Power supply structure and power supply system
The power supply structure and system address limited power supply by redirecting external power to all building loads, ensuring convenience and supporting hybrid vehicles during emergencies.
Patent Information
- Application Number
- JP2020192468
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2020-11-19
- Publication Date
- 2024-10-04
- Estimated Expiration
- 2040-11-19
AI Technical Summary
Existing power supply systems from vehicle batteries to buildings are limited, allowing power to only some electrical loads, reducing convenience during emergencies.
A power supply structure and system that includes an external power supply connection, emergency and normal power supply paths, and switching units to redirect power from an external source like a vehicle to all electrical loads in a building, with control units for automated switching.
Ensures wide-ranging power usage during emergencies by switching to external power sources, providing convenience and supporting hybrid vehicles without charging ports.
Smart Images

Figure 0007561582000001 
Figure 0007561582000002 
Figure 0007561582000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a power supply structure and a power supply system. [Background technology]
[0002] The following Patent Document 1 discloses a power supply system that can supply power from an on-board battery to a building in an emergency by connecting the building and an automobile with a power line. The power supply system in the following Patent Document 1 is configured to stop supplying power to the building when the remaining capacity of the on-board battery falls below a predetermined value. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2009-278776 A Summary of the Invention [Problem to be solved by the invention]
[0004] However, when power is supplied from an on-board battery to a building, the amount of power that can be supplied is limited, so power may only be supplied to some of the electrical loads (electrical appliances such as home appliances and lighting fixtures) in the building. In this case, the residents of the building can only use some of the electrical loads, which significantly reduces convenience in an emergency.
[0005] In consideration of the above, an object of the present invention is to provide a power supply structure and a power supply system that can supply power to a building from an external power source other than a commercial power source, and that can ensure convenience even in emergencies. [Means for solving the problem]
[0006] The power supply structure of the first embodiment is provided in a building and includes an external power source connection unit to which an external power source other than a commercial power source is connected, a power supply path switching unit to which an emergency power supply path from the external power source connection unit and a normal power supply path from the commercial power source are connected and which is configured to be able to switch between the emergency power supply path and the normal power supply path, a plurality of indoor wirings which respectively connect the power supply path switching unit to a plurality of electrical loads within the building, and a power supply target switching unit which switches the indoor wirings to which power is supplied from the emergency power supply path.
[0007] In the power supply structure according to the first aspect, an external power supply connection unit is provided in a building, and an external power supply other than a commercial power supply is connected to the external power supply connection unit. An emergency power supply path from the external power supply connection unit and a normal power supply path from the commercial power supply are connected to the power supply path switching unit. Here, the power supply path switching unit is configured to be able to switch between the emergency power supply path and the normal power supply path. As a result, when a power outage occurs due to a disaster or the like and power cannot be supplied to the building from the normal power supply path, the power supply path switching unit switches the power supply path to the emergency power supply path, making it possible to supply power from the external power supply to the building.
[0008] In addition, in the power supply structure, the power supply path switching unit and a plurality of electrical loads in the building are connected by indoor wiring, and the indoor wiring to which power is supplied from the emergency power supply path can be switched by the power supply target switching unit. This allows a wide range of electrical appliances to be used by switching the power supply destination, even when the amount of power that can be supplied is limited.
[0009] A power supply structure according to a second aspect is the power supply structure of the first aspect, wherein the external power supply connection portion is configured to be electrically connectable to an accessory outlet of a vehicle.
[0010] In the power supply structure according to the second aspect, power can be supplied from the accessory outlet of the vehicle to the building. This allows even a hybrid vehicle (HV) that does not have a charging port to supply power to the building as long as it has an accessory outlet.
[0011] The power supply structure according to a third aspect is the power supply structure of the first or second aspect, further comprising a power supply destination display unit that displays a room or the electric load to which power can be supplied by the power supply target switching unit.
[0012] In the power supply structure according to the third aspect, the power supply destination display section displays the rooms or electrical loads to which power can be supplied, so that the user can know the available electrical loads simply by looking at the power supply destination display section.
[0013] A power supply structure according to a fourth aspect is any one of the first to third aspects, wherein the power supply target switching unit switches the power supply target for each room partitioned within a building.
[0014] In the power supply structure of the fourth aspect, the power supply target can be switched for each room in a building, so that, for example, the living room can be the power supply target area during the day and the bedroom can be the power supply target area at night.
[0015] A power supply system according to a fifth aspect includes a power supply structure according to any one of the first to third aspects, and a control unit that electrically controls switching by the power supply target switching unit, and the control unit switches the power supply target switching unit so as to enable power supply to the electrical load in a room specified by a user.
