Secondary battery charging control device

The charging control device adapts the charging current to the battery's state by creating a target temperature profile, ensuring rapid and efficient charging with minimal deterioration.

JP7561522B2Active Publication Date: 2024-10-04SUBARU CORP
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
JP2020095816
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2020-06-02
Publication Date
2024-10-04
Estimated Expiration
2040-06-02

AI Technical Summary

Technical Problem

Conventional secondary battery charging methods do not effectively balance the need for rapid charging while minimizing deterioration, and there is a requirement for improved charging control that adapts to the battery's state.

Method used

A charging control device that measures the battery's state, creates a target temperature profile based on the measurement results, and adjusts the charging current to achieve a desired temperature change, using a reference profile for ideal charging conditions, and includes a cooling device to manage temperature.

Benefits of technology

The device enables efficient charging that adapts to the battery's state, achieving rapid charging while minimizing deterioration and optimizing power consumption.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007561522000002
    Figure 0007561522000002
  • Figure 0007561522000003
    Figure 0007561522000003
  • Figure 0007561522000004
    Figure 0007561522000004
Patent Text Reader

Abstract

To provide a secondary battery charge control device that can achieve good charging according to the state of a secondary battery.SOLUTION: A secondary battery charge control device (20) includes a measuring unit (6) that measures the state of a secondary battery (5), a target creation unit (202) that creates a target temperature profile showing a relationship between a charging time and the temperature of the secondary battery on the basis of the measurement results of the measuring unit, and a charge control unit (203) that sends a charge current to the secondary battery (5) such that the temperature changes according to the target temperature profile.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a charging control device for a secondary battery. [Background technology]

[0002] Various methods are known for charging secondary batteries, such as a constant current constant voltage method. In conventional charging methods for secondary batteries, the charging current is also controlled based on the temperature of the secondary battery. For example, in the charging method of Patent Document 1, the charging current is reduced or stopped when the temperature change rate of the secondary battery during charging exceeds a threshold value. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Japanese Patent Application Publication No. 9-154239 Summary of the Invention [Problem to be solved by the invention]

[0004] For example, there is a demand for a method of charging a secondary battery to complete charging in a short time while suppressing deterioration. In addition, various other demands may be imposed. Conventional charging methods do not completely satisfy such demands, and there is room for improvement in the method of charging a secondary battery.

[0005] An object of the present invention is to provide a charge control device for a secondary battery that can realize good charging according to the state of the secondary battery. [Means for solving the problem]

[0006] The invention described in claim 1 is A measurement unit that measures a state of the secondary battery; a target creating unit that creates a target temperature profile indicating a relationship between a charging time and a temperature of the secondary battery based on a measurement result of the measuring unit; a charge control unit that supplies a charging current to the secondary battery so as to cause a temperature change according to the target temperature profile; a storage unit that stores a reference temperature profile that represents one relationship between a charging time and a temperature of the secondary battery; Equipped with 、 The target creation unit creates the target temperature profile by correcting the reference temperature profile. The present invention relates to a charging control device for a secondary battery.

[0007] The invention described in claim 2 is the charging control device for a secondary battery described in claim 1, A time acquisition unit that acquires a planned charging time is further provided, The target creating unit creates the target temperature profile based on the measurement result of the measuring unit and the planned charging time.

[0009] Claim 3 The invention described is as follows: 1 or claim 2 In the charging control device for the secondary battery described above, the measurement results include a temperature and a charging rate of the secondary battery; The target creation unit creates the target temperature profile by shifting the reference temperature profile parallel to a temperature axis, scaling it, or both, based on the temperature of the secondary battery and the limit temperature, or by scaling the reference temperature profile parallel to a time axis, cutting out a portion of the reference temperature profile in the time axis direction, or both, based on the charging rate.

