Microgrid operation system

The microgrid operation system stabilizes microgrid operation during natural disasters by coordinating power storage equipment through AC lines, addressing the reliance on communication networks and ensuring frequency stability and power demand satisfaction.

JP7579541B2Active Publication Date: 2024-11-08CHUDENKO CORP +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2020193616
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2020-11-20
Publication Date
2024-11-08
Estimated Expiration
2040-11-20

AI Technical Summary

Technical Problem

Existing microgrid systems face challenges in stabilizing operation during natural disasters without relying on communication networks, as they often require communication networks for load control and frequency management, which can be unreliable during such events.

Method used

A microgrid operation system that utilizes electricity storage equipment of consumers to manage charging and discharging of power storage facilities via AC lines, allowing stable operation without communication networks by coordinating frequency and power distribution among individual units.

Benefits of technology

Enables stable operation of microgrids disconnected from commercial power systems by effectively utilizing power storage equipment, ensuring frequency stability and power demand satisfaction within the microgrid.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007579541000002
    Figure 0007579541000002
  • Figure 0007579541000003
    Figure 0007579541000003
  • Figure 0007579541000004
    Figure 0007579541000004
Patent Text Reader

Abstract

To allow a micro-grid to be stably operated by effectively using power storage facilities of users of the micro-grid disconnected from a commercial power system without using a communication network.SOLUTION: Deviation from a planned value is calculated by subtracting the preset planned value of output power of an individual unit from a power value currently output by the individual unit. A charging / discharging target value of power is calculated by multiplying a value obtained by subtracting a target frequency determined according to a power storage state of a power storage facility from a current frequency of the individual unit by equivalent capacity. The power storage facility of each individual unit is charged / discharged so that the sum value of the deviation and the charging / discharging target value is 0.SELECTED DRAWING: Figure 5
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an operation system for a microgrid, which is a small-scale energy network in which multiple consumers are connected by AC lines, and in particular to a technical field of operating a microgrid by utilizing energy storage facilities of consumers. [Background technology]

[0002] In general, large-scale commercial power systems operated by power companies and the like are operated so that the total power consumption by the load matches the amount of power generated by the generator. For example, if the total power consumption by multiple consumers becomes greater than the amount of power generated, causing a discrepancy between the total power consumption and the amount of power generated, the flywheel effect in the power system causes a slow change in frequency, and the output of the power plant is controlled in a direction that suppresses the frequency change.

[0003] Meanwhile, in recent years, there has been an increasing demand for a stable supply of power even in the event of a sudden power loss due to, for example, a natural disaster. Microgrids, which can be operated separately from large-scale commercial power grids, have been attracting attention as a system that can meet this demand.

[0004] Microgrids are also known as small-scale systems, and examples of operation systems thereof include the systems disclosed in Patent Documents 1 and 2. In the system of Patent Document 1, when an abnormality occurs in the power system, the microgrid is separated from the power system, the engine generator is operated autonomously so as to achieve a target voltage, and the system transitions to a voltage control mode in which the frequency and voltage are fixed. A communication network is used when switching to the voltage control mode.

[0005] In the system of Patent Document 2, the loads (devices and facilities that consume power) in the microgrid are connected to the microgrid via a load connection / disconnection means, which utilizes a communication network such as a wireless LAN. [Prior art documents] [Patent documents]

[0006] [Patent Document 1] JP 2018-207574 A [Patent Document 2] JP 2020-28198 A Summary of the Invention [Problem to be solved by the invention]

[0007] Up until now, battery operation technology has been researched for system operation and system stabilization, but in recent years, the number of consumers with battery storage facilities has been increasing, and there is a demand for technology to effectively utilize the consumers' battery storage facilities. In particular, in the event of a natural disaster, technology to separate the above-mentioned microgrid from the commercial power system and operate it independently is important. For this reason, there has been a demand to effectively utilize the battery storage facilities of the consumers that make up the microgrid to realize stable operation of the microgrid.

[0008] In this regard, in Patent Document 1, a communication network is used to control an engine generator, and in Patent Document 2, a communication network is used to control a load connection / disconnection means in a microgrid.

[0009] However, building a communication network can be difficult, and it is possible that abnormalities may occur in the communication network itself during a natural disaster. Therefore, a system that can operate a microgrid stably without using a communication network is desired.

[0010] The present invention has been made in consideration of the above-mentioned points, and its object is to enable stable operation of a microgrid by effectively utilizing the power storage equipment of microgrid consumers that is isolated from the commercial power system without using a communication network. [Means for solving the problem]

[0011] This disclosure is directed to a technology for constructing a small-scale system (microgrid) by utilizing the energy storage facilities of consumers and operating the constructed microgrid. The microgrid can be a single-phase AC or three-phase AC system having multiple energy storage type distributed power sources and load facilities.

[0012] The means for achieving the above object is premised on an operation system of a microgrid in which a plurality of consumers are connected to each other via AC lines. The AC lines include three-phase or single-phase AC low-voltage or high-voltage distribution lines, main system transmission lines, and other private lines. This microgrid is connected to the commercial power system via a switch that switches between a connected state connected to the commercial power system and a disconnected state disconnected from the commercial power system. An individual unit is provided for each consumer, the individual unit having a load equipment that consumes the power supplied via the AC lines, a power storage equipment that stores the power supplied via the AC lines, and a control unit that controls charging and discharging of the power storage equipment. The individual units include a mixture of an individual unit having the load equipment but not the power storage equipment, and an individual unit having the load equipment, the power storage equipment, and the control unit.

