Reinforcement method for reinforced concrete members
The method optimizes reinforcement by converting reinforcement diagrams into non-overlapping, prefabricated elements with customized lengths and shapes, addressing labor-intensive and error-prone manual handling, enhancing efficiency and accuracy in reinforced concrete construction.
Patent Information
- Application Number
- JP2022518329
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Priority Date
- 2019-09-19
- Filing Date
- 2020-08-24
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2040-08-24
AI Technical Summary
Existing reinforcement methods for reinforced concrete members require manual handling and connection of reinforcing bars, which are time-consuming, labor-intensive, and prone to errors, especially in labor-shortage situations, and do not account for unique site conditions.
A method involving the computational conversion of reinforcement diagrams into modified arrangements with non-overlapping, arbitrarily long reinforcing bars, allowing for prefabricated elements with customized lengths, shapes, and installation orders, minimizing manual labor and reducing errors through optimized material use and prefabricated reinforcement elements.
Significantly reduces installation time and error rates by using prefabricated reinforcement elements tailored to specific site conditions, ensuring efficient and accurate reinforcement without manual handling, particularly beneficial for BIM components using the IFC format.
Smart Images

Figure 0007590421000001 
Figure 0007590421000002 
Figure 0007590421000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a method for the individual production of reinforcements for reinforced concrete components made of prefabricated reinforcing elements. [Background technology]
[0002] Typically, structural engineers design reinforcement diagrams for reinforced concrete members, which are optimized for steel quantities and product neutral and are often electronically rendered in 3D using a round bar module in a CAD program. These diagrams are used to fabricate the reinforcement of the reinforced concrete members on-site or in a precast factory, and to manufacture the reinforced concrete members. These diagrams include the location and quantity of rebars to be laid in the foundations on the top and bottom planes, as well as other reinforcing elements such as spacers, hooks, bent bars, cages, etc. that are placed between them. These already electronically rendered 3D diagrams are often converted into 2D drawings and printed on paper for use.
[0003] On site, the rebars are laid manually, cut and bent individually, and then manually connected with cable ties based on the rebar arrangement plan. This work is tedious, time-consuming, uneconomical, and prone to errors, especially in the face of a growing labor shortage. Therefore, to realize the rebar arrangement plan, it is generally desirable to use standardized reinforcing elements, for example in the form of concrete reinforcing mats, welded wire mesh, mesh cages, etc., which can be prefabricated and stored, and thus quickly used on the construction site.
[0004] The applicant is also familiar with individual reinforcing elements in the form of uniaxial rolled rebar mesh, which consists of parallel bars connected at several points along their length by static, non-actuating straps, resulting in a roll that can be manufactured, shipped, moved, and simply unrolled at its destination. Summary of the Invention [Problem to be solved by the invention]
[0005] The drawback of this method is that the individual conditions at each construction site cannot be adequately recorded, so manual joining of the rebars is still often required.
[0006] SUMMARY OF THE PRESENT EMBODIMENT It is therefore an object of the present invention to avoid the above mentioned drawbacks. [Means for solving the problem]
[0007] The above object is achieved by a method for individually manufacturing reinforcements of reinforced concrete members, mainly consisting of prefabricated reinforcement elements, comprising the steps of: reading a first reinforcement drawing of a reinforced concrete member based on reinforcing bars with a planar foundation reinforcement; converting the planar foundation reinforcement into a modified foundation reinforcement with reinforcing bars without length restrictions, so that the reinforcing bars do not overlap in the foundation reinforcement; To create individual reinforcement diagrams, Individually modify and update rebars with regard to number, shape, length, diameter, position and steel type. Place The method includes at least a step of calculating a plurality of individual reinforcement elements from the revised foundation reinforcement drawing and the first reinforcement drawing by specifying a construction order.
