Floor slab fixing method and floor slab fixing device

The floor slab fixing method and device stabilize deck slabs on main girders using multiple fixing devices to reduce road closure times by suppressing vertical, axial, and perpendicular vibrations during bridge deck renewal.

JP2024168201APending Publication Date: 2024-12-05TECHNOS CO LTD +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023084678
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-23
Publication Date
2024-12-05

AI Technical Summary

Technical Problem

Existing methods for replacing concrete slabs in bridge deck renewal work result in prolonged road closures due to insufficient vibration suppression during the process, causing vertical and axial shaking of the deck slabs, which affects road administrators and users.

Method used

A floor slab fixing method and device that includes vertical, bridge axis, and perpendicular direction fixing devices to stabilize the deck slab on the main girder, using wedge-shaped members, stoppers, and connecting plates to restrict shaking in multiple directions.

Benefits of technology

The method and device effectively reduce road closure periods by allowing the use of old slabs as roads during renewal, stabilizing the deck slabs against vertical, axial, and perpendicular vibrations, thus minimizing disruption.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024168201000001_ABST
    Figure 2024168201000001_ABST
Patent Text Reader

Abstract

To provide a floor slab fixing method or the like capable of improving a suppression effect on shaking in a vertical direction, shaking in a bridge axis direction, and shaking in a direction perpendicular to the bridge axis of a floor slab placed and fixed on a main girder after being separated from the main girder.SOLUTION: A floor slab fixing method according to the present invention is a floor slab fixing method in which a floor slab (detached floor slab 3) separated from a main girder 2 of a bridge 1 is placed on and fixed to the main girder 2, wherein the shaking of the floor slab (detached floor slab 3) placed on the main girder 2 in the vertical direction, the shaking of the floor slab (detached floor slab 3) placed on the main girder 2 in the direction of the bridge axis, and the floor slab (detached floor slab 3) is fixed to the main girder 2 in a state in which shaking of the floor slab (detached floor slab 3) placed on the main girder 2 in the direction perpendicular to the bridge axis is restricted.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a deck fixing method and deck fixing device for fixing a deck detached from a main girder to the main girder until the deck detached from the main girder is replaced with a new deck in deck replacement work in which a concrete deck joined onto a main girder is replaced with a new deck. [Background technology]

[0002] Conventionally, in deck renewal work to replace the concrete decks of bridges such as road bridges, railway bridges, and waterway bridges with new decks, the existing main girders are reused, so the deck that is installed on top of and joined to the main girders is cut, separated from the main girders, and removed, and then the new deck is joined on top of the main girders. Deck renewal work requires repeated work including slab cutting, in which the deck in the area to be renewed is cut using a cutting device such as a wire saw to separate it from the main girders, and slab removal, in which the deck that has been separated from the main girders is removed. This is followed by slab joining work, in which a new deck is joined on top of the main girders from which the deck was removed, which results in a long time required for the deck renewal work in the area to be renewed. In this case, the road must be closed from the time of the deck cutting work until the completion of the deck joining work, which will result in a long continuous road closure period, resulting in great inconvenience to road managers and road users due to the road closure. Therefore, in deck renewal work, the applicant has developed a known technology in which, while the deck is in use as a road, the deck is separated from the main girders and the deck separated from the main girders is fixed onto the main girders using a fixing device, and after the deck is fixed, the deck is used as a road until the fixing device is removed and the deck is removed (see Patent Document 1). [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Patent Publication No. 2021-88895 Summary of the Invention [Problem to be solved by the invention]

[0004] However, the method of fixing the deck using the above-mentioned fixing device had the problem that it did not provide sufficient measures to suppress vertical shaking, shaking in the direction of the bridge axis, and shaking perpendicular to the bridge axis of the deck, which is separated from the main girders and then placed on top of the main girders and fixed thereto. The present invention aims to provide a deck fixing method and a deck fixing device that can improve the suppression effect against vertical swaying, swaying in the bridge axis direction, and swaying perpendicular to the bridge axis of a deck that is separated from the main girder and then placed and fixed on the main girder. [Means for solving the problem]

[0005] The deck fixing method of the present invention is a deck fixing method in which a deck slab separated from the main girders of a bridge is placed on the main girders and fixed, and is characterized in that the deck slab is fixed to the main girders so that the vertical swaying of the deck slab placed on the main girders, the swaying of the deck slab placed on the main girders in the bridge axis direction, and the swaying of the deck slab placed on the main girders in the direction perpendicular to the bridge axis are restricted. The deck fixing device of the present invention is a deck fixing device that places and fixes a deck separated from the main girders of a bridge on the main girders, and is characterized in that it comprises a vertical fixing device that fixes the deck to the main girders so that the vertical swaying of the deck placed on the main girders is restricted, a bridge axis direction fixing device that fixes the deck placed on the main girders so that the swaying of the deck placed on the main girders in the bridge axis direction is restricted, and a bridge axis perpendicular direction fixing device that fixes the deck placed on the main girders so that the swaying of the deck placed on the main girders in the direction perpendicular to the bridge axis is restricted. The vertical fixing device is also characterized by comprising a cutting surface support device that is installed between an upper cutting surface and a lower cutting surface formed by horizontally cutting the portion to be cut of the deck slab joined above the main girder, and supports the upper and lower cutting surfaces, and a fixing device that fixes the deck slab placed on the main girder to the main girder via the cutting surface support device. The cut surface support device is also characterized by comprising a wedge-shaped member placed between the cut surfaces, and a fall prevention member that prevents the wedge-shaped member placed between the cut surfaces from falling from between the cut surfaces. The fixing device is also characterized by comprising a support material that receives the lower end of the main girder, and a support material hanging fixture that fixes the deck slab to the main girder by fixing the support material to the deck slab in a suspended state. The bridge axis direction fixing device is also characterized by having a pair of stoppers arranged to sandwich the cross girder, which is connected to the main girder and extends perpendicular to the bridge axis, from both sides in the bridge axis direction, and a fixing means for fixing the stoppers to the deck placed on the main girder. In addition, the bridge axis perpendicular direction fixing device comprises a connecting plate installed so as to penetrate, in the bridge axis perpendicular direction, between an upper cut surface and a lower cut surface formed by horizontally cutting the portion to be cut of the deck slab joined above the main girder, and each clamping member connected to each protruding portion of the connecting plate that protrudes outward on both sides in the bridge axis perpendicular direction from between the cut surfaces, and the clamping members comprise an upper member arranged above the protruding portion and a lower member arranged below the protruding portion, and each upper member of each clamping member is installed in a state in which it is in contact with each side surface on both sides in the bridge axis perpendicular direction of the deck slab that is separated from the main girder and located above the cut surfaces, and each lower member of each clamping member is installed in a state in which it is in contact with each end face on both sides in the bridge axis perpendicular direction of the main girder that is located below the cut surfaces, and the upper member and lower member of one clamping member are connected by sandwiching one protruding portion of the connecting plate, and the upper member and lower member of the other clamping member are connected by sandwiching the other protruding portion of the connecting plate. In addition, the fixing device perpendicular to the bridge axis is characterized by having a pair of stoppers arranged to sandwich the main girder from both sides perpendicular to the bridge axis, and a fixing means for fixing the stoppers to a deck placed on the main girder. The deck fixing method and deck fixing device of the present invention make it possible to provide a deck fixing method and deck fixing device that can improve the suppression effect against vertical swaying, swaying in the bridge axis direction, and swaying perpendicular to the bridge axis of the deck that is separated from the main girders and then placed on and fixed on the main girders. [Brief description of the drawings]

