Building column construction method for seismic reinforcement

The method of embedding stud bolts and concrete connections in beams and columns addresses the seismic resistance issue by creating a robust, earthquake-resistant structure with simplified manufacturing and reduced construction time.

KR103046564B1Active Publication Date: 2026-11-10오승은
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
KR1020230124807
Authority / Receiving Office
KR · KR
Patent Type
Patents
Current Assignee / Owner
Filing Date
2023-09-19
Publication Date
2026-11-10
Estimated Expiration
2043-09-19

AI Technical Summary

Technical Problem

Existing buildings lack sufficient seismic resistance, leading to potential collapse during earthquakes, necessitating an economical method to enhance structural strength and stiffness for seismic reinforcement.

Method used

A method involving the insertion of stud bolts into beams and columns, followed by embedding them with concrete to create a firm connection, using simplified stud bolt shapes for easy manufacturing and construction.

Benefits of technology

Ensures robust connection between beams and columns, preventing collapse during earthquakes while simplifying manufacturing and reducing construction time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 112023103741128-PAT00005_ABST
    Figure 112023103741128-PAT00005_ABST
Patent Text Reader

Abstract

The present invention relates to a method for constructing a building column for seismic reinforcement, and more specifically, to a method for constructing a building column for seismic reinforcement characterized by installing a beam horizontally and long on the lower surface of the ceiling, and installing a column vertically on the upper surface of the floor so as to be close to the beam, and then inserting a plurality of stud bolts protruding from the beam and the column, respectively, on the lower surface of the beam and the upper surface of the column, and then pouring concrete so that the stud bolts are embedded to connect the beam and the column. As described above, the method for constructing a building column for seismic reinforcement according to the present invention involves inserting stud bolts so as to protrude into the beam and column, and then pouring concrete so that the stud bolts are embedded to connect the beam and column, thereby ensuring that the beam and column are firmly connected. This prevents the column from easily collapsing even under external influences such as earthquakes, and in particular, by simplifying the shape of the stud bolts, it is easy to manufacture and the construction period can be shortened, among other significant effects.
Need to check novelty before this filing date? Find Prior Art

Description

Technology Field

[0001] The present invention relates to a method for constructing building columns, and more specifically, to a method for constructing seismic reinforcement building columns capable of withstanding earthquakes. Background Technology

[0003] In the modern era, floods and droughts caused by climate anomalies due to global warming are occurring more frequently than in the past, and as their intensity increases, the damage is also growing.

[0004] In addition, earthquakes are occurring more frequently than before, and their intensity is also increasing significantly, causing immense damage that is reaching the level of a disaster.

[0005] Accordingly, earthquake-resistant design is required to reduce earthquake damage.

[0006] Seismic design refers to designing buildings to withstand earthquakes. (Naver Dictionary)

[0007] However, existing buildings constructed before the establishment of seismic design standards have very insufficient seismic resistance, so collapse and damage are expected in the event of an earthquake.

[0008] Accordingly, there is a need for an economical seismic reinforcement method that can improve seismic performance by increasing the load-bearing capacity of existing buildings through the enhancement of structural strength and stiffness of structural members.

[0009] In addition, to address these issues, we are continuously conducting seismic performance evaluations and seismic reinforcement projects for buildings.

[0010] In particular, the government's seismic reinforcement project for existing buildings is being carried out extensively, targeting schools, local government offices, hospitals, fire stations, and the like. Prior art literature

[0012] Korean Registered Patent Publication No. 10-1791819 (Seismic reinforcement method for steel plate frame concrete that enhances column stability to improve building seismic performance. Registration Date: October 24, 2017) Korean Registered Patent Publication No. 10-1671894 (Stud-anchor connection method for PC wall panel reinforcement for seismic reinforcement of aging RC beam-column buildings. Registration Date: October 27, 2016) Korean Registered Patent Publication No. 10-1904491 (Seismic reinforcement method for columns in which seismic resistance is improved through parallel structural lifting and ground reinforcement. Registration Date: September 27, 2018) Korean Registered Patent Publication No. 10-1982596 (Seismic reinforcement structure for concrete columns for architectural structures. Registration Date: May 21, 2019) The problem to be solved

[0013] The present invention was devised to solve the aforementioned problems, and aims to provide a method for constructing a building column for seismic reinforcement that connects the beam and the column by inserting stud bolts so as to protrude into the beam and the column, and then pouring concrete so that the stud bolts are embedded, thereby ensuring that the beam and the column are firmly connected so that the column does not easily collapse even under external influences such as earthquakes, and also simplifies the shape of the stud bolts to make manufacturing and construction very easy. means of solving the problem

[0015] The method for constructing a building column for seismic reinforcement according to the present invention is characterized by installing a long horizontal beam on the lower surface of the ceiling and installing a column vertically on the upper surface of the floor so as to be close to the beam, and then inserting a plurality of stud bolts protruding from the beam and the column, respectively, on the lower surface of the beam and the upper surface of the column, and then pouring concrete so that the stud bolts are embedded to connect the beam and the column. Effects of the invention

