Lifting device and construction method for lifting device
The lifting device with an upper bracket, rail section, and adjustable connecting member addresses safety risks and efficiency issues in lifting under elevated structures, ensuring stable and timely material handling.
Patent Information
- Application Number
- JP2021016308
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-02-04
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2041-02-04
AI Technical Summary
Existing lifting technologies, such as those described in Patent Document 1, face safety risks due to the load of hanger rails acting downward on upper support beams, potentially causing the hanger rail to fall, especially in spaces under elevated structures where mobile cranes cannot be used.
A lifting device comprising an upper receiving bracket on the upper surface of an elevated structure, a rail section on the lower surface connected by a connecting member, and a lifting machine movable along the rail, with adjustable components to accommodate varying heights and ensure stability.
Enables safe and efficient lifting of materials under elevated structures, reducing safety risks and shortening construction time by stabilizing the rail system and allowing installation without obstructing vehicle traffic or requiring additional drilling.
Smart Images

Figure 0007558832000001 
Figure 0007558832000002 
Figure 0007558832000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a lifting device and a method for installing the lifting device. [Background technology]
[0002] Normally, when installing supports for reinforcing or replacing the main slab in the space under the girders of an existing viaduct, a mobile crane is used to lift the materials. However, in places where there is insufficient space under the girders, the boom of the mobile crane may come into contact with the existing viaduct, making it impossible to use the mobile crane.
[0003] Conventionally, a temporary construction work device for working on a structure is disclosed in Patent Document 1. The temporary construction work device of Patent Document 1 comprises a hanger rail attached along a structure, a hoisting machine movably mounted on the hanger rail, a second hoisting machine suspended by the hoisting machine and connected to the hoisting machine in a state in which it can rotate along a horizontal plane, and a truss beam supported by the hoisting machine. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] Japanese Patent Application Publication No. 1-287363 Summary of the Invention [Problem to be solved by the invention]
[0005] However, in the technology disclosed in Patent Document 1, the hanger rail is attached to an existing upper support beam, so the load of the hanger rail etc. acts downward on the upper support beam, posing safety issues such as the risk of the hanger rail falling.
[0006] Therefore, the present invention has been devised in consideration of the above-mentioned problems, and its object is to provide a lifting device and a construction method for a lifting device that makes it possible to lift materials in the space under an elevated structure, thereby improving safety. [Means for solving the problem]
[0007] The lifting device according to the present invention is a lifting device used when lifting materials in a space under an elevated structure, and includes an upper receiving bracket placed on the upper surface side of the elevated structure, a rail section arranged on the lower surface side of the elevated structure, a connecting member connecting the upper receiving bracket and the rail section, and a lifting machine movable along the rail section. The upper support bracket is installed on a first elevated structure and a second elevated structure that is erected at a distance from the first elevated structure, and the connecting member is disposed between the first elevated structure and the second elevated structure. It is characterized by the above. The lifting device of the present invention is a lifting device used when lifting materials in the space under an elevated structure, and comprises an upper receiving bracket placed on the upper side of the elevated structure, a rail section arranged on the underside of the elevated structure, a connecting member connecting the upper receiving bracket and the rail section, and a lifting machine movable along the rail section, wherein the connecting member is arranged in a through hole that penetrates from the upper side to the underside of the elevated structure. The lifting device of the present invention is a lifting device used when lifting materials in the space under an elevated structure, and comprises an upper receiving bracket placed on the upper side of the elevated structure, a rail section arranged on the underside of the elevated structure, a connecting member connecting the upper receiving bracket and the rail section, and a lifting machine capable of moving along the rail section, wherein the rail section has a first plate section arranged opposite the underside of the elevated structure, and an adjustment member that penetrates the first plate section and is capable of adjusting the protruding length from the upper surface of the first plate section.
