Wind turbine inspection device, method, and program

The wind turbine inspection device optimizes inspection timing and method using work robots and sensors to improve facility utilization and reduce power output losses by addressing weather-induced shaking and operational interruptions.

JP7581174B2Active Publication Date: 2024-11-12KK TOSHIBA
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
JP2021185264
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-11-12
Publication Date
2024-11-12
Estimated Expiration
2041-11-12

AI Technical Summary

Technical Problem

Periodic inspections of wind turbines require stopping the operation, reducing equipment utilization rate and increasing lost power output, and are affected by weather conditions, risking robot malfunctions due to turbine shaking.

Method used

A wind turbine inspection device with a work robot and sensors to optimize inspection timing and method, using shaking data to determine standby conditions and adjust work posture, and incorporating forecast data for optimized planning.

Benefits of technology

Improves facility utilization rate and reduces lost power output by optimizing inspection timing and method, minimizing collisions and malfunctions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007581174000001
    Figure 0007581174000001
  • Figure 0007581174000002
    Figure 0007581174000002
  • Figure 0007581174000003
    Figure 0007581174000003
Patent Text Reader

Abstract

To provide a windmill inspection technology to reduce lost power generation output by optimizing an execution method and an execution timing of inspections by a working robot, and improving a facility use rate.SOLUTION: A windmill inspection device includes: a transmission part for transmitting work information 36 on a work tool 45 (45a and 45b) whose work position and work posture are designated; a reception part for receiving detection data 43 from a shake sensor 34 installed in a nacelle 30; a reading part for reading a shake amplitude from the detection data 43; and a determination part for determining whether or not execution of the work tool 45 according to the work information 36 is to be kept on standby on the basis of the shake amplitude.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] An embodiment of the present invention relates to a technique for inspecting a wind turbine used for wind power generation. [Background technology]

[0002] Wind power is a type of renewable energy that can be found anywhere, does not emit carbon dioxide, does not run out, and can be used perpetually. To promote power generation using wind power, it is important to establish technology to inspect the soundness of operation in order to improve the stability and sustainability of power generation. Furthermore, regular inspections are mandatory from the perspective of preventing accidents that could lead to unexpected interruptions to wind power generation.

[0003] In offshore wind power generation, the cost of dispatching workers to the turbines is high, and there is a desire to reduce the number of dispatches. Therefore, there are considerations of introducing work robots such as drones and articulated arms into the turbine nacelle, and completing inspections and other work by remote control as much as possible. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2017-112631 A Summary of the Invention [Problem to be solved by the invention]

[0005] Because periodic inspections require the operation of the wind turbine to be stopped for a certain period of time, the more frequent and longer the inspections are, the lower the equipment operating rate will be and the more lost power output will increase. Furthermore, the efficiency of wind power generation is greatly affected by meteorological conditions such as wind and waves, so the amount of lost power output will vary greatly depending on how and when the periodic inspections are carried out. In addition, when using a work robot to inspect the inside of the nacelle, there is a concern that the wind and waves may cause the offshore wind turbine to shake significantly, causing the work robot to collide with the equipment or inner walls inside the nacelle and causing breakdowns.

[0006] An embodiment of the present invention has been made taking these circumstances into consideration, and aims to provide a wind turbine inspection technique that optimizes the method and timing of inspection using a work robot, thereby improving equipment utilization rate and reducing lost power generation output. [Means for solving the problem]

[0007] In an embodiment, the wind turbine inspection device comprises: a work tool that works inside a nacelle that houses at least a rotor shaft that transmits rotational energy converted from wind flow energy and a generator that converts the rotational energy into electrical energy; a work robot that supports the work tool in the internal space of the nacelle and variably sets at least one of its work position and work posture; a transmitter that transmits work information specifying the work position and work posture to a drive unit of the work robot; a receiver that receives detection data from a sway sensor installed in the nacelle; a reader that reads the sway amplitude from the detection data; and a determination unit that determines whether to put the execution of the work tool in accordance with the work information on hold based on the sway amplitude. It is equipped with: Effect of the Invention

[0008] An embodiment of the present invention provides a wind turbine inspection technique that optimizes the method and timing of inspection using a work robot, improves facility utilization rate, and reduces lost power generation output. [Brief description of the drawings]