[0016] In the power supply structure according to the fifth aspect, the power supply target switching unit can switch the room (power supply target area) to which power can be supplied by a signal from the control unit, thereby eliminating the need for the user to manually switch the power supply target area.
[0017] In the power supply structure of the sixth aspect, in the fifth aspect, the control unit includes a power supply target acquisition unit that acquires the names of each of the electrical loads stored in advance, and switches the power supply target switching unit so that power can be supplied to the electrical load corresponding to the name selected by the user as the power supply target.
[0018] In the power supply structure of the sixth aspect, for example, if the name of an electrical appliance is stored for each electrical load, the user can simply select the name of the electrical appliance they want to use, and the power supply path can be switched so that power is supplied to that electrical appliance.
[0019] The power supply structure of the seventh aspect is the same as that of the fifth aspect, and further includes a human presence sensor that detects a person in a building, and the control unit switches the power supply target switching unit so that power can be supplied to the electrical load in a room in which a person is detected based on a signal from the human presence sensor.
[0020] In the power supply structure according to the seventh aspect, the user can use electrical devices in the room in which the user is present without having to switch the power supply target area by himself / herself. Effect of the Invention
[0021] As described above, the power supply structure and power supply system according to the present invention can ensure convenience even in emergencies. [Brief description of the drawings]
[0022] [Figure 1] 1 is a schematic diagram showing an overall configuration of a power supply system including a power supply structure according to a first embodiment. [Diagram 2] FIG. 4 is a diagram showing a display example of a mobile terminal in the first embodiment. [Diagram 3] 1 is a block diagram showing a hardware configuration of a power supply system according to a first embodiment. [Figure 4] 1 is a block diagram showing a functional configuration of a power supply system according to a first embodiment. [Diagram 5] 5 is a flowchart showing an example of the flow of a power supply target switching process performed by the power supply system according to the first embodiment. [Figure 6] FIG. 4 is a schematic diagram showing an overall configuration of a power supply system according to a modified example of the first embodiment. [Figure 7] FIG. 11 is a block diagram showing a functional configuration of a power supply system according to a second embodiment. [Figure 8] FIG. 11 is a diagram showing a display example of a mobile terminal in the second embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0023] First Embodiment A power supply system 10 including a power supply structure according to a first embodiment will be described with reference to the drawings.
[0024] As shown in FIG. 1, a building 12 to which the power supply system 10 of this embodiment is applied is, for example, a modular building assembled using a plurality of building units, and is configured to include a building body 14 and a roof 16.
[0025] The building main body 14 is composed of a first floor and a second floor, and in this embodiment, as an example, the first floor is a living / dining / kitchen 14A (hereinafter referred to as "LDK14A").
[0026] The second floor of the main building 14 includes a bedroom 14B and a study 14C. Although not shown, the main building 14 also includes a toilet, a bathroom, and other facilities necessary for daily life.
[0027] Here, the building main body 14 is provided with an external power supply connection section 18 to which an external power supply other than a commercial power supply is connected. The external power supply connection section 18 is provided on the outer wall of the building main body 14, and in this embodiment, as an example, the external power supply connection section 18 is configured by a waterproof flange inlet.
[0028] One end of a cable 20 is connected to the external power supply connection unit 18. The other end of the cable 20 is connected to a vehicle V serving as an external power supply. The vehicle V is a hybrid vehicle (HV) using an engine and a motor as drive sources, and is equipped with a battery serving as a storage battery.
[0029] Here, an AC 100V accessory outlet is provided in the passenger compartment of the vehicle V, and the other end of the cable 20 is connected to the accessory outlet. Then, with the building 12 and the vehicle V connected by the cable 20, the vehicle V is operated under a predetermined condition such as an emergency, thereby supplying power from the vehicle V to the building 12. Even when the vehicle V is supplying power to the building 12, power is generated by starting the engine of the vehicle V, and the generated power is supplied to the battery of the vehicle V. In this manner, it is configured to be possible to supply power to the building 12 for a long period of time.
[0030] The vehicle V is not limited to a hybrid vehicle, and may be any vehicle other than a hybrid vehicle as long as it is capable of supplying power to the building 12. For example, the vehicle V may be an electric vehicle (EV) or a fuel cell vehicle (FCV).
[0031] Furthermore, the external power source is not limited to the vehicle V, and a generator or the like may also be connected.
[0032] One end of a first power line 22A is connected to the external power supply connection unit 18, and the other end of the first power line 22A is connected to a power supply target switching unit 24. The power supply target switching unit 24 will be described in detail later.
