Main column replacement device and method for angle steel tower

The main column replacement device and method efficiently replace main pillars near the bend point in angle steel towers by using adjustable support frames and jacks, avoiding large-scale construction and lateral arm interference, while maintaining structural stability through temporary diagonal members.

JP7595834B2Active Publication Date: 2024-12-09DENRO CORP +2

Patent Information

Application Number
JP2020219998
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2020-12-15
Publication Date
2024-12-09
Estimated Expiration
2040-12-15

AI Technical Summary

Technical Problem

Existing methods for replacing main pillars in angle steel towers near the bend point are cumbersome, requiring large-scale construction work such as installing temporary steel towers, and face interference issues with lateral arms, leading to high costs and labor inefficiencies.

Method used

A main column replacement device and method that uses two fixing devices with support members, including adjustable elongated frames and jacks, allowing installation across the bend point without parallel alignment to the main pillars, and temporary diagonal members to maintain structural integrity.

Benefits of technology

Enables efficient replacement of main pillars near the bend point without large-scale construction, reduces interference with lateral arms, and maintains structural stability by creating a temporary truss structure, thus minimizing costs and labor.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007595834000001
    Figure 0007595834000001
  • Figure 0007595834000002
    Figure 0007595834000002
  • Figure 0007595834000003
    Figure 0007595834000003
Patent Text Reader

Abstract

To provide a main column material replacing device and a main column material replacing method for an angle steel iron tower, capable of replacing a main column material near a bent point with the main column material replacing device installed over the bent point of the main column material of the angle steel iron tower.SOLUTION: The main column material replacing device for the iron tower equipped with two fixing tools fixed to two main column materials connected to both ends of a replacement main column material and a support member installed between the two fixing tools, is constructed such that the fixing tools have connection metal fittings fixed to the outer side surfaces of the main column materials, pairs of long support frames fixed to the connection metal fittings, parallel to each other and installed at right angles to the main column materials, and joint metal fittings rotatably attached between the support frames. The support member has an upper end connection tool fixed to the joint metal fitting of the upper fixing tool, a support steel pipe formed by one or a plurality of unit members and adjustable in length depending on a used type and a number, and a jack fixed to the joint metal fitting of the lower fixing tool.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a main pillar replacement device and a main pillar replacement method for replacing the main pillars of an angle steel tower. [Background technology]

[0002] Generally, an angle steel tower comprises a tower body erected vertically from the ground and cross arms protruding horizontally from the tower body. The tower body comprises four main columns arranged vertically and extending to the top end of the tower body, a plurality of horizontal members arranged horizontally connecting adjacent main columns, and a plurality of diagonal members arranged at an angle to the main columns and horizontal members connecting adjacent main columns. The main columns are constructed by connecting a plurality of main column members made of angle steel with joints at their ends, overlapping the joints of each main column member and joining them with bolts and nuts.

[0003] The main poles are inclined so that they approach the other main poles diagonally as they go upward. The inclination angle of the main poles changes at a position (bend point) at a certain height from the ground, and the inclination angle of each main pole above the bend point is smaller than the inclination angle of each main pole from the ground to the bend point. As a result, each main pole is bent at the bend point. The cross arm is usually installed at a position above the bend point on the tower body.

[0004] When the main pillars of these angle steel towers become corroded, deformed, or otherwise damaged due to aging or disasters, the damaged main pillars are replaced. When replacing the main pillars, a temporary track is set up to bypass the power transmission route, and the power lines are removed from the angle steel tower before the main pillar replacement work can be carried out. However, there is a problem in that setting up the temporary track and changing the power transmission route is very expensive.

[0005] Therefore, a method of replacing the main pillars of an angle steel tower using a jack has been proposed. For example, a main pillar replacement device is used, which includes an upper fixing tool fixed to an upper main pillar connected to the upper side of the replacement main pillar, a lower fixing tool fixed to a lower main pillar connected to the lower side of the replacement main pillar, and a support member installed between the upper fixing tool and the lower fixing tool with a jack interposed therebetween, and the support member is pushed up by the jack to transfer the stress of the replacement main pillar to the support member, and then the replacement main pillar is removed, a new main pillar is inserted, and the new main pillar is assembled, thereby replacing the main pillar (see, for example, Patent Document 1). The support members installed between the upper fixing tool and the lower fixing tool are located on the left and right of the replacement main pillar when the tower body is viewed diagonally from the replacement main pillar side, and are installed in parallel with the replacement main pillar, the upper main pillar, and the lower main pillar.

[0006] However, the main pillar material replacement device in Patent Document 1 installs support members parallel to the replacement main pillar material, the upper main pillar material, and the lower main pillar material, and since the main pillar is bent with a changing inclination angle at the bend point, there was a problem that if the replacement main pillar material was a main pillar material near a bend point, the main pillar material replacement device could not be installed on the main pillar across the bend point.

[0007] In addition, the main pillar replacement device in Patent Document 1 has support members located on the left and right of the replacement main pillar when viewed diagonally from the replacement main pillar side, which means that the support members may interfere with the cross arm protruding laterally from the tower body, making it impossible to install the main pillar replacement device. In this case, it is necessary to remove the cross arm to install the main pillar replacement device.

[0008] Therefore, a method of replacing the main pillar material near the bend point of an angle steel tower is to use a height-raising method (see, for example, Patent Document 2). In this height-raising method, a temporary tower is installed on an existing tower to surround the upper part where the cross arm is installed, the power transmission line is removed from the cross arm and temporarily fixed to the temporary tower, and then the cross arm is removed from the tower and the temporary cross arm is installed on the temporary tower. After the power transmission line is transferred to this temporary cross arm, the tower is separated into a lower part that supports the temporary tower and an upper part that is surrounded by the temporary tower, and this upper part is raised to a specified height and supported by the temporary tower. After this, new members are assembled between the upper and lower parts of the tower, a new cross arm is installed at the upper part, and the power transmission line is transferred from the temporary cross arm. Finally, the temporary cross arm and the temporary tower are removed to obtain a raised tower. This height-raising method makes it possible to replace the main pillar material near the bend point of an angle steel tower. [Prior art documents] [Patent documents]

[0009] [Patent Document 1] JP 2011-149171 A [Patent Document 2] JP 2000-110407 A Summary of the Invention [Problem to be solved by the invention]

[0010] However, the method of replacing main pillar materials using the height-raising technique described in Patent Document 2 had the problem that the construction work was extremely large-scale, as it required the installation of a temporary tower to surround the upper part of the existing tower, where the cross arm was installed.

