The automatic driving system for construction machines in tunnels uses SLAM and odometry with sensor fusion to overcome GPS loss and dynamic environments, ensuring accurate navigation and map adaptation.
Patent Information
- Application Number
- JP2021117625
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-07-16
- Publication Date
- 2024-09-20
- Estimated Expiration
- 2041-07-16
AI Technical Summary
Conventional automatic driving technologies are ineffective inside tunnels due to GPS signal loss and insufficient feature points for position estimation, and the dynamic environment complicates map reuse.
An automatic driving system for construction machines using a combination of SLAM (Simultaneous Localization And Mapping) and odometry, with sensors like LiDAR, IMU, and encoders to estimate position, and a control system that switches methods based on tunnel entry and exit.
Enables accurate autonomous driving within tunnels by integrating SLAM and odometry, adapting to changing environments, and updating maps for precise navigation.
Smart Images

Figure 0007554718000004 
Figure 0007554718000009 
Figure 0007554718000015
Abstract
Description
[Technical field]
[0001] The present invention relates to an automated driving system. [Background technology]
[0002] In recent years, there has been active development of autonomous driving technologies for vehicles (see, for example, Patent Documents 1 to 3). In autonomous driving technologies, the position of a vehicle is identified by some method, and control is performed based on the identified vehicle position. The technology described in Patent Document 1 enables automatic driving of dump trucks in construction sites. In the technology described in Patent Document 1, a communication means is installed in the dump truck, and the position of the dump truck is identified by communication between the communication means of the dump truck and a GPS (Global Positioning System). The technology described in Patent Document 2 enables autonomous driving of trailers in a container yard. In the technology described in Patent Document 2, a laser finder that detects the three-dimensional shape of the surroundings is installed on the trailer. A three-dimensional map of the surroundings is created from the three-dimensional shape of the surroundings detected by the laser finder, and the trailer's position is estimated by matching the created three-dimensional map with a simulated map. The technology described in Patent Document 3 describes a method for estimating position using a LiDAR (Light Detection and Ranging) system. LiDAR uses light pulses to measure the distance to an object based on the time of flight (TOF) of each light pulse. For LiDAR, a single laser emitter / detector combination incorporating, for example, a rotating mirror is used to effectively scan an entire plane. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2003-044141 A [Patent Document 2] JP 2017-228198 A [Patent Document 3] Special Publication No. 2020-533601 Summary of the Invention [Problem to be solved by the invention]
[0004] However, because conventional technology does not take into account the environment inside a tunnel, it has been difficult to use it for automatic operation of construction machinery inside a tunnel. For example, since radio waves from GPS satellites do not reach inside tunnels, it is difficult to apply the technology described in Patent Document 1 to construction machinery inside tunnels. In addition, since the tunnel itself has a uniform cylindrical cross-sectional shape, the inside of the tunnel has the characteristic that the same scenery continues in the direction of travel and there are few distinctive features. Therefore, it is difficult to estimate the position only by scan matching using the 3D shape detected inside the tunnel, and the technology described in Patent Documents 2 and 3 does not provide sufficient accuracy in estimating the position of construction machinery inside the tunnel. In addition, during construction, the environment inside the tunnel changes constantly with the progress of excavation and lining work. Therefore, the 3D environmental map cannot be reused and must be constantly updated. From this perspective, the present invention provides an automatic driving system capable of automatic driving inside a tunnel. [Means for solving the problem]
[0005] The automatic driving system according to the present invention is an automatic driving system for a construction machine moving in a tunnel. This automatic driving system includes a first sensor provided on the construction machine and detecting first information related to the shape of a surrounding object, a second sensor provided on a moving part of the construction machine and detecting second information related to the amount of movement, a third sensor provided in the construction machine and configured to detect third information relating to angular velocity and acceleration; and a control unit. The control unit has a SLAM processing unit, an odometry processing unit, and a weighting processing unit. The SLAM processing unit uses the first information to obtain a first estimated position by calculating a position using SLAM (Simultaneous Localization And Mapping). The odometry processing unit uses the second information to obtain a second estimated position by calculating a position using odometry. The weighting processing unit obtains a third estimated position based on the first estimated position and the second estimated position. The SLAM processing unit, for example, performs blur correction for the first sensor using the third information, and obtains the first estimated position using the first information after the blur correction. The odometry processing unit, for example, performs slippage correction using the third information and obtains the second estimated position after slippage correction. The weighting processing unit, for example, weights the first estimated position and the second estimated position, and obtains the third estimated position based on the weighted values by calculation using a statistical method. In the automatic driving system according to the present invention, in addition to SLAM, odometry is used to estimate the position. Therefore, it is possible to estimate the vehicle's own position even in a tunnel with few characteristic points, and as a result, automatic driving in the tunnel can be performed. 。 The construction machine may have a plate-shaped base mounted on a vehicle body. For example, the first sensor is mounted on an upper surface of the base, and the third sensor is mounted on a lower surface of the base.