[0013] The control unit is configured to, when the switch is disconnected and the microgrid is isolated from the commercial power system, calculate a deviation from the planned value by subtracting a preset planned value of the output power of the individual unit from the power value currently output by the individual unit in the microgrid, calculate a target charge / discharge value of power by multiplying a value obtained by subtracting a target frequency determined according to the storage state of the power storage equipment from the current frequency of the individual unit by an equivalent capacity, and control the charge / discharge of the power storage equipment so that the sum of the deviation and the target charge / discharge value becomes zero.

[0014] For example, the greater the amount of stored energy in the energy storage equipment of an individual unit, the higher the target frequency can be set, whereas the smaller the amount of stored energy, the lower the target frequency can be set. When the microgrid is disconnected from the commercial power system, an individual unit having an energy storage equipment with a large amount of stored energy can output the power of the energy storage equipment to other individual units. At this time, the deviation from the planned value can be calculated by finding the difference between the power value currently output by the individual unit and the planned value of the output power of the individual unit.

[0015] In addition, since the current frequency of an individual unit is the same as the frequency within the microgrid including other individual units connected via AC lines, the frequency will decrease if the power consumption of the entire microgrid exceeds the power supply. The charge / discharge target value of the energy storage facility can be calculated by multiplying the value obtained by subtracting the target frequency determined according to the storage state of the energy storage facility from the current frequency of this individual unit by the equivalent capacity.

[0016] Then, by controlling charging and discharging so that the sum of the deviation and the charge / discharge target value becomes 0, for example, when the current frequency is low and the amount of stored power in an individual unit is sufficiently large, the frequency in the microgrid can be increased by discharging from the power storage equipment of that individual unit and supplying it to other individual units in the microgrid. This amount of discharge changes according to the power storage state of the power storage equipment; the more the amount of stored power, the greater the amount of discharge, and conversely, the less the amount of stored power, the less the amount of discharge.

[0017] In other words, the power demand within the microgrid can be met by managing the discharge amount of the energy storage equipment for each individual unit while managing the frequency of the entire microgrid in a coordinated manner. This charge and discharge control can be implemented as long as the equipment is connected by AC lines, so no communication network is required.

[0018] Furthermore, the equivalent capacity may be different for each individual unit. For example, the larger the storage capacity of the storage facility, the larger the equivalent capacity can be.

[0019] In addition, it may be possible to set the discharge allowance of the power storage equipment that discharges during the independent microgrid operation control. For example, if the discharge allowance of the power storage equipment of the individual unit is not set, there is a risk that the power storage equipment will discharge until it runs out of stored power. If the power storage equipment of the individual unit runs out of stored power, the individual unit will not be able to use the load equipment. However, if the discharge allowance is set as in this configuration, it is possible to avoid the situation where the stored power runs out, and the load equipment can be used. Effect of the Invention

[0020] As described above, by controlling the charging and discharging of the energy storage equipment of each individual unit connected by an AC line, a microgrid that is separated from the commercial power system can be operated stably without using a communication network. [Brief description of the drawings]

[0021] [Figure 1] 1 is a schematic diagram showing a configuration of a microgrid according to an embodiment of the present invention. [Diagram 2] FIG. 2 is a schematic diagram showing a configuration of an individual unit. [Diagram 3] FIG. 13 is a diagram showing a specific example of a SOC shared function. [Figure 4] FIG. 13 is a diagram for explaining output conditions of individual units. [Diagram 5] FIG. 2 is a diagram illustrating an example of the configuration of a control circuit. [Figure 6] FIG. 1 is a schematic diagram illustrating a method for managing a power storage facility by a management generator in an independent microgrid. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0022] Hereinafter, the preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. Note that the following description of the preferred embodiments is merely illustrative in nature and is not intended to limit the present invention, its applications, or its uses.

[0023] FIG. 1 is a schematic diagram showing the configuration of a microgrid 1 according to an embodiment of the present invention. The microgrid 1 is connected to a commercial power system 3 by an AC line 2. The commercial power system 3 is a large-scale power system operated by, for example, a power company, and is capable of supplying power from multiple power plants. The microgrid 1 is connected to the commercial power system 3 via a grid interconnection switch 4. When the grid interconnection switch 4 is closed, the microgrid 1 is in a connected state in which it is connected to the commercial power system 3, whereas when the grid interconnection switch 4 is opened, the microgrid 1 is in a disconnected state in which it is disconnected from the commercial power system 3.

[0024] The microgrid 1 is a small-scale energy network in which multiple consumers 5, 5, ... are connected by AC lines 2. The microgrid 1 can be a single-phase AC or three-phase AC system having multiple energy storage type distributed power sources and load equipment, but is not limited to this, and may be a small-scale power supply system that has been known in the past. The energy storage type distributed power source is a power generation facility that can store energy, and examples of such facilities include a storage facility made of a storage battery or a fuel storage type generator. The microgrid 1 that is the subject of this embodiment may be a partial system that is separated when a part of the AC line 2 is separated in an emergency such as when the commercial power system 3 side is blacked out, or may be a consumer-side network that is normally connected to the commercial power system 3, or may be a small-scale network that is constructed for various purposes. The microgrid 1 that is the subject of this embodiment may be a network that can be operated separately from the large-scale commercial power system 3 as a system that can stably supply power even when a sudden power loss occurs due to a natural disaster or the like. The microgrid 1 may be a network that is provided at the end of the commercial power system 3. The microgrid 1 may be a large-scale power system itself, which is a commercial power system that is interconnected and can be operated independently.

[0025] The microgrid 1 may include a management generator 6. The management generator 6 is not essential to the present invention and may be omitted. When the management generator 6 is included, the management generator 6 is connected to the AC line 2 via a switch 7. By closing the switch 7, the management generator 6 can be brought into a connected state in which it is connected to the AC line 2, whereas by opening the switch 7, the management generator 6 can be brought into a non-connected state in which it is disconnected from the AC line 2. Although not shown, the microgrid 1 may also include various types of distributed power sources, which can also be connected to the AC line 2 via a switch in this case, similar to the management generator 6.