[0011] Therefore, the object of the present invention is to provide a main pillar material replacement device and a main pillar material replacement method for an angle steel tower, which can replace the main pillar material near the bend point by installing a main pillar material replacement device across the bend point of the main pillar, and which does not require large-scale construction such as installing a temporary tower large enough to surround the top of the existing tower, as is the case with conventional main pillar material replacement methods that utilize height-raising construction methods, thereby reducing the labor and cost of construction work. [Means for solving the problem]

[0012] In order to solve the above problems, the main pillar replacement device for an angle steel tower of the present invention is a main pillar replacement device for a tower equipped with two fixing devices fixed to each of the two main pillar materials connected to both ends of a replacement main pillar material, and a support member installed between these two fixing devices, wherein the fixing devices have a connecting fitting fixed to the outer surface of the main pillar material, a pair of long support frames fixed to the connecting fittings, parallel to each other, and installed perpendicular to the main pillar materials, and a connecting fitting rotatably attached between the pair of support frames, and the support member has an upper end connecting fitting fixed to the connecting fitting of the upper fixing device, a supporting steel pipe formed of one or more unit members whose overall length can be adjusted depending on the type and number used, and a jack fixed to the connecting fitting of the lower fixing device.

[0013] The connecting fitting is further characterized in that it is formed as an L-shaped body having a width greater than the flange width of the main pillar material, that the connecting fitting has a bolt hole on the inner surface of the L-shape for connecting to the main pillar material and bolt holes on both ends of the L-shape in the width direction for connecting to the support frame, and that the connecting fitting is fixed to the main pillar material by abutting the inner surface of the L-shape against the outer surface of the main pillar material.

[0014] Further, a bolt hole for connecting to the connecting fitting is provided near the center of the support frame, and holes for pin connection to the connecting fitting are provided at both ends of the support frame, and the pair of support frames are each fixed to both ends of the connecting fitting at the positions of the bolt holes provided near the center.

[0015] In addition, the connecting fitting of the upper fixing device which is fixed to the main column material connected to the upper side of the replacement main column material is formed as a box-shaped body which is open at the bottom, has a hole on the top surface for fixing the upper end connecting fitting of the support member, and has a hole on the side surface which faces the support frame for pin connection to the support frame, and is characterized in that the connecting fitting is connected to the support frame by inserting a pin through the hole on the side surface and through holes on both ends of the support frame.

[0016] In addition, the connecting fitting of the lower fixing device which is fixed to the main pillar material connected to the lower side of the replacement main pillar material is formed as a box-shaped body which is open at the top, has a hole on the bottom surface for fixing the jack of the support member, and has a hole on the side surface which faces the support frame for pin connection to the support frame, and is characterized in that the connecting fitting is connected to the support frame by inserting a pin through the hole on the side surface and through holes on both ends of the support frame.

[0017] The support member is also characterized by having a screw adjustment portion between the support steel pipe and the jack, the length of which can be adjusted according to the screw-threaded position.

[0018] The method for replacing main pillars of an angle steel tower of the present invention is characterized by comprising the steps of fixing connecting fittings to two main pillars connected to both ends of a replacement main pillar, fixing a support frame to the connecting fittings, rotatably connecting connecting fittings between a pair of support frames at both ends of the support frame, and fixing a fixing device to the main pillar; fixing a jack to the connecting fitting of the lower fixing device, connecting an upper end connecting device to the upper end of the support steel pipe, fixing the upper end connecting device to the connecting fitting of the upper fixing device, connecting a screw adjustment part between the support steel pipe and the jack, and installing a support member between the two fixing devices; extending the jack to transfer the load of the replacement main pillar to the support member; and removing the replacement main pillar and installing a new main pillar.

[0019] In addition, the method for replacing main pillar materials of an angle steel tower of the present invention is characterized by comprising the steps of fixing connecting fittings to two main pillar materials connected to both ends of a replacement main pillar material, fixing a support frame to the connecting fittings, rotatably connecting connecting fittings between a pair of support frames at both ends of the support frame, and fixing a fixing device to the main pillar material; fixing a jack to the connecting fitting of the lower fixing device, connecting an upper end connecting device to the upper end of the support steel pipe, fixing the upper end connecting device to the connecting fitting of the upper fixing device, connecting a screw adjustment part between the support steel pipe and the jack, and installing a support member between the two fixing devices; installing a temporary diagonal member between the main pillar having the replacement main pillar material and the adjacent main pillar in the area where the truss structure of the tower will be lost due to the removal of the replacement main pillar material; extending the jack to transfer the load of the replacement main pillar material to the support member; and removing the replacement main pillar material and installing a new main pillar material. Effect of the Invention

[0020] According to the main pillar material replacement device and main pillar material replacement method for an angle steel tower of the present invention, the connecting fitting of the upper fixing device to which the upper end connector of the support member is fixed is rotatably connected to the support frame of the upper fixing device by a pin, and the connecting fitting of the lower fixing device to which the jack of the support member is fixed is rotatably connected to the support frame of the lower fixing device by a pin, so that the main pillar material replacement device can be installed across the bend point where the inclination angle of the main pillar changes, and the main pillar material near the bend point can be replaced. In other words, the main pillar material replacement device can be installed in a location where the support member of the main pillar material replacement device is not parallel to the replacement main pillar material, the upper main pillar material, and the lower main pillar material.

[0021] In addition, when looking at the tower body diagonally from the side of the main pillar adjacent to the replacement main pillar material, the support members installed between the upper and lower fixtures are located on the left and right of the replacement main pillar material, with one support member located inside the tower body and the other outside the tower body, so that the support members do not interfere with the cross arm protruding laterally from the tower body, and the main pillar material replacement device can be installed. Therefore, the main pillar material near the bend point can be replaced without removing the cross arm.

[0022] Furthermore, the length of the support steel pipe of the support member can be adjusted by selecting the type and number of unit members, and the screw adjustment unit installed between the support steel pipe and the jack can adjust the length by adjusting the screw engagement position. This allows the combined length of the support member and the screw adjustment unit to be adapted to the distance between the two fasteners fixed to the main column material. Therefore, the fixing position of the fastener to the main column material can be selected with a high degree of freedom without being restricted by the length of the support member. As a result, the main column material replacement device can be installed on a variety of angle steel towers without being affected by the length of the replacement main column material or the installation conditions of metal fittings, bolts, etc. on the main column material that fixes the fastener, resulting in high versatility.

[0023] Furthermore, the angle steel tower is reinforced by temporary diagonal members installed between the main column having the replacement main column material and the adjacent main column. In particular, even if the connection of the diagonal members to the replacement main column material is released and the truss structure of the angle steel tower is lost due to the removal of the replacement main column material, a temporary truss structure can be formed by the temporary diagonal members. Therefore, the angle steel tower can be stably held even if the replacement main column material is removed.

