Energy management device, energy management system, and energy management program
The energy management device optimizes energy distribution at airports by predicting aircraft battery capacity and using it to charge vehicles, addressing the challenge of increased power consumption and environmental impact.
Patent Information
- Application Number
- JP2020150500
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2020-09-08
- Publication Date
- 2024-10-04
- Estimated Expiration
- 2040-09-08
AI Technical Summary
Existing technologies for reducing environmental impact at airports, such as those described in Patent Document 1, are insufficient in addressing the increased power consumption required for charging electric vehicles and do not effectively utilize the power generated by aircraft storage batteries.
An energy management device that predicts the remaining capacity of aircraft storage batteries and uses this information to create a power usage plan for airport equipment, including charging vehicles with the stored energy from these batteries, thereby optimizing energy distribution and reducing environmental load.
The solution effectively reduces environmental load by efficiently utilizing aircraft battery power for charging vehicles, minimizing unnecessary movement and power consumption, and optimizing energy distribution at airports.
Smart Images

Figure 0007561546000001 
Figure 0007561546000002 
Figure 0007561546000003
Abstract
Description
[Technical field]
[0001] The present disclosure relates to an energy management device, an energy management system, and an energy management program for managing energy in an airport. [Background technology]
[0002] In recent years, efforts to reduce emissions of greenhouse gases such as carbon dioxide have been underway in various fields as a measure against global warming. There is also a demand to reduce the environmental impact of aircraft themselves and airports.
[0003] Patent Document 1 discloses a technology in which a passenger boarding and disembarking vehicle, which is an example of airport equipment, is equipped with solar cells, and when auxiliary equipment is used, the power generated by the solar cells is used to drive the auxiliary equipment without driving the engine. As a result, the technology of Patent Document 1 can reduce fuel consumption and reduce the environmental load. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2013-133066 A Summary of the Invention [Problem to be solved by the invention]
[0005] In the future, it is expected that the use of electric vehicles at airports will increase as a measure against global warming, and power consumption for charging these vehicles will increase. With the technology described in Patent Document 1, although the power generated by solar cells can drive auxiliary equipment, it cannot cover the power required to run electric vehicles, and the effect of reducing the environmental load is limited. There is a demand for further reduction in the environmental load at airports.
[0006] The present disclosure has been made in consideration of the above, and aims to provide an energy management device that can reduce the environmental load at airports. [Means for solving the problem]
[0007] In order to solve the above-mentioned problems and achieve the object, an energy management device according to the present disclosure includes: an acquisition unit that acquires a remaining charge of a storage battery installed in an aircraft; a remaining charge prediction unit that predicts a remaining charge of a storage battery at the time of landing of a first aircraft that is scheduled to land at an airport; and a predicted value predicted by the remaining charge prediction unit. A plan creation unit that creates a power usage plan that is a power usage plan for airport facilities that are airport facilities using the above. The remaining charge prediction unit predicts the remaining charge of the storage battery at the time of landing of the first aircraft based on information indicating the remaining charge of the storage battery and the corresponding time acquired in a past flight of the first aircraft or a second aircraft other than the first aircraft, and information indicating the remaining charge of the storage battery acquired from the first aircraft during flight. do. Effect of the Invention
[0008] According to the present disclosure, it is possible to reduce the environmental burden at airports. [Brief description of the drawings]
[0009] [Figure 1] FIG. 1 is a diagram showing a configuration example of an energy management system according to a first embodiment; [Diagram 2] 1 is a flowchart showing an example of an energy management process procedure in the energy management device according to the first embodiment. [Diagram 3] FIG. 1 is a diagram showing an example of first remaining amount information according to the first embodiment; [Figure 4] FIG. 13 is a diagram showing an example of second remaining amount information according to the first embodiment; [Diagram 5] FIG. 1 is a diagram showing an example of vehicle position information according to the first embodiment; [Figure 6] FIG. 1 is a schematic diagram showing an example of the remaining charge of a storage battery of an aircraft that has been operated in the past according to the first embodiment; [Figure 7] FIG. 1 is a diagram showing an example of a power usage plan according to the first embodiment. [Figure 8] FIG. 2 is a diagram showing an example of the location of each facility in an airport according to the first embodiment; [Figure 9] FIG. 1 is a diagram showing an example of a vehicle operation plan according to the first embodiment. [Figure 10] FIG. 1 is a diagram showing a configuration example of a computer system that realizes an energy management device according to a first embodiment. [Figure 11] FIG. 1 is a diagram showing a configuration example of an energy management system according to a second embodiment; [Figure 12] 11 is a flowchart showing an example of an energy management procedure in the energy management device according to the second embodiment when a disaster occurs. [Figure 13] FIG. 13 is a diagram showing an example of a power usage plan in the event of a disaster according to the second embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0010] An energy management device, an energy management system, and an energy management program according to embodiments will be described below in detail with reference to the drawings.
[0011] Embodiment 1 1 is a diagram showing a configuration example of an energy management system according to a first embodiment. The energy management system of the present embodiment includes an energy management device 1 that manages energy in an airport, and vehicles 2-1 to 2-n that are equipped with storage batteries and perform work in the airport. n is an integer of 2 or more.
[0012] In this embodiment, in order to reduce the environmental load, at least a part of the work vehicles used at the airport is electrified, and the aircraft itself is also electrified. Here, the electrified aircraft is a hybrid electric aircraft that flies using both aircraft fuel and electrical energy. An example of the aircraft in this embodiment is a system called a series-parallel partial hybrid, in which aircraft fuel is burned to obtain propulsion power, a turbine is rotated by the combustion to generate electricity, and the generated electricity is used to drive a motor to rotate a propulsion fan. Surplus electricity generated by the aircraft that is not used by the motor is stored in a storage battery mounted on the aircraft. The electricity stored in the storage battery mounted on the aircraft may be used to rotate the propulsion fan, or may be consumed by other electrical devices in the aircraft. In the following, an example will be described in which all aircraft that take off and land at the airport are hybrid electric aircraft, but some of the aircraft that take off and land at the airport may be hybrid electric aircraft. When some of the aircraft that take off and land at the airport are hybrid electric aircraft, the aircraft that are the subject of the energy management process described below may be limited to hybrid electric aircraft.
[0013] The vehicles 2-1 to 2-n are part of airport facilities, that is, airport facilities, and are work vehicles used for work at the airport. The vehicles 2-1 to 2-n are ground support equipment called GSE (Ground Support Equipment), and are work vehicles that perform various work at the airport. The vehicles 2-1 to 2-n generally include a plurality of types of vehicles, for example, boarding bridges, ramp buses, towing cars, marshalling cars, cargo dollies, air-conditioned vehicles, snow removal vehicles, and the like. The vehicles 2-1 to 2-n are electrified vehicles, that is, electric vehicles or hybrid vehicles that use both electricity and fuel such as gasoline, and are equipped with storage batteries. The vehicles 2-1 to 2-n also have a communication function and transmit information indicating the remaining amount of the storage battery to the energy management device 1 as second remaining amount information. The vehicles 2-1 to 2-n further have a position detection function for detecting their own current position, and transmit information indicating their current position to the energy management device 1 as vehicle position information. The position detection in the vehicles 2-1 to 2-n may use a GPS (Global Positioning System) or other methods. As an example of another method, an airport is divided into a plurality of areas, and a communication device is arranged in each area with a communication range within the area, and the vehicles 2-1 to 2-n detect which area they are in by receiving an identifier of the communication device, thereby detecting the current position for each area. The position detection method in the vehicles 2-1 to 2-n is not limited to these examples. Hereinafter, when the vehicles 2-1 to 2-n are referred to without being individually distinguished, they will be described as vehicle 2.
[0014] In this embodiment, in order to further reduce the environmental load, a power usage plan is created so that vehicle 2 is charged using power stored in the storage battery of an aircraft that has landed at an airport, and the storage battery of vehicle 2 is charged in accordance with the power usage plan. That is, the power usage plan of this embodiment includes a charging plan to charge vehicle 2 by discharging the storage battery of the aircraft. Specifically, the energy management device 1 creates the power usage plan based on the remaining capacity of the storage battery of the aircraft that is scheduled to land at the airport and the remaining capacity of the storage battery of vehicle 2. The power usage plan includes a discharging plan for the storage battery of the aircraft that is scheduled to land at the airport, and a charging plan for the storage battery of vehicle 2. The energy management device 1 further creates an operation plan for vehicle 2 using the power usage plan.
[0015] Note that work vehicles at the airport may include vehicles other than vehicle 2, i.e., non-electric vehicles that are neither electric vehicles nor hybrid vehicles. Non-electric vehicles are not subject to the charging plan in the power usage plan created by the energy management device 1, but the operation plan may include a plan for operating non-electric vehicles.
[0016] The energy management device 1 is capable of communicating with an flight management center 3 that manages the flights of aircraft, and an operation management system 4. The flight management center 3 is a system used for air traffic control, and manages the flight plans of aircraft. The operation management system 4 is a system that manages the operation of aircraft, and manages data indicating the status of aircraft. In addition, the energy management device 1 is capable of communicating with each of the vehicles 2-1 to 2-n.
[0017] The energy management device 1 includes a flight plan receiving unit 11, a remaining amount receiving unit 12, a remaining amount predicting unit 13, a plan creating unit 14, a vehicle communication unit 15, an input accepting unit 16 and a memory unit 17.
