Steel pipe pile with wings and its construction method

The construction method for feathered steel pipe piles addresses the uncertainty of intermediate layer thickness by measuring penetration resistance, ensuring adequate support and efficient construction.

JP7584342B2Active Publication Date: 2024-11-15ASAHI KASEI CONSTRUCTION MATERIALS CO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
JP2021050242
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-03-24
Publication Date
2024-11-15
Estimated Expiration
2041-03-24

AI Technical Summary

Technical Problem

The challenge in constructing steel pipe piles with wings is determining the thickness of the intermediate layer in the ground, which is crucial for ensuring adequate support, as it is often unknown and varies, leading to potential underestimation or overestimation of supporting capacity, necessitating costly and time-consuming surveys.

Method used

A construction method for feathered steel pipe piles that involves attaching vanes a predetermined length above the tip, measuring changes like rotational torque during penetration, and confirming the support layer thickness by monitoring resistance increases, ensuring the vanes are rooted in the support layer.

Benefits of technology

Enables confirmation of the support layer thickness without prior surveys, allowing for efficient construction by verifying the necessary thickness and ensuring adequate support, reducing costs and time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007584342000001
    Figure 0007584342000001
  • Figure 0007584342000002
    Figure 0007584342000002
  • Figure 0007584342000003
    Figure 0007584342000003
Patent Text Reader

Abstract

To confirm whether or not an intermediate layer has a thickness required at all points where steel pipe piles are constructed by a simple method.SOLUTION: When a steel pipe pile 10 with a blade mounted with a spiral blade 13 is buried in a ground G by rotational force, the steel pipe pile 10 with the blade is adopted in which the blade 13 is mounted at a position above by a predetermined length L along a central axis 11C from a tip 12 of the steel pipe pile 10 with the blade. When the steel pipe pile 10 with the blade is penetrated into a support layer GS in the ground G, it is confirmed that the support layer GS has at least a thickness L or thicker by measuring a change amount changing in response to the penetration, and the blade 3 is embedded in the support layer GS.SELECTED DRAWING: Figure 4
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a steel pipe pile with wings and a method for installing the same. [Background technology]

[0002] Steel pipe piles with wings are used as foundations for structures built on soft ground. In constructing steel pipe piles with wings, it is common to insert a steel pipe pile with a spiral blade attached to its tip into the ground while rotating it (see, for example, Patent Document 1). During construction, the spiral blade generates a driving force for the pile into the ground as it rotates, and after construction, it functions to support the pile in the ground. To fully utilize the support function of the blade, it is important that the blade is located in a stronger layer (supporting layer) in the ground, not in a weak layer (see Figure 12). [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Japanese Patent Application Publication No. 11-303070 Summary of the Invention [Problem to be solved by the invention]

[0004] However, when steel pipe piles are anchored in a supporting layer called the intermediate layer (if there is soft ground under the supporting layer, the supporting layer may be called the intermediate layer), it is difficult to know whether the supporting capacity is guaranteed or not because the thickness of the intermediate layer is unknown at a location away from the boring survey location. This is especially worrying when the number of boring surveys is small compared to the size of the site, or when the thickness of the intermediate layer varies within the site. In addition, to actually check the intermediate layer, it is necessary to conduct frequent boring surveys or test excavations (a task of digging in the vicinity of the position where the piles will be driven before construction to check the thickness of the intermediate layer), which requires considerable cost and time. For example, even if the initial plan should have a supporting layer (intermediate layer) of sufficient thickness (see Figure 12), the thickness of the supporting layer (intermediate layer) is not necessarily uniform within the construction area, so it may actually be the case that the supporting layer (intermediate layer) is thinner than initially planned (see Figure 13). In that case, the bearing capacity obtained will be less than expected, but because this fact cannot be grasped, the construction results will be deemed to be fine (see Figure 13). Also, if it is discovered that the depth of the bearing layer (middle layer) is deeper than expected (the upper soft layer is thick) (see Figure 14), it will be estimated that the bearing capacity will be smaller, and it will become necessary to re-investigate the ground.