[0017] As described above, the method for constructing a building column for seismic reinforcement according to the present invention involves inserting stud bolts so as to protrude into the beam and column, and then pouring concrete so that the stud bolts are embedded to connect the beam and column, thereby ensuring that the beam and column are firmly connected. This prevents the column from easily collapsing even under external influences such as earthquakes, and in particular, by simplifying the shape of the stud bolts, it is easy to manufacture and the construction period can be shortened, among other significant effects. Brief explanation of the drawing

[0019] FIG. 1 is a schematic diagram of a front cross-section according to the method for constructing a building column for seismic reinforcement of the present invention. FIG. 2 is a schematic diagram of a side cross-section according to the method for constructing a building column for seismic reinforcement of the present invention. FIG. 3 is a schematic diagram of a front cross-section according to another embodiment of the method for constructing a building column for seismic reinforcement of the present invention. Specific details for implementing the invention

[0020] The method for constructing a building column for seismic reinforcement according to the present invention is characterized by installing a beam (20) horizontally on the lower surface of the ceiling (10) and installing a column (30) vertically on the upper surface of the floor so as to be close to the beam (20), and then installing a plurality of stud bolts (40) protruding from the beam (20) and the column (30) respectively on the lower surface of the beam (20) and the upper surface of the column (30), and then pouring concrete (60) so that the stud bolts (40) are embedded to connect the beam (20) and the column (30).

[0021] The above stud bolt (40) has a vertical cross-section of ' It is characterized by being formed in a shape.

[0022] And the stud bolt (40) inserted so as to protrude downward from the beam (20) and the stud bolt (40) inserted so as to protrude upward from the column (30) are inserted so as to intersect each other at heights, and thus a plurality of reinforcing bars (50) are installed horizontally in the rectangular space formed by the intersecting stud bolts (40).

[0023] In addition, the width of the stud bolt (30) inserted into the column (30) is formed wider than that of the stud bolt (40) inserted into the beam (20).

[0024] Additionally, a beam (20) is installed horizontally on the lower surface of the ceiling (10), and a column (30) is installed vertically on the upper surface of the floor surface in the form of a steel H-beam (30') so as to be close to the beam (20). A plurality of stud bolts (40) protruding from the beam (20) and the column (30) are installed on the lower surface of the beam (20) and the upper surface of the column (30), respectively. The stud bolts (40) installed on the steel H-beam (30') are fixed to each other by welding, and then concrete (60) is poured to embed the stud bolts (40) to connect the beam (20) and the column (30).

[0026] The method for constructing building columns for seismic reinforcement according to the present invention will be explained in detail with reference to the attached drawings as follows.

[0027] FIG. 1 is a schematic diagram of a front cross-section according to the method for constructing a building column for seismic reinforcement of the present invention, and FIG. 2 is a schematic diagram of a side cross-section according to the method for constructing a building column for seismic reinforcement of the present invention.

[0028] As illustrated in FIGS. 1 and 2, the present invention is a method for constructing a building column for seismic reinforcement, characterized by installing a beam (20) horizontally on the lower surface of a ceiling (10), and installing a column (30) vertically on the upper surface of a floor surface so as to be close to the beam (20), and then installing a plurality of stud bolts (40) protruding from the beam (20) and the column (30) respectively on the lower surface of the beam (20) and the upper surface of the column (30), and then pouring concrete (60) so that the stud bolts (40) are embedded to connect the beam (20) and the column (30).

[0029] That is, a long horizontal beam (20) is installed on the lower surface of the ceiling (10), and a column (30) is installed vertically on the upper surface of the floor so as to be close to the beam (20).

[0030] And a plurality of stud bolts (40) protruding from the beam (20) and the column (30) are installed on the lower surface of the beam (20) and the upper surface of the column (30), respectively.

[0031] At this time, the stud bolt (40) inserted into the beam (20) and the stud bolt (40) inserted into the column (30) are installed to intersect each other.

[0032] In particular, the above stud bolt (40) has a vertical cross-section of ' Ensure that it is formed into a shape.

[0033] In addition, the stud bolt (40) inserted so as to protrude downward from the beam (20) and the stud bolt (40) inserted so as to protrude upward from the column (30) are inserted so as to intersect at different heights.

[0034] Accordingly, since the stud bolt (40) protruding from the top to the bottom and the stud bolt (40) protruding from the bottom to the top intersect each other, a rectangular space is formed by the intersecting stud bolt (40), and by installing multiple reinforcing bars (50) in the horizontal direction, the beam (20) and the column can maintain a solid connection with each other even if the column (30) shakes left and right due to an earthquake.

[0035] Meanwhile, since the width of the column (30) must generally be wider than the width of the beam (20) to support the ceiling (10) and the beam (20) more stably, the width of the stud bolt (30) inserted into the column (30) is formed to be wider than the width of the stud bolt (40) inserted into the beam (20).