[0018] The flight plan receiving unit 11 receives the flight plan of the aircraft from the flight management center 3 and stores the received flight plan in the storage unit 17. For example, the flight plan receiving unit 11 periodically receives the flight plan of each flight managed by the flight management center 3 by periodically requesting the flight management center 3 to acquire the flight plan. The flight plan receiving unit 11 may receive a new flight plan and an updated flight plan by requesting the flight management center 3 to transmit the corresponding flight plan when a new flight plan is registered and when a flight plan is changed. In addition, the flight plan receiving unit 11 may receive the flight plans of all flights managed by the flight management center 3, or may receive the flight plans of flights that will arrive at the airport within a certain period of time. The certain period of time is, for example, a period from the current time to X hours (X is a real number).
[0019] The remaining amount receiving unit 12 receives first remaining amount information indicating the remaining amount of the storage battery mounted on the aircraft from the operation management system 4, and stores the received first remaining amount information in the storage unit 17. That is, the remaining amount receiving unit 12 is an acquisition unit that acquires the remaining amount of the storage battery mounted on the aircraft. Here, an example is described in which the energy management device 1 receives a flight plan from the flight management center 3 via a communication line, but the method of acquiring the flight plan in the energy management device 1 is not limited to this, and for example, the flight plan received from the flight management center 3 may be displayed on another device (not shown), and the operator may manually input the displayed flight plan into the energy management device 1. Similarly, the method of acquiring the first remaining amount information in the energy management device 1 is not limited to the method of acquiring the information via a communication line, and the operator may manually input the information into the energy management device 1. In addition, the first remaining amount information includes information received from an aircraft in flight and information recorded in a recorder during flight and read out after landing. However, the first remaining amount information may be only information recorded in a recorder during flight and read out after landing, not including information received from an aircraft in flight.
[0020] Vehicle communication unit 15 communicates with each of vehicles 2-1 to 2-n. Vehicle communication unit 15 receives second remaining amount information indicating the remaining amount of the storage batteries of vehicles 2-1 to 2-n, and stores the received second remaining amount information in storage unit 17. Vehicle communication unit 15 also reads out the vehicle operation plan created by plan creation unit 14 and stored in storage unit 17, and transmits the vehicle operation plan to vehicles 2-1 to 2-n.
[0021] The remaining charge prediction unit 13 predicts the remaining charge of the storage battery of a first aircraft scheduled to land at an airport when the first aircraft lands. In detail, the remaining charge prediction unit 13 reads out the first remaining charge information stored in the storage unit 17, and predicts the remaining charge of the storage battery of the aircraft scheduled to land at the airport using the read out first remaining charge information. For example, the remaining charge prediction unit 13 predicts the remaining charge of the storage battery of the aircraft scheduled to land at the airport based on the first remaining charge information indicating the remaining charge of the storage battery acquired from the aircraft scheduled to land at the airport, and the first remaining charge information of a flight operated in the past that has similar conditions such as the model and the number of passengers to the flight of the aircraft. The prediction method in the remaining charge prediction unit 13 will be described in detail later.
[0022] The plan creation unit 14 creates a power usage plan for the airport facilities using the remaining capacity of the storage battery of the aircraft. In detail, the plan creation unit 14 reads out the facility information, the first remaining capacity information, and the second remaining capacity information stored in the storage unit 17, creates a power usage plan for the airport using the read out information and the predicted value predicted by the remaining capacity prediction unit 13, and stores the created power usage plan in the storage unit 17. The facility information is information on each facility at the airport, and includes, for example, the type of each vehicle 2, the parking location at the airport, the position of the waiting location of the vehicle 2, the model of each aircraft, information such as the capacity of the storage battery installed, the model of each flight, the weight of cargo carried, the number of passengers, and the like. The facility information is input by the operator via the input reception unit 16 and stored in the storage unit 17. The parking location at the airport is also called an apron, and is, for example, one of a plurality of fixed spots close to the terminal building, or a parking location called an open spot away from the terminal building. Information such as the type of vehicle, the weight of cargo carried, and the number of passengers for each flight may be stored in the storage unit 17 as operation information separately from the equipment information. Although an example in which the equipment information is input by an operator will be described here, the energy management device 1 may receive the equipment information via a communication line from another device (not shown). The operation information may be received from the operation control center 3, or may be included in the operation plan stored in the storage unit 17. In addition, the plan creation unit 14 reads out the power usage plan stored in the storage unit 17, creates a vehicle operation plan for vehicles 2-1 to 2-n using the read power usage plan, and stores the created vehicle operation plan in the storage unit 17.
[0023] The input receiving unit 16 receives input from an operator and stores the input information in the memory unit 17. The memory unit 17 stores a flight plan, first remaining amount information, second remaining amount information, vehicle position information, facility information, a power usage plan, and a vehicle operation plan.
[0024] Next, the operation of this embodiment will be described. Fig. 2 is a flowchart showing an example of an energy management processing procedure in the energy management device 1 of this embodiment. The energy management processing shown in Fig. 2 is processing for creating a power usage plan for airport energy management. In the example shown in Fig. 2, the energy management device 1 creates a vehicle operation plan in addition to the power usage plan, but it is also possible to create only the power usage plan without creating the vehicle operation plan.
[0025] The energy management device 1 determines whether or not there is an aircraft that is due to land within a certain time period (step S1). In detail, the plan creation unit 14 refers to the flight plan stored in the memory unit 17 and determines whether or not there is an aircraft flight that is due to arrive within a certain time period from the current time.
[0026] If there is no aircraft that lands a certain time before (step S1 No), the energy management device 1 repeats step S1. If there is an aircraft that lands a certain time before (step S1 Yes), the energy management device 1 acquires information (first remaining amount information) indicating the remaining amount of the storage battery of the aircraft (step S2). In detail, when the plan creation unit 14 judges that there is an aircraft that will arrive a certain time after the current time, it decides to start creating a power usage plan, and notifies the remaining amount receiving unit 12, the remaining amount predicting unit 13, and the vehicle communication unit 15 of the start of creating the power usage plan. A flight corresponding to an aircraft that will arrive a certain time after the current time is called a processing target flight, and an aircraft corresponding to the processing target flight is also called a processing target aircraft. The remaining amount receiving unit 12 receives the first remaining amount information indicating the remaining amount of the processing target aircraft, that is, the first remaining amount information during the flight of the processing target aircraft, from the operation management system 4, and stores it in the storage unit 17. The first remaining amount information obtained from the flying aircraft includes a flight name that is the identification information of the flight, and the remaining amount of the storage battery and the corresponding time. The remaining amount is generally obtained as SOC (State Of Charge), so here we will explain the remaining amount as SOC, but if we know the SOC and the capacity of the storage battery, we can find the amount of electricity stored in the storage battery.
[0027] FIG. 3 is a diagram showing an example of the first remaining amount information of the present embodiment. In the example shown in FIG. 3, an example of the first remaining amount information related to a flight with flight name A1 is shown, and additional information used for predicting the remaining amount of the storage battery, which will be described later, such as the type of aircraft, the weight of loaded cargo, the number of passengers, and the capacity of the storage battery is added to the first remaining amount information obtained during the flight of the flight with flight name A1. Here, the additional information is assumed to be included in the equipment information, and the remaining amount receiving unit 12 reads out the additional information corresponding to each flight from the equipment information stored in the storage unit 17 and adds it to the first remaining amount information received from the operation management system 4. In addition, the additional information may include aircraft identification information for identifying the aircraft. As described above, the number of passengers for each flight may be stored in the storage unit 17 as operation information separately from the equipment information, and in this case, the remaining amount receiving unit 12 may read out the corresponding additional information from the equipment information and operation information stored in the storage unit 17 and add it. Note that the total weight included in the flight plan may be used instead of the weight of loaded cargo and the number of passengers. In addition, additional information does not have to be added to the first remaining amount information, and if additional information is not added, additional information corresponding to the flight to be processed is read from the equipment information stored in the memory unit 17 in the remaining amount prediction processing described below.
[0028] Returning to the description of FIG. 2, next, the energy management device 1 acquires information indicating the remaining amount of the storage battery of the vehicle 2 (second remaining amount information) and vehicle position information indicating the current position of the vehicle (step S3). In detail, upon receiving the notification of the start of the creation of the power usage plan, the vehicle communication unit 15 requests the vehicles 2-1 to 2-n to acquire the second remaining amount information and the vehicle position information, thereby receiving the second remaining amount information and the vehicle position information from the vehicles 2-1 to 2-n and storing them in the storage unit 17. Without being limited to this, the vehicle communication unit 15 may periodically receive the second remaining amount information and the vehicle position information from the vehicles 2-1 to 2-n regardless of the timing of the start of the creation of the power usage plan, and store the received second remaining amount information and vehicle position information in the storage unit 17 upon receiving the notification of the start of the creation of the power usage plan.