[0008] The conversion process according to the invention is carried out through a first step of computationally determining the corrective foundation reinforcement of the member. In this step, the reinforcing bars provided by the designer are converted into reinforcing bars that run continuously from one side of the reinforced concrete member to the other side. Thus, the corrective foundation reinforcement of each reinforcing layer of the reinforced concrete member has parallel reinforcing bars of any length without overlaps. Thus, According to the present invention Whether or not it is actually possible to obtain such extremely long rebars, Rebar It is possible to select any length. In this case, the length between the two foundation reinforcements is In Regarding other reinforcement parts of the first reinforcement drawing, the first reinforcement drawing was changed. figure, Next Step in, From this revised foundation reinforcement and other reinforcement parts of the first reinforcement drawing, several individual reinforcement elements are calculated. Therefore, According to the present invention, Target The number, shape, length, diameter, position, and steel quality of the rebars Regarding The order of installation is specified. Fixed Or Additional weld points orIt may differ from that of the first reinforcing bar arrangement plan in that other welding points are provided, and other reinforcing components may be included if this makes installation easier and faster.
[0009] The method according to the invention, although more material is spent, very advantageously increases the simplicity of the installation of the reinforcement, in particular because the method determines structurally unobstructed areas that are easy to reinforce, provides these areas with reinforcing elements that can be installed easily, quickly and as simply as possible, and, if necessary, extends the obstructed areas with further reinforcing elements, resulting in an increased use of material. The method is particularly advantageous in that it can be used in so-called BIM (Building Information Modeling) components, i.e. components that represent buildings or their parts in digital form. This is particularly true when the IFC format is used. In other words, according to the invention, a design-optimized reinforcement measure is calculated from a quantity-optimized reinforcement measure. A design-optimized reinforcement measure is realized in particular by reinforcements that are individually manufactured for the construction site.
[0010] The method according to the invention may further comprise the steps of minimizing the number of reinforcing elements of the individual reinforcing diagrams, determining the individual reinforcing elements with respect to the type and arrangement of the reinforcing bars of the individual reinforcing diagrams, generating a machine data set for manufacturing at least one calculated individual reinforcing element, transferring the machine data set to a manufacturing machine and manufacturing at least one individual reinforcing element, and manufacturing the reinforcement individually on the construction site, all steps of the method being preferably performed with computer support, if reasonably possible. The last three steps are not mandatory for the method. Very advantageously, there is no need to lay the reinforcing bars individually by hand and to connect them with tie wires, and according to the invention it is possible to mainly or exclusively use prefabricated reinforcing elements that are individually calculated for each construction site instead of the original multiple reinforcing bars. This significantly reduces the working time required for the manufacturing of the reinforcement on site. Also, the number of parts to be attached and connected is significantly reduced, which is very advantageous, so that the probability of installation errors is also minimized. This process of the method optimizes the size and shape of the individual reinforcing elements and minimizes their quantity. This further reduces the working time required for connecting the individual reinforcing elements.
[0011] The method preferably also performs a contact check of the rebars to ensure that variations in quantity, shape, length, location and installation sequence do not cause problems.
[0012] The method involves the selection of the type of reinforcing element to be manufactured or used from uniaxial reinforcing mesh, in particular rolled uniaxial reinforcing mesh, biaxial reinforcing mesh, edge cage, connection cage, welded reinforcing cage, and individual reinforcing bars. Panel-shaped reinforcement can therefore also be used. This is a static reinforcement measure in which several reinforcing bars of different diameters, lengths and spacing are combined into a plate-shaped concrete casing. In addition, spacers or other additional reinforcement can be incorporated between the two layers of foundation reinforcement, but this is not mandatory. In the case of uniaxial reinforcing mesh, the upper and lower foundation reinforcement each have two layers of mesh oriented perpendicular to each other. Biaxial or drawn mats are used when they can be used advantageously at each construction site. Edge cages and connection cages are used to connect individual reinforcements and to connect panel reinforcement with wall reinforcement, and they save a considerable amount of time compared to the individual laying and bending of connecting reinforcing bars. However, these cages are not standardized according to the present invention, but are calculated and manufactured individually for each construction site and are optimally adapted to the local connection and surrounding conditions. Additional reinforcements, according to the invention, are in particular spacers, but also include steel-optimized rebars, which cannot be changed in the original calculations.
