Integrated data generation system, construction plan management system, integrated data generation method, construction plan management method, and program

The integrated data generation and construction plan management systems address the lack of process management in existing 3D model-based construction methods by linking work objects to target areas within a three-dimensional model, facilitating efficient construction planning and execution.

JP7595300B2Active Publication Date: 2024-12-06PANASONIC INTELLECTUAL PROPERTY MANAGEMENT CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2021058423
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-03-30
Publication Date
2024-12-06
Estimated Expiration
2041-03-30

AI Technical Summary

Technical Problem

Existing construction support methods, such as those described in Patent Document 1, can integrate building and processed parts using 3D models but fail to manage the construction process effectively, including work scheduling and control.

Method used

An integrated data generation system and construction plan management system that utilizes a three-dimensional model of a building, linking work objects with specific information to target areas, enabling the creation of construction plans and managing the construction process through a computer system.

Benefits of technology

Enables effective management of construction processes, including scheduling and resource allocation, by integrating work objects with three-dimensional models, thereby enhancing the efficiency and standardization of construction activities.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007595300000001
    Figure 0007595300000001
  • Figure 0007595300000002
    Figure 0007595300000002
  • Figure 0007595300000003
    Figure 0007595300000003
Patent Text Reader

Abstract

To provide an integrated data generation system, a construction plan management system, an integrated data generation method, a construction plan management method, and a program, which enable management of construction processes using a three-dimensional model of a building.SOLUTION: An integrated data generation system 2 is provided, comprising a linking unit 21 and a storage unit 26. The linking unit 21 links a target area corresponding to a portion of a building in a three-dimensional model representing a three-dimensional shape of the building to be constructed to a work object including information on work to be done when constructing the building. The storage unit 26 stores integrated data including data of the three-dimensional model having at least the work object linked to the target area.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to an integrated data generation system, a construction plan management system, an integrated data generation method, a construction plan management method, and a program. [Background technology]

[0002] The construction support method of Patent Document 1 supports the construction of a construction object through the transportation of a plurality of processed members processed in a processing plant to a construction site and the installation of the transported plurality of processed members. This construction support method includes a construction drawing acquisition step, a construction object BIM model creation step, a processed member BIM model creation step, and an integrated BIM model creation step.

[0003] The construction drawing acquisition step acquires a construction drawing for constructing the construction object.

[0004] The construction object BIM model creation step creates a construction object BIM model, which is a three-dimensional model of the construction object, based on the construction drawings.

[0005] The processed member BIM model creation step includes a processing shape information extraction step and an installation position information extraction step, and creates a processed member BIM model for each of the multiple processed members based on a processing drawing for processing the multiple processed members, which is created based on the working drawing. The processing shape information extraction step extracts processing shape information including the shape and dimensions of each of the multiple processed members from the processing drawing. The installation position information extraction step extracts installation position information including the installation position of each of the multiple processed members within the construction object from the processing drawing.

[0006] The integrated BIM model creation step creates an integrated BIM model in which the BIM model of the construction object and the BIM models of the multiple processed parts are integrated by incorporating the BIM model of each of the multiple processed parts into the BIM model of the construction object based on the processing shape information and installation position information.

[0007] The construction support method of Patent Document 1 mentioned above makes it possible to verify the consistency of processing drawings with construction drawings using the integrated BIM model, even if the entities that create the processing drawings and the construction drawings are different, because the information on the processing drawings that should be followed during manufacturing (processing work) is reflected in the integrated BIM model.

[0008] Furthermore, since it is possible to carry out manufacturing using processing drawings whose validity has been verified in advance, the risk of manufacturing processed parts that lack consistency with the working drawings is reduced.

[0009] In other words, in the construction support method of Patent Document 1 mentioned above, by creating an integrated BIM model that integrates the BIM model of the construction object and the BIM models of each of the multiple processed parts, it is possible to verify the consistency between the construction drawings and the processing drawings, thereby reducing the risk of manufacturing processed parts that lack consistency. [Prior art documents] [Patent documents]

[0010] [Patent Document 1] JP 2019-21190 A Summary of the Invention [Problem to be solved by the invention]

[0011] However, while the construction support method of Patent Document 1 can align a building and processed parts using a 3D model of the building, it cannot use the 3D model of the building to manage construction processes such as specific work and schedules at the construction site.

[0012] An object of the present disclosure is to provide an integrated data generation system, a construction plan management system, an integrated data generation method, a construction plan management method, and a program that can manage construction processes using a 3D model of a building. [Means for solving the problem]

[0013] An integrated data generation system according to an embodiment of the present disclosure includes a linking unit and a storage unit. The linking unit links a work object, including information on work to be performed during construction of a building, to a target area corresponding to a part of the building in a 3D model representing a 3D shape of the building. The storage unit stores integrated data including at least data of the 3D model in which the work object is linked to the target area. The attribute of the work object includes the type of the work. The three-dimensional model includes an element model corresponding to at least one element constituting the building. The element model includes an element object to which element-specific information, which is information on the work targeting the element, is set in advance. If the target area corresponds to the element model, the linking unit links the work object to the target area by setting the element-specific information to the attribute of the work object.

[0014] A construction plan management system according to an embodiment of the present disclosure includes a construction plan creation unit and a data output unit. Based on the integrated data of the integrated data generating system, A construction plan for the building is created. The data output unit outputs data of the construction plan.

[0015] An integrated data generation method according to an aspect of the present disclosure includes a linking step and a storage step. include The linking step links a work object including information on work to be performed during construction of a building to a target area corresponding to a part of the building in a three-dimensional model representing the three-dimensional shape of the building to be constructed. The storage step stores integrated data including at least data of the three-dimensional model in which the work object is linked to the target area. The attributes of the work object include the type of work, and the 3D model includes an element model corresponding to at least one element constituting the building. The element model includes an element object to which element-specific information, which is information on the work targeting the element, is set in advance. In the linking step, if the target area corresponds to the element model, the element-specific information is set in the attributes of the work object, thereby linking the work object to the target area.

[0016] A construction plan management method according to one aspect of the present disclosure includes a construction plan creation step and a data output step. include The construction plan creation step includes: The integrated data generation method A construction plan for the building is created based on the integrated data. The data output step outputs data of the construction plan.

[0017] A program according to one aspect of the present disclosure causes a computer system to execute the integrated data generation method described above.

[0018] A program according to one aspect of the present disclosure causes a computer system to execute the construction plan management method described above. Effect of the Invention

[0019] As described above, the present disclosure has an advantage of being able to manage construction processes using a three-dimensional model of a building. [Brief description of the drawings]

