Beam bottom member and beam construction method

The beam bottom member with partially buried reinforcing bars and lightweight formwork reduces weight and construction costs, enhancing beam integrity and precision in construction.

JP7587551B2Active Publication Date: 2024-11-20TAISEI ULEC
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
JP2022098491
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2022-06-17
Publication Date
2024-11-20
Estimated Expiration
2042-06-17

AI Technical Summary

Technical Problem

Conventional methods for constructing beams using precast concrete beam bottom members result in increased weight and construction costs due to the need for large lifting machines.

Method used

A beam bottom member made of precast concrete with reinforcing bars partially buried in the concrete body, where the reinforcing bars have lower and upper rod-shaped parts connected by a connecting part, reducing the thickness of the concrete body and enhancing its rigidity, and using lightweight synthetic resin weir plates and aluminum formwork retainers for construction.

Benefits of technology

Reduces construction costs by enabling the use of smaller cranes, improves beam integrity, and allows for wider support intervals, while ensuring precise construction with reusable formwork materials.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007587551000001
    Figure 0007587551000001
  • Figure 0007587551000002
    Figure 0007587551000002
  • Figure 0007587551000003
    Figure 0007587551000003
Patent Text Reader

Abstract

To provide a beam bottom member capable of reducing construction costs.SOLUTION: A beam bottom member 10 is a member which is made in precast concrete as a bottom part of a beam 2. The beam bottom member 10 comprises: a concrete body 30; a plurality of lower beam main bars 20 which are embedded in the concrete body 30 and are substantially parallel to each other; and a reinforcement bar 40 which is partially embedded in the concrete body 30. The reinforcement bar 40 comprises: a lower rod-like part 41 which is embedded between the lower beam main bars 20 of the concrete body 30; a rod-like upper rod-like part 42 which is arranged at an upper part of the concrete body 30 and extends substantially parallel to the lower rod-like part 41; and a connection part 43 which connects the lower rod-like part 41 and the upper rod-like part 42.SELECTED DRAWING: Figure 3
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a precast concrete beam bottom member that serves as the bottom of a beam, and a method for constructing a beam using this beam bottom member. [Background technology]

[0002] Conventionally, a method of constructing a beam using a precast concrete beam bottom member has been proposed (see Patent Documents 1 and 2). Patent Document 1 shows a precast plate that constitutes the bottom surface of a beam in a reinforced concrete structure. The bottom ends of the beam stirrups and the beam bottom reinforcement are embedded in the precast plate. Patent Document 2 shows a half-precast beam that constitutes the framework of an architectural structure. The half-precast beam includes multiple main beam reinforcements, multiple shear reinforcements surrounding the main beam reinforcements, and a precast concrete plate formed by arranging a part of the main beam reinforcements and the shear reinforcements inside the plate. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Japanese Patent Application Publication No. 9-78690 [Patent Document 2] JP 2012-241311 A Summary of the Invention [Problem to be solved by the invention]

[0004] However, in the conventional method, the weight of the beam bottom member is large, and it is necessary to use a large lifting machine, which increases the construction cost.

[0005] An object of the present invention is to provide a beam bottom member that can reduce construction costs, and a method for constructing a beam using this beam bottom member. [Means for solving the problem]

[0006] The beam bottom member of the first invention (e.g., beam bottom members 10 and 10A described later) is a precast concrete beam bottom member that serves as the bottom of a beam (e.g., beam 2 described later), and comprises a concrete body (e.g., concrete body 30 described later), a plurality of beam main reinforcements (e.g., lower beam main reinforcements 20 described later) that are approximately parallel to each other and embedded in the concrete body, and a reinforcing bar (e.g., reinforcing bar 40 described later), a portion of which is embedded in the concrete body, wherein the reinforcing bar comprises a lower rod-shaped portion (e.g., lower rod-shaped portion 41 described later) embedded between the beam main reinforcements of the concrete body, a rod-shaped upper rod-shaped portion (e.g., upper rod-shaped portion 42 described later) that is disposed above the concrete body and extends approximately parallel to the lower rod-shaped portion, and a connecting portion (e.g., connecting portion 43 described later) that connects the lower rod-shaped portion and the upper rod-shaped portion.