[0029] FIG. 4 is a diagram showing an example of the second remaining amount information of the present embodiment. FIG. 4 shows the second remaining amount information received by the vehicle communication unit 15 from the vehicles 2-1 to 2-n in response to a request made by the vehicle communication unit 15 to acquire the second remaining amount information and current location information at time 9:30. The second remaining amount information acquired from each vehicle 2 includes information for identifying the vehicle 2 and the remaining amount of the storage battery of the vehicle 2. In the example shown in FIG. 4, the type of each vehicle 2 is added to the second remaining amount information. The type of each vehicle 2 is included in the facility information. In this way, the vehicle communication unit 15 may read out the type of each vehicle 2, which is information used when generating a power usage plan described later, from the facility information stored in the storage unit 17 based on the information for identifying the vehicle 2, and add it to the second remaining amount information and store it in the storage unit 17. The type of each vehicle 2 may not be added to the second remaining amount information. In this case, the type of each vehicle 2 is extracted from the facility information when generating a power usage plan described later. The second remaining amount information acquired from each vehicle may include the time when the remaining amount of the storage battery was detected.
[0030] Fig. 5 is a diagram showing an example of vehicle position information according to the present embodiment. Fig. 5 shows vehicle position information received by vehicle communication unit 15 from vehicles 2-1 to 2-n in response to a request made by vehicle communication unit 15 to vehicles 2-1 to 2-n to obtain second remaining amount information and current position information at time 9:30. The vehicle position information obtained from each vehicle 2 includes the identification information of vehicle 2 and the current position of the vehicle 2.
[0031] Returning to the explanation of FIG. 2, the energy management device 1 next predicts the remaining amount of the storage battery mounted on the aircraft when it arrives at the airport, using the first remaining amount information (step S4). In detail, when the first remaining amount information of the target flight, i.e., the aircraft a certain time before landing, is stored in the memory unit 17, the remaining amount prediction unit 13, which has been notified by the plan creation unit 14 to start creating a power usage plan, predicts the remaining amount of the storage battery mounted on the target aircraft when it arrives at the airport, using the first remaining amount information and past first remaining amount information stored in the memory unit 17. The remaining amount prediction unit 13 outputs the predicted remaining amount to the plan creation unit 14.
[0032] As described above, the first remaining amount information includes not only information corresponding to an aircraft in flight, but also first remaining amount information operated in the past and recorded in a recorder. In this embodiment, for example, the first remaining amount information of the flight to be processed and the first remaining amount information of flights operated in the past that have similar conditions to the flight to be processed are used to predict the remaining amount of the storage battery of the aircraft of the flight to be processed when it arrives at the airport. An example of a flight with similar conditions is a flight with the same total weight or a difference in total weight within a certain value. The remaining amount prediction unit 13 can calculate the total weight based on the model, number of passengers, and weight of cargo carried, which are additional information added to the first remaining amount information. The weight of the aircraft for each model and the weight per passenger are determined in advance and stored as equipment information in the storage unit 17. Alternatively, as described above, the total weight included in the flight plan may be used instead of these. Note that the conditions may include not only the total weight, but also at least one of the capacity of the storage battery installed in the aircraft, the type of storage battery, the model, and the route. For example, a flight with similar conditions may be one that travels the same route as the target flight, uses the same type of aircraft, and has a difference in total weight within a certain value. Note that hereinafter, similarity will also be included in the term "identical." As shown in FIG. 3, if additional information such as the number of passengers is added to the first remaining amount information, the plan creation unit 14 can easily extract the first remaining amount information of a flight with similar conditions to the target flight by using this additional information.
[0033] FIG. 6 is a schematic diagram showing an example of the remaining charge of the storage battery of an aircraft operated in the past according to the present embodiment. In FIG. 6, the horizontal axis indicates time, and the vertical axis indicates the remaining charge of the storage battery of the aircraft. A plurality of data 51 shown by a rectangle indicates the remaining charge of the storage battery of an aircraft of flight #1 operated in the past, and a plurality of data 52 shown by a triangle indicates the remaining charge of the storage battery of an aircraft of flight #2 operated in the past. In FIG. 6, the symbols 51 and 52 are shown one by one, and each of the rectangles is one of the plurality of data 51, and each of the triangles is one of the plurality of data 52. Flight #1 and flight #2 are flights with similar conditions to the flight to be processed. As shown in FIG. 6, for example, the remaining charge prediction unit 13 obtains a remaining charge curve 53 showing the time change of the remaining charge using data 51 and data 52, which are the remaining charges of the storage batteries of past flights with similar conditions to the flight to be processed. The remaining charge curve 53 can be calculated by any method including regression analysis.
[0034] As shown in Fig. 6, in general, during steady flight, the change in the remaining charge of the storage battery may differ for each flight due to the influence of power generation in the aircraft, but it is expected that the remaining charge of the storage battery will decrease approximately linearly from a certain time before landing with little influence of charging. Therefore, it is possible to obtain the remaining charge of the storage battery of an aircraft that will land at an airport in a certain time from now based on the change in the remaining charge of flights with similar past conditions. During steady flight, for example, if the remaining charge included in the first remaining charge information obtained from the target aircraft a certain time before landing is data 54, a predicted curve 55 of the remaining charge of the storage battery of the target aircraft after the time corresponding to data 54 is obtained by translating remaining charge curve 53 in the vertical axis direction until it coincides with data 54. Since it is only necessary to predict the remaining battery charge upon arrival at the airport, in the case where remaining battery charge curve 53 is translated parallel to the vertical axis to obtain predicted curve 55, the remaining battery charge a certain time before landing on remaining battery charge curve 53 is R1, the remaining battery charge corresponding to the landing time on remaining battery charge curve 53 is R2, and the remaining battery charge corresponding to data 54 (the remaining battery charge a certain time before landing) is R3, then the remaining battery charge prediction unit 13 will calculate the remaining battery charge of the aircraft being processed at the time of landing by R3-(R2-R1).
[0035] In the above example, the remaining charge curve 53 obtained from the past first remaining charge information of flights with similar conditions to those of the processing target is used, but this remaining charge curve 53 may be corrected using the total weight before use. For example, when the average value of the total weights of the multiple flights used when using the remaining charge curve 53 is M1 and the total weight of the processing target aircraft is M2, the remaining charge prediction unit 13 may obtain the remaining charge of the storage battery at the time of landing of the processing target aircraft by R3-(R2-R1)×(M2 / M1).
[0036] As described above, the remaining charge prediction unit 13 predicts the remaining charge of the storage battery at the time of landing for the aircraft to be processed, which is the first aircraft scheduled to land, based on information indicating the remaining charge of the storage battery and the corresponding time obtained during past flights of the first aircraft operated in the past or a second aircraft which is an aircraft other than the first aircraft, and information indicating the remaining charge of the storage battery obtained from the first aircraft currently in flight.
[0037] The method of predicting the remaining battery charge at the time of landing of the aircraft to be processed is not limited to the above example. For example, a data set in which the remaining battery charge, model, total weight, etc. of a flight operated in the past are input and the remaining battery charge at the time of landing is output as teacher data may be used to generate a machine learning model using machine learning such as a neural network and store it in the storage unit 17. The remaining charge prediction unit 13 may predict the remaining battery charge at the time of landing by inputting the remaining battery charge, model, and total weight of the aircraft to be processed at the time of landing to this machine learning model.
[0038] In the above example, the first remaining amount information from a certain time before the landing of the target aircraft is used to predict the remaining amount of the storage battery at the time of landing of the target aircraft, but the remaining amount of the storage battery at the time of landing of the target aircraft may be predicted from the first remaining amount information of a flight operated in the past, without using the remaining amount of the storage battery from the aircraft in flight. For example, the remaining amount prediction unit 13 may use the first battery information of flights operated in the past stored in the memory unit 17, which have similar conditions to the target aircraft, to obtain the average value, median value, etc. of the remaining amount of the storage battery at the time of landing of the flights having similar conditions to the target aircraft, and set the obtained value as the predicted value of the remaining amount of the storage battery at the time of landing of the target aircraft.
[0039] Returning to the explanation of Fig. 2, the energy management device 1 then creates a power usage plan using the predicted remaining amount, the second remaining amount information, and the current location of the vehicle (step S5). In detail, the plan creation unit 14 creates a power usage plan based on the predicted remaining amount received from the remaining amount prediction unit 13, and the second remaining amount information and vehicle location information stored in the storage unit 17, and stores the created power usage plan in the storage unit 17.
[0040] In this embodiment, a power usage plan is created so that at least some of the vehicles 2 performing work on the landed aircraft charge their storage batteries with power obtained by discharging the storage batteries of the aircraft. This makes it possible to reduce commercial power sold for charging the vehicles 2, thereby suppressing the environmental load. Charging the storage batteries of the vehicles 2 is hereinafter also referred to as charging the vehicles 2.
[0041] In addition, since the vehicle 2 performing work related to the landed aircraft is generally placed near the aircraft, by charging such vehicle 2 using the power stored in the storage battery of the aircraft, unnecessary movement of the vehicle 2 can be suppressed, and the power consumption of the vehicle 2 can be suppressed. That is, in this embodiment, the vehicle to be charged, which is the vehicle 2 that is charged by discharging the storage battery of the aircraft, is selected from the vehicles 2 used in the work related to the landing of the aircraft, so that unnecessary movement of the vehicle 2 can be suppressed. In addition, in general, an aircraft is operated so that a certain amount of remaining battery power remains at the time of landing in order to provide redundancy in preparation for unexpected situations. Therefore, the remaining power left to provide redundancy is often not used when the aircraft lands, and this remaining power is wasted. In this embodiment, the remaining power of the storage battery of the aircraft at the time of landing is predicted, and a power usage plan is created so that the storage battery of the aircraft is discharged to charge the vehicle 2, so that the power stored in the storage battery of the aircraft can be effectively utilized.