[0005] Therefore, an object of the present invention is to provide a bladed steel pipe pile and a construction method thereof that enables a simple method of confirming whether the required intermediate layer thickness is present at all points where the steel pipe pile is constructed. [Means for solving the problem]

[0006] One aspect of the present invention is a construction method for embedding a bladed steel pipe pile having a blade attached thereto into the ground by rotational force, A steel pipe pile with wings is used, in which the wings are attached at a position a predetermined length L above the tip of the steel pipe pile along the central axis, When a steel pipe pile with wings is driven into the supporting layer in the ground, the amount of change that occurs as the pile penetrates is measured to confirm that the supporting layer is at least as thick as L, and then the wings are embedded into the supporting layer.

[0007] During construction of a steel pipe pile with wings, resistance increases when the tip of the pile reaches the supporting layer, and the amount of change continues to increase thereafter. If the pile can continue to penetrate the supporting layer with the amount of change increased thereafter, it can be confirmed that the thickness of the supporting layer is at least the predetermined length L at this point. When the wings reach the supporting layer, resistance increases further, and the amount of change that changes with penetration changes. On the other hand, if the amount of change, for example, the rotational torque, decreases once before it increases further while the pile continues to penetrate the supporting layer with the amount of change changed, it can be considered that the tip breaks through the supporting layer before the wings reach the supporting layer, and it can be confirmed that the thickness of the supporting layer does not reach the predetermined length L at this point.

[0008] In the construction method of a steel pipe pile with blades as described above, the specified length L may generally be 3 to 5 times the outer diameter of the blade, or may be 3 to 5 times the outer diameter of the blade plus the embedded depth of the blade into the supporting layer.

[0009] The amount of change is, for example, any one of rotation torque, vibration, and sound.

[0010] Another aspect of the present invention is a steel pipe pile with wings for use in the above construction method.

[0011] In the above-mentioned steel pipe pile with wings, the outer diameter of the steel pipe in at least a portion of the steel pipe pile closer to the tip than the attachment position of the wings may be smaller than the outer diameter of the steel pipe on the base end side of the steel pipe closer to the attachment position.

[0012] A pressure surface for receiving a reaction force from the supporting layer may be formed between the tip of the above-mentioned steel pipe pile with blades and the mounting position of the blades.

[0013] In the above-mentioned steel pipe pile with wings, the pressure-receiving surface may be formed by a step of the steel pipe pile provided at a position directly below the wings. Effect of the Invention

[0014] According to the present invention, it becomes possible to confirm in a simple manner whether the required thickness of the intermediate layer is present at all points where a steel pipe pile is installed. [Brief description of the drawings]

[0015] [Figure 1] This is a diagram showing an outline of the ground with a soft layer and a supporting layer (intermediate layer), along with their depths and the expected changes in N-value. [Diagram 2] This is a diagram showing the state in which the tip of a bladed steel pipe pile in the process of being buried has reached the supporting layer in the ground. [Diagram 3] This is a diagram showing the state in which the blades of a bladed steel pipe pile in the process of being buried have reached the supporting layer in the ground. [Figure 4] FIG. 4 is a diagram showing the state after the bladed steel pipe pile has been further buried and the blades have been embedded in the pile from the state shown in FIG. [Diagram 5] This is a six-view diagram showing an example of a steel pipe pile with wings, consisting of (A) a front view, (B) a right side view, (C) a rear view, (D) a left side view, (E) a top view, and (F) a bottom view. [Figure 6] This figure shows (A) a front view (side view) of a pile with a closed tip and (B) the effective area (projected surface) contributing to the bearing capacity, which explains the stress distribution from the tip of a steel pipe pile with wings and the pressure-receiving surface of the pile. [Figure 7] This is a diagram showing the state in which the tip of a bladed steel pipe pile in the process of being buried has broken through the supporting layer in the ground. [Figure 8] FIG. 11 is a six-view diagram showing an example of a bladed steel pipe pile in the second embodiment of the present invention, comprising (A) a front view, (B) a right side view, (C) a rear view, (D) a left side view, (E) a top view, and (F) a bottom view. [Figure 9] FIG. 1A is a front view and FIG. 1B is a bottom view showing an example of a steel pipe pile with open tips, which explains the stress dispersion from the tip of the steel pipe pile with wings and the pressure-receiving surface of the pile. [Figure 10] FIG. 13A is a front view and FIG. 13B is a bottom view showing an example of a steel pipe pile with wings having an open tip, illustrating stress dispersion from the tip of the steel pipe pile with wings in the second embodiment and the pressure-receiving surface of the pile. [Figure 11] This is a diagram showing the state of a bladed steel pipe pile, in which the steel pipe at the tip of the blade is made smaller in diameter, in the middle of being embedded. [Figure 12] FIG. 1 is a diagram showing, for reference, how a conventional steel pipe pile with blades is embedded in the ground. [Figure 13] FIG. 13 is a diagram showing, for reference, how a conventional steel pipe pile with wings is embedded in ground having a thinner bearing layer (less thickness) than that in the case of FIG. 12. [Figure 14] FIG. 14 is a diagram showing, for reference, how a conventional steel pipe pile with wings is embedded in ground having a bearing layer at a different position (depth) from that in the case of FIG. 13. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0016] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the configuration of the present invention will be described in detail based on an example of an embodiment shown in the drawings.