[0009] [Figure 1] 1A and 1B are overall views of a wind turbine to which an embodiment of the present invention is applied. [Diagram 2] FIG. 2 is a conceptual diagram of the inside of a nacelle in which a mechanical unit is installed in the wind turbine inspection device according to each embodiment. [Diagram 3] FIG. 2 is a block diagram of a control unit in the wind turbine inspection device according to the first embodiment. [Figure 4] FIG. 11 is a block diagram of a control unit in a wind turbine inspection device according to a second embodiment. [Diagram 5] 4 is a flowchart illustrating the steps of a wind turbine inspection method and an algorithm of a wind turbine inspection program according to the embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0010] (First embodiment) Hereinafter, an embodiment of the present invention will be described with reference to the accompanying drawings. Figures 1(A) and 1(B) are overall views of a wind turbine 20 to which an embodiment of the present invention is applied. As described above, the wind turbine 20 shown in Figures 1(A) and 1(B) is a floating type installed on the sea, but the wind turbine to which each embodiment is applied may be a bottom-mounted type installed on the sea or a land-mounted type. As described above, the wind turbine 20 includes blades 25, a tower 26, a nacelle 30, and a hub 51.

[0011] The blades 25 are arranged radially so as to be connected to a rotor shaft 27 (FIG. 2) at a hub 51. The pitch angle of these blades 25 is adjusted with respect to the inflowing wind direction so that the flow energy of the wind can be efficiently converted into rotational energy. A driving mechanism (not shown) such as a motor, brake, and emergency power supply for adjusting the pitch angle is provided inside the hub 51. The tower 26 is connected to a floating body 56, which is tethered via a mooring line 58 to a foundation 59 built on the seabed, so as to be exposed above the sea surface.

[0012] 2 is a conceptual diagram of the inside of a nacelle 30 in which a mechanism unit 40 is installed in a wind turbine inspection device (hereinafter simply referred to as "inspection device") according to each embodiment. In this way, the nacelle 30 is mounted on the top of a tower 26 via a yaw drive unit 23 that automatically makes the rotor shaft 27 follow the wind direction. Inside this tower 26, there is provided a lifting means 24 that transfers goods or workers that have been transported by sea and landed on a floating body 56 into the inside of the nacelle 30.

[0013] Various structures 33 are housed in the nacelle 30. Examples of such structures 33 include a main bearing 33a that supports the rotor shaft 27, a speed increaser 33b that is connected to the end of the rotor shaft 27 and increases the rotation speed, a generator 33c that converts rotational energy into electrical energy, a conversion circuit 33e that modulates and transforms the output of the generator 33c to produce an external power output 29 that matches the system frequency and system voltage, and a transmission circuit 33d that is connected to a plurality of sensors 34 installed in these structures 33 (33a, 33b...) and collects and transmits each detected data 43 to the outside.

[0014] Here, the main purpose of the sensor 34 is to individually detect the vibrations of each of the structures 33 (33a, 33b, ...) on which it is installed, but it is also possible to detect the vibration of the nacelle 30. Examples of the vibration sensor 34 that can detect such vibration include a gyro sensor, an acceleration sensor, a pressure sensor, and a distance sensor.

[0015] The mechanical section 40 of the inspection device is equipped with a work tool 45 (45a, 45b) that works inside the nacelle 30, and a work robot 46 (46a, 46b) that supports the work tool 45 in the internal space 47 of the nacelle 30 and variably sets at least one of its work position and work posture. The nacelle 30 is further provided with a drive section 49 that inputs work information 36 from the control section 10 and outputs a drive signal for the work robot 46.

[0016] Here, the work robot 46 may be a flying object 46a or an articulated arm 46b. In some cases, only one of these work robots 46 may be deployed, or both may be deployed. In other cases, the work robot 46 may be configured as a single robot, or as a plurality of robots that are controlled in cooperation with each other. In normal times, the flying object 46a is always stationed at a heliport provided inside the nacelle 30, and is supplied with power, etc.

[0017] The articulated arm 46b is configured to move on the rail 19 at its base end, and can work over a wide range inside the nacelle 30. The rail 19 can be configured to move not only on the rail but also in three dimensions by combining a lateral movement and a vertical telescopic mechanism. The lateral movement, traveling, and telescopic mechanism of the above configuration can grip the flying object 46a at the tip of the telescopic mechanism and move inside the nacelle 30, and the flying object 46a can be released from the top end of the tower 26 to inspect the inside of the tower 26 using only the flying object 46a. The articulated arm 46b may be provided on a mobile robot (not shown) instead of the rail 19.

[0018] Furthermore, the work robot 46 can work not only inside the nacelle 30, but also inside the tower 26 and the hub 51 with the work tool 45. In this case, work can be performed on the fastening of bolts at the joints of the tower 26 and on the structure 33 arranged inside. As the camera, which is the main work tool 45, an optical camera, an infrared camera, a multispectral camera, or a hyperspectral camera can be used, and a 360-degree camera can also be used.