[0010] Claim 4 The invention described is as follows: 3 In the charging control device for a secondary battery according to any one of claims 1 to 5, During charging, when the charging current reaches a limit current and the temperature change of the secondary battery falls below the target temperature profile, a request to reduce the output of a cooling device that cools the secondary battery is output. Effect of the Invention

[0011] According to the present invention, the charge control unit controls the charging current of the secondary battery so that a temperature change occurs according to the target temperature profile. If the target temperature profile has suitable characteristics, the above-mentioned charge control realizes good charging. Furthermore, according to the present invention, the target creation unit creates a target temperature profile based on the measurement results of the state of the secondary battery. Therefore, a target temperature profile according to the current state of the secondary battery can be created, and this makes it possible to realize good charging of the secondary battery according to the state of the secondary battery. [Brief description of the drawings]

[0012] [Figure 1] 1 is a diagram showing a charging control device for an electric vehicle and a secondary battery according to an embodiment of the present invention; [Diagram 2] FIG. 4 is a diagram showing a reference temperature profile stored in a storage unit. [Diagram 3] FIG. 4 is an explanatory diagram showing a first example of a target temperature profile. [Figure 4] FIG. 11 is an explanatory diagram showing a second example of a target temperature profile. [Diagram 5] 4 is a flowchart showing a charge control process executed by a charge control device. [Figure 6] 4 is a timing chart illustrating a charging control process. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0013] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, an embodiment of the present invention will be described in detail with reference to the drawings. Fig. 1 is a diagram showing a charging control device for an electric vehicle and a secondary battery according to an embodiment of the present invention.

[0014] The electric vehicle 1 of this embodiment includes a driving wheel 2, a traveling motor 3 that generates power for the driving wheel 2, an inverter 4 that drives the traveling motor 3, and a secondary battery 5 that supplies power to the traveling motor 3. The secondary battery 5 is, for example, a lithium ion secondary battery or a nickel-hydrogen secondary battery, and outputs a high voltage. The secondary battery 5 is provided with a measurement unit 6 that measures temperature, charge and discharge current, and the like. The electric vehicle 1 further includes a cooling device (for example, a cooling fan) 9 that cools the secondary battery 5, an operation panel 12 that allows a user to input charging conditions such as a charging end time, a vehicle control unit 11 that controls the electric vehicle 1, an equipment battery 8 that supplies power to devices (auxiliary equipment, accessory devices, etc.) other than the traveling motor 3, and a DC / DC converter 7 that supplies power for the devices using power from the secondary battery 5. The electric vehicle 1 further includes an inlet 13 to which power is input from the outside via a charging cable 51, and a charging control device 20 that controls charging of the secondary battery 5. The charging control device 20 may be included in an on-board charger.

[0015] The vehicle control unit 11 includes a battery management unit that receives the measurement results from the measurement unit 6 and manages the temperature and SOC (State of Charge) of the secondary battery 5, a peripheral device control unit that controls the driving of the cooling device 9, an input / output control unit that processes operation inputs from a user via the operation panel 12, and a drive control unit that controls the inverter 4 based on the user's driving operation. The input / output control unit allows the user to input commands such as a charging start command and a charging end command from the operation panel 12. Furthermore, the input / output control unit may allow the user to input commands specifying charging time such as a charging start time and a charging end time from the operation panel 12. The vehicle control unit 11 is composed of multiple ECUs (Electronic Control Units) that communicate with each other and operate in cooperation with each other.

[0016] The charging control device 20 sends a charging current generated using power input via the inlet 13 to the secondary battery 5 to charge the secondary battery 5. Temperature information and SOC information of the secondary battery 5 are sent from the vehicle control unit 11 to the charging control device 20. Furthermore, user commands related to charging (such as a command to start charging and a command to specify the charging time) input via the operation panel 12 are sent from the vehicle control unit 11 to the charging control device 20. Furthermore, the charging control device 20 can output a control request for peripheral devices, including a request to reduce the output of the cooling device 9, to the vehicle control unit 11.