[0006] The vehicle may further include a server that stores an environmental map used in the SLAM. In this case, the SLAM processing unit transmits a new environmental map acquired in association with autonomous driving to the server, and the server updates the stored environmental map with the new environmental map or accumulates and stores the new environmental map. This makes it possible to respond to changes inside the tunnel (e.g., progress on the lining, movement of objects, extension of excavation distance, etc.). The vehicle may further include a receiver for receiving fourth information transmitted from a positioning satellite. In this case, the control unit may have a determination unit for determining whether or not the vehicle is inside a tunnel, and may use the fourth information to determine an estimated position when the vehicle is outside a tunnel. In this way, the method of estimating the vehicle's own position can be switched to an appropriate one when entering or exiting a tunnel, enabling highly accurate autonomous driving both inside and outside the tunnel. Effect of the Invention
[0007] According to the present invention, automatic operation inside a tunnel is possible. [Brief description of the drawings]
[0008] [Figure 1] 1 is a schematic configuration diagram of an autonomous driving system according to a first embodiment of the present invention. FIG. [Diagram 2] FIG. 1 is an image diagram of an autonomous driving mechanism in an autonomous driving system according to a first embodiment of the present invention. [Diagram 3] FIG. 1 is a diagram for explaining a position estimation technique using scan matching. [Figure 4] 1A is a perspective view showing the LiDAR in an installed state, FIG. 1B is a side view, and FIG. 1C is a plan view. [Diagram 5] FIG. 2 is a block diagram for explaining functions of a control unit. [Figure 6] FIG. 1 is an image showing an overview of SLAM (Simultaneous Localization And Mapping) technology. [Figure 7] This is an image of self-location estimation using LiDAR when there are feature points. [Figure 8] This is an image of self-location estimation using LiDAR when there are no feature points. [Figure 9] FIG. 1 is a diagram for explaining a calculation formula used in odometry, where (a) is a schematic diagram of a construction machine equipped with crawlers, and (b) is a diagram showing a model of an opposing two-wheel vehicle. [Figure 10] 4 is a flowchart showing a process flow of a self-position estimation unit. FIG. [Figure 11] FIG. 11 is a sequence diagram illustrating an example of a route (waypoint) generation process. [Figure 12] FIG. 1 is an example of a sequence diagram illustrating a series of processes related to autonomous driving. [Figure 13] FIG. 1 is a schematic configuration diagram of an autonomous driving system according to a second embodiment of the present invention. [Figure 14] 13 is an example of a flowchart showing an automatic update process of three-dimensional map information. [Figure 15] FIG. 11 is a schematic configuration diagram of an autonomous driving system according to a third embodiment of the present invention. [Figure 16] 13 is an example of a flowchart illustrating a map information switching process. [Figure 17] 13 is an example of a flowchart illustrating a map information switching process. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0009] Hereinafter, the embodiment of the present invention will be described in detail with reference to the drawings. Each drawing is merely a schematic illustration to allow a sufficient understanding of the present invention. Therefore, the present invention is not limited to the illustrated examples. In each drawing, common or similar components are denoted by the same reference numerals, and duplicated explanations thereof will be omitted. [First embodiment] <Configuration of the autonomous driving system according to the first embodiment> The configuration of an automatic driving system 1 according to the first embodiment will be described with reference to FIG. 1. FIG. 1 is a schematic configuration diagram of the automatic driving system 1. The automatic driving system 1 may constitute a part of another system, for example, may constitute a part of a construction system related to the construction of a tunnel. The automatic driving system 1 shown in FIG. 1 is a system in which a construction machine 3 moves within a tunnel by automatic driving. The automatic driving system 1 can be used for various types of tunnels without limiting the type of tunnel. In addition, the type of the construction machine 3 and the purpose for which the construction machine 3 moves are not limited.
[0010] First, an overview of the mechanism of autonomous driving in the autonomous driving system 1 will be described with reference to Fig. 2. Fig. 2 is an image diagram of the mechanism of autonomous driving in the autonomous driving system 1. As shown in FIG. 2, in the autonomous driving system 1, a route 8 along which the construction machine 3 moves is set in advance within the tunnel 2, and the construction machine 3 moves by tracing the route 8. The route 8 is made up of a number of waypoints 9. The waypoints 9 are points through which the construction machine 3 passes during autonomous driving. The waypoints 9 are set at predetermined intervals (for example, 1 m intervals), and each waypoint 9 is associated with position information (coordinate information) and speed information. The construction machine 3 achieves autonomous driving by passing through the waypoints 9 in order while estimating its own position. In this embodiment, as a preparation process for automatic driving, a human drives the construction machine 3 along a route 8 to register information on a waypoint 9. For example, a route 8 is drawn in a tunnel in a manner that can be recognized by a human, and the construction machine 3 is driven along the drawn route 8 to register information on a waypoint 9. If the construction machine is outside the tunnel, it is possible to estimate its own position using information transmitted from a positioning satellite used in a global navigation satellite system (GNSS: Global Navigation Satellite System), so that it is easy to estimate its own position when registering a waypoint 9 and when driving automatically. However, radio waves from a positioning satellite do not reach the inside of a tunnel, and it is not possible to estimate its own position using the GNSS. Therefore, in this embodiment, a position estimation technique using scan matching (see FIG. 3) and a position estimation technique using odometry are combined to estimate the position of the construction machine 3 when registering a waypoint 9 and when driving automatically. Fig. 3 is a diagram for explaining the position estimation technology using scan matching. As shown in Fig. 3, the self-position is estimated by comparing the environmental map acquired in advance (see Fig. 3(a)) with the environmental map acquired at the current position (see Fig. 3(b)).