[0026] The consumers 5 constituting the microgrid 1 are dispersed. An individual unit Y (shown in FIG. 2 ) is provided for each consumer 5. One individual unit Y is present in one home, one factory, one office, or the like. In other words, there are as many individual units Y as there are consumers 5 constituting the microgrid 1.

[0027] The individual units Y include units that have a load equipment 10 that consumes power supplied via the AC line 2, a power storage equipment 11 that stores the power supplied via the AC line 2, a control unit 12 that controls the charging and discharging of the power storage equipment 11, and an inverter 13, as well as units that have the load equipment 10 but do not have the power storage equipment 11 or the control unit 12, and both types of units are mixed within the microgrid 1.

[0028] The storage facility 11 and the inverter 13 may be, for example, a combination of a dam that stores hydraulic energy and a generator of a pumped storage power station. storageThe load equipment 10 may be a combination of a normal generator and a motor having an energy facility. The load equipment 10 is a home appliance or an electric device that consumes power, and is connected to an AC line 14 in the individual unit Y via indoor wiring. A typical example of the power storage equipment 11 is a storage battery. The power storage capacity is not particularly limited, and may be, for example, a relatively small capacity one that is popular in general households, or a relatively large capacity one that is installed in various factories. In addition, in the case of a consumer 5 that owns an electric vehicle, the electric vehicle may be the load equipment 10 in some cases, and the storage battery of the electric vehicle may be the power storage equipment 11 in other cases. The individual unit Y may have, for example, a solar power generation device (not shown).

[0029] The individual unit Y also has an inverter 13. The inverter 13 is interposed between the power storage equipment 11 and the AC line 14 in the individual unit Y. The inverter 13 can convert the AC current supplied from the AC line 14 in the individual unit Y into a DC current of a predetermined voltage and supply it to the power storage equipment 11, and can also convert the DC current discharged from the power storage equipment 11 into an AC current of a predetermined voltage and supply it to the AC line 14 in the individual unit Y.

[0030] The individual unit Y has a first switch S1 and a second switch S2. The first switch S1 is interposed between the AC line 14 in the individual unit Y and the AC line 2 of the microgrid 1, and is provided in a portion closer to the AC line 2 of the microgrid 1 than the load equipment 10. By closing the first switch S1, a connected state can be established in which the AC line 14 in the individual unit Y and the AC line 2 of the microgrid 1 are connected, whereas by opening the first switch S1, a non-connected state can be established in which the AC line 14 in the individual unit Y and the AC line 2 of the microgrid 1 are disconnected.

[0031] The second switch S2 is provided between the inverter 13 and the load equipment 10. By closing the second switch S2, the inverter 13 and the AC line 14 in the individual unit Y can be brought into a connected state in which they are connected, whereas by opening the second switch S2, the inverter 13 and the AC line 14 in the individual unit Y can be brought into a non-connected state in which they are separated.

[0032] A consumer 5 having a power storage facility 11 can also be called a power generation consumer. This is because the power storage facility 11 can supply power to the outside. The power generation consumer 5 has at least the power storage facility 11 and usually also has a load facility 10, but may also have a power generation facility that uses renewable energy. The power generation consumer 5 can be assumed to be a single household connected with single-phase AC as the smallest unit, but may also be a consumer with only the power storage facility 11 and no load, or a factory that receives three-phase AC. A consumer 5 that does not have the power storage facility 11 may be included in the microgrid 1. A consumer 5 that does not have the power storage facility 11 becomes a consumer that only consumes power.

[0033] Up until now, storage battery operation technology has been studied for system operation and system stabilization, but as the number of power generation consumers 5 as described above is also increasing, there has been a demand for technology to effectively utilize the power storage equipment 11 owned by the power generation consumers 5. In particular, assuming a natural disaster or the like, there has been a demand for the microgrid 1 to be separated from the commercial power system 3 and operated independently. This embodiment enables the effective use of the power storage equipment 11 owned by the power generation consumers 5 constituting the microgrid 1. The microgrid 1 separated from the commercial power system 3 can be called an independent microgrid. Note that the microgrid 1 that is not separated from the commercial power system 3 is supplied with power in the same way as power is supplied by a general power supply network.

[0034] The operation system 100 of the microgrid 1 of this embodiment is a system capable of maintaining the reliability of the independent microgrid 1 by utilizing the power storage equipment 11 owned by the power generation consumer 5. That is, the operation system 100 is a system that synchronously connects an unspecified number of inverter units each equipped with the power storage equipment 11 without using a communication network, and can maximize the power supply capacity and supply reliability of the microgrid 1 while automatically coordinating with each other.

[0035] The individual unit Y of the power generation consumer 5 is preferably provided with a stable synchronous operation function (stable steady-state operation, second-level stabilization technology) capable of constructing the microgrid 1. Examples of inverters capable of realizing such functions include a three-phase GFM inverter (Grid-Forming inverter) and a single-phase synchronous power inverter modified for single-phase use. The three-phase GFM inverter and the single-phase synchronous power inverter are inverters in which the characteristics of a synchronous generator used as a large-scale power source are implemented, and have the ability to maintain stability by themselves. For this reason, the single-phase microgrid 1 can be stably operated with any number of units. Another advantage is that it can be freely connected to a large power source. Single-phase synchronous power inverters are well known in the art, so a detailed description will be omitted, but for example, one disclosed in JP 2017-127141 A and the like can be used.