[0017] The charge control device 20 includes a ROM (Read Only Memory) that stores a control program, and a CPU (Central Processing Unit) that executes the control program. The CPU executes the control program to realize a plurality of software function modules in the charge control device 20. The plurality of software function modules include a target creation unit 202 that creates data 202a of a target temperature profile, and a charge control unit 203 that controls the output of a charging current. The charge control device 20 further includes a storage unit 201 that previously stores data 201a of a reference temperature profile, and a power conversion circuit that generates a charging current from input power. The charge control unit 203 includes a portion of the above software function modules and a power conversion circuit, which work together to output a charging current. The target creation unit 202 also functions as a time acquisition unit according to the present invention.

[0018] FIG. 2 is a diagram showing a reference temperature profile stored in the storage unit. R (t) represents the reference relationship between the charging time t and the temperature T of the secondary battery 5, as shown in FIG. 2 and the following Data Table 1. R(t) represents the temperature of the secondary battery 5 at each time point obtained when ideal charging is performed from a reference charging start state (e.g., start temperature Tr0=20° C., SOC=5%) to a reference charging end state (e.g., SOC=100%). Ideal charging is, for example, charging that can fully charge the secondary battery 5 in a short time while suppressing deterioration of the secondary battery 5. Parameters such as charging current at each time point that realize ideal charging and the temperature of the secondary battery 5 at each time point are obtained in advance by experiment or simulation. The requirements imposed for ideal charging are not limited to suppression of deterioration and high-speed charging, and various requirements may be added or replaced. When the imposed requirements change, parameters such as charging current that satisfy the requirements and the temperature of the secondary battery 5 that occurs at each time point during charging are obtained by experiment or simulation, and the obtained temperatures at each time point correspond to the reference temperature profile F. R (t) may be used as the reference temperature profile data 201a stored in the storage unit 201. The reference temperature profile data 201a stored in the storage unit 201 is not limited to data in a data table format, and may be data in a function format.

[0019] [Table 1]

[0020] When starting charging of the secondary battery 5, the target generation unit 202 generates the state information of the secondary battery 5 (temperature information, SOC information, etc.) and the reference temperature profile F R The target temperature profile is generated based on the state information of the secondary battery 5 and the reference temperature profile F R In addition to (t), other information such as external environment information (ambient temperature of the secondary battery 5, cooling capacity, etc.) may be included, and the target temperature profile may be created based on this information. More specifically, the target creation unit 202 creates the reference temperature profile F R A target temperature profile is created by correcting (t) based on the above information. The target temperature profile represents the target temperature of the secondary battery 5 at each point in time during charging. When the target temperature profile is created, the data 202a is temporarily stored.

[0021] 3 is an explanatory diagram showing a first example of a target temperature profile. In the example of FIG. 3, the starting temperature T0 of the secondary battery 5 during charging is set to a value in accordance with the reference temperature profile F R 3 shows a case where the SOC at the start of charging is lower than the start temperature Tr0 of the reference temperature profile F R In this case, the target creation unit 202 creates a reference temperature profile F R (t) is translated in the direction of the temperature axis and scaled to obtain the target temperature profile F T (t) is created. The parallel movement is the reference temperature profile F R The start point A0 of (t) is positioned on the actual start temperature T0. The expansion and contraction is performed so that the temperature obtained by subtracting the margin ΔT from the limit temperature Tmax is the target temperature profile F T By such translation and expansion / contraction, the reference temperature profile F R The target temperature profile F has a temperature change rate that is approximately proportional to (t) and changes the temperature from the start temperature T0 to near the limit temperature Tmax. T (t) is created.

[0022] 4 is an explanatory diagram showing a second example of the target temperature profile. In the example of FIG. 4, the starting temperature T0 of the secondary battery 5 during charging is set to a value in accordance with the reference temperature profile F R (t) is lower than the start temperature Tr0 and the SOC (=N%) at the start of charging (t=0) is within the range of the reference temperature profile F R This shows a case where the SOC is higher than the starting SOC (=5%) that was used as a reference when creating (t). If the SOC at the start of charging is high, the time required for full charging will be shorter. The goal creation unit 202 first calculates the expected time until full charging from the SOC (=N%) at the start of charging. The expected time may be obtained by dividing the amount of power equivalent to the difference in the starting SOC (N%-5%) by the standard charging power at the beginning of charging, or the goal creation unit 202 may hold in advance a data table showing the standard relationship between the difference in the starting SOC and the expected time, and obtain the expected time by referring to this data table.