[0011] The automatic driving system 1 shown in FIG. 1 mainly includes a construction machine 3 and a management PC (Personal Computer) 4. The construction machine 3 is placed inside the tunnel 2 (inside the tunnel shaft). The installation location of the management PC 4 is not particularly limited, and it is installed, for example, in a monitoring room. A remote control controller 41 is connected to the management PC 4, and an operator can remotely control the construction machine 3 using the controller 41. The monitor remotely controls the construction machine 3 in special cases, such as when an error occurs during automatic driving. In other words, the remote control of the construction machine 3 is an auxiliary function and is not a function essential to the automatic driving system 1. The controller 41 is an example of an HMI (Human Machine Interface). It is also possible for a human being to ride and drive the construction machine 3.
[0012] The construction machine 3 shown in Fig. 1 is a vehicle used in tunnel construction and is capable of moving inside a tunnel. In this embodiment, a crawler dump truck is assumed as the construction machine 3. The construction machine 3 mainly comprises a vehicle body unit 31, a moving unit 32, a communication unit 33, a sensor unit 34, and a control unit 35. Note that the configuration of the construction machine 3 shown in Fig. 1 is merely an example. The construction machine 3 may be, for example, a manned machine that has been improved so that it can be driven automatically. The vehicle body 31 has a driver's cab where operation takes place. A camera for remote control is installed in the driver's cab, and the camera captures images of the area ahead of the construction machine 3. The vehicle body 31 is rotatable about a vertical axis. The moving unit 32 is a mechanism for moving the construction machine 3, and is installed under the vehicle body 31. The moving unit 32 is composed of wheels 32a and crawlers 32b surrounding the wheels 32a. The moving unit 32 does not have to be of the crawler type shown in FIG. 1, but may be of the wheel type. The communication unit 33 is a device that realizes wireless communication with the management PC 4. The communication unit 33 is composed of, for example, an antenna and its peripheral devices. The construction machine 3 (particularly, the control unit 35) transmits and receives information required for automatic driving to and from the management PC 4 via the communication unit 33.
[0013] The sensor unit 34 is a device that acquires information about the construction machine 3 itself and information about the environment in which the construction machine 3 is placed (for example, information about the surroundings). Information detected by the sensor unit 34 is used for controlling and monitoring automatic driving. The sensor unit 34 transmits the detected information to the control unit 35. The sensor unit 34 in this embodiment is mainly configured to include an encoder 34a for the crawlers, an encoder 34b for turning the vehicle body, an IMU (Inertial Measurement Unit) 34c, and a LiDAR (Light Detection and Ranging) 34d. The number of LiDARs 34d is not limited to one, and may be multiple. The crawler encoder 34a is attached to the output shaft of the motor that drives the wheels 32a and detects the angle of the output shaft. The information detected by the encoder 34a is used for position estimation using odometry. The body turning encoder 34b is attached to an axis that turns the body 31, and detects the angle of turning of the body 31. The information detected by the encoder 34b is used for position estimation using odometry. The IMU 34c includes, for example, a three-axis gyro sensor and a three-directional accelerometer, and calculates three-dimensional angular velocity and acceleration. The IMU 34c is installed on the underside of a plate-shaped base 31a installed on the front side of the vehicle body 31. The IMU 34c can measure the inclination and vibration of the construction machine 3. Information detected by the IMU 34c is used to correct position estimation using odometry and to correct blurring of the LiDAR 34d.
[0014] The LiDAR 34d is a device that detects the shape of surrounding objects using laser sensor (distance sensor) technology. The LiDAR 34d irradiates a large number of laser beams to the surroundings and receives the laser beams reflected off the objects. In this way, the LiDAR 34d obtains the shape of the surface of the surrounding objects as a set of coordinates of points that completely cover the surface (point cloud data). The point cloud data is, for example, relative coordinates (local coordinates with the installation position of the LiDAR 34d as the origin). The point cloud data (shape and distance) of the surrounding objects detected by the LiDAR 34d is associated with the measurement time. The LiDAR 34d in this embodiment will be described with reference to FIG. 4. FIG. 4 is a diagram for explaining the LiDAR 34d, in which (a) is a perspective view showing an installed state, (b) is a side view, and (c) is a plan view. As shown in FIG. 4(a), the LiDAR 34d is installed on the upper surface of a plate-shaped pedestal 31a installed in front of the vehicle body 31. The installation position of the LiDAR 34d is, for example, 1 m to 1.5 m from the ground. As shown in FIG. 4(b) and (c), the LiDAR 34d rotates n lasers ("n" is a plurality, for example, a dozen) 360 degrees and acquires information (coordinates, distance) of m points ("m" is, for example, hundreds of thousands of points) per second.
