Battery monitoring device and program

The battery monitoring device calculates SOC in lithium ion batteries by utilizing impedance value changes and alternating current to overcome integration errors and temperature dependence, ensuring accurate SOC determination even in plateau regions.

JP7593089B2Active Publication Date: 2024-12-03DENSO CORP
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
JP2020209592
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2020-12-17
Publication Date
2024-12-03
Estimated Expiration
2040-12-17

AI Technical Summary

Technical Problem

Existing methods for calculating the state of charge (SOC) of lithium ion batteries using the SOC-OCV characteristic are inaccurate due to integration errors and temperature dependence, especially in plateau regions where open circuit voltage (OCV) changes minimally with SOC changes.

Method used

A battery monitoring device that calculates SOC by monitoring impedance value changes during charging and discharging, using predetermined capacities and threshold values to determine storage capacity without relying on SOC-OCV characteristics, and incorporates an alternating current to enhance impedance measurement accuracy.

Benefits of technology

Accurately calculates SOC in lithium ion batteries, including plateau regions, by correcting integration errors and minimizing noise influence, while maintaining precision and adaptability to temperature variations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007593089000001
    Figure 0007593089000001
  • Figure 0007593089000002
    Figure 0007593089000002
  • Figure 0007593089000003
    Figure 0007593089000003
Patent Text Reader

Abstract

To provide a battery monitor that can properly calculate the power storage capacity of a secondary battery without using an SOC-OCV characteristic.SOLUTION: The present invention includes: an acquisition unit 50 applied to a secondary battery 40 where a change is generated in a reaction heat amount of a predetermined capacity when a change is generated in the power storage capacity in association with conduction, the acquisition unit 50 acquiring a change of the impedance value of the secondary battery at the time of conduction; and a capacity determination unit 50 for determining whether the power storage capacity of the secondary battery is the predetermined capacity, on the basis of the change of the impedance value acquired by the acquisition unit.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a battery monitoring device for a secondary battery. and Program Regarding. [Background technology]

[0002] In recent years, lithium-ion batteries have been attracting attention as lightweight, high-energy-density secondary batteries. Some lithium-ion batteries have a plateau region, where the change in open circuit voltage (OCV) associated with the change in state of charge (SOC), which indicates the charge state of the battery, is small. In the plateau region, it is difficult to calculate the SOC of a secondary battery using the SOC-OCV characteristic, which indicates the correlation between SOC and open circuit voltage (OCV).

[0003] As a technique for calculating SOC without using the SOC-OCV characteristic, a technique for calculating SOC by integrating the current flowing into and out of a secondary battery is known. However, when calculating SOC by current integration, if the current integration period is extended, an integration error accumulates, causing a problem of reduced accuracy in SOC calculation. Therefore, in Patent Document 1, the SOC of a secondary battery is calculated based on the voltage change rate, which is the value obtained by dividing the voltage change per unit time of the secondary battery during charging or discharging by the current capacity flowing into and out of the secondary battery during that time. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] International Publication No. 2017 / 010475 Summary of the Invention [Problem to be solved by the invention]

[0005] The voltage change rate during current flow is highly dependent on the temperature of the secondary battery. Therefore, when calculating the SOC based on the voltage change rate during current flow, the SOC cannot be calculated properly due to the temperature change of the secondary battery during current flow. There is a demand for technology that can properly calculate the SOC of a secondary battery without using the SOC-OCV characteristics.

[0006] The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a battery monitoring device that can properly calculate the storage capacity of a secondary battery without using the SOC-OCV characteristic. and Program The purpose of this invention is to provide [Means for solving the problem]

[0007] A first means for solving the above problem is applied to a secondary battery in which a change in reaction heat quantity occurs at a predetermined capacity when the storage capacity changes with the passage of current, and includes an acquisition unit that acquires a change in impedance value of the secondary battery when current is passed through, and a capacity determination unit that determines that the storage capacity of the secondary battery is the predetermined capacity based on the change in impedance value acquired by the acquisition unit.

[0008] In a secondary battery in which a change in the amount of heat of reaction occurs at a given capacity as current is passed through it, the temperature of the secondary battery changes with the change in the amount of heat of reaction at the given capacity. In a secondary battery, there is a correlation between temperature and impedance value, and when the temperature of the secondary battery changes, the impedance value of the secondary battery changes. In other words, in the above secondary battery, the impedance value of the secondary battery changes at a given capacity. The present inventors have focused on this point and discovered a method for calculating the storage capacity.

[0009] Specifically, in the above configuration, the impedance value change of the secondary battery is acquired during energization, and based on this impedance value change, it is determined that the storage capacity of the secondary battery is a predetermined capacity. The impedance value change at the predetermined capacity of the secondary battery can be used to calculate the storage capacity of the secondary battery, and the storage capacity of the secondary battery can be properly calculated without using the SOC-OCV characteristic.

[0010] In the second means, the capacity determination unit determines that the storage capacity of the secondary battery is the predetermined capacity when an absolute value of a time change amount of the impedance value change is greater than a predetermined threshold value.

[0011] Even if the impedance value of the secondary battery changes, if the change is small, there is a high possibility that the impedance value change is due to noise or the like. In the above configuration, if the absolute value of the time change in the impedance value change is greater than a predetermined threshold, it is determined that the storage capacity of the secondary battery is a predetermined capacity. Therefore, the influence of noise and the like can be suppressed and the storage capacity of the secondary battery can be calculated appropriately.

[0012] The third means is applied to a secondary battery having a first capacity and a second capacity as the specified capacity, and during charging, the absolute value of the impedance value change is larger on the high capacity side of the first capacity than on the low capacity side, and smaller on the high capacity side of the second capacity than on the low capacity side, and during discharging, the absolute value of the impedance value change is larger on the low capacity side of the first capacity than on the high capacity side, and smaller on the low capacity side of the second capacity than on the high capacity side, and the capacity determination unit determines that the storage capacity of the secondary battery is the first capacity when the impedance value change decreases with current flow, and determines that the storage capacity of the secondary battery is the second capacity when the impedance value change increases with current flow.