[0042] Fig. 7 is a diagram showing an example of the power usage plan of this embodiment. As shown in Fig. 7, the power usage plan includes, for each flight, the amount of power that can be discharged from the storage battery when the aircraft lands and the amount of charge to be charged to the storage battery of the vehicle 2 used in work related to the landing of the aircraft. The amount of power that can be discharged is calculated based on a predicted value of the remaining amount, which is the SOC, the capacity of the storage battery, and the operational lower limit value of the SOC. For example, the amount of power that can be discharged is calculated by multiplying a value obtained by subtracting the lower limit value of the SOC from the predicted value of the remaining amount by the capacity of the storage battery.
[0043] The power plan in step S5 is created, for example, according to the following procedure. The plan creation unit 14 reads out the parking location where the aircraft to be processed will land from the flight plan stored in the memory unit 17. Next, the plan creation unit 14 uses information such as the read-out spot and the model of the aircraft to be processed to obtain the number of vehicles 2 required for landing operations of the aircraft to be processed for each type of vehicle 2 from the facility information stored in the memory unit 17. The facility information stores, for example, the number of vehicles 2 required for landing operations for each type of vehicle 2 for each model and parking location.
[0044] The plan creation unit 14 selects the vehicles 2 to be charged by discharging the storage battery of the target aircraft, using the number of vehicles 2 for each type of vehicle 2, second remaining amount information indicating the remaining amount of the storage battery of each vehicle 2, location information indicating the current location of each vehicle, and the parking location of the aircraft. At this time, if a vehicle operation plan described below has already been stored in the storage unit 17, the plan creation unit 14 refers to the vehicle operation plan and excludes vehicles 2 scheduled to be operated for work related to another aircraft during the time period when work related to the landing of the target aircraft is performed from the vehicles 2 to be charged.
[0045] For example, when one boarding bridge is required for the landing operation of the target aircraft, the vehicle 2 whose type is a boarding bridge and whose battery charge level is within a certain distance from the parking location of the aircraft is extracted. Then, the plan creation unit 14 selects the vehicle 2 whose battery charge level is the lowest among the extracted vehicles 2 as the vehicle 2 to be charged from the aircraft. In this way, the plan creation unit 14 can suppress the travel distance of the vehicle 2 by selecting the vehicle 2 to be charged based on the current position of the vehicle 2 and the parking location of the aircraft. Alternatively, the vehicle 2 whose battery charge level is also taken into consideration and whose type is a boarding bridge and whose distance from the parking location of the aircraft is within a certain distance may be selected as the vehicle 2 to be charged. In this example, the case where one vehicle 2 is required for landing work for each type of vehicle 2 has been described, but if multiple vehicles 2 are required, multiple vehicles 2 may be selected as charging targets in the same manner, from among the vehicles 2 that are within a certain distance from the aircraft parking area, in order of the vehicles 2 with the least remaining charge, or in order of the vehicles with the greatest difference between the fully charged capacity and the current amount of stored power. Note that if the remaining charge in the storage battery of a vehicle 2 is too low, it may be possible that the vehicle 2 cannot reach the aircraft parking area, so the above selection of vehicles 2 to be charged may be performed after previously excluding vehicles 2 that cannot reach the aircraft parking area.
[0046] In addition, an example has been described here in which the vehicle 2 to be charged is selected from among the vehicles 2 whose distance from the parking location of the aircraft is within a certain value, taking into consideration the remaining amount of the storage battery, but the method of selecting the vehicle 2 to be charged is not limited to this example. For example, the plan creation unit 14 may weight-add the distance from the parking location and the inverse of the remaining amount, and select the vehicle 2 to be charged using the result of the weighted addition. Similarly, the plan creation unit 14 may weight-add the distance from the parking location and the difference between the full charge capacity and the current storage amount, and select the vehicle 2 to be charged using the result of the weighted addition. That is, the plan creation unit 14 may select the vehicle 2 to be charged by giving priority to the vehicle 2 that is close to the parking location of the aircraft, while taking into consideration the remaining amount of the storage battery of the vehicle 2. In addition, in this example, the vehicle 2 to be charged is selected using the current position of the vehicle 2, but this is not limited to this. The vehicle 2 to be charged may be selected in order of the least remaining amount of the storage battery of the vehicle 2, or in order of the greatest difference between the full charge capacity and the current storage amount, without using the current position of the vehicle 2, that is, regardless of the distance between the parking location and the vehicle 2.
[0047] When the number of vehicles 2 to be charged is equal to or less than the number of charging ports of the aircraft charger, which is a charger that discharges the storage battery of the aircraft to be processed and charges the vehicle 2, the plan creation unit 14 calculates the amount of charging power, which is the amount of power to be charged for the vehicle 2 to be charged, and includes it in the power usage plan. For example, for each vehicle 2, the plan creation unit 14 calculates the amount of charging power for the vehicle 2 to be charged by multiplying the charging time that is equal to or less than the parking time and the charging power based on the charging power of the storage battery of the vehicle 2 and the parking time that is the time from when the aircraft to be processed arrives at the parking location until the aircraft moves to the next location. The charging power of each vehicle 2 is included in the facility plan, and the plan creation unit 14 acquires the charging power of the vehicle 2 to be charged from the facility plan stored in the storage unit 17. The charging time can be, for example, the work time for each vehicle 2 in the work on the aircraft to be processed. For example, the plan creation unit 14 for the vehicle 2 calculates the work time for each vehicle 2 to work near the aircraft to be processed based on the weight of the cargo carried by the aircraft to be processed, the number of passengers, and the like for each type of vehicle 2.
[0048] For vehicles 2 that will be fully charged in a time shorter than the charging time, the plan creation unit 14 calculates the amount of charge required to fully charge the vehicle 2. The example shown in FIG. 7 shows that when flight A1, which has a flight name A1, is scheduled to land at 10:05, vehicles 2-2 and 2-3 are scheduled to be charged with the power stored in the storage battery of the aircraft of flight A1. The plan creation unit 14 determines the amount of charging power for each vehicle 2 so that the total amount of charging power for the vehicles 2 to be charged during the parking time is equal to or less than the amount of power that can be discharged from the storage battery of the aircraft to be processed. Note that the aircraft charger / discharger may be provided in the aircraft or at the airport.
[0049] In the above example, the working time of each vehicle 2 is set as the charging time, but the power usage plan may be created by setting the parking time of the target aircraft as the charging time. In this case, too, the plan creation unit 14 calculates the amount of charge required to fully charge a vehicle 2 that will be fully charged in a time shorter than the parking time.
[0050] Furthermore, the plan creation unit 14 may determine the vehicle 2 to be charged using the amount of charging power calculated based on the work time and the charging power. Alternatively, the plan creation unit 14 may determine the vehicle 2 to be charged based on the work time. For example, a vehicle 2 that has a long work time may be preferentially selected as the vehicle to be charged, or a vehicle that has a large amount of charging power may be preferentially selected as the vehicle to be charged.
[0051] In addition, when there are more vehicles 2 to be charged than the number of charging ports on the aircraft charger / discharger, the plan creation unit 14 may determine charging priorities in advance based on the type of vehicle, etc., and exclude vehicles 2 with low priority from those to be charged, or may plan to charge more vehicles 2 than the number of charging ports by charging in a time-sharing manner.
[0052] Returning to the explanation of Fig. 2, the energy management device 1 then creates a vehicle operation plan using the power usage plan and the facility information (step S6), and ends the process. In detail, the plan creation unit 14 creates a vehicle operation plan based on the power usage plan and the facility information stored in the storage unit 17, and stores the created vehicle operation plan in the storage unit 17.
[0053] The vehicle operation plan is information indicating which flight each vehicle 2 is to be used for. At the airport, each vehicle 2 has time periods during which it waits at a waiting area, i.e., time periods during which it is not in operation, and time periods during which it works at an area where an aircraft is parked.
[0054] FIG. 8 is a diagram showing a schematic example of the location of each facility in an airport according to the present embodiment. In the example shown in FIG. 8, the airport is provided with spots 5-1 to 5-5, which are fixed parking locations for aircraft, and waiting locations 6-1 and 6-2, where a vehicle 2 waits. An aircraft that lands at the airport is assigned a parking location to one of the spots 5-1 to 5-5, or a location of the spots 5-1 to 5-5 called an open spot. When the target aircraft is parked at the spots 5-1 to 5-5 or an open spot, the vehicle 2 selected as the target for charging in the above-mentioned step S5 is charged with the power stored in the storage battery of the aircraft while performing work related to the aircraft.
[0055] Fig. 9 is a diagram showing an example of a vehicle operation plan according to the present embodiment. As shown in Fig. 9, the vehicle operation plan includes information on whether or not each vehicle 2 is in operation at each time, and the work location if the vehicle is in operation. Note that Fig. 9 shows that the time periods in which work locations such as spot 5-1 are shown are times when the vehicle is in operation, and the number of the waiting location is also shown for time periods when the vehicle is not in operation. The vehicle operation plan is not limited to this, and may include only the time periods in which each vehicle 2 is in operation and the corresponding work locations.