[0013] The method according to the invention solves the overlap and collision problems, particularly by modifying them as follows:
[0014] the above The modifications include, in particular, the addition of sacrificial or auxiliary material with regard to the presence, arrangement, length and diameter of at least one reinforcing bar. The modified foundation reinforcement for the production of individual reinforcing elements is modified according to the invention in particular by the extension of at least one reinforcing bar compared to the original reinforcement plan, by the addition of sacrificial or purely structural auxiliary material. Sacrificial material in this sense refers to material that is not provided in the calculation of the original reinforcement plan. auxiliaryThis refers to the material. However, the addition of such sacrificial material should in principle be avoided as it increases the costs, but it is particularly advantageous in areas where the load is not mainly static and where welding is not permitted and therefore the ends of the reinforcing bars cannot be connected with straps. Also, according to the invention, in order to allow the attachment to at least two assembly elements without the addition of a separate connecting reinforcing bar, an extension of the reinforcing bar is provided so that the reinforcing mesh can be joined with an edge cage or a connection cage or so that the reinforcing bar can be connected to the next assembly belt or the next assembly bar. Also, such reinforcing elements have an extension that must ensure a sufficient overlap at the reinforcing joint behind the obstacle to be overcome. Alternatively, such an extension reinforcing element is an extension itself, i.e. two separate reinforcing elements, such as uniaxial roll mats, which cannot be deployed together because they are separated by an obstacle, are connected by overlapping. This extension of the reinforcing bar according to the invention is more expensive than the initially calculated needs for the structure, but the result is a simple and quick installation, which allows a significant time saving during the reinforcement construction. This is particularly advantageous since the labor costs make up a large proportion of the total cost of the reinforcement work.
[0015] According to the invention, it is envisaged to provide an overlap at adjacent joints of the reinforcing elements with the extended rebars of the reinforcing elements. Thus, according to the invention, it is possible to offset the rebars of the reinforcing elements with respect to the rebars of two adjacent reinforcing elements, so that the position of the offset reinforcing elements deviates from the calculated corrected foundation reinforcement. In particular here, an offset is provided by the diameter of the reinforcing bars, so that two adjacent meshes (reinforcing elements) can be laid overlapping without the reinforcing bars coming into contact with each other. In this connection, it is also according to the invention that, when producing a reinforcing element in the form of a uniaxially rolled reinforcing mesh, one or more strips lying in the subsequent overlap area as mounting elements for the reinforcing bars of the mesh are moved along the longitudinal axis of the reinforcing bars, so that collisions in the height direction are avoided and the plane of the reinforcing layer is maintained. The correction also includes automatic displacements of the reinforcing bars due to the machine specifications in the production process, for example due to the production plant minimizing the spacing of the reinforcing bars.
[0016] In addition to the above mentioned modifications, overlapping reinforcing elements may also be calculated and created additionally, in particular in the form of correspondingly short axially overlapping meshes from parallel reinforcing bars, which are designed to be connected to fastening elements and are arranged in an overlapping manner between the respective adjacent reinforcing meshes, the fastening elements being statically non-active straps in the case of uniaxial reinforcing meshes and statically active or non-active fastening bars in the case of uniaxial or biaxial meshes.
[0017] According to the invention, two or more reinforcing elements can also be manufactured and transported connected with a continuous fastening element, and the connected reinforcing elements can be installed on site by cutting the fastening element in the corresponding areas, which are specifically marked. death Unless there is, it will not be separated.
[0018] The method according to the invention envisages moving reinforcing bars and / or adding reinforcing bars, possibly by reducing the diameter of the reinforcing bars in question, especially in the case of reinforcing elements forming the upper layer of the foundation reinforcement, which are too far away for workers to walk safely, for example when concreting the reinforced concrete member. In this embodiment too, the basic principles of the invention apply, simplifying and accelerating the installation of reinforcing elements with additional material, by creating an installation optimized design from a quantity optimized design, which is preferably done electronically.
[0019] In one embodiment of the method according to the invention, it is envisaged that the rebars, which have been extended in the region of the sacrificial material, are connected to possibly also extended attachment elements, such as straps or bars. If the original ends of the extended rebars are in a weld-prohibited region, they cannot be welded to the connecting attachment straps in this region, which would result in the disadvantage that the ends of the rebars are not connected and would become loose. By extending the rebars by a length that is purely structurally and statically insignificant, welding is possible in this region, which allows the installation of attachment elements that connect the rebars together, thus stabilising their position.
[0020] A further development of the method envisages the creation of additional rebars for the short end regions of the reinforcing rebar mesh. That is, if there is a recess in the end region of the reinforcing mesh, the rebar cut by the recess is reinforced with an additional rebar whose end adjacent to the recess is calculated. This ensures the transmission of compressive and tensile forces between the short rebars and the reinforcing bars in the recess region, without preventing the simple unfolding or laying of the reinforcing mesh beyond the recess. This again means a significant reduction in construction time, which in terms of process optimization is outweighed by the fact that more material is used.