[0007] According to this invention, the lower rod-shaped portion of the reinforcing bar is embedded in the concrete body of the beam bottom member, and the upper rod-shaped portion of the reinforcing bar is placed above the concrete body, and the lower rod-shaped portion and the upper rod-shaped portion are connected by a connecting portion. In this way, only the lower rod-shaped portion of the reinforcing bar is embedded in the concrete body, so the thickness of the concrete body can be made thin. In addition, since the upper rod-shaped portion reinforces the lower rod-shaped portion, the rigidity of the lower rod-shaped portion is increased, so that cracks in the concrete body can be prevented even if the concrete body is made thin. Therefore, the weight of the beam bottom member can be reduced, so that the beam bottom member can be lifted by a small crane, and construction costs can be reduced. Furthermore, by being able to reduce the weight of the beam bottom member while preventing cracks in this way, when the beam bottom member is lifted and installed in a designated location, the installation spacing of the supports supporting the beam bottom member can be made wider, thereby reducing construction costs. In addition, since the lower rod-shaped part of the reinforcing bar is embedded in the concrete body of the beam base member and the upper rod-shaped part of the reinforcing bar is embedded in the concrete of the beam that is poured later, the reinforcing bar ensures the integrity of the concrete body of the beam base member and the post-cast structure of the beam.

[0008] The beam bottom member of the second invention is characterized in that the upper surface of the concrete body is formed with projections and recesses.

[0009] According to this invention, unevenness is formed on the upper surface of the concrete body of the beam bottom member, thereby improving the frictional resistance of the joint surface between the concrete body of the beam bottom member and the post-cast beam back-cast structure, thereby improving the integrity between the beam bottom member and the post-cast beam structure.

[0010] The beam bottom member of the third invention further comprises an approximately U-shaped second reinforcing bar (e.g., second reinforcing bar 90 described below) partially embedded in the concrete body and engaged with the main beam reinforcement, and the second reinforcing bar comprises a rod-shaped horizontal portion (e.g., horizontal portion 91 described below) arranged on the underside of the main beam reinforcement, and a rod-shaped vertical portion (e.g., vertical portion 92 described below) extending upward from both ends of the horizontal portion.

[0011] According to this invention, a second reinforcing bar is provided with a portion embedded in the concrete body of the beam base member. Therefore, by embedding the remaining portion of the second reinforcing bar in the concrete of the beam that is poured later, the second reinforcing bar can ensure the integrity of the concrete body of the beam base member and the post-cast beam skeleton. In addition, since the second reinforcing bar is engaged with the main beam reinforcement, the pull-out strength of the second reinforcing bar is improved, and the integrity between the concrete body of the beam base member and the post-cast beam structure is further improved.

[0012] The beam construction method of the fourth invention is a method of constructing a beam using the above-mentioned beam bottom member, and is characterized in that it includes the steps of placing a synthetic resin sheathing (e.g., sheathing 71 described below) on the beam bottom member on the ground, placing an aluminum or synthetic resin formwork clamp (e.g., formwork clamp 72 described below) on the outer surface of the sheathing, and temporarily fixing the lower end of the formwork clamp to the side end surface of the beam bottom member with a fixing hardware (e.g., fixing hardware 73 described below) (e.g., step S1 described below), lifting the beam bottom member and placing it in a predetermined position (e.g., step S2 described below), placing reinforcement on the beam bottom member and pouring concrete (e.g., steps S4 and S5 described below), and removing the fixing hardware and removing the formwork clamp and the sheathing (e.g., step S6 described below).

[0013] According to this invention, the beam is constructed using a lightweight beam bottom member, so that the construction cost of the beam can be reduced. In addition, since synthetic resin sheathing and aluminum or synthetic resin formwork clamps are used as the side formwork of the beam attached to the beam bottom member, the beam bottom unit including the beam bottom member can be made lighter, further reducing construction costs. In addition, synthetic resin sheathing is lightweight and has excellent peelability, improving work efficiency. Also, the formwork holder is made of lightweight aluminum, making it easy to handle and improving work efficiency. In addition, the synthetic resin sheathing and aluminum formwork retainers can be reused, reducing construction costs.

[0014] The beam construction method of the fifth invention is characterized in that in the step of lifting and positioning the beam bottom member, a precast concrete deck (e.g., deck 50 described below) is placed adjacent to the beam bottom member, and a second fixing hardware (e.g., second fixing hardware 80 described below) is attached to the underside of the deck to temporarily fix the upper end of the formwork retainer.