[0020] [Figure 1] FIG. 1 is a block diagram showing the configuration of a construction plan management system including an integrated data generation system according to an embodiment. [Diagram 2] FIG. 2 is a perspective view showing an example of a three-dimensional model of the construction plan management system. [Diagram 3] FIG. 3 is a flowchart showing the operation of the integrated data generating system. [Figure 4] FIG. 4 is a diagram for explaining setting of a target area in the integrated data generation system. [Diagram 5] FIG. 5 is a diagram showing a work object in the integrated data generation system. [Figure 6] FIG. 6 is a diagram showing element models of a three-dimensional model in the integrated data generation system. [Figure 7] FIG. 7 is a diagram showing element objects in the integrated data generation system. [Figure 8] FIG. 8 is a diagram for explaining linking of work objects in the integrated data generation system. [Figure 9] Fig. 9A is a diagram for explaining a process of setting element-specific information for a first work object in the integrated data generation system of the embodiment, and Fig. 9B is a diagram showing the first work object to which the element-specific information has been set of the embodiment. [Figure 10] FIG. 10 is a diagram showing a second work object in the integrated data generation system. [Figure 11] FIG. 11 is a flowchart showing the operation of the construction plan management system. [Figure 12]FIG. 12 is a diagram showing linked work objects in the construction plan management system. [Figure 13] Fig. 13A is a diagram showing a construction flow created by the construction plan management system of the embodiment, and Fig. 13B is a diagram showing a work flow of the embodiment. [Figure 14] 14A and 14B are diagrams showing an optimal work flow and a process flow, respectively, created by the construction plan management system of the embodiment. [Figure 15] 15A and 15B are diagrams showing element objects and a work object in the first modified example of the embodiment, respectively; [Figure 16] FIG. 16 is a diagram showing external information in the second modified example of the above embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0021] The following embodiments generally relate to an integrated data generation system, a construction plan management system, an integrated data generation method, a construction plan management method, and a program. More specifically, the following embodiments relate to an integrated data generation system, a construction plan management system, an integrated data generation method, a construction plan management method, and a program using a three-dimensional model of a building.

[0022] (1) Overview Generally, there are three types of construction work on buildings: A construction work, B construction work, and C construction work. A construction work is carried out by a contractor designated by the owner, at the expense of the owner (lessor). B construction work is carried out by a contractor designated by the owner, at the expense of the lessee. C construction work is carried out by a contractor designated by the lessee, at the expense of the lessee.

[0023] In recent years, the use of BIM (Building Information Modelling), including 3D models of buildings, has been increasing from the design and planning stages, mainly in construction related to skeletons (building structures) that constitute construction type A. On the other hand, construction of construction type C and infill (interior and equipment) related construction, which is downstream in the construction process within construction type A, is mainly done by the experience of site supervisors or specialist contractors, and the use of digital technologies such as BIM has not progressed.

[0024] In the infill-related construction of the C construction and the A construction, there are many types of equipment to handle, and the construction method depends on the know-how of the workers, compared to the skeleton-related construction of the A construction, where the process is more standardized. In addition, there are various combinations of elements for each construction site and each project. In addition, changes due to the progress of the construction at the construction site and the workers occur daily, and detailed changes according to the progress of the construction are necessary. In addition, there are few on-site personnel who can handle BIM-related technologies, which require advanced skills. Due to these factors, it was difficult to standardize the process in the infill-related construction of the C construction and the A construction, and it was difficult to utilize digital technologies such as BIM for work at the construction site. In addition, it is difficult for manufacturers who develop equipment to accumulate data related to construction, which is one of the factors that make it difficult to develop new equipment products and solutions that lead to reduced construction.

[0025] Therefore, in this embodiment, we will describe an integrated data generation system, a construction plan management system, an integrated data generation method, a construction plan management method, and a program that can manage the construction process using a 3D model of a building, even for infill-related construction of C construction and A construction.

[0026] The construction plan management system of this embodiment manages construction plans related to the construction of buildings. Construction of buildings includes various construction works carried out in the repair (remodeling, renovation, reconstruction, and expansion, etc.) of buildings and new construction of buildings. The buildings may be any of detached houses, apartment buildings, factories, stores, offices, office buildings, and various facilities, and the purpose, size, and shape of the buildings are not limited to specific purposes, sizes, and shapes. The construction contents may be construction works related to the construction of buildings, such as construction works, electrical works, water supply and drainage works, and civil engineering works. Examples of construction works of buildings include construction works for office lighting fixtures, air conditioning equipment, and ventilation equipment, interior construction works, power line wiring works, information wiring works, wireless works, and installation works of building management systems.

[0027] 1 includes a measurement unit 1, an integrated data generation system 2, a data processing unit 3, a data output unit 4, and an output device 5. The integrated data generation system 2 includes a linking unit 21, an integrated data generation unit 22, a communication unit 23, a communication unit 24, an integrated data acquisition unit 25, and a storage unit 26.

[0028] The functions of the measurement unit 1, the linking unit 21, the integrated data generation unit 22, and the communication unit 23 described above are preferably realized by a portable information terminal B1 such as a tablet terminal or a smartphone. The information terminal B1 is an information terminal managed by a contractor such as a building construction contractor or a design contractor, and is operated by the contractor. The operation of the information terminal B1 (hereinafter referred to as terminal operation) is performed on the operation units such as the touch panel display, keyboard, and voice recognition device of the information terminal B1.

[0029] The information terminal B1 includes a computer system. When this computer system executes a program, some or all of the functions of the measurement unit 1, the linking unit 21, the integrated data generation unit 22, and the communication unit 23 are realized. The computer includes a processor that operates according to a program as a main hardware configuration. The type of processor is not important as long as it can realize the function by executing the program. The processor is composed of one or more electronic circuits including a semiconductor integrated circuit (IC) or an LSI (large scale integration). Here, it is called an IC or an LSI, but the name changes depending on the degree of integration, and it may be called a system LSI, a VLSI (very large scale integration), or an ULSI (ultra large scale integration). A field programmable gate array (FPGA) that is programmed after the manufacture of the LSI, or a reconfigurable logic device that can reconfigure the connection relationship inside the LSI or set up the circuit partition inside the LSI, can also be used for the same purpose. Multiple electronic circuits may be integrated into one chip or provided on multiple chips. Multiple chips may be integrated into one device or provided on multiple devices. The program is recorded in a non-transitory recording medium such as a computer-readable ROM, an optical disk, a hard disk drive, etc. The program may be stored in the non-transitory recording medium in advance, or may be supplied to the non-transitory recording medium via a wide area communication network including the Internet.

[0030] The functions of the communication unit 24, the integrated data acquisition unit 25, the storage unit 26, the data processing unit 3, and the data output unit 4 are preferably realized by, for example, a server device C1. The server device C1 is configured to be able to communicate with the information terminal B1 via a communication network NT1 including the Internet. The server device C1 is managed by either a contractor such as a building construction company or a design company, or a management company of the construction plan management system A1.

[0031] The server device C1 includes a computer system that executes a program to realize some or all of the functions of the communication unit 24, the integrated data acquisition unit 25, the storage unit 26, the data processing unit 3, and the data output unit 4.

[0032] The measuring unit 1 preferably creates a 3D model of the whole or part of the building based on images of the interior and exterior of the building captured by the camera of the information terminal B1. The 3D model reflects the shape and position of each of the fixtures in each room, such as desks and bookshelves, lighting fixtures, air conditioners, ventilation fans, air vents, fire alarms, televisions, wiring devices, and other equipment, doors, and windows, in addition to the layout of the building. The measuring unit 1 can also create a 3D model including not only the building but also the site by capturing an image of the site on which the building stands using the camera of the information terminal B1. The building to be imaged may be either a building before or during renovation, or a new building under construction.

[0033] The measurement unit 1 is realized, for example, by an information terminal B1 executing an application for creating a 3D model. At a construction site, it is difficult to carry around a high-performance personal computer capable of running BIM software, and so an information terminal B1 such as a tablet terminal or smartphone that is easy to carry is used. For this reason, the 3D model of the building created by the measurement unit 1 has a relatively small data volume. The 3D model may also be created by using an acceleration sensor or gyro sensor provided in the information terminal B1 in combination with a camera.

[0034] Furthermore, the measurement unit 1 may create a three-dimensional model using a LiDAR (light detection and ranging) or a three-dimensional laser scanner that is separate from the information terminal B1.