[0021] According to the invention, the recesses of the individual reinforcing elements are also calculated and additional reinforcing bars are inserted individually by computer for the omitted reinforcing bars in the recessed areas. The added reinforcing bars are extended as necessary so that they can be attached to the two attachment elements. Recesses may be necessary due to holes or recesses protruding perpendicularly to the reinforcing layer or wall connections. In such places, only the attachment straps are deployed and the added reinforcing bars according to the invention ensure that the forces are transmitted around the obstacles. Although additional material is required, the construction time can be significantly reduced.
[0022] The method according to the invention also envisages calculating the length of the reinforcing bars so that the reinforcing mesh and the edge cage can be connected by overlapping the reinforcing bars of the reinforcing mesh with the edge cage, thus allowing the connection between the reinforcing mesh and the edge cage without the need for additional reinforcing bars.
[0023] According to the present invention, when creating a reinforcing element from a foundation reinforcement by calculation, , supplement Against strong elements Reinforcing bars Individual To Follow up Add It is also possible The separately added rebar is not or cannot be incorporated into the reinforcing element. In this way, prefabrication of reinforcement elements is possible even when, for production or technical reasons regarding the reinforcement, it is not possible to incorporate reinforcing bars into the prefabricated reinforcement elements. By manually adding the corresponding reinforcing bars, the necessary reinforcement from a structural point of view can be ensured.
[0024] The method according to the invention also provides for fixing the type, shape, position or design of the individual reinforcing elements when they are manufactured from the corrected foundation reinforcement. The actual situation at the construction site may differ from the pre-calculated one. As a result, the need arises to modify parts of the reinforcement, leading to new manufacture of reinforcing elements from the corrected foundation reinforcement and further reinforcement of the first reinforcement drawing, whereas the fixed reinforcing elements cannot be changed. Thus, since only local modifications are required, modifications of many reinforcing elements can be avoided, which is very advantageous. [Brief description of the drawings]
[0025] An embodiment of the present invention will now be described with reference to several figures.
[0026] [Figure 1] FIG. 2 shows in detail in three sub-views a), b) and c) a schematic reinforcement diagram before and after application of the method according to the invention. [Figure 2a] FIG. 13 is a detailed view of the redesigned individual reinforcement elements. [Figure 2b] FIG. 13 is a detailed view of the redesigned individual reinforcement elements. [Figure 2c] FIG. 13 is a detailed view of the redesigned individual reinforcement elements. [Figure 2d] FIG. 13 is a detailed view of the redesigned individual reinforcement elements. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0027] FIG. 1 shows, in three partial views, a schematic reinforcement diagram of a component before and after application of the method according to the invention.
[0028] Partial drawing a) shows the original, preferably quantity-optimized, product-neutral drawing of a structural engineer's external reinforced concrete structure 1, which has overlaps 6 in all rows based on the reinforcing bars 3, which are arranged arbitrarily depending on the length of the underlying reinforcing bars 2 used. Spacers and other reinforcements below or above the drawing are not shown. Only one layer of planar foundation reinforcement is shown, which is often modified by the method according to the invention to a greater extent than the above-mentioned reinforcements not shown.
[0029] Partial drawing b) shows the corrected foundation reinforcement calculated from the original first reinforcement drawing in the first step of the method according to the invention, and the length is zero so that the corrected foundation reinforcement without any overlap is calculated. system The maximum rebar of 3 is used in the calculation.
[0030] Partial drawing c) shows diagrammatically several reinforcing elements, in this case two reinforcing elements 4, 4', which are calculated individually for each construction site and produced from the modified foundation reinforcement via the method according to the invention. According to the invention, this results in a greater amount of material being spent, but makes the installation easier. Naturally, in practice, considerably more reinforcing elements are calculated than the two reinforcing elements 4, 4' shown.