[0024] Furthermore, the main pillar replacement device for an angle steel tower of the present invention is a device of simple configuration comprising two fasteners fixed to each of the two main pillar materials connected to both ends of the replacement main pillar material, and a support member installed between these two fasteners.Since it is installed between the two main pillar materials connected to both ends of the replacement main pillar material, there is no need to install a temporary tower large enough to surround the top of the existing tower, as is the case with conventional main pillar replacement methods that utilize height-raising construction methods, thereby reducing the work effort and costs involved in the construction work. [Brief description of the drawings]

[0025] [Figure 1] A front view showing an example of the installation state of the main pillar material replacement device of the present invention. [Diagram 2] 2 is a plan view of the upper fixture as seen from line AA in FIG. 1. [Diagram 3] FIG. 13 is a top view of the connecting fittings of the upper fixture and the lower fixture. [Figure 4]4 is a front view of the connecting fitting as seen from line BB in FIG. 3. [Diagram 5] 4 is a side view of the connecting fitting as seen from line CC in FIG. 3. [Figure 6] FIG. 3 is a cross-sectional view of the upper fixture taken along line DD in FIG. 2. [Figure 7] 13 is a side view showing the surface of the connecting fitting of the upper fixing device that faces the support frame. FIG. [Figure 8] 2 is a plan view of the lower fixture as seen from line EE in FIG. 1. [Figure 9] 9 is a cross-sectional view of the lower fixture taken along line FF in FIG. 8. [Figure 10] 13 is a side view showing the surface of the connecting fitting of the lower fixing device that faces the support frame. FIG. [Figure 11] This is a front view showing an example of the installation state of the main pillar material replacement device of the present invention (a view of the tower body diagonally from the side of the main pillar material adjacent to the replacement main pillar material). [Figure 12] This is a diagram showing an example of a cross-section of a tower body after a main pillar material replacement device has been installed. [Figure 13A] FIG. 1 is a schematic diagram showing an example of a steel tower in which a main pillar material is replaced. [Figure 13B] This is a schematic diagram showing the appearance after the main pillar material of the tower has been removed. [Figure 14A] FIG. 13 is a schematic diagram showing an example of another steel tower in which the main pillar material is replaced. [Figure 14B] This is a schematic diagram showing the appearance of removing the main pillar material of the tower without installing temporary diagonal materials. [Figure 14C] This is a schematic diagram showing the state after temporary diagonal members have been installed and the main pillar members of the tower have been removed. [Figure 15] FIG. 1 is a schematic diagram showing an example of a temporary diagonal member. [Figure 16] FIG. 1 is a front view showing an example of an angle steel tower. [Figure 17] FIG. 2 is an enlarged front view showing an example of the vicinity of the middle part of an angle steel tower. [Figure 18] FIG. 1 is a diagram showing an example of a cross section of a tower body. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0026] Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

[0027] FIG. 16 is a front view showing an example of an angle steel tower, and FIG. 17 is an enlarged front view showing an example of an angle steel tower near its middle part. The angle steel tower 100 includes a tower body 101 erected vertically from the ground, and an arm 102 protruding horizontally from the tower body 101. The tower body 101 includes four main columns 111 arranged vertically and extending to the upper end of the tower body 101. The tower body 101 also includes a plurality of horizontal members 112 arranged horizontally and connecting adjacent main columns 111, and a plurality of diagonal members 113 arranged at an angle with respect to the main columns 111 and the horizontal members 112 and connecting adjacent main columns 111. In addition, a cross-section member 116 is installed in the rectangular cross section of the tower body 101 to suppress deformation of the cross section, as shown in FIG. 18.

[0028] Each main pillar 111 is constructed by connecting a plurality of main pillar materials 114 formed of angle steel having joints at their ends, overlapping the joints of each main pillar material 114 and joining them with bolts and nuts. Each main pillar 111 is inclined so as to approach the other main pillar 111 located diagonally as it moves upward. The inclination angle of this main pillar 111 changes at a position (bend point 115) at a predetermined height from the ground, and the inclination angle of each main pillar 111 above the bend point 115 is smaller than the inclination angle of each main pillar 111 from the ground to the bend point 115. As a result, each main pillar 111 is bent at the bend point 115.

[0029] Each cross arm 102 is usually installed at a position above the bend point 115 of the tower body 101, and has a pair of cross arm main members 121 protruding laterally (left and right when viewed from the front of the tower in Figs. 16 and 17) from the tower body 101. Also, each cross arm 102 has a pair of cross arm suspension members 122 protruding from the tower body 101 and arranged so as to be inclined relative to the cross arm main member 121, connecting the tower body 101 and the tip of the cross arm main member 121.

[0030] Fig. 1 is a front view showing an example of the installation state of the main pillar replacement device 1 of the present invention, and shows an example in which the bend point 115 of the tower body 101 is located at the lower main pillar material 11 connected to the lower side of the replacement main pillar material 9. The main pillar replacement device 1 of the present invention comprises an upper fixing tool 2 fixed to the upper main pillar material 10 connected to the upper side of the replacement main pillar material 9, a lower fixing tool 3 fixed to the lower main pillar material 11 connected to the lower side of the replacement main pillar material 9, and a support member 4 installed between the upper fixing tool 2 and the lower fixing tool 3. The upper main pillar material 10 has a bolt hole for connecting the upper fixing tool 2, and the lower main pillar material 11 has a bolt hole for connecting the lower fixing tool 3.

[0031] First, we will explain the upper fixing device 2 that is fixed to the upper main pillar material 10. Fig. 2 is a plan view of the upper fixing device 2 as seen from line AA in Fig. 1. The upper fixing device 2 is composed of a connecting fitting 12, a support frame 13, a connecting fitting 14, and a pin 21.

[0032] Fig. 3 is a top view of the connecting fittings 12, 22 of the upper fixing tool 2 and the lower fixing tool 3, Fig. 4 is a front view of the connecting fittings 12, 22 as viewed from line BB in Fig. 3, and Fig. 5 is a side view of the connecting fittings 12, 22 as viewed from line CC in Fig. 3. The connecting fittings 12 of the upper fixing tool 2 are formed as L-shaped bodies with a width larger than the flange width of the upper main column material 10, and a bolt hole 15 for connecting to the upper main column material 10 is provided on the inner surface of the L-shape, and bolt holes 16 for connecting to the support frame 13 are provided at both ends of the connecting fitting 12 in the width direction. The inner surface of the L-shape of the connecting fitting 12 is abutted against the outer surface of the upper main column material 10, and bolts are inserted into the bolt holes for connecting to the upper fixing tool 2 of the upper main column material 10 and the bolt holes 15 for connecting to the upper main column material 10 of the connecting fitting 12, and the connecting fitting 12 is fixed to the upper main column material 10 by connecting with bolts and nuts.