[0013] Some secondary batteries have a plurality of predetermined capacities. In this case, even if it is determined that the battery has a predetermined capacity based on the impedance value change, it is not possible to determine which of the plurality of predetermined capacities the battery has. In this respect, in this embodiment, the battery has a first capacity and a second capacity as the predetermined capacity, and during charging, the absolute value of the impedance value change is larger on the high capacity side of the first capacity than on the low capacity side, and smaller on the high capacity side of the second capacity than on the low capacity side. Also, during discharging, the absolute value of the impedance value change is larger on the low capacity side of the first capacity than on the high capacity side, and smaller on the low capacity side of the second capacity than on the high capacity side. Therefore, in the first capacity, the impedance value change decreases with current flow, and in the second capacity, the impedance value change increases with current flow. Therefore, in a secondary battery having a plurality of predetermined capacities, it is possible to determine whether the predetermined capacity is the first capacity or the second capacity by using the difference in the manner of the impedance value change.

[0014] The fourth means includes a calculated capacity calculation unit that calculates the storage capacity of the secondary battery as a calculated capacity by integrating the current flowing into and out of the secondary battery, and when the capacity determination unit determines that the storage capacity of the secondary battery is the specified capacity, the calculated capacity calculation unit corrects the calculated capacity using the specified capacity.

[0015] In the calculation of the storage capacity by current integration, if the current integration period is extended, an integration error accumulates and the calculation accuracy of the calculated capacity decreases. In this respect, in the above configuration, the calculated capacity is corrected using a predetermined capacity, so that the integration error of the calculated capacity can be reset.

[0016] The fifth means includes an AC generating unit that generates a predetermined AC current to be superimposed on the current flowing into and out of the secondary battery, and the acquisition unit acquires the change in impedance value when the AC current is generated by the AC generating unit.

[0017] When the current flowing into and out of the secondary battery changes, the impedance value of the secondary battery changes, and the impedance value of the secondary battery is acquired when this current changes. However, when the change in the current flowing into and out of the secondary battery is small, for example when the secondary battery is being charged with a constant current, the impedance value of the secondary battery cannot be acquired, and it cannot be determined that the storage capacity of the secondary battery is a predetermined capacity. In this regard, the above configuration includes an AC current generating unit that superimposes an AC current on the current flowing into and out of the secondary battery. By changing the current flowing into and out of the secondary battery using an AC current, the storage capacity of the secondary battery can be properly calculated even when the change in the current before superimposition is small, and it can be determined that the storage capacity of the secondary battery is a predetermined capacity.

[0018] The sixth means includes a full charge determination unit which determines when the secondary battery is fully charged, and a discharge capacity calculation unit which calculates a discharge capacity of the secondary battery using an integrated amount of current flowing into and out of the secondary battery between a first timing when the capacity determination unit determines that the storage capacity of the secondary battery is the specified capacity and a second timing when the full charge determination unit determines that the secondary battery is in a fully charged state, and the specified capacity.

[0019] In a secondary battery, the discharge capacity, which indicates the deterioration state of the secondary battery, decreases due to deterioration. On the other hand, the predetermined capacity is an amount that does not change due to deterioration of the secondary battery. In the above configuration, the discharge capacity of the secondary battery can be calculated appropriately by calculating the discharge capacity using the predetermined capacity that does not change due to deterioration of the secondary battery.

[0020] In a seventh aspect, the secondary battery has a plateau region in which the change in the open circuit voltage of the secondary battery associated with the change in the charge storage capacity of the secondary battery is small, and the predetermined capacity exists within the plateau region.

[0021] In a secondary battery having a plateau region, it is difficult to calculate the storage capacity using the SOC-OCV characteristics in the plateau region. In this respect, in the above configuration, since there is a predetermined capacity at which a change in the amount of heat of reaction occurs in the plateau region, the storage capacity of the secondary battery can be properly calculated in the plateau region using this predetermined capacity. [Brief description of the drawings]

[0022] [Figure 1] 1 is an overall configuration diagram of a battery control device according to a first embodiment. [Diagram 2] FIG. 4 is a diagram showing the relationship between storage capacity and voltage change amount. [Diagram 3] 4 is a flowchart of a determination process according to the first embodiment. [Figure 4] 4 is a time chart showing an example of a determination process according to the first embodiment. [Diagram 5] 6 is a time chart showing another example of the determination process in the first embodiment. [Figure 6] FIG. 11 is an overall configuration diagram of a battery control device according to a second embodiment. [Figure 7] FIG. [Figure 8] 10 is a flowchart of a determination process according to the second embodiment. [Figure 9] FIG. 4 is a graph showing a change in discharge capacity due to deterioration of a battery. [Figure 10] 13 is a flowchart of a determination process according to the third embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0023] (First embodiment) Hereinafter, a first embodiment in which a battery monitoring device according to the present invention is applied to an on-board battery control device 100 will be described with reference to the drawings.

[0024] As shown in Fig. 1, a battery control device 100 according to this embodiment is a device that monitors the storage capacity and charge / discharge state of a battery 40. The battery 40 is a rechargeable storage battery (secondary battery), and more specifically, is a battery pack in which a plurality of lithium ion storage batteries 41 are connected in series. In this embodiment, the lithium ion storage battery 41 uses lithium iron phosphate as the positive electrode active material and graphite as the negative electrode active material.

[0025] The battery 40 is connected to the rotating electric machine 10 via the inverter 20. The rotating electric machine 10 inputs and outputs electric power to and from the battery 40, and during power running, it provides a propulsive force to the vehicle using electric power supplied from the battery 40, and during regeneration, it generates electric power using the deceleration energy of the vehicle and outputs the electric power to the battery 40.

[0026] The battery control device 100 includes a voltage sensor 30, a current sensor 31, first to fourth relay switches 32 to 35, and a BMU (Battery Management Unit) 50 as a battery monitoring device.

[0027] The voltage sensor 30 detects the terminal voltage of each of the lithium ion batteries 41 constituting the battery 40, and detects the battery voltage VB which is the sum of these terminal voltages. The current sensor 31 is provided on the connection line LC which connects the battery 40 and the inverter 20, and detects the magnitude and direction of the charge / discharge current IS which is the current flowing in and out of the battery 40. The detection values ​​of each sensor are input to the BMU 50.