[0017] [First embodiment] FIG. 1 etc. show a preferred embodiment of a bladed steel pipe pile and a construction method thereof according to the present invention.

[0018] <Configuration of steel pipe pile with wings> The bladed steel pipe pile 10 comprises a pile body 11, a tip portion 12, and blades 13 (see FIG. 5, etc.).

[0019] The pile main body 11 is made of, for example, a cylindrical steel pipe. The cylindrical steel pipe is formed along a central axis 11C.

[0020] The tip 12 is one end of the pile body 11, and is the end portion on the digging side that faces downward when buried (see FIG. 5). The tip 12 may be open or closed, and may be equipped with a digging blade or digging claws to improve penetration into the supporting layer.

[0021] The blades 13 are formed in a spiral shape on the circumferential surface of the pile main body 11 (see FIG. 5). When the bladed steel pipe pile 10 is buried, the blades rotate around the central axis 11C in accordance with the rotation of the pile main body 11, and the rotational force is converted into a vertically downward propulsive force in the ground G to bury the bladed steel pipe pile 10. After burying, the blades 13 receive a large ground reaction force in the ground G, thereby obtaining the bearing force of the pile main body 11. The blades 13 are formed to be substantially circular when viewed from above, and the blade diameter (outer diameter of the blades 13) is Dw (see FIG. 9, etc.). Note that in this embodiment, the blades 13 are described as being spiral-shaped, but this is merely one suitable example, and it goes without saying that the blades 13 may have other shapes, such as a flat plate shape.

[0022] The blade 13 in this embodiment is provided at a position that is a predetermined length L above the tip 12 of the pile main body 11 along the central axis 11C (see FIG. 9, etc.). This predetermined length L may be defined more precisely. As an example, in this embodiment, the predetermined length L is defined as the length when the tip of the pile main body 11 (the part that is the endmost part of the tip 12) is taken as the starting point and the part of the blade 13 that is closest to the tip 12 is taken as the ending point.

[0023] Here, the above-mentioned predetermined length L, which corresponds to the length from the tip 12 of the pile body 11 to the blade 13, may be set to a length 3 to 5 times the outer diameter of the blade, or may be set to a length that is 3 to 5 times the outer diameter of the blade plus the embedment depth of the blade into the supporting layer. This will be explained below (see FIG. 6, etc.).

[0024] For example, when trying to obtain a bearing capacity from the closed tip 12 and the blade 13 arranged immediately adjacent to it, the ground reaction force acts on the entire (total area) of the circular bearing surface (pressure-receiving surface) consisting of both the tip 12 and the blade 13 (see Fig. 6), but even in such a case, the load acting on the bearing surface (pressure-receiving surface) disperses as it moves away from the bearing surface (in this example, the part consisting of the projection surfaces of both the tip 12 and the blade 13) (i.e., as it becomes deeper from the tip 12 and the blade 13) (this phenomenon is referred to as "stress dispersion" in this specification). Considering such stress dispersion, it is said that the ground depth that affects the bearing capacity of the steel pipe pile with blades 10 is about 3 to 5 times the blade diameter (outer diameter of the blade 13) Dw, and based on this, it can be said that the strength of the ground in this range of ground depth (i.e., 3Dw to 5Dw) affects the magnitude of the bearing capacity (see Figs. 12 to 14). If the depth is less than 3Dw, the stress from the blades will affect the soft layer underneath, and there is a possibility that the pile will sink. If the depth is more than 5Dw, the bearing capacity will not be an issue, but the pile material costs will be high. If this is the case, it can be explained that it is important to bury the pile in such a way that a hard bearing layer GS exists in the ground depth range of 3Dw to 5Dw below the supporting surface (see FIG. 6). Thus, in this embodiment, we propose a bladed steel pipe pile 10 and a construction method for said pile that are structured so that a hard bearing layer GS exists in the ground depth range of 3Dw to 5Dw below the supporting surface.