[0006] [Figure 1] FIG. 1 shows a deck fixing method using a deck fixing device according to an embodiment, where (a) is a diagram showing the positional relationship between each fixing device and each girder from above the bridge, and (b) is a cross-sectional view taken along the arrow A in (a). [Diagram 2] 1(a) is a view taken in the direction of arrow B in FIG. 1(a), (b) is a view taken in the direction of arrow C in FIG. 1(a), and (c) is a view taken in the direction of arrow D in FIG. 1(a). [Diagram 3] 1A is a diagram showing an example of a cutting surface support device of a vertical fixing device, (a) is a plan view showing the cutting surface support device, (b) is a left side view of the cutting surface support device, and (c) is a front view of the cutting surface support device. [Figure 4] 1A and 1B are diagrams showing the state in which the cutting surface support device is installed between the cutting surfaces, where (a) is a diagram showing the cutting surface support device installed between the cutting surfaces from above, and (b) is a diagram showing the cutting surface support device installed between the cutting surfaces from the side. [Diagram 5] This is a diagram showing an example of a vertical fixing device, where (a) is a diagram showing the cutting surface support device installed between the cutting surfaces as viewed from above, (b) is a diagram showing the fixing device as viewed from one side (front side) in the bridge axis direction, (c) is a diagram showing the fixing device as viewed from one side (right side) perpendicular to the bridge axis, and (d) is a diagram showing (b) as viewed from below. [Figure 6] FIG. 1 shows an example of a bridge axis direction fixing device, where (a) is a view of the device from one side (front side) in the bridge axis direction, and (b) is a view of the device from one side (right side) perpendicular to the bridge axis. [Figure 7] FIG. 1 shows an example of a bridge axis direction fixing device, where (a) is a view of the device from one side (right side) perpendicular to the bridge axis, and (b) is a view of the device from one side (front side) in the bridge axis direction. [Figure 8] This is a diagram showing an example of a fixing device perpendicular to the bridge axis, where (a) is a diagram of the device seen from above, (b) is a diagram of the device seen from one side (front side) in the bridge axis direction, and (c) is a diagram of the device seen from one side (right side) in the direction perpendicular to the bridge axis. [Figure 9]This is a diagram showing an example of a fixing device perpendicular to the bridge axis, where (a) is a diagram of the device seen from above, (b) is a diagram of the device seen from one side (front side) in the bridge axis direction, and (c) is a diagram of the device seen from one side (right side) in the direction perpendicular to the bridge axis. [Figure 10] This is a diagram showing an example of a fixing device perpendicular to the bridge axis, where (a) is a diagram of the device seen from above, (b) is a diagram of the device seen from one side (front side) in the bridge axis direction, and (c) is a diagram of the device seen from one side (right side) in the direction perpendicular to the bridge axis. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0007] Hereinafter, with reference to Figs. 1 to 10, an embodiment of a deck fixing method and deck fixing device for placing and fixing a deck 3 separated from a main girder 2 of a bridge 1 on the main girder 2 will be described. In the following description, the deck slab 3 that is separated from the main girder 2, placed on the main girder 2, and fixed to the main girder 2 by the deck slab fixing device of the present invention is referred to as the "detachable deck slab 3." In addition, in this specification, the terms front, rear, top, bottom, left and right are defined as directions shown in each drawing. In addition, Figure 1(a) is a view (plan view) of bridge 1 seen from above, and should show the detachable deck 3 fixed by each fixing device (vertical fixing device 4, bridge axis direction fixing device 5, bridge axis perpendicular fixing device 6) described below, but in order to clarify the positional relationship between each fixing device and each girder, the detachable deck 3 has been omitted from Figure 1(a). Fig. 1(b) is a cross-sectional view taken along the line A in Fig. 1(a), but the hatching showing the cross section is omitted. Also, if each fixing device were shown in Fig. 1(b), the fixing devices would overlap and become unclear, so the fixing devices are omitted in Fig. 1(b). Bridge 1 is a road bridge, railway bridge, waterway bridge, etc., and as shown in Figure 1 (b), bridge 1 has a structure in which the deck is supported by piers 2F via main girders 2. In deck renewal work, after the deck section to be cut 30 is cut and the deck is separated from the main girders 2, the detachable deck 3 is fixed to the main girders 2 using each fixing device. Types of main girders 2 include box-shaped (R-shaped cross section) box girders 2A and 2B and I-shaped (I-shaped cross section) I-girder 2C. Figure 1 illustrates an example of a bridge 1 in which box girder 2A is a main girder 2 located on the sea side (right side), box girder 2B is a box-shaped main girder 2 located on the mountain side (left side), and I-girder 2C is a main girder 2 located between the box girder 2A on the sea side and the box girder 2B on the mountain side. In addition, in Figure 1(b), 2G is a wall parapet, 2H is a bracket, 2I and 2J are stiffening girders, and 2M is a splice plate that connects the cross beam 2D ​​portion provided on the box girders 2A and 2B to the bracket 2H, or a splice plate that connects the connecting portion with the cross beam 2D ​​provided on the box girders 2A and 2B to the cross beam 2D ​​(see Figures 6(a) and 7(b)). In addition, the stiffening girders 2I and 2J are components for reinforcing and stiffening the deck, which are provided to prevent cracks from occurring on the underside of the deck and resulting in a decrease in the rigidity of the deck when the live load of automobiles acts on the deck for a long period of time.