[0023] After calculating the scheduled time, the target generation unit 202 creates a reference temperature profile F R The reference temperature profile F is set so that the time length from the start point A0 to the end point An of (t) is the above scheduled time. R The target generation unit 202 expands or contracts the reference temperature profile F(t) in the direction along the time axis. R Instead of scaling (t) along the time axis, for example, R The range to be cut out may be, for example, a range of the planned time from the start point A0, a range of the planned time in the center on the time axis, or a range of the planned time before the end point An. Furthermore, the target creation unit 202 may perform both cutting and scaling. The above-mentioned time axis scaling process, cutting process, or both processes may be used to create a post-intermediate-correction reference temperature profile F in which a temperature change for the planned time is indicated. R1 (t) is obtained.

[0024] Next, the target creation unit 202 creates a reference temperature profile F after intermediate correction. R1 (t) is translated in the temperature axis direction and scaled to obtain the target temperature profile F T (t) is created. Translation and scaling are performed in the same manner as described in FIG. 3. By this correction process, the reference temperature profile F R A target temperature profile F in which the temperature changes from the start temperature T0 to near the limit temperature Tmax over a scheduled time with a rate of change that is approximately proportional to (t). T (t) is created.

[0025] The target creation unit 202 uses the above-mentioned reference temperature profile F R In addition to translating, scaling, and cutting out (t), a different correction process is added according to the state of the secondary battery 5, the external environment, or both, to obtain the target temperature profile F T In addition, the storage unit 201 may store a plurality of reference temperature profiles F(t) corresponding to the state of the secondary battery 5, the external environment, or both.R (t) is stored, and the target creation unit 202 creates one reference temperature profile F according to the situation. R (t) is selected and used to determine the target temperature profile F T (t) may be created.

[0026] The charging control unit 203 performs charging start control, charging current output control, and charging end control of the secondary battery 5. In the charging current output control, the charging control unit 203 performs feedforward control and feedback control based on the temperature information of the secondary battery 5 measured during charging, and controls the temperature of the secondary battery 5 to match the target temperature profile F. T The charging control unit 203 increases or decreases the charging current so as to change in accordance with (t). The charging control unit 203 can further request adjustment of the output of the cooling device 9 during the charging process.

[0027] <Charging control process> Fig. 5 is a flowchart showing the charge control process executed by the charge control device. Fig. 6 is a timing chart explaining the charge control process. The charge control process is started when an external power source is connected via the charge cable 51 and a charge start command is input by the user via the operation panel 12. The command input by the user may include a planned charging time, such as a time from when charging will start and when charging will end.

[0028] When the charging control process is started, first, the target creation unit 202 acquires the temperature and SOC of the secondary battery 5 (step S1). The temperature information and SOC information are sent from the vehicle control unit 11 to the charging control device 20. Next, the target creation unit 202 acquires the scheduled charging time (step S2). The process of step S2 corresponds to the process of the time acquisition unit according to the present invention. The scheduled time is calculated from the SOC of the secondary battery 5 as described in FIG. 4. If the command entered by the user includes the scheduled time, the shorter of the scheduled time calculated from the SOC and the scheduled time included in the command may be selected.

[0029] The target generation unit 202 further reads the reference temperature profile F RThe data 201a of (t) is read (step S3), and the reference temperature profile F R (t) is corrected based on the temperature, SOC, and planned charging time of the secondary battery 5 to obtain the target temperature profile F T The method of creating (t) is as described with reference to FIGS.

[0030] Next, in the charge control device 20, the charge control section 203 starts charging the secondary battery 5 and starts counting the charging time t (step S5). n Then, the charging control section 203 repeatedly executes a loop process (steps S6 to S12) for controlling the output of the charging current.