[0025] <Construction method of steel pipe piles with wings> In this embodiment, the bladed steel pipe pile 10 having the above-mentioned structure is constructed as follows, so that a sufficient bearing capacity can be obtained below the supporting surface. Hereinafter, the method will be described with reference to the drawings (see Figs. 1 to 4, etc.).

[0026] First, as a ground G of a possible pattern when burying a steel pipe pile with wings 10, a ground G in which a soft layer GW1 is directly below the ground surface GL, a supporting layer GS is below that, and another soft layer GW2 is below that (see FIG. 1). In order to make it easier to understand, the supporting layer GS is shown darker than the other layers in the figure. As shown in the figure, the supporting layer GS in this ground G is located between the upper soft layer GW1 and the lower soft layer GW2, and due to this aspect, such a supporting layer may be called an "intermediate layer". As described above, when constructing a steel pipe pile with wings 10 in such a so-called soft ground G, it is important to construct the steel pipe pile with wings 10 so that the supporting function of the wings 13 is fully exerted, so that the wings 13 are positioned in the supporting layer GS that is stronger than the soft layer GW. In order to perform such construction, the following method is adopted in this embodiment.

[0027] That is, in this embodiment, when the bladed steel pipe pile 10 is penetrated into the unexcavated ground G, the amount of change that occurs with the penetration, such as the rotational torque, is measured, and the value of the rotational torque is confirmed while construction is performed. Although the rotational torque is not particularly shown, it can be measured using a torque meter, for example, when the bladed steel pipe pile 10 is rotated using a pile driver having a leader, an auger, a vibration prevention device, a torque meter, etc. Also, in this embodiment, the N value of a given ground G, which is assumed to be from above as the soft layer GW-supporting layer GS-soft layer GW, is assumed or set in advance, and the state of the ground G is explored while comparing the rotational torque T measured as described above with the N value (see FIG. 1, etc.).

[0028] From the start of construction of the bladed steel pipe pile 10 until its tip 12 reaches the supporting layer GS, the bladed steel pipe pile 10 penetrates the soft layer GW1 (see FIG. 2). Therefore, the rotational torque during this period is the smallest value during construction. In this embodiment, the average value of the rotational torque T during this period is set to T1 (see FIG. 2). The depth reached by the tip 12 at this time is tentatively set to D1 (see FIG. 2).

[0029] After the tip 12 reaches the bearing layer GS, the resistance acting on the bladed steel pipe pile 10 mainly via the tip 12 increases, resulting in an increase in the rotational torque T. The average value of the rotational torque at this time is defined as T2 (see FIG. 3). Also, the depth reached by the tip 12 when the blades 13 reach the bearing layer GS is defined as D2 (see FIG. 3).

[0030] As described above, by carrying out construction while checking the value of the rotation torque that changes with penetration, it is possible to grasp the thickness of the supporting layer GS at the construction site. That is, if the change in the value of the rotation torque with penetration is as described above, it is estimated that the thickness of the supporting layer GS at the construction site is at least the predetermined length L or more. If it is determined based on such an estimation that there is no problem with the thickness of the supporting layer GS, the bladed steel pipe pile 10 is further rotated to penetrate to a certain depth, for example, until the tip 12 reaches a depth D3, and the blades 13 are embedded in the supporting layer GS (see FIG. 4). According to this method, it is possible to carry out construction while checking whether the necessary thickness of the supporting layer (intermediate layer) GS exists while carrying out construction at the actual site where the bladed steel pipe pile 10 is actually buried, without conducting a prior investigation. In addition, the length L may be set to a length that is 3 to 5 times the blade diameter Dw (3Dw to 5Dw) plus the embedded depth of the blades 13 into the supporting layer GS, taking the above-mentioned embedded portion into consideration in advance. In such a case, it is possible to carry out construction while checking whether the necessary thickness of the supporting layer GS (at least 3Dw) exists below the blade 13 after embedding.