[0056] In this embodiment, the power usage plan is created on the premise that the vehicle 2 to be charged, which is charged with the power stored in the storage battery of the aircraft to be processed, is operated as the vehicle 2 to perform work on the aircraft. Therefore, the vehicle operation plan is created so that the vehicle 2 selected as the vehicle to be charged in the above-mentioned power usage plan is operated for work on the aircraft to be processed. The vehicle operation plan may include not only the vehicle operation plan of the vehicle 2 to perform work on the aircraft to be processed, but also the vehicle operation plans of all the vehicles 2. In the initial state, all the vehicles 2 are not in operation in the vehicle operation plan, and the waiting location of each vehicle is specified. When the vehicle 2 to perform work on the aircraft to be processed is determined, the vehicle operation plan is updated. The vehicle operation plan may also include the vehicle operation plan of a non-electric vehicle other than the vehicle 2. When non-electric vehicles and electric vehicles 2 are mixed, the vehicle 2 is used preferentially, but when the number of vehicles 2 alone is insufficient, the vehicle operation plan may be created so that the non-electric vehicles are also used. Furthermore, when creating the above-mentioned power usage plan, the plan creation unit 14 may also use non-electric vehicles if the remaining charge in the storage battery of the aircraft being processed is low.
[0057] In the example shown in FIG. 9, as shown in the power usage plan shown in FIG. 7, vehicles 2-2 and 2-3 are selected as charging targets for the aircraft of flight A1. Therefore, in the vehicle operation plan, vehicles 2-2 and 2-3 are also planned to be operated for work on the aircraft of flight A1. Vehicle 2-1 is not operated for work on the aircraft of flight A1. In this manner, the plan creation unit 14 creates a vehicle operation plan based on the power usage plan. In addition, the plan creation unit 14 may specify a waiting location for the vehicle 2 that is not in operation, in which case the waiting location is specified based on the current position of the vehicle 2.
[0058] For example, when the energy management device 1 acquires the current positions of the vehicles 2 in step S3, as shown in FIG. 8, the vehicle 2-1 is present at the waiting location 6-2, and the vehicles 2-2 and 2-3 are present at the waiting location 6-1. In the power usage plan, if the vehicle 2-1 is not selected as a charging target for the aircraft of flight A1, which is the aircraft to be processed, the plan creation unit 14 makes the vehicle 2-1 wait at the waiting location 6-2 without moving it from its current location. The locations of the waiting locations 6-1 and 6-2 are included in the facility information, and the plan creation unit 14 can determine which waiting location the vehicle 2 is located at based on the facility information and the local location of the vehicle 2. Here, the aircraft of flight A1 is parked at spot 5-1, and the vehicles 2-2 and 2-3 are present at the waiting location 6-1 close to spot 5-1, which is the parking location of the aircraft of flight A1, which is the aircraft to be processed. For this reason, the vehicles are selected as a charging target for the aircraft of flight A1, and are also planned to be operated during the work of the aircraft of flight A1 in the vehicle operation plan.
[0059] Through the above-described processing, the power usage plan and the vehicle operation plan of the vehicle 2 are created. The vehicle communication unit 15 reads out the parts of the power usage plan and the vehicle operation plan corresponding to each vehicle 2 from the storage unit 17, and transmits them to each vehicle 2. As a result, each vehicle 2 charges and operates based on the received information. Each vehicle 2 may have a display means such as a display or a monitor, and the display means may display the power usage plan and the vehicle operation plan corresponding to the vehicle 2, causing the operator of the vehicle 2 to charge and operate according to these plans, or in the case of an autonomous vehicle 2, the vehicle 2 may move based on these plans.
[0060] 2 is an example, and for example, steps S2 and S3 may be performed in parallel, or the order of steps S2 and S3 may be reversed. In this way, any process may be performed that can obtain results equivalent to those of the process shown in FIG. 2, and the specific process is not limited to the example shown in FIG.
[0061] The process shown in FIG. 2 is a process for one aircraft a certain time before landing, but the energy management device 1 repeats this process to perform the same process for the next aircraft scheduled to land. As a result, the vehicle 2 to be charged is determined from each aircraft in sequence. In the example shown in FIG. 7, an example of a power usage plan after the above-mentioned processes are performed with aircraft of three flights, A1, A2, and A3, as processing targets is shown. Similarly, in FIG. 9, a vehicle usage plan after the above-mentioned processes are performed with aircraft of three flights, A1, A2, and A3, as processing targets is shown, but in FIG. 9, the vehicle 2 corresponding to flight A3 is omitted. As shown in FIG. 7 and FIG. 9, the vehicle 2-3 is operated on flight A3 after being operated on flight A1. Note that the aircraft of flight A1 is parked at spot 5-1, and the aircraft of flight A3 is parked at spot 5-5. In FIG. 8, the movement route of the vehicle 2-2 is shown by a dashed line, and the movement route of the vehicle 2-3 is shown by a dashed line. By creating a power usage plan and a vehicle operation plan that will keep such travel routes as short as possible, it is possible to reduce power consumption.
[0062] In the above example, the above process is performed for each aircraft a certain time before landing, but the power usage plan and vehicle operation plan may be formulated at once for multiple aircraft scheduled to land within a certain period. For example, when the certain time is T and the current time is t, and there are multiple flights arriving between time t+T and time t+T+ΔT, the energy management device 1 creates a power usage plan taking these multiple aircraft into consideration at once. For example, in step S2, first remaining charge information is obtained for the above-mentioned aircraft A1 and aircraft A2 for these multiple aircraft, and in the above-mentioned step S4, the remaining charge of the storage battery is predicted for each of the aircraft A1 and aircraft A2.
[0063] In this case, the time from the current time until landing differs between the aircraft of flight A1 and the aircraft of flight A2, but the remaining charge can be predicted in the same way by using the remaining charge curve 53. When performing processing with a unified time before landing, the prediction processing may be performed by waiting until the first remaining charge information is obtained a certain time before landing for a flight with a later landing. When creating a power usage plan, the vehicle 2 to be charged from each aircraft is selected so as to reduce power consumption, on the premise that the storage batteries of the multiple aircraft are each discharged. For example, when selecting the vehicle 2 to be charged, the vehicle 2 to be charged of each aircraft is selected based on the current position of the vehicle 2 and the parking location of the aircraft so as to reduce the movement of the vehicle 2.
[0064] 2 may be performed for each aircraft, and the power usage plan for the aircraft that has already been created may be modified when creating a power usage plan for an aircraft that lands later. For example, the process shown in FIG. 2 is performed for the aircraft of flight A1 to create a power usage plan and a vehicle operation plan. After that, the process shown in FIG. 2 is similarly performed for the aircraft of flight A2. In the above example, the vehicle 2 that is being operated for work on the aircraft of flight A1 during the time period when the aircraft of flight A2 is parked is excluded from the vehicle to be charged, but in creating the power usage plan in step S5, if changing the charging plan for the aircraft of flight A1 results in less overall power consumption, the vehicle 2 that is planned to be operated for work on the aircraft of flight A1 may also be included as a vehicle to be charged.
[0065] For example, there are cases where overall power consumption can be reduced by setting the vehicle 2 scheduled for operation during work on the aircraft of flight A1 as the charging target for the aircraft of flight A2, and setting another vehicle 2 that is not in operation as the charging target for the aircraft of flight A1. In this case, the plan creation unit 14 creates a power usage plan corresponding to the aircraft of flight A2 by setting the vehicle 2 scheduled for operation during work on the aircraft of flight A1 as the charging target for the aircraft of flight A2, and updates the already created power usage plan for the aircraft of flight A1 so that the other vehicle 2 that is not in operation is set as the charging target for the aircraft of flight A1. The already created vehicle operation plan for the aircraft of flight A1 is also updated accordingly.
[0066] In the above example, the power usage plan includes a plan to charge the vehicle 2 using the power to discharge the storage battery of the aircraft, but may also include a plan to charge the vehicle 2 using a charger provided at the airport. Depending on the remaining power of the storage battery of the aircraft, it is not always possible to charge all of the vehicles 2 used in the landing operation. For this reason, the power usage plan may include a plan to charge the vehicles 2 using the chargers 7-1 to 7-3 for the vehicles 2 that are used in the operation of the aircraft to be processed but are not charged using the power obtained by discharging the storage battery of the aircraft, and for the vehicles 2 that are waiting. As shown in FIG. 8, the airport is provided with chargers 7-1 to 7-3 that can charge the vehicle 2. The plan creation unit 14 can create a power usage plan that reduces power consumption overall by including a plan to charge the vehicle 2 using the chargers 7-1 to 7-3 in the power usage plan so that the movement of the vehicle 2 is minimized. Chargers 7-1 to 7-3 are chargers installed at airports and charge vehicle 2 using a power source other than the aircraft's storage battery, for example, chargers that charge using commercial power, but are not limited to this and may be chargers that charge using power obtained by storing electricity generated by solar power generation equipment or the like installed at the airport in a power storage facility.
[0067] Next, a hardware configuration of the energy management device 1 of this embodiment will be described. The energy management device 1 of this embodiment is realized by, for example, a computer system. The energy management device 1 may be realized by one computer system or by multiple computer systems. For example, the energy management device 1 may be realized by a cloud system. In a cloud system, the hardware of the computer system and devices such as servers for each function can be arbitrarily set. For example, one computer system may have the functions of multiple devices, or multiple computer systems may have the functions of one device.