[0033] One end of the second power line 22B and one end of the third power line 22C are connected to the power supply target switching unit 24. The other end of the second power line 22B is connected to an living / dining / kitchen area switching unit 30 serving as a power supply path switching unit. The other end of the third power line 22C is connected to a bedroom switching unit 32 serving as a power supply path switching unit.
[0034] Meanwhile, a distribution board 26 is provided in the building main body 14. A power transmission line 28 is connected to the distribution board 26, and commercial power (grid power) is supplied to the building 12 from a commercial power source (not shown) via this power transmission line 28.
[0035] One end of a fourth power line 22D and one end of a fifth power line 22E are connected to the distribution board 26. The other end of the fourth power line 22D is connected to the living / dining / kitchen switching unit 30. The other end of the fifth power line 22E is connected to the bedroom switching unit 32.
[0036] As described above, the LDK switching unit 30 is connected to the emergency power supply path from the vehicle V via the first power line 22A and the second power line 22B. In addition, the LDK switching unit 30 is connected to the normal power supply path from the commercial power source via the fourth power line 22D. On the other hand, the bedroom switching unit 32 is connected to the emergency power supply path from the vehicle V via the first power line 22A and the third power line 22C. In addition, the bedroom switching unit 32 is connected to the normal power supply path from the commercial power source via the fifth power line 22E.
[0037] Here, the LDK switching unit 30 is connected to an LDK unit cable 34 as indoor wiring, and the LDK unit cable 34 is wired to each electrical load of the LDK 14A. In Fig. 1, as an example, a state in which the LDK unit cable 34 is wired to a TV 40, a lighting fixture 42, an outlet 44, a refrigerator 46, and an IH heater 48 is shown.
[0038] The LDK switching unit 30 is configured to be able to switch between an emergency power supply path and a normal power supply path. Specifically, the LDK switching unit 30 includes a changeover switch, and is able to switch between an "emergency state" in which the power supply target switching unit 24 and the LDK unit cable 34 are connected to supply power from the emergency power supply path, and a "normal state" in which the distribution board 26 and the LDK unit cable 34 are connected to supply power from the normal power supply path.
[0039] The bedroom switching unit 32 is connected to a bedroom unit cable 36 as indoor wiring, and the bedroom unit cable 36 is wired to each electrical load in the bedroom 14B. In Fig. 1, as an example, the state where the bedroom unit cable 36 is wired to a lighting fixture 50 and an outlet 52 is shown.
[0040] Bedroom switching unit 32 is configured to be able to switch between an emergency power supply path and a normal power supply path. Specifically, bedroom switching unit 32 includes a switch and is able to switch between an "emergency state" in which power supply target switching unit 24 and bedroom unit cable 36 are connected to supply power from the emergency power supply path, and a "normal state" in which distribution board 26 and bedroom unit cable 36 are connected to supply power from the normal power supply path.
[0041] The living / dining / kitchen area switching unit 30 and the bedroom switching unit 32 are configured to be switched at the same time. Therefore, when the supply of power from the commercial power source is stopped during a power outage, both the living / dining / kitchen area switching unit 30 and the bedroom switching unit 32 can be switched from the "normal state" to the "emergency state" to supply power from the vehicle V to the building 12 via the emergency power supply path.
[0042] For ease of explanation, FIG. 1 only illustrates and explains the wiring for the living / dining / kitchen area 14A and the bedroom 14B. Similarly, the wiring for the study 14C is arranged so that an emergency power supply path and a normal power supply path can be switched, and a study switching unit (not shown) is provided.
[0043] (Power supply target switching unit 24) Next, the power supply target switching unit 24 in this embodiment will be described in detail. The power supply target switching unit 24 in this embodiment is connected to the living / dining / kitchen area switching unit 30 and the bedroom switching unit 32. Although not shown, the power supply target switching unit 24 is also connected to a study switching unit that serves as a power supply path to the study 14C.
[0044] Here, the power supply target switching unit 24 includes a changeover switch, and is configured to be able to switch the power supply destination of the power supplied from the vehicle V via the first power line 22A by the living / dining / kitchen area switching unit 30, the bedroom switching unit 32, and the study switching unit. In other words, the power supply target switching unit 24 is configured to be able to switch the power supply destination to which power is supplied from the emergency power supply path for each room divided in the building 12.
[0045] Moreover, in the initial state, the power supply target switching unit 24 sets the position of the changeover switch so that the LDK 14A in which the refrigerator 46 is installed becomes the power supply destination. Here, in this embodiment, the changeover of the changeover switch in the power supply target switching unit 24 is electrically controlled by the control unit 60 (see FIG. 3) constituting the power supply system 10.