[0015] According to this invention, the upper end of the formwork retainer is temporarily fixed to the deck slab by the second fixing metal fitting, thereby preventing the sheathing and formwork retainer from shifting when the concrete for the beam is poured, allowing the beam to be constructed with high precision. Effect of the Invention

[0016] According to the present invention, it is possible to provide a beam bottom member that can reduce construction costs, and a method for constructing a beam using this beam bottom member. [Brief description of the drawings]

[0017] [Figure 1] 1 is a vertical cross-sectional view of a beam portion of a building constructed using a beam bottom member according to a first embodiment of the present invention. FIG. [Diagram 2] FIG. 2 is a plan view of the beam bottom member according to the first embodiment. [Diagram 3]2 is a cross-sectional view taken along line AA of the beam bottom member according to the first embodiment. FIG. [Figure 4] 4 is a flowchart showing the procedure for constructing a beam portion of a building using the beam bottom member according to the first embodiment. [Diagram 5] FIG. 2 is a vertical cross-sectional view of a beam bottom unit using a beam bottom member according to the first embodiment. [Figure 6] FIG. 2 is a side view of a beam bottom unit using a beam bottom member according to the first embodiment. [Figure 7] This is an explanatory diagram of the beam construction procedure (Part 1, with the beam bottom unit in place). [Figure 8] This is an explanatory diagram of the beam construction procedure (part 2, with the deck slab in place). [Figure 9] 6 is a vertical cross-sectional view of a beam portion of a building constructed using a beam bottom member according to a second embodiment of the present invention. FIG. [Figure 10] FIG. 2 is a vertical cross-sectional view of a beam portion of a building constructed using a beam bottom member according to a first modified example of the present invention. [Figure 11] 13 is a vertical cross-sectional view of a beam portion of a building constructed using a beam bottom member according to a second modified example of the present invention. FIG. [Figure 12] FIG. 11 is a vertical cross-sectional view of a beam portion of a building constructed using a beam bottom member according to a third modified example of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0018] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. In the following description of the embodiments, the same components are denoted by the same reference numerals, and the description thereof will be omitted or simplified. [First embodiment] FIG. 1 is a vertical cross-sectional view of a beam portion of a building 1 constructed using a beam base member 10 according to a first embodiment of the present invention. The building 1 comprises a reinforced concrete beam 2 and a reinforced concrete floor slab 3 provided on both sides of the beam 2. The beam 2 comprises a beam base member 10 made of precast concrete and a beam post-cast structure 11 constructed by placing reinforcement on top of the beam base member 10 and then pouring concrete.

[0019] The beam 2 is provided with four lower beam main reinforcements 20 that are substantially parallel to each other, four upper beam main reinforcements 21 that are substantially parallel to each other and disposed above the lower beam main reinforcements 20, rectangular frame-shaped stirrup reinforcements 22 that are provided at a predetermined interval along the length direction of the beam main reinforcements 20 and 21, abdominal reinforcements 23 that are provided at the intermediate height of the stirrup reinforcements 22, and width stop reinforcements 24 that are provided between the abdominal reinforcements 23. The stirrup reinforcements 22 are composed of a stirrup reinforcement body 25 that is substantially U-shaped with an open upper side, and a cap 26 that is placed on the stirrup reinforcement body 25 from above. Hooks are provided on both ends of the substantially U-shaped stirrup reinforcement body 25, and the hooks of the stirrup reinforcement body 25 are engaged with the upper beam main reinforcement 21. A hook is provided on one end of the cap 26, and the hooks of the cap 26 are engaged with the upper beam main reinforcement 21.

[0020] Fig. 2 is a plan view of the beam bottom member 10. Fig. 3 is an AA cross-sectional view of the beam bottom member 10. Here, Fig. 2(a) shows the beam bottom member 10 arranged in the longitudinal direction of the building 1, and Fig. 2(b) shows the beam bottom member 10 arranged in the lateral direction of the building 1. The beam bottom member 10 comprises a flat concrete body 30 having a thickness t, the above-mentioned lower beam main reinforcement 20 embedded in the concrete body 30, the above-mentioned stirrup main body 25 whose lower end is embedded in the concrete body 30, and a reinforcing bar 40 whose portion is embedded in the concrete body 30. The reinforcing bar 40 comprises a pair of approximately parallel lower rod-shaped portions 41 embedded between the lower beam main bars 20 in the concrete body 30, an upper rod-shaped portion 42 positioned above the concrete body 30 and extending approximately parallel to the pair of lower rod-shaped portions 41, and a connecting portion 43 connecting the pair of lower rod-shaped portions 41 and the upper rod-shaped portion 42. Furthermore, when the concrete of the concrete body 30 is poured, the upper surface of the poured concrete is brushed, so that an uneven surface 31 is formed over the entire upper surface of the concrete body 30.