[0031] In the loop process, first, the charging control unit 203 acquires the measured temperature T of the secondary battery 5 and calculates the time change rate ΔT / Δt (step S6). Then, the charging control unit 203 calculates the measured temperature T at the current time and the time count value t n The target temperature profile value F(t n ) and the time rate of change ΔT / Δt of the current measured temperature and the time count value t n The time derivative of the target temperature profile |d(F T ) / dt| t=tn From the difference between the measured temperature T of the secondary battery 5 and the target temperature profile F T The increase or decrease in the required charging current is calculated so that the charging current varies according to the target temperature profile F(t) (step S7). T When the temperature is likely to drop below (t), the charging current is increased to raise the temperature, and the target temperature profile F T When the temperature is likely to become higher than (t), the charging control unit 203 calculates the amount of increase or decrease in the required charging current so as to reduce the charging current so as to lower the temperature.

[0032] Next, the charging control unit 203 determines whether the requested charging current exceeds the limit current (step S8). The limit current may be a current value limited by a configuration other than the secondary battery 5, and may be determined, for example, from the specifications of the charging cable 51, the specifications of the power conversion circuit included in the charging control unit 203, etc. The requested charging current may exceed the limit current if the temperature of the secondary battery 5 is low and the current continues to increase. In this case, the temperature of the secondary battery 5 is increased by the target temperature profile F T The temperature is lower than (t).

[0033] If the determination result in step S8 is YES, the charging control unit 203 limits the requested charging current to the limited current (step S9). Furthermore, the charging control unit 203 outputs a request to the vehicle control unit 11 to reduce the output of the cooling device 9 for a predetermined period (step S10). By the process of step S10, the capacity of the cooling device 9 is reduced for the predetermined period, and the temperature of the secondary battery 5 is controlled to the target temperature profile F T (t). Furthermore, the power consumption of the cooling device 9 is reduced, and the power consumption from the secondary battery 5 via the DC / DC converter 7 is reduced, so that the charging efficiency of the secondary battery 5 can be improved.

[0034] Subsequently, or if the result of the determination in step S8 is NO, the charge control unit 203 determines whether a charge termination condition is satisfied (step S11). T For example, when the end time (t) is reached, or when the SOC reaches 100% before that.

[0035] If the result of the determination in step S11 is NO, the charging control unit 203 controls the output of the charging current so that the requested charging current is output (step S12), and the process returns to step S6. Then, the charging control unit 203 repeats the loop process (steps S6 to S12) for controlling the charging current. On the other hand, if the result of the determination in step S11 is YES, the charging control unit 203 stops the charging current (step S13), and ends the charging control process.

[0036] By this charging control process, the charging current is appropriately controlled to achieve the target temperature profile F T Charging is realized in which the temperature (actual temperature) of the secondary battery 5 changes along (t).

[0037] As described above, according to the charging control device 20 and the electric vehicle 1 of the present embodiment, the target temperature profile F T The charging control unit 203 supplies a charging current to the secondary battery 5 so that a temperature change occurs according to the target temperature profile F T Once (t) is obtained, the target temperature profile F T By charging according to (t), good charging can be realized. Furthermore, according to the charge control device 20 and the electric vehicle 1 of this embodiment, the target creation unit 202 uses the measurement result of the measurement unit 6 to create the target temperature profile F T Therefore, the target creating unit 202 creates a target temperature profile F(t) according to the state of the secondary battery 5. T As a result, good charging according to the state of the secondary battery 5 can be achieved.

[0038] Furthermore, according to the charging control device 20 and the electric vehicle 1 of this embodiment, the target creation unit 202 acquires the planned charging time, and creates the target temperature profile F based on the state of the secondary battery 5 and the planned time. T Therefore, the target creation unit 202 creates a target temperature profile F(t) suitable for the length of the charging time. T (t) can be created, and good charging can be achieved according to the length of the charging time.