[0033] The support frame 13 of the upper fixture 2 is formed of a long groove-shaped body, and a bolt hole 17 for connecting to the connecting fitting 12 is provided near the center of the support frame 13, and holes 18 for pin connection to the connecting fitting 14 are provided at both ends of the support frame 13. A bolt is inserted into the bolt hole 17 for connecting to the connecting fitting 12 of the support frame 13 and the bolt hole 16 for connecting to the support frame 13 of the connecting fitting 12, and the pair of support frames 13 are fixed to both ends of the connecting fitting 12 in the width direction by connecting with a bolt nut. The pair of support frames 13 fixed to the connecting fitting 12 in this way are parallel to each other and are installed at right angles to the upper main column material 10. In addition, two connecting fittings 14 are rotatably attached between the pair of support frames 13 at both ends of the support frame 13, and in the plan view of the upper fixture 2 shown in FIG. 2, the upper fixture 2 is formed in a rectangular shape by the pair of support frames 13 and the two connecting fittings 14. The upper fixing device 2 is fixed to the upper main pillar material 10 so that the upper main pillar material 10 passes through the center of this rectangle in the vertical direction.

[0034] Fig. 6 is a cross-sectional view of the upper fixing device 2 taken along line DD in Fig. 2, and Fig. 7 is a side view showing the surface of the connecting fitting 14 of the upper fixing device 2 facing the support frame 13. The connecting fitting 14 of the upper fixing device 2 is formed in a box shape with an open bottom, and has a bolt hole 20 for fixing the support member 4 on the top surface, and a hole 19 for pin connection to the support frame 13 on the side surface facing the support frame 13. The two connecting fittings 14 are rotatably attached between the pair of support frames 13 by inserting a pin 21 through the hole 19 for pin connection to the support frame 13 of the connecting fitting 14 and the hole 18 for pin connection to the connecting fitting 14 of the support frame 13.

[0035] Next, we will explain the lower fixing device 3 that is fixed to the lower main pillar material 11. Fig. 8 is a plan view of the lower fixing device 3 seen from the line EE in Fig. 1. Like the upper fixing device 2, the lower fixing device 3 is composed of a connecting metal fitting 22, a support frame 23, a connecting metal fitting 24, and a pin 21.

[0036] The connecting fitting 22 of the lower fixing device 3 has the same shape as the connecting fitting 12 of the upper fixing device 2, and as shown in Figures 3 to 5, is formed as an L-shaped body with a width larger than the flange width of the lower main pillar material 11, with bolt holes 25 for connection to the lower main pillar material 11 provided on the inner surface of the L shape, and bolt holes 16 for connection to the support frame 23 provided at both ends of the connecting fitting 22 in the width direction. The inner surface of the L shape of the connecting fitting 22 is abutted against the outer surface of the lower main pillar material 11, and bolts are inserted through the bolt holes for connection to the lower fixing device 3 of the lower main pillar material 11 and the bolt holes 25 for connection to the lower main pillar material 11 of the connecting fitting 22, and the connecting fitting 22 is fixed to the lower main pillar material 11 by connecting with bolts and nuts.

[0037] The support frame 23 of the lower fixture 3 has the same shape as the support frame 13 of the upper fixture 2, and is formed of a long groove-shaped body. A bolt hole 17 for connecting to the connecting fitting 22 is provided near the center of the support frame 23, and holes 18 for pin connection to the connecting fitting 24 are provided at both ends of the support frame 23. The pair of support frames 23 are fixed to both ends of the connecting fitting 22 in the width direction by inserting bolts into the bolt holes 17 for connecting to the connecting fitting 22 of the support frame 23 and the bolt holes 16 for connecting to the supporting frame 23 of the connecting fitting 22 and connecting with bolt nuts. The pair of support frames 23 fixed to the connecting fitting 22 in this way are parallel to each other and installed at right angles to the lower main column material 11. Furthermore, two connecting fittings 24 are rotatably attached between the pair of support frames 23 at both ends of the support frame 23, and in the plan view of the lower fixing device 3 shown in Fig. 8, the lower fixing device 3 is formed into a rectangular shape by the pair of support frames 23 and the two connecting fittings 24. The lower fixing device 3 is fixed to the lower main pillar material 11 so that the lower main pillar material 11 passes through the center of this rectangular shape in the vertical direction.

[0038] Fig. 9 is a cross-sectional view of the lower fixing device 3 taken along line FF in Fig. 8, and Fig. 10 is a side view showing the surface of the connecting fitting 24 of the lower fixing device 3 facing the support frame 23. The connecting fitting 24 of the lower fixing device 3 is formed in a box-like body with an open top, with a hole 26 for fixing the jack 5 provided on the bottom surface, and a hole 19 for pin connection to the support frame 23 provided on the side surface facing the support frame 23. The two connecting fittings 24 are rotatably attached between the pair of support frames 23 by inserting and connecting the pin 21 through the hole 19 for pin connection to the support frame 23 of the connecting fitting 24 and the hole 18 for pin connection to the connecting fitting 24 of the support frame 23.

[0039] Next, the support member 4 installed between the upper fixture 2 and the lower fixture 3 will be described. The support member 4 has an upper end connector 7, a support steel pipe 8, and a jack 5. The support steel pipe 8 is formed of steel pipe pieces 8a, 8b, 8c, and 8d as unit members of multiple types of different lengths. After the upper fixture 2 is fixed to the upper main column material 10 and the lower fixture 3 is fixed to the lower main column material 11, the type and number of the steel pipe pieces 8a, 8b, 8c, and 8d are set according to the distance between the upper fixture 2 and the lower fixture 3, making it possible to adjust the length of the support member 4 with a high degree of freedom.

[0040] The upper end connector 7 is connected to the upper end of the support steel pipe 8. The upper end connector 7 has a threaded portion 7a formed with a male screw, a connection steel pipe 7b with the threaded portion 7a fixed to the upper end, and a nut 7c screwed onto the threaded portion 7a. The threaded portion 7a is formed to a diameter that can be inserted into a bolt hole 20 for fixing the support member 4 provided on the upper surface of the connection fitting 14 of the upper fixing bracket 2. The upper end connector 7 is fixed to the connection fitting 14 by inserting the threaded portion 7a into the bolt hole 20 for fixing the support member 4 provided on the upper surface of the connection fitting 14 of the upper fixing bracket 2 and screwing the nut 7c onto the threaded portion 7a. In addition, the lower end of the connection steel pipe 7b is fixed to the upper end of the support steel pipe 8a. As a result, the support member 4 is fixed to the connection fitting 14 of the upper fixing bracket 2 via the upper end connector 7.