[0008] The deck fixing method according to an embodiment of the present invention is a deck fixing method in which a detachable deck 3 separated from the main girder 2 of a bridge 1 is placed on the main girder 2 and fixed thereon, and the detachable deck 3 is fixed to the main girder 2 so that the vertical swaying of the detachable deck 3 placed on the main girder 2, the swaying of the detachable deck 3 placed on the main girder 2 in the bridge axis direction, and the swaying of the detachable deck 3 placed on the main girder 2 in the direction perpendicular to the bridge axis are restricted. In addition, the deck fixing device of the embodiment is a deck fixing device that places and fixes a detachable deck 3 separated from the main girder 2 of a bridge 1 on the main girder 2, and is equipped with a vertical fixing device 4 (see Figures 3 to 5) for fixing the detachable deck 3 to the main girder 2 so that the vertical shaking of the detachable deck 3 placed on the main girder 2 is restricted, a bridge axis direction fixing device 5 (see Figures 6 and 7) for fixing the detachable deck 3 placed on the main girder 2 so that the shaking of the detachable deck 3 in the bridge axis direction is restricted, and a bridge axis perpendicular direction fixing device 6 (see Figures 8, 9, and 10) for fixing the detachable deck 3 placed on the main girder 2 so that the shaking of the detachable deck 3 in the direction perpendicular to the bridge axis is restricted.

[0009] In an embodiment, in deck renewal work to replace an old concrete deck that was installed on and joined to the main girders 2 of a bridge 1 with a new deck, a deck separation step is performed to separate the old deck from the main girders 2 while the old deck is in service as a road, and a deck fixing step is performed to fix the detached deck 3 separated from the main girders 2 onto the main girders 2 using a deck fixing device.Furthermore, after the deck fixing step is completed, the detached deck 3 is in service as a road until the deck removal step is started, in which the deck fixing device is removed and the detached deck 3 is removed.

[0010] The cutting work of the deck to be updated, which is carried out in the deck separation step, involves using a cutting device such as a wire saw as disclosed in Patent Document 1 to horizontally cut the deck to be cut portion 30 located above the boundary between the deck and the main girder 2, thereby separating the old deck from the main girder 2. In the deck fixing step, a deck fixing operation is performed in which the detachable deck 3, which has been separated from the main girder 2, is fixed onto the main girder 2 using a deck fixing device. In this case, it is preferable to repeatedly perform a cutting operation to cut the old deck using a cutting device and a deck fixing operation to fix the detachable deck 3 to the main girder 2 using a deck fixing device. For example, by repeatedly performing a work cycle in which cutting operation using a cutting device is performed for tens of centimeters to tens of meters, followed by deck fixing operation of the detachable deck 3 using the deck fixing device, the deck separation step and the deck fixing step can be performed consecutively on the lower side of the deck, and since it is not necessary to close the road during the deck separation step and the deck fixing step, the road closure period during the deck renewal work can be shortened. Then, when the detachable deck 3 fixed to the main girder 2 using the deck fixing device in the deck fixing step is replaced with a new deck, the road is closed to traffic, and in the deck removal step, deck removal work is carried out in which the deck fixing device is removed and the detachable deck 3 is removed, and then deck joining work is carried out in which a new deck is joined on top of the main girder 2 from which the detachable deck 3 has been removed. Therefore, the cutting work and deck fixing work can be carried out while the old deck is still in use as a road, and further, the detachable deck 3 fixed to the main girder 2 using the deck fixing device can be used as a road until the old deck, that is, the detachable deck 3, is removed. In other words, in the deck renewal work related to the embodiment, the old deck can be used as a road during the period from the deck separation step to the deck removal step, and there is no need to close the road to traffic. This shortens the period of road closure during deck renewal work, thereby reducing the inconvenience to road managers and road users associated with road closures.

[0011] The deck fixing step will be described in detail below with reference to Figs. The deck fixing step includes a vertical fixing step, a bridge axis direction fixing step, and a fixing step perpendicular to the bridge axis. The vertical fixing step is a step in which the detachable floor slab 3 placed on the main girder 2 is fixed to the main girder 2 using a vertical fixing device 4 so that the vertical shaking of the detachable floor slab 3 placed on the main girder 2 is restricted. The bridge axial direction fixing step is a step in which the bridge axial direction fixing device 5 is used to fix the cut-off deck 3 placed on the main girder 2 so that the swaying of the cut-off deck 3 in the bridge axial direction is restricted. The bridge axis perpendicular fixing step is a step in which the detachable deck 3 placed on the main girder 2 is fixed using a bridge axis perpendicular fixing device 6 so that the swaying of the detachable deck 3 in the direction perpendicular to the bridge axis is restricted. In addition, the vertical direction corresponds to the up-down direction shown in each figure, the bridge axis direction corresponds to the front-to-back direction shown in each figure, and the direction perpendicular to the bridge axis corresponds to the left-to-right direction shown in each figure.

[0012] Next, the configuration of the vertical fixing device 4 will be described with reference to FIGS. 3 to 5 show a vertical fixing device 4 for fixing the detachable deck 3 onto the sea-side box girder 2A serving as the main girder 2. The vertical fixing device 4 is configured to include, for example, a cutting surface support device 4A that is installed in the cutting surface area 31 between the upper cutting surface 31x and the lower cutting surface 31y formed by horizontally cutting the cutting target portion 30 of the deck slab joined above the main girder 2, and supports the upper and lower cutting surfaces 31x, 31y, and a fixing device 4B that fixes the detachable deck slab 3 placed on the main girder 2 to the main girder 2 via the cutting surface support device 4A.

[0013] The cutting surface support device 4A is configured, for example, to include a wedge-shaped member 10A placed between the cutting surfaces 31, and a fall prevention member 10B that prevents the wedge-shaped member 10A placed between the cutting surfaces 31 from falling from the cutting surfaces 31. The wedge-shaped member 10A has an inclined surface 10s that slopes upward from the tip side (left side in FIG. 3(c)) to the rear end side (right side in FIG. 3(c)) when inserted between the cut surfaces 31. The fall prevention member 10B is configured to protrude forward (to the left in FIG. 3(c)) from the tip side of the wedge-shaped member 10A.