[0028] The battery 40 is configured to be connectable to an off-vehicle charger 200 via first and second external charging terminals TA, TB. The off-vehicle charger 200 is, for example, a DC quick charger. When the off-vehicle charger 200 is connected to the first and second external charging terminals TA, TB, the battery 40 is constant-current charged or constant-voltage charged by high-voltage DC power input from the off-vehicle charger 200.

[0029] The first and second external charging terminals TA, TB are connected to the connection line LC via first and second charging paths LA, LB. Specifically, the first external charging terminal TA is connected to a first contact PA on the connection line LC between the positive terminal of the battery 40 and the inverter 20 via the first charging path LA. The second external charging terminal TB is connected to a second contact PB on the connection line LC between the negative terminal of the battery 40 and the inverter 20 via the second charging path LB.

[0030] The first relay switch 32 is provided between a first contact PA on the connection line LC and the inverter 20, and the second relay switch 33 is provided between a second contact PA on the connection line LC and the inverter 20. The first and second relay switches 32, 33 switch the connection state between the battery 40 and the rotating electric machine 10. The third relay switch 34 is provided on the first charging path LA, and the fourth relay switch 35 is provided on the second charging path LB. The third and fourth relay switches 34, 35 switch the connection state between the battery 40 and the off-vehicle charger 200.

[0031] The BMU 50 is a control device composed of a CPU, a ROM, a RAM, etc. The BMU 50 calculates the storage capacity of the battery 40 based on the detection values ​​input from each sensor. The BMU 50 calculates the discharge capacity indicating the deterioration state of the battery 40 based on the calculated storage capacity of the battery 40.

[0032] The BMU 50 is also connected to the first to fourth relay switches 32 to 35, and switches the connection states of the first to fourth relay switches 32 to 35 based on the power storage capacity of the battery 40. The BMU 50 is also communicatively connected to the cruise control ECU 70 via an in-vehicle network interface 51, and outputs a command to the cruise control ECU 70 to control the rotating electric machine 10 based on the power storage capacity of the battery 40. Based on the command from the BMU 50, the cruise control ECU 70 controls the inverter 20 so as to control the control amount of the rotating electric machine 10 in accordance with the command. The control amount is, for example, torque.

[0033] Incidentally, as a method for calculating the storage capacity of the battery 40, a method using the SOC-OCV characteristic that indicates the correlation between the SOC (State Of Charge) that indicates the storage state of the battery 40 and the open circuit voltage OCV is known. However, in this embodiment, the lithium ion storage battery 41 that constitutes the battery 40 uses lithium iron phosphate as the positive electrode active material and graphite as the negative electrode active material. In a storage battery using these active materials, the open circuit voltage OCV is stable over a wide range of SOC, and there is a region where the change in the open circuit voltage OCV with the change in SOC is small, that is, a plateau region PR. In the plateau region PR, it is difficult to calculate the SOC of the storage battery using the SOC-OCV characteristic and calculate the storage capacity.

[0034] As a technique for calculating the storage capacity of the battery 40 without using the SOC-OCV characteristics, a technique for calculating the storage capacity by integrating the charge / discharge current IS of the battery 40 is known. However, when calculating the storage capacity by integrating the current, a problem occurs in that an integration error accumulates over a long current integration period, reducing the calculation accuracy of the storage capacity.

[0035] In a storage battery, when the storage capacity changes with the passage of current, the reaction heat WR changes. The reaction heat WR is the amount of heat generated by the battery WB due to the passage of current minus the Joule heat WJ due to the impedance component of the battery, as shown in the following formula (1). The reaction heat WR is expressed as shown in the following formula (2) using the battery temperature TM, the charge / discharge current IS, and the voltage change ΔOCV, which is the amount of change in the open-circuit voltage OCV per unit temperature.

[0036] WB = WJ + WR (1) WR = TM × IS × ΔOCV (2) According to formula (2), the reaction heat WR is proportional to the voltage change ΔOCV. This voltage change ΔOCV has a value for each storage capacity of the storage battery, and some storage batteries have a voltage change ΔOCV that changes when the storage capacity changes. In such a storage battery, if the storage capacity changes, the reaction heat WR changes, and the temperature TM changes. In addition, in a storage battery, the temperature TM and the impedance value RA are correlated. Therefore, if the temperature TM of the storage battery changes, the impedance value RA of the storage battery changes.

[0037] In a storage battery, a predetermined capacity at which a relatively large voltage change amount ΔOCV occurs is determined in advance depending on the active material used, etc. FIG. 2 shows the relationship between the storage capacity and the voltage change amount ΔOCV in the battery 40 of this embodiment. As shown in FIG. 2, the battery 40 has a first capacity QA and a second capacity QB as the predetermined capacity, and when the storage capacity increases from the low capacity side to the first capacity QA, the voltage change amount ΔOCV increases rapidly, and when the storage capacity reaches the first capacity QA, the increase in the voltage change amount ΔOCV tends to saturate. Also, when the storage capacity increases from the low capacity side to the second capacity QB, the voltage change amount ΔOCV decreases rapidly, and when the storage capacity reaches the second capacity QB, the decrease in the voltage change amount ΔOCV tends to saturate.

[0038] In the first and second capacities QA and QB, the change in the voltage change amount ΔOCV is steep, so the change in the impedance value RA is large. The present inventors have focused on this point and found a method for calculating the storage capacity of the battery 40.

[0039] Specifically, the BMU 50 acquires an impedance value change HA of the battery 40 when the battery 40 is energized. The BMU 50 calculates an impedance value RA by dividing a change amount ΔVB of the battery voltage VB when the charge / discharge current IS changes by a change amount ΔIS of the charge / discharge current IS. Then, the BMU 50 calculates an impedance value change HA, which is a change amount of the impedance value RA per unit time. The BMU 50 performs a determination process to determine whether the storage capacity of the battery 40 is the first and second capacities QA and QB based on the impedance value change HA. According to the determination process, the storage capacity of the battery 40 can be calculated using the impedance value change HA in the first and second capacities QA and QB of the battery 40, and the storage capacity of the battery 40 can be properly calculated without using the SOC-OCV characteristic.

[0040] In the battery 40 of this embodiment, the first and second capacities QA and QB exist in the plateau region PR as shown in Figures 4 and 5. Therefore, in the plateau region PR where it is difficult to calculate the SOC of the storage battery using the SOC-OCV characteristics, the storage capacity of the battery 40 can be properly calculated.