[0019] Other examples of the work tool 45 include distance measuring devices using millimeter wave radar or lasers, and sensors that measure state quantities such as vibration, acceleration, and temperature. Further examples of the work tool 45 include a portable vibration sensor (not shown) equivalent to the vibration sensor 34, and a tool that performs contact work on the structure 33. Also, a plurality of different types of cameras and sensors may be supported as the work tool 45. Furthermore, the work tool 45 can be replaced or attached according to the detected defect phenomenon, or to a type that the inspector considers appropriate.

[0020] 3 is a block diagram showing an example of a control unit 10A (10) in the inspection device for a wind turbine according to the first embodiment. Thus, the control unit 10A of the inspection device includes a transmitter 21 that transmits work information 36 specifying the work position and work posture of the work tool 45 to a drive unit 49 of the work robot 45 (45a, 45b), a receiver 15 that receives detection data 43 from a vibration sensor 34 arranged in the nacelle 30, a reader 11 that reads vibration amplitude 44a from the detection data 43, and a determiner 12 that determines whether or not to put the execution of the work tool 45 in accordance with the work information 36 on hold based on the vibration amplitude 44a.

[0021] The transmission unit 21 transmits the work information 36 of the work tool 45 to the drive unit 49, thereby making it possible to make the work tool 45 approach a pre-specified structure 33. If the work tool 45 is a camera, it is possible to obtain image data 39 of the structure 33 from various positions and orientations, focusing only on the areas required for analysis. Also, if there are multiple structures 33 to be noted, the position and orientation of the work tool 45 (camera) can be changed to make it approach each of them.

[0022] Furthermore, the control unit 10 of the inspection device is provided with an operation unit 18 for manually setting the work position and work posture of the work tool 45 by arbitrarily operating the transmitted work information 36. In addition to the work information 36 being registered in advance, the work information 36 can also be registered and specified using the operation unit 18 from three-dimensional data constructed from laser scan data, 3D CAD data, etc. As a result, even if a satisfactory work cannot be performed using the pre-linked work information 36, the position and posture of the work tool 45 can be corrected and the work can be performed again.

[0023] In addition, three-dimensional data can be generated by reconstruction from videos (time series data) from a 360-degree camera (omnidirectional camera) or a monocular camera, stereo images, etc. By updating the three-dimensional data from image data 39 from a camera as a work tool 45, it can be used not only to update the work information 36 but also to inspect changes in shape (differences from the past).

[0024] When the work tool 45 (45a, 45b) is a camera, image data 39 captured by the camera is displayed on a display unit (not shown). The image data 39 may be a still image or a video. The received image data 39 may be displayed in real time, or may be recorded and played back at a later date.

[0025] The detection data 43 acquired by the receiving unit 15 is the output value of the vibration sensor 34 for the above-mentioned CMS (Condition Monitoring System) application or a sensor provided exclusively for detecting the vibration of the nacelle 30. This detection data 43 reflects the displacement of the nacelle 30 that vibrates up and down and left and right due to the swell of waves on the sea surface where the wind turbine 20 is located and the vibration of the wind.

[0026] The reader 11 extracts the waveform components resulting from the above-mentioned rocking of the nacelle 30 from the waveform signal of the detection data 43, and reads the rocking amplitude 44a. When the nacelle 30 is affected by wind and waves and rocks in the absolute coordinate system on the earth's surface, the structure 33 arranged inside it also rocks with the same phase and amplitude as the nacelle 30.

[0027] However, the working work tool 45 (46a, 46b) and work robot 46 (46a, 46b) tend to remain stationary in the absolute coordinate system due to their own inertia. As a result, in the relative coordinate system of the nacelle 30, the work tool 45 (46a, 46b) and work robot 46 (46a, 46b) swing relative to the structure 33. If the swing amplitude 44a is large, the work tool 45 or work robot 46 may collide with and break the structure 33 or cause damage to nearby structures 33.

[0028] The determination unit 12 checks the swing amplitude 44a against the pre-created standby conditions 35 to determine whether or not to put the work tool 45 in standby according to the work information 36. If the swing amplitude 44a is large and a "standby required" determination is made, an emergency stop command 22 is issued to urgently stop the work tool 45 in accordance with the transmitted work information 36. If the swing amplitude 44a is small and a "standby not required" determination is made, this emergency stop command 22 is not issued.

[0029] Second embodiment Next, a second embodiment of the present invention will be described with reference to Fig. 4. Fig. 4 is a block diagram showing an example of a control unit 10B(10) in a wind turbine inspection device according to the second embodiment. In Fig. 4, parts having the same configuration or function as Fig. 1 are indicated by the same reference numerals, and duplicated explanations will be omitted.