[0014] As shown in FIG. 3, the wedge-shaped member 10A is composed of a lower flat plate 11, an upper inclined flat plate 12, a spacer 13, and a stop plate 14, for example. The lower flat plate 11 is configured such that the front end portion (left side in FIG. 3(a)) which is one end side in the longitudinal direction of the rectangular flat plate is formed in a trapezoid shape. In other words, the lower flat plate 11 is configured to include a rectangular flat plate portion 11a and a tip portion 11b which is a trapezoidal flat plate portion provided at one end side in the longitudinal direction of the rectangular flat plate portion 11a. The upper inclined flat plate 12 is formed of a rectangular flat plate or the like having a size corresponding to that of the rectangular flat plate portion 11a. The spacer 13 is composed of a rod-shaped material or the like, the upper surface of which is formed into an inclined surface that slopes upward from one end side (left side in Figure 3(c)) of the rectangular flat portion 11a in the longitudinal direction to the other end side (right side in Figure 3(c)). The spacers 13 are provided on one surface of the rectangular flat portion 11a of the lower flat plate 11 so as to extend along the long side edges of the rectangular flat portion 11a at positions on both long side edges of the rectangular flat portion 11a, and are also provided on a central position between the long side edges so as to extend along the long side edges. That is, for example, three spacers 13 are provided on one surface of the rectangular flat portion 11a of the lower flat plate 11 at predetermined intervals along the short side of the rectangular flat portion 11a. Furthermore, one of the plate surfaces of the upper inclined flat plate 12 is placed on the inclined surfaces which are the upper surfaces of the three spacers 13, 13, 13 mentioned above, so that the other plate surface of the upper inclined flat plate 12 is formed into an inclined surface 10s which slopes upward from one end side (left side in Figure 3(c)) to the other end side (right side in Figure 3(c)). That is, the lower flat plate 11, the spacer 13 and the upper inclined flat plate 12 form a wedge-shaped portion. The stop plate 14 extends along the short side edge of the rectangular flat plate portion 11a so that the plate surface is perpendicular to one plate surface of the rectangular flat plate portion 11a at the other end side of the one plate surface of the rectangular flat plate portion 11a. The upper inclined flat plate 12 is provided so that its upper end surface is configured of a flat plate or the like having a size such that it is positioned higher than the other plate surface (inclined surface 10s) of the upper inclined flat plate 12. The wedge-shaped member 10A is constructed by connecting a lower flat plate 11, an upper inclined flat plate 12, a spacer 13 and a stop plate 14 by connecting means such as welding.

[0015] As shown in Figures 3 and 4, the fall prevention member 10B is configured, for example, to include a threaded rod 15 having one end protruding forward from the tip side of the wedge-shaped member 10A, and a nut 16 and a washer 17 screwed onto one end of the threaded rod 15. The threaded rod 15 is provided so as to extend along the center line of the trapezoid on one plate surface of the tip portion 11b of the lower flat plate 11 and protrude forward beyond the tip portion 11b. The other end side of the threaded rod 15 and one plate surface of the tip portion 11b of the lower flat plate 11 are connected by a connecting means such as welding. The washer 17 functions as a locking means for engaging with the side surface 31a of the remaining portion of the deck extending downward from the edge perpendicular to the bridge axis between the cutting surfaces 31, and the side surface 31b of the detachable deck 3 extending upward from the edge perpendicular to the bridge axis between the cutting surfaces 31, and the nut 16 functions as a positioning means for the washer 17.

[0016] As shown in Figure 5, the fixing device 4B is configured, for example, to include a support material 20A that receives the lower end 2e of the main girder 2, and a support material hanging fixture 20B that fixes the detachable floor slab 3 to the main girder 2 by fixing the support material 20A to the underside 3u side of the detachable floor slab 3 in a suspended state. In FIG. 5(b), the cut surface supporting device 4A is omitted. The support member 20A is made of a long material such as a square steel pipe. The receiving material hanging fixing device 20B is composed of left and right hanging portions 21, 21 provided on both ends of the receiving material 20A, left and right fastening hanging members 22, 22 respectively connected to each hanging portion 21, 21, and left and right fixing members 23, 23 for fixing the left and right fastening hanging members 22, 22 to the underside 3u side of the detachable floor slab 3. The hanging portion 21 is configured by combining so-called angle members having an L-shaped cross section. The fastening hanging member 22 is composed of a fastening material 27, a lower connecting member 28 that connects the lower end of the fastening material 27 to the hanging portion 21, and an upper connecting member 29 that connects the upper end of the fastening material 27 to the fixing member 23. The fastening material 27 is a cut bolt or the like. The lower connecting member 28 is a connecting member including a joint fitting 28a and a shackle 28b. As the upper connecting member 29, a connecting member including a joint fitting 29a, a shackle 29b, and a multi-eyebolt 29c is used. The fixing member 23 is an anchor such as a female thread anchor.

[0017] That is, the fixing member 23 is fixed to the lower surface 3u of the separation floor slab 3, the female thread of the female thread anchor of the fixing member 23 is connected to the bolt of the multi-eyebolt 29c, the shackle portion of the multi-eyebolt 29c is connected to the shackle 29b, and the shackle 29b is connected to the joint fitting 29a. The upper end side of the fastening material 27 is connected to the joint fitting 29a via a fastening adjustment tool 27a such as an adjustment nut, and the lower end side of the fastening material 27 is connected to the joint fitting 28a via a fastening adjustment tool 27b such as an adjustment nut, and the joint fitting 28a is connected to the hanging part 21 via the shackle 28b. In other words, the upper end side of the fastening material 27 is rotatably connected to the fixing member 23 fixed to the underside 3u of the detachable floor slab 3 via a joint fitting 29a, a shackle 29b, and a multi-eye bolt 29c, and the hanging portion 21 is rotatably connected to the lower end side of the fastening material 27 via a joint fitting 28a and a shackle 28b.

[0018] In the vertical fixing step, after the old deck slab is separated from the main girder 2, a cutting surface support device 4A is installed between the cutting surfaces 31, and then the cutting deck slab 3 is fixed to the main girder 2 using a fixing device 4B. That is, after the old deck is separated from the main girder 2, the threaded rod 15 of the cutting surface support device 4A is inserted into the cutting surface gap 31 from one side of the section to be cut 30 of the old deck that was joined to the main girder 2, perpendicular to the bridge axis, and the wedge-shaped member 10A is fitted into the cutting surface gap 31 so that one end of the threaded rod 15 protrudes outside the cutting surface gap 31. Thereafter, a washer 17 is screwed onto one end of the threaded rod 15 protruding outside the cut surface gap 31, and the nut 16 is fastened onto one end of the threaded rod 15 so that the washer 17 is pressed against the side surface 31a of the remaining deck portion and the side surface 31b of the cut-off deck 3 as shown in Fig. 4(b), thereby installing the cut surface support device 4A into the cut surface gap 31. That is, the washer 17 screwed onto one end of the threaded rod 15 etc. welded to the wedge-shaped member 10A is brought into contact with the above-mentioned side surface 31a and side surface 31b, thereby realizing a structure that prevents the wedge-shaped member 10A from falling off. Then, the fixing members 23, 23 of the fixing device 4B are fixed to the underside 3u side of the detachable floor slab 3 placed on the main girder 2, and the support material hanging fixture 20B is attached to the fixing member 23. Furthermore, the left and right hanging portions 21, 21 of the support material 20A arranged below the main girder 2 are connected to the lower ends of the left and right support material hanging fixtures 20B, 20B. Thereafter, by operating the fastening adjustment devices 27a, 27b such as nuts provided at the upper and lower ends of the left and right fastening materials 27, 27 to set the fastening material 27 in a fastened state, the detachable deck 3 placed on the main girder 2 is fixed to the main girder 2A in a state in which shaking in the vertical direction (up and down direction in Figure 1(b)) is restricted.