[0036] The present embodiment can be applied to a general generator or a conventional inverter other than the single-phase synchronous inverter. Also, the present embodiment can be applied to various conventional rotary generators having a stable synchronous operation function.

[0037] (Inverter control for each individual unit) The control unit 12 of the individual unit Y performs the following control. That is, the control unit 12 calculates a deviation from the planned value by subtracting a preset planned value of the output power of the individual unit Y from the power value currently output by the individual unit Y. Furthermore, the control unit 12 calculates a charge / discharge target value of the power by multiplying a value obtained by subtracting a target frequency determined according to the storage state of the power storage facility 11 from the current frequency of the individual unit Y by an equivalent capacity. Then, the control unit 12 performs independent microgrid operation control to discharge the power storage facility 11 so that the sum of the calculated deviation and the charge / discharge target value becomes zero.

[0038] The following is a specific description of the processing performed by the control unit 12. First, the calculation formula (1) that is the basis of the control will be described.

[0039] BCEi=ΔPi+Ki(fi-fRi) (W) … Equation (1)

[0040] In equation (1), BCEi is the battery control error of each individual unit Y(i) and is expressed in units of W (watts). In equation (1), ΔPi is the deviation, which can be calculated by the following equation (2). Also in equation (1), Ki is the gain. Also in equation (1), fi is the current frequency (Hz) of the individual unit Y(i). Also in equation (1), fRi is the target frequency (Hz) of the individual unit Y(i).

[0041] ΔPi=Pi-Pschi (W) … Equation (2)

[0042] In formula (2), Pi is the power value (current output value) currently output by the individual unit Y(i), and its unit is W. Also, in formula (2), Pschi is the planned value (planned output value) of the output power of the individual unit Y(i), and its unit is W. Each power value and frequency can be acquired by a conventionally known method, and for example, can be acquired by measuring with a sensor or the like included in the control unit 12, or may be acquired by detecting with a sensor provided separately from the control unit 12 and inputting the detected value to the control unit 12.

[0043] Here, the measurement point of the current output value Pi of the individual unit Y(i) may be the connection portion (indicated by reference symbol P1 in FIG. 2) between the AC line 14 in the individual unit Y and the AC line 2 of the microgrid 1. This is because it is considered natural to consider the contribution to the microgrid 1 as the deviation amount from the planned output value (power sale or contracted power amount) of the individual unit Y. However, the measurement point of the current output value Pi is not limited to the above-mentioned portion, and may be a portion (indicated by reference symbol P2 in FIG. 2) where direct active power output of the power storage facility 11 can be obtained, or may be any point on the AC line 2 where measurement or estimated calculation is possible.

[0044] This embodiment is characterized in that a different target frequency fRi is set for each individual unit Y based on the power storage state of the power storage equipment 11 of each individual unit Y. As an equation showing this characteristic, equation (3) is shown.

[0045] fRi=funci(SOCi) (Hz) … Equation (3)

[0046] In formula (3), SOCi is the SOC of the individual unit Y(i). The SOC is a value indicating the internal state of the power storage equipment 11, i.e., the power storage state of the power storage equipment 11. Also, in formula (3), funci is the SOC sharing function of the individual unit Y.

[0047] Regarding the SOC sharing function, SOCi=1 means that the power storage equipment 11 is in a fully charged state, and SOCi=0 means that the power storage equipment 11 is in an empty state. However, each individual unit Y may limit the amount of power to be supplied to the microgrid 1 in an emergency based on prior consultation or the like. In this case, SOCi=0 can be a lower limit value when the power storage equipment 11 is not in an empty state and supplies some amount of stored power to the microgrid 1. This lower limit value is not particularly limited, but can be set to a value of 20% or less, 10% or less, for example, of the total amount of stored power in the power storage equipment 11. In other words, it is possible to set the discharge allowable amount of the power storage equipment 11 that is discharged during the independent microgrid operation control for each individual unit Y.

[0048] Also, SOCi=1 means that the power storage equipment 11 of the individual unit Y is in a fully charged state, but the storage capacity of the power storage equipment 11 of each individual unit Y may be different for each individual unit Y. That is, even if the value of SOCi is the same among a plurality of individual units Y, if the storage capacities of the power storage equipment 11 are different, a difference occurs in the amount of power that can be supplied to the microgrid 1, but such a case is also permitted in this embodiment. In other words, the SOC sharing function is for sharing the storage capacity for provision in an emergency, which is determined in advance, fairly within the microgrid 1. For this reason, it is preferable that the SOC sharing function is the same for all individual units Y (func1=func2=··=funci=···=func), and an equivalent capacity (W) determined from the storage capacity (Wh) of the power storage equipment 11 of the individual unit Y is set as the value of Ki. However, the SOC sharing function may also be set for each individual unit Y according to individual circumstances.

[0049] The SOC sharing function is set to satisfy the following conditional expressions 1 and 2.

[0050] Conditional expression 1 SOC management upper and lower limits: 0 <SOCi<1

[0051] "0" indicates that the power storage equipment 11 of the individual unit Y is in an empty state, and "1" indicates that the power storage equipment 11 of the individual unit Y is in a fully charged state.

[0052] Conditional expression 2 fL3 <fRi(SOCi)<fH3

[0053] Here, fRi(0) = fL3, fRi(1) = fH3, and fRi is an increasing function of SOC.

[0054] The specific shape of the SOC sharing function can be determined based on discussion within the microgrid 1, but may also satisfy the following formula (4).

[0055] fRi(SOCi)=fL3+SOCi×(fH3-fL3) …Equation (4)

[0056] An example of the characteristics of equation (4) is shown in the graph of Figure 3. The horizontal axis of the graph in Figure 3 indicates the storage state of the power storage equipment 11, with the origin being SOC = 0 and the amount of stored power increasing toward the right. The vertical axis of the graph in Figure 3 indicates the operating frequency (Hz), with the frequency increasing toward the top. The range from fL3 to fH3 is the management frequency. Each individual unit Y changes its target frequency fRi within the management frequency range according to the SOC of its own power storage equipment 11.