[0036] Finally, the beam (20) and the column (30) are connected by pouring concrete (60) so that the stud bolt (40) is embedded therein.

[0037] At this time, a formwork (70) protruding upward above the column is manufactured and installed on the side of the column (30), so that concrete (60) can be easily poured into the inside of the formwork (70).

[0039] FIG. 3 is a schematic diagram of a front cross-section according to another embodiment of the method for constructing a building column for seismic reinforcement of the present invention.

[0040] As shown in FIG. 3, in another embodiment, a beam (20) is installed horizontally on the lower surface of the ceiling (10), and a column (30) is installed vertically on the upper surface of the floor surface in the form of a steel H-beam (30') so as to be close to the beam (20). A plurality of stud bolts (40) protruding from the beam (20) and the column (30) are installed on the lower surface of the beam (20) and the upper surface of the column (30), respectively. The stud bolts (40) installed on the steel H-beam (30') are fixed to each other by welding, and then concrete (60) is poured so that the stud bolts (40) are embedded to connect the beam (20) and the column (30).

[0041] That is, a long horizontal beam (20) is installed on the lower surface of the ceiling (10), and a steel H-beam (30') is installed as a vertical column (30) on the upper surface of the floor.

[0042] At this time, the steel H-beam (30') is installed so as to be close to the beam (20) without touching it.

[0043] And, on the lower surface of the beam (20) and the upper surface of the steel beam (30'), a plurality of stud bolts (40) protruding from the beam (20) and the steel beam (30'), respectively, are installed.

[0044] The stud bolts (40) installed on the steel H-beam (30') are fixed to each other by welding.

[0045] Finally, concrete (60) is poured between the beam (20) and the H-beam (30') so that stud bolts (40) protruding from the beam (20) and the H-beam (30') are embedded.

[0046] Of course, as explained above, the stud bolt (40) protruding from the beam (20) and H-beam (30') has a vertical cross-section of ' The heights of the stud bolt (40) that is inserted so as to protrude downward from the beam (20) and the stud bolt (40) that is installed so as to protrude upward from the column (30), which are formed in a shape, are inserted so as to intersect each other.

[0047] In addition, the width of the stud bolt (30) installed on the H-beam (30') should be formed wider than that of the stud bolt (40) installed on the beam (20).

[0049] As described above, the method for constructing a building column for seismic reinforcement according to the present invention involves inserting stud bolts so as to protrude into the beam and column, and then pouring concrete so that the stud bolts are embedded to connect the beam and column, thereby ensuring that the beam and column are firmly connected. This prevents the column from easily collapsing even under external influences such as earthquakes, and in particular, by simplifying the shape of the stud bolts, it is easy to manufacture and the construction period can be shortened, among other significant effects. Explanation of the symbols

[0051] 10. Ceiling 20. Bo 30. Column 30'. H-beam 40. Stud bolt 50. Rebar 60. Concrete 70. Formwork

Claims

Claim 1 A beam (20) is installed horizontally and lengthwise on the lower surface of the ceiling (10), and a column (30) is installed vertically on the upper surface of the floor so as to be close to the beam (20). Then, a plurality of stud bolts (40) protruding from the beam (20) and the column (30) are installed on the lower surface of the beam (20) and the upper surface of the column (30), respectively, and then concrete (60) is poured so that the stud bolts (40) are embedded to connect the beam (20) and the column (30). The stud bolts (40) have a vertical cross-section of ' A stud bolt (40) inserted so as to protrude downward from the beam (20) and a stud bolt (40) inserted so as to protrude upward from the column (30) are inserted so as to intersect each other in height, thereby allowing a plurality of reinforcing bars (50) to be installed horizontally in a rectangular space formed by the intersecting stud bolts (40), wherein the width of the stud bolt (40) inserted in the column (30) is formed wider than that of the stud bolt (40) inserted in the beam (20), and the column (30) is installed vertically as a steel H-beam (30') so as to be close to the beam (20), and a plurality of stud bolts (40) protruding from the beam (20) and the column (30) are installed on the lower surface of the beam (20) and the upper surface of the column (30), respectively, and the stud bolts (40) installed in the steel H-beam (30') are fixed to each other by welding, and then the stud bolts (40) are embedded A method for constructing building columns for seismic reinforcement, characterized by connecting the beam (20) and the column (30) by pouring concrete (60). Claim 2 delete Claim 3 delete Claim 4 delete Claim 5 delete

Citation Information

Patent Citations

  • Reinforcing construction of existing building

    JP1997317198A

  • Mounting structure of reinforcing wall for existing building

    JP2001207653A

  • Vertical member joining method and joining structure

    JP2006070499A

  • The remodeling earthquake resistant connection details by using precast concrete member for old reinforced beam-column building structures and the remodeling construction method using the same

    KR1020100106259A