[0035] FIG. 2 shows a three-dimensional model M1 as an example of a three-dimensional model. The three-dimensional model M1 is composed of a room model M11, an element model M12, and the like. The room model M11 is a three-dimensional model of a room in a building. The element model M12 is a three-dimensional model of components that constitute a room and elements such as equipment installed in the room. The components are building materials, piping, wiring, and the like. The equipment is devices such as lighting fixtures, air conditioners, ventilation fans, air vents, fire alarms, televisions, and wiring devices, wiring, fixtures such as desks and bookshelves, doors, and windows.

[0036] The integrated data generation system 2 mainly comprises a linking unit 21 and a storage unit 26. The linking unit 21 links a work object including information on work performed during construction of a building to a target area corresponding to a part of the building in a 3D model representing the 3D shape of the building. The storage unit 26 stores integrated data including at least data of the 3D model in which the work object is linked to the target area.

[0037] For example, in FIG. 2, two target areas 9 are set in the three-dimensional model M1. One target area 9 is an element target area 91 that corresponds to the element model M12, and corresponds to elements such as equipment and components. The other target area 9 is a spatial target area 92 that corresponds to a space within the building (such as a corner, center, top, or bottom of a room). Hereinafter, the target area 9 that corresponds to an element may be referred to as the element target area 91, and the target area 9 that corresponds to a space within the building may be referred to as the spatial target area 92. A work object that includes information about work to be performed when constructing the element is linked to each of the target areas 9.

[0038] The construction plan management system A1 mainly comprises a construction plan creation unit 31 and a data output unit 4. The construction plan creation unit 31 creates a construction plan for a building based on the integrated data. The data output unit 4 outputs data of the construction plan to an output device 5.

[0039] The output device 5 is a tablet terminal, a smartphone, a personal computer, or the like having a display device, receives the construction plan data from the data output unit 4, and displays the construction plan data on the display device. The display device is a liquid crystal display device, an organic EL display device, or the like. Note that, although a display device is basically used as the output device 5, a printer may also be used in combination.

[0040] The above-mentioned integrated data generation system 2 generates integrated data including at least data of a three-dimensional model in which a work object is linked to a target area 9, and stores the integrated data in the storage unit 26. By storing the integrated data, the integrated data generation system 2 can manage the construction process using a three-dimensional model of the building.

[0041] In addition, the construction plan management system A1 can create and output data on a construction plan based on the integrated data, thereby managing the construction process using a three-dimensional model of the building.

[0042] (2) Integrated Data Generation System The integrated data generation system 2 includes a linking unit 21, an integrated data generation unit 22, a communication unit 23, a communication unit 24, an integrated data acquisition unit 25, and a storage unit 26. The integrated data generation system 2 performs each process of a 3D model acquisition step S1, a linking step S2, an integrated data creation step S3, and a storage step S4 shown in the flowchart of FIG.

[0043] (2.1) 3D model acquisition step First, in a three-dimensional model acquisition step S1, the integrated data generation unit 22 acquires from the measurement unit 1 data of a three-dimensional model that represents the three-dimensional shape of a building.

[0044] In the 3D model acquisition step S1, the integrated data generation unit 22 may acquire 3D model data converted from 2D drawing data of the building. In addition, in the case of construction A, the integrated data generation unit 22 may acquire a 3D model of the building created by a prime contractor such as a general construction company.

[0045] (2.2) Linking step Next, in a linking step S2, the linking unit 21 links the work object to the target area of ​​the three-dimensional model. The process in the linking step S2 will be described in detail below.

[0046] (2.2.1) Target Area The linking unit 21 displays the three-dimensional model data acquired by the integrated data generating unit 22 from the measuring unit 1 on the display of the information terminal B1. The display form of the three-dimensional model on the display of the information terminal B1 may be either a perspective view or a floor plan (plan view), and it is preferable that the display form be switchable by operating the terminal.

[0047] For example, Fig. 4 shows a floor plan of a three-dimensional model M2 displayed on a display G1 of an information terminal B1. The three-dimensional model M2 includes a structure model M20, room models M21-M24, an element model M26, and a site model M27. The site model M27 is a three-dimensional model of the site on which the building stands. The structure model M20 is a three-dimensional model of the exterior structure of the building. The room models M21-M24 are three-dimensional models of each room in the building. The element model M26 is a three-dimensional model of an element of the building.

[0048] When an element model M26 is selected as the target area 9 by a terminal operation, the linking unit 21 automatically creates an element target area 91 corresponding to the element model M26. Then, the linking unit 21 links a work object including information on work performed during construction of a building to the element target area 91.

[0049] Furthermore, the linking unit 21 creates a spatial target area 92 corresponding to the space of the three-dimensional model M2 as the target area 9 through a terminal operation. If the display G1 is a touch panel display, the spatial target area 92 is set by performing an operation such as tapping, pinching, or dragging with a finger or the like on the surface of the display G1. Then, the linking unit 21 links the work object to the spatial target area 92.

[0050] (2.2.2) Work Objects The linking unit 21 links the task object OA shown in Fig. 5 to the target area 9. The task object OA has attributes "task type", "task position", and "task time", and is an object with a data structure in which information can be set for each attribute. The task object OA in Fig. 5 is in an unset state in which no information has been set for each attribute.

[0051] The work objects OA include a first work object OA1 linked to the element target area 91 described above, and a second work object OA2 linked to the spatial target area 92 described above.

[0052] The linking unit 21 sets element-specific information included in an element object OB, which will be described later, to each attribute of the first work object OA1.

[0053] The linking unit 21 sets information corresponding to the terminal operation for each attribute of the second task object OA2. Information corresponding to the content, scale, and scope of the construction work associated with the construction of the building is set for each attribute of the second task object OA2 by the terminal operation. For example, the task time is preferably a standard task time for one worker. Specifically, if the task type is transportation, the standard task time is set per meter of transport distance by one worker. Alternatively, the task time may be the standard task time plus additional time taking into account individual differences between workers.

[0054] In order to make the contents of the work object OA easy to understand, it is preferable to set a name, an icon, etc. to the work object OA.

[0055] (2.2.3) Element Objects 6 illustrates element models M261-M264 as four element models M26 included in the three-dimensional model. Element models M262 and M263 are arranged on the upper surface of element model M261, and element model M262 and element model M263 are connected by element model M264. In this case, element model M261 is a three-dimensional model of member P1 such as a substrate. Element model M262 is a three-dimensional model of equipment P2 such as an electric device. Element model M263 is a three-dimensional model of equipment P3 such as an electric device. Element model M264 is a three-dimensional model of member P4 such as wiring.

[0056] The element model M26 includes an element object OB for which element-specific information is set in advance. The element-specific information is information on an operation for which the element is the object.

[0057] The element object OB has attributes "element object name", "work position", "work type", and "work time", and the information set in each attribute corresponds to element-specific information. In the attribute "element object name" of the element object OB, the name of the element corresponding to the element object OB is set as element-specific name information. In the attribute "work position" of the element object OB, the element target area 91 of the element model M26 corresponding to the element object OB is set as element-specific position information. In the attribute "work type" of the element object OB, the type (name) of the work performed on the element model M26 during the construction of a building is set as element-specific type information. The types of work are, for example, "transport", "wiring", "piping", "assembly preparation", "assembly", and "inspection". In the attribute "work time" of the element object OB, the time required for the work set in "work type" is set as element-specific time information. Note that the element object OB may have one set of the attributes "work type" and "work time", or may have multiple sets of the attributes "work type" and "work time".