[0057] As described above, each individual unit Y monitors the battery control error BCEi of equation (1) in real time, feeds it back to the control command value to the inverter 13, and performs individual and distributed inverter output control with the following equation (5) as a control target.

[0058] BCEi=0 … Equation (5)

[0059] (SOC coordinated control) In this operation system 100, by employing the above-mentioned control method, it becomes possible for the power storage facility 11 owned by a power generation consumer 5 to be shared among a plurality of consumers 5 in the microgrid 1. The sharing mechanism of the power storage facility 11 will be described below.

[0060] As described above, this operation system 100 uses negative feedback with the above formula (5) as a control target while monitoring the battery control error BCE in all individual units Y having the battery storage equipment 11. Here, assume a situation in which the control target of the above formula (5) is achieved in all individual units Y. Generally, the frequency in a system becomes the same in the microgrid 1 when the oscillation component is eliminated, so the following formula (6) holds.

[0061] f1=f2=…=fn=f … Equation (6)

[0062] Therefore, the following holds true from equations (1), (4), (5), and (6).

[0063] ΔPi = (Pi - PRi) = Ki (fRi - f) =Ki(fL3-f+SOCi×(fH3-fL3)) … Equation (7)

[0064] ΔPi on the left side of equation (7) is the incremental output of the individual unit Y(i) obtained by subtracting the planned output value from the current output value of the inverter. ΔPi is due to automatic control of the inverter, and corresponds to the incremental power caused by increasing the discharge amount above the planned value in the operation of the energy storage facility 11. Also, f is the equilibrium point of the frequency when the control target equation (5) is achieved in all individual units Y.

[0065] The equilibrium point f can be actively controlled separately as described later. However, if no active control is implemented and only the proposed control is implemented for all inverters, the value will be determined by the proposed control and the load characteristics. In other words, f at this time is determined depending on the SOC of the battery equipment 11 in the microgrid 1 according to equation (7).

[0066] ΔPi in formula (7) is a function of SOCi and frequency f. First, the value of SOCi where ΔPi = 0, which is the planned value and no additional charging or discharging, is calculated from formula (7) as follows:

[0067] SOCi * =(f-fL3) / (fH3-fL3) … Equation (8)

[0068] Equation (8) shows the equilibrium state of the individual units Y(i) in the operation system 100. As described above, the SOC * In this case, by substituting f in equation (8) into equation (7), we obtain the following equation.

[0069] ΔPi = Ki(SOCi - SOC * )×(fH3-fL3) … Equation (9)

[0070] In this operation system 100, in each individual unit Y, the above SOC * The charging state (ΔPi<0) or discharging state (ΔPi>0) is maintained with the boundary being expressed by the following condition formula.

[0071] 0 <SOCi<SOC * When: ΔPi<0 charging state SOC * <SOCi<1のとき:ΔPi> 0 Discharged state

[0072] This control then continues in all individual units Y until the following is satisfied:

[0073] SOCi = SOC * … Formula (10)

[0074] This means that the charging and discharging conditions are the same for all the individual units Y, and charging and discharging can be performed in a fair share within the microgrid 1. In other words, by observing a common f for each individual unit Y, the present operation system 100 can realize stable operation of the microgrid 1 while managing the SOC of all the individual units Y to the same value within the management frequency range. Furthermore, by utilizing this characteristic, the overall energy storage state within the microgrid 1 can also be estimated from the operation frequency f using equation (8). In other words, although there is an error due to the control residual, it can be estimated that the group of energy storage equipment 11 is in a completely discharged state when the management frequency is near the lower limit, and that the group of energy storage equipment 11 is in a fully charged state when the management frequency is near the upper limit.

[0075] Figure 4 shows the charge and discharge conditions based on equation (7). As described above, by selecting a common SOC sharing function within the microgrid 1, it is possible to construct a control form that contributes to frequency control with a common standard for all individual units Y. Each individual unit Y performs charge or discharge control based on the remaining SOC. This control maintains stable operation of the microgrid 1 until the remaining SOC in all individual units Y becomes zero.

[0076] (Example of control circuit configuration) Next, an example of the configuration of a control circuit (corresponding to the control unit 12 in FIG. 2) capable of realizing the above-mentioned control will be described. However, the present invention is not limited to this example configuration, and any circuit configuration capable of realizing the above-mentioned control will suffice.

[0077] A specific control circuit of the control unit 12 is shown in Fig. 5. The control unit 12 includes a calculation unit 20, a controller 21, and a designation circuit 22, but may also include other circuits. Of the calculation unit 20, the controller 21, and the designation circuit 22 that constitute the control unit 12, the calculation unit 20 is characterized in that it calculates BCEi in this operation system 100 and sets it as the control target, while various controllers 21 and designation circuits 22 are possible, so configurations other than those in this example may also be used.

[0078] The calculation unit 20 is a part that calculates BCEi based on equations (1) to (4) and conditional equations 1 and 2. The controller 21 is a part that generates ΔPs from BCEi to realize equation (5). The designation circuit 22 is a circuit that subtracts the output ΔPs of the controller 21 from the planned output value Psch and issues a command to the generator.

[0079] Here, the controller 21 may have any configuration as long as it can stably control BCEi to near zero. Fig. 5 shows the simplest example, in which PI control (proportional-integral control) is used as the configuration of the controller 21. As shown in Fig. 5, it is possible to realize this operation system 100 with BCEi as the core.