[0041] A flowchart of the determination process of this embodiment is shown in Fig. 3. The BMU 50 repeatedly performs the determination process at each predetermined control period while the battery 40 is energized.

[0042] When the determination process starts, first in step S10, it is determined whether or not the charge / discharge current IS has changed by a threshold current or more. If the determination in step S10 is negative, the determination process ends. On the other hand, if the determination in step S10 is positive, the process proceeds to step S11.

[0043] In step S11, the impedance value RA of the battery 40 is calculated by the above-mentioned method. In the following step S12, the impedance value change HA is calculated using the impedance value RA calculated in step S11, and the process proceeds to steps S13 and S14. In this embodiment, the process of step S12 corresponds to the "acquisition unit."

[0044] In steps S13 and S14, it is determined that the storage capacities of the battery 40 are the first and second capacities QA and QB based on the impedance value change HA calculated in step S12. Specifically, a time change ΔHA of the impedance value change HA is calculated, and it is determined whether the absolute value of the time change ΔHA is greater than thresholds α, β (α, β>0). In this embodiment, the processes in steps S13 and S14 correspond to a "capacity determination unit."

[0045] In step S13, it is determined whether the absolute value of the time change amount ΔHA of the impedance value change HA is greater than the threshold value α and whether the impedance value change HA is decreasing with the current flow. In the first capacity QA, with the change in the voltage change amount ΔOCV, the absolute value of the impedance value change HA is greater on the high capacity side than on the low capacity side during charging, and the absolute value of the impedance value change HA is greater on the low capacity side than on the high capacity side during discharging. That is, in the first capacity QA, the impedance value change HA decreases with the current flow, and the time change amount ΔHA becomes smaller than the threshold value -α, so that the positive determination is made in step S13. In this case, in step S15, it is determined that the storage capacity of the battery 40 is the first capacity QA, and the process proceeds to step S18. On the other hand, if the negative determination is made in step S13, the process proceeds to step S14.

[0046] In step S14, it is determined whether the absolute value of the time change amount ΔHA of the impedance value change HA is greater than the threshold value β and whether the impedance value change HA increases with current flow. The threshold value β may be equal to or different from the threshold value α. In the second capacity QB, the absolute value of the impedance value change HA is smaller on the high capacity side than on the low capacity side during charging with the change in the voltage change amount ΔOCV, and the absolute value of the impedance value change HA is smaller on the low capacity side than on the high capacity side during discharging. That is, in the second capacity QB, the impedance value change HA increases with current flow, and the time change amount ΔHA becomes greater than the threshold value β, so that the determination in step S14 is affirmative. In this case, in step S16, it is determined that the storage capacity of the battery 40 is the second capacity QB, and the process proceeds to step S18. On the other hand, if the determination in step S14 is negative, the process proceeds to step S17.

[0047] In step S17, the storage capacity of the battery 40 is calculated by current integration, and the determination process is terminated. In step S17, the storage capacity of the battery 40 is calculated as a calculated capacity QM by integrating the charge / discharge current IS. Specifically, in step S17, the charge / discharge current IS flowing into and out of the battery 40 from the previous determination process to the current determination process is integrated, and this integrated value is added to the calculated capacity QM in the previous determination process.

[0048] In step S18, the calculated capacity QM is corrected to the first and second capacities QA and QB determined in steps S15 and S16, and the determination process ends. In this embodiment, the processes in steps S17 and S18 correspond to a "calculated capacity calculation unit."

[0049] Next, an example of the determination process is shown in Figures 4 and 5. Figure 4 shows the transition of the calculated capacity QM when the battery 40 is constant-voltage charged using the off-vehicle charger 200. In Figures 4 and 5, (A) shows the transition of the open-circuit voltage OCV, (B) shows the transition of the calculated capacity QM, (C) shows the transition of the impedance value RA, (D) shows the transition of the impedance value change HA, and (E) shows the transition of the amount of change over time ΔHA of the impedance value change HA.

[0050] In Fig. 4(B) and Fig. 5(B), the accurate storage capacity is shown by a broken line, the calculated capacity QM in which an integrated error on the high capacity side is accumulated with respect to this storage capacity is shown by a solid line as a first calculated capacity QM1, and the calculated capacity QM in which an integrated error on the low capacity side is accumulated is shown by a solid line as a second calculated capacity QM2. In addition, in this embodiment, an example is shown in which the resistance value, which is the real component of the impedance value RA of the battery 40, is used, and Fig. 4(C) and Fig. 5(C) show the transition of the resistance value.

[0051] In the example shown in FIG. 4, at time t1, constant voltage charging is started in a state where the storage capacity of the battery 40 is lower than the plateau region PR. At time t1, the storage capacity of the battery 40 is not within the plateau region PR, so the first and second calculated capacities QM1 and QM2 are corrected using the SOC-OCV characteristics. Then, when constant voltage charging is started, the first and second calculated capacities QM1 and QM2 and the open circuit voltage OCV increase. Since the first and second calculated capacities QM1 and QM2 are calculated by current integration, the integration error ΔQ increases with the increase in the elapsed time from time t1. When the storage capacity of the battery 40 reaches the lower limit capacity of the plateau region PR at the subsequent time t2, the open circuit voltage OCV stops increasing and is maintained approximately constant.

[0052] The impedance value RA decreases by a predetermined first impedance value change HA1 as the time elapsed from time t1 increases. When the storage capacity becomes the first capacity QA at a later time t3, the impedance value change HA of the impedance value RA decreases from the first impedance value change HA1 to a predetermined second impedance value change HA2. When the time change ΔHA of the impedance value change HA becomes smaller than the threshold value −α, the BMU 50 determines that the storage capacity is the first capacity QA, and corrects the first and second calculated capacities QM1 and QM2 to the first capacity QA at this time t3.

[0053] At a later time t4, when the storage capacity becomes the second capacity QB, the impedance value change HA of the impedance value RA increases from the second impedance value change HA2 to a predetermined third impedance value change HA3. As a result, when the time change amount ΔHA of the impedance value change HA becomes larger than the threshold value β, the BMU 50 determines that the storage capacity is the second capacity QB, and corrects the first and second calculated capacities QM1 and QM2 to the second capacity QB at this time t4.