[0031] The reinforcing elements 4, 4' thus calculated are each fitted with reinforcing bars 3 spaced at regular intervals and connected by fastening elements 5. . Supplementary Auxiliary material 7 is inserted in the end region of another reinforcing element 4' adjacent to the strong element 4 in the form of an extension of the reinforcing bar 3. By doing , an overlapping portion 6 of the reinforcing bars of the two reinforcing elements 4 and 4' is formed. Even if they are separated, sufficient static effect can be obtained. The mounting straps 5 ensure a stable spacing of the reinforcing bars 3 of the reinforcing elements 4, 4' and at the same time prevent the ends of the reinforcing bars 3 from spreading. ,beside Orientation or Vertical Not desirable Force is generated thing It can also be seen that the strap 5' of the first reinforcing element 4 is located away from the end region along the longitudinal axis of the reinforcing bar 3 in order to prevent the two reinforcing elements 4, 4' from stacking vertically. Thus, in the illustrated example, the laying sequence is also set up such that the reinforcing element 4' is deployed first, and then the reinforcing elements 4 are deployed one on top of the other. Also, the reinforcing bars 3 of the reinforcing element 4 are offset from the reinforcing bars 3 of the reinforcing element 4' by a reinforcing bar diameter, so that they do not come into a butting situation. Iko It can be seen that such a procedure is automatically carried out by the method of the present invention. Furthermore, it can be seen that the reinforcing bar 3 of the reinforcing element 4 is extended to form an overlapping portion 6. This overlapping portion is , there were many "disorderly" dispersed junctions rather than continuous, ordered junctions. The original reinforcement drawing shown in part a) does not include It was .
[0032] Figure 2 shows the detailed views 2a) to 2d) showing the details of the redesigned individual reinforcing elements. In this redesign, specifically, unobstructed spatial areas are identified from the modified foundation reinforcement 2, appropriate reinforcing elements are manufactured for the identified areas, and the manufactured reinforcing elements are deployed or laid without being disturbed. On the other hand, in the structurally disturbed areas, reinforcement is additionally manufactured and supplemented by special laying.
[0033] Fig. 2a shows diagrammatically an exemplary reinforcement diagram for a reinforced concrete part 1, produced with the method according to the invention. The reinforcement is realized on the basis of a reinforcing element 4 in the form of a uniaxial reinforcing mesh, in which the reinforcing bars 3 are arranged at intervals and connected by means of fastening straps 5. Taking into account the interference zone 9, the freedom of the reinforcing bars 3 is Edge To shorten it, the straps 5' are moved from their original relative positions shown in dashed lines to the positions shown in solid lines, thereby ensuring the laying of the rebars 3. By shortening the top two rebars 3, the area obstructed by the area 9 remains, and the deployability is also maintained.
[0034] 2b shows diagrammatically another reinforcing element 4 with a mounting bar 5 and a reinforcing bar 3. The free end 10 of the short reinforcing bar 3 is extended by an auxiliary material 7 so that it can be attached to an adjacent mounting bar 5 and thus to at least two mounting elements 5.
[0035] Fig. 2c shows a part of a prefabricated rolled reinforcing element 4, which is provided for installation in places where welding is not permitted due to non-static loading alone and where the welded reinforcing bar 3 may not be evaluated as valid for structural analysis from the weld point. The weld line 11 crosses the reinforcing bar 3 and therefore terminates there according to the modified foundation reinforcement. To keep the free end 10 ready for laying, an additional material 7, shown in dashed lines, is added so that it can be welded to the nearest attachment strap 5. However, this weld is not statically relevant as it does not affect the statically active area of the reinforcing bar 3, shown in solid lines. The attachment element 5 is therefore extended to this area as well.
[0036] Figure 2d shows the structure of the prefabricated reinforcement element 4 part The reinforcing element is shown diagrammatically in FIG. On the surface , has a recess 12, e.g. a ceiling hole. In order to be able to lay a reinforcing element 4 above this disturbed area, the reinforcing bar 3 is shortened in that area. According to the invention, in order to transmit the forces in the area of the recess 12, auxiliary material 7 in the form of an additional reinforcing bar 3' is added, which is further extended for fastening to the mounting strap 5. Thus, according to the invention, by adding the auxiliary material 7, reinforcement is again possible on the basis of the prefabricated reinforcing element 4.