[0080] (Actual operation mode) A microgrid 1 as shown in FIG. 1 is required to operate stably under any circumstances. Generally speaking, in an operation connected to a large power source, the system can be stably maintained by an existing methodology without using a communication network. On the other hand, in order to operate a plurality of generators in a coordinated manner in an independent microgrid 1 separated from a commercial power system 3, a communication network is indispensable in the existing methods as shown in the above-mentioned Patent Documents 1 and 2. However, as described above, according to the present operation system 100, the independent microgrid 1 can be stably operated without using a communication network. However, the microgrid 1 has at least three operation modes, namely, a normal mode in which the microgrid 1 is operated in a state connected to the commercial power system 3, an independent microgrid coordinated operation mode in which the microgrid 1 is operated in a coordinated manner while separated from the commercial power system 3, and an islanded operation mode. It is desirable to operate the microgrid 1 stably even if the operation mode is suddenly switched. Below, each operation mode will be explained, and then switching of the operation mode will be explained.

[0081] (1) Normal mode In Fig. 1, the state in which the microgrid 1 is operated while connected to the commercial power system 3 is defined as normal mode. The normal mode is a conventional power system operation mode, and since the reliability of the power supply (supply reliability) is guaranteed on the large system side (the commercial power system 3 side), no special control is required within the microgrid 1. In other words, in normal mode, the operation of the power storage facility 11 does not significantly affect the reliability of the microgrid 1. (2) Independent microgrid cooperative operation mode (cooperative mode) A state in which the microgrid 1 is disconnected from the commercial power system 3 and operated independently is defined as an independent microgrid coordinated operation mode. In this independent microgrid coordinated operation mode, the supply reliability depends on the operation method of the battery storage equipment 11 of the independent microgrid 1, so the control method of the above-mentioned present operation system 100 is applied. (3) Standalone operation mode (standalone mode) A state in which a consumer 5 is disconnected from the microgrid 1 and supplies power only to its own load equipment 10 is defined as an islanded operation mode.

[0082] (Cooperative transition method of operation mode using operating frequencies) In normal mode, microgrid 1 can share information and perform control via communications, but in emergencies, such as when a large-scale natural disaster occurs, it is desirable to have highly reliable and smooth independent operation that does not rely on a communications network. Below, we explain the smooth switching method and operation method between normal mode and cooperative mode. Specifically, this is a method that utilizes the frequency control characteristics of the control method in cooperative mode to manage the entire microgrid 1 while monitoring and controlling the operating frequency without relying on a communications network. Note that since cooperation between individual units Y is not necessary for the standalone mode, it will not be mentioned here.

[0083] Table 1 provides an overview of how to switch operational modes.

[0084] [Table 1]

[0085] The first column of Table 1 describes the operating state, and the second and subsequent columns describe the concept of frequency operation in each operating mode and the rules and regulations regarding switching between operating modes. Below, we will explain the details of how to switch between operating modes based on Table 1.

[0086] In normal mode, since the microgrid 1 is connected to the commercial power grid 3, frequency management is performed by the commercial power grid 3, and therefore the microgrid 1 is operated in a narrow frequency band (for example, frequency deviation within 0.2 Hz) around the nominal frequency (50 Hz or 60 Hz). At this time, equation (11), which will be described later, is set as the BCE in each individual unit Y. As a result, frequency control is not performed in each individual unit Y, and frequency management in the microgrid 1 is left to the commercial power grid 3.

[0087] Switching from normal mode to cooperative mode utilizes frequency deviation. That is, since the microgrid 1 operating in normal mode does not implement frequency control, when the grid interconnection switch 4 between the microgrid 1 and the commercial power grid 3 is opened, the frequency in the microgrid 1 fluctuates and deviates from a preset upper or lower limit. Therefore, in each individual unit Y, the control unit 12 detects the frequency deviation and switches the BCE control from equation (11) to equation (1). This allows the transition from normal mode to cooperative mode to be completed in a short time.

[0088] In the cooperative mode, operation is performed in a wider allowable frequency band than in the normal mode. In the cooperative mode using equation (1) as the BCE, the SOC becomes a function of the operating frequency, and the margin to the operating limit of the microgrid 1 can be monitored from the frequency drop status. In addition, the SOC in the microgrid 1 can be managed separately by frequency control of the management generator 6. The details of this will be described later.

[0089] The switching from the cooperative mode to the normal mode is performed when a frequency deviation is detected in each individual unit Y during operation in the cooperative mode. That is, the control unit 12 continuously detects the frequency of each individual unit Y, determines whether the detected frequency deviates from the operating frequency, and switches from the cooperative mode to the normal mode in a short time when it is determined that the frequency of each individual unit Y deviates from the operating frequency. In order to cause this frequency deviation, the manager of the microgrid 1 uses the management generator 6 to perform frequency control in the microgrid 1. When the commercial power system 3 and the microgrid 1 are interconnected, the management generator 6 is made to consume a large amount of power in order to cause the frequency in the microgrid 1 to deviate below the lower limit of the operating frequency. When the management generator 6 consumes a large amount of power, the frequency in the microgrid 1 decreases and deviates from the lower limit of the operating frequency, which triggers the switching of the operation mode of the microgrid 1 from the cooperative mode to the normal mode. Thereafter, the frequency in the microgrid 1 is adjusted to the frequency of the commercial power system 3, phase control is performed, and the grid interconnection switch 4 is closed to complete synchronization. Incidentally, one of the consumers 5 can be assigned as the management generator 6.