[0054] The open circuit voltage OCV increases again when the storage capacity of the battery 40 reaches the upper limit capacity of the plateau region PR at time t5. Then, when the open circuit voltage OCV reaches a predetermined upper charge voltage VUth at time t6, the BMU 50 determines that the battery 40 is fully charged, and terminates the constant voltage charging of the battery 40 at time t6.

[0055] 5 shows the transition of the calculated capacity QM when the battery 40 is discharged by the rotating electric machine 10. In the example shown in FIG. 5, at time t11, discharging is started in a state in which the storage capacity of the battery 40 is higher than the plateau region PR. At time t11, the storage capacity of the battery 40 is not within the plateau region PR, so the first and second calculated capacities QM1 and QM2 are corrected using the SOC-OCV characteristics. Then, when discharging is started, the first and second calculated capacities QM1 and QM2 and the open circuit voltage OCV decrease. When the storage capacity of the battery 40 reaches the upper limit capacity of the plateau region PR at a later time t12, the open circuit voltage OCV stops decreasing and is maintained substantially constant.

[0056] The impedance value RA decreases by a predetermined fourth impedance value change HA4 as the time elapsed from time t11 increases. When the storage capacity becomes the second capacity QB at a later time t13, the impedance value change HA of the impedance value RA increases from the fourth impedance value change HA4 to a predetermined fifth impedance value change HA5. When the time change amount ΔHA of the impedance value change HA becomes larger than the threshold value β, the BMU 50 determines that the storage capacity is the second capacity QB and corrects the first and second calculated capacities QM1 and QM2 to the second capacity QB at this time t13.

[0057] At a later time t14, when the storage capacity becomes the first capacity QA, the impedance value change HA of the impedance value RA decreases from the fifth impedance value change HA5 to a predetermined sixth impedance value change HA6. As a result, when the time change amount ΔHA of the impedance value change HA becomes smaller than the threshold value −α, the BMU 50 determines that the storage capacity is the first capacity QA, and corrects the first and second calculated capacities QM1 and QM2 to the first capacity QA at this time t14.

[0058] The open circuit voltage OCV decreases again when the storage capacity of the battery 40 reaches the lower limit capacity of the plateau region PR at time t15. Then, when the open circuit voltage OCV reaches a predetermined discharge lower limit voltage VDth at time t16, the BMU 50 determines that the battery 40 is in a fully discharged state and terminates discharging the battery 40 at time t16.

[0059] According to the present embodiment described above in detail, the following effects can be obtained.

[0060] In this embodiment, the impedance value change HA of the battery 40 is calculated during energization, and it is determined that the storage capacity of the battery 40 is the first and second calculated capacities QM1 and QM2 based on this impedance value change HA. The storage capacity of the battery 40 can be calculated using the impedance value change HA in the first and second calculated capacities QM1 and QM2 of the battery 40, and the storage capacity of the battery 40 can be properly calculated without using the SOC-OCV characteristic.

[0061] In particular, in this embodiment, the battery 40 has a plateau region PR, and the first and second calculated capacities QM1, QM2 exist in this plateau region PR. Therefore, in the plateau region PR where it is difficult to calculate the storage capacity using the SOC-OCV characteristics, the storage capacity of the battery 40 can be properly calculated using the first and second calculated capacities QM1, QM2.

[0062] In this embodiment, the first and second calculated capacities QM1, QM2 are calculated by current integration. In calculating the storage capacity by current integration, if the current integration period is extended, an integration error ΔQ accumulates and the calculation accuracy of the first and second calculated capacities QM1, QM2 decreases. In this embodiment, the storage capacity of the battery 40 is calculated using the impedance value change HA in the first and second calculated capacities QM1, QM2 of the battery 40, and the first and second calculated capacities QM1, QM2 are corrected using the first and second calculated capacities QM1, QM2, so that the integration error ΔQ of the first and second calculated capacities QM1, QM2 can be reset.

[0063] Even if the impedance value change HA of the battery 40 changes, if the change is small, there is a high possibility that the impedance value change HA has changed due to noise or the like. In the above configuration, if the absolute value of the time change amount ΔHA of the impedance value change HA is greater than predetermined threshold values ​​α and β, it is determined that the storage capacity of the battery 40 is the first and second calculated capacities QM1 and QM2. Therefore, the influence of noise and the like can be suppressed and the storage capacity of the battery 40 can be appropriately calculated.

[0064] Some storage batteries have multiple predetermined capacities at which a relatively large voltage change ΔOCV occurs. In this case, even if the predetermined capacity is determined based on the impedance value change HA, it is not possible to determine which of the multiple predetermined capacities the predetermined capacity is.

[0065] In this regard, in this embodiment, the predetermined capacity has a first capacity QA and a second capacity QB, and during charging, the absolute value of the impedance value change HA is larger on the high capacity side of the first capacity QA than on the low capacity side, and the absolute value of the impedance value change HA is smaller on the high capacity side of the second capacity QB than on the low capacity side. Also, during discharging, the absolute value of the impedance value change HA is larger on the low capacity side of the first capacity QA than on the high capacity side, and the absolute value of the impedance value change HA is smaller on the low capacity side of the second capacity QB than on the high capacity side. That is, in the first capacity QA, the impedance value change HA decreases with current flow, and in the second capacity QB, the impedance value change HA increases with current flow. Therefore, in a secondary battery having a plurality of predetermined capacities, it is possible to determine whether the predetermined capacity is the first capacity QA or the second capacity QB by using the difference in the state of the impedance value change HA.

[0066] Second embodiment The second embodiment will be described below with reference to Figures 6 to 8, focusing on the differences from the first embodiment. The present embodiment differs from the first embodiment in that the battery control device 100 includes a current generating circuit 60 as an AC current generating unit.

[0067] As described above, the impedance value RA is calculated using the change amount ΔVB of the battery voltage VB and the change amount ΔIS of the current when the charge / discharge current IS changes. Therefore, for example, when the battery 40 is charged at a constant current, the charge / discharge current IS does not change, so the impedance value RA is not calculated and the impedance value change HA cannot be determined. Therefore, it is not possible to determine whether the storage capacity of the battery 40 is the first or second calculated capacity QM1 or QM2 based on the impedance value change HA.

