Construction method of sliding hanger for closure section of continuous beam across existing line
By adopting the sliding hanging frame construction method in cross-existing lines, the problem of traditional construction methods occupying space for a long time is solved, and efficient and safe construction of the joint section is achieved, reducing the impact on the operation of the existing line and the construction cost.
Patent Information
- Application Number
- CN202510250477.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-04
- Publication Date
- 2025-04-04
- Estimated Expiration
- 2045-03-04
AI Technical Summary
Traditional construction methods require a long time to install and remove the hanger above the existing line, which leads to interference in the existing line operations, long construction cycle and high cost.
The construction method of sliding hanger spanning the existing wire continuous beam joint section is adopted. By installing the construction track, the hanger is installed on the track through the suspension system, and the test movement and verification is carried out to ensure the stability of the hanger, and then the hanger is closed and then the construction is carried out, and finally the removal and recycling is carried out.
Minimize interference to existing line operations, reduce construction safety risks, shorten the construction cycle of the dragon section, improve construction efficiency, and reduce equipment investment and labor costs.