a vibration sensor; Vibration level information obtained by the vibration sensor is transmitted from the plant to a server; The upcycle plant system according to claim 4, characterized in that, when the vibration level information reaches or exceeds a predetermined value, the server determines that it is time for maintenance of the plant and notifies a predetermined contact point of the identification information and that the vibration level is above a predetermined value.

6. The plant has a metal detection sensor and a buzzer in a path in front of the plant's inlet, 6. The upcycle plant system according to claim 5, wherein when the metal detection sensor detects metal, it sounds a buzzer and transmits information indicating that metal has been detected from the plant to a server.

7. The plant has a means for selecting a type of the raw material, The server has a timer function, An upcycle plant system as described in any one of claims 3 to 6, characterized in that type selection information from the type selection means and weight information from the weight measuring sensor are transmitted from the plant to a server, and the server determines the heating time based on this and controls the heating means of the plant.

8. The plant has a measuring means for measuring the weight or volume of the raw material before it is input, Measurement result information by the measuring means is transmitted from the plant to a server; The upcycling plant system according to any one of claims 2 to 6, characterized in that the server calculates waiting time information for raw materials awaiting processing based on the operating status information, processing capacity information, and measurement result information of each plant, and transmits information to a specified terminal instructing the transportation of raw materials from a plant with a long waiting time to a plant with a short waiting time based on pre-registered location information of each plant and the calculated waiting time information for the raw materials awaiting processing of each plant.

9. A program for an upcycle plant system that controls a plant having a heating means for heating a raw material to generate something more valuable than the original raw material, a transmission step in which, during operation of the plant, the plant transmits temperature information obtained by a temperature sensor provided in the plant to a server; a determination step of determining whether or not the temperature information received from the plant is equal to or greater than a predetermined threshold; A program for an upcycle plant system, comprising a stop control step in which a server controls to stop operation of the plant when it is determined that the temperature information is equal to or higher than a predetermined threshold.

Citation Information

Patent Citations

  • Waste treatment equipment and waste treatment plants

    JP7246839B1

Cited By

  • Method for producing granules

    JP2026002750A

  • Recycling Management System

    JP7838139B1

  • Manufacturing method for granular material

    JP7838148B1

  • Manufacturing method for granular material

    JP7872399B2

  • Method for producing granular material

    WO2025263341A1