[0021] Returning to FIG. 1, the floor slab 3 includes a precast concrete floor slab 50 and a floor post-cast structure 51 constructed by arranging reinforcement on the floor slab 50 and then pouring concrete. The lower end of floor reinforcement bars 60 is embedded in the floor slab 50. In this floor slab 3, lattice-shaped lower slab reinforcement bars 61 arranged on the floor slab 50 and lattice-shaped upper slab reinforcement bars 62 arranged on the floor reinforcement bars 60 are arranged.

[0022] Hereinafter, a procedure for constructing the beam portion of the building 1 using the beam bottom member 10 will be described with reference to the flow chart of FIG. In step S1, on the ground, as shown in Figs. 5 and 6, a beam bottom unit 70 is assembled on the ground surface 4 using the beam bottom members 10. Specifically, a base 5 is installed on the ground surface 4, and a beam bottom member 10 is placed on the base 5. Next, a synthetic resin sheathing 71 is placed on the beam bottom member 10, and an aluminum formwork retainer 72 is placed on the outer surface of the sheathing 71. The lower end of the formwork retainer 72 is temporarily fixed to the side end surface of the concrete body 30 of the beam bottom member 10 with a fixing hardware 73. This fixing hardware 73 is composed of a separator 74 and a P cone 75 embedded in the concrete body 30 of the beam bottom member 10, and a nut 76 screwed into this P cone 75. In addition, the belly bars 23 and width stop bars 24 are arranged in the stirrup body 25 of the beam bottom member 10, and the upper beam main bars 21 are placed on the width stop bars 24 and temporarily fixed in place.

[0023] In step S2, as shown in Fig. 7, the beam bottom units 70 are lifted by a small lifting machine (not shown) and erected between the columns 6, and are supported at predetermined intervals by supports 7. Note that in Fig. 7, the illustration of the sheathing boards 71 ​​and the formwork retainers 72 is omitted. In step S3, as shown in Fig. 8, the precast concrete floor slab 50 is lifted and placed adjacent to the beam bottom unit 70 and supported by supports (not shown). Next, a second fixing hardware 80 that temporarily fixes the upper end of the formwork retainer 72 to the underside of the floor slab 50 is attached. This second fixing hardware 80 includes an insert 81 embedded in the floor slab 50, a nut 82 screwed into this insert 81, and a pressing plate 83 that is sandwiched between the insert 81 and the nut 82 and presses down the upper end of the formwork retainer 72.

[0024] In step S4, as shown in Fig. 8, reinforcement is performed on the beam bottom unit 70 and on the floor slab 50. Specifically, the upper beam main reinforcement 21 temporarily fixed on the width stopper bars 24 is lifted and arranged, and the cap 26 is attached on the stirrup reinforcement body 25. In addition, the lower slab reinforcement 61 and the upper slab reinforcement 62 are arranged on the floor slab 50. In step S5, concrete is poured onto the beam bottom unit 70 and the floor slab 50 to construct the beam post-cast structure 11 and the floor post-cast structure 51, thereby completing the beam 2 and floor slab 3. In step S6, the nuts 76 of the fixing hardware 73 and the nuts 82 of the second fixing hardware 80 are removed, and the retaining plate 83, the formwork retainer 72, and the sheathing board 71 are removed.