[0019] As shown in Figures 5(a) and (c), a pair of cutting surface support devices 4A, 4A are placed at a specified interval along the bridge axis direction. That is, one cutting surface support device 4A is installed with its wedge-shaped member 10A on one side (left side of Figure 5(a)) of the cutting surface interval 31 in the direction perpendicular to the bridge axis, and the other cutting surface support device 4A is installed with its wedge-shaped member 10A on the other side (right side of Figure 5(a)) of the cutting surface interval 31 in the direction perpendicular to the bridge axis. The fixing device 4B is installed so as to be located between a pair of cut surface support devices 4A, 4A arranged at a predetermined interval along the bridge axis direction. Therefore, since both ends of the cutting surface space 31 perpendicular to the bridge axis are supported by the wedge-shaped members 10A, 10A of a pair of cutting surface support devices 4A, 4A, the cutting floor slab 3 can be supported in a stable state that is close to horizontal, and the cutting floor slab 3 can be fixed to the main girder 2 in a stable state that is close to horizontal, it is possible to maintain a stable fixed state that can regulate the vertical swaying of the cutting floor slab 3 placed on the main girder 2.

[0020] 3 to 5, the fixing device 4B is exemplified as a fixing device for fixing the cut-out floor slab 3 onto the sea-side box girder 2A, but fixing devices of a similar configuration may be used for the fixing device for fixing the cut-out floor slab 3 onto the mountain-side box girder 2B and the fixing device for fixing the cut-out floor slab 3 onto the I-girder 2C. In other words, fixing devices with different lengths of fastening material 27 and receiving material 20A may be used according to the cross-sectional shape and dimensions of the main girder 2. 3 to 5, the cutting surface support device 4A is illustrated as a cutting surface support device installed in the cutting surface gap 31 formed on the sea-side box girder 2A, but a cutting surface support device with a similar configuration may be used for the cutting surface support device placed on the mountain-side box girder 2B and the cutting surface support device placed on the I-girder 2C. The cutting surface support device 4A may be used by facing the inclined surface 10s of the wedge-shaped member 10A downward so that the inclined surface 10s contacts the lower cutting surface 31y. In other words, even if the main girder 2 is different, the vertical fixing device 4 may have a similar configuration.

[0021] Next, the configuration of the bridge axis direction fixing device 5 will be described with reference to Figs. In addition, Figure 6 illustrates a bridge axial direction fixing device 5A that acts on a cross girder 2D extending from the sea side box girder 2A serving as the main girder 2 to suppress shaking in the bridge axial direction, and Figure 7 illustrates a bridge axial direction fixing device 5B that acts on a cross girder 2D extending from the mountain side box girder 2B serving as the main girder 2 to suppress shaking in the bridge axial direction. The bridge axis direction fixing device 5 is configured, for example, to include a pair of front and rear stoppers arranged to sandwich the cross girder 2D, which is connected to the main girder 2 and extends perpendicular to the bridge axis, from both sides in the bridge axis direction (front-to-back direction in Figures 6(b) and 7(a)), and a fixing means 51 for fixing the stoppers to the detachable deck 3 placed on the main girder 2. As the bridge axial direction fixing device 5, a bridge axial direction fixing device 5A using a pair of front and rear stoppers 50A, 50A as shown in Figure 6(b), or a bridge axial direction fixing device 5B using a pair of front and rear stoppers 50B, 50B as shown in Figure 7(a) is used. The bridge axial direction fixing device 5A is a bridge axial direction fixing device used when the fixing means 51 can be fixed to the side 31b of the cut-off deck 3 extending upward from the end edge of the cutting surface 31, and the bridge axial direction fixing device 5B is a bridge axial direction fixing device used when the fixing means 51 cannot be fixed to the side 31b of the cut-off deck 3 and is fixed to the underside 3u of the cut-off deck 3. Furthermore, in the case of an I-girder 2C as the main girder 2, the fixing means 51 is configured to be able to be fixed to the side surface 31b of the detachable deck 3, so that a bridge axis direction fixing device 5A can be used, as shown in Figure 1(a).

[0022] The stopper 50A is composed of a claw plate 52 and a filler 53. The stopper 50B is composed of a web 55 and a base 56. The claw plate 52 and the web 55 are formed of a flat plate having a right-angled triangular surface. The filler 53 is composed of a plate material or the like that fills the gap between the side surface 31b of the detachable floor slab 3 and the plate surface of the claw plate 52. The base 56 is composed of a plate material or the like that functions as a fixed part that is connected by welding or the like to one end side of the web 55 so that the plate surface is perpendicular to the plate surface of the web 55 and is fixed to the detachable deck slab 3 by fixing means 51. The fixing means 51 is composed of anchor bolts or the like for fixing the stoppers 50A and 50B to the separation floor slab 3. The stopper 50A of the bridge axial direction fixing device 5A is fixed to the side surface 31b of the detachable deck 3 using a fixing means 51. The stopper 50A of the bridge axial direction fixing device 5B is fixed to the underside 3u of the separation deck 3 using fixing means 51.

[0023] In the bridge axis direction fixing step, after the deck is separated from the main girder 2, a pair of front and rear stoppers 50A, 50A or 50B, 50B are arranged to sandwich the front and rear of the cross girder 2D in the bridge axis direction, and these stoppers 50A, 50A or 50B, 50B are fixed to the cut-off deck 3 so that they are in contact with the front and rear end faces 2a, 2a in the bridge axis direction at the upper end of the cross girder 2D.As a result, the cut-off deck 3 placed on the main girder 2 is fixed to the main girder 2 via the bridge axis direction fixing device 5A or 5B so that the swaying of the cut-off deck 3 in the bridge axis direction is restricted.