[0046] (Hardware configuration of power supply system 10) 3, the control unit 60 constituting the power supply system 10 of this embodiment includes a CPU (Central Processing Unit: processor) 62, a ROM (Read Only Memory) 64, a RAM (Random Access Memory) 66, a storage 68, a communication interface 70, and an input / output interface 72. Each component is connected to each other via a bus 74 so as to be able to communicate with each other.
[0047] The CPU 62 is a central processing unit that executes various programs and controls each part. That is, the CPU 62 reads a program from the ROM 64 or the storage 68, and executes the program using the RAM 66 as a working area. The CPU 62 controls each of the above components and performs various arithmetic processing according to the program recorded in the ROM 64 or the storage 68.
[0048] The ROM 64 stores various programs and various data. The RAM 66 temporarily stores programs or data as a working area. The storage 68 is a non-temporary recording medium configured with an HDD (Hard Disk Drive) or an SSD (Solid State Drive) and stores various programs including an operating system and various data. In this embodiment, the ROM 64 or the storage 68 stores a program for executing a power supply target cut-off house process and the like.
[0049] The communication interface 70 is an interface for the control unit 60 to communicate with external devices via the network N, and uses standards such as 5G, LTE, Wi-Fi (registered trademark), and Ethernet (registered trademark). In this embodiment, the communication interface 70 enables the control unit 60 to communicate with a mobile terminal 89 serving as a power supply destination display unit. The mobile terminal 89 is, for example, a smartphone carried by a user of the building 12, and by starting a predetermined application from this mobile terminal 89, electric loads to which power can be supplied are displayed.
[0050] A display device 76 as a power supply destination display unit, an input device 78, a power supply target switching unit 24, an LDK switching unit 30, and a bedroom switching unit 32 are connected to the input / output interface 72. The display device 76 is configured to include, for example, a monitor attached inside the building 12, and displays on this display device 76 the electric loads that can be supplied with power.
[0051] The input device 78 is a device for a user to input to the control unit 60, and is configured to include, for example, a touch panel unit mounted on a monitor installed in a room. That is, in this embodiment, a touch panel type monitor is provided in a room of the building 12, and this monitor has the functions of the display device 76 and the input device 78.
[0052] The power supply object switching unit 24, the living / dining / kitchen area switching unit 30, and the bedroom switching unit 32 are each configured so that the changeover switch is switched by a signal from the control unit 60.
[0053] (Functional configuration of power supply system 10) The power supply system 10 uses the above hardware resources to realize various functions. The functional configuration realized by the power supply system 10 will be described with reference to FIG.
[0054] 4, the power supply system 10 includes, as functional components, an external power supply connection confirmation unit 80, a route switching unit 81, an instruction receiving unit 82, a power supply target area switching unit 83, and a display control unit 84. Each functional component is realized by the CPU 62 reading and executing a program stored in the ROM 64 or the storage 68.
[0055] The external power supply connection confirmation unit 80 confirms that an external power supply has been connected. Specifically, sensors that detect that the cable 20 has been connected are provided in the external power supply connection unit 18 in Fig. 1, and the external power supply connection unit 18 confirms that the external power supply has been connected based on signals from the sensors.
[0056] The path switching unit 81 switches between an emergency power supply path and a normal power supply path. Specifically, the path switching unit 81 switches the changeover switches of the living / dining / kitchen area switching unit 30 and the bedroom switching unit 32 from the "normal state" to the "emergency state." Similarly, the path switching unit 81 switches the changeover switch of the study switching unit from the "normal state" to the "emergency state" during a power outage.
[0057] Here, the path switching unit 81 may automatically switch each changeover switch from the "normal state" to the "emergency state" when a power outage is detected. Also, the path switching unit 81 may automatically switch each changeover switch from the "normal state" to the "emergency state" when the external power connection confirmation unit 80 confirms that an external power source is connected. As an example in this embodiment, when a power outage is detected and / or when an external power source is connected to the external power source connection unit 18, the path switching unit 81 switches each changeover switch from the "normal state" to the "emergency state".
[0058] The instruction receiving unit 82 receives an instruction from a user. Specifically, the instruction receiving unit 82 receives an instruction to switch the power supply target area from the user via the input device 78 or the mobile terminal 89.