[0025] According to this embodiment, the following effects are obtained. (1) The lower rod-shaped portion 41 of the reinforcing bar 40 is embedded in the concrete body 30 of the beam bottom member 10, and the upper rod-shaped portion 42 of the reinforcing bar 40 is disposed above the concrete body 30, and the lower rod-shaped portion 41 and the upper rod-shaped portion 42 are connected by the connecting portion 43. In this manner, since only the lower rod-shaped portion 41 of the reinforcing bar 40 is embedded in the concrete body 30, the thickness t of the concrete body 30 can be made thin. In addition, since the upper rod-shaped portion 42 reinforces the lower rod-shaped portion 41, the rigidity of the lower rod-shaped portion 41 is increased, so that cracks in the concrete body 30 can be prevented even if the concrete body 30 is made thin. Therefore, the beam bottom member 10 can be made lighter, and the beam bottom member 10 can be lifted by a small crane, and construction costs can be reduced. Furthermore, by being able to prevent cracks while reducing the weight of the concrete body 30 of the beam bottom member 10 in this way, when the beam bottom member 10 is lifted and installed in a designated location, the installation intervals of the supports 7 supporting the beam bottom member 10 can be made wider, thereby reducing construction costs. In addition, since the lower rod-shaped portion 41 of the reinforcing bar 40 is embedded in the concrete body 30 of the beam bottom member 10 and the upper rod-shaped portion 42 of the reinforcing bar 40 is embedded in the concrete of the beam 2 which is poured later, the reinforcing bar 40 ensures the integrity of the concrete body 30 of the beam bottom member 10 and the post-cast beam body 11.

[0026] (2) Since an uneven surface 31 is formed on the upper surface of the concrete body 30 of the beam bottom member 10, the frictional resistance of the joint surface between the concrete body 30 of the beam bottom member 10 and the post-cast structure 11 of the post-cast beam is improved, thereby improving the integrity between the beam bottom member 10 and the post-cast structure 11 of the beam. (3) Since the beam 2 is constructed using the lightweight beam bottom member 10, the construction cost of the beam 2 can be reduced. In addition, since a synthetic resin sheathing 71 and an aluminum formwork retainer 72 are used as the side formwork of the beam attached to the beam bottom member 10, the weight of the beam bottom unit 70 can be reduced, further reducing construction costs. In addition, the synthetic resin sheathing 71 is lightweight and has excellent peelability, improving work efficiency. Also, the formwork holder 72 is made of lightweight aluminum, making it easy to handle, improving work efficiency. Furthermore, the synthetic resin sheathing 71 and the aluminum formwork retainer 72 can be reused repeatedly, which reduces construction costs. (4) Since the upper end of the formwork retainer 72 is temporarily fixed to the deck 50 by the second fixing hardware 80, the sheathing 71 and the formwork retainer 72 are prevented from shifting when the concrete for the beam 2 is poured, enabling the beam 2 to be constructed with high precision.

[0027] Second Embodiment FIG. 9 is a vertical cross-sectional view of a beam portion of a building 1 constructed using a beam bottom member 10A according to the second embodiment of the present invention. This embodiment differs from the first embodiment in that second reinforcing bars 90, part of which is embedded in the concrete body 30, are provided at both ends of the concrete body 30 in the longitudinal direction. That is, the second reinforcing bar 90 is substantially U-shaped and is engaged with two lower beam main reinforcing bars 20. This second reinforcing bar 90 includes a rod-shaped horizontal portion 91 disposed on the lower surface of the lower beam main reinforcing bar 20 and rod-shaped vertical portions 92 extending upward from both ends of the horizontal portion 91. According to this embodiment, in addition to the above-mentioned advantages (1) to (4), the following advantages are obtained.

[0028] (5) A second reinforcing bar 90 is provided with its lower portion embedded in the concrete body 30 of the beam base member 10. Thus, by embedding the upper portion of the second reinforcing bar 90 in the concrete of the beam 2 to be poured later, the second reinforcing bar 90 can ensure the integrity of the concrete body 30 of the beam base member 10 and the post-cast beam structure 11. In addition, since the second reinforcing bar 90 is engaged with the lower beam main reinforcement 20, the pull-out strength of the second reinforcing bar 90 is improved, and the integrity between the concrete body 30 of the beam bottom member 10 and the beam post-cast body 11 is further improved.

[0029] The present invention is not limited to the above-described embodiment, and modifications and improvements within the scope of the present invention that can achieve the object of the present invention are included in the present invention. For example, in each of the above-described embodiments, when the concrete of the concrete body 30 is poured, the upper surface of the poured concrete is brushed to form the uneven surface 31 on the upper surface of the concrete body 30, but this is not limited thereto, and when the concrete of the concrete body 30 is poured, an air bubble sheet may be attached to the upper surface of the poured concrete to form the uneven surface 31 on the upper surface of the concrete body 30. Alternatively, when the concrete of the concrete body 30 is poured, the upper surface of the concrete may be leveled with a metal trowel to make the upper surface of the concrete body 30 a smooth surface. In addition, in each of the above-described embodiments, an uneven surface 31 is formed over the entire upper surface of the concrete body 30, but this is not limited to the above, and unevenness may be provided only on a portion of the upper surface of the concrete body 30, with the remaining portion being a smooth surface.