[0058] 7 shows element objects OB1-OB4, which are the element objects OB of the element models M261-M264. The element object OB1 of the element model M261 has a member P1 set in the "element object name" and a target area P2 set in the "work position". 911 The element object OB2 of the element model M262 has equipment P2 set in the "element object name" and the target area set in the "work location". 912 The element object OB3 of the element model M263 has the equipment P3 set in the "element object name" and the target area set in the "work location". 913 The element object OB4 of the element model M264 has the member P4 set in the "element object name" and the target area P4 set in the "work position". 914 is set, and each piece of information is also set in the group of "task type" and "task time."

[0059] (2.2.4) Linking The linking unit 21 links the work objects OA (first work object OA1, second work object OA2) to each of the target areas 9 (element target area 91, spatial target area 92).

[0060] (First work object) When a work object model OM (see FIG. 8), which is a model of the first work object OA1, is superimposed on an element model M26 of a three-dimensional model displayed on the display G1 of the information terminal B1 by a user's terminal operation, the linking unit 21 sets an element object OB1 of the element model M26 to the first work object OA1. The work object model OM is displayed on the display G1, and moves within the display G1 by performing an operation such as dragging with a finger on the display G1. In FIG. 8, the user moves the work object model OM to superimpose it on the element model M261. The process of superimposing the work object model OM on the element model M26 corresponds to the process of pasting the first work object OA1 on the element model M26.

[0061] In this case, as shown in Fig. 9A, the linking unit 21 sets (overwrites) the element-specific information of the element object OB1 of the element model M261 to the first work object OA1 of the work object model OM. Specifically, the linking unit 21 sets each of the element-specific information of the element object OB1, namely, the work position, work type, and work time, to the attributes "work position", "work type", and "work time" of the first work object OA1, respectively. Fig. 9B shows the first work object OA1 to which the element-specific information of the element object OB1 has been set. The first work object OA1 is linked to the target area 9 by the information of the element target area 91 set to the attribute "work position".

[0062] It is preferable that the linking unit 21 judges whether the element-specific information set for each attribute of the element object OB1 matches the first work object OA1. If the linking unit 21 judges that the element-specific information matches the first work object OA1, the linking unit 21 sets the element-specific information of the element object OB1 for each attribute of the first work object OA1. Specifically, the linking unit 21 compares each attribute of the element object OB1 with each attribute of the first work object OA1, and sets the element-specific information corresponding to the attribute of the first work object OA1 to the first work object OA1. The linking unit 21 does not set the element-specific information that does not match the attribute of the first work object OA1 to the first work object OA1.

[0063] (Second work object) The linking unit 21 links the second task object OA2 to the spatial target area 92 (see FIG. 4) of the three-dimensional model displayed on the display G1 of the information terminal B1 by the user's terminal operation. FIG. 10 shows the second task object OA2 with information set for each attribute. Information is set for the attributes "task position", "task type", and "task time" of the second task object OA2 by the user's terminal operation. The spatial target area 92 is set for the attribute "task position" of the second task object OA2. The type (name) of the task performed in the spatial target area 92 during the construction of the building is set for the attribute "task type" of the second task object OA2. The task types are, for example, "demolition", "demolition and transportation", "marking out", and "cleaning". The time required for the task set for the "task type" is set for the attribute "task time".

[0064] (2.3) Integrated data creation step In the integrated data creation step S3, the integrated data creation unit 22 creates integrated data based on the three-dimensional model created by the measurement unit 1 and the work object OA that the linking unit 21 links to the target area 9 of the three-dimensional model.

[0065] The integrated data generating unit 22 of this embodiment converts the format of the data of the three-dimensional model linked to the work object OA into a specific data format of 3D (three dimensions) data or Building Information Modelling (BIM) data, and treats the converted data as integrated data. Note that since BIM data provides a higher degree of freedom and real-time performance in setting attribute information, it is preferable to use BIM data as the integrated data.

[0066] The data format of the 3D model created by the measurement unit 1 is a general-purpose data format with an extension such as csv, json, xml, yaml, dxf, etc. In order to convert the data of the 3D model in such a general-purpose data format into BIM data, for example, an API (Application Programming Interface) is used. Alternatively, it is also possible to convert it into BIM data by using a web application on a server.

[0067] The integrated data generating unit 22 may generate the data in which the 3D model created by the measurement unit 1 is linked to the work object OA as integrated data without converting the data format. That is, the integrated data may be data including the 3D model created by the measurement unit 1 and the work object OA linked to the target area 9 of the 3D model by the linking unit 21.

[0068] (2.4) Communication unit, integrated data acquisition unit, and storage unit The communication unit 23 of the information terminal B1 and the communication unit 24 of the server device C1 are configured to be able to communicate with each other via a communication network NT1 including the Internet.

[0069] The communication unit 23 of the information terminal B1 transmits the integrated data generated by the integrated data generating unit 22 to the server device C1 via the communication network NT1.

[0070] In the server device C1, the communication unit 24 receives the various data transmitted via the communication network NT1. The integrated data acquisition unit 25 of the server device C1 extracts integrated data from the various data received by the communication unit 24, and stores the extracted integrated data in the storage unit 26. In other words, the storage unit 26 functions as a database that stores the integrated data.

[0071] By storing the integrated data, the integrated data generation system 2 can manage the construction process, such as specific work at the construction site and schedules. In other words, the integrated data generation system 2 can manage the construction process using a 3D model of the building. That is, the integrated data generation system 2 can digitize and centrally manage information related to work for each area of ​​the building by linking the work object OA to the target area 9 of the 3D model of the building to be constructed at each point before and during the construction of the building. As a result, the integrated data generation system 2 can simplify data management and can also standardize data management among multiple departments.

[0072] Furthermore, if the integrated data is BIM data, apart from the 3D model of the building, the work objects OA, and the element objects OB, it becomes easy to include other information related to the construction schedule, the construction labor resources, the construction costs, the pre-construction planning, and the contractors involved in the construction in the integrated data.

[0073] (3) Construction plan management system The construction plan management system A1 includes a measurement unit 1, an integrated data generation system 2, a data processing unit 3, a data output unit 4, and an output device 5. The data processing unit 3 includes a construction plan creation unit 31 and a feedback unit 32. The construction plan management system A1 processes each step of S11-S22 shown in the flowchart of FIG. 11. For example, in the construction work of C construction, the site agent often conducts a site survey and creates a schematic construction drawing and a construction plan, and the CAD operator in the office is in charge of the drawing. Examples of C construction include the installation of office lighting fixtures, air conditioning equipment, and ventilation equipment, interior construction, power line wiring construction, information wiring construction in the building, wireless equipment construction, and the installation of a building management system.

[0074] (3.1) 3D model acquisition step In the three-dimensional model acquisition step S11, similar to the three-dimensional model acquisition step S1 of the integrated data generating method shown in FIG.

[0075] In the 3D model acquisition step S11, the integrated data generation unit 22 may acquire 3D model data converted from 2D drawing data of the building. In addition, in the case of construction A, the integrated data generation unit 22 may acquire a 3D model of the building created by the prime contractor.

[0076] (3.2) Integrated Data Step Next, an integrated data step S12 performs processes similar to the linking step S2, the integrated data creation step S3, and the storage step S4 of the integrated data generation method shown in Fig. 3. That is, by the processes in the 3D model acquisition step S11 and the integrated data step S12, the integrated data including the 3D model and the work object OA linked to the target area 9 of the 3D model is stored in the storage unit 26.