[0015] The control unit 35 is configured with, for example, a CPU (Central Processing Unit), a ROM (Read Only Memory), a RAM (Random Access Memory), etc. The control unit 35 may be built into the construction machine 3 in advance, or may be connected later (for example, a PC (Personal Computer)). As shown in FIG. 5, the control unit 35 mainly includes a sensing processing unit 35a, a self-position estimation unit 35b, a route generation unit 35c, and a vehicle control unit 35d. FIG. 5 is a block diagram for explaining the functions of the control unit 35. The control unit 35 realizes these functions by executing, for example, automatic driving software stored in a storage unit (not shown). The automatic driving software is an application program in which processing related to automatic driving is described, and similar or corresponding software is also stored in the management PC 4. Note that FIG. 2 shows only functions related to automatic driving.
[0016] The sensing processing unit 35a has a function of identifying objects (e.g., obstacles) present around (particularly in the traveling direction) the construction machine 3. Information detected by the LiDAR 34d is input to the sensing processing unit 35a. Information on the objects identified by the sensing processing unit 35a is output to the path generating unit 35c. The self-position estimation unit 35b is a function for estimating the position of the construction machine 3. The position of the construction machine 3 may be the position of a reference point set on the construction machine 3, for example, the center, center of gravity, or representative point of the construction machine 3. Information detected by the encoders 34a and 34b, the IMU 34c, and the LiDAR 34d is input to the self-position estimation unit 35b. As described above, in this embodiment, the position estimation of the construction machine 3 is performed by combining a position estimation technique using scan matching and a position estimation technique using odometry. For this reason, the self-position estimation unit 35b has a SLAM (Simultaneous Localization And Mapping) processing unit 35e related to the position estimation using scan matching, and an odometry processing unit 35f related to the position estimation using odometry. In addition, the self-position estimation unit 35b has a weighting processing unit 35g that weights the estimated position calculated by the SLAM processing unit 35e and the estimated position calculated by the odometry processing unit 35f to calculate a final estimated position. Details of the self-position estimation unit 35b will be described later. The position information estimated by the self-position estimating unit 35b is output to the route generating unit 35c.
[0017] The route generating unit 35c generates a route for the construction machine 3 during autonomous driving. For example, the route generating unit 35c generates a route to the next Waypoint 9. Information on objects identified by the sensing processing unit 35a and position information estimated by the self-position estimating unit 35b are input to the route generating unit 35c. As shown in FIG. 2, for example, when there is an obstacle in the traveling direction, an avoidance route is generated. The route information generated by the route generating unit 35c is output to the vehicle control unit 35d. The vehicle control unit 35d transmits control signals related to automatic driving to each unit of the construction machine 3. The route information generated by the route generation unit 35c and estimated position information are input to the vehicle control unit 35d. The vehicle control unit 35d calculates hydraulic valve operation amounts and the like based on the route information and position information, and outputs the calculated operation amounts and the like to each unit of the construction machine 3 as control signals.
[0018] (Regarding self-location estimation) The SLAM processing unit 35e will be described with reference to FIG. 6. FIG. 6 is an image diagram showing an overview of the SLAM technology. The SLAM technology is a technology in which a moving object performs self-location estimation and environmental map creation at the same time, and the moving object compares "measurement values obtained by sensing" with "measurement values obtained by moving" and performs convergent calculation of the error, thereby estimating the self-location on the created map. As shown in FIG. 6, the SLAM technology mainly performs processes (1) to (4). In process (1), the surrounding environmental map is acquired with the self-location set to "0", and in process (2), the self-location is estimated by comparing with the initially acquired environmental map. Next, in process (3), the newly acquired environmental map is superimposed on the position estimated in process (2) and the existing map, and in process (4), the self-location is estimated by comparing with the map acquired in process (3). Then, by repeating processes (3) and (4), continuous "environmental map data" and "coordinate data of self-location" are created.