[0041] The jack 5 has a cylinder 5a, a rod 5b, and a rod connection steel pipe 5c. The cylinder 5a is fixed to a hole 26 for fixing the jack 5 provided on the underside of the connection fitting 24 of the lower fixture 3, and is connected to a hydraulic pump (not shown). The rod connection steel pipe 5c has its lower end fixed to the tip of the rod 5b driven forward and backward by the cylinder 5a, and its upper end fixed to the lower end of the support steel pipe 8d or a screw adjustment part 6 described later. When transferring a load between the replacement main column material 9 and the support member 4, the jack 5 adjusts the distance between the upper fixture 2 and the lower fixture 3 by driving the cylinder 5a to extend and retract based on the operation of the hydraulic pump by the operator.

[0042] In addition, the support member 4 may be connected to a screw adjustment part 6 between the support steel pipe 8 and the jack 5, the length of which can be adjusted according to the screw threading position. The screw adjustment part 6 is composed of a screw body 6a formed with a male screw, an upper flange 6b screwed into the upper part of the screw body 6a, a lower flange 6c fixed to the upper end of the rod connection steel pipe 5c of the jack 5 and screwed into the lower part of the screw body 6a, and a screw connection steel pipe 6d fixed to the lower end of the support steel pipe 8d and having the upper flange 6b fixed to its lower end. This screw adjustment part 6 is adapted to adjust the overall length in the axial direction by rotating the upper flange 6b or the lower flange 6c relative to the screw body 6a. After adjusting the overall length of the support member 4 according to the type and number of the support steel pipes 8a, 8b, 8c, and 8d, it is possible to accurately match the overall length of the support member 4 and the screw adjustment part 6 according to the distance between the upper fixture 2 and the lower fixture 3 by adjusting the overall length of the screw adjustment part 6. Although the screw adjustment part 6 is usually connected between the supporting steel pipe 8 and the jack 5, it may be connected between the supporting steel pipe 8 and the upper end connector 7. In this case, the screw adjustment part 6 is connected by fixing the screw connection steel pipe 6d to the lower end of the upper end connector 7 and fixing the lower flange 6c to the upper end of the supporting steel pipe 8a.

[0043] Next, a method for replacing the replacement main pillar material 9 of the angle steel tower 100 using the main pillar material replacement device 1 of the present invention configured as described above will be described. Here, an example will be described in which the main pillar material replacement device 1 is installed across the bend point 115 of the main pillar 111 of the angle steel tower 100, and the replacement main pillar material 9 directly above the bend point 115 is replaced. Figure 11 is a front view showing an example of the installation state of the main pillar material replacement device 1 when the tower body 101 is viewed diagonally from the side of the main pillar material adjacent to the replacement main pillar material 9.

[0044] In the first step, holes are drilled in the main pillar materials 10, 11 connected to the upper and lower sides of the replacement main pillar material 9 to install the upper and lower fixing devices 2 and 3 of the main pillar material replacement device 1.

[0045] First, drilling is performed to fix the upper fixing tool 2 of the main column replacement device 1 to the upper main column material 10 connected to the upper side of the replacement main column material 9. The diameter and arrangement of the bolt holes provided in this upper main column material 10 for connecting to the upper fixing tool 2 correspond to the bolt holes 15 provided in the connecting fitting 12 of the upper fixing tool 2 for connecting to the upper main column material 10. Next, drilling is performed to fix the lower fixing tool 3 of the main column replacement device 1 to the lower main column material 11 connected to the lower side of the replacement main column material 9. The diameter and arrangement of the bolt holes provided in this lower main column material 11 for connecting to the lower fixing tool 3 correspond to the bolt holes 25 provided in the connecting fitting 22 of the lower fixing tool 3 for connecting to the lower main column material 11.

[0046] In the second step, the lower fixing device 3 is fixed to the lower main pillar material 11 that is connected to the lower side of the replacement main pillar material 9.

[0047] First, the connecting metal fitting 22 of the lower fixing device 3 is positioned so that the inner surface of the L-shape abuts against the outer surface of the lower main pillar material 11. At this time, the bolt holes 25 for connecting to the lower main pillar material 11 provided in the connecting metal fitting 22 are positioned so as to overlap with the bolt holes for connecting to the lower fixing device 3 on the lower main pillar material 11, and the connecting metal fitting 22 of the lower fixing device 3 is fixed to the lower main pillar material 11 by inserting bolts into these bolt holes and connecting with bolt nuts.

[0048] Next, the support frame 23 is fixed to the connecting fitting 22 fixed to the lower main pillar material 11. At this time, the bolt holes 17 for connecting to the connecting fitting 22 provided near the center of the support frame 23 are arranged so as to overlap with the bolt holes 16 for connecting to the support frame 23 provided at both ends of the connecting fitting 22 in the width direction, and the pair of support frames 23 are fixed to both ends of the connecting fitting 22 in the width direction by inserting bolts through these bolt holes 16, 17 and connecting with bolt nuts. The pair of support frames 23 fixed to the connecting fitting 22 in this way are parallel to each other and installed at right angles to the lower main pillar material 11.

[0049] Next, the connecting fittings 24 are attached to the support frames 23 fixed to the linking fittings 22. At this time, the connecting fittings 24 are positioned between the pair of support frames 23 so that holes 19 for pin connection to the support frames 23, which are provided on the side of the connecting fittings 24, overlap with holes 18 for pin connection to the connecting fittings 24, which are provided at both ends of the support frames 23, and the pins 21 are inserted through these holes 18, 19 to connect, thereby rotatably attaching the two connecting fittings 24 between the pair of support frames 23.

[0050] By the above-mentioned second process, in a plan view of the lower fixing device 3 shown in Figure 8, the lower fixing device 3 is formed into a rectangular shape by a pair of support frames 23 and two connecting fittings 24, and the lower fixing device 3 is fixed to the lower main pillar material 11 so that the lower main pillar material 11 penetrates the center of this rectangular shape in the vertical direction.

[0051] In the third step, the upper fixing device 2 is fixed to the upper main pillar material 10 that is connected to the upper side of the replacement main pillar material 9.

[0052] First, the connecting metal fitting 12 of the upper fixing device 2 is positioned so that the inner surface of the L-shape abuts against the outer surface of the upper main pillar material 10. At this time, the bolt holes 15 for connecting to the upper main pillar material 10 provided in the connecting metal fitting 12 are positioned so as to overlap with the bolt holes for connecting to the upper fixing device 2 on the upper main pillar material 10, and the connecting metal fitting 12 of the upper fixing device 2 is fixed to the upper main pillar material 10 by inserting bolts into these bolt holes and connecting with bolt nuts.

[0053] Next, the support frame 13 is fixed to the connecting fitting 12 fixed to the upper main pillar material 10. At this time, the bolt holes 17 for connecting to the connecting fitting 12 provided near the center of the support frame 13 are arranged so as to overlap with the bolt holes 16 for connecting to the support frame 13 provided at both ends of the connecting fitting 12 in the width direction, and the pair of support frames 13 are fixed to both ends of the connecting fitting 12 in the width direction by inserting bolts through these bolt holes 16, 17 and connecting with bolt nuts. The pair of support frames 13 fixed to the connecting fitting 12 in this way are parallel to each other and installed at right angles to the upper main pillar material 10.