[0068] Therefore, the battery control device 100 of this embodiment includes a current generating circuit 60. The current generating circuit 60 generates an AC current IA for calculating the impedance value RA, in addition to the charge / discharge current IS from the rotating electric machine 10 and the off-vehicle charger 200. As shown in Fig. 6, the current generating circuit 60 is connected to both ends of each of the lithium ion storage batteries 41 that constitute the battery 40. The current generating circuit 60 has an AC power supply, and uses this AC power supply to apply an AC voltage to each of the lithium ion storage batteries 41 individually to generate an AC current IA.

[0069] The BMU 50 is connected to the current generating circuit 60, and switches between a state in which an AC current IA is generated and a state in which it is not generated for each lithium ion storage battery 41. This switches between a state in which the AC current IA is superimposed on the charge / discharge current IS and a state in which it is not superimposed.

[0070] FIG. 7 shows the superposition of the charge / discharge current IS and the AC current IA. In this embodiment, the AC current IA is set as a sine wave. The frequency of the sine wave is preferably 1 kHz or less. This is because an impedance value RA of an ion conductive component with significant temperature dependency is obtained at 1 kHz or less. As shown in FIG. 7, the amplitude of the AC current IA is a small value compared to the absolute value of the charge / discharge current IS. In the determination process of this embodiment, the impedance value change HA is calculated when the charge / discharge current IS changes due to the AC current IA. In other words, the impedance value change HA is calculated when the AC current IA is generated by the current generating circuit 60.

[0071] A flowchart of the determination process of this embodiment is shown in Fig. 8. Note that in Fig. 6, the same processes as those shown in Fig. 3 are denoted by the same step numbers for convenience, and the description thereof will be omitted.

[0072] As shown in Fig. 8, when the determination process of this embodiment starts, first in step S21, an AC current IA is superimposed on the charge / discharge current IS, and the process proceeds to steps S11 and S12. In this case, in step S12, an impedance value change HA is calculated when the AC current IA is superimposed in step S21. In this embodiment, the process of step S21 corresponds to an "AC current generating unit."

[0073] According to the present embodiment described above in detail, the following effects can be obtained.

[0074] In this embodiment, a current generating circuit 60 is provided that superimposes an AC current IA on the charge / discharge current IS. By using the current generating circuit 60, the charge / discharge current IS can be changed using the AC current IA, so that the storage capacity of the battery 40 can be calculated appropriately even if the change in the charge / discharge current IS before superimposition is small, for example, when the battery 40 is being charged with a constant current.

[0075] In this embodiment, an AC current IA is used as the current to be superimposed on the charge / discharge current IS, which makes it possible to suppress the deterioration of the EMC characteristics compared to when a DC current is used.

[0076] Third embodiment The third embodiment will be described below with reference to Figs. 9 and 10, focusing on the differences from the first embodiment. This embodiment differs from the first embodiment in that the discharge capacity of the battery 40 is calculated as the calculated discharge capacity QH in the determination process. The discharge capacity is the storage capacity of the battery 40 in a fully charged state, and decreases as the battery 40 deteriorates.

[0077] FIG. 9 shows the change in discharge capacity associated with the deterioration of the battery 40. In FIG. 7, the relationship between the storage capacity and the voltage change amount ΔOCV at the time of manufacturing the battery 40 is shown by a solid line, and the relationship between the storage capacity and the voltage change amount ΔOCV after the start of use of the battery 40 is shown by a dashed line. As shown by the arrow YA in FIG. 7, the discharge capacity of the battery 40 decreases with deterioration. On the other hand, in the battery 40, the first and second capacities QA and QB do not change even if the discharge capacity decreases. In this embodiment, focusing on this point, the calculated discharge capacity QH is calculated based on the second capacity QB.

[0078] Fig. 8 shows a flowchart of the determination process of this embodiment. Fig. 8 shows a flowchart of the determination process for calculating the calculated discharge capacity QH during charging of the battery 40. In Fig. 8, for convenience, the same processes as those shown in Fig. 3 are given the same step numbers and the description thereof is omitted.

[0079] As shown in FIG. 8, in the determination process of this embodiment, when it is determined in step S15 that the storage capacity of the battery 40 is the first capacity QA, the calculated capacity QM is corrected to the first capacity QA in step S18, and the determination process ends.

[0080] Furthermore, if it is determined in step S16 that the storage capacity of the battery 40 is the second capacity QB, then in step S31, the calculated capacity QM is corrected to the second capacity QB. In the following step S32, it is determined whether the battery 40 is being charged. Whether the battery 40 is being charged or not is determined based on the direction of the charge / discharge current IS detected by the current sensor 31. If a negative determination is made in step S32, the determination process is terminated. On the other hand, if a positive determination is made in step S32, the process proceeds to step S33.

[0081] In step S33, the full charge flag FA is turned on, and the process proceeds to step S34. The full charge flag FA is a flag indicating that the storage capacity of the battery 40 is equal to or greater than the second capacity QB and that the battery 40 is being charged, and is turned on when the above two conditions are met.

[0082] In step S34, calculation of the additional capacity QD by current integration is started, and the determination process is terminated. The additional capacity QD is the integrated amount of the charge / discharge current IS flowing into and out of the battery 40 from the time when it is determined that the storage capacity of the battery 40 is the second capacity QB to the time when it is determined that the battery 40 is in a fully charged state. In this embodiment, the timing of the process in step S16 corresponds to the "first timing".

[0083] Furthermore, when the calculated capacity QM is calculated by current integration in step S17, it is determined in step S35 whether or not the full charge flag FA is on. If the determination in step S35 is negative, the determination process ends. On the other hand, if the determination in step S35 is positive, the process proceeds to step S36.

[0084] In step S36, it is determined whether or not the battery 40 is fully charged. If a negative determination is made in step S36, the process proceeds to step S37. In step S37, an additional capacity QD is calculated by current integration, and the determination process ends.

[0085] On the other hand, if the determination in step S36 is affirmative, the process proceeds to step S38. In step S38, the additional capacity QD is added to the second capacity QB to calculate the calculated discharge capacity QH. In the following step S39, the full charge flag FA is turned off, and the determination process ends. In this embodiment, the process in step S36 corresponds to the "full charge determination unit", and the process in step S38 corresponds to the "discharge capacity calculation unit". Also, the timing of the affirmative determination in step S36 corresponds to the "second timing".