[0019] Here, images of self-location estimation using the LiDAR 34d are shown in Fig. 7 and Fig. 8. Fig. 7 is an image diagram of self-location estimation using the LiDAR 34d when there is a feature point (e.g., an obstacle). Fig. 8 is an image diagram of self-location estimation using the LiDAR 34d when there is no feature point (e.g., an obstacle). In the matching process of point cloud data, point cloud data at different times are matched (overlapped) so that the number of common feature points is maximized. For example, as shown in FIG. 7(a), point cloud data obtained at time t1 and point cloud data obtained at time t2 are matched, and as shown in FIG. 7(b), the overlay position with the most matching point clouds is set as the correct overlay position. In this case, if there is a feature point, the matching process is quick (i.e., the correct overlay position can be found quickly), and the behavior of the construction machine 3 is stable. In FIG. 7, since there is an obstacle 7 in the tunnel 2, the obstacle 7 becomes a clear feature point, and the correct overlay position can be found quickly. On the other hand, as shown in FIG. 8(a), if the point cloud data does not include information on the obstacle that is a feature point, multiple overlay positions close to the correct answer are found as shown in FIG. 8(b). Therefore, since it becomes difficult to find the correct overlay position, the matching process is slowed down, and the behavior of the construction machine 3 becomes unstable. Therefore, when estimating the self-position by SLAM, the position calculation by odometry is performed in parallel to improve the processing speed and accuracy of the self-position estimation. The odometry here is a process for calculating the relative position of the construction machine 3 from the rotation amount of both the left and right crawlers 32b of the construction machine 3.
[0020] The odometry processing unit 35f will be described with reference to Fig. 9. Fig. 9 is a diagram for explaining a calculation formula used for odometry, in which (a) is a schematic diagram of a construction machine 3 equipped with a crawler 32b, and (b) is a diagram showing an opposing two-wheel vehicle model. In this embodiment, odometry calculation is performed by regarding the construction machine 3 shown in Fig. 9(a) as the opposing two-wheel vehicle model shown in Fig. 9(b). For the odometry calculation, for example, the following equations (1) to (5) are used. (Calculation formula for V and ω) V = (V R +V L ) / 2 ···Formula (1) ω=(V R -V L ) / 2d ···Formula (2) (coordinate) θ a =θ a-1 +ω ···Equation (3) X a =X a-1 +Vcosθ a ·Formula (4) Y a =Y a-1 +Vsinθ a ·Equation (5)
[0021] The process of the self-position estimation unit 35b will be described with reference to Fig. 10. Fig. 10 is a flow chart showing the flow of the process of the self-position estimation unit 35b. The SLAM processing unit 35e uses the point cloud data (first information on the shapes of surrounding objects) detected by the LiDAR 34d to obtain a first estimated position by calculating the position using SLAM. The odometry processor 35f uses the angle of the motor output shaft detected by the crawler encoder 34a (second information on the amount of movement) to calculate the position by odometry to obtain a second estimated position. The odometry processor 35f calculates the movement distance and speed based on the angle of the motor output shaft, for example, and calculates the relative position therefrom. Slip correction may be performed using information detected by the IMU 34c (angular velocity and acceleration). The weighting processing unit 35g obtains a third estimated position from the first estimated position obtained by the SLAM processing unit 35e and the second estimated position obtained by the odometry processing unit 35f. The weighting processing unit 35g, for example, weights the first estimated position and the second estimated position, and obtains a third estimated position based on the weighted value by calculation using a statistical method. The weighting processing unit 35g, for example, divides the distance and direction obtained by SLAM and the distance and direction obtained by odometry by weighting, and sets the synthesized position as the third estimated position. It is preferable to set weights for the first estimated position and the second estimated position according to the situation of the construction machine 3 and the surrounding situation. For example, when the construction machine 3 travels on a slippery road surface, it is considered that the accuracy of the position estimation by odometry is reduced, so it is preferable to lower the weighting for the second estimated position obtained by the odometry processing unit 35f compared to the weighting for the first estimated position (that is, it is preferable to lower the influence of the position estimation by odometry compared to the position estimation by SLAM).
[0022] <Operation of the autonomous driving system according to the first embodiment> The operation of the automatic driving system 1 according to this embodiment will be described with reference to Figs. 11 and 12 (see Figs. 1 to 10 as appropriate). Here, a case will be described in which, as a first step, a process of generating a route 8 (waypoint 9) is performed by manual driving by a person, and, as a second step, automatic driving is performed along the generated route 8. Fig. 11 is an example of a sequence diagram showing a process of generating a route (waypoint). Fig. 12 is an example of a sequence diagram showing a series of processes related to automatic driving. It is also possible to perform the process of generating the route 8 (waypoint 9) on a computer. Also, the components of the construction machine 3 excluding the control unit 35 (for example, the vehicle body unit 31, the moving unit 32, etc.) may be collectively referred to as the "actual machine unit".
[0023] (Route (Waypoint) Generation Process) The process of generating a route 8 will be described with reference to Fig. 11. It is assumed that the route 8 starts from a starting point, goes to a turning point, and returns to the starting point as a goal point. First, the manager starts up the automatic driving software stored in the control unit 35 of the construction machine 3 (step S1), and the driver enters the driver's cab of the construction machine 3 and releases the hydraulic lock lever (step S2). This completes preparations for running the construction machine 3. Next, the manager instructs the control unit 35 of the construction machine 3 to start SLAM processing (step S3), and then instructs the control unit 35 of the construction machine 3 to start recording waypoint 9 on the outbound journey (step S4). The driver operates the construction machine 3 to drive it manually (step S5). When the construction machine 3 has driven through the tunnel and reached the turnaround point, the manager instructs the control unit 35 of the construction machine 3 to end recording waypoint 9 on the outbound journey (step S6). This ends the recording of waypoint 9 on the outbound journey.