[0024] Regarding the bridge axis direction fixing devices 5A, 5B, Figure 1(a) illustrates an example in which the devices are installed on only one side of the main girder 2, either to the left or right, along the direction perpendicular to the bridge axis, while Figures 6(a) and 7(b) illustrate examples in which the devices are installed on both sides of the main girder 2, along the direction perpendicular to the bridge axis. In other words, whether the bridge axis direction fixing device 5A and the bridge axis direction fixing device 5B are placed on both the left and right sides of the main girder 2 along the direction perpendicular to the bridge axis, or only on one side, can be decided appropriately depending on the relationship between the design load and the device strength. In other words, with regard to the bridge axis direction fixing devices 5A, 5B, if the design load can be satisfied by simply placing them on either the left or right side of the main girder 2 along the direction perpendicular to the bridge axis, then it is sufficient to place the device on only one side, and if the design load cannot be satisfied by simply placing them on either the left or right side, then it is sufficient to place the device on both the left and right sides.

[0025] Next, the configuration of the bridge axis perpendicular direction fixing device 6 will be described with reference to Figs. In addition, Figure 8 illustrates a fixing device 6A perpendicular to the bridge axis that acts on the I-girder 2C as the main girder 2 to suppress swaying in the direction perpendicular to the bridge axis, and Figure 9 illustrates a bridge axis direction fixing device 6B that acts on the mountain side box girder 2B as the main girder 2 to suppress swaying in the direction perpendicular to the bridge axis. That is, as the bridge axis perpendicular direction fixing device 6, for example, a clamp type bridge axis perpendicular direction fixing device 6A as shown in FIG. 8, or a stopper type bridge axis perpendicular direction fixing device 6B as shown in FIG. The clamp-type fixing device 6A in the direction perpendicular to the bridge axis is a fixing device in the direction perpendicular to the bridge axis that is used when there is space in the section 30 of the deck to be cut in which a clamping member 61 described below can be installed. The stopper type fixing device 6B in the direction perpendicular to the bridge axis is a fixing device in the direction perpendicular to the bridge axis that is used when there is no space in the section 30 of the deck to be cut to install the clamping member 61 described below. Furthermore, in the case of the sea-side box girder 2A serving as the main girder 2, there is space in the section 30 of the deck to be cut in which a clamping member 61 (described later) can be installed, so a clamp-type fixing device 6A perpendicular to the bridge axis can be used, as shown in Figure 1(a).

[0026] As shown in Figure 8, the clamp-type fixing device 6A perpendicular to the bridge axis comprises a connecting plate 60 installed so as to penetrate, along the direction perpendicular to the bridge axis, the cutting surface area 31 between the upper cutting surface 31x and the lower cutting surface 31y formed by horizontally cutting the cutting target portion 30 of the deck slab joined above the main girder 2, and each clamping member 61, 61 connected to each of the protrusions 60a, 60a of the connecting plate 60 protruding outward on both sides in the direction perpendicular to the bridge axis from the cutting surface area 31. The sandwiching member 61 includes an upper member 61A disposed above the protruding portion 60a and a lower member 61B disposed below the protruding portion 60a. The upper member 61A and the lower member 61B are each composed of, for example, an angle member 61a having an L-shaped cross section, and a reinforcing rib member 61b joined to the vertical and horizontal plates of the angle member 61a. Then, the upper members 61A, 61A of each clamping member 61, 61 are installed in contact with the opposing side surfaces 31b, 31b on both sides of the deck slab that is separated from the main girder 2C and positioned above the cutting surface 31, perpendicular to the bridge axis. In addition, the lower members 61B, 61B of each clamping member 61, 61 are installed in contact with the opposing side surfaces 31a, 31a on both sides perpendicular to the bridge axis of the remaining deck portion located below the cut surface 31, and the opposing edge surfaces 2t, 2t on both sides perpendicular to the bridge axis at the upper end of the main girder 2. In addition, bolt-through holes 62b, such as long holes, are formed in the upper member 61A and the lower member 61B of the clamping member 61 and the protruding portion 60a of the connecting plate 60, and the upper member 61A and the lower member 61B of the clamping member 61 and the connecting plate 60 are connected by passing a bolt 62a through the bolt-through hole 62b and fastening a nut (not shown). That is, the upper member 61A and the lower member 61B of one clamping member 61 are connected by sandwiching one protrusion 60a of the connecting plate 60, and the upper member 61A and the lower member 61B of the other clamping member 61 are connected by sandwiching the other protrusion 60a of the connecting plate 60.

[0027] In the bridge axis perpendicular fixing step using the bridge axis perpendicular fixing device 6A shown in Figure 8, a connecting plate 60 is inserted into the cut surface gap 31 between the upper cut surface 31x and the lower cut surface 31y at the point where the deck slab 3 is cut, and the left and right ends of the connecting plate 60 located on both sides in the direction perpendicular to the bridge axis are installed so as to protrude outward beyond the left and right ends of the cut surface gap 31, and clamping members 61 are provided on the left and right protruding portions 60a, 60a of the connecting plate 60 installed in this manner, respectively. That is, the upper member 61A and the lower member 61B are arranged symmetrically above and below each protrusion 60a, 60a of the connecting plate 60, and the angle iron 61a of the upper member 61A is brought into contact with the side surface 31b and the angle iron 61a of the lower member 61B is brought into contact with the side surface 31a and the edge surface 2t, and then the upper member 61A, the protrusion 60a of the connecting plate 60, and the lower member 61B are connected with connecting means (bolt 62a, bolt through hole 62b, and nut not shown) to integrate the upper member 61A, the protrusion 60a of the connecting plate 60, and the lower member 61B. As described above, when the fixing device 6A perpendicular to the bridge axis is used, the detachable deck 3 placed on the main girder 2 is fixed to the main girder 2 via the fixing device 6A perpendicular to the bridge axis so that the swaying of the detachable deck 3 placed on the main girder 2 in the direction perpendicular to the bridge axis is restricted.

[0028] As shown in Figure 9, the bridge axis perpendicular fixing device 6B is configured to include a pair of left and right stoppers 65, 65 arranged to sandwich the main girder 2 on both sides perpendicular to the bridge axis, and a fixing means 66 for fixing the stopper 65 to the underside 3u of the detachable deck 3 placed on the main girder 2.

[0029] The stopper 65 is formed of a flat plate or the like. The fixing means 66 is composed of a connecting member 67 connected to the stopper 65 and a fixing member 68 that fixes the connecting member 67 to the underside 3u of the separation floor slab 3. The connecting member 67 is composed of a plate-like member with a T-shaped cross section, with a stopper 65 connected to the vertical plate portion of the T and a horizontal plate portion of the T fixed to the underside 3u of the detachable floor slab 3 by a fixing member 68. In addition, a bolt-through hole 65b, such as a long hole, is formed in the stopper 65 and the vertical plate portion of the connecting member 67, and the stopper 65A and the connecting member 67 are connected by passing a bolt 65a through the bolt-through hole 65b and fastening a nut (not shown). The fixing member 68 is constituted by an anchor bolt or the like.