[0077] At this point, the site agent can perform outline process design while checking the situation at the construction site and requests from site supervisors such as the client and the prime contractor. The site agent specifies the work targets for each day in the three-dimensional model as outline process design. The work targets are specified by linking the work object OA to the target area 9 of the three-dimensional model. For example, the linking unit 21 links the first work object OA1 to the element target area 91 of the element model M26 by attaching the first work object OA1 to the element model M26 of the three-dimensional model in response to the terminal operation of the site agent. In addition, the linking unit 21 sets a spatial target area 92 in the three-dimensional model in response to the terminal operation of the site agent, and links the second work object OA2 to the spatial target area 92.

[0078] The site agent can easily create a daily outline process flow by arranging the work objects OA (first work object OA1, second work object OA2) attached to the target area 9 (element target area 91, space target area 92) of the 3D model on the Gantt chart displayed on the display G1 of the information terminal B1. Also, when the equipment or materials used in the building are changed or the location of the equipment is changed due to an agreement with the client, other construction companies, or logistics companies, the outline process flow can be automatically corrected by extracting only the changes from the integrated data. Also, the outline process flow can be changed by replacing the work object OA. Also, by using a learning model constructed by machine learning using the procedure of creating and changing the Gantt chart in the outline process flow of past construction as training data, an outline process design can be automatically created, reducing the workload of the site agent.

[0079] (3.3) Work object confirmation step and notification step Next, in a work object confirmation step S13, the construction plan creation unit 31 determines whether or not there is any setting omission of a work object OA in the integrated data in the storage unit .

[0080] Specifically, when the site agent creates an outline process flow, he / she specifies a target range for the 3D model of the integrated data displayed on the display G1 of the information terminal B1. The construction plan creation unit 31 extracts all work objects OA included in the specified range and determines whether information is set for each attribute of the extracted work objects OA. In the work object confirmation step S13, the construction plan creation unit 31 defines a work object OA for which information is not set for at least one attribute as an unset work object.

[0081] If there is an unset work object, the construction plan creation unit 31 transmits information about the unset work object to the information terminal B1. The information terminal B1 notifies the site agent that there is an omission in setting the work object OA by displaying the information about the unset work object on the display G1 (notification step S20). That is, if there is an omission in setting the work object OA, the construction plan management system A1 causes the information terminal B1 to display the part of the omission in setting, and prompts the site agent to set the work object OA (for example, manually).

[0082] The construction plan creation unit 31 repeats the integrated data step S12, the work object confirmation step S13, and the notification step S20 until all the work objects OA have been set.

[0083] 12 shows first work objects OA11, OA12, and OA13 as examples of three first work objects OA1 with no missing settings. The first work object OA11 is the first work object OA1 linked to the target area 911 (see FIG. 6) (pasted on the element model M261). The first work object OA12 is the first work object OA1 linked to the target area 912 (see FIG. 6) (pasted on the element model M262). The first work object OA13 is the first work object OA1 linked to the target area 913 (see FIG. 6) (pasted on the element model M263).

[0084] (3.4) Flow Creation Steps Next, in the flow creation step S14, the construction plan creation unit 31 determines the order in which the tasks corresponding to each of the task objects OA are performed based on the task position information included in each of the multiple task objects OA. Then, the construction plan creation unit 31 develops the tasks for each task type of each task object OA in parallel. Then, the construction plan creation unit 31 creates an optimal work flow that shows the flow of tasks included in each of the multiple task objects OA. Furthermore, it is preferable that the construction plan creation unit 31 creates a process flow based on the optimal work flow. Note that this flow creation process may be performed on a Gantt chart.

[0085] The flow creation process will be described below using the first work objects OA11, OA12, and OA13 in FIG.

[0086] The construction plan creation unit 31 determines the work order of the first work objects OA11, OA12, and OA13 based on the position information (position in the target area 91) set in the attribute "work position" of each of the first work objects OA11, OA12, and OA13. For example, the construction plan creation unit 31 determines the work order that allows the work to be efficiently carried out based on the attribute "work position" of each of the first work objects OA11, OA12, and OA13, the movement line of the workers, the arrival status of the elements, the status of the workers, and the like. Here, as shown in FIG. 13A, the construction plan creation unit 31 creates a construction flow F1 that proceeds in the order of the first work objects OA11, OA12, and OA13.

[0087] Next, as shown in FIG. 13B, the construction plan creation unit 31 expands the first task object OA1 into each task type included in the first task object OA1 to create a workflow F2. The first task object OA11 is expanded into task types W11-W14 corresponding to the four task types included in the first task object OA11. The first task object OA12 is expanded into task types W21-W24 corresponding to the four task types included in the first task object OA12. The first task object OA13 is expanded into task types W31-W34 corresponding to the four task types included in the first task object OA13. The task types W11, W21, and W31 are "transportation". The task types W12, W22, and W32 are "wiring". The task types W13, W23, and W33 are "assembly". The task types W14, W24, and W34 are "inspection".

[0088] Next, the construction plan creation unit 31 creates an optimal work flow F3 by expanding the work types W11-W14, W21-W24, and W31-W34 of the work flow F2 in parallel, as shown in Fig. 14A. In Fig. 14A, the construction plan creation unit 31 creates an optimal work flow F3 in which up to three work types proceed simultaneously, assuming division of labor by up to three workers. In other words, the optimal work flow F3 is a flow that optimizes the flow of each work type in the work flow F2 so that each work of the first work objects OA11, OA12, and OA13 can be completed in the shortest time by the number of workers who can divide the labor.

[0089] Next, the construction plan creation unit 31 creates a process flow F4 that optimizes the work schedules of the first work objects OA11, OA12, and OA13 based on the optimal work flow F3, as shown in Fig. 14B. Here, "optimizing the work schedule" means creating a process flow F4 that can complete each of the work of the first work objects OA11, OA12, and OA13 in the shortest time with the number of workers who can be assigned the tasks.

[0090] For example, the construction plan creation unit 31 can automatically create an optimal work flow F3 using the work time for each work type. Furthermore, when the optimal work flow F3 is changed due to an agreement with the client, a logistics company, or a contractor in another industry, the construction plan creation unit 31 can read only the changes and change the process flow F4. Furthermore, when the construction plan creation unit 31 determines that the total work time of the process flow F4 exceeds the specified work time per day, it can extend the working hours of the workers or move some of the work objects OA to the construction flow (or Gantt chart) of the next day to modify the construction flow F1, work flow F2, optimal work flow F3, and process flow F4 of the day.

[0091] Furthermore, the site agent can modify the optimal work flow F3 by shifting the work type while assuming available workers based on the situation at the construction site and the planned construction costs.

[0092] (3.5) Flow confirmation step and notification step Next, in the flow confirmation step S15, the site agent specifies the target flow range for the optimal work flow F3 or process flow F4 displayed on the display G1 of the information terminal B1. The construction plan creation unit 31 extracts all work types included in the specified flow range and judges whether or not there is a missing setting of a work type in the flow.

[0093] If there is an omission in the setting of the work type, the construction plan creation unit 31 transmits information about the omission in the setting of the work type to the information terminal B1. The information terminal B1 notifies the site agent that there is an omission in the setting of the work type by displaying the information about the omission in the setting of the work type on the display G1 (notification step S21). That is, if there is an omission in the setting of the work type, the construction plan management system A1 causes the information terminal B1 to display the part where the setting is omitted, and prompts the site agent to set the work type (for example, manually).

[0094] The construction plan creation unit 31 repeats the flow confirmation step S15 and the notification step S21 until all the work types in the flow have been set.