[0024] Next, the waypoint 9 on the return journey is recorded using the same procedure as for the outbound journey. The driver turns the body unit 31 of the construction machine 3 by 180 degrees and points the body unit 31 toward the goal position (the same as the start position) (Step S7). Next, the manager instructs the control unit 35 of the construction machine 3 to start recording waypoint 9 on the return journey (Step S8). The driver operates the construction machine 3 to drive it manually (Step S9). When the construction machine 3 has driven inside the tunnel and reached the goal point, the manager instructs the control unit 35 of the construction machine 3 to end recording waypoint 9 on the return journey (Step S10). This ends the recording of waypoint 9 on the return journey. After the manager confirms that the construction machine 3 is stopped at the goal position, he instructs the control unit 35 of the construction machine 3 to end the generation of the 3D map (step S11). The manager checks the generated 3D map and the trajectory of the machine's own position (step S12), and if this information has been generated correctly, generates a scenario based on the generated 3D map and the trajectory of the machine's own position (step S13). The scenario is generated by arranging the actions of, for example, "traveling," "pivot turn," "dump up," "dump down," and "upper swing" for each task, and putting them in the order of a series of construction actions.
[0025] (Autonomous driving processing) The automatic driving process will be described with reference to Fig. 12. First, the administrator starts the automatic driving software stored in the management PC 4 (step T1) and releases the hydraulic lock lever of the construction machine 3 (step T2). This completes preparations for running the construction machine 3. Next, the administrator operates the management PC 4 to start automatic driving (step T3), and the management PC 4 sends an instruction to start automatic driving to the control unit 35 of the construction machine 3 (step T4). This starts automatic driving of the construction machine 3. The control unit 35 sends control instructions to the vehicle body unit 31, the moving unit 32, etc. (actual machine units) during the period when the construction machine 3 is operating automatically (step T5), and the actual machine units send data related to the actual machine units (actual machine data) detected during automatic driving to the control unit 35 (step T6). The transmission of the control instructions in step T5 and the actual machine data in step T6 is performed periodically. The control unit 35 notifies the management PC 4 of the automatic driving status at a predetermined timing (step T7).
[0026] Furthermore, if the construction machine 3 goes into a waiting state for some reason (for example, a malfunction of the construction machine 3), the manager checks whether the state can be released, and if so, performs a wait release operation on the management PC 4 (step T8). The management PC 4 sends an instruction to release the wait for automatic operation to the control unit 35 of the construction machine 3 (step T9). This causes the automatic operation of the construction machine 3 to resume. With the resumption of automatic operation, the control unit 35 sends control instructions to the vehicle body unit 31, the moving unit 32, etc. (actual machine unit) (step T10), and the actual machine unit sends data related to the actual machine unit (actual machine data) detected during automatic operation to the control unit 35 (step T11). The control unit 35 notifies the management PC 4 of the state of automatic operation at a predetermined timing (step T12).
[0027] When terminating automatic operation, the manager sends a stop instruction to the management PC 4 (step T14), and the management PC 4 transmits the stop instruction to the control unit 35 of the construction machine 3 (step T15). The control unit 35 that receives the stop instruction executes a stop process (step T16) and transmits a stop instruction to the vehicle body unit 31, the moving unit 32, etc. (actual machine unit) (step T17). Then, the control unit 35 notifies the management PC 4 of the interruption of automatic operation (step T18). Furthermore, if the control unit 35 of the construction machine 3 detects any error (step T19), the control unit 35 executes a stop process (step T20) and transmits a stop instruction to the vehicle body unit 31, the moving unit 32, etc. (actual machine unit) (step T21). Then, the control unit 35 notifies the management PC 4 that an error has occurred during automatic operation (step T22). As described above, in the autonomous driving system 1 according to the first embodiment, in addition to SLAM-based position estimation, odometry-based position estimation is performed. Therefore, it is possible to estimate the vehicle's own position even inside a tunnel with few feature points, and as a result, autonomous driving inside the tunnel can be performed.
[0028] [Second embodiment] In the first embodiment, the case where automatic driving is repeatedly performed is not assumed. In the second embodiment, control in the case where automatic driving is repeatedly performed will be described. Note that repeated automatic driving includes a case where one construction machine 3 repeatedly performs automatic driving multiple times, and a case where multiple construction machines 3 perform automatic driving in sequence. In the second embodiment, the 3D map information is automatically updated every time automatic driving is performed. <Configuration of the autonomous driving system according to the second embodiment> The configuration of an autonomous driving system 101 according to the second embodiment will be described with reference to Fig. 13. Fig. 13 is a schematic configuration diagram of the autonomous driving system 101. As shown in Fig. 13, the autonomous driving system 101 includes a server 5 that constitutes a cloud system. An environmental map used in SLAM is stored in the server 5. The SLAM processing unit 35e of the construction machine 3 transmits a new environmental map acquired in association with the autonomous driving to the server 5, and the server 5 updates the stored environmental map with the new environmental map, or accumulates and stores the new environmental map.