[0031] The above is the case where the change in the rotational torque value is as expected, but if there is a change that is not as expected, it may not be possible to estimate that the thickness of the support layer GS is sufficient. In other words, if the tip 12 comes out of the support layer GS (the bottom) before the blade 13 reaches the support layer GS (see Figure 7), it may happen that the rotational torque T decreases before it increases from T2 to T3. In such a case, it is possible to consider reducing the bearing capacity and take measures such as driving in additional piles.

[0032] [Second Embodiment] As the steel pipe pile 10 with fins, a structure in which the outer diameter of the pile main body 11 changes midway may be adopted. Hereinafter, while giving specific examples of such a steel pipe pile 10 with fins, reference will be made to FIGS. 8, 10, etc. for description as the second embodiment of the present invention).

[0033] In the steel pipe pile 10 with fins of this embodiment, among the pile main body 11, the steel pipe outer diameter (indicated by reference sign Dp2) of the portion closer to the tip 12 than the attachment position (indicated by reference sign P 13 shown) of the fin 13 is smaller at the stepped portion 15 than the steel pipe outer diameter (indicated by reference sign Dp1) on the base end 14 side than the attachment position P 13 (Dp2 < Dp1), and it has a shape of a so-called two-stage structure (see FIGS. 10, etc.). The steel pipe pile 10 with fins having such a structure can substantially expand the pressure receiving surface (indicated by reference sign 16 in FIGS. 10, etc.) and make the ground reaction received from the ground G larger.

[0034] That is, in the case of the steel pipe pile 10 with fins having a uniform steel pipe outer diameter (here, it is assumed that the tip 12 is open), the annular portion obtained by adding the projected areas of both the tip 12 and the fin 13 becomes the pressure receiving surface 16 and the ground reaction acts on the pressure receiving surface 16. However, considering the influence of the stress dispersion described above, only the portion of the fin 13 actually functions as the pressure receiving surface 16. Therefore, actually, the area of the tip 12 is not included in the pressure receiving surface 16, and only the area of the portion of the fin 13 is effective as the substantial pressure receiving surface 16 (see FIG. 9). In this regard, in this embodiment, by making the steel pipe outer diameter of the pile main body 11 a two-stage structure via the stepped portion 15, it is possible to increase the surface that functions as the pressure receiving surface 16 in the vicinity of the fin 13 (see FIG. 10). More specifically, not only the projected area of the fin 13 but also the area of the annular stepped portion 15 substantially functions as the pressure receiving surface 16, so that the surface that functions as the pressure receiving surface 16 increases accordingly. Thus, the tip 12 of the steel pipe pile 10 with fins and the attachment position P of the fin 13 13By forming a pressure surface 16 between the blades 13 and the step 15, which receives a reaction force from the bearing layer GS, the bearing force that the bladed steel pipe pile 10 receives from the ground G can be more effectively generated (see FIG. 11, etc.). Furthermore, as is clear from the explanation so far, in consideration of the effect of stress dispersion, it is preferable that the pressure surface 16 (in this embodiment, the pressure surface increased by the step 15) be provided in a position as close to the blades 13 as possible, such as directly below the blades 13, from the standpoint of more effectively generating a bearing force.

[0035] In this embodiment, a bladed steel pipe pile 10 consisting of a pile main body 11 with a stepped structure in which the outer diameter changes at each step 15 (see FIG. 8, etc.) is shown, but this is merely one suitable example of a structure for more effectively generating bearing capacity while considering the effect of stress dispersion. Although not specifically shown, it is of course possible to have a structure in which the outer diameter changes in multiple steps by increasing the number of steps, or a structure that includes a tapered portion midway, and the specific form in which the outer diameter changes midway is not limited to the above.