[0030] The inspection device 10B (10) of the second embodiment includes, in addition to the configuration of the inspection device 10A of the first embodiment described above, an acquisition unit 16 that acquires forecast information 31 including at least one of meteorological data, sea condition data, and wind condition data, an estimation unit 17 that estimates at least the sway amplitude 44b based on the forecast information 31, and a creation unit 19 that creates an inspection plan 37 describing the execution timing of the work tool 45 in accordance with the work information 36 based on the estimated power generation output 41 and sway amplitude 44b.

[0031] Forecast information 31, such as weather data, ocean condition data, and wind condition data, can be provided externally by the Japan Meteorological Agency, local governments, private businesses, etc., and can be acquired via the Internet, etc. Although a detailed explanation will be omitted, the power generation output 41 and oscillation amplitude 44b of the wind turbine 20 can be estimated based on such forecast information 31.

[0032] In a wind power plant, an operation plan 38 is formulated that defines the operation periods and regular inspection periods of the wind turbines 20 throughout the year. This operation plan 38 is formulated based on a long-term forecast that is statistically analyzed from past weather data, etc., so as to reduce lost power output. For this reason, it is meaningful to amend this operation plan 38 in accordance with forecast information 31 that is a short-term forecast based on actually observed weather data, etc., from the perspective of further promoting the reduction of lost power output.

[0033] The creation policy of the inspection plan 37 in the creation unit 19 is as follows. That is, when the power generation output 41 is expected based on the forecast information 31, the wind turbine 20 is operated. When the power generation output 41 is not expected based on the forecast information 31 and the oscillation amplitude 44b is small, an inspection is performed. The determination of whether the oscillation amplitude 44b is large or small is based on the standby conditions 35.

[0034] Based on the inspection plan 37 created in accordance with such creation guidelines, work information 36 for the work tool 45 is sent to the drive unit 49 of the nacelle 30 at the timing of automatic operation, causing the work tool 45 to operate. In this way, by creating the inspection plan 37 based on the forecast information 31, the operation plan 38 is corrected in the correction unit 14 as necessary.

[0035] The steps of the wind turbine inspection method according to the embodiment and the algorithm of the wind turbine inspection program will be described with reference to the flowchart in Figure 5 (see Figures 2 and 3 as appropriate). Work information 36 specifying the work position and work posture of the work tool 45 inside the nacelle 30 is transmitted from transmission unit 21 to drive unit 49 of the work tool 45 (S11).

[0036] Based on this work information 36, the work robot 46 is variably operated (S12), a work position and a work posture are set (S13), and the work tool 45 supported by the work robot 46 is made to perform work (S14).

[0037] On the other hand, detection data 43 of the sway sensor 34 installed in the nacelle 30 is received (S15 No, S16). Then, the sway amplitude 44a is read from this detection data 43 (S17). Then, if the sway amplitude 44a is large and satisfies the standby condition 35 (S18: Yes), an emergency stop command 22 is issued for the work tool 45 executing the work information 36 (S19, END). Then, if the sway amplitude 44a is small and does not satisfy the standby condition 35 (S18: No), the execution of the work information 36 by the work tool 45 is continued until it is completed (S12 to S15: Yes, END).

[0038] According to at least one of the embodiments of the wind turbine inspection device described above, by determining whether or not to wait for work based on the sway amplitude of the nacelle, it is possible to optimize the method and timing of inspection by the work robot, improve equipment utilization rate, and reduce lost power generation output.

[0039] Although some embodiments of the present invention have been described, these embodiments are presented as examples and are not intended to limit the scope of the invention. These embodiments can be implemented in various other forms, and various omissions, substitutions, modifications, and combinations can be made without departing from the spirit of the invention. These embodiments and their modifications are included in the scope of the invention and its equivalents described in the claims, as well as in the scope and spirit of the invention.

[0040] The wind turbine inspection device described above includes a control device that is a highly integrated processor such as a dedicated chip, an FPGA (Field Programmable Gate Array), a GPU (Graphics Processing Unit), or a CPU (Central Processing Unit), a storage device such as a ROM (Read Only Memory) or a RAM (Random Access Memory), an external storage device such as an HDD (Hard Disk Drive) or an SSD (Solid State Drive), a display device such as a display, an input device such as a mouse or keyboard, and a communication I / F, and can be realized with a hardware configuration using a normal computer. Therefore, the components of the wind turbine inspection device can also be realized by a computer processor and can be operated by a wind turbine inspection program.