[0059] The power supply target area switching unit 83 switches the power supply target area for each room divided in the building 12. Specifically, the power supply target area switching unit 83 switches the change-over switch of the power supply target switching unit 24 in response to an instruction of the user received by the instruction receiving unit 82. In this way, the power supplied from the vehicle V via the first power line 22A is switched so as to flow to the power supply target area instructed by the user.
[0060] The display control unit 84 performs various displays on the display device 76, which is a power supply destination display unit, and the mobile terminal 89. For example, the display control unit 84 displays a power supply target area to which power can be supplied, on the display device 76 and the mobile terminal 89. A display example in which the power supply target area is displayed on the mobile terminal 89 will be described below.
[0061] 2, an icon M1 corresponding to the living / dining / kitchen area 14A, an icon M2 corresponding to the study 14C, and an icon M3 corresponding to the bedroom 14B are displayed in the display area of the mobile terminal 89. The display of FIG. 2 may be configured to be displayed, for example, by starting a predetermined application on the mobile terminal 89. Also, a message instructing the selection of a power supply destination may be displayed.
[0062] 2, the display mode of the icon M1 is displayed differently from the display modes of the icons M2 and M3 by the function of the display control unit 84. In this embodiment, the selected icon M1 is displayed inverted. By changing the display mode in this way, it is shown that the LDK 14A corresponding to the icon M1 is a power supply target area.
[0063] 2, when the user selects (touches) icon M3 corresponding to bedroom 14B, the inverted display of icon M1 is cancelled and icon M3 is displayed inverted. Furthermore, an instruction to switch bedroom 14B to the power supply target area is received by instruction receiving unit 82, and power supply target area switching unit 83 switches the switch of power supply target switching unit 24 from living / dining / kitchen switching unit 30 to bedroom switching unit 32. This makes it possible to use lighting fixture 50 and outlet 52 in bedroom 14B.
[0064] (action) Next, the operation of this embodiment will be described.
[0065] (An example of power supply target switching processing) 5 is a flowchart showing an example of the flow of the power supply target switching process by the power supply system 10. This power supply target switching process is executed by the CPU 62 reading a program from the ROM 64 or the storage 68, expanding it in the RAM 66, and executing it. Note that the power supply target switching process described below is executed in a state where the supply of commercial power is stopped due to a power outage.
[0066] As shown in FIG. 5, in step S102, the CPU 62 determines whether or not an external power source is connected to the external power source connection unit 18. In this embodiment, the CPU 62 determines whether or not a vehicle V is connected to the external power source connection unit 18. The CPU 62 acquires signals from sensors that detect that the cable 20 is connected, using the function of the external power source connection confirmation unit 80. Then, when the external power source connection confirmation unit 80 confirms that the cable 20 is connected to the vehicle V, the CPU 62 proceeds to processing in step S104. On the other hand, when the external power source connection confirmation unit 80 does not confirm that the cable 20 is connected to the vehicle V, that is, when the sensors do not detect the connection between the vehicle V and the cable 20, the CPU 62 ends the power supply target switching processing.
[0067] The CPU 62 checks the power supply path in step S104. Specifically, the CPU 62 acquires signals from the living / dining / kitchen switching unit 30, the bedroom switching unit 32, and the study switching unit. In this embodiment, in the event of a power outage or when the vehicle V is connected to the external power supply connection unit 18, the path switching unit 81 automatically switches each switch to the "emergency state." For this reason, the CPU 62 checks in step S104 that each switch is switched to the "emergency state."
[0068] Next, in step S106, the CPU 62 checks whether or not the power supply is possible. Specifically, the CPU 62 determines whether or not each of the switches of the living / dining / kitchen switching unit 30, the bedroom switching unit 32, and the study switching unit is switched to the "emergency state" and the accessory outlet of the vehicle V is turned on.
[0069] If the respective changeover switches are in the "emergency state" in step S106 and the accessory outlet of the vehicle V is ON, the CPU 62 determines that the power supply is possible and proceeds to the process of step S108.
[0070] On the other hand, if some of the changeover switches are in the "normal state" in step S106 or the accessory outlet is OFF, the CPU 62 determines that the power supply is not possible and proceeds to processing in step S110. The CPU 62 displays a message on the display device 76 and the mobile terminal 89 in step S110. For example, if the changeover switch of the LDK switching unit 30 is in the "normal state," the CPU 62 uses the function of the display control unit 84 to display a message on the display device 76 and the mobile terminal 89 that prompts the user to check the LDK switching unit 30. Also, for example, if the accessory outlet of the vehicle V is OFF, the CPU 62 uses the function of the display control unit 84 to display a message on the display device 76 and the mobile terminal 89 that prompts the user to turn on the accessory outlet.