[0029] <Method for automatically updating 3D map information by the autonomous driving system according to the second embodiment> A method for automatically updating 3D map information by the autonomous driving system 101 according to the second embodiment will be described with reference to Fig. 14. Fig. 14 is an example of a flowchart showing the automatic update process of 3D map information. The automatic update process of 3D map information is mainly composed of four steps (step (A) to step (D)). In step (A), the construction machine 3 is driven. In process (B), the environmental map and waypoint data obtained by running the construction machine 3 are stored in the server. In step (C), the environmental map and waypoint data from the previous trip are obtained from the server. In step (D), the construction machine 3 is driven on a new route, and the environmental map and waypoint data from the previous route are matched with the environmental map and waypoint data from the current route. During the first run (first vehicle), steps (A) to (B) are carried out, and from the second run (second vehicle) onwards, steps (B) to (D) are carried out.
[0030] With reference to FIG. 14, the automatic update process of the 3D map information from the first run (first vehicle) to the second run (third vehicle) will be described. (Processing of the first run (first car) (Step U10)) The first run (first unit) of construction machine 3 (vehicle) runs (process (A)), and the environmental map and waypoint data obtained during the first run are stored on the server (process (B)). (Processing the second run (second vehicle) (Step U20)) The construction machine 3 (vehicle) on the second run (second unit) acquires the environmental map and waypoint data of the first run (first unit) stored in step U10 from the server (process (C)). The construction machine 3 (vehicle) on the second run (second unit) matches the environmental map and waypoint data of the first run acquired from the server with the environmental map and waypoint data acquired during the second run (current run) (process (D)). In addition, the construction machine 3 (vehicle) saves the environmental map and waypoint data acquired during the second run as the latest data on the server (process (B)). (Processing the third run (third vehicle) (Step U30)) The construction machine 3 (vehicle) on its third run (third unit) acquires the environmental map and Waypoint data of its second run (second unit) stored in step U20 from the server (process (C)). The construction machine 3 (vehicle) on its third run (third unit) matches the environmental map and Waypoint data of its second run acquired from the server with the environmental map and Waypoint data obtained during its third run (current run) (process (D)). It also saves the environmental map and Waypoint data obtained during its third run as the latest data on the server (process (B)). Thereafter, the process is repeated from the fourth run (fourth unit) onwards. As described above, the automatic driving system 101 according to the second embodiment can respond to changes inside the tunnel (for example, progress of lining, movement of objects, extension of excavation distance, etc.).
[0031] [Third embodiment] In the first embodiment, it is assumed that the vehicle moves only inside the tunnel. In the third embodiment, control in the case where the vehicle also moves in and out of the tunnel 2 will be described. <Configuration of the autonomous driving system according to the third embodiment> The configuration of an automatic driving system 201 according to the third embodiment will be described with reference to Fig. 15. Fig. 15 is a schematic configuration diagram of the automatic driving system 201. As shown in Fig. 15, the automatic driving system 201 includes a function (receiving unit) for the construction machine 3 to receive radio waves from a positioning satellite 6. The control unit 35 of the construction machine 3 has a determination unit that determines whether or not it is inside the tunnel 2, and when outside the tunnel 2, it uses information (fourth information) transmitted from the positioning satellite 6 to obtain an estimated position. The positioning satellite 6 is a satellite used in the Global Navigation Satellite System (GNSS), and periodically transmits its own position information (orbital position information) and time information to the construction machine 3. The positioning satellite 6 may be, for example, a Global Positioning System (GPS) satellite, a Global Navigation Satellite System (GLONASS) satellite, a Galileo satellite, a quasi-zenith satellite, etc. Information (fourth information) transmitted from the positioning satellite 6 is used in the construction machine 3, for example, to control the position (latitude, longitude, altitude).
[0032] <Map information switching process by the autonomous driving system according to the third embodiment> The map information switching process by the automated driving system 201 according to the third embodiment will be described with reference to Fig. 16 and Fig. 17. Fig. 16 and Fig. 17 are diagrams illustrating an example of a flowchart showing the map information switching process. (First map information switching process) FIG. 16 shows the first map information switching process. The control unit 35 of the construction machine 3 constantly checks whether the waypoint travel by GNSS has reached the end position (i.e., the entrance of the tunnel) (step V1). When the waypoint travel has reached the end position, the control unit 35 makes the waypoint 9 for SLAM travel (step V3). On the other hand, when the waypoint travel has not reached the end position, the control unit 35 makes the waypoint 9 for GNSS travel (step V2). The first map information switching process assumes, for example, the following situation. For example, when the task of waypoint travel by GNSS outside the tunnel is completed and the tunnel entrance is reached, a scenario is set so that waypoint travel by SLAM starts as the next task. The scenario is to arrange actions such as "travel" by task and arrange them in the order of a series of construction actions. When the scenario is set in this way, when the waypoint travel by GNSS has reached the end position (i.e., the entrance of the tunnel), the travel task by GNSS is automatically transitioned to the travel task by SLAM. In other words, the GNSS-based driving task ends at the entrance to the tunnel, and from there it switches to a SLAM-based driving task according to a pre-set scenario.