[0041] The wind turbine inspection program is provided by being pre-installed in a ROM or the like. Alternatively, the program may be provided by being stored in a computer-readable storage medium such as a CD-ROM, CD-R, memory card, DVD, or flexible disk (FD) in the form of an installable or executable file.

[0042] The wind turbine inspection program according to this embodiment may be stored on a computer connected to a network such as the Internet and provided by downloading it via the network. The wind turbine inspection device may also be configured by combining separate modules that independently fulfill the functions of the components and are mutually connected via a network or dedicated lines. [Explanation of symbols]

[0043] 10 (10A, 10B)...Control unit of inspection device, 11...Reading unit, 12...Judgment unit, 14...Correction unit, 15...Receiving unit, 16...Acquisition unit, 17...Estimation unit, 18...Operation unit, 19...Creation unit, 20...Wind turbine, 21...Transmission unit, 22...Emergency stop command, 23...Yaw drive unit, 24...Lifting means, 25...Blade, 26...Tower, 27...Rotor shaft, 29...External output, 30...Nacelle, 33...Structure, 33a...Main bearing (structure), 33b...Speed ​​increaser (structure), 33c...Generator (structure), 33d...Transmission circuit (structure) , 33e... conversion circuit (structure), 34... sensor, 35... standby conditions, 36... work information, 37... inspection plan, 38... operation plan, 39... image data, 40... mechanical part of the inspection device, 43... detection data, 44a... read vibration amplitude, 44b... estimated vibration amplitude, 45 (45a, 45b)... work tool, 46... work robot, 46a... flying object (work robot), 46b... multi-joint arm (work robot), 47... internal space, 49... drive unit, 51... hub, 56... floating body, 58... mooring line, 59... foundation.

Claims

1. a rotor shaft that transmits rotational energy converted from wind flow energy, and a work tool that operates inside a nacelle that houses at least a generator that converts the rotational energy into electrical energy; a work robot that supports the work tool in an internal space of the nacelle and variably sets at least one of a work position and a work posture of the work tool; a transmitter that transmits work information that specifies the work position and the work posture to a drive unit of the working robot; A receiving unit that receives detection data from a vibration sensor installed in the nacelle; A reading unit that reads a vibration amplitude from the detection data; a determination unit that determines whether or not to put on hold the execution of the work tool in accordance with the work information based on the oscillation amplitude.

2. The wind turbine inspection device according to claim 1, An acquisition unit that acquires forecast information including at least one of meteorological data, sea condition data, and wind condition data; an estimation unit that estimates at least the vibration amplitude based on the forecast information; a creation unit that creates an inspection plan describing the execution timing of the work tool in accordance with the work information, based on the estimated power generation output and the sway amplitude.

3. The wind turbine inspection device according to claim 1 or 2, The work robot is a wind turbine inspection device that is at least one of a flying object and a multi-joint arm, which is composed of a single or multiple robots.

4. The wind turbine inspection device according to any one of claims 1 to 3, The work tool is at least one of a camera, a sensor, and a tool.

5. A step in which a work tool operates inside a nacelle that accommodates at least a rotor shaft that transmits rotational energy converted from wind flow energy and a generator that converts the rotational energy into electrical energy; supporting the work tool in an internal space of the nacelle and variably setting at least one of a work position and a work posture of the work tool by a work robot; transmitting work information specifying the work position and the work posture to a drive unit of the working robot; receiving detection data from a vibration sensor installed in the nacelle; Reading a vibration amplitude from the detection data; determining whether or not to put on hold the execution of the work tool in accordance with the work information, based on the oscillation amplitude.

6. On the computer, A step in which a work tool operates inside a nacelle that houses at least a rotor shaft that transmits rotational energy converted from wind flow energy and a generator that converts the rotational energy into electrical energy; supporting the work tool in an internal space of the nacelle and variably setting at least one of a work position and a work posture of the work tool by a work robot; transmitting work information specifying the work position and the work posture to a drive unit of the working robot; receiving detection data from a vibration sensor installed in the nacelle; reading a vibration amplitude from the detection data; a step of determining, based on the oscillation amplitude, whether or not to put on hold the execution of the work tool in accordance with the work information.

Citation Information

Patent Citations

  • Method for operating a wind installation and wind installation for carrying out the method

    JP2003532835A

  • Sensor mechanism for wind mill and vibration reducing method for wind mill

    JP2007231911A

  • Wind mill sensor mechanism and vibration reducing method for wind mill

    JP2011256881A

  • State monitoring system of wind power generation device

    JP2013087732A

  • Wind turbine assembly and management robot and wind turbine system including the same

    JP2014506968A