[0030] In the bridge axis perpendicular direction fixing step using the bridge axis perpendicular direction fixing device 6B, after the deck slab is separated from the main girder 2, a pair of left and right stoppers 65, 65 are arranged so as to sandwich the main girder 2 from both sides in the bridge axis perpendicular direction. Then, after the stoppers 65, 65 are set in contact with the opposing side surfaces 31a, 31a of the main girder 2 located below the cutting surface 31 in the bridge axis perpendicular direction, and the opposing edge surfaces 2t, 2t on both sides in the bridge axis perpendicular direction at the upper end of the main girder 2, the stoppers 65, 65 are fixed to the underside 3u of the separated deck slab 3 via fixing means 66, 66. In other words, when the fixing device 6B perpendicular to the bridge axis is used, the detachable deck 3 placed on the main girder 2 is fixed to the main girder 2 via the fixing device 6B perpendicular to the bridge axis so that the swaying of the detachable deck 3 placed on the main girder 2 in the direction perpendicular to the bridge axis is restricted.

[0031] As shown in FIG. 10, a stopper type fixing device 6C in the direction perpendicular to the bridge axis may be used as the fixing device 6 in the direction perpendicular to the bridge axis. FIG. 10 illustrates a fixing device 6C perpendicular to the bridge axis that acts on the sea-side box girder 2A serving as the main girder 2 to suppress swaying perpendicular to the bridge axis. The fixing device 6C perpendicular to the bridge axis is configured to include a pair of left and right stoppers 65A, 65A arranged to sandwich the main girder 2 on both sides perpendicular to the bridge axis, and a fixing means 66A for fixing the stopper 65A to the side 31b of the detachable deck 3 placed on the main girder 2.

[0032] The stopper 65A is formed of a flat plate or the like. The fixing means 66A is composed of a connecting member 67A connected to the stopper 65A and a fixing member 68A that fixes the connecting member 67A to the side surface 31b of the separation floor slab 3. The connecting member 67A is composed of a plate-like member with a T-shaped cross section, with a stopper 65A connected to the vertical plate portion of the T, and a horizontal plate portion of the T fixed by a fixing member 68A to the side surface 31b of the separation floor slab 3. Note that a bolt-through hole 65b such as a long hole is formed in the stopper 65A and the vertical plate portion of the connecting member 67A, and the stopper 65A and the connecting member 67A are connected by passing a bolt 65a through the bolt-through hole 65b and fastening a nut (not shown). The fixing member 68A is constituted by an anchor bolt or the like.

[0033] In the bridge axis perpendicular direction fixing step using the bridge axis perpendicular direction fixing device 6B, after the deck slab is separated from the main girder 2, a pair of left and right stoppers 65A, 65A are arranged so as to sandwich the main girder 2 from both sides in the bridge axis perpendicular direction. Then, after the stoppers 65A, 65A are set in contact with the opposing side surfaces 31a, 31a of the main girder 2 located below the cutting surface 31 in the bridge axis perpendicular direction, and the opposing edge surfaces 2t, 2t on both sides in the bridge axis perpendicular direction at the upper end of the main girder 2, the stoppers 65A, 65A are fixed to the side surface 31b of the separated deck slab 3 via the fixing means 66A, 66A. In other words, when the fixing device 6C perpendicular to the bridge axis is used, the detachable deck 3 placed on the main girder 2 is fixed to the main girder 2 via the fixing device 6C perpendicular to the bridge axis so that the swaying of the detachable deck 3 placed on the main girder 2 in the direction perpendicular to the bridge axis is restricted.

[0034] The clamp-type fixing device 6A in the direction perpendicular to the bridge axis shown in Fig. 8 is configured to install a connecting plate 60 between the cut surfaces 31, but differences in the cutting method, etc. may result in poor surface accuracy (cutting accuracy) of the cut surfaces of the upper cut surface 31x and the lower cut surface 31y between the cut surfaces 31. For example, if the surface accuracy of the cut surfaces is poor due to factors such as the cut surfaces being meandering or cutting chips remaining, it may be difficult to insert and penetrate the connecting plate 60 made of a thin steel plate or the like between the cut surfaces 31, and there is a possibility that the clamp-type fixing device 6A in the direction perpendicular to the bridge axis cannot be adopted. Therefore, in such a case, instead of the clamp-type fixing device 6A perpendicular to the bridge axis shown in Figure 8, it is sufficient to use the stopper-type fixing device 6C perpendicular to the bridge axis shown in Figure 10, which has a configuration that does not require the installation of a connecting plate 60 between the cutting surfaces 31.

[0035] As described above, according to the deck fixing method and deck fixing device of the embodiment, the cut-off deck 3 placed on the main girder 2 can be fixed to the main girder 2 in a state in which the vertical swaying of the cut-off deck 3 is restricted using the vertical fixing device 4, the cut-off deck 3 placed on the main girder 2 can be fixed to the main girder 2 in a state in which the swaying of the cut-off deck 3 in the bridge axis direction is restricted using the bridge axis direction fixing device 5, and further, the cut-off deck 3 can be fixed to the main girder 2 in a state in which the swaying of the cut-off deck 3 placed on the main girder 2 in the bridge axis direction is restricted using the bridge axis perpendicular direction fixing device 6. In other words, according to the deck fixing method and deck fixing device of the embodiment, it is possible to provide a deck fixing method and deck fixing device that can improve the suppression effect against vertical swaying, swaying in the bridge axis direction, and swaying perpendicular to the bridge axis of the detachable deck 3, which is separated from the main girder 2 and then placed and fixed on top of the main girder 2.

[0036] In addition, the cutting width of the cut surface 31 after the deck is cut and the unevenness of the upper and lower cut surfaces 31x, 31y are likely to vary due to the resistance during cutting and the influence of the vehicle load. However, according to the embodiment, a cut surface support device 4A equipped with a wedge-shaped member 10A is used so that it can be installed in close contact with the cut surface 31. In other words, by using the cut surface support device 4A equipped with the above-mentioned wedge-shaped member 10A, even if the cutting width or unevenness of the cut surface 31 varies, the insertion amount of the wedge-shaped member 10A into the cut surface 31 can be adjusted so that the wedge-shaped member 10A can be installed in close contact with the upper and lower cut surfaces 31x, 31y of the cut surface 31, thereby stably and reliably supporting the cut surfaces 31x, 31y.