[0008] The construction method of the lifting device according to the present invention includes an installation step of placing an upper receiving bracket on the upper surface side of an elevated structure and connecting the upper receiving bracket and a rail portion disposed on the lower surface side of the elevated structure with a connecting member, and an attachment step of attaching a lifting machine movable along the rail portion to the rail portion. The upper receiving bracket is installed on a first elevated structure and a second elevated structure that is erected at a distance from the first elevated structure, and in the installation step, the connecting member is disposed between the first elevated structure and the second elevated structure. It is characterized by the above. The construction method of the lifting device of the present invention comprises an installation process in which an upper receiving bracket is placed on the upper side of an elevated structure and the upper receiving bracket and a rail section arranged on the underside of the elevated structure are connected with a connecting member, and an attachment process in which a lifting machine movable along the rail section is attached to the rail section, and is characterized in that in the installation process, the connecting member is placed in a through hole that penetrates from the upper side to the underside of the elevated structure. The construction method of the lifting device of the present invention comprises an installation process in which an upper receiving bracket is placed on the upper surface of an elevated structure and the upper receiving bracket and a rail section arranged on the underside of the elevated structure are connected by a connecting member, and an attachment process in which a lifting machine capable of moving along the rail section is attached to the rail section, wherein the rail section has a first plate section arranged opposite the underside of the elevated structure, and an adjustment member that penetrates the first plate section and is capable of adjusting the protruding length from the upper surface of the first plate section, and the installation process is characterized in that the protruding length of the adjustment member from the upper surface of the first plate section is adjusted and the upper end of the adjustment member is brought into contact with the underside of the elevated structure. Effect of the Invention
[0009] According to the present invention, it is possible to provide a technology that makes it possible to lift materials in the space under an elevated structure, thereby improving safety. [Brief description of the drawings]
[0010] [Figure 1] FIG. 1 is a diagram showing an example of an elevated structure in which the lifting device according to the first embodiment is used. [Diagram 2] FIG. 2 is an enlarged view of the lifting device according to the first embodiment. [Diagram 3]FIG. 3 is a diagram showing an example of a method of using the lifting device according to the first embodiment. [Figure 4] FIG. 4 is an enlarged view of a lifting device according to the second embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0011] Hereinafter, a lifting device and a method for constructing a lifting device according to an embodiment will be described in detail with reference to the drawings.
[0012] First Embodiment As shown in Fig. 1, the lifting device 1 according to the first embodiment is used to lift materials in the space below an elevated structure 9 such as a bridge. The lifting device 1 is used during assembly and dismantling of supports 8 for holding a main slab 93 of the elevated structure 9 when reinforcing and replacing the main slab 93. The elevated structure 9 has a first elevated structure 91 and a second elevated structure 92 erected at a distance from the first elevated structure 91. The lifting device 1 is provided between the first elevated structure 91 and the second elevated structure 92.
[0013] 2, the lifting device 1 includes a lifting machine 5 and a holding section 6 that holds the lifting machine 5 on an elevated structure 9. The holding section 6 includes an upper receiving bracket 2, a rail section 3, and a connecting member 4.
[0014] The upper receiving bracket 2 is placed on the upper surface 9a side of the elevated structure 9. The upper receiving bracket 2 is erected between the first elevated structure 91 and the second elevated structure 92. The upper receiving bracket 2 is made of steel such as H-shaped steel or channel steel.
[0015] The rail portion 3 is disposed on the underside 9b of the elevated structure 9. The rail portion 3 has a first plate portion 31, a rail main body portion 32, and an adjustment member 33.
[0016] The first plate portion 31 is made of a steel plate or the like and is disposed opposite the lower surface 9b of the elevated structure 9. The first plate portion 31 is disposed so as to straddle the first elevated structure 91 and the second elevated structure 92. The rail main body portion 32 is made of an I-beam or the like.
[0017] The adjustment member 33 is, for example, a bolt that penetrates the first plate portion 31. The adjustment member 33 is capable of adjusting the protruding length from the upper surface of the first plate portion 31, and the upper end of the adjustment member 33 is in contact with the lower surface 9b of the elevated structure 9. The adjustment member 33 fixes the rail main body portion 32 to the first plate portion 31. The adjustment members 33 are arranged on both sides of the connecting member 4.
[0018] Here, there are cases where the heights of the lower surfaces 9b of the elevated structures 9 on both sides of the connecting member 4 are different. For example, the height of the lower surface 9b of the first elevated structure 91 is disposed at a position higher than the height of the lower surface 9b of the second elevated structure 92.
[0019] The connecting member 4 connects the rail portion 3 and the lifting machine 5. The connecting member 4 is composed of, for example, a rod-shaped member 41 such as a PC steel bar extending in the height direction Z, and a nut 42 that can be screwed onto the rod-shaped member 41. The connecting member 4 is disposed between the first elevated structure 91 and the second elevated structure 92.
[0020] The lifting machine 5 is capable of lifting materials, and for example, an electric chain block is used. The lifting machine 5 is capable of traveling and moving along the rail section 3. The lifting machine 5 is also capable of rotating in the horizontal direction.
[0021] Next, a description will be given of a construction method for the lifting device according to the first embodiment. The construction method for the lifting device includes an installation step and an attachment step that is performed after the installation step.
[0022] First, in the installation process, the upper receiving bracket 2 is placed on the upper surface 9a side of the elevated structure 9. In the installation process, the upper receiving bracket 2 is erected between a first elevated structure 91 and a second elevated structure 92 that are erected with a gap between them in the direction perpendicular to the bridge axis Y. A plurality of upper receiving brackets 2 are provided in the bridge axis direction X.
[0023] Then, in the installation process, the connecting member 4 is installed on the upper receiving metal fitting 2 using a high-altitude work vehicle or the like. The connecting member 4 is disposed between the first elevated structure 91 and the second elevated structure 92.