[0068] An example of the configuration of a computer system that realizes the energy management device 1 will be described. Fig. 10 is a diagram showing an example of the configuration of a computer system that realizes the energy management device 1 of the present embodiment. As shown in Fig. 10, this computer system includes a control unit 101, an input unit 102, a storage unit 103, a display unit 104, a communication unit 105, and an output unit 106, which are connected via a system bus 107.
[0069] In FIG. 10, the control unit 101 is, for example, a CPU (Central Processing Unit) or the like. The control unit 101 executes an energy management program in which each process performed by the energy management device 1 of the present embodiment is described. The input unit 102 is, for example, composed of a keyboard, a mouse, and the like, and is used by a user of the computer system to input various information. The storage unit 103 includes various memories such as a RAM (Random Access Memory) and a ROM (Read Only Memory) and a storage device such as a hard disk, and stores the program to be executed by the control unit 101, necessary data obtained in the process of the process, and the like. The storage unit 103 is also used as a temporary storage area for the program. The display unit 104 is composed of an LCD (Liquid Crystal Display: liquid crystal display panel) or the like, and displays various screens to the user of the computer system. The communication unit 105 is, for example, a communication circuit that performs communication processing. The communication unit 105 may be composed of a plurality of communication circuits corresponding to a plurality of communication methods, respectively. The output unit 106 is an output interface that outputs data to an external device such as a printer or an external storage device.
[0070] Note that Fig. 10 is an example, and the configuration of the computer system is not limited to the example of Fig. 10. For example, the computer system may not include the output unit 106. In addition, when the energy management device 1 is realized by a plurality of computer systems, all of these computer systems may not be the computer systems shown in Fig. 10. For example, some of the computer systems may not include at least one of the display unit 104, the output unit 106, and the input unit 102 shown in Fig. 10.
[0071] Here, an example of the operation of the computer system until the energy management program describing the processing of the energy management device 1 of this embodiment is in an executable state will be described. In the computer system having the above-mentioned configuration, for example, the energy management program is installed in the storage unit 103 from a CD-ROM or DVD-ROM set in a CD (Compact Disc)-ROM drive or DVD (Digital Versatile Disc)-ROM drive (not shown). Then, when the energy management program is executed, the energy management program read from the storage unit 103 is stored in an area serving as the main storage device of the storage unit 103. In this state, the control unit 101 executes the processing as the energy management device 1 of this embodiment in accordance with the energy management program stored in the storage unit 103.
[0072] In the above description, a program describing the processing in the energy management device 1 is provided on a CD-ROM or DVD-ROM as a recording medium. However, the present invention is not limited to this. Depending on the configuration of the computer system, the capacity of the program to be provided, etc., it is also possible to use a program provided over a transmission medium such as the Internet via the communication unit 105.
[0073] The energy management program of this embodiment causes a computer to execute an acquisition step of acquiring the remaining charge of the storage battery installed on the aircraft, and a planning step of creating a power usage plan, which is a power usage plan for the airport facilities, using the remaining charge of the storage battery.
[0074] The flight plan receiving unit 11, remaining amount receiving unit 12 and vehicle communication unit 15 shown in Fig. 1 are realized by the communication unit 105 shown in Fig. 10, the memory unit 17 shown in Fig. 1 is a part of the memory unit 103 shown in Fig. 10, and the remaining amount predicting unit 13 and plan creating unit 14 shown in Fig. 1 are realized by the control unit 101 shown in Fig. 10. The input accepting unit 16 shown in Fig. 1 is realized by the input unit 102 or the communication unit 105 shown in Fig. 10.
[0075] As described above, the energy management device 1 of the present embodiment predicts the remaining charge of the storage battery of the aircraft when the aircraft arrives at the airport based on the remaining charge of the storage battery mounted on the aircraft, and creates a power usage plan to include a plan to discharge the storage battery mounted on the aircraft using the predicted remaining charge to charge the vehicle 2. This makes it possible to reduce commercial power for charging the vehicle 2 and reduce the environmental load. In addition, the remaining charge of the storage battery of the aircraft can be effectively utilized. Furthermore, since the vehicle 2 used for aircraft work is selected as the vehicle to be charged for the aircraft, the movement of the vehicle 2 is reduced and power consumption can be reduced. Furthermore, power consumption can be further reduced by selecting the vehicle 2 to be charged for the aircraft so that the movement is reduced based on the current position of the vehicle 2.
[0076] Embodiment 2 Fig. 11 is a diagram showing a configuration example of an energy management system according to a second embodiment. The energy management system of this embodiment is similar to the energy management system of the first embodiment, except that an energy management device 1a is provided instead of the energy management device 1 of the first embodiment. Components having the same functions as those of the first embodiment are given the same reference numerals as those of the first embodiment, and duplicated explanations will be omitted. Below, differences from the first embodiment will be mainly explained.
[0077] In this embodiment, the energy management device 1a manages the power of airport facilities at an airport that serves as a disaster base in the event of a disaster. The energy management device 1a of this embodiment normally performs the same operation as the energy management device 1 of the first embodiment, and in the event of a disaster, creates a power usage plan using the remaining charge of the storage battery of an aircraft that has already arrived at the airport and the predicted remaining charge at the time of landing of an aircraft scheduled to land at the airport, so that at least a part of the power consumed by the airport facilities, i.e., the airport facilities, is covered by discharging the storage battery of the aircraft. The airport facilities that consume power are, for example, equipment such as air conditioning equipment, lighting equipment, and communication equipment of buildings at the airport, such as a terminal building. That is, the airport facilities of this embodiment include at least one of the air conditioning equipment, lighting equipment, and communication equipment at the airport.
[0078] When a disaster occurs, it is expected that flights will be suspended and many users will be waiting at the airport. In particular, in the case of a large-scale disaster, at an airport that serves as a disaster base, these users and airport staff may stay at the airport for several days or more. Furthermore, during the disaster base period, during which the airport functions as a disaster base, the airport may also accept disaster victims in other locations.
[0079] In the event of a large-scale disaster accompanied by a power outage, commercial power will not be supplied to the airport, and so emergency generators are used at the airport. In this embodiment, not only the power supplied from the emergency generator, but also the power stored in the storage batteries of aircraft that have already arrived and those scheduled to land is supplied to various facilities at the airport. This makes it possible to reduce the amount of power generated by the emergency generator and to reduce the environmental load.
[0080] The energy management device 1a of this embodiment adds a power consumption prediction unit 18 to the energy management device 1 of embodiment 1, and is equipped with a remaining amount prediction unit 13a and a plan creation unit 14a instead of the remaining amount prediction unit 13 and the plan creation unit 14.
[0081] The remaining charge prediction unit 13a of this embodiment has the same function as the remaining charge prediction unit 13 of the first embodiment, and when a disaster occurs, predicts the remaining charge of the storage battery of an aircraft scheduled to land during a disaster base period. The plan creation unit 14a of this embodiment has the same function as the plan creation unit 14 of the first embodiment, and when a disaster occurs, creates a power usage plan for the disaster base period.
[0082] Next, the operation of this embodiment will be described. The normal operation of the energy management device 1a of this embodiment, that is, the operation when no disaster occurs, is the same as that of the energy management device 1 of embodiment 1. When a disaster occurs, for example, the input receiving unit 16 receives an input of an instruction to create a disaster power usage plan, which is a power usage plan for when a disaster occurs, from the operator, and the energy management device 1a creates a power usage plan for when a disaster occurs.
[0083] Fig. 12 is a flowchart showing an example of an energy management process procedure in the energy management device 1a of this embodiment when a disaster occurs. The energy management process shown in Fig. 12 is a process for creating a power usage plan (power usage plan in the event of a disaster) for energy management of an airport that serves as a disaster base.
[0084] The energy management device 1a first acquires the current number of people in the airport and the power consumption of the airport (step S11). For example, the input receiving unit 16 receives input of the current number of people in the airport and the power consumption of the airport from the operator, and outputs the received information to the power consumption prediction unit 18. As described above, the number of people in the airport includes users who are staying at the airport due to the suspension of flight operations, airport staff, and also includes disaster victims when disaster victims are accepted from outside. In addition, the operator may calculate the power consumption of the airport by grasping the measured value of a power measuring device if there is one, or may use the power generation amount of the emergency generator as the power consumption of the airport if the power in the airport is supplied by an emergency generator, or may calculate the total power consumption based on the rated value of each device. In addition, in the case where the power obtained by discharging the storage battery of the aircraft has already been used for consumption by the facilities of the airport as described later, the power consumption may be calculated by adding the power generation amount of the emergency generator and the power obtained by discharging the storage battery of the aircraft.
[0085] Next, the energy management device 1a extracts aircraft that will arrive at the airport within the disaster base period from the flight plan (step S12). In detail, the plan creation unit 14a extracts aircraft that will arrive at the airport within the disaster base period from the flight plan stored in the storage unit 17. The energy management device 1a receives the flight plan periodically or when it is updated from the flight management center 3 similar to the first embodiment. This flight plan is a flight plan for the time of a disaster, and is therefore generally different from normal flight plans. During the disaster base period, it is assumed that aircraft in flight will land at the airport, but aircraft carrying passengers will not take off from the airport.