[0037] In addition, the bridge axis direction fixing device 5 is configured using a pair of stoppers 50A, 50A and 50B, 50B that are arranged to contact both end faces 2a, 2a in the bridge axis direction of the cross beam 2D, which is connected to the main girder 2 and extends perpendicular to the bridge axis, and to clamp the cross beam 2D ​​from both end sides in the bridge axis direction, so that the fixing work can be performed simply and easily.

[0038] In addition, the fixing device 6 perpendicular to the bridge axis is configured to use a clamp-type fixing device 6A perpendicular to the bridge axis that is arranged to clamp the detachable deck 3 and main girder 2 from both sides perpendicular to the bridge axis, or a stopper-type fixing device 6B or 6C perpendicular to the bridge axis that is arranged to clamp the main girder 2 from both sides perpendicular to the bridge axis, so that the fixing work can be performed simply and easily.

[0039] For the vertical fixing work, bridge axis fixing work, and fixing work perpendicular to the bridge axis, for example, a cutting device can be used to cut the deck slab to a specified length (for example, about 1 to 2 m) along the bridge axis direction, and each time the cutting device is replaced, fixing work corresponding to the cut location can be carried out successively. Note that in this case, if the fixing members such as anchors that secure each fixing device are installed in advance before the cutting work, the fixing work can be carried out quickly.

[0040] Furthermore, the vertical fixing device used in the present invention is not limited to the configuration described in the above embodiment, but may be any device that has a configuration that can fix the detachable floor slab 3 placed on the main girder 2 to the main girder 2 so as to restrict the vertical shaking of the detachable floor slab 3. Furthermore, the bridge axial direction fixing device used in the present invention is not limited to the configuration described in the above embodiment, but may be any device that has a configuration that can fix the detachable deck 3 placed on the main girder 2 to the main girder 2 so as to restrict the swaying of the detachable deck 3 in the bridge axial direction. Furthermore, the fixing device used in the present invention in the direction perpendicular to the bridge axis is not limited to the configuration described in the above embodiment, but may be any device that has a configuration that can fix the detachable deck 3 placed on the main girder 2 to the main girder 2 so as to restrict the swaying of the detachable deck 3 in the direction perpendicular to the bridge axis. [Explanation of symbols]

[0041] 1 Bridges 2 Main digit 2A,2B Box girder (main girder) 2C I-beam (main beam) 2D crossbeam 2a End face of main girder 3. Detachable deck (a deck that is separated from the main girder, placed on top of the main girder, and fixed to the main girder by a deck fixing device) 4 Vertical Fixation Device 4A Cut surface support device 4B Fixing device 10A Wedge-shaped member 10B Fall prevention member 5,5A,5B Bridge axial direction fixing device 6,6A,6B,6C Bridge axis perpendicular direction fixing device 20A receiving material 20B Receiving material hanging fixture 30 Amputation area 31 Between cutting planes, 31a,31b side 31x Upper cut surface 31y Lower cut surface, 50A, 50B Stopper 51 Fixing means 60 Connecting plate 60a protrusion, 61 Clamping member 61A Upper member 61B Lower part 65,65A Stopper 66,66A Fixing means

Claims

1. A method for fixing a deck slab by placing a deck slab separated from a main girder of a bridge on the main girder and fixing the deck slab, A method for fixing a deck slab to a main girder so as to restrict the vertical swaying of the deck slab placed on the main girder, the swaying of the deck slab placed on the main girder in the direction of the bridge axis, and the swaying of the deck slab placed on the main girder in the direction perpendicular to the bridge axis.

2. A deck fixing device that places a deck separated from a main girder of a bridge on the main girder and fixes it, A vertical fixing device that fixes the deck to the main girder so as to restrict the vertical sway of the deck placed on the main girder; A bridge axial direction fixing device that fixes the deck so that the swaying of the deck placed on the main girder in the bridge axial direction is restricted; A bridge axis perpendicular fixing device that fixes the deck placed on the main girder so that the swaying of the deck in the direction perpendicular to the bridge axis is restricted; A deck fixing device comprising:

3. The deck fixing device described in claim 2, characterized in that the vertical fixing device comprises a cutting surface support device that is installed between an upper cutting surface and a lower cutting surface formed by horizontally cutting the portion of the deck to be cut that is joined above the main girder, and supports the upper and lower cutting surfaces, and a fixing device that fixes the deck placed on the main girder to the main girder via the cutting surface support device.

4. The deck fixing device described in claim 3, characterized in that the cut surface support device comprises a wedge-shaped member installed between the cut surfaces and a fall prevention member that prevents the wedge-shaped member installed between the cut surfaces from falling from between the cut surfaces.

5. A deck fixing device as described in claim 3 or claim 4, characterized in that the fixing device comprises a support material that supports the lower end of the main girder, and a support material hanging fixing device that fixes the deck slab to the main girder by fixing the support material to the deck slab in a suspended state.

6. The bridge axial direction fixing device is characterized in that it comprises a pair of stoppers arranged to sandwich a cross girder connected to the main girder and extending perpendicular to the bridge axis from both sides in the bridge axial direction, and a fixing means for fixing the stoppers to a deck placed on the main girder.

7. The bridge axis perpendicular fixing device includes a connecting plate installed so as to penetrate along the bridge axis perpendicular direction between an upper cut surface and a lower cut surface formed by horizontally cutting the section to be cut of the deck joined above the main girder, and clamping members respectively connected to each protrusion of the connecting plate protruding outward on both sides in the bridge axis perpendicular direction from between the cut surfaces, The clamping member includes an upper member disposed above the protruding portion and a lower member disposed below the protruding portion, A deck fixing device as described in claim 2, characterized in that the upper members of each clamping member are installed in a state in which they are in contact with each side surface on both sides of the deck slab that is separated from the main girder and located above the cutting surfaces, in the direction perpendicular to the bridge axis, and the lower members of each clamping member are installed in a state in which they are in contact with each end surface on both sides of the main girder that is located below the cutting surfaces, in the direction perpendicular to the bridge axis, and the upper and lower members of one clamping member are connected by sandwiching one protrusion of the connecting plate, and the upper and lower members of the other clamping member are connected by sandwiching the other protrusion of the connecting plate.

8. The deck fixing device described in claim 2, characterized in that the bridge axis perpendicular direction fixing device comprises a pair of stoppers arranged to sandwich the main girder from both sides perpendicular to the bridge axis, and a fixing means for fixing the stoppers to a deck placed on the main girder.

Citation Information