[0071] When the CPU 62 proceeds to the process of step S108 from step S106, it displays the power supply target area on the display device 76 and the mobile terminal 89. In the initial state, the changeover switch is set to a position such that power is supplied to the LDK 14A, and therefore the display on the mobile terminal 89 is as shown in FIG.
[0072] Next, the CPU 62 determines whether or not there has been an instruction to switch the power supply target area in step S112. Specifically, when the CPU 62 receives an instruction to switch the power supply target area from the user via the input device 78 or the mobile terminal 89 by the function of the instruction receiving unit 82, it determines that there has been an instruction to switch, and proceeds to processing in step S114. On the other hand, when the CPU 62 has not received an instruction to switch from the user, it returns to step S108.
[0073] In step S114, the CPU 62 switches the power supply target area and changes the display on the display device 76 and the mobile terminal 89. Specifically, the CPU 62 switches the change-over switch of the power supply target switching unit 24 according to the user's instruction received in step S112, using the function of the power supply target area switching unit 83. In addition, the CPU 62 displays the switched power supply target area on the display device 76 and the mobile terminal 89 in step S114. Then, the power supply target switching process ends.
[0074] As described above, in this embodiment, the living / dining / kitchen area switching unit 30 and the bedroom switching unit 32 are configured to be able to switch between the emergency power supply path and the normal power supply path. This allows power to be supplied to the building 12 from an external power source such as a vehicle V via the emergency power supply path even in the event of a power outage and the building being unable to be supplied with power from the normal power supply path.
[0075] In addition, in this embodiment, the power supply target switching unit 24 is configured to be able to switch the power supply destination to which power is supplied from the emergency power supply path. This allows a wide range of electrical appliances to be used by switching the power supply destination even when the amount of power that can be supplied from an external power source is limited. As a result, convenience can be ensured even in an emergency.
[0076] In particular, in this embodiment, the power supply target area is switched by a signal from the control unit 60, which eliminates the need for the user to manually switch the power supply target area.
[0077] Furthermore, in this embodiment, the vehicle V is configured to be able to supply power to the building 12 from an accessory outlet. This allows even a hybrid vehicle (HV) that does not have a charging port to supply power to the building 12.
[0078] Furthermore, in this embodiment, the rooms to which power can be supplied are displayed on the display device 76 and the mobile terminal 89, so that the user can grasp the available electric loads simply by looking at the display device 76 or the mobile terminal 89.
[0079] In addition, in this embodiment, the power supply target can be switched for each room in the building 12, so that, for example, a room such as the living / dining / kitchen area 14A can be the power supply target area during the day, and a room such as the bedroom 14B can be the power supply target area at night.
[0080] (Modification) Next, a modified example of the power supply structure according to the first embodiment will be described with reference to Fig. 6. In this modified example, the wiring for supplying power is partially different.
[0081] 6, in this modification, one end of a first power line 23A is connected to the external power supply connection portion 18, and the other end of the first power line 23A is connected to a vehicle connection device 85. The vehicle connection device 85 has built-in sensors and the like that detect the connection of a vehicle V.
[0082] One end of the second power line 23B is connected to the vehicle connection device 85, and the other end of the second power line 23B is connected to a power supply path switching unit 86. The power supply path switching unit 86 is connected to the distribution board 26 via the third power line 23C, and is configured to be able to switch between the emergency power supply path and the normal power supply path by a changeover switch.
[0083] One end of the fourth power line 23D is connected to a terminal on the emergency power supply path side of the power supply path switching unit 86, and the other end of the fourth power line 23D is connected to a power supply target switching unit 88. Here, the power supply target switching unit 88 has a changeover switch and is configured to be able to switch the power supply target area to which power is supplied from the emergency power supply path. As an example, the power supply target switching unit 88 of this modified example can switch between a path toward the living / dining / kitchen unit cable 34 and a path toward the bedroom unit cable 36.
[0084] On the other hand, one end of the fifth power line 23E is connected to a terminal on the normal power supply path side of the power supply path switching unit 86, and the other end of the fifth power line 23E is connected to the living / dining / kitchen unit cable 34 and the bedroom unit cable 36.
[0085] Since this modified example is configured as described above, in normal operation, the changeover switch of the power supply path switching unit 86 is set to the normal power supply path. In this state, the terminal on the third power line 23C side connecting the distribution board 26 and the terminal on the fifth power line 23E side are electrically connected to each other.