[0054] Next, the connecting fittings 14 are attached to the support frames 13 fixed to the connecting fittings 12. At this time, the connecting fittings 14 are placed between the pair of support frames 13 so that holes 19 for pin connection to the support frames 13, which are provided on the side of the connecting fittings 14, overlap with holes 18 for pin connection to the connecting fittings 14, which are provided at both ends of the support frames 13, and the two connecting fittings 14 are rotatably attached between the pair of support frames 13 by inserting pins 21 through these holes 18, 19 to connect them.

[0055] By the above-mentioned third step, in a plan view of the upper fixing device 2 shown in Figure 2, the upper fixing device 2 is formed into a rectangular shape by a pair of support frames 13 and two connecting fittings 14, and the upper fixing device 2 is fixed to the upper main pillar material 10 so that the upper main pillar material 10 passes through the center of this rectangular shape in the vertical direction.

[0056] In the fourth step, the support member 4 is installed between the upper fixture 2 and the lower fixture 3. Here, the case where the screw adjustment part 6 is connected between the supporting steel pipe 8 and the jack 5 will be described.

[0057] Once the upper and lower fixtures 2 and 3 have been fixed to the main pillar materials 10, 11 connected to the upper and lower sides of the replacement main pillar material 9, the cylinder 5a of the jack 5 is fixed to the connecting fitting 24 of the lower fixture 3, hydraulic piping is connected to the cylinder 5a, and the jack 5 is operably installed on the lower fixture 3. Then, the lower flange 6c of the screw adjustment part 6 is fixed to the upper end of the rod connection steel pipe 5c of the jack 5, and the jack 5 and the screw adjustment part 6 are connected.

[0058] After this, the distance between the upper fixture 2 and the lower fixture 3 is measured, the length of the supporting steel pipe 8 that matches the measured value is set, and the type and number of steel pipe pieces 8a, 8b, 8c, and 8d that match this set length are determined. The determined type and number of steel pipe pieces 8a, 8b, 8c, and 8d are connected to each other to form the supporting steel pipe 8, and the upper end connector 7 is connected to the upper end of this supporting steel pipe 8. The upper end connector 7 is fixed to the connector 14 by inserting the threaded portion 7a into the bolt hole 20 for fixing the supporting member 4 provided on the upper surface of the connector 14 of the upper fixture 2 and screwing the nut 7c into the threaded portion 7a. As a result, the supporting member 4 is fixed to the connector 14 of the upper fixture 2 via the upper end connector 7.

[0059] Note that the upper fixing device 2 is fixed to the upper main pillar material 10 above the bend point 115, and the lower fixing device 3 is fixed to the lower main pillar material 11 below the bend point 115, so that the upper fixing device 2 and the lower fixing device 3 have different inclination angles. In order to install a linear support member 4 between the upper fixing device 2 and the lower fixing device 3 which have different inclination angles, the connecting fitting 14 of the upper fixing device 2 is rotated at the pin 21 position, and the connecting fitting 24 of the lower fixing device 3 is rotated at the pin 21 position, and the angle of the connecting fittings 14, 24 is set to an angle that allows the linear support member 4 to be installed between the upper fixing device 2 and the lower fixing device 3.

[0060] Thereafter, the screw body 6a of the screw adjustment part 6 is rotated relative to the lower flange 6c, and the upper flange 6b and the screw-connection steel pipe 6d are also rotated relative to the screw body 6a to adjust the length of the screw adjustment part 6. When the flange at the upper end of the screw-connection steel pipe 6d comes into contact with the flange at the lower end of the steel pipe piece 8d provided at the lower end of the support steel pipe 8 by adjusting the length of the screw adjustment part 6, the screw-connection steel pipe 6d and the steel pipe piece 8d are fixed with bolts and nuts. In this way, the two sets of support members 4 and screw adjustment parts 6 are installed between both ends of the upper fixture 2 and the lower fixture 3, with their respective overall lengths adjusted.

[0061] The support members 4 installed between both ends of the upper fixture 2 and the lower fixture 3 are located on the left and right of the replacement main pillar material 9 when the tower body 101 is viewed diagonally from the main pillar material side adjacent to the replacement main pillar material 9, as shown in Figs. 11 and 12, with one support member 4 being arranged inside the tower body 101 and the other support member 4 being arranged outside the tower body 101. At this time, if the support member 4 arranged inside the tower body 101 interferes with the cross-section member 116 installed on the cross-section of the tower body 101, the interfering cross-section member 116 is removed. If the strength of the cross-section of the tower body 101 is insufficient due to the removal of the cross-section member 116, reinforcement is performed by increasing the member size of the cross-section member 116 on the non-interfering side, or by installing a temporary material at a position that does not interfere with the support member 4 on the cross-section of the tower body 101. The installation of the main pillar material replacement device 1 across the bend point 115 of the main pillar 111 is completed by the above-mentioned first to fourth steps.

[0062] In the fifth step, if necessary, a temporary diagonal member 27 is installed between a main column P having a replacement main column material 9 and an adjacent main column PN.

[0063] In the replacement of the main pillar material of the angle steel tower 100 with a double Warren truss structure as shown in FIG. 13A, when the replacement main pillar material 9 is removed, the load transmission function of the diagonal members 113a and 113b is lost as shown in FIG. 13B. On the other hand, the load transmission function of the diagonal members 113c and 113d remains, so that the single Warren truss structure composed of these diagonal members 113c and 113d remains. Therefore, since the load on the adjacent main pillar PN and the main pillar material replacement device 1 is relatively small, the replacement of the replacement main pillar material 9 can be performed without installing a temporary diagonal member. Note that in FIG. 13, the cross arm 102 is omitted, and the members in the tower body 101 that substantially lose the load transmission function are shown by dashed lines.

[0064] On the other hand, when the replacement main column material 9 has two or more member connection points as shown in FIG. 14A, when the replacement main column material 9 is removed, as shown in FIG. 14B, the load transmission function of the diagonal members 113a, 113b, 113c, and 113d is lost, and the load transmission function of the diagonal members 113f and 113g is also lost. Therefore, the truss structure is lost. Therefore, as shown in FIG. 14C, a temporary diagonal member 27 is installed between the main column P having the replacement main column material 9 and the adjacent main column PN, and a temporary single Warren truss structure composed of the diagonal member 113e and the temporary diagonal member 27 is formed. In FIG. 14, the cross arm 102 is omitted, and the members in the tower body 101 that substantially lose the load transmission function are shown by dashed lines.