[0095] When all work types in the flow have been set, the construction plan creation unit 31 includes each data of the created optimal work flow F3 and process flow F4 in the integrated data and stores it in the storage unit 26. That is, the integrated data includes each data of the 3D model of the building, the work object OA, the element object OB, the optimal work flow F3, and the process flow F4. Therefore, the construction plan management system A1 can centrally manage each information of the construction site using the integrated data.

[0096] The data output unit 4 outputs each data of the optimal workflow F3 and the process flow F4 to the output device 5. The output device 5 receives each data of the optimal workflow F3 and the process flow F4, and displays each data of the optimal workflow F3 and the process flow F4 on a display device.

[0097] (3.6) Construction planning steps Next, in the construction plan creation step S16, the construction plan creation unit 31 creates a daily construction plan using the work type and work time based on the optimal work flow F3 and the process flow F4. The construction plan creation unit 31 may use at least one of the optimal work flow F3 and the process flow F4 as a construction plan.

[0098] The site agent can estimate the number of workers that can be utilized and revise the construction plan based on the availability of workers, the situation at the construction site, the planned construction costs, and the like.

[0099] If the optimum work flow F3 and the process flow F4 need to be changed in conjunction with the correction of the construction plan by the site agent, the construction plan creation unit 31 changes the optimum work flow F3 and the process flow F4.

[0100] (3.7) Plan confirmation step and notification step Next, in a plan confirmation step S17, the construction plan preparation unit 31 judges the validity of the construction plan prepared in the construction plan preparation step S16.

[0101] For example, the construction plan creation unit 31 judges whether or not there is an error in the construction plan created in the construction plan creation step S16. If there is an error in the construction plan, the construction plan creation unit 31 transmits information about the error to the information terminal B1. The information terminal B1 notifies the site agent that there is an error in the construction plan by displaying the information about the error on the display G1 (notification step S22). That is, if there is an error in the construction plan, the construction plan management system A1 causes the information terminal B1 to display the location of the error and prompts the site agent to correct the error (for example, manually correct it).

[0102] Furthermore, if there is a bottleneck task with low work efficiency in the work plan, the construction plan creation unit 31 adds information about the bottleneck task and transmits the information about the bottleneck task to the information terminal B1. The information terminal B1 notifies the site agent that there is a bottleneck task by displaying the information about the bottleneck task on the display G1 (notification step S22). In other words, the construction plan management system A1 prompts the site agent to modify the construction plan in accordance with the bottleneck task.

[0103] The construction plan creation unit 31 repeats the plan confirmation step S17 and the notification step S22 until there are no more errors in the construction plan and no more bottleneck tasks.

[0104] When the errors in the construction plan and the bottleneck work are eliminated, the construction plan creation unit 31 includes the data of the created construction plan in the integrated data and stores it in the storage unit 26. That is, the integrated data includes each data of the 3D model of the building, the work object OA, the element object OB, the optimal work flow F3, the process flow F4, and the construction plan. Therefore, the construction plan management system A1 can centrally manage each information of the construction site by using the integrated data.

[0105] The data output unit 4 outputs the data of the construction plan to the output device 5. The output device 5 receives the data of the construction plan and displays the data of the construction plan on a display device (data output step).

[0106] (3.8) Estimate Creation Steps Next, in estimate creation step S18, the construction plan creation unit 31 creates an estimate for construction based on the construction plan created in the plan confirmation step S17.

[0107] Specifically, the construction plan creation unit 31 calculates the labor cost by accumulating the work time and the worker unit price of each work.

[0108] Furthermore, the construction plan creating unit 31 calculates the material cost by accumulating the prices of the elements corresponding to the element objects OB in the three-dimensional model.

[0109] In addition, the construction plan creation unit 31 determines the costs required for tools such as heavy machinery and equipment to be used in the work, as well as other necessary expenses.

[0110] Then, the construction plan creation unit 31 creates an estimate for construction using information such as labor costs, material costs, tool costs, and other necessary expenses.

[0111] The construction plan creation unit 31 includes the created estimate data in the integrated data and stores it in the storage unit 26. That is, the integrated data includes each data of the 3D model of the building, the work object OA, the element object OB, the optimal work flow F3, the process flow F4, the construction plan, and the estimate. Therefore, the construction plan management system A1 can centrally manage each information of the construction site by using the integrated data.

[0112] The data output unit 4 outputs the estimate data to the output device 5. The output device 5 receives the estimate data and displays the estimate data on a display device.

[0113] (3.9) Practical work feedback step At the construction site, each task is carried out according to the construction plan created by each of the processes S1-S18 and S20-S22 described above.

[0114] If the construction plan changes due to arrangements with each contractor, delays in the delivery of parts and equipment due to logistics issues, or worker-related issues, the site representative can change the start time of work and the working hours of workers, regardless of the current work plan.

[0115] For example, if the site manager determines that the time required for a certain task will significantly exceed the specified working hours per day, he or she will extend the workers' working hours or move some of the work objects (OA) to the next day's construction flow (or Gantt chart).

[0116] In addition, the work plan data can be accessed by the work manager and workers other than the site agent, and the work manager and workers can easily reflect the progress of the work in the work plan. Alternatively, the construction plan management system A1 can automatically collect the progress of the work using IoT devices such as cameras installed at the construction site.

[0117] The above-mentioned changes to the construction plan by the site manager, the input of the work progress by the work manager and workers, and the work progress collected by the IoT device reflect the actual work performance in the building and correspond to performance data according to the work performance.

[0118] Therefore, in the actual work feedback step S19, the feedback unit 32 acquires the performance data and updates the element-specific information of the element object OB in the integrated data based on the performance data. The element-specific information to be updated is, for example, information on the attribute "work time", but may also be information on the attribute "work level" described later.

[0119] For example, the feedback unit 32 measures or detects the number of workers, work time, and worker level for each work type based on the performance data, and stores them in the memory unit 26. Then, the feedback unit 32 analyzes influencing factor information such as design information (installation position, surrounding conditions, etc.), construction environment information (weather, delays in previous processes, schedule revisions, etc.), work learning effects (the higher up the building you go, the shorter the actual work time becomes), and worker characteristics (work efficiency decreases on weekends, etc.) using a learning model constructed by machine learning, and predicts variations in work time, etc.

[0120] In this way, by feeding back performance data, the feedback unit 32 can identify issues at the construction site and update the integrated data, particularly the element-specific information of element objects, to information that is appropriate for actual work.

[0121] (4) First Modification Fig. 15A shows a modified example of an element object OB. In addition to the attributes "element object name", "task position", "task type" and "task time", the element object OB may further have an attribute "task level". In the attribute "task level" of the element object OB, element-specific level information indicating the difficulty of the task set in the "task type" is set. In Fig. 15A, the difficulty level is represented by a number of 1, 2, or 3, and the higher the number, the higher the difficulty level.

[0122] 15B shows a modified example of a task object OA. The task object OA has attributes "task type", "task position", and "task time" as well as "task level". If the task object OA is a first task object OA1, the linking unit 21 sets the element-specific level information included in the element object OB to the attribute "task level" of the first task object OA1.

[0123] If the task object OA is the second task object OA2, the linking unit 21 sets the element-specific level information according to the terminal operation to the attribute "task level" of the first task object OA1.

[0124] In this modified example, by adding a "task level" to each attribute of the element objects OB and the task objects OA, a construction plan can be created that takes into account the degree of difficulty of the tasks.