[0086] According to the present embodiment described above in detail, the calculated discharge capacity QH is calculated using the second capacity QB. In the battery 40, the discharge capacity of the battery 40 decreases due to deterioration. On the other hand, the second capacity QB does not change due to deterioration of the battery 40. Therefore, by calculating the calculated discharge capacity QH using the second capacity QB that does not change due to deterioration of the battery 40, the calculated discharge capacity QH can be calculated appropriately.

[0087] (Other embodiments) The present invention is not limited to the above-described embodiment, and may be implemented as follows.

[0088] In the above embodiment, the absolute value of the time change amount ΔHA of the impedance value change HA is compared with the threshold values ​​α and β in the determination process, but this is not limited to the above. For example, the time change amount ΔHA itself may be compared with the threshold values ​​−α and β.

[0089] In the above embodiment, when the calculated capacity QM is corrected using the first and second capacities QA and QB in the determination process, the first and second capacities QA and QB are corrected to the calculated capacity QM. However, this is not limited to the above. For example, if the battery 40 is being charged, the calculated capacity QM may be corrected to the first and second capacities QA and QB by adding the increase in the storage capacity due to charging until the actual correction is performed. Also, for example, if the battery 40 is being discharged, the calculated capacity QM may be corrected to the first and second capacities QA and QB by subtracting the decrease in the storage capacity due to discharging until the actual correction is performed.

[0090] In the above embodiment, the impedance value used in the determination process is the resistance value, which is the real component of the impedance value, but this is not limited to the above. For example, the imaginary component of the impedance value may be used, or the phase of the impedance value, that is, the phase difference between the charge / discharge current IS and the battery voltage VB, may be used. Furthermore, the absolute value of the impedance value may be used.

[0091] In the second embodiment, a sine wave is used as an example of the waveform of the AC current IA superimposed on the charge / discharge current IS, but the waveform is not limited to this and may be a periodic wave such as a trapezoidal wave or a rectangular wave.

[0092] In the second embodiment, the AC current IA is applied to the battery 40 only when the impedance value RA is calculated, but the present invention is not limited to this. For example, the AC current IA may be constantly applied to the battery 40. In this case, the control of the current generating circuit 60 by the BMU 50 becomes unnecessary.

[0093] In the second embodiment, the frequency of the sine wave generated by the current generating circuit 60 is set to 1 kHz or less, and the impedance value RA of the ion conductive component having a significant temperature dependency is obtained, but this is not limited to the above. The frequency may be higher than 1 kHz. Even when the frequency is higher than 1 kHz, the impedance value RA has a characteristic of decreasing as the battery temperature increases, as in the case of a frequency of 1 kHz or less. Therefore, the impedance value RA can be obtained even when the frequency is higher than 1 kHz.

[0094] In the above second embodiment, when a sine wave AC current IA is superimposed on the charge / discharge current IS, assuming that the amplitude of the AC current IA is the amplitude WA, the maximum value of the current after superimposition is the charge / discharge current IS+amplitude WA, and the minimum value is the charge / discharge current IS-amplitude WA, but this is not limiting. For example, the AC current IA may be adjusted so that the maximum value is the charge / discharge current IS and the minimum value is the charge / discharge current IS-2×amplitude WA, or the AC current IA may be adjusted so that the maximum value is the charge / discharge current IS+2×amplitude WA and the minimum value is the charge / discharge current IS.

[0095] In the above third embodiment, an example was shown in which the calculated discharge capacity QH was calculated when the battery 40 was charged in the determination process, but the calculated discharge capacity QH may be calculated when the battery 40 was discharged. For example, when discharging the battery 40 from a fully charged state, an added capacity QD from the start of discharge until it is determined that the storage capacity of the battery 40 is the second capacity QB may be calculated, and the added capacity QD may be added to the second capacity QB to calculate the calculated discharge capacity QH. In this case, the timing of the start of discharge corresponds to the "second timing."

[0096] In the above embodiment, the method of calculating the calculated capacity QM is exemplified by current integration, but the present invention is not limited to this, and any known technique for calculating the storage capacity of the battery 40 can be used.

[0097] In the above embodiment, an example has been shown in which a storage battery having a plateau region PR is used as the battery 40. However, the technology of the present embodiment may be used for a storage battery that does not have a plateau region PR.

[0098] In the above embodiment, an example is shown in which the battery 40 has two predetermined capacities, the first capacity QA and the second capacity QB, but this is not limited to the above. The number and size of the predetermined capacities in the battery 40 vary depending on the positive electrode active material and the negative electrode active material used in the battery 40. The technology of the present embodiment can be applied regardless of the number and size of the predetermined capacities in the battery 40.

[0099] In the above embodiment, the amount of change per unit time is used as the impedance value change of the secondary battery, but this is not limiting. For example, the amount of change per unit capacity may be used.

[0100] The control device and the method described in the present disclosure may be realized by a dedicated computer provided by configuring a processor and a memory programmed to execute one or more functions embodied in a computer program. Alternatively, the control device and the method described in the present disclosure may be realized by a dedicated computer provided by configuring a processor with one or more dedicated hardware logic circuits. Alternatively, the control device and the method described in the present disclosure may be realized by one or more dedicated computers configured by a combination of a processor and a memory programmed to execute one or more functions and a processor configured with one or more hardware logic circuits. In addition, the computer program may be stored in a computer-readable non-transitory tangible recording medium as instructions executed by the computer. [Explanation of symbols]

[0101] 40…batteries, 50…BMU.

Claims

1. The present invention is applied to a secondary battery (40) in which a change in reaction heat quantity occurs at a predetermined capacity when the storage capacity changes with the passage of current, An acquisition unit (50) that acquires a change in impedance value of the secondary battery when it is energized; a capacity determination unit (50) that determines whether a storage capacity of the secondary battery is the predetermined capacity based on the impedance value change acquired by the acquisition unit, the secondary battery has a first capacity and a second capacity as the predetermined capacity, and during charging, the absolute value of the impedance value change is larger on the high-capacity side of the first capacity than on the low-capacity side, and smaller on the high-capacity side of the second capacity than on the low-capacity side; and during discharging, the absolute value of the impedance value change is larger on the low-capacity side of the first capacity than on the high-capacity side, and smaller on the low-capacity side of the second capacity than on the high-capacity side, The capacity determination unit is When the impedance value change decreases with energization, the storage capacity of the secondary battery is determined to be the first capacity; The battery monitoring device determines that the storage capacity of the secondary battery is the second capacity when the impedance value change increases with energization.