[0036] Furthermore, when constructing a bladed steel pipe pile 10 whose outer diameter changes midway as described above, differences in the shape and size of the tip 12 and the presence or absence and position of the step 15 should have some effect on the magnitude and change in the rotational torque; however, the basic point of measuring the rotational torque as a change that occurs with penetration and detecting the thickness of the soft layer GW1 and supporting layer GS based on the value of that rotational torque while proceeding with construction is the same as the construction method described in the first embodiment.

[0037] The above-mentioned embodiment is an example of a preferred embodiment of the present invention, but is not limited thereto and can be modified in various ways without departing from the scope of the present invention. For example, in this embodiment, the rotational torque is measured as a change amount that changes with penetration, but this is only one preferred example of a parameter that indicates a change. In addition, for example, it is naturally possible to use the vibration and sound that change with penetration, especially the vibration and sound that change when the tip part 12 penetrates from the soft layer GW1 to the supporting layer GS or vice versa, as the change amount. The vibration and sound can be measured by attaching a sensor to the excavation equipment, but it is also effective for the pile driver operator or construction manager to make an empirical judgment based on the change in the vibration and sound generated in the excavation equipment. [Industrial Applicability]

[0038] INDUSTRIAL APPLICABILITY The present invention is suitable for application to a bladed steel pipe pile and to the construction of embedding the pile in the ground by rotational force. [Explanation of symbols]

[0039] 10...Steel pipe pile with wings 11...Pile body of steel pipe pile with wings 11C…Central axis 12...Tip of steel pipe pile with wings 13...(spiral) feather 14...Base end of steel pipe pile with wings 15...Double part 16…Pressure surface Dp1: Outer diameter of thick part of steel pipe Dp2: Outer diameter of thin part of steel pipe Dw…Blade diameter G: Ground GL…Ground surface GS…Support layer (middle layer) GW1…soft layer GW2…soft layer L: The specified length from the tip to the blade P 13 …Blade installation position

Claims

1. A construction method for embedding a steel pipe pile with wings attached in the ground by rotational force, comprising: A steel pipe pile with a blade is adopted in which the blade is attached to a position that is a predetermined length L above the tip of the steel pipe pile with a blade along the central axis, This construction method for a steel pipe pile with wings is characterized in that, when the steel pipe pile with wings is penetrated into an intermediate layer, which is a supporting layer located between the upper and lower weak layers in the ground, the average value of the rotational torque T, which changes with penetration, is measured, and D1 is the depth reached by the tip of the pile when the average value of the rotational torque increases from T1, which is the relatively smallest value during construction, to T2, and D2 is the depth reached by the tip of the pile when the average value of the rotational torque next increases from T2 to T3, and by checking that D2-D1≧L, it is confirmed that the supporting layer is at least thicker than L, and the wings are then embedded into the supporting layer.

2. 2. The method for constructing a steel pipe pile with blades according to claim 1, wherein the predetermined length is 3 to 5 times the outer diameter of the blade.

3. 2. The method for constructing a steel pipe pile with wings according to claim 1, wherein the predetermined length is 3 to 5 times the outer diameter of the wing plus the embedded depth of the wing into the supporting layer.

4. The method for constructing a bladed steel pipe pile according to claim 1 , wherein the amount of change is any one of rotational torque, vibration, and sound.

5. A bladed steel pipe pile used in the construction method according to any one of claims 1 to 4.

6. The steel pipe pile with wings according to claim 5, wherein the outer diameter of the steel pipe in at least a portion of the steel pipe pile closer to the tip than the wings is smaller than the outer diameter of the steel pipe on the base end side of the steel pipe than the wings.

7. The steel pipe pile with wings according to claim 6 , wherein a pressure-receiving surface for receiving a reaction force from the supporting layer is formed between the tip and the wings.

8. The steel pipe pile with wings according to claim 7 , wherein the pressure-receiving surface is formed by a step of the steel pipe pile provided at a position directly below the wings.

Citation Information

Patent Citations

  • Steel pipe pile

    JP1984109616A

  • Execution method for steel pipe pile with nose blade

    JP1999303070A

  • Screwed steel pipe pile and execution method thereof

    JP2001311147A

  • Foundation pile

    JP2003293367A

  • Steel pipe pile and method of constructing the same

    JP2009215808A