[0033] (Second map information switching process) FIG. 17 shows the second map information switching process. The control unit 35 of the construction machine 3 constantly checks whether GNSS radio waves are being received (step W1). This process is, for example, to determine whether the reception level of the GNSS radio waves has fallen below a threshold. If the GNSS radio waves are not being received, the control unit 35 travels along the SLAM waypoint 9 (step W3). On the other hand, if the GNSS radio waves are being received, the control unit 35 travels along the GNSS waypoint 9 (step W2). The second map information switching process assumes, for example, the following situation. For example, when traveling under a high-precision environmental map using GNSS, if the GNSS reception level suddenly falls below a threshold, from that point on, the process is automatically switched to traveling according to SLAM using a high-precision environmental map. Examples of when the GNSS reception level falls below the threshold include when the number of receivable satellites simply decreases, when it becomes impossible to acquire L1 signals from the Quasi-Zenith Satellite System (QZSS), when GNSS based on RTK positioning changes from a fixed solution to a float solution, etc. In other words, these are cases when centimeter-level positioning becomes impossible overall.
[0034] As described above, according to the autonomous driving system 201 of the third embodiment, the method of estimating the vehicle's own position can be switched to an appropriate one when entering or exiting the tunnel 2, thereby enabling highly accurate autonomous driving both inside and outside the tunnel. Although the embodiment of the present invention has been described above, the present invention is not limited to this and can be practiced within the scope of the claims. [Explanation of symbols]
[0035] 1,101,201 Autonomous Driving System 2. Tunnel 3. Construction machinery 4 Management PC 5 Server 6 Positioning satellites 8 Routes 9 Waypoint 31 Body 31a Pedestal 32 Mobile section 32a wheels 32b Crawler 33 Communications Department 34 Sensor section 34a Encoder (second sensor) 34b Encoder 34c IMU (third sensor) 34d LiDAR (first sensor) 35 Control section 35a Sensing processing section 35b Self-position estimation section 35c Route Generation Unit 35d Vehicle control unit 35e SLAM processing section 35f Odometry processing section 35g Weighting processing section 41 Controller
Claims
1. An automatic driving system for construction machinery moving inside a tunnel, A first sensor provided on the construction machine and configured to detect first information relating to a shape of a surrounding object; a second sensor provided on a moving part of the construction machine and configured to detect second information relating to a moving amount; a third sensor provided in the construction machine and configured to detect third information relating to angular velocity and acceleration; A control unit, The control unit is a SLAM (Simultaneous Localization and Mapping) processing unit that uses the first information to calculate a position by SLAM to obtain a first estimated position; an odometry processing unit that uses the second information to calculate a second estimated position by odometry; a weighting processing unit that determines a third estimated position based on the first estimated position and the second estimated position, the SLAM processing unit performs blur correction for the first sensor using the third information, and obtains the first estimated position using the first information after the blur correction; The odometry processing unit performs slippage correction using the third information to obtain the second estimated position after slippage correction. An automated driving system characterized by
2. the weighting processing unit weights the first estimated position and the second estimated position, and obtains the third estimated position based on the weighted values by calculation using a statistical method. The automated driving system according to claim 1 .
3. The construction machine has a plate-shaped base installed on a vehicle body, The first sensor is installed on an upper surface of the base, and the third sensor is installed on a lower surface of the base. The automated driving system according to claim 1 .
4. A server that stores an environmental map used in the SLAM is further provided. The SLAM processing unit transmits a new environmental map acquired in association with autonomous driving to the server, The server updates the stored environmental map with the new environmental map, or accumulates and stores the new environmental map. The automatic driving system according to any one of claims 1 to 3.
5. A receiving unit that receives fourth information transmitted from the positioning satellite, The control unit has a determination unit that determines whether or not the vehicle is inside a tunnel, and when the vehicle is outside a tunnel, the control unit determines an estimated position by using the fourth information. The automatic driving system according to any one of claims 1 to 4.
Citation Information
Patent Citations
Management system for carrier
JP2003044141A
Tunnel section detection device, control method, program, and storage medium
JP2015121416A
Information processing apparatus, information terminal, and information processing method
JP2017068589A
Autonomous travel controller and autonomous travel method
JP2017204089A
Semi-automatic trailer and container terminal system
JP2017228198A