[0086] Next, the energy management device 1a predicts the remaining battery capacity of each of the extracted aircraft (step S13). In detail, the plan creation unit 14a predicts the remaining battery capacity of each of the extracted aircraft using the past first remaining capacity information stored in the storage unit 17, and outputs the predicted remaining capacity to the plan creation unit 14a. As in the first embodiment, for the extracted aircraft that are scheduled to arrive a certain time before landing or close to that time, the remaining battery capacity of the aircraft in flight is acquired and predicted as in the first embodiment. As for the extracted aircraft that have a considerable time until landing and are difficult to predict by the same method as in the first embodiment, the remaining battery capacity at the time of landing is predicted based on the first remaining capacity information of the past first remaining capacity information stored in the storage unit 17 that has similar conditions to the aircraft. For example, the average value or median of the remaining battery capacity at the time of landing in the first remaining capacity information that has similar conditions to the aircraft to be predicted is used as the predicted value.
[0087] Next, the energy management device 1a sets the capacity for the disaster base period, and predicts the power consumption for the disaster base period using the current number of people in the airport and the power consumption of the airport (step S14). In detail, the power consumption prediction unit 18 sets the capacity for the disaster base period, and predicts the power consumption for the disaster base period based on the set capacity, the current number of people in the airport and the power consumption of the airport input in step S11. The capacity for the disaster base period is input by the operator, for example, via the input reception unit 16. The capacity is the number of people staying in the airport, similar to the current number of people in the airport described above, but it is also possible that users will move from the airport. The operator assumes and inputs the capacity for the disaster base period taking these factors into consideration. Alternatively, if the number of disaster victims to be accepted has already been specified by a local government or the like, the operator may also determine the capacity taking the number of disaster victims into consideration.
[0088] For example, the power consumption prediction unit 18 predicts the power consumption during the disaster base period using the ratio C1 of the portion of the total power consumption of the airport that depends on the capacity, the ratio C2 of the portion of the total power consumption of the airport that does not depend on the capacity, and the number of people and power consumption in the airport input in step S11. If the number of people in the airport input in step S11 is N0, the power consumption input in step S11 is P0, and the capacity set in step S14 is N1, the predicted value of power consumption P p is calculated using the following formula (1). P p =P0×C1×(N1 / N0)+P0×C2...(1)
[0089] In the above formula (1), it is assumed that the portion of the total power consumption that depends on the capacity is proportional to the number of people, but this is not limiting, and the power consumption may be predicted in the same manner as the above formula (1) using another function in which the power consumption increases as the number of people increases. In addition, for example, if a certain area is used for a capacity of up to 1000 people, and another area is used when the capacity exceeds 1000 people, the power consumption changes stepwise with respect to the capacity. In such a case, for example, the range of the capacity and the coefficient used instead of the above C1×(N1 / N0) may be stored in the storage unit 17 as a table, and the power consumption of the portion that depends on the capacity may be obtained using this table. For example, the coefficient Z1 is set for the range of 1 to 1000 people, the coefficient Z2 is set for the range of 1001 to 3000 people, the coefficient Z3 is set for the range of 3001 to 5000 people, and so on, and the power consumption prediction unit 18 predicts the power consumption using the ratio between the coefficient corresponding to the number of people in the airport input in step S11 and the coefficient corresponding to the capacity set in step S14.
[0090] Furthermore, when creating a power usage plan on the assumption that the number of people accommodated will change during the disaster base period, in step S14, the disaster base period may be divided into a number of time slots and the number of people accommodated may be set for each time slot. In this case, power consumption will be predicted for each time slot. Also, since power consumption may change throughout the day, the power consumption input in step S12 may be input for each time slot. In this case as well, power consumption will be predicted for each time slot.
[0091] In step S14, the capacity may not be input, and in this case, the power consumption prediction unit 18 sets the current number of people in the airport input in step S12 as the capacity for the disaster base period. Therefore, in this case, the predicted value of power consumption is the same as the power consumption of the airport input in step S12.
[0092] Furthermore, instead of inputting the current number of people in the airport and the power consumption of the airport in step S11, the power consumption according to the number of people in the airport may be stored in advance in the memory unit 17 as a table or a formula for calculating a function according to the number of people, and the power consumption prediction unit 18 may predict the power consumption using the capacity of the disaster base period set in step S14 and the table or formula.
[0093] Next, the energy management device 1a creates a power usage plan using the predicted value of power consumption and the predicted value of the remaining battery charge of each aircraft (step S15). In detail, the plan creation unit 14a creates a power usage plan for the disaster base period using the predicted value of power consumption output from the power consumption prediction unit 18 and the predicted value of the remaining battery charge of each aircraft output from the remaining charge prediction unit 13a. At this time, since aircraft carrying normal passengers will be suspended in the event of a disaster, the power usage plan is created on the premise that power discharged from the aircraft's storage battery will not be used to charge the vehicle 2. In addition, if there are non-electric vehicles, the non-electric vehicles may be used preferentially in the event of a disaster. For aircraft that have already landed, the power usage plan is created using the remaining battery charge acquired from the aircraft. In addition, if the emergency generator is a generator that generates power using fuel, the power usage plan is created taking into consideration the remaining fuel charge. The remaining fuel charge may be a standard reserve amount that is stored in advance in the storage unit 17 as equipment information, or may be input by the operator in step S12.
[0094] FIG. 13 is a diagram showing an example of a power usage plan at the time of occurrence of a disaster according to the present embodiment. As shown in FIG. 13, the power usage plan at the time of occurrence of a disaster includes the supply power / supplyable power (power amount), the power consumption (power amount), and the difference for each time period. The difference indicates a value obtained by subtracting the power consumption from the supplyable power, and a positive value indicates that the supplyable amount exceeds the power consumption and surplus power occurs, and a negative value indicates that a power shortage occurs. In FIG. 13, the storage battery of the aircraft is shown in the form of supply power / supplyable power, such as 50 / 300. The supply power indicates the amount of power to be supplied during that time period, i.e., the amount of power to be discharged from the storage battery of the aircraft, and the supplyable amount indicates the amount of power equivalent to the remaining amount of the storage battery. For the emergency generator, the supplyable amount is omitted because it is set as a rated value as the maximum power generation amount, and only the amount of power to be supplied, i.e., the supply power, is shown. In the example shown in FIG. 13, the maximum power generation amount of the emergency generator, i.e., the supplyable power, is set to 1000.
[0095] Returning to the description of Fig. 12, the energy management device 1a next determines whether or not a power shortage will occur (step S16). In detail, the plan creation unit 14a refers to the power usage plan created in step S15 and determines whether or not there is a time period in which the difference obtained by subtracting the power consumption from the available power is negative.
[0096] When a power shortage occurs (Yes in step S16), the energy management device 1a acquires the remaining charge of the storage battery of the vehicle 2 (step S18). The method of acquiring the remaining charge of the storage battery of the vehicle 2 is the same as in the first embodiment.
[0097] Next, the energy management device 1a creates a power usage plan using the predicted value of power consumption, the predicted value of the remaining battery charge of each aircraft, and the remaining battery charge of the vehicle (step S19), and ends the process. In detail, the plan creation unit 14a creates a power usage plan in the same way as in step S15, but at this time, for the battery of the vehicle 2, the available power supply is calculated based on the remaining battery charge in the same way as for the battery of the aircraft, and the power supply for each time period is determined. For the difference in the power usage plan, the available power supply of the vehicle 2 is also taken into consideration in the same way as for the battery of the aircraft, and a value is calculated by subtracting the power consumption from the available power supply. Note that there are cases where the power shortage is not resolved even if the batteries of all the vehicles 2 are discharged. In such a case, the energy management device 1a may notify the operator by displaying the fact that the power shortage is not resolved. In response to this, the operator takes measures such as limiting the number of people accommodated or saving power.
[0098] If no power shortage occurs (No in step S16), the energy management device 1a judges whether or not surplus power occurs (step S17). In detail, the plan creation unit 14a refers to the power usage plan created in step S15 and judges whether or not the difference obtained by subtracting the power consumption from the available power is positive in all time periods.
[0099] If surplus power occurs (step S17 Yes), the energy management device 1a changes at least one of the capacity and the disaster base period, updates the predicted value of power consumption (step S20), and performs the process from step S15 again. In detail, in step S20, the plan creation unit 14a increases at least one of the capacity and the disaster base period so as to increase at least one of the capacity and the disaster base period. In this way, if surplus power occurs in the disaster power utilization plan during the disaster base period, the capacity during the disaster base period can be increased or the disaster base period can be extended by recreating the disaster power utilization plan with changes to increase at least one of the disaster base period and the capacity.
[0100] If no surplus power is generated (step S17: No), the energy management device 1a ends the process. In the example shown in FIG. 12, the process ends after step S19, but if the process from step S17 onward is performed after step S19 and surplus power is generated by using the storage battery of the vehicle 2, at least one of the accommodation capacity and the disaster base period may be increased.
[0101] 12 is merely an example, and for example, steps S11 and S12 may be performed in parallel, or the order of steps S11 and S12 may be reversed. In this manner, any process may be performed that can obtain results equivalent to those of the process shown in FIG. 12, and the specific process is not limited to the example shown in FIG.
[0102] In addition, in the above example, it was assumed that vehicle 2 would not be charged using the electricity stored in the aircraft's battery, but for aircraft carrying passengers, a power usage plan may be created on the assumption that vehicle 2 will be charged, as in embodiment 1.