[0024] Then, in the installation process, the rail portion 3 is installed on the connecting member 4 using a high-altitude work vehicle or the like. As a result, the upper receiving bracket 2 and the rail portion 3 are connected by the connecting member 4. In detail, in the installation process, the first plate portion 31 is arranged facing the lower surface 9b of the elevated structure 9, and the first plate portion 31 is connected to the connecting member 4. Then, in the installation process, the rail main body portion 32 is fixed to the first plate portion 31 by the adjustment member 33. At this time, the protruding length of the adjustment member 33 from the upper surface of the first plate portion 31 is adjusted, and the upper end of the adjustment member 33 is brought into contact with the lower surface 9b of the elevated structure 9. This allows the rail main body portion 32 to be adjusted horizontally. The rail portions 3 are provided sequentially so as to extend in the bridge axis direction X.
[0025] Next, in the installation process, the lifting machine 5 is installed on the rail main body portion 32.
[0026] This completes the construction method for the lifting device according to the first embodiment.
[0027] When assembling the shoring 8 using the lifting device 1, as shown in Fig. 3, the girder 81 in the material yard is lifted up by the lifting machine 5. Then, the lifting machine 5 is moved along the rail section 3 to the assembly location of the shoring 8. Then, the lifting machine 5 is rotated horizontally, the girder 81 is installed, and the shoring 8 is assembled.
[0028] According to this embodiment, a lifting machine 5 capable of moving along the rail portion 3 is provided. This makes it possible to lift materials such as long beams 81 in the space below the elevated structure 9.
[0029] According to this embodiment, there is provided an upper receiving bracket 2 that is placed on the upper surface 9a side of the elevated structure 9. This makes it possible to support the upper receiving bracket 2, on which the load of the rail section 3 acts, from below the existing elevated structure 9. This makes it possible to hold the rail section 3 in a more stable state, thereby increasing safety.
[0030] According to this embodiment, the upper receiving bracket 2 is erected on a first elevated structure 91 and a second elevated structure 92 erected at a distance from the first elevated structure 91, and the connecting member 4 is disposed between the first elevated structure 91 and the second elevated structure 92. This makes it possible to connect the upper receiving bracket 2 and the rail section 3 by the connecting member 4 in a short time without requiring work such as drilling holes in the first elevated structure 91 and the second elevated structure 92. This makes it possible to shorten the construction time.
[0031] In addition, according to this embodiment, the connecting member 4 is disposed between the first elevated structure 91 and the second elevated structure 92. As a result, even when the first elevated structure 91 and the second elevated structure 92 are in service and vehicles or the like are passing between them, the upper receiving bracket 2 does not impede the passage of vehicles. Therefore, even when the elevated structure 9 is in service, the lifting device 1 can be installed without traffic restrictions.
[0032] According to this embodiment, there is provided a first plate portion 31 disposed opposite the lower surface 9b of the elevated structure 9, and an adjustment member 33 penetrating the first plate portion 31 and capable of adjusting the protruding length from the upper surface of the first plate portion 31. As a result, even if the height of the lower surface 9b of the first elevated structure 91 and the height of the lower surface 9b of the second elevated structure 92 are different, it is possible to adjust the rail portion 3 horizontally by adjusting the protruding length of the adjustment member 33.
[0033] According to this embodiment, the adjustment members 33 are disposed on both sides of the connecting member 4. This makes it easier to adjust the rail portion 3 to be horizontal. This makes it possible to shorten the installation time of the lifting device 1.
[0034] <Second embodiment> In the lifting device 1 according to the second embodiment, as shown in FIG. 4, the connecting member 4 is disposed in a through hole 99 that penetrates the elevated structure 9 from the upper surface 9a side to the lower surface side.
[0035] Next, a description will be given of a construction method for a lifting device according to the second embodiment. The construction method for a lifting device includes an installation step and an attachment step carried out after the installation step.
[0036] First, in the installation process, the upper receiving bracket is placed on the upper surface 9a side of the elevated structure 9. A plurality of upper receiving brackets 2 are provided in the bridge axis direction X.
[0037] Then, in the installation process, a drilling device is used to drill a through hole 99 from the upper surface 9a side to the lower surface 9b side of the elevated structure 9, the connecting member 4 is placed in the through hole 99, and the connecting member 4 is installed on the upper receiving bracket 2. Note that if the through hole 99 has been prepared in advance, the connecting member 4 may be placed in the through hole 99 without performing the drilling work.
[0038] Then, in the installation process, the rail portion 3 is installed on the connecting member 4 using a high-altitude work vehicle or the like. As a result, the upper receiving bracket 2 and the rail portion 3 are connected by the connecting member 4. Details are omitted since they are the same as those in the first embodiment.