[0065] The temporary diagonal member 27 may have any structure as long as it can be installed between the main columns P and PN of the angle steel tower 100 and has a load transmission capacity, but it is preferable that the temporary diagonal member 27 can be installed without removing the existing diagonal members 113 and horizontal members 112 and has a structure that allows the length to be adjusted. For example, as shown in FIG. 15, a temporary diagonal member 27 composed of a fixing portion 28, a connecting member 29, and an adjustment portion 30 is used. In this temporary diagonal member 27, fixing portions 28 to be attached to the main column P having the replacement main column material 9 and the adjacent main column PN are attached to both ends of the temporary diagonal member 27, and the fixing portions 28 are connected to the connecting member 29 via the adjustment portion 30. The fixing portions 28 are composed of a pair of L-shaped bodies and are joined to the main column material or a plate attached to the main column material with bolts and nuts. The connecting member 29 is formed of steel pipe members as unit members of multiple types with different lengths, and the length of the connecting member 29 can be adjusted with a high degree of freedom by setting the type and number of steel pipe members according to the distance between the fixing parts 28, 28 attached to the main pillars P, PN. In addition, the two connecting members 29 are attached between the main pillars P, PN with a gap wider than the width of the main pillar materials, and can be installed without removing the existing diagonal members 113 and horizontal members 112. The adjustment part 30 is composed of a screw part 30a and an adjustment nut 30b, and the screw part 30a is fixed to the end of the connecting member 29 by passing through a through hole provided in the fixing part 28, and the adjustment nut 30b is attached to the through hole of the fixing part 28, and the distance between the fixing parts 28, 28 attached to the main pillars P, PN can be adjusted by moving the position of the adjustment nut 30b. By using the temporary diagonal member 27 whose length can be adjusted in this manner, it can be used for replacement work of main pillar materials in various positions for steel towers where the distance between the main pillars P, PN is different, making it highly versatile.

[0066] In this way, by installing the temporary diagonal member 27 between the main column P having the replacement main column material 9 and the adjacent main column PN, a temporary single Warren truss structure can be formed even if the truss structure of the angle steel tower 100 is lost due to the removal of the replacement main column material 9. Therefore, even if the replacement main column material 9 is removed, the angle steel tower 100 can be stably held.

[0067] In the sixth step, the jack 5 is extended to transfer the load of the replacement main pillar material 9 to the support member 4.

[0068] The diagonal members 113 and horizontal members 112 connected to the replacement main column member 9 are separated from the replacement main column member 9 by removing the bolts and nuts that were fastened at their joining positions. Next, the bolts and nuts that join the replacement main column member 9 to the lower main column member 11 and the bolts and nuts that connect the replacement main column member 9 to the upper main column member 10 are loosened, and the hydraulic pump is operated to drive the cylinder 5a to expand and contract, and the load acting on the replacement main column member 9 is transferred to the support member 4. At this time, the hydraulic pump is operated simultaneously for the two jacks 5, 5 to drive the cylinders 5a, 5a to expand and contract, but since the amount of expansion and contraction of each jack 5, 5 may not be uniform, an extensometer may be attached between the lower fixing device 3 and the supporting steel pipe 8, and the jacks 5 may be operated while controlling the amount of expansion and contraction of each jack 5, 5.

[0069] In the seventh step, the replacement main pillar material 9 is removed and a new main pillar material is installed.

[0070] Once the load acting on the replacement main column material 9 has been transferred to the support member 4, the replacement main column material 9 is removed, and a new main column material is installed between the upper end of the lower main column material 11 and the lower end of the upper main column material 10. After the new main column material is installed, the diagonal members 113 and horizontal members 112 that were detached from the replacement main column material 9 in the sixth step are connected to the new main column material. Then, the jack 5 is contracted to transfer the load of the support member 4 to the new main column material, and the support member 4 and the screw adjustment unit 6 are removed. Finally, the temporary diagonal members 27 are removed, the lower fixing device 3 is removed from the lower main column material 10, and the upper fixing device 2 is removed from the upper main column material 9, completing the replacement work.

[0071] According to the main pillar material replacement device 1 and main pillar material replacement method for the angle steel tower 100 described above, the connecting fitting 14 of the upper fixing tool 2 to which the upper end connector 7 is fixed is rotatably pin-connected to the support frame 13 of the upper fixing tool 2, and the connecting fitting 24 of the lower fixing tool 3 to which the jack 5 is fixed is rotatably pin-connected to the support frame 23 of the lower fixing tool 3, so that the main pillar material replacement device 1 can be installed across the bend point 115 where the inclination angle of the main pillar 111 changes, and the main pillar material near the bend point 115 can be replaced. In other words, the main pillar material replacement device 1 can be installed in a location where the support member 4 of the main pillar material replacement device 1 is not parallel to the replacement main pillar material 9, the upper main pillar material 10, and the lower main pillar material 11.

[0072] Furthermore, the support members 4 installed between the upper fixing device 2 and the lower fixing device 3 are located on the left and right of the replacement main pillar material 9 when looking diagonally at the tower body 101 from the side of the main pillar material adjacent to the replacement main pillar material 9, and one support member 4 is disposed inside the tower body 101 and the other support member 4 is disposed outside the tower body 101, so that the main pillar material replacement device 1 can be installed without the support members 4 interfering with the cross arm 102 protruding laterally from the tower body 101. Therefore, the main pillar material near the bend point 115 can be replaced without removing the cross arm 102 to install the main pillar material replacement device 1.

[0073] Furthermore, the length of the support steel pipe 8 of the support member 4 can be adjusted by selecting the type and number of unit members, and the screw adjustment unit 6 installed between the support steel pipe 8 and the jack 5 can adjust the length by adjusting the screw engagement position of the screw. This allows the combined length of the support member 4 and the screw adjustment unit 6 to be adapted to the distance between the two fasteners 2, 3 fixed to the main pillar materials 10, 11. Therefore, the fixing positions of the fasteners 2, 3 to the main pillar materials 10, 11 can be selected with a high degree of freedom without being restricted by the length of the support member 4. As a result, the main pillar material replacement device 1 can be installed on various angle steel towers 100 without being affected by the length of the replacement main pillar material 9 or the installation conditions of metal fittings, bolts, etc. on the main pillar materials 10, 11 that fix the fasteners 2, 3, so high versatility is obtained.