[0103] Furthermore, if a power shortage occurs in step S16 or in the power usage plan created in step S19, the energy management device 1a may request the aviation management center 3 to change the flight plan of aircraft scheduled to land at other airports or aircraft waiting at other airports to land at airports managed by the energy management device 1a. In the event of a disaster, by consolidating out-of-service aircraft at an airport that serves as a disaster base to the extent that the airport can accept, the storage batteries of more aircraft can be used as power supply sources.
[0104] In the above example, the same operation as in the first embodiment is performed under normal circumstances, and the process shown in Fig. 12 is performed when a disaster occurs, but the present invention is not limited to this. The energy management device may be configured to not perform the operation of the first embodiment under normal circumstances, but to perform the process shown in Fig. 12 when a disaster occurs. In this case, the energy management device does not need to have a function to perform the process of the first embodiment.
[0105] Also, in the case where the airport does not have an emergency generator, the disaster power usage plan may be created by considering only the power to discharge the storage battery of the aircraft without using the emergency generator as the supply power. That is, in this embodiment, the plan creation unit 14a may create a disaster power usage plan using the remaining capacity of the storage battery of the aircraft. As in the above example, the plan creation unit 14a may create a disaster power usage plan by further using the power generated by the emergency generator. Also, as in the above example, when a power shortage occurs, the plan creation unit 14a may create a disaster power usage plan by further using the remaining capacity of the storage battery of the vehicle 2. Also, in the above example, it is assumed that the commercial power source will be powered out when a disaster occurs, but when a power outage does not occur, a power usage plan may be created so that the power supplied from the commercial power source is suppressed to a certain value or less while considering the commercial power source as a supply power.
[0106] The hardware configuration of the energy management device 1a of this embodiment is the same as that of embodiment 1. The power consumption prediction unit 18, remaining power prediction unit 13a, and plan creation unit 14a of this embodiment are realized, for example, by a control unit 101 shown in Fig. 10. The method of executing an energy management program for realizing the processing of this embodiment and the method of providing an energy management program for realizing the processing of the embodiment are also the same as those of embodiment 1.
[0107] According to the above process, in this embodiment, a power usage plan for use in the event of a disaster can be created using the power stored in the storage battery of the aircraft. This allows the power stored in the storage battery of the aircraft to be effectively utilized, and increases the power that can be supplied at the airport that has become a disaster base. If a power usage plan is created so that the amount of power generated by the emergency generator is reduced by the amount of power stored in the storage battery of the aircraft, the environmental load can be reduced by reducing the amount of power generated by the emergency generator. Furthermore, if the power stored in the storage battery of the vehicle 2 is used, the environmental load can be further reduced. Furthermore, by using the power stored in the storage battery of the aircraft, the number of people that can be accommodated at the airport that is a disaster base can be increased, and more disaster victims can be accepted. Furthermore, by using the power stored in the storage battery of the aircraft, the period during which the airport is a disaster base can be extended.
[0108] The configurations shown in the above embodiments are merely examples, and may be combined with other known technologies, or the embodiments may be combined with each other. Also, parts of the configurations may be omitted or modified without departing from the spirit of the invention. [Explanation of symbols]
[0109] 1,1a energy management device, 2-1 to 2-n vehicles, 3 flight management center, 4 operation management system, 11 flight plan receiving unit, 12 remaining amount receiving unit, 13,13a remaining amount prediction unit, 14,14a plan creation unit, 15 vehicle communication unit, 16 input reception unit, 17 memory unit, 18 power consumption prediction unit.
Claims
1. an acquisition unit that acquires a remaining charge of a storage battery installed in an aircraft; a remaining charge prediction unit that predicts a remaining charge of the storage battery at the time of landing of a first aircraft that is the aircraft scheduled to land at an airport; a plan creation unit that creates a power usage plan that is a power usage plan for airport facilities that are airport facilities, using the predicted value predicted by the remaining power prediction unit; Equipped with The energy management device is characterized in that the remaining charge prediction unit predicts the remaining charge of the storage battery at the time of landing of the first aircraft based on information indicating the remaining charge of the storage battery and the corresponding time obtained during past flights of the first aircraft or a second aircraft which is an aircraft other than the first aircraft that has been operated in the past, and information indicating the remaining charge of the storage battery obtained from the first aircraft during flight.
2. the airport facility includes motorized vehicles used for operations at the airport; The energy management device according to claim 1 , wherein the plan creation unit includes a charging plan for discharging the storage battery to charge the vehicle.
3. The energy management device according to claim 2, characterized in that the plan creation unit selects the vehicle to be charged, which is the vehicle whose storage battery is discharged and charged, from among the vehicles used for work related to the landing of the aircraft.
4. The energy management device according to claim 3 , wherein the plan creation unit acquires a current position of the vehicle, and selects the vehicle to be charged based on the current position and a parking location of the aircraft.
5. The energy management device according to claim 4 , wherein the plan creation unit selects, as the vehicle to be charged, the vehicle that is closer to the parking location with priority.
6. 6. The energy management device according to claim 3, wherein the plan creation unit selects the vehicle to be charged based on a remaining charge of a storage battery of the vehicle.
7. The energy management device according to claim 6 , wherein the plan creation unit further selects the vehicle to be charged based on a task time for each vehicle of the task related to the landing of the aircraft.
8. 8. The energy management device according to claim 2, wherein the plan creation unit creates a vehicle operation plan that is an operation plan for the vehicle, based on the power usage plan.
9. 9. The energy management device according to claim 2, wherein the power usage plan further includes a charging plan for the vehicle using charging equipment installed at the airport for charging the vehicle using a power source other than the storage battery.
10. The airport facilities include at least one of air conditioning equipment, lighting equipment, and communication equipment at the airport; The energy management device according to claim 1 , wherein the plan creation unit creates a disaster power usage plan that is the power usage plan for when a disaster occurs.
11. The energy management device according to claim 10 , wherein the plan creation unit creates the disaster power utilization plan by further using power generated by an emergency power generator installed at the airport.
12. The energy management device according to claim 11 , wherein the plan creation unit creates the disaster power utilization plan for a disaster base period during which the airport serves as a disaster base.
13. The remaining charge prediction unit predicts a remaining charge of the storage battery at the time of landing of the first aircraft scheduled to land at the airport during the disaster base period, The plan creation unit The energy management device described in claim 12, characterized in that the disaster power usage plan for the disaster base period is created using the remaining charge of the storage battery of the aircraft that has already landed at the airport and the remaining charge of the storage battery at the time of landing of the first aircraft scheduled to land at the airport during the disaster base period predicted by the remaining charge prediction unit.
14. a power consumption prediction unit that predicts the power consumption of the airport facility using a capacity that is a number of people that can be accommodated at the airport; Equipped with 14. The energy management device according to claim 12 or 13, wherein the plan creation unit creates the disaster power usage plan for the disaster base period using the power consumption predicted by the power consumption prediction unit.
15. The energy management device described in claim 14, characterized in that when a surplus of electricity occurs in the disaster power utilization plan for the disaster base period, the plan creation unit recreates the disaster power utilization plan by making changes to increase at least one of the disaster base period and the capacity.
16. the airport facility includes motorized vehicles used for operations at the airport; The energy management device described in any one of claims 12 to 15, characterized in that when a power shortage occurs in the disaster power utilization plan during the disaster base period, the plan creation unit creates the disaster power utilization plan by further using the remaining capacity of the vehicle's storage battery.
17. Airport facilities, which are the facilities of the airport; An energy management device that manages the power of the airport facility; Equipped with The energy management device includes: an acquisition unit that acquires a remaining charge of a storage battery installed in an aircraft; a remaining charge prediction unit that predicts a remaining charge of the storage battery at the time of landing of a first aircraft that is the aircraft scheduled to land at the airport; a plan creation unit that creates a power usage plan, which is a power usage plan for the airport facility, using the predicted value predicted by the remaining amount prediction unit; Equipped with The energy management system is characterized in that the remaining charge prediction unit predicts the remaining charge of the storage battery at the time of landing of the first aircraft based on information indicating the remaining charge of the storage battery and the corresponding time obtained during past flights of the first aircraft or a second aircraft which is an aircraft other than the first aircraft that has been operated in the past, and information indicating the remaining charge of the storage battery obtained from the first aircraft during flight.
18. On the computer, An acquisition step of acquiring a remaining capacity of a storage battery installed in the aircraft; a prediction step of predicting a remaining charge of the storage battery at the time of landing of a first aircraft, the first aircraft being the aircraft scheduled to land at an airport; A plan creation step of creating a power usage plan that is a power usage plan for airport facilities that are airport facilities, using the remaining capacity of the storage battery; Run the command, The prediction step predicts the remaining charge of the storage battery at the time of landing of the first aircraft based on information indicating the remaining charge of the storage battery and the corresponding time obtained during past flights of the first aircraft or a second aircraft other than the first aircraft that have been operated in the past, and information indicating the remaining charge of the storage battery obtained from the first aircraft during flight.
Citation Information
Patent Citations
Electric power supply system, electric power supply device and electric power supply method
JP2012178909A
Vehicle for airport
JP2013133066A
Charger / feeder, charge / feed management apparatus, energy management system and charge / feed management method
JP2014135877A
Operation plan generation device and operation plan generation method
JP2015060570A
Energy management system
JP2015156785A