[0086] In addition, in the event of an emergency, the changeover switch of the power supply path switching unit 86 is automatically or manually switched to the emergency power supply path, whereby the terminal on the side of the second power line 23B connecting the vehicle connection device 85 and the fourth power line 23D extending to the power supply target switching unit 88 are electrically connected to each other (the state shown in FIG. 6).
[0087] Then, in a state in which the emergency power supply path is selected, the power supply target area can be switched by switching the power supply target switching unit 88. In this manner, in this modified example, the number of power supply target switching units 88 can be reduced compared to the above embodiment.
[0088] <Second embodiment> Next, a power supply system 90 including a power supply structure according to a second embodiment will be described with reference to the drawings. Note that the same components as those in the first embodiment are given the same reference numerals, and the description will be omitted as appropriate.
[0089] The overall configuration and hardware configuration of the power supply system 90 in this embodiment are the same as those of the first embodiment shown in Fig. 1 and Fig. 3. Here, in the power supply system 90 of this embodiment, a changeover switch (not shown) is provided in the LDK unit cable 34 and the bedroom unit cable 36 in Fig. 1. The changeover switch provided in the LDK unit cable 34 can switch the power supply target from among the individual electric loads (the television 40, the lighting fixture 42, the outlet 44, the refrigerator 46, and the IH heater 48) in the LDK 14A, which is different from the first embodiment. Similarly, the changeover switch provided in the bedroom unit cable 36 can switch the power supply target from among the individual electric loads (the lighting fixture 50 and the outlet 52) in the bedroom 14B.
[0090] (Functional configuration of power supply system 90) The power supply system 90 realizes various functions using the hardware resources shown in Fig. 3. The functional configuration realized by the power supply system 90 will be described with reference to Fig. 4.
[0091] 7, the power supply system 90 includes, as functional components, an external power supply connection confirmation unit 80, a path switching unit 81, an instruction receiving unit 82, a power supply target acquisition unit 91, a power supply target device switching unit 92, and a display control unit 84. Each functional component is realized by the CPU 62 reading out and executing a program stored in the ROM 64 or the storage 68.
[0092] The power supply target acquisition unit 91 acquires the names of the electric loads stored in advance. For example, a user registers in advance a combination of an identification number of an indoor outlet and an electric load connected to the outlet, and the combination is stored in the storage 68 or the like. The power supply target acquisition unit 91 acquires data from the storage 68 or the like, and acquires information on the electric load connected to each outlet. Furthermore, based on the combination acquired by the power supply target acquisition unit 91, the display control unit 84 displays on the display device 76 and the mobile terminal 89.
[0093] 8, some of the devices registered as electric loads are displayed. Here, as electric devices in the living room kitchen 14A, an icon M4 corresponding to the refrigerator 46, an icon M5 corresponding to the television 40, an icon M6 corresponding to the lighting fixture 42, and an icon M7 corresponding to the induction heater 48 are displayed.
[0094] The power supply target device switching unit 92 in FIG. 7 switches the changeover switch in response to the user's instructions received by the instruction receiving unit 82, thereby causing the power supplied from the vehicle V to flow to the power supply target device specified by the user.
[0095] For example, in the display example of Fig. 8, the refrigerator 46 and the lighting fixture 42 are specified as the power supply destinations. In this case, the power supply target device switching unit 92 sets the change-over switch of the power supply target switching unit 24 to the LDK switching unit 30 side. The power supply target device switching unit 92 also switches the change-over switch provided on the LDK unit cable 34 so that power is supplied to the refrigerator 46 and the lighting fixture 42. In this way, in this embodiment, it is possible to supply power to the electric loads corresponding to the names selected by the user as the power supply destinations.
[0096] (action) Next, the operation of this embodiment will be described.
[0097] In the power supply system 90 of this embodiment, for example, if the name of an electrical appliance is stored for each electrical load, the user can simply select the name of the electrical appliance he or she wants to use to switch the power supply path so that power is supplied to the electrical appliance. Other operations are the same as those of the first embodiment.
[0098] Although the power supply systems 10 and 90 according to the first and second embodiments have been described above, it is needless to say that the present invention can be embodied in various forms without departing from the scope of the present invention. For example, in the above first embodiment, a configuration in which the power supply target area is switched according to a user's instruction has been described, but the present invention is not limited to this, and a configuration in which the power supply target area is switched by detecting the user's position may also be adopted.
[0099] For example, a human presence sensor using an infrared sensor or the like may be used to detect the position of a user, and the power supply target switching unit may be switched so that power can be supplied to the electrical load in the room where a person is detected based on a signal from the human presence sensor. Also, instead of an infrared sensor, a human presence sensor may be used that detects people by image recognition using a camera or the like. In such a configuration, wiring may be provided so that power is preferentially supplied from the external power source to the human presence sensor regardless of the position of the changeover switch.