[0074] In addition, since the connecting fitting 14 of the upper fixing device 2 and the connecting fitting 24 of the lower fixing device 3 are rotatably pin-connected to the support frames 13, 23, the main pillar material replacement device 1 and the main pillar material replacement method of the above-mentioned angle steel tower 100 can be installed at locations where the support member 4 of the main pillar material replacement device 1 is parallel to the replacement main pillar material 9, the upper main pillar material 10 and the lower main pillar material 11, and can also be applied to the replacement of main pillar materials other than near the bend point 115. [Explanation of symbols]

[0075] 1. Main pillar material replacement device 2 Upper fixture 3 Lower fixture 4 Support member 5 Jack 5a Cylinder 5b Rod 5c Rod connecting steel pipe 6 Screw adjustment part 6a Screw body 6b Upper flange 6c Lower flange 6d Threaded Connection Steel Pipe 7 Upper end connector 7a Threaded part 7b Connecting steel pipe 7c Nut 8 Support steel pipe 9 Replacement main pillar material 10 Upper main pillar material 11 Lower main pillar material 12 Upper fixing bracket connection metal fitting 13 Upper fixture support frame 14 Upper Fixture Connection Fitting 15 Bolt holes for connecting the connecting bracket to the upper main pillar material 16 Bolt holes for connecting the connecting bracket to the support frame 17 Bolt holes for connecting to the support frame connecting fittings 18 Holes for connecting the support frame fittings and pins 19 Holes for pin connection to the support frame of the connector 20 Bolt holes for fixing the support members of the connecting fittings 21 pin 22 Lower fixing joint 23 Lower fixture support frame 24 Lower Fixture Connection Fitting 25 Bolt holes for connecting the connecting bracket to the lower main pillar material 26 Hole for fixing the jack of the connecting fitting 27 Temporary diagonal members 28 Fixed part 29 Connecting members 30 Adjustment part 30a Threaded part 30b Adjustment nut 100 Angle Steel Tower 101 Tower body 102 Arms 111 Main pillar 112 Horizontal material 113 Diagonal members 114 Main pillar material 115 Bend Points 116 Section material 121 Bracket main material 122 Arm hanging material P Main pillar with replacement main pillar material PN adjacent main pillar

Claims

1. A main column replacement device for an angle steel tower is provided with two fasteners fixed to two main columns connected to both ends of a replacement main column, and a support member installed between the two fasteners, The fixing device is A connecting fitting fixed to an outer surface of the main pillar material; A pair of long support frames fixed to the connecting fittings, parallel to each other, and perpendicular to the main pillars; A connecting fitting rotatably attached between the pair of support frames; It has The support member is An upper end connector that is fixed to the connector of the upper fixing device; A support steel pipe formed of one or more unit members whose overall length can be adjusted depending on the type and number of units used; A jack fixed to the connecting fitting of the lower fixing device; A main column replacement device for an angle steel tower, comprising:

2. In the device for replacing a main column of an angle steel tower according to claim 1, The connecting fitting is formed as an L-shaped body having a width larger than the flange width of the main pillar material; The connecting fitting has a bolt hole on the inner side of the L-shape for connecting to the main pillar material, and bolt holes are provided at both ends of the width direction of the L-shape for connecting to the support frame; The connecting fitting is fixed to the main pillar material by abutting the inner surface of the L-shape against the outer surface of the main pillar material; This is a main pillar material replacement device for angle steel towers.

3. In the device for replacing a main column of an angle steel tower according to claim 1, A bolt hole for connecting to the connecting fitting is provided near the center of the support frame, and holes for pin connection to the connecting fitting are provided at both ends of the support frame; The pair of support frames are fixed to both ends of the connecting fitting at bolt holes provided near the center of the frame, This is a main pillar material replacement device for angle steel towers.

4. In the main column replacement device for an angle steel tower according to claim 1, the connecting fitting of the upper fixing device fixed to the main column connected to the upper side of the replacement main column is The support member is formed of a box-shaped body with an open bottom, and has a hole on the top surface for fixing the upper end connector of the support member, and has a hole on the side surface facing the support frame for pin connection to the support frame; The connecting fitting is connected to the support frame by inserting a pin through a hole provided on a side surface of the connecting fitting and holes provided at both ends of the support frame; This is a main pillar material replacement device for angle steel towers.

5. In the main column replacement device for an angle steel tower according to claim 1, the connecting fitting of the lower fixing device fixed to the main column connected to the lower side of the replacement main column is The support member is formed of a box-shaped body with an open top, and a hole for fixing a jack of the support member is provided on the bottom surface, and a hole for pin connection to the support frame is provided on the surface of the side surface facing the support frame, The connecting fitting is connected to the support frame by inserting a pin through a hole provided on a side surface of the connecting fitting and holes provided at both ends of the support frame; This is a main pillar material replacement device for angle steel towers.

6. In the device for replacing a main column of an angle steel tower according to claim 1, The support member is provided with a screw adjustment portion between the support steel pipe and the jack, the length of which can be adjusted according to the screw engagement position; This is a main pillar material replacement device for angle steel towers.

7. a step of fixing connecting fittings to two main pillar materials connected to both ends of the replacement main pillar material, fixing a support frame to the connecting fittings, and rotatably connecting connecting fittings between a pair of support frames at both ends of the support frame to fix a fastener to the main pillar material; A process of fixing a jack to the connecting fitting of the lower fixing device, connecting an upper end connecting device to the upper end of the supporting steel pipe, fixing the upper end connecting device to the connecting fitting of the upper fixing device, connecting a screw adjustment part between the lower end of the supporting steel pipe and the upper end of the jack, and installing a supporting member between the two fixing devices; Extending the jack to transfer the load of the replacement main column material to the support member; The process of removing the replacement main pillar material and installing a new main pillar material; A method for replacing a main pillar material of an angle steel tower, comprising:

8. a step of fixing connecting fittings to two main pillar materials connected to both ends of the replacement main pillar material, fixing a support frame to the connecting fittings, and rotatably connecting connecting fittings between a pair of support frames at both ends of the support frame to fix a fastener to the main pillar material; A process of fixing a jack to the connecting fitting of the lower fixing device, connecting an upper end connecting device to the upper end of the supporting steel pipe, fixing the upper end connecting device to the connecting fitting of the upper fixing device, connecting a screw adjustment part between the lower end of the supporting steel pipe and the upper end of the jack, and installing a supporting member between the two fixing devices; A step of installing a temporary diagonal member between a main column having a replacement main column material and an adjacent main column in an area where the truss structure of the angle steel tower will be lost due to removal of the replacement main column material; Extending the jack to transfer the load of the replacement main column material to the support member; The process of removing the replacement main pillar material and installing a new main pillar material; A method for replacing a main pillar material of an angle steel tower, comprising:

Citation Information

Patent Citations

  • Main pillar member replacement device for steel pipe tower

    JP1996163729A

  • Tower body raising construction method

    JP2000110407A

  • Device and method for replacing main column material of tower structure

    JP2011149171A

  • Replacement device and replacement method for main column material of iron tower constituted of angle steel

    JP2015229917A

  • Inter-main column material distance adjustment jig of iron tower

    JP2017186839A

Cited By

  • Method of replacing member of space frame and temporary reinforcement element therefor

    KR102971028B1