[0039] Furthermore, according to the charging control device 20 and the electric vehicle 1 of the present embodiment, the reference temperature profile F R The target creating unit 202 has a reference temperature profile F R Correct (t) to obtain the target temperature profile F T Therefore, an ideal reference temperature profile F(t) that enables charging that satisfies various requirements is created in advance. RBy preparing the target temperature profile F(t), the target generation unit 202 can generate a target temperature profile F(t) that enables good charging according to the state of the secondary battery 5. T (t) can be easily created.

[0040] Furthermore, according to the charging control device 20 and the electric vehicle 1 of this embodiment, the target creation unit 202 creates a reference temperature profile F based on the temperature, limit temperature, charging rate, etc. of the secondary battery 5. R (t) is expanded or contracted in the temperature axis direction, time axis direction, or both directions, cut out a part, and translate it in the temperature axis direction to obtain the target temperature profile F T As a result, the target creation unit 202 creates a target temperature profile F(t) that enables good charging according to the state of the secondary battery 5. T (t) can be easily created.

[0041] Furthermore, according to the charging control device 20 and the electric vehicle 1 of this embodiment, when the charging current reaches the limit current, the temperature change of the secondary battery 5 changes according to the target temperature profile F T If the temperature of the secondary battery 5 falls below the target temperature profile F(t), the charging control unit 203 sends a request to the vehicle control unit 11 to reduce the output of the cooling device 9 (step S10 in FIG. 5). T Furthermore, the power consumption of the cooling device 9 can be reduced, and the charging efficiency of the secondary battery 5 can be improved.

[0042] Above, each embodiment of the present invention has been described. However, the present invention is not limited to the above-mentioned embodiment. For example, in the above-mentioned embodiment, the target creation unit corrects the reference temperature profile to create the target temperature profile, but the target creation unit may create a target temperature profile that enables good charging without using the reference temperature profile. In addition, in the above-mentioned embodiment, the charging control device is configured to be provided in the electric vehicle, but the charging control device may be configured to be provided in the charging device of the charging station. In addition, the details shown in the embodiment, such as the method of supplying power from the outside to the charging control device, can be appropriately changed without departing from the spirit of the invention. [Explanation of symbols]

[0043] 1 Electric vehicles 5 Secondary battery 9 Cooling device 13 Inlet 20 Charging control device 201 Storage section 202 Goal Creation Department 203 Charging control unit F R (t) Reference temperature profile F T (t) Target temperature profile T0 starting temperature Tmax limit temperature

Claims

1. A measurement unit that measures a state of the secondary battery; a target creating unit that creates a target temperature profile indicating a relationship between a charging time and a temperature of the secondary battery based on a measurement result of the measuring unit; a charge control unit that supplies a charging current to the secondary battery so as to cause a temperature change according to the target temperature profile; a storage unit that stores a reference temperature profile that represents one relationship between a charging time and a temperature of the secondary battery; Equipped with The charging control device for a secondary battery, wherein the target creating unit creates the target temperature profile by correcting the reference temperature profile.

2. A time acquisition unit that acquires a planned charging time is further provided, 2. The charging control device for a secondary battery according to claim 1, wherein the target creating unit creates the target temperature profile based on the measurement result of the measuring unit and the planned charging time.

3. the measurement results include a temperature and a charging rate of the secondary battery; The charging control device for a secondary battery as described in claim 1 or claim 2, characterized in that the target creation unit creates the target temperature profile by shifting, scaling, or both of the reference temperature profile in a temperature axis direction based on the temperature of the secondary battery and the limit temperature, or by scaling the reference temperature profile in a time axis direction, cutting out a portion in the time axis direction, or both of the above, based on the charging rate.

4. A charging control device for a secondary battery as described in any one of claims 1 to 3, characterized in that, during charging, when the charging current reaches a limit current and the temperature change of the secondary battery falls below the target temperature profile, a request to reduce the output of a cooling device that cools the secondary battery is output.

Citation Information

Patent Citations

  • Charging of secondary battery

    JP1997154239A

  • Device and system for charging battery

    JP2000278878A

  • Method and apparatus for charging battery

    JP2002051479A

  • Compound battery and battery pack

    JP2004342580A

  • Charger for a plurality of batteries

    JP2005110337A