2. a calculated capacity calculation unit (50) that calculates a storage capacity of the secondary battery as a calculated capacity by integrating current flowing into and flowing out of the secondary battery; 2 . The battery monitoring device according to claim 1 , wherein the calculated capacity calculation unit corrects the calculated capacity by using the predetermined capacity when the capacity determination unit determines that the storage capacity of the secondary battery is the predetermined capacity.

3. The present invention is applied to a secondary battery (40) in which a change in reaction heat quantity occurs at a predetermined capacity when the storage capacity changes with the passage of current, An acquisition unit (50) that acquires a change in impedance value of the secondary battery when it is energized; a capacity determination unit (50) that determines whether a storage capacity of the secondary battery is the predetermined capacity based on the impedance value change acquired by the acquisition unit; a calculated capacity calculation unit (50) that calculates a storage capacity of the secondary battery as a calculated capacity by integrating current flowing into and flowing out of the secondary battery, The calculated capacity calculation unit corrects the calculated capacity using the predetermined capacity when the capacity determination unit determines that the storage capacity of the secondary battery is the predetermined capacity.

4. an alternating current generating unit (60) for generating a predetermined alternating current to be superimposed on a current flowing into and out of the secondary battery; The battery monitoring device according to claim 1 , wherein the acquisition unit acquires the impedance value change when the AC current is generated by the AC current generation unit.

5. A full charge determination unit (50) for determining whether the secondary battery is fully charged; 5. The battery monitoring device according to claim 1, further comprising a discharge capacity calculation unit (50) that calculates a discharge capacity of the secondary battery using an integrated amount of current flowing into and out of the secondary battery between a first timing when the capacity determination unit determines that the storage capacity of the secondary battery is the specified capacity and a second timing when the full charge determination unit determines that the secondary battery has reached a fully charged state, and the specified capacity.

6. The present invention is applied to a secondary battery (40) in which a change in reaction heat quantity occurs at a predetermined capacity when the storage capacity changes with the passage of current, An acquisition unit (50) that acquires a change in impedance value of the secondary battery when it is energized; a capacity determination unit (50) that determines whether a storage capacity of the secondary battery is the predetermined capacity based on the impedance value change acquired by the acquisition unit; A full charge determination unit (50) for determining whether the secondary battery is fully charged; a discharge capacity calculation unit (50) that calculates a discharge capacity of the secondary battery using an integrated amount of current flowing into and out of the secondary battery between a first timing when the capacity determination unit determines that the storage capacity of the secondary battery is the specified capacity and a second timing when the full charge determination unit determines that the secondary battery has reached a fully charged state, and the specified capacity.

7. the secondary battery has a plateau region in which a change in open circuit voltage of the secondary battery due to a change in the charge storage capacity of the secondary battery is small, The battery monitoring device according to claim 1 , wherein the predetermined capacity is within the plateau region.

8. The battery monitoring device according to any one of claims 1 to 7, wherein the capacity determination unit determines that the storage capacity of the secondary battery is the predetermined capacity when an absolute value of a time change amount of the impedance value change is greater than a predetermined threshold value.

9. The present invention is applied to a secondary battery (40) in which a change in reaction heat quantity occurs at a predetermined capacity when the storage capacity changes with the passage of current, On the computer, An acquisition process for acquiring an impedance value change of the secondary battery when the secondary battery is energized; a capacity determination process for determining whether a storage capacity of the secondary battery is equal to the predetermined capacity based on the impedance value change acquired by the acquisition process; the secondary battery has a first capacity and a second capacity as the predetermined capacity, and during charging, the absolute value of the impedance value change is larger on the high-capacity side of the first capacity than on the low-capacity side, and smaller on the high-capacity side of the second capacity than on the low-capacity side; and during discharging, the absolute value of the impedance value change is larger on the low-capacity side of the first capacity than on the high-capacity side, and smaller on the low-capacity side of the second capacity than on the high-capacity side, In the capacity determination process, When the impedance value change decreases with energization, the storage capacity of the secondary battery is determined to be the first capacity; a program for determining that the storage capacity of the secondary battery is the second capacity when the impedance value change increases with energization;

10. The present invention is applied to a secondary battery (40) in which a change in reaction heat quantity occurs at a predetermined capacity when the storage capacity changes with the passage of current, On the computer, An acquisition process for acquiring an impedance value change of the secondary battery when the secondary battery is energized; a capacity determination process for determining whether the storage capacity of the secondary battery is the predetermined capacity based on the impedance value change acquired by the acquisition process; a calculated capacity calculation process for calculating a storage capacity of the secondary battery as a calculated capacity by integrating currents flowing into and flowing out of the secondary battery; a program for correcting the calculated capacity by using the predetermined capacity when it is determined in the calculated capacity calculation process that the storage capacity of the secondary battery is equal to the predetermined capacity by the capacity determination process;

11. The present invention is applied to a secondary battery (40) in which a change in reaction heat quantity occurs at a predetermined capacity when the storage capacity changes with the passage of current, On the computer, An acquisition process for acquiring an impedance value change of the secondary battery when the secondary battery is energized; a capacity determination process for determining whether the storage capacity of the secondary battery is the predetermined capacity based on the impedance value change acquired by the acquisition process; a full charge determination process for determining whether the secondary battery is fully charged; a discharge capacity calculation process that calculates the discharge capacity of the secondary battery using an integrated amount of current flowing into and out of the secondary battery between a first timing when the capacity determination process determines that the storage capacity of the secondary battery is the specified capacity and a second timing when the full charge determination process determines that the secondary battery has reached a fully charged state, and the specified capacity.

Citation Information

Patent Citations

  • Charge state detecting device, its program and charge state detecting method, and charge / discharge control device

    JP2004056945A

  • Battery charger

    JP2004173373A

  • Battery state estimation method, battery state monitoring device, and battery power source system

    JP2008128802A

  • State determination device and control device of secondary battery

    JP2010249797A

  • Secondary battery state detection device and secondary battery state detection method

    JP2014074588A