[0037] Not shown are smaller diameter bars spaced closer together, or larger diameter bars spaced farther apart, but these adjustments, as well as the quality of the steel, are within the scope of the present invention. [Explanation of symbols]
[0038] 1. Reinforced concrete members / structures 2 Modified basic reinforcement 3. Steel Bars 3' Additional rebar 4 Reinforcing elements 4' Reinforcing elements 5 Mounting elements / mounting straps / mounting rods 5' Strap 6 Overlap 7 Auxiliary materials 8 Periphery 9 Disturbance area 10 free end 11 Welding line 12 Recess
Claims
1. A method for individually manufacturing reinforcements for reinforced concrete components (1) consisting mainly of prefabricated reinforcement elements (4), said method comprising the steps of: A step of reading a first reinforcement drawing of a reinforced concrete member (1) based on a reinforcing bar (3) having a planar foundation reinforcement; A step of converting the foundation reinforcement of the plane into a modified foundation reinforcement (2) having rebars with no length limit so that the rebars do not overlap within the foundation reinforcement; Calculating a plurality of individual reinforcing elements (4) from the modified foundation reinforcement (2) and the first reinforcement plan by individually modifying the reinforcing bars (3) in terms of number, shape, length, diameter, position, steel type, and specifying the laying order in order to create an individual reinforcement plan; The method according to claim 1, further comprising:
2. 2. The method according to claim 1, further comprising the step of minimizing the number of reinforcing elements (4) of the individual reinforcement plans.
3. The method according to claim 1, further comprising a step of determining the individual reinforcing elements (4) with respect to the type and arrangement of the reinforcing bars (3) of the individual reinforcement diagram.
4. The method according to claim 1, further comprising a step of generating a machine data set for manufacturing at least one calculated individual reinforcing element (4).
5. The method according to claim 4, further comprising the step of transferring the machine data set to a manufacturing machine and manufacturing at least one of the individual reinforcing elements (4).
6. The method of claim 1, further comprising a step of manufacturing the reinforcement individually at a construction site.
7. 6. The method according to claim 1, wherein the individual reinforcing elements (4) are selected from uniaxially reinforcing meshes, in particular rolled uniaxially reinforcing steel meshes, biaxially reinforcing meshes, edge cages, connection cages, welded reinforcing cages and individual reinforcing bars.
8. 8. The method according to claim 1, wherein at least one reinforcing element (4) is modified in comparison with the modified foundation reinforcement with respect to the presence, arrangement, length and diameter of at least one reinforcing bar (3).
9. A method according to any one of claims 1 to 7, characterized in that at least one reinforcing element (4) is modified in comparison with the modified foundation reinforcement by adding sacrificial or auxiliary material (7) in terms of the presence, arrangement, length and diameter of at least one reinforcing bar (3), wherein the auxiliary material (7) is an extension of the reinforcing bar (3) and the sacrificial material is the auxiliary material (7) that is not provided in the calculation of the first reinforcement drawing.
10. 10. Method according to any one of the preceding claims, characterized in that the arrangement of the fastening elements (5) of the reinforcing element (4) is changed within the reinforcing element (4).
11. 11. The method according to claim 1, wherein the reading of the first reinforcement diagram is performed electronically, which is in particular a quantity-optimized and product-neutral first reinforcement diagram.
12. A method according to any one of claims 1 to 11, characterized in that the reinforcing element (4) is a uniaxially reinforcing mesh and an additional reinforcing bar (3') is inserted by a computer into an end region of the reinforcing mesh adjacent to a recess (12) provided in the rolled uniaxially reinforcing mesh.
13. A method according to any one of claims 1 to 12, characterized in that the reinforcing element (4) is a reinforcing mesh and an edge cage, and the reinforcing mesh and the edge cage are connected during assembly so that the reinforcing bars (3) of the reinforcing mesh overlap the edge cage.
14. A method according to any one of claims 1 to 13, characterized in that the reinforcing element (4) is a reinforcing mesh and the mounting elements (5) of the reinforcing mesh are separated during assembly at the marked locations.
15. A method according to any one of claims 1 to 14, characterized in that additional reinforcing bars which cannot be incorporated into prefabricated reinforcing elements (4) are added to the reinforcing bars of the modified foundation reinforcement (2).
Citation Information
Patent Citations
Prefabricated wall body steel reinforcement data processing method and apparatus
CN108427814A
Method of optimizing the concrete reinforcement arrangement and orientation in concrete
EP3421680A1
Arrangement method of slab bar
JP1994057882A
Stirrup design support device
JP1994248800A
Calculation system for reinforcement
JP2002364120A