[0039] Next, in the attachment process, the lifting machine 5 is attached to the rail main body 32 in the same manner as in the first embodiment.
[0040] This completes the construction method for the lifting device according to the second embodiment.
[0041] According to this embodiment, the connecting member 4 is placed in a through hole 99 that penetrates from the upper surface 9a side to the lower surface 9b side of the elevated structure 9. This makes it possible to set the position of the upper receiving bracket 2 placed on the upper surface 9a side of the elevated structure 9 according to the position where the through hole 99 is drilled. This allows for a high degree of freedom in the construction of the lifting device 1.
[0042] Although the embodiment of the present invention has been described above, this embodiment is presented as an example and is not intended to limit the scope of the invention. In addition, the above embodiment can be variously omitted, replaced, and modified without departing from the gist of the present invention. Such novel forms and modifications are included within the scope and gist of the present invention, and are included in the scope of the invention described in the claims and the equivalents of the invention described in the claims. [Explanation of symbols]
[0043] 1: Lifting device 2: Upper bracket 3: Rail section 31: 1st plate part 32: Rail body 33: Adjustment parts 4: Connecting member 5: Lifting machine 6: Holding part 8: Shoring 81: Girder material 9: Elevated structure 9a:Top surface 9b: Bottom surface 91:1st elevated structure 92:Second elevated structure 93: Main version 99:Through hole X: Bridge axis direction Y: Perpendicular direction to the bridge axis Z: Height direction
Claims
1. A lifting device used to lift materials in the space under an elevated structure, An upper support bracket placed on the upper surface side of the elevated structure; A rail portion disposed on the underside of an elevated structure; a connecting member that connects the upper receiving metal fitting and the rail portion; A lifting machine movable along the rail portion, The upper receiving bracket is installed on a first elevated structure and a second elevated structure erected at a distance from the first elevated structure, The connecting member is disposed between the first elevated structure and the second elevated structure. A lifting device characterized by:
2. A lifting device used to lift materials in the space under an elevated structure, An upper support bracket placed on the upper surface side of the elevated structure; A rail portion disposed on the underside of an elevated structure; a connecting member that connects the upper receiving metal fitting and the rail portion; A lifting machine movable along the rail portion, The connecting member is disposed in a through hole passing through an elevated structure from the upper surface side to the lower surface side. A lifting device characterized by:
3. A lifting device used to lift materials in the space under an elevated structure, An upper support bracket placed on the upper surface side of the elevated structure; A rail portion disposed on the underside of an elevated structure; a connecting member that connects the upper receiving metal fitting and the rail portion; A lifting machine movable along the rail portion, The rail portion is A first plate portion disposed opposite to the underside of the elevated structure; An adjustment member that is inserted through the first plate portion and is capable of adjusting a length of protrusion from an upper surface of the first plate portion. and, A lifting device characterized by:
4. The adjustment members are disposed on both sides of the connecting member.
4. The lifting device according to claim 3,
5. an installation process in which an upper receiving bracket is placed on the upper surface of an elevated structure and the upper receiving bracket and a rail portion disposed on the lower surface of the elevated structure are connected to each other by a connecting member; and an attachment step of attaching a lifting machine movable along the rail portion to the rail portion, The upper receiving bracket is installed on a first elevated structure and a second elevated structure erected at a distance from the first elevated structure, In the installation step, the connecting member is disposed between the first elevated structure and the second elevated structure. A construction method for a lifting device, comprising:
6. an installation process in which an upper receiving bracket is placed on the upper surface of an elevated structure and the upper receiving bracket and a rail portion disposed on the lower surface of the elevated structure are connected to each other by a connecting member; and an attachment step of attaching a lifting machine movable along the rail portion to the rail portion, In the installation step, the connecting member is disposed in a through hole that penetrates from an upper surface side to a lower surface side of an elevated structure. A construction method for a lifting device, comprising:
7. an installation process in which an upper receiving bracket is placed on the upper surface of an elevated structure and the upper receiving bracket and a rail portion disposed on the lower surface of the elevated structure are connected to each other by a connecting member; and an attachment step of attaching a lifting machine movable along the rail portion to the rail portion, The rail portion is A first plate portion disposed opposite to the underside of the elevated structure; An adjustment member that is inserted through the first plate portion and is capable of adjusting a length of protrusion from an upper surface of the first plate portion. and In the installation step, a protruding length of the adjustment member from an upper surface of the first plate portion is adjusted, and an upper end of the adjustment member is brought into contact with a lower surface of an elevated structure. A construction method for a lifting device, comprising:
Citation Information
Patent Citations
Execution of bridge central closure part in cantilevered type construction method
JP1988284304A
Working device for temporary work
JP1989287363A
Suspended scaffold and erection method therefor
JP2020153208A
Bridge construction machinery and method for constructing bridges
US5549176A