[0090] In the cooperative mode, the storage equipment 11 of all the individual units Y performs cooperative control using frequency characteristics. Therefore, in order to increase the frequency in the microgrid 1 in the cooperative mode, the management generator 6 needs to supply power corresponding to the increase in frequency. In particular, if the frequency in the microgrid 1 is reduced, a large amount of power needs to be supplied, which may be difficult. However, in general, it is easy to further reduce the frequency even in such a situation by consuming power. Therefore, when connecting to the commercial power system 3, the manager uses the management generator 6 to temporarily reduce the frequency as described above. Then, each consumer 5 side switches its own operation mode from the cooperative mode to the normal mode when the frequency deviates from the lower limit in the cooperative mode.

[0091] When the storage facility 11 switches to the normal mode, the frequency control based on the formula (1) stops. That is, in the normal mode, the manager can easily adjust the frequency using the management generator 6. Therefore, the manager can control the frequency in the microgrid 1 to be the same as the frequency of the commercial power grid 3, and operate the grid interconnection switch 4 to complete synchronization. When switching the operation mode, it is necessary to keep the inverter output at the same value before and after the switching in order to maintain the balance between power supply and demand in the microgrid 1.

[0092] (Inverter control method in various operation modes) Next, specific inverter control methods recommended for each operation mode will be described. The controlled object may be not only an inverter but also a normal generator. The control method for the cooperative mode has been described above, so the control methods for the other operation modes will be described below.

[0093] First, the inverter control method in normal mode will be described. In normal mode, the commercial power grid 3 performs frequency management, but the management generator 6 may also perform frequency control. In such an operation, a control method that does not steadily respond to frequency fluctuations may be preferable. Therefore, control using the following formula (11) instead of formula (1) can be recommended.

[0094] BCEi=ΔPi (W) … Equation (11)

[0095] where BCEi is the battery control error of individual unit i (W). ΔPi=Pi-Pschi: Deviation from planned output value

[0096] This is equivalent to carrying out the following treatment in equation (1): For the second term in equation (1), Ki = 0 is set to prevent response to frequency fluctuations, and only the first term is considered to maintain the planned output.

[0097] As is clear from equation (11), even if the operation mode is changed, the control structure itself is not affected. In other words, when the operation mode is switched, it is possible to simply replace equation (1) with equation (11) and carry out control as is. Note that switching of the operation mode is as described above.

[0098] Next, an inverter control method in the isolated mode will be described. In the above description, it is assumed that the consumer 5 is connected to the microgrid 1 in all cases. That is, the first switch S1 and the second switch S2 in Fig. 1 are both closed. However, each individual unit Y can supply single-phase AC power only to its own load equipment 10 from its own power storage equipment 11, solar power generation equipment, etc. by opening the first switch S1 while keeping the second switch S2 closed and disconnecting from the microgrid 1.

[0099] This is the stand-alone mode, in which the single-phase synchronous power inverter supplies AC power at a constant frequency (50 Hz or 60 Hz) by itself. In this case, the single-phase synchronous power inverter can perform frequency control with the same characteristics as a synchronous generator by using the following equation instead of equation (1).

[0100] In this embodiment, a case where a single-phase synchronous power inverter is used is described, but the present invention is not limited to this, and any generator or inverter, such as a normal synchronous generator or a GFM inverter, can be controlled. The synchronous generator is a three-phase generator, and various generators, such as those used for private power generation and those used in power plants, can be targeted. Various inverters, such as three-phase and single-phase inverters, can also be targeted. In other words, the present invention can be applied to various things as long as they have the same characteristics as a conventional synchronous generator.

[0101] BCEi=Ki(fi-fR) (W) … Equation (12) Ki:Gain fi: current frequency of individual unit i (Hz) fR: Frequency target value (Hz)

[0102] Equation (12) is a control method equivalent to the conventional constant frequency control (FFC method), and is a method whose only purpose is to maintain the frequency target value. If equation (12) is applied to a single-phase synchronous power inverter, consistency in formulation can be maintained when transitioning from island mode to normal mode and independent microgrid cooperative operation mode, which is advantageous in designing control equipment. In island operation mode, there is no need to consider commonality of the storage equipment 11, so the frequency target value fR can be set as a constant.

[0103] (Frequency management control using management generators) The management generator 6 of the microgrid 1 may be any inverter or generator, but one capable of storing energy can be used. Examples of the management generator 6 include a conventional diesel generator capable of storing fuel, a conventional inverter (CVCF: constant voltage, constant frequency inverter) equipped with a power storage facility, and a small hydroelectric power plant with a regulating reservoir.

[0104] In the absence of such a management generator 6 in the microgrid 1, one of the individual units Y may be used as the management generator 6, which will be referred to below as the "management unit". Applications of the management generator 6 include:

[0105] (1) Grid connection of Microgrid 1 In the above explanation, the management generator 6 is not required at all except when switching from the cooperative mode to the normal mode, i.e., when connecting to the grid. However, the management generator 6 is absolutely necessary when connecting the microgrid 1 to the commercial power grid 3. In other words, it is necessary to use the management generator 6 to control the frequency, phase, and voltage value on the microgrid 1 side so that the synchronization conditions for closing the grid-connection switch are satisfied. (2) Constant frequency control This constant frequency control is a control in which all individual units Y except for the management generator 6 are operated in normal mode, and the management generator 6 maintains the frequency at a constant level. In this case, the microgrid 1 is disconnected from the commercial power grid 3, but the frequency is maintained at the same value as when it is connected to the grid. When a management unit is provided, the management unit operates in island mode. (3) Energy storage facility control through frequency management This control utilizes the characteristics of a control method for SOC management (a control method in a cooperative mode) to collectively manage the SOC of all the power storage devices 11 in the microgrid 1. This control is called a frequency management SOC control method. Details of the frequency management SOC control method will be described below.