[0100] In addition, the power supply target switching unit may be switched according to the time period or situation registered in advance by the user. For example, the power supply target switching unit may be automatically switched so that the power supply target area is the living room or a room with little light during the day, and the power supply target area is the bedroom or the like at night.
[0101] Furthermore, a configuration may be adopted in which power is supplied preferentially to some of the electric loads. For example, in the case of a long-term power outage, power may be supplied to the refrigerator 46 regardless of the power supply area because food inside the refrigerator 46 may be spoiled.
[0102] Furthermore, in the second embodiment, the electric loads selectable by the user may be displayed on the mobile terminal 89. For example, when power supply up to 1500 W is possible, and the total power required for the electric loads already selected by the user is close to 1500 W, only the electric loads that can be used within a range not exceeding 1500 W may be displayed.
[0103] In addition, the processing executed by the CPU 62 by reading the software (program) in the above embodiment may be executed by various processors other than the CPU. In this case, examples of the processor include a PLD (Programmable Logic Device) such as an FPGA (Field-Programmable Gate Array) whose circuit configuration can be changed after manufacture, and a dedicated electric circuit such as an ASIC (Application Specific Integrated Circuit) which is a processor having a circuit configuration designed exclusively for executing a specific processing. The above processing may be executed by one of these various processors, or may be executed by a combination of two or more processors of the same or different types (for example, a plurality of FPGAs, and a combination of a CPU and an FPGA). The hardware structure of these various processors is, more specifically, an electric circuit that combines circuit elements such as semiconductor elements.
[0104] Furthermore, in the above embodiment, the storage 68 is the recording unit, but is not limited to this. For example, a non-transitory recording medium such as a CD (Compact Disk), a DVD (Digital Versatile Disk), or a USB (Universal Serial Bus) memory may be used as the recording unit. In this case, various programs may be stored in these recording media. [Explanation of symbols]
[0105] 10. Power Supply System 12. Building 18 External power supply connection 24 Power supply target switching unit 30 LDK switching unit (power supply path switching unit) 32 Bedroom switching unit (power supply path switching unit) 34 LDK unit cable (indoor wiring) 36 Bedroom unit cable (indoor wiring) 40 Television (electrical load) 42 Lighting equipment (electrical load) 44 Outlets (Electrical Load) 46 Refrigerator (electrical load) 48 IH heater (electrical load) 50 Lighting equipment (electrical load) 52 Outlets (electrical load) 60 Control section 76 Display device (power supply destination display section) 89 Portable terminal (power supply destination display section) 90 Power Supply System 91 Power Supply Target Acquisition Section V Vehicle
Claims
1. an external power supply connection unit provided in the building and to which a vehicle, which is an external power supply other than a commercial power supply, is connected; a power supply path switching unit that is configured to connect an emergency power supply path from the external power supply connection unit and a normal power supply path from a commercial power supply and to be able to switch between the emergency power supply path and the normal power supply path; a plurality of indoor wirings respectively connecting the power supply path switching unit and a plurality of electrical loads in a building; A power supply target switching unit that switches the indoor wiring to which power is supplied from the emergency power supply path; having The power supply structure, wherein the external power supply connection portion is configured to be electrically connectable to an accessory outlet provided within a passenger compartment of the vehicle.
2. A power supply destination display unit that displays a room or the electrical load to which power can be supplied by the power supply target switching unit, The power supply structure according to claim 1 , wherein the power supply destination display section includes a display area for a mobile terminal.
3. A power supply structure as described in claim 1 or 2, wherein the power supply target switching unit switches the power supply target for each separated room within a building.
4. A power supply structure according to any one of claims 1 to 3, A control unit that electrically controls the switching by the power supply target switching unit; Equipped with The control unit switches the power supply target switching unit so that power can be supplied to the electrical load in the room specified by a user.
5. The control unit includes a power supply target acquisition unit that acquires names of each of the electrical loads stored in advance, The power supply system according to claim 4 , wherein the power supply target switching unit is switched so as to enable power supply to the electric load corresponding to a name selected by a user as the power supply target.
6. A human presence sensor for detecting people in a building, The power supply system according to claim 4 , wherein the control unit switches the power supply target switching unit so as to enable power supply to the electric load in a room in which a person is detected based on a signal from the human presence sensor.
Citation Information
Patent Citations
Power supply system for building
JP2009278776A
Energy saving support system and energy saving support method
JP2012098963A
Power supply system
JP2016073186A