[0030] In addition, in each of the above-described embodiments, the reinforcing bar 40 has two lower rod-shaped portions 41, but this is not limited thereto, and the reinforcing bar 40 may have only one lower rod-shaped portion 41, as shown in FIG. 10. In addition, in the above-mentioned second embodiment, the second reinforcing bar 90 is approximately U-shaped and is engaged with two lower beam main bars 20, but this is not limited to this. As shown in Figure 11, the second reinforcing bar 93 may be hook-shaped at both ends and the lower hook of the second reinforcing bar 93 may be engaged with one lower beam main bar. In addition, in the above-mentioned first embodiment, the lower main reinforcement 20 and the upper beam main reinforcement 21 of the beam 2 are each in one tier, but this is not limited thereto. As shown in FIG. 12, the lower main reinforcement 20 and the upper beam main reinforcement 21 of the beam 2 may each be in two tiers, upper and lower. [Explanation of symbols]

[0031] 1...Building 2...Beam 3...Floor slab 4...Ground surface 5... Stand 6... Pillar 7... Support 10, 10A... Beam bottom member 11... Beam rear cast structure 20...Lower beam main bar 21...Upper beam main bar 22...Stirrus bar 23...Abdominal bar 24…Width stop bar 25…Stirrup body 26…Cap 30...Concrete body 31...Uneven surface 40...Reinforcement bar 41...Lower bar-shaped part 42...Upper bar-shaped part 43...Connection part 50... Floor slab 51... Floor back cast structure 60...Floor reinforcement bar 61...Lower slab bar 62...Upper slab bar 70... Beam bottom unit 71... Sheathing 72... Formwork retainer 73... Fixing hardware 74...Separator 75...P cone 76...Nut 80...Second fixing hardware 81...Insert 82...Nut 83...Press plate 90, 93...Second reinforcement bar 91...Horizontal section 92...Vertical section

Claims

1. A precast concrete beam bottom member that serves as the bottom of a beam, A concrete body, A substantially U-shaped stirrup body having a lower end embedded in the concrete body and an upper side open; A plurality of beam reinforcements substantially parallel to each other are embedded on the substantially horizontal portion of the lower end of the stirrup body inside the concrete body; A reinforcing bar is provided, the reinforcing bar being partially embedded in the concrete body. The reinforcing bar includes a lower rod-shaped portion embedded between the beam main bars inside the concrete body and above the substantially horizontal portion of the lower end of the stirrup body, and extending substantially parallel to the beam main bars; an upper rod-shaped portion disposed above the concrete body and extending substantially parallel to the lower rod-shaped portion; A beam bottom member characterized by having a connecting portion that connects the lower rod portion and the upper rod portion.

2. 2. The beam bottom member according to claim 1, wherein the upper surface of the concrete body is formed with projections and recesses.

3. Further, a substantially U-shaped second reinforcing bar is provided, the second reinforcing bar being partially embedded in the concrete body and engaged with the beam main reinforcing bar, The second reinforcing bar includes a rod-shaped horizontal portion disposed on the lower surface of the beam main reinforcing bar, The beam bottom member according to claim 1 or 2, further comprising: a rod-shaped vertical portion extending upward from both ends of the horizontal portion.

4. A method for constructing a beam using the beam bottom member according to claim 1 or 2, comprising the steps of: a step of placing a resin sheathing on the beam bottom member on the ground, placing an aluminum formwork clamp on the outer surface of the sheathing, and temporarily fixing a lower end of the formwork clamp to a side end surface of the beam bottom member with a fixing metal fitting; Lifting the beam bottom member and placing it in a predetermined position; A step of placing reinforcement on the beam bottom member and pouring concrete; and removing the fixing hardware and the formwork retainer and the sheathing.

5. A beam construction method as described in claim 4, characterized in that in the step of lifting and positioning the beam bottom member, a precast concrete deck is placed adjacent to the beam bottom member, and a second fixing hardware is attached to the underside of the deck to temporarily fix the upper end of the formwork retainer.

Citation Information

Patent Citations

  • Construction of building

    JP1986126272A

  • Precast member

    JP1997078690A

  • Concrete form and production method thereof

    JP1997268702A

  • Beam for hybrid-structure frame

    JP2002364072A

  • Substrate for concrete form panel

    JP2006118222A