[0125] (5) Second Modification It is preferable that the linking unit 21 links external information, which is information about the outside of the building, to the three-dimensional model.

[0126] The external information is information about the outside of the building, such as the site surrounding the building, the houses, shops, schools, and roads in the vicinity of the building.

[0127] The external information on the site surrounding the building includes construction passage information such as the dimensions between the exterior wall of the building and the outer edge of the site, neighboring house information such as agreements with neighboring houses regarding construction, and store information such as nearby stores, etc. Note that the specific content of the external information is not limited to the above content, and it may be any information on the outside of the building.

[0128] 16 shows a floor plan of a three-dimensional model M2 displayed on a display G1 of an information terminal B1. Then, the linking unit 21 links the external information input by terminal operation to the external information area 8 specified by terminal operation. At least one piece of external information is linked to one external information area 8, and multiple pieces of external information may be linked to one external information area 8.

[0129] 16, external information areas 81 and 82 are set as the external information area 8. The external information area 81 is formed outside the site model M27, and is linked to external information (neighborhood information) relating to an agreement with a neighboring house, such as "Agreement with Mr. / Ms. XX's house: construction hours possible from 9:00 a.m. to 5:00 p.m." The external information area 82 is formed in the space between the structure model M20 and the outer edge of the site model M27, and is linked to external information (construction path information), such as "Path width: 3 m, road condition: be careful of drainage."

[0130] If the external information area 8 is set to a model of a nearby store, the external information includes store information such as the type and business hours of the store, and the time required to reach the store.

[0131] As described above, the integrated data generation system 2 can reflect information about the surroundings of the building in the three-dimensional model M2 by linking the external information to the external information area 8. As a result, the external information is included in the integrated data.

[0132] (6) Third Modification The functions of the construction plan management system A1 may be distributed to a plurality of devices, and the plurality of devices may constitute the construction plan management system A1. For example, the construction plan management system A1 may be realized by cloud computing technology.

[0133] Furthermore, the construction plan management system A1 may be configured as a single device such as a personal computer.

[0134] Moreover, the construction plan management system A1 only needs to include at least the construction plan creation unit 31 and the data output unit 4.

[0135] In addition, in a data output step, the data output unit 4 outputs the data of the construction plan to the output device 5. If the integrated data in the storage unit 26 includes the construction plan, the data output unit 4 can output the data of the construction plan at any timing.

[0136] (summary) The integrated data generation system (2) of the first aspect according to the embodiment described above includes a linking unit (21) and a storage unit (26). The linking unit (21) links a work object (OA) including information on work to be performed during construction of a building to a target area (9) corresponding to a part of the building in a three-dimensional model (M1-M2) representing the three-dimensional shape of the building to be constructed. The storage unit (26) stores integrated data including data of the three-dimensional model (M1-M2) in which the work object (OA) is linked to the target area (9).

[0137] The above-mentioned integrated data generation system (2) can manage the construction process using a three-dimensional model of the building (M1-M2).

[0138] It is preferable that the integrated data generation system (2) of the second aspect according to the above-mentioned embodiment further includes an integrated data generation unit (22) that generates integrated data based on the three-dimensional model (M1-M2) and the work object (OA) linked to the target area (9) by the linking unit (21) in the first aspect.

[0139] The above-mentioned integrated data generation system (2) can manage the construction process using a three-dimensional model of the building (M1-M2).

[0140] In the integrated data generation system (2) of the third aspect according to the above-mentioned embodiment, in the first or second aspect, it is preferable that the linking unit (21) can set a target area (92) corresponding to the space of the building.

[0141] The above-mentioned integrated data generation system (2) can reflect the work object (OA) in space in the three-dimensional model (M1-M2).

[0142] In the integrated data generation system (2) of the fourth aspect of the above-mentioned embodiment, in any one of the first to third aspects, it is preferable that the linking unit (21) links external information, which is information about the outside of the building, to the three-dimensional model (M1-M2).

[0143] The integrated data generation system (2) described above can reflect information about the surroundings of a building in the three-dimensional model (M1-M2).

[0144] In the integrated data generating system (2) of the fifth aspect according to the above-mentioned embodiment, in any one of the first to fourth aspects, it is preferable that the attribute of the work object (OA) includes a type of work.

[0145] The above-mentioned integrated data generation system (2) can link a task object (OA) according to a task type to a target area (9).

[0146] In the sixth aspect of the integrated data generation system (2) according to the embodiment described above, in the fifth aspect, it is preferable that the attributes of the work object (OA) further include the location where the work is performed and the time required for the work.

[0147] The above-mentioned integrated data generation system (2) can link a task object (OA), in which a task type is associated with a task location and a task time, to a target area (9).

[0148] In the integrated data generation system (2) of the seventh aspect according to the embodiment described above, in the fifth or sixth aspect, the three-dimensional model (M1-M2) preferably includes an element model (M12, M26) corresponding to at least one element constituting the building. The element model (M12, M26) includes an element object (OB) in which element-specific information, which is information on work targeting the element, is set in advance. If the target area (9) corresponds to the element model (M12, M26), the linking unit (21) links the work object (OA1) to the target area (9, 91) by setting the element-specific information to the attribute of the work object (OA1).

[0149] The above-mentioned integrated data generation system (2) can link the work object (OA1) to the target area (9, 91) by associating the work object (OA1) with the element model (M12, M26) of the three-dimensional model (M1-M2).

[0150] In the integrated data generation system (2) of the eighth aspect of the above-mentioned embodiment, in the seventh aspect, it is preferable that the element-specific information includes element-specific type information indicating the type of work targeting the element, and element-specific time information indicating the time required for the work targeting the element.

[0151] The above-mentioned integrated data generation system (2) can reflect element-specific time information in the work object (OA1).

[0152] In the integrated data generation system (2) of the ninth aspect of the above-mentioned embodiment, in the eighth aspect, it is preferable that the element-specific information further includes element-specific level information indicating the difficulty level of the task targeting the element.

[0153] The above-mentioned integrated data generation system (2) can reflect element-level information in the work object (OA1).

[0154] In the integrated data generation system (2) of the tenth aspect according to the above embodiment, in any one of the seventh to ninth aspects, it is preferable that the linking unit (21) determines whether the element-specific information matches the work object (OA1). If the linking unit (21) determines that the element-specific information matches the work object (OA1), it sets the element-specific information to the attribute of the work object (OA1).

[0155] The above-mentioned integrated data generation system (2) can automatically reflect element-specific information in the work object (OA1).

[0156] The construction plan management system (A1) of the eleventh aspect according to the embodiment described above includes a construction plan creation unit (31) and a data output unit (4). The construction plan creation unit (31) creates a construction plan for the building based on integrated data including data of the three-dimensional model (M1-M2) in which a work object (OA) including information on work to be performed during the construction of the building is linked to a target area (9) corresponding to a part of the building in the three-dimensional model (M1-M2) that represents the three-dimensional shape of the building to be constructed. The data output unit (4) outputs the data of the construction plan.

[0157] The above-mentioned construction plan management system (A1) can manage the construction process by using the three-dimensional model (M1-M2) of the building.

[0158] In the construction plan management system (A1) of the twelfth aspect according to the embodiment described above, in the eleventh aspect, the work object (OA) includes information on the work type, which is the type of work, the work position, which is the position where the work is performed, and the work time, which is the time required for the work. The integrated data includes a plurality of work objects (OA). The construction plan creation unit (31) determines the order in which the work corresponding to each of the work objects (OA) is performed based on the work position information included in each of the plurality of work objects (OA). The construction plan creation unit (31) develops the work for each work type of each of the work objects (OA) in parallel. Then, it is preferable that the construction plan creation unit (31) creates an optimal work flow (F3) that indicates the flow of work included in each of the plurality of work objects (OA).