[0106] For example, when the microgrid 1 does not have a management generator 6, the group of power storage equipment 11 distributed in the microgrid 1 cooperates with each other as described above to independently manage the SOC of the power storage equipment 11, thereby improving the reliability of the microgrid 1. In this case, the steady state SOC of the group of power storage equipment 11 is determined as a function of the frequency of the microgrid 1. Here, a method of managing the SOC of all power storage equipment 11 by actively using the management generator 6 in a microgrid 1 having such characteristics will be described.

[0107] The above formula (8) represents the relationship between the steady-state frequency value of the microgrid 1 and the SOC of each of the power storage facilities 11 when the power storage facilities 11 of all the individual units Y are operating in the cooperative mode.

[0108] Now, assuming that the frequency f in equation (8) can be controlled by the management generator 6, it becomes possible to collectively control the SOC of each power storage device 11 by controlling the frequency f. Transforming equation (8) gives the following equation.

[0109] f = fL3 + (fH3 - fL3) × SOC * … Formula (13)

[0110] Based on equation (13), all the storage devices 11 in the microgrid 1 can maintain the SOC of equation (13) by controlling the frequency f. * In summary, by setting the frequency control target of the management generator 6 as shown in the following equation, SOC management of all the power storage devices 11 in the microgrid 1 becomes possible.

[0111] fR = fL3 + (fH3 - fL3) × SOC * … Formula (14) fR: Target frequency setting value (Hz) SOC * : SOC management target value for storage equipment in microgrid

[0112] Fig. 6 is a schematic diagram explaining a method for managing the power storage equipment by the management generator 6 in the independent microgrid 1. As shown in this figure, the manager checks the remaining amount of the energy resources (fuel for power generation and storage batteries) that he / she manages, while adjusting the frequency to send and receive energy to and from all the power storage equipment 11 in the microgrid 1, and manages the remaining amount of the power storage equipment 11 distributed throughout. The control method for the management generator may be frequency control with the target value given by equation (14), and for example, a conventional FFC control method may be adopted.

[0113] Alternatively, a normal CVCF inverter may be used for control and the frequency value of equation (14) may be directly specified for operation, or a control unit may be used.

[0114] (Frequency management SOC control method using a management unit) When one of the individual units Y is used as a management unit, as an example of the FFC method, each unit can be operated in the following operation modes.

[0115] (1) Management unit: Operates in standalone mode, and specifies the value of equation (14) as fR in equation (12). (2) Other individual units: Operate in coordinated mode.

[0116] If the interconnected inverters are each operated at a specified frequency, the system becomes unstable. This is because even when the same frequency is specified, subtle errors occur in the specified frequency value. In other words, in this operation system 100, it is preferable to limit the number of management generators 6 or management units to one and adopt the FFC method.

[0117] In addition, when there are multiple generators for management, it is preferable to adopt an FFC method based on a method of controlling multiple generators collectively as if they were one generator, or an FFC method in which the control amount calculated as if they were one generator is shared among multiple generators.

[0118] (Effects of the embodiment) As described above, according to this embodiment, it is possible to satisfy the power demand within the microgrid 1 by managing the discharge amount of the power storage equipment 11 for each individual unit Y while performing coordinated management of the frequency of the entire microgrid 1 isolated from the commercial power system 3 without using a communication network.

[0119] The above-described embodiment is merely illustrative in all respects and should not be construed as limiting. Furthermore, all modifications and variations within the scope of the claims are within the scope of the present invention. [Industrial Applicability]

[0120] As described above, the microgrid operation system according to the present invention can be used in, for example, a small-scale system in which a plurality of consumers are connected by AC lines, or in any subsystem in a general power system that includes a group of generators and a group of loads that are accompanied by energy reserve or storage. [Explanation of symbols]

[0121] 1. Microgrid 2 AC line 3 Commercial power system 4. Grid-connection switch 5 Consumer 6. Generator for maintenance 10 Load equipment 11 Energy storage facilities 12 Control section Y Individual Unit

Claims

1. In a microgrid operation system in which a plurality of consumers are connected to each other via AC lines, the microgrid is connected to the commercial power grid via a switch that switches between a connection state in which the microgrid is connected to the commercial power grid and a disconnection state in which the microgrid is disconnected from the commercial power grid; Individual units are provided for each consumer, the individual units include a load equipment that consumes the power supplied through the AC line and does not have a power storage equipment that stores the power supplied through the AC line, and an individual unit that has the load equipment, the power storage equipment, and a control unit that controls charging and discharging of the power storage equipment, The control unit is configured to, when the switch is disconnected and the microgrid is isolated from the commercial power system, calculate a deviation from the planned value by subtracting a preset planned value of the output power of the individual unit from the power value currently output by the individual unit in the microgrid, calculate a target charge / discharge value of power by multiplying a value obtained by subtracting a target frequency determined in accordance with the storage state of the power storage equipment from the current frequency of the individual unit by an equivalent capacity, and perform independent microgrid operation control to charge and discharge the power storage equipment so that the sum of the deviation and the target charge / discharge value becomes zero.

2. The microgrid operation system according to claim 1, A microgrid operation system, characterized in that the target frequency is set higher as the amount of stored electricity in the electricity storage facility increases.

3. In the microgrid operation system according to claim 1 or 2, A microgrid operation system, characterized in that the equivalent capacity is set to a larger value as the storage capacity of the storage facility increases.

4. In the microgrid operation system according to any one of claims 1 to 3, A microgrid operation system capable of setting a discharge allowance of the power storage facility that discharges during operation control of the independent microgrid.

Citation Information

Patent Citations

  • Isolated operation method and system of low voltage system

    JP2008125290A

  • Composite power generation system

    JP2018107991A

  • Microgrid control system and method

    JP2018207574A

  • Microgrid control system

    JP2020028198A