[0159] The above-mentioned construction plan management system (A1) creates an optimal work flow (F3) for carrying out work in parallel, so that it is possible to propose an efficient work flow.

[0160] The construction plan management system (A1) of the thirteenth aspect according to the above-mentioned embodiment is preferably further provided with a feedback unit (32) in the eleventh or twelfth aspect. The three-dimensional model (M1, M2) includes an element model (M12, M26) corresponding to at least one element constituting the building. The element model (M12, M26) includes an element object (OB) in which element-specific information, which is information on work targeting the element, is set in advance. If the target area (9) corresponds to the element model, the work object (OA1) includes the element-specific information as work information. The feedback unit (32) acquires performance data according to the performance of the work on the building, and updates the element-specific information based on the performance data.

[0161] The above-mentioned construction plan management system (A1) can update the element-specific information of the element objects to information suited to the actual work by feeding back the performance data.

[0162] The integrated data generating method of the fourteenth aspect according to the above-mentioned embodiment includes a linking step (S2) and a storage step (S4). The linking step (S2) links a work object (OA) including information on work to be performed during construction of a building to a target area (9) corresponding to a part of the building in a three-dimensional model (M1-M2) representing the three-dimensional shape of the building to be constructed. The storage step (S4) stores integrated data including at least data of the three-dimensional model (M1-M2) in which the work object (OA) is linked to the target area (9).

[0163] The above-mentioned integrated data generation method can manage the construction process using a three-dimensional model of the building (M1-M2).

[0164] The construction plan management method of the fifteenth aspect according to the embodiment described above includes a construction plan creation step (S16) and a data output step. The construction plan creation step (S16) creates a construction plan for the building based on integrated data including data of the three-dimensional model (M1-M2) in which a work object (OA) including information on work to be performed during the construction of the building is linked to a target area (9) corresponding to a part of the building in the three-dimensional model (M1-M2) that represents the three-dimensional shape of the building to be constructed. The data output step outputs the data of the construction plan.

[0165] The above-mentioned construction plan creation method can manage the construction process using a three-dimensional model (M1-M2) of the building.

[0166] A program according to a sixteenth aspect of the above-described embodiment causes a computer system to execute the integrated data generation method according to the fourteenth aspect.

[0167] The above mentioned program is able to manage the construction process using a three-dimensional model of the building (M1-M2).

[0168] A program according to a seventeenth aspect of the above-described embodiment causes a computer system to execute the construction plan management method according to the fifteenth aspect.

[0169] The above mentioned program is able to manage the construction process using a three-dimensional model of the building (M1-M2).

[0170] The above-described embodiment is merely an example of the present invention. Therefore, the present invention is not limited to the above-described embodiment, and various modifications can be made according to the design and the like without departing from the technical concept of the present invention. [Explanation of symbols]

[0171] 2. Integrated Data Generation System 21 Stringing section 22 Integrated Data Generation Department 26 Memory section 31 Construction Planning Department 32 Feedback section 4 Data output section 9 Target Area 91 Element Target Area (Target Area) 92 Spatial target area (target area) A1 Construction planning management system F3 Optimal Workflow M1-M2 3D model M12, M26 element models OA Work Objects OA1 First work object (work object) OA2 Second work object (work object) OB Element Object S2 pegging step S4 Memory Step S16 Construction planning steps

Claims

1. a linking unit that links a work object including information on work to be performed during construction of a building to a target area corresponding to a part of the building in a three-dimensional model that represents a three-dimensional shape of the building; a storage unit configured to store integrated data including data of the three-dimensional model in which at least the work object is linked to the target area; The attribute of the work object includes a type of the work, The three-dimensional model includes an element model corresponding to at least one element constituting the building, the element model includes an element object for which element-specific information, which is information on the work targeting the element, is set in advance; If the target area corresponds to the element model, the linking unit links the work object to the target area by setting the element-specific information to the attribute of the work object. Integrated data generation system.

2. The apparatus further includes an integrated data generating unit that generates the integrated data based on the three-dimensional model and the work object that is linked to the target area by the linking unit. The integrated data generation system of claim 1.

3. The linking unit can set the target area corresponding to the space of the building. The integrated data generating system according to claim 1 or 2.

4. The linking unit links external information, which is information about the outside of the building, to the three-dimensional model.

4. The integrated data generating system according to claim 1.

5. The attributes of the work object further include a location where the work is performed and a time required for the work.

5. The integrated data generating system according to any one of claims 1 to 4.

6. The element-specific information includes element-specific type information indicating a type of the work for the element, and element-specific time information indicating a time required for the work for the element. The integrated data generation system of claim 5.

7. The element-specific information further includes element-specific level information indicating the degree of difficulty of the task targeting the element. The integrated data generation system of claim 6.

8. The linking unit determines whether or not the element-specific information matches the work object, and if it determines that the element-specific information matches the work object, sets the element-specific information to the attribute of the work object. The integrated data generating system according to claim 6 or 7.

9. A construction plan creation unit that creates a construction plan for the building based on the integrated data of any one of the integrated data generation systems of claims 1 to 8; A data output unit that outputs the data of the construction plan. Construction planning management system.

10. The work object includes information on a work type, which is a type of the work, a work position, which is a position where the work is performed, and a work time, which is a time required for the work, the integrated data includes a plurality of the work objects; The construction plan creation unit includes: determining an order in which the tasks corresponding to each of the plurality of task objects are to be performed based on the task position information included in each of the plurality of task objects; The work for each of the work types of the work objects is expanded in parallel, An optimal work flow is created that indicates the flow of the work included in each of the plurality of work objects. The construction plan management system according to claim 9.

11. Further comprising a feedback unit. The three-dimensional model includes an element model corresponding to at least one element constituting the building, the element model includes an element object for which element-specific information, which is information on the work targeting the element, is set in advance; If the target area corresponds to the element model, the work object includes the element-specific information as information on the work, The feedback unit acquires performance data corresponding to the performance of the work in the building, and updates the element-specific information based on the performance data. The construction plan management system according to claim 9 or 10.

12. A linking step of linking a work object including information on work to be performed during construction of a building to a target area corresponding to a part of the building in a three-dimensional model representing the three-dimensional shape of the building to be constructed; and storing integrated data including data of the three-dimensional model in which at least the work object is associated with the target area; The attribute of the work object includes a type of the work, The three-dimensional model includes an element model corresponding to at least one element constituting the building, the element model includes an element object for which element-specific information, which is information on the work targeting the element, is set in advance; In the linking step, if the target area corresponds to the element model, the element-specific information is set to the attribute of the work object, thereby linking the work object to the target area. Integrated data generation methods.

13. A construction plan creation step of creating a construction plan for the building based on the integrated data of the integrated data generation method of claim 12; A data output step of outputting data of the construction plan. Construction planning management methods.

14. A method for causing a computer system to execute the integrated data generation method of claim 12. program.

15. A computer system that executes the construction plan management method of claim 13. program.

Citation Information

Patent Citations

  • Plant construction supporting system

    JP1998115096A

  • Device and system for processing information and storage medium

    JP2002163304A

  • Server device and information management system

    JP2013164681A

  • Building management support method, building management support program, and building management support device

    JP2017004227A

  • Construction support method and construction support system

    JP2019021190A